SlideShare a Scribd company logo
Activity Name Original
Duration
Start Finish
. Soorty 540d 31-Dec-2014 A 22-Jun-2016
..Soorty SOORTY GREEN FACTORY UNI 540d 31-Dec-2014 A 22-Jun-2016
..Soorty.Mob MOBILIZATION 47d 31-Dec-2014 A 29-Jan-2015 A
Start of Work 0d 31-Dec-2014 A
Mobilization / Approval of Concrete Mix design 30d 31-Dec-2014 A 29-Jan-2015 A
..Soorty.1 Sub Structure works 353d 11-Jan-2015 29-Dec-2015
Excavation Including Dismantling & Disposal 153d 11-Jan-2015 12-Jun-2015
Lean under Isolated Foundations & Walls 120d 16-Feb-2015 15-Jun-2015
Foundation Conc WorkAll Type 122d 19-Feb-2015 20-Jun-2015
Installation and Commisioning of Tower Crane 20d 06-Mar-2015 25-Mar-2015
..Soorty.1.. SOG Slab Conc 102d 31-Mar-2015 10-Jul-2015
SOG Under Zone-1 15d 31-Mar-2015 14-Apr-2015
SOG Under Zone-2 15d 15-Apr-2015 29-Apr-2015
SOG Under Zone -3 25d 30-Apr-2015 24-May-2015
SOG Under Zone-4 20d 25-May-2015 13-Jun-2015
SOG Under Zone-6 27d 14-Jun-2015 10-Jul-2015
..Soorty.1.1 Conc Work Retaining Wall, Lift Wall & W 264d 10-Apr-2015 29-Dec-2015
..Soorty.1.1.1 East Wall 83d 10-Apr-2015 01-Jul-2015
Excavation( Rain Water Tank) 15d 10-Apr-2015 24-Apr-2015
Base Slab Lean 8d 18-Apr-2015 25-Apr-2015
Rebar Fixing of Base Slab including Formwork 15d 22-Apr-2015 06-May-2015
Pouring of Base Slab 4d 02-May-2015 05-May-2015
Rebar Fixing of Wall 20d 03-May-2015 22-May-2015
Formwork of Wall 20d 07-May-2015 26-May-2015
Pouring of wall 22d 12-May-2015 02-Jun-2015
Slab form work 20d 22-May-2015 10-Jun-2015
Slab Rebar 10d 03-Jun-2015 12-Jun-2015
Slab Pouring 10d 05-Jun-2015 14-Jun-2015
Excavation for Retaining Wall 15d 25-May-2015 08-Jun-2015
Base Slab Lean Line15/Grid N~ I 15d 27-May-2015 10-Jun-2015
Rebar Fixing of Base Slab including Formwork as
per section N-N
13d 31-May-2015 12-Jun-2015
Pouring of Base Slab 9d 07-Jun-2015 15-Jun-2015
Rebar Fixing of Wall incl wall above tank slab 10d 09-Jun-2015 18-Jun-2015
Formwork of Wall incl wall above tank slab 15d 11-Jun-2015 25-Jun-2015
Pouring of wall incl wall above tank slab 18d 14-Jun-2015 01-Jul-2015
..Soorty.1.1.2 North Wall 254d 20-Apr-2015 29-Dec-2015
Excavation 30d 20-Apr-2015 19-May-2015
Base Slab Lean 20d 25-Apr-2015 14-May-2015
Rebar Fixing of Base Slab including Formwork 22d 27-Apr-2015 18-May-2015
Pouring of Base Slab 24d 02-May-2015 25-May-2015
Rebar Fixing of Wall 22d 06-May-2015 27-May-2015
Formwork of Wall 26d 08-May-2015 02-Jun-2015
Pouring of wall 30d 10-May-2015 08-Jun-2015
Earth Filling upto soffit of Beam/Planter Slab at wa 25d 01-Aug-2015 25-Aug-2015
Install Rebar for beams/Planter Slab along with PC 30d 21-Aug-2015 19-Sep-2015
Instal formwork for beams at wall back off 25d 10-Sep-2015 04-Oct-2015
Pour Concrete for beams/Planter Slab at wall back 15d 30-Sep-2015 14-Oct-2015
Resume earth Filling upto Top of Beams/Planter A 30d 10-Oct-2015 08-Nov-2015
Install Rebar For PC Columns 25d 02-Nov-2015 26-Nov-2015
Install Formwork for PC columns 30d 20-Nov-2015 19-Dec-2015
Pour Concrete For PC Columns 20d 10-Dec-2015 29-Dec-2015
..Soorty.1.1.3 West Wall inclu Effluent Pit 92d 30-Apr-2015 30-Jul-2015
Excavation 30d 30-Apr-2015 29-May-2015
Base Slab Lean 30d 11-May-2015 09-Jun-2015
Rebar Fixing of Base Slab including Formwork 25d 15-May-2015 08-Jun-2015
Pouring of Base Slab 13d 01-Jun-2015 13-Jun-2015
Rebar Fixing of Wall 15d 06-Jun-2015 20-Jun-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
-Dec-2014 22-Jun-2
-Dec-2014 22-Jun-2
-Dec-2014 16-Feb-2015
Start of Work
11-Jan-2015 29-Dec-2015
31-Mar-2015 10-Jul-2015
10-Apr-2015 29-Dec-2015
10-Apr-2015 01-Jul-2015
20-Apr-2015 29-Dec-2015
30-Apr-2015 30-Jul-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Formwork of Wall 20d 10-Jun-2015 29-Jun-2015
Pouring of wall 20d 13-Jun-2015 02-Jul-2015
Slab form work for Rain Water Tank 15d 18-Jun-2015 02-Jul-2015
Slab Rebar for Rain Water Tank 10d 28-Jun-2015 07-Jul-2015
Slab Pouring for Rain Water Tank 10d 30-Jun-2015 09-Jul-2015
Rebar Fixing of Wall above tank slab 8d 12-Jul-2015 19-Jul-2015
Formwork of Wall above tank slab 12d 16-Jul-2015 27-Jul-2015
Pouring of wall above tank slab 10d 21-Jul-2015 30-Jul-2015
..Soorty.1.1.4 South Wall 36d 09-Jun-2015 14-Jul-2015
Excavation 20d 09-Jun-2015 28-Jun-2015
Base Slab Lean 21d 09-Jun-2015 29-Jun-2015
Rebar Fixing of Base Slab including Formwork 22d 13-Jun-2015 04-Jul-2015
Pouring of Base Slab 22d 15-Jun-2015 06-Jul-2015
Rebar Fixing of Wall 18d 21-Jun-2015 08-Jul-2015
Formwork of Wall 17d 25-Jun-2015 11-Jul-2015
Pouring of wall 19d 26-Jun-2015 14-Jul-2015
..Soorty.2 Ground Floor (Basment Slab) at EL4'-3" 100d 20-Apr-2015 28-Jul-2015
..Soorty.2.1 GZ1 42d 20-Apr-2015 31-May-2015
Layout (Zone 1 ~ Zone-6) 20d 20-Apr-2015 09-May-2015
column reinf 8d 21-Apr-2015 28-Apr-2015
Column Erection (Formwork) 10d 22-Apr-2015 01-May-2015
Column Concrete 7d 26-Apr-2015 02-May-2015
Column Formwork removel 8d 27-Apr-2015 04-May-2015
Beams & Slab erection (formwork) 15d 30-Apr-2015 14-May-2015
Beams & Slab Reinf 27d 02-May-2015 28-May-2015
Final Closing & inspection 1d 30-May-2015 30-May-2015
Beams & Slab Concrete 1d 31-May-2015 31-May-2015
..Soorty.2.2 GZ2 45d 01-May-2015 14-Jun-2015
Column Erection 20d 01-May-2015 20-May-2015
Column Concrete 21d 02-May-2015 22-May-2015
Column Formwork removel 21d 03-May-2015 23-May-2015
Beams & Slab erection (formwork) 15d 20-May-2015 03-Jun-2015
Beams & Slab Reinf 22d 22-May-2015 12-Jun-2015
Final Closing & inspection 1d 14-Jun-2015 14-Jun-2015
Beams & Slab Concrete 1d 14-Jun-2015 14-Jun-2015
..Soorty.2.3 GZ3 37d 24-May-2015 29-Jun-2015
Column Erection (Formwork) 8d 24-May-2015 31-May-2015
Column Concrete 7d 26-May-2015 01-Jun-2015
Column Formwork removel 8d 27-May-2015 03-Jun-2015
Beams & Slab erection (formwork) 15d 08-Jun-2015 22-Jun-2015
Beams & Slab Reinf 14d 13-Jun-2015 26-Jun-2015
Final Closing & inspection 1d 28-Jun-2015 28-Jun-2015
Beams & Slab Concrete 1d 29-Jun-2015 29-Jun-2015
..Soorty.2.4 GZ4 29d 04-Jun-2015 02-Jul-2015
Column Erection (Formwork) 10d 04-Jun-2015 13-Jun-2015
Column Concrete 7d 08-Jun-2015 14-Jun-2015
Column Formwork removel 8d 09-Jun-2015 16-Jun-2015
Beams & Slab erection (formwork) 15d 11-Jun-2015 25-Jun-2015
Beams & Slab Reinf 14d 16-Jun-2015 29-Jun-2015
Final Closing & inspection 1d 01-Jul-2015 01-Jul-2015
Beams & Slab Concrete 1d 02-Jul-2015 02-Jul-2015
..Soorty.2.5 GZ5 29d 17-Jun-2015 15-Jul-2015
Column Erection (Formwork) 10d 17-Jun-2015 26-Jun-2015
Column Concrete 7d 21-Jun-2015 27-Jun-2015
Column Formwork removel 8d 22-Jun-2015 29-Jun-2015
Beams & Slab erection (formwork) 15d 24-Jun-2015 08-Jul-2015
Beams & Slab Reinf 14d 29-Jun-2015 12-Jul-2015
Final Closing & inspection 1d 14-Jul-2015 14-Jul-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
09-Jun-2015 14-Jul-2015
20-Apr-2015 28-Jul-2015
20-Apr-2015 31-May-2015
01-May-2015 14-Jun-2015
24-May-2015 29-Jun-2015
04-Jun-2015 02-Jul-2015
17-Jun-2015 15-Jul-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Beams & Slab Concrete 1d 15-Jul-2015 15-Jul-2015
..Soorty.2.6 GZ6 Drop Area at EL -00 29d 30-Jun-2015 28-Jul-2015
Column Erection (Formwork) 10d 30-Jun-2015 09-Jul-2015
Column Concrete 7d 04-Jul-2015 10-Jul-2015
Column Formwork removel 9d 05-Jul-2015 13-Jul-2015
Beams & Slab erection (formwork) 15d 07-Jul-2015 21-Jul-2015
Beams & Slab Reinf 14d 12-Jul-2015 25-Jul-2015
Final Closing & inspection 1d 27-Jul-2015 27-Jul-2015
Beams & Slab Concrete 1d 28-Jul-2015 28-Jul-2015
..Soorty.2.7 GZ6 28d 30-Jun-2015 27-Jul-2015
Column Erection (Formwork) 10d 30-Jun-2015 09-Jul-2015
Column Concrete 7d 04-Jul-2015 10-Jul-2015
Column Formwork removel 9d 05-Jul-2015 13-Jul-2015
Beams & Slab erection (formwork) 15d 07-Jul-2015 21-Jul-2015
Beams & Slab Reinf 14d 12-Jul-2015 25-Jul-2015
Final Closing & inspection 1d 26-Jul-2015 26-Jul-2015
Beams & Slab Concrete 1d 27-Jul-2015 27-Jul-2015
..Soorty.3 Super Structur Works 346d 22-Jun-2015 01-Jun-2016
..Soorty.3.1 Civil Work 346d 22-Jun-2015 01-Jun-2016
..Soorty.3.1.7 Mezzanine Floor at EL 17'-6" 78d 22-Jun-2015 07-Sep-2015
..Soorty.3.1.7.1 MZ1 32d 22-Jun-2015 23-Jul-2015
Layout 10d 22-Jun-2015 01-Jul-2015
column reinf 10d 23-Jun-2015 02-Jul-2015
Column Erection (Formwork) 10d 26-Jun-2015 05-Jul-2015
Column Concrete 7d 30-Jun-2015 06-Jul-2015
Column Formwork removel 8d 01-Jul-2015 08-Jul-2015
Beams & Slab erection (formwork) 15d 03-Jul-2015 17-Jul-2015
Beams & Slab Reinf 14d 07-Jul-2015 20-Jul-2015
Final Closing & inspection 1d 22-Jul-2015 22-Jul-2015
Beams & Slab Concrete 1d 23-Jul-2015 23-Jul-2015
..Soorty.3.1.7.2 MZ2 33d 09-Jul-2015 10-Aug-2015
Column Erection (Formwork) 10d 09-Jul-2015 18-Jul-2015
Column Concrete 7d 13-Jul-2015 19-Jul-2015
Column Formwork removel 8d 14-Jul-2015 21-Jul-2015
Beams & Slab erection (formwork) 19d 16-Jul-2015 03-Aug-2015
Beams & Slab Reinf 14d 25-Jul-2015 07-Aug-2015
Final Closing & inspection 1d 09-Aug-2015 09-Aug-2015
Beams & Slab Concrete 1d 10-Aug-2015 10-Aug-2015
..Soorty.3.1.7.3 MZ3 31d 22-Jul-2015 21-Aug-2015
Column Erection (Formwork) 10d 22-Jul-2015 31-Jul-2015
Column Concrete 7d 26-Jul-2015 01-Aug-2015
Column Formwork removel 8d 27-Jul-2015 03-Aug-2015
Beams & Slab erection (formwork) 15d 31-Jul-2015 14-Aug-2015
Beams & Slab Reinf 14d 05-Aug-2015 18-Aug-2015
Final Closing & inspection 1d 20-Aug-2015 20-Aug-2015
Beams & Slab Concrete 1d 21-Aug-2015 21-Aug-2015
..Soorty.3.1.7.5 MZ4 35d 04-Aug-2015 07-Sep-2015
Column Erection (Formwork) 10d 04-Aug-2015 13-Aug-2015
Column Concrete 7d 08-Aug-2015 14-Aug-2015
Column Formwork removel 8d 09-Aug-2015 16-Aug-2015
Beams & Slab erection (formwork) 19d 13-Aug-2015 31-Aug-2015
Beams & Slab Reinf 14d 22-Aug-2015 04-Sep-2015
Final Closing & inspection 1d 06-Sep-2015 06-Sep-2015
Beams & Slab Concrete 1d 07-Sep-2015 07-Sep-2015
..Soorty.3.1.7.4 MZ 5 & 5-A(open Area ) 40d 18-Jul-2015 26-Aug-2015
Column Erection (Formwork) Level-1 15d 18-Jul-2015 01-Aug-2015
Column Concrete Level-1 10d 26-Jul-2015 04-Aug-2015
Column Formwork removel Level-1 9d 28-Jul-2015 05-Aug-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
30-Jun-2015 28-Jul-2015
30-Jun-2015 27-Jul-2015
22-Jun-2015 01-Jun-2016
22-Jun-2015 01-Jun-2016
22-Jun-2015 07-Sep-2015
22-Jun-2015 23-Jul-2015
09-Jul-2015 10-Aug-2015
22-Jul-2015 21-Aug-2015
04-Aug-2015 07-Sep-2015
18-Jul-2015 26-Aug-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Column Erection (Formwork) Level-2 22d 02-Aug-2015 23-Aug-2015
Column Concrete Level-2 15d 11-Aug-2015 25-Aug-2015
Column Formwork removel Level-2 9d 18-Aug-2015 26-Aug-2015
..Soorty.3.1.6 First Floor at EL 28'-6" 113d 26-Aug-2015 16-Dec-2015
..Soorty.3.1.6.1 FZ1 39d 26-Aug-2015 03-Oct-2015
Layout 20d 26-Aug-2015 14-Sep-2015
column reinf 10d 27-Aug-2015 05-Sep-2015
Column Erection (Formwork) 10d 30-Aug-2015 08-Sep-2015
Column Concrete 7d 03-Sep-2015 09-Sep-2015
Column Formwork removel 8d 04-Sep-2015 11-Sep-2015
Beams & Slab erection (formwork) 19d 08-Sep-2015 26-Sep-2015
Beams & Slab Reinf 14d 17-Sep-2015 30-Sep-2015
Final Closing & inspection 1d 02-Oct-2015 02-Oct-2015
Beams & Slab Concrete 1d 03-Oct-2015 03-Oct-2015
..Soorty.3.1.6.2 FZ2 34d 11-Sep-2015 14-Oct-2015
Column Activity 15d 11-Sep-2015 25-Sep-2015
Beams & Slab erection (formwork) 19d 18-Sep-2015 06-Oct-2015
Beams & Slab Reinf 14d 27-Sep-2015 10-Oct-2015
Final Closing & inspection 1d 12-Oct-2015 12-Oct-2015
Beams & Slab Concrete 1d 14-Oct-2015 14-Oct-2015
..Soorty.3.1.6.3 FZ3 69d 29-Aug-2015 05-Nov-2015
Column Activity 10d 29-Aug-2015 07-Sep-2015
Beams & Slab erection (formwork) 19d 11-Oct-2015 29-Oct-2015
Beams & Slab Reinf 14d 20-Oct-2015 02-Nov-2015
Final Closing & inspection 1d 04-Nov-2015 04-Nov-2015
Beams & Slab Concrete 1d 05-Nov-2015 05-Nov-2015
..Soorty.3.1.6.4 FZ4 53d 21-Sep-2015 12-Nov-2015
Column Erection (Formwork) 8d 21-Sep-2015 28-Sep-2015
Column Concrete 5d 25-Sep-2015 29-Sep-2015
Column Formwork removel 8d 23-Sep-2015 30-Sep-2015
Beams & Slab erection (formwork) 19d 18-Oct-2015 05-Nov-2015
Beams & Slab Reinf 14d 27-Oct-2015 09-Nov-2015
Final Closing & inspection 1d 11-Nov-2015 11-Nov-2015
Beams & Slab Concrete 1d 12-Nov-2015 12-Nov-2015
..Soorty.3.1.6.5 FZ5 66d 01-Oct-2015 05-Dec-2015
Column Erection (Formwork) 10d 01-Oct-2015 10-Oct-2015
Column Concrete 7d 05-Oct-2015 11-Oct-2015
Column Formwork removel 8d 06-Oct-2015 13-Oct-2015
Beams & Slab erection (formwork) 19d 10-Nov-2015 28-Nov-2015
Beams & Slab Reinf 14d 19-Nov-2015 02-Dec-2015
Final Closing & inspection 1d 04-Dec-2015 04-Dec-2015
Beams & Slab Concrete 1d 05-Dec-2015 05-Dec-2015
..Soorty.3.1.6.6 FZ6 64d 14-Oct-2015 16-Dec-2015
Column Erection (Formwork) 10d 14-Oct-2015 23-Oct-2015
Column Concrete 7d 18-Oct-2015 24-Oct-2015
Column Formwork removel 8d 19-Oct-2015 26-Oct-2015
Beams & Slab erection (formwork) 19d 21-Nov-2015 09-Dec-2015
Beams & Slab Reinf 14d 30-Nov-2015 13-Dec-2015
Final Closing & inspection 1d 15-Dec-2015 15-Dec-2015
Beams & Slab Concrete 1d 16-Dec-2015 16-Dec-2015
..Soorty.3.1.3 Second Floor at EL 45'-6" 114d 19-Oct-2015 09-Feb-2016
..Soorty.3.1.3.1 SZ1 60d 19-Oct-2015 17-Dec-2015
Layout 5d 19-Oct-2015 23-Oct-2015
column reinf 10d 20-Oct-2015 29-Oct-2015
Column Erection (Formwork) 8d 23-Oct-2015 30-Oct-2015
Column Concrete 8d 24-Oct-2015 31-Oct-2015
Column Formwork removel 8d 25-Oct-2015 01-Nov-2015
Beams & Slab erection (formwork) 15d 26-Nov-2015 10-Dec-2015
Beams & Slab Reinf 12d 03-Dec-2015 14-Dec-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
26-Aug-2015 16-Dec-2015
26-Aug-2015 03-Oct-2015
11-Sep-2015 14-Oct-2015
29-Aug-2015 05-Nov-2015
21-Sep-2015 12-Nov-2015
01-Oct-2015 05-Dec-2015
14-Oct-2015 16-Dec-2015
19-Oct-2015 09-Feb-2016
19-Oct-2015 17-Dec-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Final Closing & inspection 1d 16-Dec-2015 16-Dec-2015
Beams & Slab Concrete 1d 17-Dec-2015 17-Dec-2015
..Soorty.3.1.3.2 SZ2 61d 02-Nov-2015 01-Jan-2016
Column Erection (Formwork) 10d 02-Nov-2015 11-Nov-2015
Column Concrete 7d 06-Nov-2015 12-Nov-2015
Column Formwork removel 8d 07-Nov-2015 14-Nov-2015
Beams & Slab erection (formwork) 16d 10-Dec-2015 25-Dec-2015
Beams & Slab Reinf 14d 16-Dec-2015 29-Dec-2015
Final Closing & inspection 1d 31-Dec-2015 31-Dec-2015
Beams & Slab Concrete 1d 01-Jan-2016 01-Jan-2016
..Soorty.3.1.3.3 SZ3 53d 15-Nov-2015 06-Jan-2016
Column Erection (Formwork) 10d 15-Nov-2015 24-Nov-2015
Column Concrete 7d 19-Nov-2015 25-Nov-2015
Column Formwork removel 8d 20-Nov-2015 27-Nov-2015
Beams & Slab erection (formwork) 19d 12-Dec-2015 30-Dec-2015
Beams & Slab Reinf 14d 21-Dec-2015 03-Jan-2016
Final Closing & inspection 1d 05-Jan-2016 05-Jan-2016
Beams & Slab Concrete 1d 06-Jan-2016 06-Jan-2016
..Soorty.3.1.3.4 SZ4 54d 28-Nov-2015 20-Jan-2016
Column Erection (Formwork) 10d 28-Nov-2015 07-Dec-2015
Column Concrete 7d 02-Dec-2015 08-Dec-2015
Column Formwork removel 8d 03-Dec-2015 10-Dec-2015
Beams & Slab erection (formwork) 19d 27-Dec-2015 14-Jan-2016
Beams & Slab Reinf 14d 04-Jan-2016 17-Jan-2016
Final Closing & inspection 1d 19-Jan-2016 19-Jan-2016
Beams & Slab Concrete 1d 20-Jan-2016 20-Jan-2016
..Soorty.3.1.3.5 SZ5 49d 11-Dec-2015 28-Jan-2016
Column Erection (Formwork) 10d 11-Dec-2015 20-Dec-2015
Column Concrete 7d 15-Dec-2015 21-Dec-2015
Column Formwork removel 8d 16-Dec-2015 23-Dec-2015
Beams & Slab erection (formwork) 19d 03-Jan-2016 21-Jan-2016
Beams & Slab Reinf 14d 12-Jan-2016 25-Jan-2016
Final Closing & inspection 1d 27-Jan-2016 27-Jan-2016
Beams & Slab Concrete 1d 28-Jan-2016 28-Jan-2016
..Soorty.3.1.3.6 SZ6 48d 24-Dec-2015 09-Feb-2016
Column Erection (Formwork) 10d 24-Dec-2015 02-Jan-2016
Column Concrete 7d 28-Dec-2015 03-Jan-2016
Column Formwork removel 8d 29-Dec-2015 05-Jan-2016
Beams & Slab erection (formwork) 19d 16-Jan-2016 03-Feb-2016
Beams & Slab Reinf 14d 25-Jan-2016 07-Feb-2016
Final Closing & inspection 1d 08-Feb-2016 08-Feb-2016
Beams & Slab Concrete 1d 09-Feb-2016 09-Feb-2016
..Soorty.3.1.2 Third Floor at EL 62'-6" 108d 28-Dec-2015 13-Apr-2016
..Soorty.3.1.2.1 TZ1 55d 28-Dec-2015 20-Feb-2016
Layout 5d 28-Dec-2015 01-Jan-2016
column reinf (Zone 1 ~ Zone-6) 10d 29-Dec-2015 07-Jan-2016
Column Erection (Formwork) 10d 01-Jan-2016 10-Jan-2016
Column Concrete 7d 05-Jan-2016 11-Jan-2016
Column Formwork removel 8d 06-Jan-2016 13-Jan-2016
Beams & Slab erection (formwork) 19d 26-Jan-2016 13-Feb-2016
Beams & Slab Reinf 14d 04-Feb-2016 17-Feb-2016
Final Closing & inspection 1d 19-Feb-2016 19-Feb-2016
Beams & Slab Concrete 1d 20-Feb-2016 20-Feb-2016
..Soorty.3.1.2.2 TZ2 50d 14-Jan-2016 03-Mar-2016
Column Erection (Formwork) 10d 14-Jan-2016 23-Jan-2016
Column Concrete 7d 18-Jan-2016 24-Jan-2016
Column Formwork removel 8d 19-Jan-2016 26-Jan-2016
Beams & Slab erection (formwork) 19d 07-Feb-2016 25-Feb-2016
Beams & Slab Reinf 14d 16-Feb-2016 29-Feb-2016
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
02-Nov-2015 01-Jan-2016
15-Nov-2015 06-Jan-2016
28-Nov-2015 20-Jan-2016
11-Dec-2015 28-Jan-2016
24-Dec-2015 09-Feb-2016
28-Dec-2015 13-Apr-2016
28-Dec-2015 20-Feb-2016
14-Jan-2016 03-Mar-2016
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Final Closing & inspection 1d 02-Mar-2016 02-Mar-2016
Beams & Slab Concrete 1d 03-Mar-2016 03-Mar-2016
..Soorty.3.1.2.3 TZ3 44d 27-Jan-2016 10-Mar-2016
Column Erection (Formwork) 10d 27-Jan-2016 05-Feb-2016
Column Concrete 7d 31-Jan-2016 06-Feb-2016
Column Formwork removel 8d 01-Feb-2016 08-Feb-2016
Beams & Slab erection (formwork) 15d 18-Feb-2016 03-Mar-2016
Beams & Slab Reinf 14d 23-Feb-2016 07-Mar-2016
Final Closing & inspection 1d 09-Mar-2016 09-Mar-2016
Beams & Slab Concrete 1d 10-Mar-2016 10-Mar-2016
..Soorty.3.1.2.4 TZ4 43d 09-Feb-2016 22-Mar-2016
Column Erection (Formwork) 10d 09-Feb-2016 18-Feb-2016
Column Concrete 7d 13-Feb-2016 19-Feb-2016
Column Formwork removel 8d 14-Feb-2016 21-Feb-2016
Beams & Slab erection (formwork) 15d 01-Mar-2016 15-Mar-2016
Beams & Slab Reinf 14d 06-Mar-2016 19-Mar-2016
Final Closing & inspection 1d 21-Mar-2016 21-Mar-2016
Beams & Slab Concrete 1d 22-Mar-2016 22-Mar-2016
..Soorty.3.1.2.5 TZ5 37d 22-Feb-2016 29-Mar-2016
Column Erection (Formwork) 10d 22-Feb-2016 02-Mar-2016
Column Concrete 7d 26-Feb-2016 03-Mar-2016
Column Formwork removel 8d 27-Feb-2016 05-Mar-2016
Beams & Slab erection (formwork) 15d 08-Mar-2016 22-Mar-2016
Beams & Slab Reinf 14d 13-Mar-2016 26-Mar-2016
Final Closing & inspection 1d 28-Mar-2016 28-Mar-2016
Beams & Slab Concrete 1d 29-Mar-2016 29-Mar-2016
..Soorty.3.1.2.6 TZ6 39d 06-Mar-2016 13-Apr-2016
Column Erection (Formwork) 10d 06-Mar-2016 15-Mar-2016
Column Concrete 7d 10-Mar-2016 16-Mar-2016
Column Formwork removel 8d 11-Mar-2016 18-Mar-2016
Beams & Slab erection (formwork) 15d 23-Mar-2016 06-Apr-2016
Beams & Slab Reinf 14d 28-Mar-2016 10-Apr-2016
Final Closing & inspection 1d 12-Apr-2016 12-Apr-2016
Beams & Slab Concrete 1d 13-Apr-2016 13-Apr-2016
..Soorty.3.1.5 Roof Level at EL 79'-6" 87d 07-Mar-2016 01-Jun-2016
..Soorty.3.1.5.1 RZ1 40d 07-Mar-2016 15-Apr-2016
Layout 20d 07-Mar-2016 26-Mar-2016
column reinf 10d 08-Mar-2016 17-Mar-2016
Column Erection (Formwork) 10d 11-Mar-2016 20-Mar-2016
Column Concrete 7d 15-Mar-2016 21-Mar-2016
Column Formwork removel 8d 16-Mar-2016 23-Mar-2016
Beams & Slab erection (formwork) 14d 28-Mar-2016 10-Apr-2016
Beams & Slab Reinf 13d 31-Mar-2016 12-Apr-2016
Final Closing & inspection 1d 14-Apr-2016 14-Apr-2016
Beams & Slab Concrete 1d 15-Apr-2016 15-Apr-2016
..Soorty.3.1.5.2 RZ2 37d 24-Mar-2016 29-Apr-2016
Column Erection (Formwork) 10d 24-Mar-2016 02-Apr-2016
Column Concrete 7d 28-Mar-2016 03-Apr-2016
Column Formwork removel 8d 29-Mar-2016 05-Apr-2016
Beams & Slab erection (formwork) 14d 12-Apr-2016 25-Apr-2016
Beams & Slab Reinf 13d 15-Apr-2016 27-Apr-2016
Final Closing & inspection 1d 28-Apr-2016 28-Apr-2016
Beams & Slab Concrete 1d 29-Apr-2016 29-Apr-2016
..Soorty.3.1.5.3 RZ3 27d 06-Apr-2016 02-May-2016
Column Erection (Formwork) 10d 06-Apr-2016 15-Apr-2016
Column Concrete 7d 10-Apr-2016 16-Apr-2016
Column Formwork removel 8d 11-Apr-2016 18-Apr-2016
Beams & Slab erection (formwork) 14d 14-Apr-2016 27-Apr-2016
Beams & Slab Reinf 13d 17-Apr-2016 29-Apr-2016
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
27-Jan-2016 10-Mar-2016
09-Feb-2016 22-Mar-2016
22-Feb-2016 29-Mar-2016
06-Mar-2016 13-Apr-2016
07-Mar-2016 01-Jun-2016
07-Mar-2016 15-Apr-2016
24-Mar-2016 29-Apr-2016
06-Apr-2016 02-May-2016
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Activity Name Original
Duration
Start Finish
Final Closing & inspection 1d 01-May-2016 01-May-2016
Beams & Slab Concrete 1d 02-May-2016 02-May-2016
..Soorty.3.1.5.4 RZ4 28d 19-Apr-2016 16-May-2016
Column Erection (Formwork) 10d 19-Apr-2016 28-Apr-2016
Column Concrete 7d 23-Apr-2016 29-Apr-2016
Column Formwork removel 8d 24-Apr-2016 01-May-2016
Beams & Slab erection (formwork) 14d 28-Apr-2016 11-May-2016
Beams & Slab Reinf 15d 29-Apr-2016 13-May-2016
Final Closing & inspection 1d 15-May-2016 15-May-2016
Beams & Slab Concrete 1d 16-May-2016 16-May-2016
..Soorty.3.1.5.5 RZ5 21d 01-May-2016 21-May-2016
Column Erection (Formwork) 5d 02-May-2016 06-May-2016
Column Concrete 7d 03-May-2016 09-May-2016
Column Formwork removel 8d 04-May-2016 11-May-2016
Beams & Slab erection (formwork) 14d 01-May-2016 14-May-2016
Beams & Slab Reinf 13d 06-May-2016 18-May-2016
Final Closing & inspection 1d 20-May-2016 20-May-2016
Beams & Slab Concrete 1d 21-May-2016 21-May-2016
..Soorty.3.1.5.6 RZ6 21d 12-May-2016 01-Jun-2016
Column Erection (Formwork) 10d 12-May-2016 21-May-2016
Column Concrete 7d 16-May-2016 22-May-2016
Column Formwork removel 8d 17-May-2016 24-May-2016
Beams & Slab erection (formwork) 14d 14-May-2016 27-May-2016
Beams & Slab Reinf 13d 17-May-2016 29-May-2016
Final Closing & inspection 1d 31-May-2016 31-May-2016
Beams & Slab Concrete 1d 01-Jun-2016 01-Jun-2016
..Soorty.4 Architectural Works 348d 11-Jul-2015 22-Jun-2016
Block Masonary 343d 11-Jul-2015 17-Jun-2016
Plaster 330d 26-Jul-2015 19-Jun-2016
Paint Work (Primer, Putty , 1st Coat) 272d 24-Sep-2015 21-Jun-2016
Flooring Including Tilling 249d 14-Oct-2015 18-Jun-2016
Doors & Windows inclu Carpentry & Joinery Work 210d 23-Nov-2015 19-Jun-2016
External Finishing (Elevation Features) 173d 02-Jan-2016 22-Jun-2016
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
19-Apr-2016 16-May-2016
01-May-2016 21-May-2016
12-May-2016 01-Jun-2016
11-Jul-2015 22-Jun-2
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
Scale
Date
Drawn By
Checked By
Project Number
Consultant
Address
Address
Address
Phone
Consultant
Address
Address
Address
Phone
Consultant
Address
Address
Address
Phone
Consultant
Address
Address
Address
Phone
Consultant
Address
Address
Address
Phone
30-May-152:53:46PM
S.1
Total Slab Area
608,459.58 SFT
SOORTY ENT
SOORTY GREEN
PROJECT UNIT 14
AAMIR
ALI
29 May 2015
Soorty Green
1
Ground Floor Slice 86,423.69 SFT
2
Meeznine Floor Slice 69,961.68 SFT
3
First Floor Slice 112,369.86
4
Secound Floor Slice 113,234.89 SFT
5
Third Floor Slice 113,234.89 SFT
6
Roof/fourth Floor Slice 113,234.89 SFT
No. Description Date
ScheduleRev- 6
ScheduleRev- 6
ScheduleRev- 6

More Related Content

Viewers also liked

cv of ravi bhushan
 cv of ravi bhushan cv of ravi bhushan
cv of ravi bhushan
CS RAVI BHUSHAN
 
Taller 10. grupo 5
Taller 10. grupo 5Taller 10. grupo 5
Taller 10. grupo 5
ramiro ramirez
 
How to Kick-Start Your Small Business in India?
How to Kick-Start Your Small Business in India?How to Kick-Start Your Small Business in India?
How to Kick-Start Your Small Business in India?
Biz2Credit Info Services
 
Higiene industrial
Higiene industrialHigiene industrial
Fuentes+derecho+tributario
Fuentes+derecho+tributarioFuentes+derecho+tributario
Fuentes+derecho+tributario
danielruiz00
 
Fabrication&erection sequence proposal
Fabrication&erection sequence proposalFabrication&erection sequence proposal
Fabrication&erection sequence proposal
M. Nailes Jhondava
 
Federalismo Fiscal
Federalismo FiscalFederalismo Fiscal
Federalismo Fiscal
Puertos de Falcón
 
Diaspositivas derecho financiero
Diaspositivas derecho financieroDiaspositivas derecho financiero
Diaspositivas derecho financiero
lunaestrella123
 
Coduri partea 1
Coduri partea 1Coduri partea 1
Coduri partea 1lecca vera
 
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana QuilesENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
fabianaquileshey
 
Derecho internacional privado
Derecho internacional privadoDerecho internacional privado
Derecho internacional privado
Carlos Castillo
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
C.V Ahmed Moharam
C.V Ahmed MoharamC.V Ahmed Moharam
C.V Ahmed Moharam
Ahmed Moharam
 

Viewers also liked (13)

cv of ravi bhushan
 cv of ravi bhushan cv of ravi bhushan
cv of ravi bhushan
 
Taller 10. grupo 5
Taller 10. grupo 5Taller 10. grupo 5
Taller 10. grupo 5
 
How to Kick-Start Your Small Business in India?
How to Kick-Start Your Small Business in India?How to Kick-Start Your Small Business in India?
How to Kick-Start Your Small Business in India?
 
Higiene industrial
Higiene industrialHigiene industrial
Higiene industrial
 
Fuentes+derecho+tributario
Fuentes+derecho+tributarioFuentes+derecho+tributario
Fuentes+derecho+tributario
 
Fabrication&erection sequence proposal
Fabrication&erection sequence proposalFabrication&erection sequence proposal
Fabrication&erection sequence proposal
 
Federalismo Fiscal
Federalismo FiscalFederalismo Fiscal
Federalismo Fiscal
 
Diaspositivas derecho financiero
Diaspositivas derecho financieroDiaspositivas derecho financiero
Diaspositivas derecho financiero
 
Coduri partea 1
Coduri partea 1Coduri partea 1
Coduri partea 1
 
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana QuilesENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quiles
 
Derecho internacional privado
Derecho internacional privadoDerecho internacional privado
Derecho internacional privado
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
C.V Ahmed Moharam
C.V Ahmed MoharamC.V Ahmed Moharam
C.V Ahmed Moharam
 

Similar to ScheduleRev- 6

ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
Ahmed Khaled
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
Nixzalis Bourdier
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
WaqarHussain183
 
Presentation
PresentationPresentation
Presentation
Krm Chari
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
Ahmed Mehrem
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
Adi Manurung
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Ahmed Mehrem
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduit
Emilie Guichard
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
John Mueller
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
Manish Shah
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
Ahmed Mehrem
 
Qatar Petroleum Procedure
Qatar Petroleum ProcedureQatar Petroleum Procedure
Qatar Petroleum Procedure
Mohammad Al-Sous
 
QP_Presentation_20151027
QP_Presentation_20151027QP_Presentation_20151027
QP_Presentation_20151027
Ian Kelly
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
SubramanianSaravanan8
 
Naperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling ProjectNaperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling Project
Georgiann Baldino
 
ABB Internal Courses
ABB Internal CoursesABB Internal Courses
ABB Internal Courses
Pardeep Sindhu
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
Tofik Nazirov, B.Sc., PhD
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
Baig Ali
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
SajidMumtazGurmani
 

Similar to ScheduleRev- 6 (20)

ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Presentation
PresentationPresentation
Presentation
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduit
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
Qatar Petroleum Procedure
Qatar Petroleum ProcedureQatar Petroleum Procedure
Qatar Petroleum Procedure
 
QP_Presentation_20151027
QP_Presentation_20151027QP_Presentation_20151027
QP_Presentation_20151027
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
Naperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling ProjectNaperville Woman’s Club Landmark Remodeling Project
Naperville Woman’s Club Landmark Remodeling Project
 
ABB Internal Courses
ABB Internal CoursesABB Internal Courses
ABB Internal Courses
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 

ScheduleRev- 6

  • 1.
  • 2. Activity Name Original Duration Start Finish . Soorty 540d 31-Dec-2014 A 22-Jun-2016 ..Soorty SOORTY GREEN FACTORY UNI 540d 31-Dec-2014 A 22-Jun-2016 ..Soorty.Mob MOBILIZATION 47d 31-Dec-2014 A 29-Jan-2015 A Start of Work 0d 31-Dec-2014 A Mobilization / Approval of Concrete Mix design 30d 31-Dec-2014 A 29-Jan-2015 A ..Soorty.1 Sub Structure works 353d 11-Jan-2015 29-Dec-2015 Excavation Including Dismantling & Disposal 153d 11-Jan-2015 12-Jun-2015 Lean under Isolated Foundations & Walls 120d 16-Feb-2015 15-Jun-2015 Foundation Conc WorkAll Type 122d 19-Feb-2015 20-Jun-2015 Installation and Commisioning of Tower Crane 20d 06-Mar-2015 25-Mar-2015 ..Soorty.1.. SOG Slab Conc 102d 31-Mar-2015 10-Jul-2015 SOG Under Zone-1 15d 31-Mar-2015 14-Apr-2015 SOG Under Zone-2 15d 15-Apr-2015 29-Apr-2015 SOG Under Zone -3 25d 30-Apr-2015 24-May-2015 SOG Under Zone-4 20d 25-May-2015 13-Jun-2015 SOG Under Zone-6 27d 14-Jun-2015 10-Jul-2015 ..Soorty.1.1 Conc Work Retaining Wall, Lift Wall & W 264d 10-Apr-2015 29-Dec-2015 ..Soorty.1.1.1 East Wall 83d 10-Apr-2015 01-Jul-2015 Excavation( Rain Water Tank) 15d 10-Apr-2015 24-Apr-2015 Base Slab Lean 8d 18-Apr-2015 25-Apr-2015 Rebar Fixing of Base Slab including Formwork 15d 22-Apr-2015 06-May-2015 Pouring of Base Slab 4d 02-May-2015 05-May-2015 Rebar Fixing of Wall 20d 03-May-2015 22-May-2015 Formwork of Wall 20d 07-May-2015 26-May-2015 Pouring of wall 22d 12-May-2015 02-Jun-2015 Slab form work 20d 22-May-2015 10-Jun-2015 Slab Rebar 10d 03-Jun-2015 12-Jun-2015 Slab Pouring 10d 05-Jun-2015 14-Jun-2015 Excavation for Retaining Wall 15d 25-May-2015 08-Jun-2015 Base Slab Lean Line15/Grid N~ I 15d 27-May-2015 10-Jun-2015 Rebar Fixing of Base Slab including Formwork as per section N-N 13d 31-May-2015 12-Jun-2015 Pouring of Base Slab 9d 07-Jun-2015 15-Jun-2015 Rebar Fixing of Wall incl wall above tank slab 10d 09-Jun-2015 18-Jun-2015 Formwork of Wall incl wall above tank slab 15d 11-Jun-2015 25-Jun-2015 Pouring of wall incl wall above tank slab 18d 14-Jun-2015 01-Jul-2015 ..Soorty.1.1.2 North Wall 254d 20-Apr-2015 29-Dec-2015 Excavation 30d 20-Apr-2015 19-May-2015 Base Slab Lean 20d 25-Apr-2015 14-May-2015 Rebar Fixing of Base Slab including Formwork 22d 27-Apr-2015 18-May-2015 Pouring of Base Slab 24d 02-May-2015 25-May-2015 Rebar Fixing of Wall 22d 06-May-2015 27-May-2015 Formwork of Wall 26d 08-May-2015 02-Jun-2015 Pouring of wall 30d 10-May-2015 08-Jun-2015 Earth Filling upto soffit of Beam/Planter Slab at wa 25d 01-Aug-2015 25-Aug-2015 Install Rebar for beams/Planter Slab along with PC 30d 21-Aug-2015 19-Sep-2015 Instal formwork for beams at wall back off 25d 10-Sep-2015 04-Oct-2015 Pour Concrete for beams/Planter Slab at wall back 15d 30-Sep-2015 14-Oct-2015 Resume earth Filling upto Top of Beams/Planter A 30d 10-Oct-2015 08-Nov-2015 Install Rebar For PC Columns 25d 02-Nov-2015 26-Nov-2015 Install Formwork for PC columns 30d 20-Nov-2015 19-Dec-2015 Pour Concrete For PC Columns 20d 10-Dec-2015 29-Dec-2015 ..Soorty.1.1.3 West Wall inclu Effluent Pit 92d 30-Apr-2015 30-Jul-2015 Excavation 30d 30-Apr-2015 29-May-2015 Base Slab Lean 30d 11-May-2015 09-Jun-2015 Rebar Fixing of Base Slab including Formwork 25d 15-May-2015 08-Jun-2015 Pouring of Base Slab 13d 01-Jun-2015 13-Jun-2015 Rebar Fixing of Wall 15d 06-Jun-2015 20-Jun-2015 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 -Dec-2014 22-Jun-2 -Dec-2014 22-Jun-2 -Dec-2014 16-Feb-2015 Start of Work 11-Jan-2015 29-Dec-2015 31-Mar-2015 10-Jul-2015 10-Apr-2015 29-Dec-2015 10-Apr-2015 01-Jul-2015 20-Apr-2015 29-Dec-2015 30-Apr-2015 30-Jul-2015 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 3. Activity Name Original Duration Start Finish Formwork of Wall 20d 10-Jun-2015 29-Jun-2015 Pouring of wall 20d 13-Jun-2015 02-Jul-2015 Slab form work for Rain Water Tank 15d 18-Jun-2015 02-Jul-2015 Slab Rebar for Rain Water Tank 10d 28-Jun-2015 07-Jul-2015 Slab Pouring for Rain Water Tank 10d 30-Jun-2015 09-Jul-2015 Rebar Fixing of Wall above tank slab 8d 12-Jul-2015 19-Jul-2015 Formwork of Wall above tank slab 12d 16-Jul-2015 27-Jul-2015 Pouring of wall above tank slab 10d 21-Jul-2015 30-Jul-2015 ..Soorty.1.1.4 South Wall 36d 09-Jun-2015 14-Jul-2015 Excavation 20d 09-Jun-2015 28-Jun-2015 Base Slab Lean 21d 09-Jun-2015 29-Jun-2015 Rebar Fixing of Base Slab including Formwork 22d 13-Jun-2015 04-Jul-2015 Pouring of Base Slab 22d 15-Jun-2015 06-Jul-2015 Rebar Fixing of Wall 18d 21-Jun-2015 08-Jul-2015 Formwork of Wall 17d 25-Jun-2015 11-Jul-2015 Pouring of wall 19d 26-Jun-2015 14-Jul-2015 ..Soorty.2 Ground Floor (Basment Slab) at EL4'-3" 100d 20-Apr-2015 28-Jul-2015 ..Soorty.2.1 GZ1 42d 20-Apr-2015 31-May-2015 Layout (Zone 1 ~ Zone-6) 20d 20-Apr-2015 09-May-2015 column reinf 8d 21-Apr-2015 28-Apr-2015 Column Erection (Formwork) 10d 22-Apr-2015 01-May-2015 Column Concrete 7d 26-Apr-2015 02-May-2015 Column Formwork removel 8d 27-Apr-2015 04-May-2015 Beams & Slab erection (formwork) 15d 30-Apr-2015 14-May-2015 Beams & Slab Reinf 27d 02-May-2015 28-May-2015 Final Closing & inspection 1d 30-May-2015 30-May-2015 Beams & Slab Concrete 1d 31-May-2015 31-May-2015 ..Soorty.2.2 GZ2 45d 01-May-2015 14-Jun-2015 Column Erection 20d 01-May-2015 20-May-2015 Column Concrete 21d 02-May-2015 22-May-2015 Column Formwork removel 21d 03-May-2015 23-May-2015 Beams & Slab erection (formwork) 15d 20-May-2015 03-Jun-2015 Beams & Slab Reinf 22d 22-May-2015 12-Jun-2015 Final Closing & inspection 1d 14-Jun-2015 14-Jun-2015 Beams & Slab Concrete 1d 14-Jun-2015 14-Jun-2015 ..Soorty.2.3 GZ3 37d 24-May-2015 29-Jun-2015 Column Erection (Formwork) 8d 24-May-2015 31-May-2015 Column Concrete 7d 26-May-2015 01-Jun-2015 Column Formwork removel 8d 27-May-2015 03-Jun-2015 Beams & Slab erection (formwork) 15d 08-Jun-2015 22-Jun-2015 Beams & Slab Reinf 14d 13-Jun-2015 26-Jun-2015 Final Closing & inspection 1d 28-Jun-2015 28-Jun-2015 Beams & Slab Concrete 1d 29-Jun-2015 29-Jun-2015 ..Soorty.2.4 GZ4 29d 04-Jun-2015 02-Jul-2015 Column Erection (Formwork) 10d 04-Jun-2015 13-Jun-2015 Column Concrete 7d 08-Jun-2015 14-Jun-2015 Column Formwork removel 8d 09-Jun-2015 16-Jun-2015 Beams & Slab erection (formwork) 15d 11-Jun-2015 25-Jun-2015 Beams & Slab Reinf 14d 16-Jun-2015 29-Jun-2015 Final Closing & inspection 1d 01-Jul-2015 01-Jul-2015 Beams & Slab Concrete 1d 02-Jul-2015 02-Jul-2015 ..Soorty.2.5 GZ5 29d 17-Jun-2015 15-Jul-2015 Column Erection (Formwork) 10d 17-Jun-2015 26-Jun-2015 Column Concrete 7d 21-Jun-2015 27-Jun-2015 Column Formwork removel 8d 22-Jun-2015 29-Jun-2015 Beams & Slab erection (formwork) 15d 24-Jun-2015 08-Jul-2015 Beams & Slab Reinf 14d 29-Jun-2015 12-Jul-2015 Final Closing & inspection 1d 14-Jul-2015 14-Jul-2015 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 09-Jun-2015 14-Jul-2015 20-Apr-2015 28-Jul-2015 20-Apr-2015 31-May-2015 01-May-2015 14-Jun-2015 24-May-2015 29-Jun-2015 04-Jun-2015 02-Jul-2015 17-Jun-2015 15-Jul-2015 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 4. Activity Name Original Duration Start Finish Beams & Slab Concrete 1d 15-Jul-2015 15-Jul-2015 ..Soorty.2.6 GZ6 Drop Area at EL -00 29d 30-Jun-2015 28-Jul-2015 Column Erection (Formwork) 10d 30-Jun-2015 09-Jul-2015 Column Concrete 7d 04-Jul-2015 10-Jul-2015 Column Formwork removel 9d 05-Jul-2015 13-Jul-2015 Beams & Slab erection (formwork) 15d 07-Jul-2015 21-Jul-2015 Beams & Slab Reinf 14d 12-Jul-2015 25-Jul-2015 Final Closing & inspection 1d 27-Jul-2015 27-Jul-2015 Beams & Slab Concrete 1d 28-Jul-2015 28-Jul-2015 ..Soorty.2.7 GZ6 28d 30-Jun-2015 27-Jul-2015 Column Erection (Formwork) 10d 30-Jun-2015 09-Jul-2015 Column Concrete 7d 04-Jul-2015 10-Jul-2015 Column Formwork removel 9d 05-Jul-2015 13-Jul-2015 Beams & Slab erection (formwork) 15d 07-Jul-2015 21-Jul-2015 Beams & Slab Reinf 14d 12-Jul-2015 25-Jul-2015 Final Closing & inspection 1d 26-Jul-2015 26-Jul-2015 Beams & Slab Concrete 1d 27-Jul-2015 27-Jul-2015 ..Soorty.3 Super Structur Works 346d 22-Jun-2015 01-Jun-2016 ..Soorty.3.1 Civil Work 346d 22-Jun-2015 01-Jun-2016 ..Soorty.3.1.7 Mezzanine Floor at EL 17'-6" 78d 22-Jun-2015 07-Sep-2015 ..Soorty.3.1.7.1 MZ1 32d 22-Jun-2015 23-Jul-2015 Layout 10d 22-Jun-2015 01-Jul-2015 column reinf 10d 23-Jun-2015 02-Jul-2015 Column Erection (Formwork) 10d 26-Jun-2015 05-Jul-2015 Column Concrete 7d 30-Jun-2015 06-Jul-2015 Column Formwork removel 8d 01-Jul-2015 08-Jul-2015 Beams & Slab erection (formwork) 15d 03-Jul-2015 17-Jul-2015 Beams & Slab Reinf 14d 07-Jul-2015 20-Jul-2015 Final Closing & inspection 1d 22-Jul-2015 22-Jul-2015 Beams & Slab Concrete 1d 23-Jul-2015 23-Jul-2015 ..Soorty.3.1.7.2 MZ2 33d 09-Jul-2015 10-Aug-2015 Column Erection (Formwork) 10d 09-Jul-2015 18-Jul-2015 Column Concrete 7d 13-Jul-2015 19-Jul-2015 Column Formwork removel 8d 14-Jul-2015 21-Jul-2015 Beams & Slab erection (formwork) 19d 16-Jul-2015 03-Aug-2015 Beams & Slab Reinf 14d 25-Jul-2015 07-Aug-2015 Final Closing & inspection 1d 09-Aug-2015 09-Aug-2015 Beams & Slab Concrete 1d 10-Aug-2015 10-Aug-2015 ..Soorty.3.1.7.3 MZ3 31d 22-Jul-2015 21-Aug-2015 Column Erection (Formwork) 10d 22-Jul-2015 31-Jul-2015 Column Concrete 7d 26-Jul-2015 01-Aug-2015 Column Formwork removel 8d 27-Jul-2015 03-Aug-2015 Beams & Slab erection (formwork) 15d 31-Jul-2015 14-Aug-2015 Beams & Slab Reinf 14d 05-Aug-2015 18-Aug-2015 Final Closing & inspection 1d 20-Aug-2015 20-Aug-2015 Beams & Slab Concrete 1d 21-Aug-2015 21-Aug-2015 ..Soorty.3.1.7.5 MZ4 35d 04-Aug-2015 07-Sep-2015 Column Erection (Formwork) 10d 04-Aug-2015 13-Aug-2015 Column Concrete 7d 08-Aug-2015 14-Aug-2015 Column Formwork removel 8d 09-Aug-2015 16-Aug-2015 Beams & Slab erection (formwork) 19d 13-Aug-2015 31-Aug-2015 Beams & Slab Reinf 14d 22-Aug-2015 04-Sep-2015 Final Closing & inspection 1d 06-Sep-2015 06-Sep-2015 Beams & Slab Concrete 1d 07-Sep-2015 07-Sep-2015 ..Soorty.3.1.7.4 MZ 5 & 5-A(open Area ) 40d 18-Jul-2015 26-Aug-2015 Column Erection (Formwork) Level-1 15d 18-Jul-2015 01-Aug-2015 Column Concrete Level-1 10d 26-Jul-2015 04-Aug-2015 Column Formwork removel Level-1 9d 28-Jul-2015 05-Aug-2015 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 30-Jun-2015 28-Jul-2015 30-Jun-2015 27-Jul-2015 22-Jun-2015 01-Jun-2016 22-Jun-2015 01-Jun-2016 22-Jun-2015 07-Sep-2015 22-Jun-2015 23-Jul-2015 09-Jul-2015 10-Aug-2015 22-Jul-2015 21-Aug-2015 04-Aug-2015 07-Sep-2015 18-Jul-2015 26-Aug-2015 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 5. Activity Name Original Duration Start Finish Column Erection (Formwork) Level-2 22d 02-Aug-2015 23-Aug-2015 Column Concrete Level-2 15d 11-Aug-2015 25-Aug-2015 Column Formwork removel Level-2 9d 18-Aug-2015 26-Aug-2015 ..Soorty.3.1.6 First Floor at EL 28'-6" 113d 26-Aug-2015 16-Dec-2015 ..Soorty.3.1.6.1 FZ1 39d 26-Aug-2015 03-Oct-2015 Layout 20d 26-Aug-2015 14-Sep-2015 column reinf 10d 27-Aug-2015 05-Sep-2015 Column Erection (Formwork) 10d 30-Aug-2015 08-Sep-2015 Column Concrete 7d 03-Sep-2015 09-Sep-2015 Column Formwork removel 8d 04-Sep-2015 11-Sep-2015 Beams & Slab erection (formwork) 19d 08-Sep-2015 26-Sep-2015 Beams & Slab Reinf 14d 17-Sep-2015 30-Sep-2015 Final Closing & inspection 1d 02-Oct-2015 02-Oct-2015 Beams & Slab Concrete 1d 03-Oct-2015 03-Oct-2015 ..Soorty.3.1.6.2 FZ2 34d 11-Sep-2015 14-Oct-2015 Column Activity 15d 11-Sep-2015 25-Sep-2015 Beams & Slab erection (formwork) 19d 18-Sep-2015 06-Oct-2015 Beams & Slab Reinf 14d 27-Sep-2015 10-Oct-2015 Final Closing & inspection 1d 12-Oct-2015 12-Oct-2015 Beams & Slab Concrete 1d 14-Oct-2015 14-Oct-2015 ..Soorty.3.1.6.3 FZ3 69d 29-Aug-2015 05-Nov-2015 Column Activity 10d 29-Aug-2015 07-Sep-2015 Beams & Slab erection (formwork) 19d 11-Oct-2015 29-Oct-2015 Beams & Slab Reinf 14d 20-Oct-2015 02-Nov-2015 Final Closing & inspection 1d 04-Nov-2015 04-Nov-2015 Beams & Slab Concrete 1d 05-Nov-2015 05-Nov-2015 ..Soorty.3.1.6.4 FZ4 53d 21-Sep-2015 12-Nov-2015 Column Erection (Formwork) 8d 21-Sep-2015 28-Sep-2015 Column Concrete 5d 25-Sep-2015 29-Sep-2015 Column Formwork removel 8d 23-Sep-2015 30-Sep-2015 Beams & Slab erection (formwork) 19d 18-Oct-2015 05-Nov-2015 Beams & Slab Reinf 14d 27-Oct-2015 09-Nov-2015 Final Closing & inspection 1d 11-Nov-2015 11-Nov-2015 Beams & Slab Concrete 1d 12-Nov-2015 12-Nov-2015 ..Soorty.3.1.6.5 FZ5 66d 01-Oct-2015 05-Dec-2015 Column Erection (Formwork) 10d 01-Oct-2015 10-Oct-2015 Column Concrete 7d 05-Oct-2015 11-Oct-2015 Column Formwork removel 8d 06-Oct-2015 13-Oct-2015 Beams & Slab erection (formwork) 19d 10-Nov-2015 28-Nov-2015 Beams & Slab Reinf 14d 19-Nov-2015 02-Dec-2015 Final Closing & inspection 1d 04-Dec-2015 04-Dec-2015 Beams & Slab Concrete 1d 05-Dec-2015 05-Dec-2015 ..Soorty.3.1.6.6 FZ6 64d 14-Oct-2015 16-Dec-2015 Column Erection (Formwork) 10d 14-Oct-2015 23-Oct-2015 Column Concrete 7d 18-Oct-2015 24-Oct-2015 Column Formwork removel 8d 19-Oct-2015 26-Oct-2015 Beams & Slab erection (formwork) 19d 21-Nov-2015 09-Dec-2015 Beams & Slab Reinf 14d 30-Nov-2015 13-Dec-2015 Final Closing & inspection 1d 15-Dec-2015 15-Dec-2015 Beams & Slab Concrete 1d 16-Dec-2015 16-Dec-2015 ..Soorty.3.1.3 Second Floor at EL 45'-6" 114d 19-Oct-2015 09-Feb-2016 ..Soorty.3.1.3.1 SZ1 60d 19-Oct-2015 17-Dec-2015 Layout 5d 19-Oct-2015 23-Oct-2015 column reinf 10d 20-Oct-2015 29-Oct-2015 Column Erection (Formwork) 8d 23-Oct-2015 30-Oct-2015 Column Concrete 8d 24-Oct-2015 31-Oct-2015 Column Formwork removel 8d 25-Oct-2015 01-Nov-2015 Beams & Slab erection (formwork) 15d 26-Nov-2015 10-Dec-2015 Beams & Slab Reinf 12d 03-Dec-2015 14-Dec-2015 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 26-Aug-2015 16-Dec-2015 26-Aug-2015 03-Oct-2015 11-Sep-2015 14-Oct-2015 29-Aug-2015 05-Nov-2015 21-Sep-2015 12-Nov-2015 01-Oct-2015 05-Dec-2015 14-Oct-2015 16-Dec-2015 19-Oct-2015 09-Feb-2016 19-Oct-2015 17-Dec-2015 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 6. Activity Name Original Duration Start Finish Final Closing & inspection 1d 16-Dec-2015 16-Dec-2015 Beams & Slab Concrete 1d 17-Dec-2015 17-Dec-2015 ..Soorty.3.1.3.2 SZ2 61d 02-Nov-2015 01-Jan-2016 Column Erection (Formwork) 10d 02-Nov-2015 11-Nov-2015 Column Concrete 7d 06-Nov-2015 12-Nov-2015 Column Formwork removel 8d 07-Nov-2015 14-Nov-2015 Beams & Slab erection (formwork) 16d 10-Dec-2015 25-Dec-2015 Beams & Slab Reinf 14d 16-Dec-2015 29-Dec-2015 Final Closing & inspection 1d 31-Dec-2015 31-Dec-2015 Beams & Slab Concrete 1d 01-Jan-2016 01-Jan-2016 ..Soorty.3.1.3.3 SZ3 53d 15-Nov-2015 06-Jan-2016 Column Erection (Formwork) 10d 15-Nov-2015 24-Nov-2015 Column Concrete 7d 19-Nov-2015 25-Nov-2015 Column Formwork removel 8d 20-Nov-2015 27-Nov-2015 Beams & Slab erection (formwork) 19d 12-Dec-2015 30-Dec-2015 Beams & Slab Reinf 14d 21-Dec-2015 03-Jan-2016 Final Closing & inspection 1d 05-Jan-2016 05-Jan-2016 Beams & Slab Concrete 1d 06-Jan-2016 06-Jan-2016 ..Soorty.3.1.3.4 SZ4 54d 28-Nov-2015 20-Jan-2016 Column Erection (Formwork) 10d 28-Nov-2015 07-Dec-2015 Column Concrete 7d 02-Dec-2015 08-Dec-2015 Column Formwork removel 8d 03-Dec-2015 10-Dec-2015 Beams & Slab erection (formwork) 19d 27-Dec-2015 14-Jan-2016 Beams & Slab Reinf 14d 04-Jan-2016 17-Jan-2016 Final Closing & inspection 1d 19-Jan-2016 19-Jan-2016 Beams & Slab Concrete 1d 20-Jan-2016 20-Jan-2016 ..Soorty.3.1.3.5 SZ5 49d 11-Dec-2015 28-Jan-2016 Column Erection (Formwork) 10d 11-Dec-2015 20-Dec-2015 Column Concrete 7d 15-Dec-2015 21-Dec-2015 Column Formwork removel 8d 16-Dec-2015 23-Dec-2015 Beams & Slab erection (formwork) 19d 03-Jan-2016 21-Jan-2016 Beams & Slab Reinf 14d 12-Jan-2016 25-Jan-2016 Final Closing & inspection 1d 27-Jan-2016 27-Jan-2016 Beams & Slab Concrete 1d 28-Jan-2016 28-Jan-2016 ..Soorty.3.1.3.6 SZ6 48d 24-Dec-2015 09-Feb-2016 Column Erection (Formwork) 10d 24-Dec-2015 02-Jan-2016 Column Concrete 7d 28-Dec-2015 03-Jan-2016 Column Formwork removel 8d 29-Dec-2015 05-Jan-2016 Beams & Slab erection (formwork) 19d 16-Jan-2016 03-Feb-2016 Beams & Slab Reinf 14d 25-Jan-2016 07-Feb-2016 Final Closing & inspection 1d 08-Feb-2016 08-Feb-2016 Beams & Slab Concrete 1d 09-Feb-2016 09-Feb-2016 ..Soorty.3.1.2 Third Floor at EL 62'-6" 108d 28-Dec-2015 13-Apr-2016 ..Soorty.3.1.2.1 TZ1 55d 28-Dec-2015 20-Feb-2016 Layout 5d 28-Dec-2015 01-Jan-2016 column reinf (Zone 1 ~ Zone-6) 10d 29-Dec-2015 07-Jan-2016 Column Erection (Formwork) 10d 01-Jan-2016 10-Jan-2016 Column Concrete 7d 05-Jan-2016 11-Jan-2016 Column Formwork removel 8d 06-Jan-2016 13-Jan-2016 Beams & Slab erection (formwork) 19d 26-Jan-2016 13-Feb-2016 Beams & Slab Reinf 14d 04-Feb-2016 17-Feb-2016 Final Closing & inspection 1d 19-Feb-2016 19-Feb-2016 Beams & Slab Concrete 1d 20-Feb-2016 20-Feb-2016 ..Soorty.3.1.2.2 TZ2 50d 14-Jan-2016 03-Mar-2016 Column Erection (Formwork) 10d 14-Jan-2016 23-Jan-2016 Column Concrete 7d 18-Jan-2016 24-Jan-2016 Column Formwork removel 8d 19-Jan-2016 26-Jan-2016 Beams & Slab erection (formwork) 19d 07-Feb-2016 25-Feb-2016 Beams & Slab Reinf 14d 16-Feb-2016 29-Feb-2016 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 02-Nov-2015 01-Jan-2016 15-Nov-2015 06-Jan-2016 28-Nov-2015 20-Jan-2016 11-Dec-2015 28-Jan-2016 24-Dec-2015 09-Feb-2016 28-Dec-2015 13-Apr-2016 28-Dec-2015 20-Feb-2016 14-Jan-2016 03-Mar-2016 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 7. Activity Name Original Duration Start Finish Final Closing & inspection 1d 02-Mar-2016 02-Mar-2016 Beams & Slab Concrete 1d 03-Mar-2016 03-Mar-2016 ..Soorty.3.1.2.3 TZ3 44d 27-Jan-2016 10-Mar-2016 Column Erection (Formwork) 10d 27-Jan-2016 05-Feb-2016 Column Concrete 7d 31-Jan-2016 06-Feb-2016 Column Formwork removel 8d 01-Feb-2016 08-Feb-2016 Beams & Slab erection (formwork) 15d 18-Feb-2016 03-Mar-2016 Beams & Slab Reinf 14d 23-Feb-2016 07-Mar-2016 Final Closing & inspection 1d 09-Mar-2016 09-Mar-2016 Beams & Slab Concrete 1d 10-Mar-2016 10-Mar-2016 ..Soorty.3.1.2.4 TZ4 43d 09-Feb-2016 22-Mar-2016 Column Erection (Formwork) 10d 09-Feb-2016 18-Feb-2016 Column Concrete 7d 13-Feb-2016 19-Feb-2016 Column Formwork removel 8d 14-Feb-2016 21-Feb-2016 Beams & Slab erection (formwork) 15d 01-Mar-2016 15-Mar-2016 Beams & Slab Reinf 14d 06-Mar-2016 19-Mar-2016 Final Closing & inspection 1d 21-Mar-2016 21-Mar-2016 Beams & Slab Concrete 1d 22-Mar-2016 22-Mar-2016 ..Soorty.3.1.2.5 TZ5 37d 22-Feb-2016 29-Mar-2016 Column Erection (Formwork) 10d 22-Feb-2016 02-Mar-2016 Column Concrete 7d 26-Feb-2016 03-Mar-2016 Column Formwork removel 8d 27-Feb-2016 05-Mar-2016 Beams & Slab erection (formwork) 15d 08-Mar-2016 22-Mar-2016 Beams & Slab Reinf 14d 13-Mar-2016 26-Mar-2016 Final Closing & inspection 1d 28-Mar-2016 28-Mar-2016 Beams & Slab Concrete 1d 29-Mar-2016 29-Mar-2016 ..Soorty.3.1.2.6 TZ6 39d 06-Mar-2016 13-Apr-2016 Column Erection (Formwork) 10d 06-Mar-2016 15-Mar-2016 Column Concrete 7d 10-Mar-2016 16-Mar-2016 Column Formwork removel 8d 11-Mar-2016 18-Mar-2016 Beams & Slab erection (formwork) 15d 23-Mar-2016 06-Apr-2016 Beams & Slab Reinf 14d 28-Mar-2016 10-Apr-2016 Final Closing & inspection 1d 12-Apr-2016 12-Apr-2016 Beams & Slab Concrete 1d 13-Apr-2016 13-Apr-2016 ..Soorty.3.1.5 Roof Level at EL 79'-6" 87d 07-Mar-2016 01-Jun-2016 ..Soorty.3.1.5.1 RZ1 40d 07-Mar-2016 15-Apr-2016 Layout 20d 07-Mar-2016 26-Mar-2016 column reinf 10d 08-Mar-2016 17-Mar-2016 Column Erection (Formwork) 10d 11-Mar-2016 20-Mar-2016 Column Concrete 7d 15-Mar-2016 21-Mar-2016 Column Formwork removel 8d 16-Mar-2016 23-Mar-2016 Beams & Slab erection (formwork) 14d 28-Mar-2016 10-Apr-2016 Beams & Slab Reinf 13d 31-Mar-2016 12-Apr-2016 Final Closing & inspection 1d 14-Apr-2016 14-Apr-2016 Beams & Slab Concrete 1d 15-Apr-2016 15-Apr-2016 ..Soorty.3.1.5.2 RZ2 37d 24-Mar-2016 29-Apr-2016 Column Erection (Formwork) 10d 24-Mar-2016 02-Apr-2016 Column Concrete 7d 28-Mar-2016 03-Apr-2016 Column Formwork removel 8d 29-Mar-2016 05-Apr-2016 Beams & Slab erection (formwork) 14d 12-Apr-2016 25-Apr-2016 Beams & Slab Reinf 13d 15-Apr-2016 27-Apr-2016 Final Closing & inspection 1d 28-Apr-2016 28-Apr-2016 Beams & Slab Concrete 1d 29-Apr-2016 29-Apr-2016 ..Soorty.3.1.5.3 RZ3 27d 06-Apr-2016 02-May-2016 Column Erection (Formwork) 10d 06-Apr-2016 15-Apr-2016 Column Concrete 7d 10-Apr-2016 16-Apr-2016 Column Formwork removel 8d 11-Apr-2016 18-Apr-2016 Beams & Slab erection (formwork) 14d 14-Apr-2016 27-Apr-2016 Beams & Slab Reinf 13d 17-Apr-2016 29-Apr-2016 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 27-Jan-2016 10-Mar-2016 09-Feb-2016 22-Mar-2016 22-Feb-2016 29-Mar-2016 06-Mar-2016 13-Apr-2016 07-Mar-2016 01-Jun-2016 07-Mar-2016 15-Apr-2016 24-Mar-2016 29-Apr-2016 06-Apr-2016 02-May-2016 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 8. Activity Name Original Duration Start Finish Final Closing & inspection 1d 01-May-2016 01-May-2016 Beams & Slab Concrete 1d 02-May-2016 02-May-2016 ..Soorty.3.1.5.4 RZ4 28d 19-Apr-2016 16-May-2016 Column Erection (Formwork) 10d 19-Apr-2016 28-Apr-2016 Column Concrete 7d 23-Apr-2016 29-Apr-2016 Column Formwork removel 8d 24-Apr-2016 01-May-2016 Beams & Slab erection (formwork) 14d 28-Apr-2016 11-May-2016 Beams & Slab Reinf 15d 29-Apr-2016 13-May-2016 Final Closing & inspection 1d 15-May-2016 15-May-2016 Beams & Slab Concrete 1d 16-May-2016 16-May-2016 ..Soorty.3.1.5.5 RZ5 21d 01-May-2016 21-May-2016 Column Erection (Formwork) 5d 02-May-2016 06-May-2016 Column Concrete 7d 03-May-2016 09-May-2016 Column Formwork removel 8d 04-May-2016 11-May-2016 Beams & Slab erection (formwork) 14d 01-May-2016 14-May-2016 Beams & Slab Reinf 13d 06-May-2016 18-May-2016 Final Closing & inspection 1d 20-May-2016 20-May-2016 Beams & Slab Concrete 1d 21-May-2016 21-May-2016 ..Soorty.3.1.5.6 RZ6 21d 12-May-2016 01-Jun-2016 Column Erection (Formwork) 10d 12-May-2016 21-May-2016 Column Concrete 7d 16-May-2016 22-May-2016 Column Formwork removel 8d 17-May-2016 24-May-2016 Beams & Slab erection (formwork) 14d 14-May-2016 27-May-2016 Beams & Slab Reinf 13d 17-May-2016 29-May-2016 Final Closing & inspection 1d 31-May-2016 31-May-2016 Beams & Slab Concrete 1d 01-Jun-2016 01-Jun-2016 ..Soorty.4 Architectural Works 348d 11-Jul-2015 22-Jun-2016 Block Masonary 343d 11-Jul-2015 17-Jun-2016 Plaster 330d 26-Jul-2015 19-Jun-2016 Paint Work (Primer, Putty , 1st Coat) 272d 24-Sep-2015 21-Jun-2016 Flooring Including Tilling 249d 14-Oct-2015 18-Jun-2016 Doors & Windows inclu Carpentry & Joinery Work 210d 23-Nov-2015 19-Jun-2016 External Finishing (Elevation Features) 173d 02-Jan-2016 22-Jun-2016 2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 D January F March April May June July August S October N D January F March April May June July 2015 2016 19-Apr-2016 16-May-2016 01-May-2016 21-May-2016 12-May-2016 01-Jun-2016 11-Jul-2015 22-Jun-2 SOORTY GREEN FACTORY -14 Will be review after reciving of IFC Drawings Date Revision Checked Approved 26-May-2015 Draft Copy only for Review & comments Remaining Work Critical Remaining Work Milestone Summary
  • 9. Scale Date Drawn By Checked By Project Number Consultant Address Address Address Phone Consultant Address Address Address Phone Consultant Address Address Address Phone Consultant Address Address Address Phone Consultant Address Address Address Phone 30-May-152:53:46PM S.1 Total Slab Area 608,459.58 SFT SOORTY ENT SOORTY GREEN PROJECT UNIT 14 AAMIR ALI 29 May 2015 Soorty Green 1 Ground Floor Slice 86,423.69 SFT 2 Meeznine Floor Slice 69,961.68 SFT 3 First Floor Slice 112,369.86 4 Secound Floor Slice 113,234.89 SFT 5 Third Floor Slice 113,234.89 SFT 6 Roof/fourth Floor Slice 113,234.89 SFT No. Description Date