This document contains a Gantt chart schedule for a construction project called "Soorty" lasting from December 31, 2014 to June 22, 2016. The schedule is broken down into multiple levels of activities including mobilization, substructure works like excavation and foundation construction, ground floor construction in different zones, and superstructure works. Key milestones include the start of work, completion of substructure on December 29, 2015, and completion of ground floor construction on July 28, 2015.
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
This document contains a project schedule for a process build with over 120 tasks listed. It includes tasks for design, procurement, fabrication, installation, testing and completion. Key milestones include completing the design by March 2015, starting fabrication in January 2015, and project completion targeted for July 2015.
The document outlines the schedule for a 2014 highway bridge project from project initiation through completion. It includes tasks such as excavating footings, driving piles, pouring concrete for abutments and deck, setting girders, and final inspection. Key milestones include completing the abutments on August 20th and finishing the project on September 23rd. The schedule is made up of over 50 individual tasks with planned start and finish dates to guide the 70 day project from initiation to completion.
The document provides an activity schedule for a Hot Strip Mill project. It lists various activities required for construction and commissioning of the mill along with their start and finish dates spanning from June 2011 to January 2015. Key milestones include issue of main mill package LOI in June 2011, start of hot strip mill in November 2011 and target of first coil production from the mill by November 2014. The schedule also provides breakdown of activities for construction of buildings, equipment erection, refractory works, and commissioning of the hot strip mill.
El documento resume los ilícitos tributarios según el Código Orgánico Tributario venezolano. Describe los ilícitos formales e ilícitos materiales, así como ilícitos relativos a especies fiscales y gravadas. Explica la clasificación, naturaleza jurídica, sanciones aplicables como multas y prisión, y circunstancias atenuantes y agravantes. Finalmente, cubre temas como la responsabilidad penal, eximentes de responsabilidad, reincidencia e inhabilitación profesional.
The Workforce Awakens -Millennials find their Pathway to successJonathan Whipple
The Pathways Program at the U.S. Army Corps of Engineers helps train and develop recent graduates ("DA interns") to replace retiring baby boomers. Through a two-year rotational program, DA interns gain experience in various specialties like engineering, human resources, law, and more. This prepares them to become future leaders and helps maintain institutional knowledge as large numbers of experienced employees retire. The program benefits both the interns, who learn valuable skills, and the Corps, which develops new talent to take on major projects worth billions of dollars.
El documento describe un torneo de gimnasia artística de 2016. El Grupo 1 compitió en la viga, salto y paralelas. Martina Dominici ganó el primer lugar, mientras que Ayelen Tarabini y Lia Lucanero obtuvieron el segundo y tercer lugar respectivamente.
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
This document contains a project schedule for a process build with over 120 tasks listed. It includes tasks for design, procurement, fabrication, installation, testing and completion. Key milestones include completing the design by March 2015, starting fabrication in January 2015, and project completion targeted for July 2015.
The document outlines the schedule for a 2014 highway bridge project from project initiation through completion. It includes tasks such as excavating footings, driving piles, pouring concrete for abutments and deck, setting girders, and final inspection. Key milestones include completing the abutments on August 20th and finishing the project on September 23rd. The schedule is made up of over 50 individual tasks with planned start and finish dates to guide the 70 day project from initiation to completion.
The document provides an activity schedule for a Hot Strip Mill project. It lists various activities required for construction and commissioning of the mill along with their start and finish dates spanning from June 2011 to January 2015. Key milestones include issue of main mill package LOI in June 2011, start of hot strip mill in November 2011 and target of first coil production from the mill by November 2014. The schedule also provides breakdown of activities for construction of buildings, equipment erection, refractory works, and commissioning of the hot strip mill.
El documento resume los ilícitos tributarios según el Código Orgánico Tributario venezolano. Describe los ilícitos formales e ilícitos materiales, así como ilícitos relativos a especies fiscales y gravadas. Explica la clasificación, naturaleza jurídica, sanciones aplicables como multas y prisión, y circunstancias atenuantes y agravantes. Finalmente, cubre temas como la responsabilidad penal, eximentes de responsabilidad, reincidencia e inhabilitación profesional.
The Workforce Awakens -Millennials find their Pathway to successJonathan Whipple
The Pathways Program at the U.S. Army Corps of Engineers helps train and develop recent graduates ("DA interns") to replace retiring baby boomers. Through a two-year rotational program, DA interns gain experience in various specialties like engineering, human resources, law, and more. This prepares them to become future leaders and helps maintain institutional knowledge as large numbers of experienced employees retire. The program benefits both the interns, who learn valuable skills, and the Corps, which develops new talent to take on major projects worth billions of dollars.
El documento describe un torneo de gimnasia artística de 2016. El Grupo 1 compitió en la viga, salto y paralelas. Martina Dominici ganó el primer lugar, mientras que Ayelen Tarabini y Lia Lucanero obtuvieron el segundo y tercer lugar respectivamente.
A Fellow member of the Institute of Company Secretaries of India with 8 years’ post membership experience in corporate, institutions as well as in practice in the field of Company law, FEMA, IPR, Taxation and appearance before various Quasi Judicial bodies including CLB, NCLT, CIT, etc.
Este taller práctico tiene como objetivo que los docentes identifiquen los cambios necesarios para incorporar las TIC al aula y currículo escolar. El taller busca que los docentes desarrollen habilidades, estrategias y competencias para contribuir al nuevo paradigma educativo propuesto por las TIC. El taller se desarrollará a través de estrategias individuales y colaborativas para identificar métodos para fomentar la creatividad docente, afianzar nuevas habilidades del siglo XXI y aplicar tendencias educativas basadas en pedagog
Company registration has always been a major hassle for people who are looking to start-up their own business in India.With so many procedures, it has always been a lengthy task with not much an ease to complete the process. The newly introduced INC-29, a five-in-one form introduced by Ministry of Corporate affairs (MCA) in May 2015 has come a long way in improving this scenario. This presentation guides you through all the procedures one needs to go till one is officially ready to set up a small business and the relevant documents required for the same.
Este documento describe los principales riesgos en seguridad y salud ocupacional como riesgos físicos, químicos, biológicos y ergonómicos. Explica las técnicas de prevención para cada riesgo, incluyendo el uso de equipos de protección personal, controles ambientales, diseño ergonómico del puesto de trabajo y programas de limpieza. El objetivo es identificar peligros y valorar riesgos para proteger la salud y seguridad de los trabajadores.
Este documento describe las principales fuentes del derecho tributario en Venezuela. Estas incluyen la Constitución, las leyes aprobadas por la Asamblea Nacional, los decretos leyes, los reglamentos, los tratados internacionales, las providencias administrativas, la doctrina y la jurisprudencia. Explica brevemente cada una de estas fuentes y cómo se relacionan entre sí de acuerdo con la jerarquía del derecho venezolano.
This document outlines a 16-stage fabrication and erection sequence for a tank storage terminal in Karimun, Indonesia. Stage 1 involves laying the annular plate and bottom plate foundations. Stages 2-4 continue bottom plate laying. Stage 5 completes bottom plate erection and begins the first shell course. Stages 6-8 erect the second shell course and add stairways. Stages 9-14 jack up layers and erect additional shell courses. Stage 15 completes shell laying. Stage 16 involves erecting the roof.
Este documento discute el federalismo fiscal en Venezuela, incluyendo las competencias tributarias del poder nacional, estadal y municipal según la constitución. También examina jurisprudencia relevante y limitaciones del sistema para lograr una distribución óptima de responsabilidades entre los niveles de gobierno. El objetivo general del federalismo fiscal en Venezuela es promover la eficiencia, responsabilidad y fortalecimiento de los territorios con más recursos y autonomía de gestión.
El documento trata sobre el origen, definición y autonomía del derecho financiero. Explica que el primer estudioso que definió este campo fue Myrbach Rheinfeld a principios del siglo XX. Define el derecho financiero como la reglamentación jurídica de las finanzas públicas del estado y otros entes. También discute las diferentes corrientes del derecho financiero y los principales temas que cubre como tributos, impuestos, tasas y el presupuesto.
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quilesfabianaquileshey
Fuentes, definición, derecho general, constitución, la ley, los decretos, los tratados internacionales y los reglamentos. Derecho Tributario, Universidad Fermín Toro. María Fabiana Quiles
Este documento describe las características y objetivos de la Ley Venezolana de Derecho Internacional Privado de 1975. La ley tuvo como objetivos resolver problemas en el sistema de derecho internacional privado venezolano, ajustar la legislación a la realidad social del país, y adaptar las soluciones a avances en codificación internacional. La ley se caracteriza por reflejar soluciones de diferentes escuelas de derecho internacional privado, otorgar autonomía al juez, y contener normas generales.
This document provides an overview of project cost management. It defines key processes for planning, estimating, determining budgets, and controlling costs on a project. Section 7.1 discusses planning cost management by establishing policies and documentation for managing project costs. Section 7.2 covers estimating costs by developing approximations for completing project activities. Section 7.3 involves determining the project budget by aggregating activity cost estimates. Finally, section 7.4 is about controlling costs by monitoring project spending and updating the cost baseline.
Ahmed Moharam Mohamed Lotfy is an experienced Director of Engineering seeking a position as a Regional Director of Engineering. He has over 29 years of experience in hotel engineering roles including opening new hotels, managing engineering budgets and operations, and implementing preventative maintenance and energy saving plans. His experience includes roles at IHG, Accor, and Misr Real Estate Development. He has a bachelor's degree in engineering and various certifications and training in areas like HVAC, project management, and energy efficiency.
This document contains a master schedule for the preparation and processing of the twelfth floor of a headquarters building in Garden City. The schedule outlines 76 activities with original durations and planned start and finish dates from March 31, 2015 to June 14, 2015. Key milestones include establishing electrical, plumbing and HVAC by April 24, 50% of work done by May 16, 80% done including painting by June 4, and completing the project by June 14. The schedule also provides details on architectural works, MEP works including plumbing, electrical, and HVAC installation and testing.
This document contains a schedule for the lab2- Nbourdier Condo project. It lists activities with details like duration, start and finish dates, and type of work. Key activities include mobilization starting April 10th, site work from April 30th to October 1st including utilities installation and landscaping, foundation construction from May 12th to August 17th, and interior construction from August 13th to February 12th including mechanical, electrical and plumbing work, ceilings, flooring and other finishes. The schedule shows the critical path for completing the project by the final completion milestone of May 31st, 2016.
This weekly progress report provides an update on the enabling works for Al Jadaf Developments as of July 4, 2013. Key activities completed this week include the construction of guide walls in Plots H3 and S2, and ongoing secant pile wall construction in Plots H3 and S3. The forecast completion date has been delayed from November 10 to November 16 due to delays in authority approvals. Upcoming work includes obtaining permits for Plot H2 and continuing secant pile wall construction.
The progress review meeting covered the status of the construction contract, safety, quality, delays, cash flow, material and manpower mobilization, and site progress. The key points were: the work progress was 8% against a baseline of 33%; safety performance was good with no reportable incidents; quality issues included honeycombing and concrete bulges; major delays included tower crane and formwork material arrival; cash flow was tracking 11Cr against a baseline of 42.4Cr; and site photographs showed ongoing concrete work across multiple towers and structures.
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
This document provides a schedule for the Zewail City of Science and Technology B4 Contract project. It lists activities with original durations, start dates, and finish dates. The activities are grouped under headings like General, Engineering, Building B4-A, Ground Floor, Roof 1, etc. The schedule shows the project running from May 2015 to November 2016, with engineering tasks in early 2015, building work in mid-2015 to late 2016, and project handover in November 2016.
This document outlines the schedule for the Al Muraqqabat Mixed Use Development project. It lists over 100 activities with original durations, early start dates, early finish dates, late start dates, and late finish dates. The activities cover general project milestones, contractual milestones, civil works, architectural works, fit out and furnishings, MEP works, facades, authorities approvals, utilities connections, client submissions, engineering works, and mobilization tasks. The critical path runs through general project milestones with an overall planned duration of 537 days from January 2012 through October 2013.
This document outlines the activities, timelines, and progress for a waste water disposal wells project. It includes over 30 specific project tasks across various stages of earthworks, civil works, surveys, testing and drilling. The tasks range in duration from 1 to 16 days and are scheduled from May to August 2015, with percentage completions currently ranging from 0% to 84% across the different activities. The project is tracking to an end date of August 31, 2015 according to the provided schedule.
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
This document provides a schedule for engineering activities related to the Zewail City of Science and Technology B4 Contract project. It includes timelines for submitting and approving layout plans for various building systems for the basement and ground floors of Building B4, including electrical, mechanical, plumbing and other systems. The engineering work is scheduled to occur between October 2015 and November 2016, with layout plans due for approval between February and March 2016. Concurrent activities include builder works for the ground floor scheduled between March and April 2016.
1) The document outlines the construction phases for renovating two halls (A and B). It involves removing the existing roofs and frameworks, installing new steel frameworks, pouring composite floors, and completing roofing and cladding work.
2) A timeline from 2014 to mid-2015 is provided, showing the planned timing of construction phases in weekly and monthly increments.
3) Safety measures are noted such as using nets and laying plywood to protect the ground during construction work.
A Fellow member of the Institute of Company Secretaries of India with 8 years’ post membership experience in corporate, institutions as well as in practice in the field of Company law, FEMA, IPR, Taxation and appearance before various Quasi Judicial bodies including CLB, NCLT, CIT, etc.
Este taller práctico tiene como objetivo que los docentes identifiquen los cambios necesarios para incorporar las TIC al aula y currículo escolar. El taller busca que los docentes desarrollen habilidades, estrategias y competencias para contribuir al nuevo paradigma educativo propuesto por las TIC. El taller se desarrollará a través de estrategias individuales y colaborativas para identificar métodos para fomentar la creatividad docente, afianzar nuevas habilidades del siglo XXI y aplicar tendencias educativas basadas en pedagog
Company registration has always been a major hassle for people who are looking to start-up their own business in India.With so many procedures, it has always been a lengthy task with not much an ease to complete the process. The newly introduced INC-29, a five-in-one form introduced by Ministry of Corporate affairs (MCA) in May 2015 has come a long way in improving this scenario. This presentation guides you through all the procedures one needs to go till one is officially ready to set up a small business and the relevant documents required for the same.
Este documento describe los principales riesgos en seguridad y salud ocupacional como riesgos físicos, químicos, biológicos y ergonómicos. Explica las técnicas de prevención para cada riesgo, incluyendo el uso de equipos de protección personal, controles ambientales, diseño ergonómico del puesto de trabajo y programas de limpieza. El objetivo es identificar peligros y valorar riesgos para proteger la salud y seguridad de los trabajadores.
Este documento describe las principales fuentes del derecho tributario en Venezuela. Estas incluyen la Constitución, las leyes aprobadas por la Asamblea Nacional, los decretos leyes, los reglamentos, los tratados internacionales, las providencias administrativas, la doctrina y la jurisprudencia. Explica brevemente cada una de estas fuentes y cómo se relacionan entre sí de acuerdo con la jerarquía del derecho venezolano.
This document outlines a 16-stage fabrication and erection sequence for a tank storage terminal in Karimun, Indonesia. Stage 1 involves laying the annular plate and bottom plate foundations. Stages 2-4 continue bottom plate laying. Stage 5 completes bottom plate erection and begins the first shell course. Stages 6-8 erect the second shell course and add stairways. Stages 9-14 jack up layers and erect additional shell courses. Stage 15 completes shell laying. Stage 16 involves erecting the roof.
Este documento discute el federalismo fiscal en Venezuela, incluyendo las competencias tributarias del poder nacional, estadal y municipal según la constitución. También examina jurisprudencia relevante y limitaciones del sistema para lograr una distribución óptima de responsabilidades entre los niveles de gobierno. El objetivo general del federalismo fiscal en Venezuela es promover la eficiencia, responsabilidad y fortalecimiento de los territorios con más recursos y autonomía de gestión.
El documento trata sobre el origen, definición y autonomía del derecho financiero. Explica que el primer estudioso que definió este campo fue Myrbach Rheinfeld a principios del siglo XX. Define el derecho financiero como la reglamentación jurídica de las finanzas públicas del estado y otros entes. También discute las diferentes corrientes del derecho financiero y los principales temas que cubre como tributos, impuestos, tasas y el presupuesto.
ENSAYO SOBRE LAS FUENTES DEL DERECHO TRIBUTARIO. María Fabiana Quilesfabianaquileshey
Fuentes, definición, derecho general, constitución, la ley, los decretos, los tratados internacionales y los reglamentos. Derecho Tributario, Universidad Fermín Toro. María Fabiana Quiles
Este documento describe las características y objetivos de la Ley Venezolana de Derecho Internacional Privado de 1975. La ley tuvo como objetivos resolver problemas en el sistema de derecho internacional privado venezolano, ajustar la legislación a la realidad social del país, y adaptar las soluciones a avances en codificación internacional. La ley se caracteriza por reflejar soluciones de diferentes escuelas de derecho internacional privado, otorgar autonomía al juez, y contener normas generales.
This document provides an overview of project cost management. It defines key processes for planning, estimating, determining budgets, and controlling costs on a project. Section 7.1 discusses planning cost management by establishing policies and documentation for managing project costs. Section 7.2 covers estimating costs by developing approximations for completing project activities. Section 7.3 involves determining the project budget by aggregating activity cost estimates. Finally, section 7.4 is about controlling costs by monitoring project spending and updating the cost baseline.
Ahmed Moharam Mohamed Lotfy is an experienced Director of Engineering seeking a position as a Regional Director of Engineering. He has over 29 years of experience in hotel engineering roles including opening new hotels, managing engineering budgets and operations, and implementing preventative maintenance and energy saving plans. His experience includes roles at IHG, Accor, and Misr Real Estate Development. He has a bachelor's degree in engineering and various certifications and training in areas like HVAC, project management, and energy efficiency.
This document contains a master schedule for the preparation and processing of the twelfth floor of a headquarters building in Garden City. The schedule outlines 76 activities with original durations and planned start and finish dates from March 31, 2015 to June 14, 2015. Key milestones include establishing electrical, plumbing and HVAC by April 24, 50% of work done by May 16, 80% done including painting by June 4, and completing the project by June 14. The schedule also provides details on architectural works, MEP works including plumbing, electrical, and HVAC installation and testing.
This document contains a schedule for the lab2- Nbourdier Condo project. It lists activities with details like duration, start and finish dates, and type of work. Key activities include mobilization starting April 10th, site work from April 30th to October 1st including utilities installation and landscaping, foundation construction from May 12th to August 17th, and interior construction from August 13th to February 12th including mechanical, electrical and plumbing work, ceilings, flooring and other finishes. The schedule shows the critical path for completing the project by the final completion milestone of May 31st, 2016.
This weekly progress report provides an update on the enabling works for Al Jadaf Developments as of July 4, 2013. Key activities completed this week include the construction of guide walls in Plots H3 and S2, and ongoing secant pile wall construction in Plots H3 and S3. The forecast completion date has been delayed from November 10 to November 16 due to delays in authority approvals. Upcoming work includes obtaining permits for Plot H2 and continuing secant pile wall construction.
The progress review meeting covered the status of the construction contract, safety, quality, delays, cash flow, material and manpower mobilization, and site progress. The key points were: the work progress was 8% against a baseline of 33%; safety performance was good with no reportable incidents; quality issues included honeycombing and concrete bulges; major delays included tower crane and formwork material arrival; cash flow was tracking 11Cr against a baseline of 42.4Cr; and site photographs showed ongoing concrete work across multiple towers and structures.
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
This document provides a schedule for the Zewail City of Science and Technology B4 Contract project. It lists activities with original durations, start dates, and finish dates. The activities are grouped under headings like General, Engineering, Building B4-A, Ground Floor, Roof 1, etc. The schedule shows the project running from May 2015 to November 2016, with engineering tasks in early 2015, building work in mid-2015 to late 2016, and project handover in November 2016.
This document outlines the schedule for the Al Muraqqabat Mixed Use Development project. It lists over 100 activities with original durations, early start dates, early finish dates, late start dates, and late finish dates. The activities cover general project milestones, contractual milestones, civil works, architectural works, fit out and furnishings, MEP works, facades, authorities approvals, utilities connections, client submissions, engineering works, and mobilization tasks. The critical path runs through general project milestones with an overall planned duration of 537 days from January 2012 through October 2013.
This document outlines the activities, timelines, and progress for a waste water disposal wells project. It includes over 30 specific project tasks across various stages of earthworks, civil works, surveys, testing and drilling. The tasks range in duration from 1 to 16 days and are scheduled from May to August 2015, with percentage completions currently ranging from 0% to 84% across the different activities. The project is tracking to an end date of August 31, 2015 according to the provided schedule.
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
This document provides a schedule for engineering activities related to the Zewail City of Science and Technology B4 Contract project. It includes timelines for submitting and approving layout plans for various building systems for the basement and ground floors of Building B4, including electrical, mechanical, plumbing and other systems. The engineering work is scheduled to occur between October 2015 and November 2016, with layout plans due for approval between February and March 2016. Concurrent activities include builder works for the ground floor scheduled between March and April 2016.
1) The document outlines the construction phases for renovating two halls (A and B). It involves removing the existing roofs and frameworks, installing new steel frameworks, pouring composite floors, and completing roofing and cladding work.
2) A timeline from 2014 to mid-2015 is provided, showing the planned timing of construction phases in weekly and monthly increments.
3) Safety measures are noted such as using nets and laying plywood to protect the ground during construction work.
Single Family Gantt Chart-John MuellerJohn Mueller
The document provides a schedule for the excavation to framing and finish phases of the Merlin Single Family Project, including milestones, tasks, resources assigned, expected start and end dates from August 2015 through December 2015. It involves administrative tasks, excavation, foundation, framing, mechanical, electrical and plumbing work, inspections, and punchlist activities to close out the project.
The document is a project schedule for MEP works at the CICPA Qusahwira Complex in the United Arab Emirates. It details the engineering, shop drawings, material approval, and construction completion milestones for various buildings and components of the project. The schedule shows the original and remaining duration of tasks, as well as budgeted costs, actual costs incurred to date, and percentage of completion for the overall project and its sub-projects. The project is currently 42.76% complete and expected to be finished by July 2016.
This document contains a Gantt chart project schedule for the Majarrah Business Complex project. The schedule includes activities related to the Plaza Level portion of Stage I of the project, with durations from June 15, 2015 to December 31, 2015. Key activities include signing contracts, architectural and structural design, shop drawings submission and approval, material submittals and approvals, and installation of fountains, lighting, and landscaping elements. The critical path runs through design, shop drawings, material approvals, and installation activities, with the Plaza Level portion of Stage I scheduled to be completed by November 30, 2015.
The document outlines Qatar Petroleum procedures for constructing a pipe protection structure using an arch erection method. It details the excavation and preparation of the foundation, installation of arch elements with cranes, alignment checks, grouting of joints, and backfilling. Images show the erection sequence and requirements for placement of fill material over the completed structure before heavy vehicles can cross.
The document outlines Qatar Petroleum procedures for constructing a pipe protection structure using an arch erection method. It details the excavation and preparation of the foundation, installation of arch elements with cranes, alignment checks, grouting of joints, and backfilling. Images show the erection sequence and requirements for placement of fill material over the completed structure before heavy equipment can cross.
This document provides a schedule for fit out works for IHH Healthcare at 80 Bendemeer Road Phase 2. The schedule includes activities for reception and cafe area fit out, patient room fit outs, and other general works. Key activities and milestones include shop drawing approvals by December 14th, sample approvals by December 7th, authority approvals by December 28th, and completion of construction works by March 9th. The overall fit out works are scheduled to be completed by March 26th.
Naperville Woman’s Club Landmark Remodeling ProjectGeorgiann Baldino
Naperville Woman's Club’s Landmark building at 14 South Washington Street underwent extensive remodeling to remove architectural barriers. Members, guests and renters now enjoy full access to this historical Gothic Revival structure built in 1899. Three years of creative planning with the help of Naperville Heritage Society, Opperman Architects and Sequoia General Contracting Corp. led to a successful renovation. Naperville Woman’s Club now offers accessibility in ways that compliment an architecturally significant building. Their efforts adapted Naperville’s locally-designated Landmark for community use, while retaining this symbol of the City’s working class roots, religious origins and culture. For more information visit: http://www.napervillewomansclub.org/#!rental-calendar-information/c1s1t
This document contains a student transcript for Pardeep Sindhu listing the courses they have completed, not completed, failed, withdrew from, or are waitlisted for between 2010-2015 at ABB Inc. It shows that Pardeep has completed over 30 courses covering various electrical and industrial topics, but has a few courses still in progress or incomplete. Contact information is provided at the top for Pardeep in Saudi Arabia.
This document provides a progress update for the GE Compressor Rehabilitation Project. It includes information on 18 work packages that make up the project. As of the June 21st cutoff date, overall progress was 71.14%, with Civil & Structures and Process system work being the most complete at around 88% and 82% respectively. Electrical & Instrument work was lagging at around 62% completion. The project involves rehabilitation of compressors and associated equipment to restore and improve functionality.
The document provides details of the construction and engineering support services department of an organization. It includes information on cost estimates, procurement procedures, engineering works details, civil works details, establishment summary, manpower details by location, and expenditure on various projects. The department carries out engineering works, civil works, and provides support services using its staff of 369 regular employees, 21 contractual staff and 199 daily wage workers located across different sites.
This document provides a work program and schedule for the construction of a border crossing facility at Torkham. It outlines activities from February 2019 to September 2022. Key activities include design and construction drawings from April to September 2019, site grading works from May 2019 to September 2020, building works from October 2019 to September 2022, and infrastructure development works from April 2019 to July 2022. Progress payments will be submitted monthly from July 2019 to September 2022.
2. Activity Name Original
Duration
Start Finish
. Soorty 540d 31-Dec-2014 A 22-Jun-2016
..Soorty SOORTY GREEN FACTORY UNI 540d 31-Dec-2014 A 22-Jun-2016
..Soorty.Mob MOBILIZATION 47d 31-Dec-2014 A 29-Jan-2015 A
Start of Work 0d 31-Dec-2014 A
Mobilization / Approval of Concrete Mix design 30d 31-Dec-2014 A 29-Jan-2015 A
..Soorty.1 Sub Structure works 353d 11-Jan-2015 29-Dec-2015
Excavation Including Dismantling & Disposal 153d 11-Jan-2015 12-Jun-2015
Lean under Isolated Foundations & Walls 120d 16-Feb-2015 15-Jun-2015
Foundation Conc WorkAll Type 122d 19-Feb-2015 20-Jun-2015
Installation and Commisioning of Tower Crane 20d 06-Mar-2015 25-Mar-2015
..Soorty.1.. SOG Slab Conc 102d 31-Mar-2015 10-Jul-2015
SOG Under Zone-1 15d 31-Mar-2015 14-Apr-2015
SOG Under Zone-2 15d 15-Apr-2015 29-Apr-2015
SOG Under Zone -3 25d 30-Apr-2015 24-May-2015
SOG Under Zone-4 20d 25-May-2015 13-Jun-2015
SOG Under Zone-6 27d 14-Jun-2015 10-Jul-2015
..Soorty.1.1 Conc Work Retaining Wall, Lift Wall & W 264d 10-Apr-2015 29-Dec-2015
..Soorty.1.1.1 East Wall 83d 10-Apr-2015 01-Jul-2015
Excavation( Rain Water Tank) 15d 10-Apr-2015 24-Apr-2015
Base Slab Lean 8d 18-Apr-2015 25-Apr-2015
Rebar Fixing of Base Slab including Formwork 15d 22-Apr-2015 06-May-2015
Pouring of Base Slab 4d 02-May-2015 05-May-2015
Rebar Fixing of Wall 20d 03-May-2015 22-May-2015
Formwork of Wall 20d 07-May-2015 26-May-2015
Pouring of wall 22d 12-May-2015 02-Jun-2015
Slab form work 20d 22-May-2015 10-Jun-2015
Slab Rebar 10d 03-Jun-2015 12-Jun-2015
Slab Pouring 10d 05-Jun-2015 14-Jun-2015
Excavation for Retaining Wall 15d 25-May-2015 08-Jun-2015
Base Slab Lean Line15/Grid N~ I 15d 27-May-2015 10-Jun-2015
Rebar Fixing of Base Slab including Formwork as
per section N-N
13d 31-May-2015 12-Jun-2015
Pouring of Base Slab 9d 07-Jun-2015 15-Jun-2015
Rebar Fixing of Wall incl wall above tank slab 10d 09-Jun-2015 18-Jun-2015
Formwork of Wall incl wall above tank slab 15d 11-Jun-2015 25-Jun-2015
Pouring of wall incl wall above tank slab 18d 14-Jun-2015 01-Jul-2015
..Soorty.1.1.2 North Wall 254d 20-Apr-2015 29-Dec-2015
Excavation 30d 20-Apr-2015 19-May-2015
Base Slab Lean 20d 25-Apr-2015 14-May-2015
Rebar Fixing of Base Slab including Formwork 22d 27-Apr-2015 18-May-2015
Pouring of Base Slab 24d 02-May-2015 25-May-2015
Rebar Fixing of Wall 22d 06-May-2015 27-May-2015
Formwork of Wall 26d 08-May-2015 02-Jun-2015
Pouring of wall 30d 10-May-2015 08-Jun-2015
Earth Filling upto soffit of Beam/Planter Slab at wa 25d 01-Aug-2015 25-Aug-2015
Install Rebar for beams/Planter Slab along with PC 30d 21-Aug-2015 19-Sep-2015
Instal formwork for beams at wall back off 25d 10-Sep-2015 04-Oct-2015
Pour Concrete for beams/Planter Slab at wall back 15d 30-Sep-2015 14-Oct-2015
Resume earth Filling upto Top of Beams/Planter A 30d 10-Oct-2015 08-Nov-2015
Install Rebar For PC Columns 25d 02-Nov-2015 26-Nov-2015
Install Formwork for PC columns 30d 20-Nov-2015 19-Dec-2015
Pour Concrete For PC Columns 20d 10-Dec-2015 29-Dec-2015
..Soorty.1.1.3 West Wall inclu Effluent Pit 92d 30-Apr-2015 30-Jul-2015
Excavation 30d 30-Apr-2015 29-May-2015
Base Slab Lean 30d 11-May-2015 09-Jun-2015
Rebar Fixing of Base Slab including Formwork 25d 15-May-2015 08-Jun-2015
Pouring of Base Slab 13d 01-Jun-2015 13-Jun-2015
Rebar Fixing of Wall 15d 06-Jun-2015 20-Jun-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
-Dec-2014 22-Jun-2
-Dec-2014 22-Jun-2
-Dec-2014 16-Feb-2015
Start of Work
11-Jan-2015 29-Dec-2015
31-Mar-2015 10-Jul-2015
10-Apr-2015 29-Dec-2015
10-Apr-2015 01-Jul-2015
20-Apr-2015 29-Dec-2015
30-Apr-2015 30-Jul-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary
3. Activity Name Original
Duration
Start Finish
Formwork of Wall 20d 10-Jun-2015 29-Jun-2015
Pouring of wall 20d 13-Jun-2015 02-Jul-2015
Slab form work for Rain Water Tank 15d 18-Jun-2015 02-Jul-2015
Slab Rebar for Rain Water Tank 10d 28-Jun-2015 07-Jul-2015
Slab Pouring for Rain Water Tank 10d 30-Jun-2015 09-Jul-2015
Rebar Fixing of Wall above tank slab 8d 12-Jul-2015 19-Jul-2015
Formwork of Wall above tank slab 12d 16-Jul-2015 27-Jul-2015
Pouring of wall above tank slab 10d 21-Jul-2015 30-Jul-2015
..Soorty.1.1.4 South Wall 36d 09-Jun-2015 14-Jul-2015
Excavation 20d 09-Jun-2015 28-Jun-2015
Base Slab Lean 21d 09-Jun-2015 29-Jun-2015
Rebar Fixing of Base Slab including Formwork 22d 13-Jun-2015 04-Jul-2015
Pouring of Base Slab 22d 15-Jun-2015 06-Jul-2015
Rebar Fixing of Wall 18d 21-Jun-2015 08-Jul-2015
Formwork of Wall 17d 25-Jun-2015 11-Jul-2015
Pouring of wall 19d 26-Jun-2015 14-Jul-2015
..Soorty.2 Ground Floor (Basment Slab) at EL4'-3" 100d 20-Apr-2015 28-Jul-2015
..Soorty.2.1 GZ1 42d 20-Apr-2015 31-May-2015
Layout (Zone 1 ~ Zone-6) 20d 20-Apr-2015 09-May-2015
column reinf 8d 21-Apr-2015 28-Apr-2015
Column Erection (Formwork) 10d 22-Apr-2015 01-May-2015
Column Concrete 7d 26-Apr-2015 02-May-2015
Column Formwork removel 8d 27-Apr-2015 04-May-2015
Beams & Slab erection (formwork) 15d 30-Apr-2015 14-May-2015
Beams & Slab Reinf 27d 02-May-2015 28-May-2015
Final Closing & inspection 1d 30-May-2015 30-May-2015
Beams & Slab Concrete 1d 31-May-2015 31-May-2015
..Soorty.2.2 GZ2 45d 01-May-2015 14-Jun-2015
Column Erection 20d 01-May-2015 20-May-2015
Column Concrete 21d 02-May-2015 22-May-2015
Column Formwork removel 21d 03-May-2015 23-May-2015
Beams & Slab erection (formwork) 15d 20-May-2015 03-Jun-2015
Beams & Slab Reinf 22d 22-May-2015 12-Jun-2015
Final Closing & inspection 1d 14-Jun-2015 14-Jun-2015
Beams & Slab Concrete 1d 14-Jun-2015 14-Jun-2015
..Soorty.2.3 GZ3 37d 24-May-2015 29-Jun-2015
Column Erection (Formwork) 8d 24-May-2015 31-May-2015
Column Concrete 7d 26-May-2015 01-Jun-2015
Column Formwork removel 8d 27-May-2015 03-Jun-2015
Beams & Slab erection (formwork) 15d 08-Jun-2015 22-Jun-2015
Beams & Slab Reinf 14d 13-Jun-2015 26-Jun-2015
Final Closing & inspection 1d 28-Jun-2015 28-Jun-2015
Beams & Slab Concrete 1d 29-Jun-2015 29-Jun-2015
..Soorty.2.4 GZ4 29d 04-Jun-2015 02-Jul-2015
Column Erection (Formwork) 10d 04-Jun-2015 13-Jun-2015
Column Concrete 7d 08-Jun-2015 14-Jun-2015
Column Formwork removel 8d 09-Jun-2015 16-Jun-2015
Beams & Slab erection (formwork) 15d 11-Jun-2015 25-Jun-2015
Beams & Slab Reinf 14d 16-Jun-2015 29-Jun-2015
Final Closing & inspection 1d 01-Jul-2015 01-Jul-2015
Beams & Slab Concrete 1d 02-Jul-2015 02-Jul-2015
..Soorty.2.5 GZ5 29d 17-Jun-2015 15-Jul-2015
Column Erection (Formwork) 10d 17-Jun-2015 26-Jun-2015
Column Concrete 7d 21-Jun-2015 27-Jun-2015
Column Formwork removel 8d 22-Jun-2015 29-Jun-2015
Beams & Slab erection (formwork) 15d 24-Jun-2015 08-Jul-2015
Beams & Slab Reinf 14d 29-Jun-2015 12-Jul-2015
Final Closing & inspection 1d 14-Jul-2015 14-Jul-2015
2 3 0 1 2 2 0 1 1 2 0 0 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1 2 0 1 1 2
D January F March April May June July August S October N D January F March April May June July
2015 2016
09-Jun-2015 14-Jul-2015
20-Apr-2015 28-Jul-2015
20-Apr-2015 31-May-2015
01-May-2015 14-Jun-2015
24-May-2015 29-Jun-2015
04-Jun-2015 02-Jul-2015
17-Jun-2015 15-Jul-2015
SOORTY GREEN FACTORY -14
Will be review after reciving of IFC Drawings
Date Revision Checked Approved
26-May-2015 Draft Copy only for Review & comments
Remaining Work
Critical Remaining Work
Milestone
Summary