Project: GE Compressor Rehabilitation Project
Contract No: SIGUP-12-066A/B Cut-off date: 21 Jun 2015
8 10 11 12 13
03 May 15 07 Jun 15 14 Jun 15 21 Jun 15
CS1A - WO4&WO5 CS1A 49,726 01 Jun 2014 10 Nov 2015 01 Jun 2014 ---- 49.99% 65.32% 68.79% 71.14%
4 - Construction 46,146 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 53.94% 70.43% 74.19% 76.23%
4 - Site office and field work area preparation 1,800 01 Jul 2014 31 Jul 2014 01 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100%
1 - Mechanical 14,850 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 50.27% 67.38% 68.99% 73.85%
1 - Compressor on-skid and Auxiliaries 8,100 13 Mar 2015 05 Oct 2015 13 Mar 2015 ---- 46.32% 63.88% 63.88% 67.05%
1 - Centrifugal Compressor 1,630 15 Mar 2015 05 Oct 2015 15 Mar 2015 ---- 42.33% 42.33% 42.33% 42.33%
2 - Gear box 680 15 Mar 2015 15 Sep 2015 15 Mar 2015 ---- 32.35% 32.35% 32.35% 32.35%
3 - Electrical motor 420 15 Mar 2015 22 Jun 2015 15 Mar 2015 ---- 85.71% 90.48% 90.48% 90.48%
4 - Compressor Auxiliaries 2,270 13 Mar 2015 18 Sep 2015 13 Mar 2015 ---- 56.78% 92.29% 92.29% 92.29%
8 - Seal Oil Overhead Tank (New) 80 23 Apr 2015 17 Sep 2015 23 Apr 2015 ---- 0.00% 0.00% 0.00% 0.00%
2 - Manual valve replacement 750 05 Apr 2015 13 Aug 2015 05 Apr 2015 ---- 96.67% 96.67% 96.67% 96.67%
5 - Heaters 100 11 Apr 2015 23 Apr 2015 11 Apr 2015 23 Apr 2015 0.00% 100.00% 100.00% 100.00%
1 - LO and SO motor and pumps replacement 320 13 Mar 2015 26 Apr 2015 13 Mar 2015 26 Apr 2015 85.00% 100.00% 100.00% 100.00%
3 - Control valves (PCV & DPCV & LCV) 100 10 Apr 2015 27 Jun 2015 10 Apr 2015 ---- 60.00% 60.00% 60.00% 60.00%
7 - Compressor Skid Instrument 220 05 Apr 2015 18 Sep 2015 05 Apr 2015 ---- 67.14% 86.36% 86.36% 86.36%
6 - TCV piping modification and valve installation 600 04 May 2015 21 May 2015 04 May 2015 21 May 2015 100.00% 100.00% 100.00% 100.00%
4 - PSV 100 10 Apr 2015 10 May 2015 10 Apr 2015 10 May 2015 81.82% 100.00% 100.00% 100.00%
6 - Oil flushing preparation and execution 2,840 14 Mar 2015 09 Sep 2015 14 Mar 2015 ---- 36.27% 52.11% 52.11% 65.00%
5 - Oil cooler 260 15 Mar 2015 14 Aug 2015 15 Mar 2015 ---- 53.85% 76.92% 76.92% 76.92%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 0.00% 50.00% 50.00% 50.00%
2 - Pneumatic Test 140 15 Mar 2015 04 Apr 2015 15 Mar 2015 04 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Process system 6,750 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 54.87% 71.47% 74.96% 82.01%
1 - Gas cooler 1,480 22 Apr 2015 09 Sep 2015 22 Apr 2015 ---- 63.70% 50.81% 65.41% 83.78%
2 - Hydraulic test 1,060 22 Apr 2015 16 Jun 2015 22 Apr 2015 16 Jun 2015 85.42% 69.81% 81.13% 100.00%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 33.33% 50.00% 50.00% 50.00%
3 - Process Pipe 2,920 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 33.33% 65.62% 65.62% 72.60%
5 - Process piping cleaning 960 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 55.56% 91.25% 91.25% 100.00%
3 - PSV 480 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 78.95% 33.33% 33.33% 33.33%
4 - MOV and SDV 540 21 Jul 2014 07 Sep 2015 21 Jul 2014 ---- 65.70% 33.33% 33.33% 33.33%
2 - Process Control Valves 180 21 Jul 2014 15 Sep 2015 21 Jul 2014 ---- 77.27% 55.56% 55.56% 55.56%
1 - Manual valve replacement 760 20 Apr 2015 27 Jun 2015 20 Apr 2015 ---- 54.74% 78.95% 78.95% 94.74%
2 - Vessel 2,350 12 Mar 2015 07 Jul 2015 12 Mar 2015 ---- 77.78% 91.74% 92.60% 92.60%
4 - Level control valve & Glass - Klinger 510 17 Apr 2015 07 Jun 2015 17 Apr 2015 07 Jun 2015 40.39% 100.00% 100.00% 100.00%
2 - Manual valve replacement on Vessels V5,V6,V7,V10 1,100 16 Apr 2015 07 Jul 2015 16 Apr 2015 ---- 20.27% 96.36% 96.36% 96.36%
3 - Level Control Valve Replacement 380 14 Apr 2015 07 Jul 2015 14 Apr 2015 ---- 28.30% 80.53% 85.79% 85.79%
1 - Inspection 360 12 Mar 2015 22 Jun 2015 12 Mar 2015 ---- 0.00% 77.78% 77.78% 77.78%
2 - Civil & Structures 15,800 26 Jan 2015 12 Sep 2015 26 Jan 2015 ---- 77.78% 85.03% 87.66% 88.23%
2 - Structures 2,920 26 Jan 2015 27 Aug 2015 26 Jan 2015 ---- 91.78% 91.78% 91.78% 91.78%
1 - Overhead crane replacement 2,680 26 Jan 2015 14 Mar 2015 26 Jan 2015 14 Mar 2015 0.00% 100.00% 100.00% 100.00%
2 - Gratings and platform 240 15 Aug 2015 27 Aug 2015 ---- ---- 100.00% 0.00% 0.00% 0.00%
1 - Civil 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
1 - Excavation & Foundation Works (COMMON TO TRAINS A&B) 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
7 - Fiber opthic/Ethernet from UCP to HMI: (SOK9951893 cable routing plan) 120 30 Mar 2015 09 May 2015 30 Mar 2015 09 May 2015 94.44% 100.00% 100.00% 100.00%
9 - Additional Earthing System 1,080 05 Apr 2015 09 May 2015 05 Apr 2015 09 May 2015 68.33% 100.00% 100.00% 100.00%
3 - Cable routing for compressor area (T7 e T8) 2,700 16 Mar 2015 12 Sep 2015 16 Mar 2015 ---- 86.67% 70.00% 70.00% 73.33%
1 - UCP (ref dwg.SOK2310988) 900 01 Mar 2015 09 May 2015 01 Mar 2015 09 May 2015 93.85% 100.00% 100.00% 100.00%
2 - Cable routing from MCC to UCP (T1, DB1, T2) 2,780 13 Mar 2015 08 Jun 2015 13 Mar 2015 08 Jun 2015 66.67% 85.00% 100.00% 100.00%
6 - Corrugated pipes on BOP [-P6,7,17,19,20,23—from C5 to C7, C9, from C1 1,300 30 Mar 2015 16 May 2015 30 Mar 2015 16 May 2015 97.69% 100.00% 100.00% 100.00%
4 - Cable routing for BOP [T5A, DB8A, between gas cooler and V7=T5A/1 e sle 2,700 16 Mar 2015 10 Sep 2015 16 Mar 2015 ---- 65.76% 66.67% 66.67% 66.67%
5 - Corrugate pipe on compressor (SOK 9951893 pag 4/4) P2,3,4 C8, from C 1,300 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 66.67% 100.00% 100.00% 100.00%
3 - Electrical & Instrument 13,696 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 23.61% 52.57% 60.52% 61.84%
8 - Fire Fighting System 1,280 11 May 2015 14 Sep 2015 11 May 2015 ---- 0.00% 51.09% 77.34% 77.34%
10 - MV&LV Cable trays installation (COMMON TO TRAINS A&B) 320 08 Apr 2015 24 Apr 2015 08 Apr 2015 24 Apr 2015 36.36% 100.00% 100.00% 100.00%
14 - Replacement of Instrumentation on Compressor skid 740 13 Apr 2015 10 Sep 2015 13 Apr 2015 ---- 100.00% 37.84% 37.84% 37.84%
3 - UPS (COMMON TO TRAINS A&B) 160 09 Apr 2015 13 Apr 2015 09 Apr 2015 13 Apr 2015 40.54% 100.00% 100.00% 100.00%
16 - Instrument Air 660 30 Apr 2015 25 Jun 2015 30 Apr 2015 ---- 37.84% 94.55% 94.55% 94.55%
15 - Replacement of Instrumentation on BoP and Process 1,480 14 Apr 2015 12 Oct 2015 14 Apr 2015 ---- 100.00% 56.76% 73.78% 77.03%
13 - Lighting system on field 1,900 17 Apr 2015 05 Nov 2015 17 Apr 2015 ---- 21.05% 50.26% 58.95% 60.53%
11 - Instrument Cable trays 1,400 06 Apr 2015 29 Sep 2015 06 Apr 2015 ---- 20.00% 77.00% 88.00% 90.86%
12 - Cable Laying/Test/Termination 3,642 31 Jul 2014 02 Sep 2015 31 Jul 2014 ---- 2.20% 26.96% 31.27% 38.17%
1 - MV Cable 80 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 0.00% 100.00% 100.00% 100.00%
2 - LV Cable 1,362 12 May 2015 02 Sep 2015 12 May 2015 ---- 100.00% 39.79% 51.32% 69.75%
3 - Instrument Cable 2,200 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 0.00% 16.36% 16.36% 16.36%
4 - Batteries (COMMON TO TRAINS A&B) 180 03 Sep 2015 15 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - F&G (COMMON TO TRAINS A&B) 160 16 Apr 2015 18 Apr 2015 16 Apr 2015 18 Apr 2015 100.00% 100.00% 100.00% 100.00%
7 - Air conditioning system (COMMON TO TRAINS A&B) 80 28 Aug 2015 03 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
1 - Inspections 640 01 Jul 2014 12 Apr 2015 01 Jul 2014 12 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Battery room refurbishment (COMMON TO TRAINS A&B) 490 21 Jun 2015 17 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
18 - UCP 344 01 May 2015 30 May 2015 01 May 2015 30 May 2015 0.00% 100.00% 100.00% 100.00%
5 - Pre-Commissioning & Commissioning 3,580 31 Jul 2014 10 Nov 2015 31 Jul 2014 ---- 3.61% 5.26% 5.26% 5.59%
2 - Electrical and control test 20 09 May 2015 10 May 2015 09 May 2015 10 May 2015 0.00% 100.00% 100.00% 100.00%
3 - MVA Transformer activities 140 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100.00%
4 - MCC Activities 80 18 Sep 2015 23 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Fire fighting system commissioning 420 08 Oct 2015 02 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
7 - DCP Commissioning 320 17 Sep 2015 08 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
8 - UCP activities 640 21 Sep 2015 19 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
9 - Functional test compressor unit and BoP equipment 820 09 Oct 2015 11 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
10 - Motor rotating equipment 360 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 11.11% 11.11% 11.11%
1 - Main and aux lube oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
2 - Main and aux seal oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
3 - #6 gas cooler motor bump test, belt installation and running test 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
4 - #3 main & #3 stand-by Lube Oil cooler motors bump test, coupling installation and run 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - #3 main & #3 stand-by Seal Oil cooler motors bump test, coupling installation and run t 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Seal oil degassing tank agitator and blower motor bump test, coupling installation and ru 60 10 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
11 - MV Motor activities 120 11 Oct 2015 13 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
12 - Alignment and Load Coupling installation 360 13 Oct 2015 16 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
13 - Unit Start-up 300 19 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
Actual %
WO5A CS1A Construction Progress Status Report
CONSTRUCTION PHASES & AREAS
Budgeted
Labour
Units
Start Finish
Actual
Start
Actual Finish

More Related Content

What's hot

OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test bench
OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test benchOPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test bench
OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test benchOPAL-RT TECHNOLOGIES
 
Oscar Alvarez. Presentation
Oscar Alvarez. PresentationOscar Alvarez. Presentation
Oscar Alvarez. PresentationOscar Alvarez
 
Monthly report march, 2020(word)
Monthly report march, 2020(word)Monthly report march, 2020(word)
Monthly report march, 2020(word)thomas victor
 
Compact Loaders Dec 2010
Compact Loaders Dec 2010Compact Loaders Dec 2010
Compact Loaders Dec 2010FrankPlas
 
Elsayed Mohamed Elsayed.rev6
Elsayed Mohamed Elsayed.rev6Elsayed Mohamed Elsayed.rev6
Elsayed Mohamed Elsayed.rev6Elsayed Mohamed
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout Javier Siles
 
Uma mahesh Resume
Uma mahesh ResumeUma mahesh Resume
Uma mahesh Resumeuma mahesh
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringEva Susiani
 
SAID SAAD ALY CV
SAID SAAD ALY CVSAID SAAD ALY CV
SAID SAAD ALY CVSaid Ali
 

What's hot (12)

OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test bench
OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test benchOPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test bench
OPAL-RT RT14 Conference: Experience in power plant with RT-LAB BERTA test bench
 
Oscar Alvarez. Presentation
Oscar Alvarez. PresentationOscar Alvarez. Presentation
Oscar Alvarez. Presentation
 
Monthly report march, 2020(word)
Monthly report march, 2020(word)Monthly report march, 2020(word)
Monthly report march, 2020(word)
 
Compact Loaders Dec 2010
Compact Loaders Dec 2010Compact Loaders Dec 2010
Compact Loaders Dec 2010
 
Elsayed Mohamed Elsayed.rev6
Elsayed Mohamed Elsayed.rev6Elsayed Mohamed Elsayed.rev6
Elsayed Mohamed Elsayed.rev6
 
cei_overview
cei_overviewcei_overview
cei_overview
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
 
Uma mahesh Resume
Uma mahesh ResumeUma mahesh Resume
Uma mahesh Resume
 
manual de honeywell
manual de honeywellmanual de honeywell
manual de honeywell
 
Production Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical EngineeringProduction Operation Maintenance & Mechanical Engineering
Production Operation Maintenance & Mechanical Engineering
 
Dashboard
DashboardDashboard
Dashboard
 
SAID SAAD ALY CV
SAID SAAD ALY CVSAID SAAD ALY CV
SAID SAAD ALY CV
 

Similar to GE Compressor Rehabilitation Project Progress

Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015William Irving
 
Daily Production & WIP Analysis Dashboard - page 1
Daily Production & WIP Analysis Dashboard - page 1Daily Production & WIP Analysis Dashboard - page 1
Daily Production & WIP Analysis Dashboard - page 1Imran Yousuf
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxsantosh509014
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Fuel and Emission Systems Troubleshooting Information
Fuel and Emission Systems Troubleshooting InformationFuel and Emission Systems Troubleshooting Information
Fuel and Emission Systems Troubleshooting InformationOBD Codex
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptxnkarthik21
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptxnkarthik21
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdf
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdfJohn Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdf
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdfReparacionPcLaptopsDesktop
 
New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentationebbin daniel
 
supply_program compressors 2007
supply_program compressors 2007supply_program compressors 2007
supply_program compressors 2007Guenter Kirsten
 
IE4Brochure Crompton Greaves
IE4Brochure Crompton GreavesIE4Brochure Crompton Greaves
IE4Brochure Crompton GreavesMarketingSIRUS
 
Kollmorgen pma series_catalog
Kollmorgen  pma  series_catalogKollmorgen  pma  series_catalog
Kollmorgen pma series_catalogElectromate
 

Similar to GE Compressor Rehabilitation Project Progress (20)

Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
 
WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01
 
Daily Production & WIP Analysis Dashboard - page 1
Daily Production & WIP Analysis Dashboard - page 1Daily Production & WIP Analysis Dashboard - page 1
Daily Production & WIP Analysis Dashboard - page 1
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptx
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
 
Fuel and Emission Systems Troubleshooting Information
Fuel and Emission Systems Troubleshooting InformationFuel and Emission Systems Troubleshooting Information
Fuel and Emission Systems Troubleshooting Information
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdf
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdfJohn Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdf
John Deere 9650 STS and 9750 STS Combines Diagnosis and Tests Manual-TM1902.pdf
 
New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentation
 
supply_program compressors 2007
supply_program compressors 2007supply_program compressors 2007
supply_program compressors 2007
 
VW Training
VW TrainingVW Training
VW Training
 
IE4Brochure Crompton Greaves
IE4Brochure Crompton GreavesIE4Brochure Crompton Greaves
IE4Brochure Crompton Greaves
 
Kollmorgen pma series_catalog
Kollmorgen  pma  series_catalogKollmorgen  pma  series_catalog
Kollmorgen pma series_catalog
 

GE Compressor Rehabilitation Project Progress

  • 1. Project: GE Compressor Rehabilitation Project Contract No: SIGUP-12-066A/B Cut-off date: 21 Jun 2015 8 10 11 12 13 03 May 15 07 Jun 15 14 Jun 15 21 Jun 15 CS1A - WO4&WO5 CS1A 49,726 01 Jun 2014 10 Nov 2015 01 Jun 2014 ---- 49.99% 65.32% 68.79% 71.14% 4 - Construction 46,146 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 53.94% 70.43% 74.19% 76.23% 4 - Site office and field work area preparation 1,800 01 Jul 2014 31 Jul 2014 01 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100% 1 - Mechanical 14,850 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 50.27% 67.38% 68.99% 73.85% 1 - Compressor on-skid and Auxiliaries 8,100 13 Mar 2015 05 Oct 2015 13 Mar 2015 ---- 46.32% 63.88% 63.88% 67.05% 1 - Centrifugal Compressor 1,630 15 Mar 2015 05 Oct 2015 15 Mar 2015 ---- 42.33% 42.33% 42.33% 42.33% 2 - Gear box 680 15 Mar 2015 15 Sep 2015 15 Mar 2015 ---- 32.35% 32.35% 32.35% 32.35% 3 - Electrical motor 420 15 Mar 2015 22 Jun 2015 15 Mar 2015 ---- 85.71% 90.48% 90.48% 90.48% 4 - Compressor Auxiliaries 2,270 13 Mar 2015 18 Sep 2015 13 Mar 2015 ---- 56.78% 92.29% 92.29% 92.29% 8 - Seal Oil Overhead Tank (New) 80 23 Apr 2015 17 Sep 2015 23 Apr 2015 ---- 0.00% 0.00% 0.00% 0.00% 2 - Manual valve replacement 750 05 Apr 2015 13 Aug 2015 05 Apr 2015 ---- 96.67% 96.67% 96.67% 96.67% 5 - Heaters 100 11 Apr 2015 23 Apr 2015 11 Apr 2015 23 Apr 2015 0.00% 100.00% 100.00% 100.00% 1 - LO and SO motor and pumps replacement 320 13 Mar 2015 26 Apr 2015 13 Mar 2015 26 Apr 2015 85.00% 100.00% 100.00% 100.00% 3 - Control valves (PCV & DPCV & LCV) 100 10 Apr 2015 27 Jun 2015 10 Apr 2015 ---- 60.00% 60.00% 60.00% 60.00% 7 - Compressor Skid Instrument 220 05 Apr 2015 18 Sep 2015 05 Apr 2015 ---- 67.14% 86.36% 86.36% 86.36% 6 - TCV piping modification and valve installation 600 04 May 2015 21 May 2015 04 May 2015 21 May 2015 100.00% 100.00% 100.00% 100.00% 4 - PSV 100 10 Apr 2015 10 May 2015 10 Apr 2015 10 May 2015 81.82% 100.00% 100.00% 100.00% 6 - Oil flushing preparation and execution 2,840 14 Mar 2015 09 Sep 2015 14 Mar 2015 ---- 36.27% 52.11% 52.11% 65.00% 5 - Oil cooler 260 15 Mar 2015 14 Aug 2015 15 Mar 2015 ---- 53.85% 76.92% 76.92% 76.92% 1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 0.00% 50.00% 50.00% 50.00% 2 - Pneumatic Test 140 15 Mar 2015 04 Apr 2015 15 Mar 2015 04 Apr 2015 100.00% 100.00% 100.00% 100.00% 2 - Process system 6,750 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 54.87% 71.47% 74.96% 82.01% 1 - Gas cooler 1,480 22 Apr 2015 09 Sep 2015 22 Apr 2015 ---- 63.70% 50.81% 65.41% 83.78% 2 - Hydraulic test 1,060 22 Apr 2015 16 Jun 2015 22 Apr 2015 16 Jun 2015 85.42% 69.81% 81.13% 100.00% 1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 33.33% 50.00% 50.00% 50.00% 3 - Process Pipe 2,920 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 33.33% 65.62% 65.62% 72.60% 5 - Process piping cleaning 960 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 55.56% 91.25% 91.25% 100.00% 3 - PSV 480 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 78.95% 33.33% 33.33% 33.33% 4 - MOV and SDV 540 21 Jul 2014 07 Sep 2015 21 Jul 2014 ---- 65.70% 33.33% 33.33% 33.33% 2 - Process Control Valves 180 21 Jul 2014 15 Sep 2015 21 Jul 2014 ---- 77.27% 55.56% 55.56% 55.56% 1 - Manual valve replacement 760 20 Apr 2015 27 Jun 2015 20 Apr 2015 ---- 54.74% 78.95% 78.95% 94.74% 2 - Vessel 2,350 12 Mar 2015 07 Jul 2015 12 Mar 2015 ---- 77.78% 91.74% 92.60% 92.60% 4 - Level control valve & Glass - Klinger 510 17 Apr 2015 07 Jun 2015 17 Apr 2015 07 Jun 2015 40.39% 100.00% 100.00% 100.00% 2 - Manual valve replacement on Vessels V5,V6,V7,V10 1,100 16 Apr 2015 07 Jul 2015 16 Apr 2015 ---- 20.27% 96.36% 96.36% 96.36% 3 - Level Control Valve Replacement 380 14 Apr 2015 07 Jul 2015 14 Apr 2015 ---- 28.30% 80.53% 85.79% 85.79% 1 - Inspection 360 12 Mar 2015 22 Jun 2015 12 Mar 2015 ---- 0.00% 77.78% 77.78% 77.78% 2 - Civil & Structures 15,800 26 Jan 2015 12 Sep 2015 26 Jan 2015 ---- 77.78% 85.03% 87.66% 88.23% 2 - Structures 2,920 26 Jan 2015 27 Aug 2015 26 Jan 2015 ---- 91.78% 91.78% 91.78% 91.78% 1 - Overhead crane replacement 2,680 26 Jan 2015 14 Mar 2015 26 Jan 2015 14 Mar 2015 0.00% 100.00% 100.00% 100.00% 2 - Gratings and platform 240 15 Aug 2015 27 Aug 2015 ---- ---- 100.00% 0.00% 0.00% 0.00% 1 - Civil 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42% 1 - Excavation & Foundation Works (COMMON TO TRAINS A&B) 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42% 7 - Fiber opthic/Ethernet from UCP to HMI: (SOK9951893 cable routing plan) 120 30 Mar 2015 09 May 2015 30 Mar 2015 09 May 2015 94.44% 100.00% 100.00% 100.00% 9 - Additional Earthing System 1,080 05 Apr 2015 09 May 2015 05 Apr 2015 09 May 2015 68.33% 100.00% 100.00% 100.00% 3 - Cable routing for compressor area (T7 e T8) 2,700 16 Mar 2015 12 Sep 2015 16 Mar 2015 ---- 86.67% 70.00% 70.00% 73.33% 1 - UCP (ref dwg.SOK2310988) 900 01 Mar 2015 09 May 2015 01 Mar 2015 09 May 2015 93.85% 100.00% 100.00% 100.00% 2 - Cable routing from MCC to UCP (T1, DB1, T2) 2,780 13 Mar 2015 08 Jun 2015 13 Mar 2015 08 Jun 2015 66.67% 85.00% 100.00% 100.00% 6 - Corrugated pipes on BOP [-P6,7,17,19,20,23—from C5 to C7, C9, from C1 1,300 30 Mar 2015 16 May 2015 30 Mar 2015 16 May 2015 97.69% 100.00% 100.00% 100.00% 4 - Cable routing for BOP [T5A, DB8A, between gas cooler and V7=T5A/1 e sle 2,700 16 Mar 2015 10 Sep 2015 16 Mar 2015 ---- 65.76% 66.67% 66.67% 66.67% 5 - Corrugate pipe on compressor (SOK 9951893 pag 4/4) P2,3,4 C8, from C 1,300 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 66.67% 100.00% 100.00% 100.00% 3 - Electrical & Instrument 13,696 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 23.61% 52.57% 60.52% 61.84% 8 - Fire Fighting System 1,280 11 May 2015 14 Sep 2015 11 May 2015 ---- 0.00% 51.09% 77.34% 77.34% 10 - MV&LV Cable trays installation (COMMON TO TRAINS A&B) 320 08 Apr 2015 24 Apr 2015 08 Apr 2015 24 Apr 2015 36.36% 100.00% 100.00% 100.00% 14 - Replacement of Instrumentation on Compressor skid 740 13 Apr 2015 10 Sep 2015 13 Apr 2015 ---- 100.00% 37.84% 37.84% 37.84% 3 - UPS (COMMON TO TRAINS A&B) 160 09 Apr 2015 13 Apr 2015 09 Apr 2015 13 Apr 2015 40.54% 100.00% 100.00% 100.00% 16 - Instrument Air 660 30 Apr 2015 25 Jun 2015 30 Apr 2015 ---- 37.84% 94.55% 94.55% 94.55% 15 - Replacement of Instrumentation on BoP and Process 1,480 14 Apr 2015 12 Oct 2015 14 Apr 2015 ---- 100.00% 56.76% 73.78% 77.03% 13 - Lighting system on field 1,900 17 Apr 2015 05 Nov 2015 17 Apr 2015 ---- 21.05% 50.26% 58.95% 60.53% 11 - Instrument Cable trays 1,400 06 Apr 2015 29 Sep 2015 06 Apr 2015 ---- 20.00% 77.00% 88.00% 90.86% 12 - Cable Laying/Test/Termination 3,642 31 Jul 2014 02 Sep 2015 31 Jul 2014 ---- 2.20% 26.96% 31.27% 38.17% 1 - MV Cable 80 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 0.00% 100.00% 100.00% 100.00% 2 - LV Cable 1,362 12 May 2015 02 Sep 2015 12 May 2015 ---- 100.00% 39.79% 51.32% 69.75% 3 - Instrument Cable 2,200 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 0.00% 16.36% 16.36% 16.36% 4 - Batteries (COMMON TO TRAINS A&B) 180 03 Sep 2015 15 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 5 - F&G (COMMON TO TRAINS A&B) 160 16 Apr 2015 18 Apr 2015 16 Apr 2015 18 Apr 2015 100.00% 100.00% 100.00% 100.00% 7 - Air conditioning system (COMMON TO TRAINS A&B) 80 28 Aug 2015 03 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 1 - Inspections 640 01 Jul 2014 12 Apr 2015 01 Jul 2014 12 Apr 2015 100.00% 100.00% 100.00% 100.00% 2 - Battery room refurbishment (COMMON TO TRAINS A&B) 490 21 Jun 2015 17 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 18 - UCP 344 01 May 2015 30 May 2015 01 May 2015 30 May 2015 0.00% 100.00% 100.00% 100.00% 5 - Pre-Commissioning & Commissioning 3,580 31 Jul 2014 10 Nov 2015 31 Jul 2014 ---- 3.61% 5.26% 5.26% 5.59% 2 - Electrical and control test 20 09 May 2015 10 May 2015 09 May 2015 10 May 2015 0.00% 100.00% 100.00% 100.00% 3 - MVA Transformer activities 140 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100.00% 4 - MCC Activities 80 18 Sep 2015 23 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 6 - Fire fighting system commissioning 420 08 Oct 2015 02 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 7 - DCP Commissioning 320 17 Sep 2015 08 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 8 - UCP activities 640 21 Sep 2015 19 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 9 - Functional test compressor unit and BoP equipment 820 09 Oct 2015 11 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 10 - Motor rotating equipment 360 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 11.11% 11.11% 11.11% 1 - Main and aux lube oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33% 2 - Main and aux seal oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33% 3 - #6 gas cooler motor bump test, belt installation and running test 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 4 - #3 main & #3 stand-by Lube Oil cooler motors bump test, coupling installation and run 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 5 - #3 main & #3 stand-by Seal Oil cooler motors bump test, coupling installation and run t 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 6 - Seal oil degassing tank agitator and blower motor bump test, coupling installation and ru 60 10 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 11 - MV Motor activities 120 11 Oct 2015 13 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 12 - Alignment and Load Coupling installation 360 13 Oct 2015 16 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 13 - Unit Start-up 300 19 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% Actual % WO5A CS1A Construction Progress Status Report CONSTRUCTION PHASES & AREAS Budgeted Labour Units Start Finish Actual Start Actual Finish