PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 1 of 24 
Classes of Factors to be Considered in Infrastructure Investment Prioritization 
By Bob Prieto 
The prioritization of infrastructure investment must be focused on achieving the strategic objectives of the implementing agency or governmental unit while recognizing the broad role that infrastructure plays in serving society and supporting adjacent regional and national networks. Clear, robust objectives must be established; continuously articulated; alignment with affected stakeholders achieved; performance metrics established and continuously monitored and measured; and, corrective actions and portfolio adjustments made based on performance and changed futures. Many of these performance metrics will be associated with the factors to be considered in initial prioritization. 
The strategic objectives established for our infrastructure systems must as a minimum address the following objectives: 
 Economic – encompassing societal, agency (or governmental unit), and project considerations 
o Societal related economic considerations can include job creation; infrastructure efficiency; new opportunities created; level of quality of the system; contribution to directional desired change 
o Project level considerations focus more on the capital efficiency of the developed assets 
 Social – including stakeholder related concerns and desires; contextual and cultural appropriateness; compatibility with community goals and other social objectives. It is important to recognize that stakeholders may include non-local interests such as seen from national level NGO’s, trade unions and business interests. 
 Environmental – including both the environmental impacts associated with facility construction and operation but also the effects of longer term environmental factors including global climate change on our infrastructure facilities, systems and structures. Health, safety and security considerations may be considered in this context as well. 
 Political – infrastructure is an important political and policy tool and outcome; equity (impact and benefit distribution) 
 Sustaining Capacity and Capability – ensuring that public and user safety are sustained at acceptable levels and that operational and performance requirements are met throughout the life cycle by maintaining our infrastructure assets in a state of good repair. Emerging considerations around resilience as reflected in achievement of defined recovery timeframes represent new considerations for sustaining the capability and capacity of many infrastructure assets.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 2 of 24 
 Improving Outcomes – importantly, demonstrating continuous substantial improvement in life cycle cost to support capital efficiency and achievement of the broader set of objectives articulated; and addressing future resilience needs including those related to climate change and other man made and naturally occurring “events of scale” 
The final developed set of objectives should be distilled to the smallest set of objectives considering common attributes. This becomes particularly relevant as we are prioritizing sustaining capital investments or selecting among fundamentally similar projects. 
Prioritization Process 
With final objectives defined, agreed to and clearly articulated, we can now set out on the process of defining how we will achieve those objectives and importantly how we will prioritize our decisions. 
As shown in the following figure, we move through a four step process encompassing: 
 Establishment of top level objectives, as described previously 
 Development of a long term capital plan that encompasses a range of top level capital investment categories. This plan is an enterprise or portfolio level view and it is essential to allow more refined prioritization within the broader investment buckets likely to be defined. 
 Prioritization, based on consideration of the classes of factors described in this paper, or their equivalent. This prioritization goes hand in hand with the development of the long term capital plan. A first pass at prioritization may include limited or no constraints beyond those inherent in the prioritization factors themselves. 
 Constrained plan, placing financial or other constraints on the developed plan, narrowing the set of capital investments to be undertaken. 
Successfully meeting today and tomorrow’s infrastructure needs requires us to do not just more, but better. Our aspirational goal should be to reduce the life cycle cost of our new infrastructure systems and assets by 50%. 
Objective, fact based prioritization of infrastructure investments represents a key first step in that process.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 3 of 24 
Classes of factors 
It is clear from considering the scope of top level objectives to be considered when establishing infrastructure priorities that the number of potential factors that should be considered can be very large. 
In order to more appropriately evaluate this large number of factors it is useful to create a structure of “classes of factors” that ensures our decision processes are thorough and appropriately balanced. This paper suggests one such structure and subsequently provides some guidance on categorizing the resultant projects selected and the types of metrics appropriate at both a “portfolio level” as well as at the individual project level. 
The importance of a portfolio approach to prioritization cannot be overstated and even large scale programs must be understood to be part of this broader infrastructure asset portfolio. 
The classes of factors to be considered in infrastructure prioritization must at the most fundamental level create value for the end users, local community and society more broadly. These factors must also ensure we are making adequate progress towards achieving our stated objectives and, importantly, doing so in a capital efficient manner. Specifically, the following categorization is suggested as a way to classify and consider the factors used in prioritization of infrastructure investments: 
 Doing the right things 
 Doing enough of the right things 
 Doing right things right 
Categorization of enterprise or portfolio level investment categories will vary by infrastructure asset owner. Two potential categorizations include: 
Investment Categories (#1): 
• Maintenance 
• Productivity 
• Growth 
• Innovation 
Investment Categories (#2): 
• Security/ Resilience 
• Discretionary 
• System Enhancements 
• State of Good Repair
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 4 of 24 
Value Creation 
Time 
Doing right things right 
Doing enough of the right things 
Doing the right things 
Objectives 
Mapping Classes of Factors to Objectives 
Utilizing this system of classification for factors important to infrastructure 
prioritization we can construct a matrix of objective-factor relationships to begin 
translating these considerations to more actionable levels that can define the data 
required to be available, collected, analyzed and deployed to create value. Any 
prioritization activity undertaken must be seen to create value and at a later stage 
this value creation must be realized and confirmed for the prioritization process to 
retain continued support and stakeholder buy-in. 
Infrastructure Objective-Prioritization Factor Matrix 
Classes of Infrastructure Factors 
Strategic 
Objective 
Doing the right 
things 
Doing enough of 
the right things 
Doing right things 
right 
Economic  Economic 
opportunity 
creation 
 Prioritized plan 
 Job creation rate 
 Robust portfolio 
and project 
management 
 Quality 
improvement of 
infrastructure 
portfolio
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 5 of 24 
linked to achievement of objectives 
 Portfolio funding plan 
 Outcomes based projects that consider life cycle based costs, risks, uncertainties, financing strategies 
 PPP policy and framework in place 
capabilities 
 Efficiency improvement of infrastructure system Social 
 Infrastructure system is contextually and culturally aligned with societal needs 
 Infrastructure is compatible with community goals and other social objectives 
 Broad awareness of current and emerging infrastructure needs and risks 
 Engagement of disadvantaged and local businesses in project development 
 Defined sustainability framework 
 User support of selected infrastructure projects 
 User support of portfolio funding plan 
 Construction mitigation strategies reduce societal impact during construction 
 Level and extent of stakeholder support 
 Stakeholder acceptance of the selected infrastructure projects 
 Stakeholder acceptance of the changing infrastructure portfolio
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 6 of 24 
Environmental 
 Conformance with all applicable regulations 
 Environmental mitigation during construction 
 Defined sustainability framework 
 Enhanced environmental quality as a result of implementation of selected projects 
 Reducing contributions to global climate change and other environmental challenges Political 
 Effective public engagement programs 
 Supportive regulatory framework in place 
 Owner readiness 
 Equitable impact and benefit distribution 
 Bi-partisan support for funding plan 
 Full process transparency Sustaining Capacity and Capability 
 Effective preventative maintenance program 
 Infrastructure sustainment from a performance and quality standpoint 
 Asset management plan in place 
 Predictive maintenance program 
 Sustaining capital program including infrastructure productivity improvement 
 Improved resilience of critical infrastructure to the effects of climate change 
 Improved resilience of critical infrastructure to other natural and man-made events 
 Overall capital efficiency improved 
 Community resilience
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 7 of 24 
of scale 
 Resilience code Improving Outcomes 
 Life cycle cost based project prioritization and implementation 
 Accepted prioritization plan 
 Strengthened resilience focus on a project and portfolio basis 
 Performance based contracting utilizing life cycle performance standards 
 Continuous reduction in life cycle cost and progress towards a 50% reduction in life cycle cost by 2025 
 Reduced exposure and materialization of risks of all types 
 Overall capital efficiency improved 
The above matrix provides a starting point for ensuring that our investment priorities support not only the proper selection among hard choices but also that we are undertaking these activities at a rate that will actually move us forward in the direction we want at an acceptable rate. Key to achievement of our objectives is the need to continuously improve not only what we do but how we do it. We must do the right things right…and in an improving way. Appendices 1 through 6 further detail some of the individual elements in the developed matrix and are intended to be illustrative. 
Each of the candidate projects we undertake must contribute towards advancing us towards one or more of our objectives. They must be the right projects, done at the right rate and in the right way. It is helpful from a portfolio perspective to be able to categorize the candidate and ultimately selected projects to ensure that we are appropriately balancing our efforts across all classes of prioritization factors. A useful categorization of projects segregates them into four categories: 
 Maintenance 
 Productivity 
 Growth 
 Innovation 
Depending on our defined objectives we may select very different balanced portfolios as illustrated in the following figure. The first portfolio exhibits a focus on sustaining existing infrastructure and enhancing its productivity (50% +15% = 65%) while the second places similar aggregate emphasis (65%) on these two factors but seeks to improve the state of good repair with a much more limited focus on productivity enhancement (60% + 5% = 65%). While both portfolios seek to grow and improve
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 8 of 24 
outcomes through innovation, the second portfolio limits resources applied to growth 
projects in favor of step change improvement through innovation. 
15% 
50% 
25% 
10% 
5% 
60% 
15% 
20% 
Maintenance 
Innovation 
Growth 
Productivity 
Balanced Step Change 
Alternative Portfolios of Projects Reflect Defined Objectives and Strategy 
Projects are prioritized based on considerations shown in the prior table, and the 
assembled portfolio tested for the desired strategic portfolio balance that is desired. 
Within a given portfolio element, more refined prioritization can be used to establish 
alternatives to be considered and adopted or sequencing of a series of similar 
projects. For example, maintenance projects focused on supporting a state of good 
repair may be prioritized based on criticality to maintaining asset safety or 
functionality and performance levels. In effect this refined prioritization is just a 
narrowing of overall prioritization factors among similar asset or investment types.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 9 of 24 
This approach provides for strategy driven weighting of project mix and acts to ensure that singular objectives that are heavily weighted do not create an unbalanced infrastructure investment portfolio. The balanced portfolio may be tested for contributions to the various strategic objectives established and individual project scopes further rationalized to achieve the right balance and contributions to the various outcomes desired. Scope rationalization and a fact based basis for scope control are direct benefits of a strong factor based prioritization process for infrastructure investment. Portfolio level metrics may be cascaded down into individual projects to further assist in rationalization of infrastructure investments. 
The requirements of a good prioritization methodology are discussed in more detail in the following section. 
Requirements of a Good Prioritizing Methodology 
There are many requirements that a good prioritizing infrastructure investment methodology must satisfy. We have already seen some: 
 Establishment of specific, measurable strategic objectives that our infrastructure investments are intended to move us towards. A focus on common attributes helps make this a manageable task. 
 Categorization of the various prioritizing factors into three broad classes: 
– Doing the right things
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 10 of 24 
– Doing enough of the right things 
– Doing right things right 
 Mapping of these broad classes to the various strategic objectives to create a set of more explicit and actionable set of factors to be considered with further development illustrated in Appendices 1-6. 
Each of these considerations contributes to a strong prioritization foundation upon which a strong prioritizing methodology may be further built. This methodology must encompass: 
 Consideration of relative value and risk associated with various infrastructure investments including thresholds and constraints 
 Careful benefit tracking to ensure economic, environmental and social benefits are tangible and not double counted 
 Feedback loops that ensure that the various assumptions made at the project prioritization stage are realized and that further assumption bases for subsequent prioritization efforts are informed by the actual results obtained. Our three broad classes of factors we consider are thus informed by answering the question, “Are we getting the results we desire?” 
 Economic and financial models that support differentiation, prioritization and optimization of infrastructure investments 
 Cash flow requirements and concomitant funding and revenue modeling 
 Clear guidance on the components of capital efficiency to be included in the prioritization effort and the temporal limits of any analysis 
 Multi-factor analysis or a composite scoring system with well thought out weighting. 
The developed prioritization methodology provides a framework for identifying metrics to be tracked, changes to be monitored and ongoing impacts to the balanced portfolio. 
One of the challenges in any prioritization methodology is to recognize that the various prioritization factors may effectively be in different “currencies”. How do you prioritize infrastructure investments considering economic 
Prioritization of our infrastructure investments is critical in a financially constrained environment. We must maximize capital efficiency by ensuring that we are: 
- Doing the right things 
- Doing enough of the right things 
- Doing right things right
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 11 of 24 
returns ($), reduction in greenhouse gasses (tons of CO2 equivalent) and jobs created? 
One strategy for comprehensively assessing these impacts is to assign a monetary conversion factor or an “exchange rate” to environmental and social benefits and impacts. While greatly simplifying the analysis involved, it may be highly distortional, leading to a recommended infrastructure investment portfolio strategy that is either environmentally or socially unacceptable. 
From time to time, such summing may occur, in effect placing value on a day lost to illness, a life, or the totality of impacts from a ton of carbon. In such instances, it is essential that the respective “currency” values not be lost and that appropriate sensitivity analysis be performed to confirm that the selected “currency conversion” values are not distortional. We must remember that weighting involves value choices. 
An alternative approach would be to seek to optimize within a framework consisting of “multiple currencies,” utilizing a “multi-currency” or multi-objective optimization strategy. These strategies may also be referred to as: 
 Multi-objective programming 
 Vector optimization 
 Multi-criteria optimization 
 Multi-attribute optimization 
 Pareto optimization 
These strategies are used where tradeoffs may encompass two or more conflicting objectives. This may often be the case as we undertake a multi-stakeholder infrastructure investment prioritization effort. 
Let’s consider a prioritization effort involving only three currencies – economic, environmental and social. It is readily apparent that various environmental factors such as acres of green space lost and/or temperature rise in a local steam may not be readily summable, and the extension of this approach to consider a larger number of currencies is possible. 
Solutions to this three-currency optimization problem will fall within a set of Pareto optimal solutions which can then be subject to further analysis through the introduction of additional constraints or preferences. A solution is called a non- dominated, Pareto optimal solution (also sometimes referred to as Pareto efficient or non-inferior) if none of the “currency” values can be improved without impairment of other values. The set of Pareto optimal outcomes is called the Pareto front.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 12 of 24 
In a multi-objective optimization problem, we seek to minimize each of the “currencies.” In the case of a “currency” we seek to maximize, such as a benefit created, the minimization would be of its negative value. A key task is in identifying a sufficient number of constraints to adequately bound the optimization effort. 
Other prioritization methodologies are possible but must adequately consider the common attributes linked to our established strategic objectives; encompass all three classes of prioritization factors identified; and address any subjective bias inherent in dealing with “multi-currency” optimization as just described. 
Conclusion 
A framework for developing infrastructure investment objectives is suggested. A top level ontology of “classes of factors” recommended and a matrix of first level factors defined by considering this objective- class of factor prioritization space. The appendices further develop some of these first level factors and the intent is not to suggest that all be considered but rather represents an initial starting point for evaluating which small set of factors is most appropriate for use in prioritizing infrastructure investments. Finally, additional considerations that a strong prioritizing methodology must address are suggested and the challenges of “multi-currency” prioritization highlighted.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 13 of 24 
References: 
1. Application of Life Cycle Analysis in the Capital Assets Industry; Construction Management Association of America (CMAA); June 2013; ISBN 978-1- 938014-06-2 (eBook); ISBN 978-1-938014-07-9 (Print) 
2. Capital Efficiency: Pull All the Levers; Construction Management Association of America (CMAA); August 2014; 978-1-938014-08-6 (eBook); ISBN 978-1- 938014-09-3 (Print) 
3. Application of Life Cycle Analysis in the Capital Assets Industry Webinar; CMAA; July 17, 2014 
4. Role of a Sound Asset Management System in Life Cycle Program Management; PM World Journal; October, 2013 
5. Invest in infrastructure throughout its life cycle; Interview with Bob Prieto; PWC; September 10, 2013 
6. Impediments for Implementing a Sound Asset Management System; Center for Advanced Infrastructure and Transportation; State of Good Repair Summit; March 27, 2013 
7. Life Cycle Analysis – Interview with Fluor Senior VP Bob Prieto; AEC Business; August 19, 2013; http://aec-business.com/life-cycle-analysis-bob- prieto-fluor/ 
8. Addressing Project Capital Efficiency through a Business Basis of Design; PM World Journal; April 2014 
9. Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011 
10. Project Selection in Large Engineering Construction Programs; PM World Today; June 2011; http://www.pmforum.org/library/papers/2011/PDFs/june/FP-PRIETO.pdf
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 14 of 24 
Appendix 1 
Factors Related To 
Continuous Reduction in Life Cycle Cost and Progress towards A 50% Reduction in Life Cycle Cost By 2025 
 Revenue 
o First Revenue Date 
o Plant Availability Factor and Ramp-Up Period and Rate 
o Asset Life (Duration from First Revenue during analysis period) 
o Scheduled Shutdowns (Regulatory, Seasonal, Maintenance) 
o Supply/Demand Balance Normalized Price(Market Size; Competitor Actions) 
o Capacity or Throughput 
o Byproduct Value Captured 
o Tax Credits Realized 
o Inflation Adjustments to Normalized Pricing (Inflation; Currency Exchange Rates) 
 Indirect Asset Costs 
o Land use 
 Land use impacts include: Land use (the plant site) Emissions to air Emissions to water Emissions to soils. Land use change Mineral and fossil fuel use Land transformation Land occupation Soil erosion, compaction and sealing Often ignored in LCA but taking on increasing importance. 
 ISO 14040 – 14043, largely developed from industrial perspective and do not mention land use as an impact category 
 Land use considers following factors: Concurrent availability –site is available on some basis for use by other facilities. Important when evaluating large program or asset portfolio design. May be either: Constrained or limited Unconstrained or unlimited (except with respect to limiting attributes of the site independent of the facility’s presence at the site) Concurrent unavailability – the site is not available for other current use due to the facility’s presence at the site.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 15 of 24 
Loss of optionality – site use, post facility closure, is limited because of the prior presence of the facility Permanent unavailability – use of the site, post closure, is not reasonably possible 
o Tax Regime 
 Taxable 
 Tax Credit 
 Tax Exempt 
o Financing structures 
 Common factors 
 Financial factors – hyper inflation, deflation, uninsured portion of disasters (natural, manmade, or Natech) 
 Environmental factors – climate change 
 Social factors – change in user behavior, change in surrounding community behavior with respect to the facility; compatibility with community goals and other social objectives 
 Correlated risks 
 Financing structures considered in a life cycle analysis influenced by many factors including: asset characterization governing financial metrics (ROE, ROI, IRR, ROA) asset lifetimes before refurbishment or replacement refinance periods construction and operations cash flows residual value of asset 
 Externalities 
o Intangibles such as brand value 
o Complexity 
o Assumption migration associated with longer time frames (dynamic risks) 
o Stakeholder trust 
o Susceptibility to “Black Swan” type risks 
o “Strategic speed” 
o Regulatory taxes and subsidies 
o Potential “Black Swan” factors to be considered in life cycle analysis include: 
 Financial factors – hyper inflation, deflation, uninsured portion of disasters (natural, manmade, or Natech) 
 Environmental factors – climate change 
 Social factors – change in user behavior, change in surrounding community behavior with respect to the facility 
 Correlated risks 
 Planning and Permitting
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 16 of 24 
o Impact of Permitting on Life Cycle Analysis: 
 Reduced revenue 
 Higher risk weighted cost of capital –investors may seek higher returns as they wait patiently and with a higher degree of uncertainty for the facility to obtain necessary approvals. Similarly debt costs may be higher especially in instances where project funding is utilized. 
 Higher permitting costs 
 Higher environmental mitigation or enhancement costs 
 Increased project escalation costs 
 Design 
o Factors Typically Considered in a Capital Asset Life Cycle Analysis 
 Labor Costs -professional services 
 Benefits from standardization /design reuse 
 Premium costs incurred because of schedule 
 Cost of Time (design duration/phasing) 
 Value of Risk (technology or other first of a kind risks; labor availability risk) 
 Design estimate uncertainties (estimating based; management model driven; rework based on late inputs or owner driven changes) 
 Consideration given to procurement and supply chain strategies (relates to potential for design rework or impacts on procurement) 
 Degree constructability considerations have been incorporated into design activities (influences design and construction management costs with the prospect of reduced construction durations and costs) 
 Life cycle and sustainability focus and provision in cost and schedule for more aggressive engagement of O&M managers, staff and key suppliers 
 Procurement & Construction 
 Operations 
 Maintenance 
o Reliability 
o Availability 
o Capacity Factor
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 17 of 24 
Appendix 2 
Factors Related to 
PPP Policy 
 Policy framework (this is essential in any regulatory framework selected) 
 Toll rate level and structure 
 Concession payments (or government subsidy or facilities or services in kind) 
 Penalties and fines for non compliance 
 Concession period and its linkage to rate of return 
 Timing of investment and reinvestment obligations 
 Quality of service obligations 
 Investment level obligations 
 Depreciation and amortization rules (tax and accounting policy issues) 
 Forms and timing of restructurings allowed 
 Nature and duration of any exclusivity or restrictions on competing facilities 
 “Social” composition of user base (unintended social consequences) 
 Idiosyncrasies / uncertainty in forecasting models 
 Policy/rights retained and related to sequestration, forfeiture, withholding or suspension of guarantees, liability allocation and third party liability
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 18 of 24 
Appendix 3 
Factors Related to 
A Defined Sustainability Framework 
 Major elements of sustainability are a fundamental requirement 
 Focus goes beyond first cost to a comprehensive life cycle perspective 
 Set of balanced solutions exist. 
 Management and execution approach based on systems approach 
 Sustainability framework at all program and project phases 
 Procurement of local goods 
o Local construction materials & tools adds income in immediate area & 
contributes to local tax base through sales tax 
 Creation of a local service base to support the facility during operations and 
maintenance phases. 
 Anti-corruption measures 
 Tied closely with social opportunities and benefits 
 Social metrics considered 
Social Metrics 
Diversity • Existence of equal opportunity policies or programs 
• Percentage of senior executives who are women 
• Percentage of staff who are members of visible minorities 
• Percentage of staff with disabilities 
Industrial Relations • Percentage of employees represented by independent trade 
union organizations or other bona fide employee 
representatives 
• Percentage of employees covered by collective bargaining 
agreements 
• Number of grievances from employees. 
Child Labor • Whether contractors are screened (or percentage screened) 
for use of child labor. 
Community • Earnings donated to the community; 
• Use of local contractors and suppliers. 
• Involvement in projects with value to the greater community
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 19 of 24 
Appendix 4 
Factors Related to 
Owner Readiness 
 Program demand related forecasts 
 Factors related to program revenues 
 Equitable impact and benefit distribution 
 Owner’s financial condition 
 Resources available to the program 
 Competing programs and associated resource requirements and timing 
 Assumed changes to law, regulation or policy impacting owner and program and anticipated timing 
 External environment 
 Operating strategy and required lifecycle performance 
 Owner’s risk posture and philosophy 
 Business model, scenarios and relationship to program 
 Prerequisites for external approvals 
 External approval requirements, timing and likelihood 
 Prerequisites for owner’s executive approvals and linkage to a formal stage gate process including clarity and comprehensiveness of stage gate requirements and processes; stage gate approvals, authorities granted, resource commitments and constraints; approvals matrix 
 External prerequisites linked to stage gates including regulatory approvals required, process clarity and timing including safety case requirements; and process for property acquisition 
 The owner’s organization must also demonstrate readiness to: 
o Implement the stage gate process, consistent with the owner’s own requirements and consistent with a program’s demands. Approval time frames, gate expectations and nature of obtained approvals at each gate must tie clearly into program execution strategies. 
o Support management of demand for capital 
o Drive capital efficiency in projects as they advance trough the stage gate process. Among various elements of owner readiness to be considered would be the early focus on construction realities, constraints and opportunities that may be found in appropriate means and methods selection. 
o Enhance project execution by providing a disciplined project development framework 
o Enforce standards on management evaluation of alternatives including consideration of life cycle cost and performance evaluations. Significant life cycle performance benefits can accrue from strong incorporation of O&M considerations in the earliest stages of a program but many
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 20 of 24 
programs suffer from later stage changes because of lack of an early focus in this regard. 
o Influence acceptable risk frameworks commensurate with investments being undertaken and the risks program will face 
o Provide independent validation and verification 
 Capability of owner’s technology platforms to support the program are established and functioning at a level consistent with the program’s needs 
 Physical and cyber security requirements of owner and external organizations with requisite authorities are consistent with the program’s risk profile and the sensitivity of data and communications involved 
 Required reports by owner on program progress can be efficiently provided to external stakeholders and that there is a plan to do so. 
 Internal audit structure and controls are in place and associated budgeting and staffing requirements are recognized 
 Inspector general role, authorities and resources are clearly defined with respect to program role and a plan exists to mobilize these resources in support of the program
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 21 of 24 
Appendix 5 
Factors Related to 
Asset Management Plans 
 A cradle to grave life-cycle approach. 
 Developing and implementing cost-effective strategies recognizing the long-term purpose and nature of these assets 
 Defining, establishing and providing for a defined nature and level of service 
 Monitoring, maintaining and where possible enhancing asset performance. 
 Anticipating, mitigating and managing risks associated with asset degradation and failures 
 Implementing asset management to achieve these objectives on a financial, environmental and societal basis. 
 Sustaining and where possible enhancing system level characteristics of an asset such as resiliency, flexibility and future optionality. 
 Deploying the limited financial, physical and human resources of the asset owner in an efficient, effective and sustainable manner. It is about making informed tradeoffs as part of our decision making process. 
 Continuously improving asset management practices. 
 Define the minimum level of detail for an asset (what assets to track) 
 Establish a uniform asset enumeration scheme (asset organization) 
 Identify existing assets and related attributes (asset data) 
 Identify the probability and consequence of failure of an asset (asset risk) 
 Establish the level of asset management performed (asset management strategy) 
 Establish short-interval portions of asset plans 
 Establish long-interval portions of asset plans 
 Develop procedures to update asset plans 
 Asset Development including achieving these objectives: 
o Develop a systematic approach to creating assets 
o Consider constructability, maintainability, and operability in the design process 
o Require that enumeration schemes be followed by designers and contractors 
o Maximize contractor contribution to asset development 
o Prepare asset plans coincident with asset delivery 
 Asset Operations and Maintenance 
o Defining required preventative maintenance activities. 
o Preventative maintenance scheduling 
o Performing defined preventative maintenance activities at the prescribed intervals. 
o Using indirect condition assessment where cost-effective. 
o Performing corrective maintenance on a timely basis. 
o Management of maintenance using a balanced approach between preventative and corrective maintenance 
o Recording maintenance costs on an activity basis, by asset. 
o Management of operational methods to minimize the combined costs of O&M.
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 22 of 24 
o Key objectives of asset O&M: 
 Proactive safety management 
 Track asset failures consistently 
 Prioritize work order backlog by risk 
 Asset Condition Monitoring has 3 goals: 
o Define condition monitoring methods 
o Define condition monitoring program 
o Integrate condition monitoring with other management and work processes
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 23 of 24 
Appendix 6 
Factors Related to 
Reduced Exposure and Materialization of Risks of All Types 
 Labor Availability & Cost 
 Labor Productivity 
 Labor Impacts on Program Location 
 Material Availability & Cost 
 Long Lead Equipment 
 Construction Equipment 
 Logistical Costs 
 Life Cycle Costs 
 Relocation or Reconfiguration Costs 
 Industry Creation 
 Balance Sheet 
 Risk & Insurance Costs 
 Procurement and contractual frameworks 
 Craft capacity building 
 Management capacity building 
 Global leading best practices 
 Societal supporting facilities 
 Managing uncontrollable growth 
 Performance management 
 Waste streams 
 Energy 
 Water 
 Recyclable/reusable materials
PM World Journal Classes of Factors to be Considered in Infrastructure 
Vol. III, Issue X – October 2014 Investment Prioritization 
www.pmworldjournal.net Featured Paper by Bob Prieto 
© 2014 Bob Prieto www.pmworldlibrary.net Page 24 of 24 
About the Author 
Bob Prieto 
Senior Vice President 
Fluor 
Princeton, NJ, USA 
Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He focuses on the development and delivery of large, complex projects worldwide. Bob consults with owners of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry” and “Application of Life Cycle Analysis in the Capital Assets Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 500 other papers and presentations. 
Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.

More Related Content

What's hot

The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...Dr Rupert Booth
 
Howtocatalyzeprivatemoneyintoinfrastructureinvestments
HowtocatalyzeprivatemoneyintoinfrastructureinvestmentsHowtocatalyzeprivatemoneyintoinfrastructureinvestments
Howtocatalyzeprivatemoneyintoinfrastructureinvestmentsussal
 
Presentation on project appraisal
Presentation on project appraisalPresentation on project appraisal
Presentation on project appraisaljeni kayastha
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal, sksbatish
 
Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami Mikhail
 
Feasibility matrix
Feasibility matrixFeasibility matrix
Feasibility matrixIIUM
 
Policy frameworks and municipal effectiveness
Policy frameworks and municipal effectivenessPolicy frameworks and municipal effectiveness
Policy frameworks and municipal effectivenessJohn Leonardo
 
Project Management- Unit II
Project Management- Unit IIProject Management- Unit II
Project Management- Unit IILamay Sabir
 
Continuous Alignment
Continuous AlignmentContinuous Alignment
Continuous AlignmentBob Prieto
 
Projects types
Projects types Projects types
Projects types Ahmed Sakr
 
Planning concept oiudb
Planning concept oiudbPlanning concept oiudb
Planning concept oiudbAboma Amsalu
 
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)NewClimate Institute
 
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET Journal
 
Plenary Summary TRACK 1: TDA, SAP, and Participatory Process Best Practices ...
Plenary Summary TRACK 1:  TDA, SAP, and Participatory Process Best Practices ...Plenary Summary TRACK 1:  TDA, SAP, and Participatory Process Best Practices ...
Plenary Summary TRACK 1: TDA, SAP, and Participatory Process Best Practices ...Iwl Pcu
 
Project appraisal
Project appraisalProject appraisal
Project appraisalGotham Ram
 

What's hot (20)

The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...The Role of the Business Case in Public Investment Management and Project Por...
The Role of the Business Case in Public Investment Management and Project Por...
 
Howtocatalyzeprivatemoneyintoinfrastructureinvestments
HowtocatalyzeprivatemoneyintoinfrastructureinvestmentsHowtocatalyzeprivatemoneyintoinfrastructureinvestments
Howtocatalyzeprivatemoneyintoinfrastructureinvestments
 
Presentation on project appraisal
Presentation on project appraisalPresentation on project appraisal
Presentation on project appraisal
 
Project formulation (1)
Project formulation (1)Project formulation (1)
Project formulation (1)
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal,
 
Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015
 
Feasibility matrix
Feasibility matrixFeasibility matrix
Feasibility matrix
 
Policy frameworks and municipal effectiveness
Policy frameworks and municipal effectivenessPolicy frameworks and municipal effectiveness
Policy frameworks and municipal effectiveness
 
Project Management- Unit II
Project Management- Unit IIProject Management- Unit II
Project Management- Unit II
 
Continuous Alignment
Continuous AlignmentContinuous Alignment
Continuous Alignment
 
Gov4 ozyol arzu
Gov4   ozyol arzuGov4   ozyol arzu
Gov4 ozyol arzu
 
Projects types
Projects types Projects types
Projects types
 
Planning concept oiudb
Planning concept oiudbPlanning concept oiudb
Planning concept oiudb
 
Unit Iii
Unit   IiiUnit   Iii
Unit Iii
 
feasibility study
 feasibility study feasibility study
feasibility study
 
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)
Overviews on the implementation of NDCs on a sectoral level (Innovate4Climate)
 
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
 
Plenary Summary TRACK 1: TDA, SAP, and Participatory Process Best Practices ...
Plenary Summary TRACK 1:  TDA, SAP, and Participatory Process Best Practices ...Plenary Summary TRACK 1:  TDA, SAP, and Participatory Process Best Practices ...
Plenary Summary TRACK 1: TDA, SAP, and Participatory Process Best Practices ...
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
Key points
Key pointsKey points
Key points
 

Viewers also liked

Better Biz Dev – Music Startup Academy Denver - October 8, 2015
Better Biz Dev – Music Startup Academy Denver - October 8, 2015Better Biz Dev – Music Startup Academy Denver - October 8, 2015
Better Biz Dev – Music Startup Academy Denver - October 8, 2015Shawn Yeager
 
205180 cm with jde
205180 cm with jde205180 cm with jde
205180 cm with jdep6academy
 
Santa Khinche sabki taang
Santa Khinche sabki taang Santa Khinche sabki taang
Santa Khinche sabki taang sadaambalvi
 
Grm 201 project
Grm 201 projectGrm 201 project
Grm 201 projectnmjameson
 
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"PerformanceIN
 
Avaya cc control manager 6.2 brochure
Avaya cc control manager 6.2   brochureAvaya cc control manager 6.2   brochure
Avaya cc control manager 6.2 brochureraulhmata
 
Some real ghost picture
Some real ghost pictureSome real ghost picture
Some real ghost pictureNimil Jain
 
1.vitamines and coenzymes 31.03.2071
1.vitamines and coenzymes 31.03.20711.vitamines and coenzymes 31.03.2071
1.vitamines and coenzymes 31.03.2071RajDip Basnet
 
A V I D Juicy Ultimate Brake Bleeding
A V I D Juicy Ultimate Brake BleedingA V I D Juicy Ultimate Brake Bleeding
A V I D Juicy Ultimate Brake Bleedingradicallights
 
Prescrition co-owners- pdf
Prescrition   co-owners- pdfPrescrition   co-owners- pdf
Prescrition co-owners- pdfsahib rox
 
Medicaid vs. Medicare in Oregon
Medicaid vs. Medicare in OregonMedicaid vs. Medicare in Oregon
Medicaid vs. Medicare in OregonRichard Schneider
 
Product Development Communications Executive Pat Scherschel 2011
Product Development Communications Executive Pat Scherschel 2011Product Development Communications Executive Pat Scherschel 2011
Product Development Communications Executive Pat Scherschel 2011patriciaindy2011
 

Viewers also liked (20)

Better Biz Dev – Music Startup Academy Denver - October 8, 2015
Better Biz Dev – Music Startup Academy Denver - October 8, 2015Better Biz Dev – Music Startup Academy Denver - October 8, 2015
Better Biz Dev – Music Startup Academy Denver - October 8, 2015
 
Lift hero class1_presentation
Lift hero class1_presentationLift hero class1_presentation
Lift hero class1_presentation
 
NOVEL 2
NOVEL 2NOVEL 2
NOVEL 2
 
Gps4b
Gps4bGps4b
Gps4b
 
Spirax saco
Spirax sacoSpirax saco
Spirax saco
 
205180 cm with jde
205180 cm with jde205180 cm with jde
205180 cm with jde
 
Santa Khinche sabki taang
Santa Khinche sabki taang Santa Khinche sabki taang
Santa Khinche sabki taang
 
Grm 201 project
Grm 201 projectGrm 201 project
Grm 201 project
 
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
 
Avaya cc control manager 6.2 brochure
Avaya cc control manager 6.2   brochureAvaya cc control manager 6.2   brochure
Avaya cc control manager 6.2 brochure
 
Some real ghost picture
Some real ghost pictureSome real ghost picture
Some real ghost picture
 
Amit PPT
Amit PPTAmit PPT
Amit PPT
 
1.vitamines and coenzymes 31.03.2071
1.vitamines and coenzymes 31.03.20711.vitamines and coenzymes 31.03.2071
1.vitamines and coenzymes 31.03.2071
 
Pppp
PpppPppp
Pppp
 
A V I D Juicy Ultimate Brake Bleeding
A V I D Juicy Ultimate Brake BleedingA V I D Juicy Ultimate Brake Bleeding
A V I D Juicy Ultimate Brake Bleeding
 
Prescrition co-owners- pdf
Prescrition   co-owners- pdfPrescrition   co-owners- pdf
Prescrition co-owners- pdf
 
Medicaid vs. Medicare in Oregon
Medicaid vs. Medicare in OregonMedicaid vs. Medicare in Oregon
Medicaid vs. Medicare in Oregon
 
Planejamento pms
Planejamento pmsPlanejamento pms
Planejamento pms
 
VW Santana Vista - Brochure
VW Santana Vista - BrochureVW Santana Vista - Brochure
VW Santana Vista - Brochure
 
Product Development Communications Executive Pat Scherschel 2011
Product Development Communications Executive Pat Scherschel 2011Product Development Communications Executive Pat Scherschel 2011
Product Development Communications Executive Pat Scherschel 2011
 

Similar to Classes of Factors to be Considered in Infrastructure Investment Prioritization

Challenges of infrastructure and long term investment
Challenges of infrastructure and long term investmentChallenges of infrastructure and long term investment
Challenges of infrastructure and long term investmentBob Prieto
 
Opportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionOpportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
L2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxL2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxbettymakuve1
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...A Makwana
 
SKYMT|Analyzing and investing in global infrastructure projects
SKYMT|Analyzing and investing in global infrastructure projectsSKYMT|Analyzing and investing in global infrastructure projects
SKYMT|Analyzing and investing in global infrastructure projectsDestinyNixon
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio managementGlen Alleman
 
Monitioring and evaluation
Monitioring and  evaluationMonitioring and  evaluation
Monitioring and evaluationzahidss2
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalAmandaBvera
 
Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...NAP Global Network
 
Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALChristopher Matthews
 
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxRunning head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxcowinhelen
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfssuser52d5d3
 
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxPUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxkipkorirkoech5
 
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...Ricardo Viana Vargas
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process Bob Prieto
 
The Role of Infrastructure Projects in P.pdf
The Role of Infrastructure Projects in P.pdfThe Role of Infrastructure Projects in P.pdf
The Role of Infrastructure Projects in P.pdfPL Global
 
Feasibility Report seminar
Feasibility Report seminarFeasibility Report seminar
Feasibility Report seminarPujaBrahma
 

Similar to Classes of Factors to be Considered in Infrastructure Investment Prioritization (20)

Challenges of infrastructure and long term investment
Challenges of infrastructure and long term investmentChallenges of infrastructure and long term investment
Challenges of infrastructure and long term investment
 
Opportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second editionOpportunity analysis under strategic program management second edition
Opportunity analysis under strategic program management second edition
 
Project Development
Project Development Project Development
Project Development
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
L2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxL2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptx
 
2.pptx
2.pptx2.pptx
2.pptx
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
 
SKYMT|Analyzing and investing in global infrastructure projects
SKYMT|Analyzing and investing in global infrastructure projectsSKYMT|Analyzing and investing in global infrastructure projects
SKYMT|Analyzing and investing in global infrastructure projects
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Monitioring and evaluation
Monitioring and  evaluationMonitioring and  evaluation
Monitioring and evaluation
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 
Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...Developing projects and programs in a strategic manner: Adaptation Investment...
Developing projects and programs in a strategic manner: Adaptation Investment...
 
Capital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINALCapital and infrastructure solution brochure Single FINAL
Capital and infrastructure solution brochure Single FINAL
 
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxRunning head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdf
 
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptxPUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
PUBLIC PRIVATE PARTNERSHIP MANAGEMENT-Module.pptx
 
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
The Role of Infrastructure Projects in P.pdf
The Role of Infrastructure Projects in P.pdfThe Role of Infrastructure Projects in P.pdf
The Role of Infrastructure Projects in P.pdf
 
Feasibility Report seminar
Feasibility Report seminarFeasibility Report seminar
Feasibility Report seminar
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6
 
Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 5
 
Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 4
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

Classes of Factors to be Considered in Infrastructure Investment Prioritization

  • 1. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 1 of 24 Classes of Factors to be Considered in Infrastructure Investment Prioritization By Bob Prieto The prioritization of infrastructure investment must be focused on achieving the strategic objectives of the implementing agency or governmental unit while recognizing the broad role that infrastructure plays in serving society and supporting adjacent regional and national networks. Clear, robust objectives must be established; continuously articulated; alignment with affected stakeholders achieved; performance metrics established and continuously monitored and measured; and, corrective actions and portfolio adjustments made based on performance and changed futures. Many of these performance metrics will be associated with the factors to be considered in initial prioritization. The strategic objectives established for our infrastructure systems must as a minimum address the following objectives:  Economic – encompassing societal, agency (or governmental unit), and project considerations o Societal related economic considerations can include job creation; infrastructure efficiency; new opportunities created; level of quality of the system; contribution to directional desired change o Project level considerations focus more on the capital efficiency of the developed assets  Social – including stakeholder related concerns and desires; contextual and cultural appropriateness; compatibility with community goals and other social objectives. It is important to recognize that stakeholders may include non-local interests such as seen from national level NGO’s, trade unions and business interests.  Environmental – including both the environmental impacts associated with facility construction and operation but also the effects of longer term environmental factors including global climate change on our infrastructure facilities, systems and structures. Health, safety and security considerations may be considered in this context as well.  Political – infrastructure is an important political and policy tool and outcome; equity (impact and benefit distribution)  Sustaining Capacity and Capability – ensuring that public and user safety are sustained at acceptable levels and that operational and performance requirements are met throughout the life cycle by maintaining our infrastructure assets in a state of good repair. Emerging considerations around resilience as reflected in achievement of defined recovery timeframes represent new considerations for sustaining the capability and capacity of many infrastructure assets.
  • 2. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 2 of 24  Improving Outcomes – importantly, demonstrating continuous substantial improvement in life cycle cost to support capital efficiency and achievement of the broader set of objectives articulated; and addressing future resilience needs including those related to climate change and other man made and naturally occurring “events of scale” The final developed set of objectives should be distilled to the smallest set of objectives considering common attributes. This becomes particularly relevant as we are prioritizing sustaining capital investments or selecting among fundamentally similar projects. Prioritization Process With final objectives defined, agreed to and clearly articulated, we can now set out on the process of defining how we will achieve those objectives and importantly how we will prioritize our decisions. As shown in the following figure, we move through a four step process encompassing:  Establishment of top level objectives, as described previously  Development of a long term capital plan that encompasses a range of top level capital investment categories. This plan is an enterprise or portfolio level view and it is essential to allow more refined prioritization within the broader investment buckets likely to be defined.  Prioritization, based on consideration of the classes of factors described in this paper, or their equivalent. This prioritization goes hand in hand with the development of the long term capital plan. A first pass at prioritization may include limited or no constraints beyond those inherent in the prioritization factors themselves.  Constrained plan, placing financial or other constraints on the developed plan, narrowing the set of capital investments to be undertaken. Successfully meeting today and tomorrow’s infrastructure needs requires us to do not just more, but better. Our aspirational goal should be to reduce the life cycle cost of our new infrastructure systems and assets by 50%. Objective, fact based prioritization of infrastructure investments represents a key first step in that process.
  • 3. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 3 of 24 Classes of factors It is clear from considering the scope of top level objectives to be considered when establishing infrastructure priorities that the number of potential factors that should be considered can be very large. In order to more appropriately evaluate this large number of factors it is useful to create a structure of “classes of factors” that ensures our decision processes are thorough and appropriately balanced. This paper suggests one such structure and subsequently provides some guidance on categorizing the resultant projects selected and the types of metrics appropriate at both a “portfolio level” as well as at the individual project level. The importance of a portfolio approach to prioritization cannot be overstated and even large scale programs must be understood to be part of this broader infrastructure asset portfolio. The classes of factors to be considered in infrastructure prioritization must at the most fundamental level create value for the end users, local community and society more broadly. These factors must also ensure we are making adequate progress towards achieving our stated objectives and, importantly, doing so in a capital efficient manner. Specifically, the following categorization is suggested as a way to classify and consider the factors used in prioritization of infrastructure investments:  Doing the right things  Doing enough of the right things  Doing right things right Categorization of enterprise or portfolio level investment categories will vary by infrastructure asset owner. Two potential categorizations include: Investment Categories (#1): • Maintenance • Productivity • Growth • Innovation Investment Categories (#2): • Security/ Resilience • Discretionary • System Enhancements • State of Good Repair
  • 4. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 4 of 24 Value Creation Time Doing right things right Doing enough of the right things Doing the right things Objectives Mapping Classes of Factors to Objectives Utilizing this system of classification for factors important to infrastructure prioritization we can construct a matrix of objective-factor relationships to begin translating these considerations to more actionable levels that can define the data required to be available, collected, analyzed and deployed to create value. Any prioritization activity undertaken must be seen to create value and at a later stage this value creation must be realized and confirmed for the prioritization process to retain continued support and stakeholder buy-in. Infrastructure Objective-Prioritization Factor Matrix Classes of Infrastructure Factors Strategic Objective Doing the right things Doing enough of the right things Doing right things right Economic  Economic opportunity creation  Prioritized plan  Job creation rate  Robust portfolio and project management  Quality improvement of infrastructure portfolio
  • 5. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 5 of 24 linked to achievement of objectives  Portfolio funding plan  Outcomes based projects that consider life cycle based costs, risks, uncertainties, financing strategies  PPP policy and framework in place capabilities  Efficiency improvement of infrastructure system Social  Infrastructure system is contextually and culturally aligned with societal needs  Infrastructure is compatible with community goals and other social objectives  Broad awareness of current and emerging infrastructure needs and risks  Engagement of disadvantaged and local businesses in project development  Defined sustainability framework  User support of selected infrastructure projects  User support of portfolio funding plan  Construction mitigation strategies reduce societal impact during construction  Level and extent of stakeholder support  Stakeholder acceptance of the selected infrastructure projects  Stakeholder acceptance of the changing infrastructure portfolio
  • 6. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 6 of 24 Environmental  Conformance with all applicable regulations  Environmental mitigation during construction  Defined sustainability framework  Enhanced environmental quality as a result of implementation of selected projects  Reducing contributions to global climate change and other environmental challenges Political  Effective public engagement programs  Supportive regulatory framework in place  Owner readiness  Equitable impact and benefit distribution  Bi-partisan support for funding plan  Full process transparency Sustaining Capacity and Capability  Effective preventative maintenance program  Infrastructure sustainment from a performance and quality standpoint  Asset management plan in place  Predictive maintenance program  Sustaining capital program including infrastructure productivity improvement  Improved resilience of critical infrastructure to the effects of climate change  Improved resilience of critical infrastructure to other natural and man-made events  Overall capital efficiency improved  Community resilience
  • 7. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 7 of 24 of scale  Resilience code Improving Outcomes  Life cycle cost based project prioritization and implementation  Accepted prioritization plan  Strengthened resilience focus on a project and portfolio basis  Performance based contracting utilizing life cycle performance standards  Continuous reduction in life cycle cost and progress towards a 50% reduction in life cycle cost by 2025  Reduced exposure and materialization of risks of all types  Overall capital efficiency improved The above matrix provides a starting point for ensuring that our investment priorities support not only the proper selection among hard choices but also that we are undertaking these activities at a rate that will actually move us forward in the direction we want at an acceptable rate. Key to achievement of our objectives is the need to continuously improve not only what we do but how we do it. We must do the right things right…and in an improving way. Appendices 1 through 6 further detail some of the individual elements in the developed matrix and are intended to be illustrative. Each of the candidate projects we undertake must contribute towards advancing us towards one or more of our objectives. They must be the right projects, done at the right rate and in the right way. It is helpful from a portfolio perspective to be able to categorize the candidate and ultimately selected projects to ensure that we are appropriately balancing our efforts across all classes of prioritization factors. A useful categorization of projects segregates them into four categories:  Maintenance  Productivity  Growth  Innovation Depending on our defined objectives we may select very different balanced portfolios as illustrated in the following figure. The first portfolio exhibits a focus on sustaining existing infrastructure and enhancing its productivity (50% +15% = 65%) while the second places similar aggregate emphasis (65%) on these two factors but seeks to improve the state of good repair with a much more limited focus on productivity enhancement (60% + 5% = 65%). While both portfolios seek to grow and improve
  • 8. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 8 of 24 outcomes through innovation, the second portfolio limits resources applied to growth projects in favor of step change improvement through innovation. 15% 50% 25% 10% 5% 60% 15% 20% Maintenance Innovation Growth Productivity Balanced Step Change Alternative Portfolios of Projects Reflect Defined Objectives and Strategy Projects are prioritized based on considerations shown in the prior table, and the assembled portfolio tested for the desired strategic portfolio balance that is desired. Within a given portfolio element, more refined prioritization can be used to establish alternatives to be considered and adopted or sequencing of a series of similar projects. For example, maintenance projects focused on supporting a state of good repair may be prioritized based on criticality to maintaining asset safety or functionality and performance levels. In effect this refined prioritization is just a narrowing of overall prioritization factors among similar asset or investment types.
  • 9. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 9 of 24 This approach provides for strategy driven weighting of project mix and acts to ensure that singular objectives that are heavily weighted do not create an unbalanced infrastructure investment portfolio. The balanced portfolio may be tested for contributions to the various strategic objectives established and individual project scopes further rationalized to achieve the right balance and contributions to the various outcomes desired. Scope rationalization and a fact based basis for scope control are direct benefits of a strong factor based prioritization process for infrastructure investment. Portfolio level metrics may be cascaded down into individual projects to further assist in rationalization of infrastructure investments. The requirements of a good prioritization methodology are discussed in more detail in the following section. Requirements of a Good Prioritizing Methodology There are many requirements that a good prioritizing infrastructure investment methodology must satisfy. We have already seen some:  Establishment of specific, measurable strategic objectives that our infrastructure investments are intended to move us towards. A focus on common attributes helps make this a manageable task.  Categorization of the various prioritizing factors into three broad classes: – Doing the right things
  • 10. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 10 of 24 – Doing enough of the right things – Doing right things right  Mapping of these broad classes to the various strategic objectives to create a set of more explicit and actionable set of factors to be considered with further development illustrated in Appendices 1-6. Each of these considerations contributes to a strong prioritization foundation upon which a strong prioritizing methodology may be further built. This methodology must encompass:  Consideration of relative value and risk associated with various infrastructure investments including thresholds and constraints  Careful benefit tracking to ensure economic, environmental and social benefits are tangible and not double counted  Feedback loops that ensure that the various assumptions made at the project prioritization stage are realized and that further assumption bases for subsequent prioritization efforts are informed by the actual results obtained. Our three broad classes of factors we consider are thus informed by answering the question, “Are we getting the results we desire?”  Economic and financial models that support differentiation, prioritization and optimization of infrastructure investments  Cash flow requirements and concomitant funding and revenue modeling  Clear guidance on the components of capital efficiency to be included in the prioritization effort and the temporal limits of any analysis  Multi-factor analysis or a composite scoring system with well thought out weighting. The developed prioritization methodology provides a framework for identifying metrics to be tracked, changes to be monitored and ongoing impacts to the balanced portfolio. One of the challenges in any prioritization methodology is to recognize that the various prioritization factors may effectively be in different “currencies”. How do you prioritize infrastructure investments considering economic Prioritization of our infrastructure investments is critical in a financially constrained environment. We must maximize capital efficiency by ensuring that we are: - Doing the right things - Doing enough of the right things - Doing right things right
  • 11. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 11 of 24 returns ($), reduction in greenhouse gasses (tons of CO2 equivalent) and jobs created? One strategy for comprehensively assessing these impacts is to assign a monetary conversion factor or an “exchange rate” to environmental and social benefits and impacts. While greatly simplifying the analysis involved, it may be highly distortional, leading to a recommended infrastructure investment portfolio strategy that is either environmentally or socially unacceptable. From time to time, such summing may occur, in effect placing value on a day lost to illness, a life, or the totality of impacts from a ton of carbon. In such instances, it is essential that the respective “currency” values not be lost and that appropriate sensitivity analysis be performed to confirm that the selected “currency conversion” values are not distortional. We must remember that weighting involves value choices. An alternative approach would be to seek to optimize within a framework consisting of “multiple currencies,” utilizing a “multi-currency” or multi-objective optimization strategy. These strategies may also be referred to as:  Multi-objective programming  Vector optimization  Multi-criteria optimization  Multi-attribute optimization  Pareto optimization These strategies are used where tradeoffs may encompass two or more conflicting objectives. This may often be the case as we undertake a multi-stakeholder infrastructure investment prioritization effort. Let’s consider a prioritization effort involving only three currencies – economic, environmental and social. It is readily apparent that various environmental factors such as acres of green space lost and/or temperature rise in a local steam may not be readily summable, and the extension of this approach to consider a larger number of currencies is possible. Solutions to this three-currency optimization problem will fall within a set of Pareto optimal solutions which can then be subject to further analysis through the introduction of additional constraints or preferences. A solution is called a non- dominated, Pareto optimal solution (also sometimes referred to as Pareto efficient or non-inferior) if none of the “currency” values can be improved without impairment of other values. The set of Pareto optimal outcomes is called the Pareto front.
  • 12. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 12 of 24 In a multi-objective optimization problem, we seek to minimize each of the “currencies.” In the case of a “currency” we seek to maximize, such as a benefit created, the minimization would be of its negative value. A key task is in identifying a sufficient number of constraints to adequately bound the optimization effort. Other prioritization methodologies are possible but must adequately consider the common attributes linked to our established strategic objectives; encompass all three classes of prioritization factors identified; and address any subjective bias inherent in dealing with “multi-currency” optimization as just described. Conclusion A framework for developing infrastructure investment objectives is suggested. A top level ontology of “classes of factors” recommended and a matrix of first level factors defined by considering this objective- class of factor prioritization space. The appendices further develop some of these first level factors and the intent is not to suggest that all be considered but rather represents an initial starting point for evaluating which small set of factors is most appropriate for use in prioritizing infrastructure investments. Finally, additional considerations that a strong prioritizing methodology must address are suggested and the challenges of “multi-currency” prioritization highlighted.
  • 13. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 13 of 24 References: 1. Application of Life Cycle Analysis in the Capital Assets Industry; Construction Management Association of America (CMAA); June 2013; ISBN 978-1- 938014-06-2 (eBook); ISBN 978-1-938014-07-9 (Print) 2. Capital Efficiency: Pull All the Levers; Construction Management Association of America (CMAA); August 2014; 978-1-938014-08-6 (eBook); ISBN 978-1- 938014-09-3 (Print) 3. Application of Life Cycle Analysis in the Capital Assets Industry Webinar; CMAA; July 17, 2014 4. Role of a Sound Asset Management System in Life Cycle Program Management; PM World Journal; October, 2013 5. Invest in infrastructure throughout its life cycle; Interview with Bob Prieto; PWC; September 10, 2013 6. Impediments for Implementing a Sound Asset Management System; Center for Advanced Infrastructure and Transportation; State of Good Repair Summit; March 27, 2013 7. Life Cycle Analysis – Interview with Fluor Senior VP Bob Prieto; AEC Business; August 19, 2013; http://aec-business.com/life-cycle-analysis-bob- prieto-fluor/ 8. Addressing Project Capital Efficiency through a Business Basis of Design; PM World Journal; April 2014 9. Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011 10. Project Selection in Large Engineering Construction Programs; PM World Today; June 2011; http://www.pmforum.org/library/papers/2011/PDFs/june/FP-PRIETO.pdf
  • 14. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 14 of 24 Appendix 1 Factors Related To Continuous Reduction in Life Cycle Cost and Progress towards A 50% Reduction in Life Cycle Cost By 2025  Revenue o First Revenue Date o Plant Availability Factor and Ramp-Up Period and Rate o Asset Life (Duration from First Revenue during analysis period) o Scheduled Shutdowns (Regulatory, Seasonal, Maintenance) o Supply/Demand Balance Normalized Price(Market Size; Competitor Actions) o Capacity or Throughput o Byproduct Value Captured o Tax Credits Realized o Inflation Adjustments to Normalized Pricing (Inflation; Currency Exchange Rates)  Indirect Asset Costs o Land use  Land use impacts include: Land use (the plant site) Emissions to air Emissions to water Emissions to soils. Land use change Mineral and fossil fuel use Land transformation Land occupation Soil erosion, compaction and sealing Often ignored in LCA but taking on increasing importance.  ISO 14040 – 14043, largely developed from industrial perspective and do not mention land use as an impact category  Land use considers following factors: Concurrent availability –site is available on some basis for use by other facilities. Important when evaluating large program or asset portfolio design. May be either: Constrained or limited Unconstrained or unlimited (except with respect to limiting attributes of the site independent of the facility’s presence at the site) Concurrent unavailability – the site is not available for other current use due to the facility’s presence at the site.
  • 15. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 15 of 24 Loss of optionality – site use, post facility closure, is limited because of the prior presence of the facility Permanent unavailability – use of the site, post closure, is not reasonably possible o Tax Regime  Taxable  Tax Credit  Tax Exempt o Financing structures  Common factors  Financial factors – hyper inflation, deflation, uninsured portion of disasters (natural, manmade, or Natech)  Environmental factors – climate change  Social factors – change in user behavior, change in surrounding community behavior with respect to the facility; compatibility with community goals and other social objectives  Correlated risks  Financing structures considered in a life cycle analysis influenced by many factors including: asset characterization governing financial metrics (ROE, ROI, IRR, ROA) asset lifetimes before refurbishment or replacement refinance periods construction and operations cash flows residual value of asset  Externalities o Intangibles such as brand value o Complexity o Assumption migration associated with longer time frames (dynamic risks) o Stakeholder trust o Susceptibility to “Black Swan” type risks o “Strategic speed” o Regulatory taxes and subsidies o Potential “Black Swan” factors to be considered in life cycle analysis include:  Financial factors – hyper inflation, deflation, uninsured portion of disasters (natural, manmade, or Natech)  Environmental factors – climate change  Social factors – change in user behavior, change in surrounding community behavior with respect to the facility  Correlated risks  Planning and Permitting
  • 16. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 16 of 24 o Impact of Permitting on Life Cycle Analysis:  Reduced revenue  Higher risk weighted cost of capital –investors may seek higher returns as they wait patiently and with a higher degree of uncertainty for the facility to obtain necessary approvals. Similarly debt costs may be higher especially in instances where project funding is utilized.  Higher permitting costs  Higher environmental mitigation or enhancement costs  Increased project escalation costs  Design o Factors Typically Considered in a Capital Asset Life Cycle Analysis  Labor Costs -professional services  Benefits from standardization /design reuse  Premium costs incurred because of schedule  Cost of Time (design duration/phasing)  Value of Risk (technology or other first of a kind risks; labor availability risk)  Design estimate uncertainties (estimating based; management model driven; rework based on late inputs or owner driven changes)  Consideration given to procurement and supply chain strategies (relates to potential for design rework or impacts on procurement)  Degree constructability considerations have been incorporated into design activities (influences design and construction management costs with the prospect of reduced construction durations and costs)  Life cycle and sustainability focus and provision in cost and schedule for more aggressive engagement of O&M managers, staff and key suppliers  Procurement & Construction  Operations  Maintenance o Reliability o Availability o Capacity Factor
  • 17. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 17 of 24 Appendix 2 Factors Related to PPP Policy  Policy framework (this is essential in any regulatory framework selected)  Toll rate level and structure  Concession payments (or government subsidy or facilities or services in kind)  Penalties and fines for non compliance  Concession period and its linkage to rate of return  Timing of investment and reinvestment obligations  Quality of service obligations  Investment level obligations  Depreciation and amortization rules (tax and accounting policy issues)  Forms and timing of restructurings allowed  Nature and duration of any exclusivity or restrictions on competing facilities  “Social” composition of user base (unintended social consequences)  Idiosyncrasies / uncertainty in forecasting models  Policy/rights retained and related to sequestration, forfeiture, withholding or suspension of guarantees, liability allocation and third party liability
  • 18. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 18 of 24 Appendix 3 Factors Related to A Defined Sustainability Framework  Major elements of sustainability are a fundamental requirement  Focus goes beyond first cost to a comprehensive life cycle perspective  Set of balanced solutions exist.  Management and execution approach based on systems approach  Sustainability framework at all program and project phases  Procurement of local goods o Local construction materials & tools adds income in immediate area & contributes to local tax base through sales tax  Creation of a local service base to support the facility during operations and maintenance phases.  Anti-corruption measures  Tied closely with social opportunities and benefits  Social metrics considered Social Metrics Diversity • Existence of equal opportunity policies or programs • Percentage of senior executives who are women • Percentage of staff who are members of visible minorities • Percentage of staff with disabilities Industrial Relations • Percentage of employees represented by independent trade union organizations or other bona fide employee representatives • Percentage of employees covered by collective bargaining agreements • Number of grievances from employees. Child Labor • Whether contractors are screened (or percentage screened) for use of child labor. Community • Earnings donated to the community; • Use of local contractors and suppliers. • Involvement in projects with value to the greater community
  • 19. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 19 of 24 Appendix 4 Factors Related to Owner Readiness  Program demand related forecasts  Factors related to program revenues  Equitable impact and benefit distribution  Owner’s financial condition  Resources available to the program  Competing programs and associated resource requirements and timing  Assumed changes to law, regulation or policy impacting owner and program and anticipated timing  External environment  Operating strategy and required lifecycle performance  Owner’s risk posture and philosophy  Business model, scenarios and relationship to program  Prerequisites for external approvals  External approval requirements, timing and likelihood  Prerequisites for owner’s executive approvals and linkage to a formal stage gate process including clarity and comprehensiveness of stage gate requirements and processes; stage gate approvals, authorities granted, resource commitments and constraints; approvals matrix  External prerequisites linked to stage gates including regulatory approvals required, process clarity and timing including safety case requirements; and process for property acquisition  The owner’s organization must also demonstrate readiness to: o Implement the stage gate process, consistent with the owner’s own requirements and consistent with a program’s demands. Approval time frames, gate expectations and nature of obtained approvals at each gate must tie clearly into program execution strategies. o Support management of demand for capital o Drive capital efficiency in projects as they advance trough the stage gate process. Among various elements of owner readiness to be considered would be the early focus on construction realities, constraints and opportunities that may be found in appropriate means and methods selection. o Enhance project execution by providing a disciplined project development framework o Enforce standards on management evaluation of alternatives including consideration of life cycle cost and performance evaluations. Significant life cycle performance benefits can accrue from strong incorporation of O&M considerations in the earliest stages of a program but many
  • 20. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 20 of 24 programs suffer from later stage changes because of lack of an early focus in this regard. o Influence acceptable risk frameworks commensurate with investments being undertaken and the risks program will face o Provide independent validation and verification  Capability of owner’s technology platforms to support the program are established and functioning at a level consistent with the program’s needs  Physical and cyber security requirements of owner and external organizations with requisite authorities are consistent with the program’s risk profile and the sensitivity of data and communications involved  Required reports by owner on program progress can be efficiently provided to external stakeholders and that there is a plan to do so.  Internal audit structure and controls are in place and associated budgeting and staffing requirements are recognized  Inspector general role, authorities and resources are clearly defined with respect to program role and a plan exists to mobilize these resources in support of the program
  • 21. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 21 of 24 Appendix 5 Factors Related to Asset Management Plans  A cradle to grave life-cycle approach.  Developing and implementing cost-effective strategies recognizing the long-term purpose and nature of these assets  Defining, establishing and providing for a defined nature and level of service  Monitoring, maintaining and where possible enhancing asset performance.  Anticipating, mitigating and managing risks associated with asset degradation and failures  Implementing asset management to achieve these objectives on a financial, environmental and societal basis.  Sustaining and where possible enhancing system level characteristics of an asset such as resiliency, flexibility and future optionality.  Deploying the limited financial, physical and human resources of the asset owner in an efficient, effective and sustainable manner. It is about making informed tradeoffs as part of our decision making process.  Continuously improving asset management practices.  Define the minimum level of detail for an asset (what assets to track)  Establish a uniform asset enumeration scheme (asset organization)  Identify existing assets and related attributes (asset data)  Identify the probability and consequence of failure of an asset (asset risk)  Establish the level of asset management performed (asset management strategy)  Establish short-interval portions of asset plans  Establish long-interval portions of asset plans  Develop procedures to update asset plans  Asset Development including achieving these objectives: o Develop a systematic approach to creating assets o Consider constructability, maintainability, and operability in the design process o Require that enumeration schemes be followed by designers and contractors o Maximize contractor contribution to asset development o Prepare asset plans coincident with asset delivery  Asset Operations and Maintenance o Defining required preventative maintenance activities. o Preventative maintenance scheduling o Performing defined preventative maintenance activities at the prescribed intervals. o Using indirect condition assessment where cost-effective. o Performing corrective maintenance on a timely basis. o Management of maintenance using a balanced approach between preventative and corrective maintenance o Recording maintenance costs on an activity basis, by asset. o Management of operational methods to minimize the combined costs of O&M.
  • 22. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 22 of 24 o Key objectives of asset O&M:  Proactive safety management  Track asset failures consistently  Prioritize work order backlog by risk  Asset Condition Monitoring has 3 goals: o Define condition monitoring methods o Define condition monitoring program o Integrate condition monitoring with other management and work processes
  • 23. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 23 of 24 Appendix 6 Factors Related to Reduced Exposure and Materialization of Risks of All Types  Labor Availability & Cost  Labor Productivity  Labor Impacts on Program Location  Material Availability & Cost  Long Lead Equipment  Construction Equipment  Logistical Costs  Life Cycle Costs  Relocation or Reconfiguration Costs  Industry Creation  Balance Sheet  Risk & Insurance Costs  Procurement and contractual frameworks  Craft capacity building  Management capacity building  Global leading best practices  Societal supporting facilities  Managing uncontrollable growth  Performance management  Waste streams  Energy  Water  Recyclable/reusable materials
  • 24. PM World Journal Classes of Factors to be Considered in Infrastructure Vol. III, Issue X – October 2014 Investment Prioritization www.pmworldjournal.net Featured Paper by Bob Prieto © 2014 Bob Prieto www.pmworldlibrary.net Page 24 of 24 About the Author Bob Prieto Senior Vice President Fluor Princeton, NJ, USA Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He focuses on the development and delivery of large, complex projects worldwide. Bob consults with owners of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry” and “Application of Life Cycle Analysis in the Capital Assets Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 500 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.