SlideShare a Scribd company logo
1 of 14
Download to read offline
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel
with controlled blasting and monitoring in maoist affected zone of HDN
route of S.E. Railway - an experience and overview.
by
Rajesh Prasad, Executive Director
Rail Vikas Nigam Limited
Synopsis:
In South Eastern Railway Tata-Rourkela section of Chakradharpur Division of
Howrah-Nagpur-Mumbai route is one of the busiest route having 40 and 52 GMT
traffic in UP & DN respectively. The section is one of the most typical for its
geographical features compounded with the maoist affected zone. The 3rd line
work (27.5 km) is being executed by RVNL and in first phase the work from
Posoita to Manoharpur (11.6 km) has been commissioned in 2016 whereas the
2nd phase between Goelkera to Posoita (15.9 km) is likely to be completed in
next 2 months time which includes a techno – maoist challenging construction of
tunnel of 680 m long. The Engineering challenge is for execution of tunnel having
no approach and ensuring safety of the adjoining tunnel by way of controlled
blasting keeping the frequency of waves after blasting under control for safety of
existing nearby tunnel by monitoring of blasting sequences. The administrative
challenge is to execute the work in extremely maoist affected area where on two
occasions, the maoist have burnt huge no of plants, equipments, machineries of
the executing contractor. In one occasion the machineries were burnt in
approach of the tunnel by maoist. The work is being executed 100% under
security protection of SAP (Special Auxiliary Police) provided by the State
Government of Jharkhand after having incident of burning of machineries which
brought the progress to a stop. The paper deals briefly about plan design,
characteristics, maoist problems and monitoring of the existing tunnel while
blasting for construction of the said tunnel.
1.0 Introduction:
The existing double line between
Manoharpur to Goelkera (27.5 km)
is having two tunnels having 1067
m lengths and 3rd line work is being
executed with tunnel of 680 m
length. The rail tunnel is being
executed between Mahadevsal and
Posoita Railway station on the
uphill side of the existing tunnel.
The work of tunnel design has
been entrusted to CIMFR Regional
Centre (CSIR/Roorkee).
Considering the minimum
requirement as per moving
dimensions of the Railways, 6.5 m
wide and 7.5 m in height, modified
KEY PLAN
horse-shoe type tunnel has been considered from stability point of view of
the tunnel. Provision of pathway has been kept on both sides of tunnel for
working and inspecting staffs. Because of the nearby tunnel having a
running traffic over the main line of Howrah-Nagpur-Mumbai route, it was
decided to use controlled blasting technique with monitoring system in the
existing tunnel while blasting being carried out in the 3rd line construction.
2.0 Soil/ Rock characteristics:
Rock core samples were taken for obtaining the geo-mechanical properties
of rock. Laboratory tests for uniaxial crushing strength (UCS) of intact rock
material, elastic modulus (E), poison’s ratio (v) and triaxial testing for shear
strength parameters like cohesion (c) and angle of internal friction (ɸ) were
carried out. Borehole wise details of rock core depths used for various tests
carried out for mechanical properties.
The laboratory test results for mechanical properties of rock/phyllites rock
were as under:
Property Value
Uniaxial Compressive strength (UCS), MPa 21.91
Modulus of Elasticity (E), GPa 42.0
Poisson’s ratio 0.22
Triaxial testing of phyllites for shear parameters were as under:
Set No. Cohesion, MPa Angle of Internal Friction, Degree
1 12.1 27.6
2 13.9 27.4
3.0 Features of proposed tunnel:
 Curves in tunnel alignment:
The tunnel portion of the rail line is not the straight one due to space
constraint in available of land. Two curves of 3 degrees each are present in
both the approaches of the proposed tunnel. On moving from Mahadevsal
to Posoita, the first curve is towards left, whereas the second curve is
PORTAL AT TUNNEL FACE VIEW OF TUNNEL
towards right. Out of total tunnel length of 680m (Ch. 5960m to 6640m),
305m length of the tunnel is in straight between these two curves.
 Size and shape of tunnel:
On moving from Mahadevsal to Posoita, the proposed tunnel would be on
the left side of the existing up line tunnel, i.e. on the up hill side. The
proposed tunnel is required to accommodate single BG (1676mm) railway
track. Considering the schedule of dimensions (SOD) of Indian Railways to
accommodate the dynamic clearance envelope (moving dimensions) of the
Rolling Stock including the lean on curves, the size of tunnel is shown as
follows:-
CROSS SECTION AS PER SOD
KEY PLAN OF TUNNELS (CURVATURE IN THE TUNNEL)
While designing the shape of the tunnel, the rock mechanics principles have
been kept in mind and therefore, horse shoe shape with curved bottom has
been opted for best stability. Also while finalizing the shape, 750 mm
clearance below the rail level is tried to obtain in the width of 1676mm (BG
width). Considering the characteristics of rock, the tunnel excavation is
being done in heading and benching separately using control blasting
technique. The cross sectional area of tunnel excavation is 59 cum per
meter.
 Excavated size:
(i) Steel rib supported section (with provision of 30cm thick support)
 Tunnel height – 7.810m (6.726m above the rail/ formation level and
1.084m below rail level)
 Tunnel excavation width – 7.057m
(ii) SFRS (Steel Fiber Reinforced Shotcrete) and rock bolt supported
section
 Tunnel height – 7.610m (6.526m above the rail/ formation level and
1.084m below rail level)
 Tunnel excavation width – 6.657m
Finished size:
 Tunnel height – 7.21m (6.426m above the rail/ formation level and
0.784m below rail level)
 Tunnel width – 6.457m
TUNNEL EXCAVATION BEING DONE IN HEADING AND BENCHING METHOD
 Size, shape and number of trolley refuse:
Since the tunnel length is more than 100m, trolley refuses have been
provided at every 100 m interval. As such, there are five trolley refuses in a
680m long tunnel. The trolley refuse are on the left side (up hill side) of the
tunnel. On the right side there is another existing up tunnel.
 Ventilation shaft
A ventilation shaft circular in shape and 2.0m
finished diameter at the centre of the tunnel, i.e.
at ch. 6300m has been provided. The shaft is
around 35m deep from expose surface of
mountain.
 The portal location
The proposed locations of Mahadevsal and Posoita end portals are at
5960.0m and 6640.0m respectively. The length of the tunnel thus worked
out is 680.0m. It has 1 in 100 down gradient from Mahadevsal end to
Posoita end. The finished tunnel width is 6.457m and the height is around
7.21m. The ground and formation levels at the two portals and the rock
cover above the tunnel crown/ roof are given as under:
SN Location Ground level
(m)
Formation/
rail level (m)
Rock cover
above tunnel
crown (m)
1 Mahadevsal portal
(Ch. 5960m)
351.487 330.097 14.664
2 Posoita portal 343.045 323.297 13.022
The minimum rock cover above the tunnel roof or the tunnel crown at both
portal locations is about two times the tunnel diameter which is a standard
as per practice while excavating tunnel in weak rock.
 Stability of slope above portals
Because of loosened rock cover above tunnel portals at both the ends has
been excavated in such a way that it has a slope of 3V:1H (approx. an angle
of 710) from the horizontal. One 3.0m wide bench has been provided at a
height of 16.0m from formation level, i.e. about 9.5m above the tunnel roof.
This bench matches with the top bench of side slopes. Slope treatment has
been done to stabilize the slope above portal. Rock bolts, wire net and plain
shotcrete for the protection of slopes above portal have been used. The
rock bolts of length 4m long fully grouted, spaced at 3m centre to centre and
staggered. The thickness of shotcrete being used are 100mm in two layers
of 50mm each before and after fixing the wire net. The wire net of 100mm in
two layers of 50mm each before and after fixing the wire net. The wire net of
100mmx100mm size with standard galvanized wire of 3.5mm diameter.
Slope above portal are also being properly fenced by erecting wall for the
protection of persons, animals etc.
After opening of ventilation shaft
 Stability of side slopes of open excavation
The expected maximum bench height of open excavation is about 21m at
Mahadevsal end portal and 19.748m at Posoita end portal. Although the
side rock benches of open excavation in the existing tunnels are standing
without any support, but considering the appreciable height of slope and
loose rock and the weak overburden material, there are chances of cut
slope instability. Therefore, slope angle is 710 from horizontal (3V:1H) has
been provided.
4.0 Empirical approach of tunnel support design:
The rock masses of the area have been classified using the Q-system of
Barton et al. (1974).
The ratings for various parameters of Q systems for phyllites have been
collected by CIMFR from the rock exposures on the surface and bore hole
logs. The Q values, thus obtained, are given below. At portal location it is
expected that the rock joints would be loose and therefore in addition to
other parameters the rating of Jr and Ja is taken accordingly.
SN Location RQD Jn Jr Ja Jw SRF Q RMR=91nQ+44
1 Portal area 10 9 1.0 1.5 1.0 5 0.11 18
2 In tunnel 40-50 6 1.5-4.0
(2.75)
1.0 1.0 5 2-6.66
(3.65)
56
3 Intersection
of tunnel
and trolley
refuse
40-50 6x3=18 1.5-4.0
(2.75)
1.0 1.0 5 0.66-
2.22
(1.21)
46
Notations: RQD-Rock quality designation, Jn – joint set number; Jr – Joint
roughness number; Ja– joint alteration number; Jw– joint water reduction
factor; SRF – stress reduction factor and Q – rock mass quality = [ROD
JrJw)/ (JnJaSRF)] Average value is given in brackets.
The Q values at intersections of main tunnel and trolley refuse is different
because of the multiplication factor in the rating of joint set number (Jn)
[Barton et al., 1974]. The rating for Jn would be 3XJnin the intersection at
trolley refuse area respectively. As such the Q value for the design of
supports at the intersection of tunnel and trolley refuse is also given. Q
values for the portal has not used for the support design purpose.
5.0 Numerical modeling:
Numerical analysis for the rock mass has been conducted using three-
dimensional finite difference code (FLAC3D). The state of the art code has
the capabilities to model the behavior of the rock mass in continuum. The
code was chosen to perform stability analysis of the parallel tunnels. The
objective of the modeling study is to understand the behavior of rock mass
and induced stresses around tunnel.
Hoek-Brown (2002) proposed their failure criterion to provide input data for
the analysis required for the design of underground excavations in hard
rock. The Hoek- Brown failure criterion characterizes the stress conditions
that lead to failure in intact rock and rock masses. The failure surface is
nonlinear and is based on the relation between the major and minor
principal stresses. The model incorporates a plasticity flow rule that varies
as a function of the confining stress level.
Hoek-Brown criterion is defined by the equation:
0.5
Further details are available in CIMFR report.
 Result of analysis
The results of the analysis indicate that the structure is stable and no major
plastic deformations occur except for minor instability at walls which has to
be stabilized by providing rock bolt and shotcrete supports. Figures of
contour plots of major (σ1)and minor (σ3) principal stresses and maximum
displacements and state of shear failure. The principal stresses at roof and
wall are given below:
It is observed from the figures that most of the plots of shear failure for
different cases using the Hoek & Brown failure criterion that the structure is
stable and only rock bolts and shotcrete are required to stabilize minor
instabilities. These findings hold good for massive rock.
Stress model Principal stresses Stress – I Stress - II
Roof Wall Roof Wall
Depth=20m σ1 -1.45 -0.75 -2.62 -0.78
σ3 -1.25 -0.017 -0.17 0.018
Depth=40m σ1 -2.84 -1.58 -4.62 -1.39
σ3 -0.23 -0.035 -0.35 -0.03
6.0 Observation and recommendations of CIMFR:
 The tunnel between Mahadevsal and Posoita in Jharkhand state passes
through mainly phyllites.
 The geological and geotechnical data for the tunnel design were collected
from field survey, borehole logs and laboratory testing at Roorkee.
 The treatment of slopes above the tunnel portal has been done. The stability
measures required for the high benches to be cut on the two side of the
track in open area are also used.
 For the tunnel design, the tunnel is divided into three ones – (i) portal
area (ii) main tunnel, (iii) intersection zone of main tunnel and trolley
refuse.
 Five trolley refuses have been constructed at a spacing of 100m interval
towards the uphill side of the tunnel.
 Controlled blasting technique is used for the excavation of tunnel,
trolley refuse and the ventilation shaft. Accordingly, the blast designs
for all the excavations have been made. For the tunnel a MCD
(Maximum Charged density) of 14.0kg is being used.
 Empirical and numerical approaches have been used. It has been obtained
from numerical analysis that the horse-shoe shape is better than the D-
shape. Accordingly a horse-shoe shape is used. The spacing of 31m
between two tunnels, the existing tunnel and the one to be constructed, is
found to be adequate.
 It is suggested to use ISHB 200 steel rib supports at 100cm centre to centre
spacing with 30cm thick M20 plain shotcrete in the portal zone of 20m at
both the portals.
 In the remaining portion of tunnels supports have been worked out using the
empirical approach based on the Q-system. Accordingly, the rock bolt and
M25 steel fiber reinforced shotcrete (SFRS) support is used. Thus the
shotcrete is having good bond with the rock mass.
 In case the rocks encountered during excavation are different, the supports
would also differ. Hence, a geologist has been deputed at site during
construction to obtain the rock mass parameters and also to obtain the Q
value so that the supports can be modified accordingly. As and when
required.
 It was recommended to monitor the actual ground blast vibrations during the
construction of the tunnel. If required the suggested blast design may be
modified.
 It was also recommended to monitor the supports by monitoring the tunnel
roof and wall deformations.
7.0 Features :
7.1 Underground excavation
Total excavation for the underground works considering the tunnel portal to
be fixed at Ch. 5960.00m and ch. 6640.00 is as follows:
Location Length, m Area of
excavation, m2
Total volume of excavation,
m3 (rounded off)
Portal area 40m (20m
both ends)
46.74 1869.60
(say 1870.00)
Tunnel in
phyllities
640.0 43.137 27607.68
(say 27610)
Nitch for trolley
refuse (5
nitches)
3.0 9.655 28.96 (say 29 for one nitch
and 145 for five nitches)
Ventilation shaft
(excavated dia =
2.2m)
35 3.8 133.00
Total 29758
7.2 Steel rib support in portal area
Steel rib supports have been used for the portal zone in a length of 20m at
each portal. It is decided to use ISHM 200 steel rib supports for the purpose.
7.3 Shotcrete requirement
The shotcrete should have UCS of 20
MPa and it should have good bond
with the rock.
7.4 Steel fiber reinforced shotcrete (SFRS)
Steel fiber reinforced shotcrete (SFRS) has been used in main tunnel,
trolley refuse and in ventilation shaft. For plain shotcrete and for SFRS, a
rebound loss of 50 per cent has been considered while calculating the
required quantities. This got reduced to about 10 per cent after skilled
persons and machineries were deployed. This was as per the
recommended action of CIMFR.
It was also be kept in mind that the shotcrete rebound loss decreases with
the increase in the thickness of shotcrete.
7.5 Rock fiber
50 kg/ m3 steel fiber of good quality and international standard for getting
desired energy absorption capacity has been used.
7.6 Rock bolt
Full column grouted 3.0m long and 25mm diameter tor steel rock bolts are
used for the tunnel. The pull out capacity of the bolts has been considered
to be more than or equal to 15 tones. These bolts are fixed at a spacing
1.5m centre to centre.
7.7 Concrete lining
Plain concrete lining of M20 of 30cm thick is used in the floor of trolley
refuse. Reinforced concrete lining of M25 of 30cm thick has been used in
the invert of tunnel throughout its length.
STEEL RIBS FIXED ON HEADING STEEL RIBS & COMPRESSED AIR
SHOTCRETE
7.8 Drainage pipes
Two 160mm diameter perforated drainage pipes above tunnel invert in the
centre of the tunnel are used throughout the length of the tunnel.
7.9 Lighting
LED lights of 56W each are being provided at 40m interval on both the sides
of tunnel. The lights are being staggered. So there will be one light on one
of the walls at every 20m interval. Therefore, there will be a total of 34 light
points connections in full tunnel having 17 points on one wall.
8.0 Maoist affected area:
As the construction is in highly
extremist infested zone the work
is being executed under 100%
security cover of SAP posted by
State Government of Jharkhand.
The permission was earlier
granted to execute the work only
during day time by bringing
blasting material by mobile van
from Ranchi and after blasting it
has to be return back on same day as storage was permission was not
granted. With these constraints 570 m tunnel blasting was done.
Subsequently it has been brought in the notice of State Government by
CRB that if last milestone support will be given it is possible to finish the
tunnel excavation of remaining 110 m with fast pace. Hence, after the
meeting by Chairman, Railway Board with the Chief Minister of Jharkhand,
the permissions have been accorded for execution during night time on
06.12.2017 by further strengthening the protection force at site by diverting
it from other sources. The tunnel is being executed by using heading and
benching method due to poor rock structure where stand up time is not very
high. A crossing section and support section of partly and OHE
arrangements are indicated as per the drawings indicated as under:
Execution under SAP
9.0 Vibration monitoring:
The layout of the existing tunnel vis-à-vis the tunnel under construction is
indicated as per the sketch as indicated below:
As the existing tunnel is very close to the 3rd line tunnel under excavation
(31m centre to centre) the controlled blasting is being done under guidelines
of DDC, the consultancy contract given to CIMFR. There is a site monitoring
system for measuring vibration in the existing tunnel during blasting of 3rd
line. During the recent visit of Principal Scientist, the following observations
were recorded by the Principal Scientist of CSIR-CIMFR:
 Rock cover over tunnel at present location is more than 25m
 Geological features coming in Posoita end now requires SFR shotcrete
lining only.
 At Goelkera face the rock mass is of poor quality and significant water
egress is also noticed. The joints in the rock mass are clay filled having
stability problem due to reduction in shear strength. Hence steel rib support
are recommended to continue.
 The sequence of delay blasting by choosing 1 to 12 delay series of LD. The
placement of LD’s in heading is shown below. This will control the amplitude
of blasting and blasting is being done in sequences.
 Two blasting were done in presence with maximum charge per delay
approx. 10.3 kg and recorded induced ground vibration having peak
particle velocity (PPV) near existing tunnel portal at Posoita end was
found 5.65 mm/sec which is below 10mm/sec recommended for no effect on
the existing nearby tunnel. The summary of blast vibration and Fast Fourier
Transform Analysis (FFT) are as per the report attached.
10.0 Conclusion:
The technical challenge of ensuring safety of the existing tunnel has been
ensured by using vibration monitoring under the supervision of CSIR –
CIMFR. Technique is basically to have the delay introduced in sequences
of blasting so that peak particle velocity of shock waves generated after
blasting should not exceed the permissible limit to the existing nearby
structure which is in this case a old railway tunnel. The administrative
challenge of execution in maoist area has been resolved by having regular
meetings with the senior officials of Government of Jharkhand and under
the 100% protection of the police. The tunnel work is likely to be
completed by February, 2018 which was the most critical part of the
project. The section is also likely to be commissioned in coming few
months which will have large benefit to the Railways in de-congestion of
the Howrah – Nagpur – Mumbai route.
DELAY SERIES NUMBERING 1 to 12 IS SHOWN ABOVE
FFT REPORT
EVENT REPORT

More Related Content

What's hot

STEEL BRIDGE GIRDERS & PSC BRIDGE SLABS
STEEL BRIDGE GIRDERS & PSC BRIDGE SLABSSTEEL BRIDGE GIRDERS & PSC BRIDGE SLABS
STEEL BRIDGE GIRDERS & PSC BRIDGE SLABSAl Hakam Khan
 
Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Hamed Zarei
 
Ct pad-foundation
Ct pad-foundationCt pad-foundation
Ct pad-foundationWan Nee
 
Comprehensive report on Tunneling @ Abu Hamour Project_Qatar
Comprehensive report on Tunneling @ Abu Hamour Project_QatarComprehensive report on Tunneling @ Abu Hamour Project_Qatar
Comprehensive report on Tunneling @ Abu Hamour Project_QatarPallav Sharma
 
1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTUVATSAL PATEL
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reporthemanth kumar
 
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)Rakesh Kumar Choubey
 
Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Multan Prajapat
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road workRakesh Meena
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1সাফকাত অরিন
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 

What's hot (20)

DMC Piling
DMC PilingDMC Piling
DMC Piling
 
STEEL BRIDGE GIRDERS & PSC BRIDGE SLABS
STEEL BRIDGE GIRDERS & PSC BRIDGE SLABSSTEEL BRIDGE GIRDERS & PSC BRIDGE SLABS
STEEL BRIDGE GIRDERS & PSC BRIDGE SLABS
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)
 
Ct pad-foundation
Ct pad-foundationCt pad-foundation
Ct pad-foundation
 
Casting yard
Casting yardCasting yard
Casting yard
 
Comprehensive report on Tunneling @ Abu Hamour Project_Qatar
Comprehensive report on Tunneling @ Abu Hamour Project_QatarComprehensive report on Tunneling @ Abu Hamour Project_Qatar
Comprehensive report on Tunneling @ Abu Hamour Project_Qatar
 
Pilework
PileworkPilework
Pilework
 
1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU1.PILE FOUNDATION (ACE) 2160601 GTU
1.PILE FOUNDATION (ACE) 2160601 GTU
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro report
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
ERECTION/LAUNCHING OF PRECAST SEGMENT USING GROUND SUPPORT SYSTEM (UNDER SLUNG)
 
Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...Blastless track construction in tunnel and elavated metro station constructio...
Blastless track construction in tunnel and elavated metro station constructio...
 
DMC piling
DMC pilingDMC piling
DMC piling
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road work
 
Post tensioning
Post tensioningPost tensioning
Post tensioning
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
 
Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 

Similar to Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of hdn route of s.e. railway

Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnelijceronline
 
Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress reportNeha Singh
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...CrimsonPublishersAMMS
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...SYSTRA
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxAbdulMannan357156
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...Rajesh Prasad
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...IRJET Journal
 
Paper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanPaper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanSantosh Sati
 
Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Prudhvi Thota
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge Taseem mir
 

Similar to Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of hdn route of s.e. railway (20)

Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress report
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
Application of Macro-Synthetic-Fiber-Reinforced Sprayed Concrete for Primary ...
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
 
Box culverts
Box culvertsBox culverts
Box culverts
 
report
reportreport
report
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
 
Paper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanPaper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutan
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.Case studies of surveys involved in Railway Tunnel constructed under sea.
Case studies of surveys involved in Railway Tunnel constructed under sea.
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Paper 4
Paper 4Paper 4
Paper 4
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
 

More from Rajesh Prasad

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Rajesh Prasad
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdfRajesh Prasad
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLRajesh Prasad
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 Rajesh Prasad
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfRajesh Prasad
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21Rajesh Prasad
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...Rajesh Prasad
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Rajesh Prasad
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Rajesh Prasad
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalRajesh Prasad
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...Rajesh Prasad
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Rajesh Prasad
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Rajesh Prasad
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Rajesh Prasad
 

More from Rajesh Prasad (20)

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West Bengal
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
 
The RVNL Story 2019
The RVNL Story 2019The RVNL Story 2019
The RVNL Story 2019
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
 

Recently uploaded

Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 

Recently uploaded (20)

Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 

Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of hdn route of s.e. railway

  • 1. Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of S.E. Railway - an experience and overview. by Rajesh Prasad, Executive Director Rail Vikas Nigam Limited Synopsis: In South Eastern Railway Tata-Rourkela section of Chakradharpur Division of Howrah-Nagpur-Mumbai route is one of the busiest route having 40 and 52 GMT traffic in UP & DN respectively. The section is one of the most typical for its geographical features compounded with the maoist affected zone. The 3rd line work (27.5 km) is being executed by RVNL and in first phase the work from Posoita to Manoharpur (11.6 km) has been commissioned in 2016 whereas the 2nd phase between Goelkera to Posoita (15.9 km) is likely to be completed in next 2 months time which includes a techno – maoist challenging construction of tunnel of 680 m long. The Engineering challenge is for execution of tunnel having no approach and ensuring safety of the adjoining tunnel by way of controlled blasting keeping the frequency of waves after blasting under control for safety of existing nearby tunnel by monitoring of blasting sequences. The administrative challenge is to execute the work in extremely maoist affected area where on two occasions, the maoist have burnt huge no of plants, equipments, machineries of the executing contractor. In one occasion the machineries were burnt in approach of the tunnel by maoist. The work is being executed 100% under security protection of SAP (Special Auxiliary Police) provided by the State Government of Jharkhand after having incident of burning of machineries which brought the progress to a stop. The paper deals briefly about plan design, characteristics, maoist problems and monitoring of the existing tunnel while blasting for construction of the said tunnel. 1.0 Introduction: The existing double line between Manoharpur to Goelkera (27.5 km) is having two tunnels having 1067 m lengths and 3rd line work is being executed with tunnel of 680 m length. The rail tunnel is being executed between Mahadevsal and Posoita Railway station on the uphill side of the existing tunnel. The work of tunnel design has been entrusted to CIMFR Regional Centre (CSIR/Roorkee). Considering the minimum requirement as per moving dimensions of the Railways, 6.5 m wide and 7.5 m in height, modified KEY PLAN
  • 2. horse-shoe type tunnel has been considered from stability point of view of the tunnel. Provision of pathway has been kept on both sides of tunnel for working and inspecting staffs. Because of the nearby tunnel having a running traffic over the main line of Howrah-Nagpur-Mumbai route, it was decided to use controlled blasting technique with monitoring system in the existing tunnel while blasting being carried out in the 3rd line construction. 2.0 Soil/ Rock characteristics: Rock core samples were taken for obtaining the geo-mechanical properties of rock. Laboratory tests for uniaxial crushing strength (UCS) of intact rock material, elastic modulus (E), poison’s ratio (v) and triaxial testing for shear strength parameters like cohesion (c) and angle of internal friction (ɸ) were carried out. Borehole wise details of rock core depths used for various tests carried out for mechanical properties. The laboratory test results for mechanical properties of rock/phyllites rock were as under: Property Value Uniaxial Compressive strength (UCS), MPa 21.91 Modulus of Elasticity (E), GPa 42.0 Poisson’s ratio 0.22 Triaxial testing of phyllites for shear parameters were as under: Set No. Cohesion, MPa Angle of Internal Friction, Degree 1 12.1 27.6 2 13.9 27.4 3.0 Features of proposed tunnel:  Curves in tunnel alignment: The tunnel portion of the rail line is not the straight one due to space constraint in available of land. Two curves of 3 degrees each are present in both the approaches of the proposed tunnel. On moving from Mahadevsal to Posoita, the first curve is towards left, whereas the second curve is PORTAL AT TUNNEL FACE VIEW OF TUNNEL
  • 3. towards right. Out of total tunnel length of 680m (Ch. 5960m to 6640m), 305m length of the tunnel is in straight between these two curves.  Size and shape of tunnel: On moving from Mahadevsal to Posoita, the proposed tunnel would be on the left side of the existing up line tunnel, i.e. on the up hill side. The proposed tunnel is required to accommodate single BG (1676mm) railway track. Considering the schedule of dimensions (SOD) of Indian Railways to accommodate the dynamic clearance envelope (moving dimensions) of the Rolling Stock including the lean on curves, the size of tunnel is shown as follows:- CROSS SECTION AS PER SOD KEY PLAN OF TUNNELS (CURVATURE IN THE TUNNEL)
  • 4. While designing the shape of the tunnel, the rock mechanics principles have been kept in mind and therefore, horse shoe shape with curved bottom has been opted for best stability. Also while finalizing the shape, 750 mm clearance below the rail level is tried to obtain in the width of 1676mm (BG width). Considering the characteristics of rock, the tunnel excavation is being done in heading and benching separately using control blasting technique. The cross sectional area of tunnel excavation is 59 cum per meter.  Excavated size: (i) Steel rib supported section (with provision of 30cm thick support)  Tunnel height – 7.810m (6.726m above the rail/ formation level and 1.084m below rail level)  Tunnel excavation width – 7.057m (ii) SFRS (Steel Fiber Reinforced Shotcrete) and rock bolt supported section  Tunnel height – 7.610m (6.526m above the rail/ formation level and 1.084m below rail level)  Tunnel excavation width – 6.657m Finished size:  Tunnel height – 7.21m (6.426m above the rail/ formation level and 0.784m below rail level)  Tunnel width – 6.457m TUNNEL EXCAVATION BEING DONE IN HEADING AND BENCHING METHOD
  • 5.  Size, shape and number of trolley refuse: Since the tunnel length is more than 100m, trolley refuses have been provided at every 100 m interval. As such, there are five trolley refuses in a 680m long tunnel. The trolley refuse are on the left side (up hill side) of the tunnel. On the right side there is another existing up tunnel.  Ventilation shaft A ventilation shaft circular in shape and 2.0m finished diameter at the centre of the tunnel, i.e. at ch. 6300m has been provided. The shaft is around 35m deep from expose surface of mountain.  The portal location The proposed locations of Mahadevsal and Posoita end portals are at 5960.0m and 6640.0m respectively. The length of the tunnel thus worked out is 680.0m. It has 1 in 100 down gradient from Mahadevsal end to Posoita end. The finished tunnel width is 6.457m and the height is around 7.21m. The ground and formation levels at the two portals and the rock cover above the tunnel crown/ roof are given as under: SN Location Ground level (m) Formation/ rail level (m) Rock cover above tunnel crown (m) 1 Mahadevsal portal (Ch. 5960m) 351.487 330.097 14.664 2 Posoita portal 343.045 323.297 13.022 The minimum rock cover above the tunnel roof or the tunnel crown at both portal locations is about two times the tunnel diameter which is a standard as per practice while excavating tunnel in weak rock.  Stability of slope above portals Because of loosened rock cover above tunnel portals at both the ends has been excavated in such a way that it has a slope of 3V:1H (approx. an angle of 710) from the horizontal. One 3.0m wide bench has been provided at a height of 16.0m from formation level, i.e. about 9.5m above the tunnel roof. This bench matches with the top bench of side slopes. Slope treatment has been done to stabilize the slope above portal. Rock bolts, wire net and plain shotcrete for the protection of slopes above portal have been used. The rock bolts of length 4m long fully grouted, spaced at 3m centre to centre and staggered. The thickness of shotcrete being used are 100mm in two layers of 50mm each before and after fixing the wire net. The wire net of 100mm in two layers of 50mm each before and after fixing the wire net. The wire net of 100mmx100mm size with standard galvanized wire of 3.5mm diameter. Slope above portal are also being properly fenced by erecting wall for the protection of persons, animals etc. After opening of ventilation shaft
  • 6.  Stability of side slopes of open excavation The expected maximum bench height of open excavation is about 21m at Mahadevsal end portal and 19.748m at Posoita end portal. Although the side rock benches of open excavation in the existing tunnels are standing without any support, but considering the appreciable height of slope and loose rock and the weak overburden material, there are chances of cut slope instability. Therefore, slope angle is 710 from horizontal (3V:1H) has been provided. 4.0 Empirical approach of tunnel support design: The rock masses of the area have been classified using the Q-system of Barton et al. (1974). The ratings for various parameters of Q systems for phyllites have been collected by CIMFR from the rock exposures on the surface and bore hole logs. The Q values, thus obtained, are given below. At portal location it is expected that the rock joints would be loose and therefore in addition to other parameters the rating of Jr and Ja is taken accordingly. SN Location RQD Jn Jr Ja Jw SRF Q RMR=91nQ+44 1 Portal area 10 9 1.0 1.5 1.0 5 0.11 18 2 In tunnel 40-50 6 1.5-4.0 (2.75) 1.0 1.0 5 2-6.66 (3.65) 56 3 Intersection of tunnel and trolley refuse 40-50 6x3=18 1.5-4.0 (2.75) 1.0 1.0 5 0.66- 2.22 (1.21) 46 Notations: RQD-Rock quality designation, Jn – joint set number; Jr – Joint roughness number; Ja– joint alteration number; Jw– joint water reduction factor; SRF – stress reduction factor and Q – rock mass quality = [ROD JrJw)/ (JnJaSRF)] Average value is given in brackets. The Q values at intersections of main tunnel and trolley refuse is different because of the multiplication factor in the rating of joint set number (Jn) [Barton et al., 1974]. The rating for Jn would be 3XJnin the intersection at trolley refuse area respectively. As such the Q value for the design of supports at the intersection of tunnel and trolley refuse is also given. Q values for the portal has not used for the support design purpose. 5.0 Numerical modeling: Numerical analysis for the rock mass has been conducted using three- dimensional finite difference code (FLAC3D). The state of the art code has the capabilities to model the behavior of the rock mass in continuum. The code was chosen to perform stability analysis of the parallel tunnels. The objective of the modeling study is to understand the behavior of rock mass and induced stresses around tunnel. Hoek-Brown (2002) proposed their failure criterion to provide input data for the analysis required for the design of underground excavations in hard rock. The Hoek- Brown failure criterion characterizes the stress conditions
  • 7. that lead to failure in intact rock and rock masses. The failure surface is nonlinear and is based on the relation between the major and minor principal stresses. The model incorporates a plasticity flow rule that varies as a function of the confining stress level. Hoek-Brown criterion is defined by the equation: 0.5 Further details are available in CIMFR report.  Result of analysis The results of the analysis indicate that the structure is stable and no major plastic deformations occur except for minor instability at walls which has to be stabilized by providing rock bolt and shotcrete supports. Figures of contour plots of major (σ1)and minor (σ3) principal stresses and maximum displacements and state of shear failure. The principal stresses at roof and wall are given below: It is observed from the figures that most of the plots of shear failure for different cases using the Hoek & Brown failure criterion that the structure is stable and only rock bolts and shotcrete are required to stabilize minor instabilities. These findings hold good for massive rock. Stress model Principal stresses Stress – I Stress - II Roof Wall Roof Wall Depth=20m σ1 -1.45 -0.75 -2.62 -0.78 σ3 -1.25 -0.017 -0.17 0.018 Depth=40m σ1 -2.84 -1.58 -4.62 -1.39 σ3 -0.23 -0.035 -0.35 -0.03 6.0 Observation and recommendations of CIMFR:  The tunnel between Mahadevsal and Posoita in Jharkhand state passes through mainly phyllites.  The geological and geotechnical data for the tunnel design were collected from field survey, borehole logs and laboratory testing at Roorkee.  The treatment of slopes above the tunnel portal has been done. The stability measures required for the high benches to be cut on the two side of the track in open area are also used.  For the tunnel design, the tunnel is divided into three ones – (i) portal area (ii) main tunnel, (iii) intersection zone of main tunnel and trolley refuse.  Five trolley refuses have been constructed at a spacing of 100m interval towards the uphill side of the tunnel.
  • 8.  Controlled blasting technique is used for the excavation of tunnel, trolley refuse and the ventilation shaft. Accordingly, the blast designs for all the excavations have been made. For the tunnel a MCD (Maximum Charged density) of 14.0kg is being used.  Empirical and numerical approaches have been used. It has been obtained from numerical analysis that the horse-shoe shape is better than the D- shape. Accordingly a horse-shoe shape is used. The spacing of 31m between two tunnels, the existing tunnel and the one to be constructed, is found to be adequate.  It is suggested to use ISHB 200 steel rib supports at 100cm centre to centre spacing with 30cm thick M20 plain shotcrete in the portal zone of 20m at both the portals.  In the remaining portion of tunnels supports have been worked out using the empirical approach based on the Q-system. Accordingly, the rock bolt and M25 steel fiber reinforced shotcrete (SFRS) support is used. Thus the shotcrete is having good bond with the rock mass.  In case the rocks encountered during excavation are different, the supports would also differ. Hence, a geologist has been deputed at site during construction to obtain the rock mass parameters and also to obtain the Q value so that the supports can be modified accordingly. As and when required.  It was recommended to monitor the actual ground blast vibrations during the construction of the tunnel. If required the suggested blast design may be modified.  It was also recommended to monitor the supports by monitoring the tunnel roof and wall deformations. 7.0 Features : 7.1 Underground excavation Total excavation for the underground works considering the tunnel portal to be fixed at Ch. 5960.00m and ch. 6640.00 is as follows: Location Length, m Area of excavation, m2 Total volume of excavation, m3 (rounded off) Portal area 40m (20m both ends) 46.74 1869.60 (say 1870.00) Tunnel in phyllities 640.0 43.137 27607.68 (say 27610) Nitch for trolley refuse (5 nitches) 3.0 9.655 28.96 (say 29 for one nitch and 145 for five nitches) Ventilation shaft (excavated dia = 2.2m) 35 3.8 133.00 Total 29758
  • 9. 7.2 Steel rib support in portal area Steel rib supports have been used for the portal zone in a length of 20m at each portal. It is decided to use ISHM 200 steel rib supports for the purpose. 7.3 Shotcrete requirement The shotcrete should have UCS of 20 MPa and it should have good bond with the rock. 7.4 Steel fiber reinforced shotcrete (SFRS) Steel fiber reinforced shotcrete (SFRS) has been used in main tunnel, trolley refuse and in ventilation shaft. For plain shotcrete and for SFRS, a rebound loss of 50 per cent has been considered while calculating the required quantities. This got reduced to about 10 per cent after skilled persons and machineries were deployed. This was as per the recommended action of CIMFR. It was also be kept in mind that the shotcrete rebound loss decreases with the increase in the thickness of shotcrete. 7.5 Rock fiber 50 kg/ m3 steel fiber of good quality and international standard for getting desired energy absorption capacity has been used. 7.6 Rock bolt Full column grouted 3.0m long and 25mm diameter tor steel rock bolts are used for the tunnel. The pull out capacity of the bolts has been considered to be more than or equal to 15 tones. These bolts are fixed at a spacing 1.5m centre to centre. 7.7 Concrete lining Plain concrete lining of M20 of 30cm thick is used in the floor of trolley refuse. Reinforced concrete lining of M25 of 30cm thick has been used in the invert of tunnel throughout its length. STEEL RIBS FIXED ON HEADING STEEL RIBS & COMPRESSED AIR SHOTCRETE
  • 10. 7.8 Drainage pipes Two 160mm diameter perforated drainage pipes above tunnel invert in the centre of the tunnel are used throughout the length of the tunnel. 7.9 Lighting LED lights of 56W each are being provided at 40m interval on both the sides of tunnel. The lights are being staggered. So there will be one light on one of the walls at every 20m interval. Therefore, there will be a total of 34 light points connections in full tunnel having 17 points on one wall. 8.0 Maoist affected area: As the construction is in highly extremist infested zone the work is being executed under 100% security cover of SAP posted by State Government of Jharkhand. The permission was earlier granted to execute the work only during day time by bringing blasting material by mobile van from Ranchi and after blasting it has to be return back on same day as storage was permission was not granted. With these constraints 570 m tunnel blasting was done. Subsequently it has been brought in the notice of State Government by CRB that if last milestone support will be given it is possible to finish the tunnel excavation of remaining 110 m with fast pace. Hence, after the meeting by Chairman, Railway Board with the Chief Minister of Jharkhand, the permissions have been accorded for execution during night time on 06.12.2017 by further strengthening the protection force at site by diverting it from other sources. The tunnel is being executed by using heading and benching method due to poor rock structure where stand up time is not very high. A crossing section and support section of partly and OHE arrangements are indicated as per the drawings indicated as under: Execution under SAP
  • 11. 9.0 Vibration monitoring: The layout of the existing tunnel vis-à-vis the tunnel under construction is indicated as per the sketch as indicated below: As the existing tunnel is very close to the 3rd line tunnel under excavation (31m centre to centre) the controlled blasting is being done under guidelines of DDC, the consultancy contract given to CIMFR. There is a site monitoring system for measuring vibration in the existing tunnel during blasting of 3rd line. During the recent visit of Principal Scientist, the following observations were recorded by the Principal Scientist of CSIR-CIMFR:  Rock cover over tunnel at present location is more than 25m  Geological features coming in Posoita end now requires SFR shotcrete lining only.  At Goelkera face the rock mass is of poor quality and significant water egress is also noticed. The joints in the rock mass are clay filled having stability problem due to reduction in shear strength. Hence steel rib support are recommended to continue.  The sequence of delay blasting by choosing 1 to 12 delay series of LD. The placement of LD’s in heading is shown below. This will control the amplitude of blasting and blasting is being done in sequences.
  • 12.  Two blasting were done in presence with maximum charge per delay approx. 10.3 kg and recorded induced ground vibration having peak particle velocity (PPV) near existing tunnel portal at Posoita end was found 5.65 mm/sec which is below 10mm/sec recommended for no effect on the existing nearby tunnel. The summary of blast vibration and Fast Fourier Transform Analysis (FFT) are as per the report attached. 10.0 Conclusion: The technical challenge of ensuring safety of the existing tunnel has been ensured by using vibration monitoring under the supervision of CSIR – CIMFR. Technique is basically to have the delay introduced in sequences of blasting so that peak particle velocity of shock waves generated after blasting should not exceed the permissible limit to the existing nearby structure which is in this case a old railway tunnel. The administrative challenge of execution in maoist area has been resolved by having regular meetings with the senior officials of Government of Jharkhand and under the 100% protection of the police. The tunnel work is likely to be completed by February, 2018 which was the most critical part of the project. The section is also likely to be commissioned in coming few months which will have large benefit to the Railways in de-congestion of the Howrah – Nagpur – Mumbai route. DELAY SERIES NUMBERING 1 to 12 IS SHOWN ABOVE