SlideShare a Scribd company logo
1 of 31
Execution of 680 m long tunnel ensuring safety of the adjoining
rail tunnel with controlled blasting and monitoring in maoist
affected zone of HDN route of S.E. Railway
By
Rajesh Prasad
Executive Director
Rail Vikas Nigam Limited
 680 m long tunnel execution.
 Monitoring of Vibration and Peak particle velocity in the
adjoining tunnel.
 Execution in LWE area.
GOELKERA – MONOHARPUR 3RD LINE
Length 27.5 Km
Phase-I (Posoita to Manoharpur) 11.6 KM
Phase –I Commissioned on 04.05.2016
Phase-II (Goelkera to Posoita) 15.9 KM
SCOPE
 RVNL Kolkata PIU is Implementing Agency
 M/s Unity-Triveni-BCPL (JV) are main Contractor.
 Central Institute of Mining & Fuel Research (CIMFR)
Roorkee - DDC (Cost Rs. 80 Lakh)
 M/s SNC-Lavalin - PMC. (Cost Rs. 2.7 Crores)
AGENCIES INVOLVED
TECHNICAL CHALLENGE
 3rd Line tunnel very close to the existing tunnel (c/c 31 m)
ADMINISTRATIVE CHALLENGE
 LWE affected area.
FEATURES IN TUNNEL EXECUTION
 Curves in Tunnel alignment :
305m , straight with two curves of 3° in approach.
Gradient - 1 in 100
 Size and Shape of Tunnel:
 Modified Horse Shoe shaped
 Excavation Height – 8.041m. & Width – 7.365m.
 Excavating by heading and benching method
 Controlled blasting technique
 Ventilation shaft
 Steel rib support in portal and weak rock area
 Steel fibre reinforced shotcrete (SFRS)
 Rock bolt
 Concrete Backfilling
 LED lighting
 Monitoring system (to ensure safety of the adjoining tunnel) for
the first time in IR
General complete cycle of tunnel excavation by drill and blast
Drilling
Survey
Bolt
Scale Dislodged
Ventilate
Blasting
Loading
ROCK BLASTING
Desirable Effects Unwanted Effects
• Breaking the rock mass
into desired shapes &
sizes.
• Displacing the broken
rock
• High Production/Pull
• Ground Vibration
• Air-blast
• Flyrock
• Over-Breakage
• Back break
• Damage to Rock Mass
• Cost escalation
• Increased cycle time
Rock strata encountered during execution tunnel
PHYLLITE ROCK
(Crack at 71º angle)
QUARTZITE ROCK
CARBONACEOUS SHALE
Tunnel excavation by Blasting
• The blast designs with MCD (Maximum
Charged density) of 14.0kg.
• Controlled blasting has been done
under guidance and direction of DDC i.e
CIMFR.
• Heading & benching method due to poor rock condition where stand up
time is not very high.
• Controlled blasting technique for the excavation of tunnel, trolley refuge,
ventilation shaft.
• Tunnel heading portion is approx. 26 Sq.m.
• Heading excavation is carried out by drilling (38 mm hole dia) with loading
of emulsion explosive of dia 32mm and blasting with a maximum pull 1.8m.
• Forepoles have been provided at immediate roof with the support of Steel
Ribs.
• Water seepage control - necessary arrangement of pumping of water.
• Depending upon Rock mass stand-up time, immediate support of 100 mm
thick reinforced shotcrete (SFRS) is being done by wet shotcrete machine.
• Approx. 12 nos to 14 nos of Rock bolting (3 m length) @ 1.5m c / c in
staggered way are provided.
• After rock bolts erection, steel ribs of ISMB 200 are placed @ 0.6m c / c
with 3.15 mm thick steel lagging before concrete back filling .
• Cement grouting is done between back fill concrete and rock surface area .
• Perforated PVC pipes are provided for weep holes at a spacing of 3.0 m
interval in staggered way to take care of surface seepage .
Heading Excavation
• Area of tunnel benching portion is approx. 25 Sq.m.
• Benching excavation is done when the heading face of tunnel is about
14 m to 15 m away.
• Excavation of benching part is also carried out through drilling and
blasting method with a maximum pull of 1.8 m by using controlled
blasting as per blasting design.
• After the benching, the side wall supports are fixed on wall beam of
ISMB 200.
• 100mm thickness of SFRS(Steel fibre reinforce shotcrete) is sprayed
before erecting Rock bolts.
• Minimum 4 to 6 nos. of rock bolts are provided below spring level
(benching portion) of the spacing between rock surface and steel ribs
and back filled with M20 Grade concrete by using concrete pump.
• Cement grouting is done before placing perforated PVC weep holes.
Benching
Explosive:
The latest generation emulsion explosive (power gel of ORICA make
having 25 mm dia ,200 mm long and 125 gm by weight ) with 80-90%
strength for blasting is used . The explosive is adequately sensitive,
powerful and safe. For initiation of non-electric detonators (also termed
as shock tube initiation system) of long delay is used. Afterwards Electric
detonators with long delay series (excel series) is being used in
underground tunnel blasting. 1.8 m deep blast hole is generally filled with
60% of emulsion explosive and remaining 40% length is filled by mud
stick.
LOADING OF EXPLOSIVE
Electronic Detonator
The sequence of delay blasting by choosing 1 to 12 delay series of LDD
(Long Delayed Detonator). The placement of LDD’s in heading is shown
below. By this, blastings were done in sequences and during each
blasting amplitude of shock waves was reduced to keep it within
permissible limit for safety of nearby existing tunnel.
Cross section of ED
Fixing of Electronic Detonator (LDD) for Blasting
VENTILATION SHAFT
A ventilation shaft (2.0 m dia) circular in shape at the
centre of the tunnel, i.e. at ch. 6300m has been provided.
The shaft is around 35m deep from exposed surface of
mountain to feed fresh air inside tunnel as well as natural
lighting to some extent.
STEEL RIBS
Specification of Steel Rib Support at Portal Area :
Type of Steel Rib : ISHB 200
Weight per meter : 0.366 kN
Cross-Section Area : 47.54 cm2
Spacing of rib : 100 cm at both the ends of tunnel
Plain Shotcrete : M20
Steel rib supports have generally been used for the portal zone
and inside the tunnel due to poor rock condition, except 160 m in
patches where the rock support has been given by shotcreting
only. ISHM 200 steel rib supports has been used. At back portion
of steel rib & between the rock surface, the gap has been filled up
by normal concrete so that full arch action could be generated for
stability of tunnel.
STEEL RIBS
Specification of Shotcrete in the Tunnel
Steel Fibre Reinforced Shortcrete (SFRS) of standard
mix was used with 28 days UCS (Uniaxial Crushing
Strength) of 50 Mpa and good bonding with the rock
surface.
FIBRE REINFORCED SHOTCRETE
SLOPE PROTECTION BY
FIXING WIREMESH
SLOPE PROTECTION BY
FIXING ROCK BOLT
SHOTCRETE AT APPROACHES
Rock Bolt
Specification of Rock Bolt in the Tunnel :
Length : 3.0 m
Diameter : 25mm tor steel
Base Plate Size : 15 cm x 15 cm
Thickness of Base Plate : 12mm
Pullout Capacity of bolt : More than or equal to 15 tones fully grouted
Spacing : Staggered systematic 1.5m centre to centre
Monitoring System
• Controlled blasting under
guidance of DDC.
• Monitoring system for
measuring vibration in the
existing tunnel during blasting
of 3rd line.
• Seismograph equipment was
installed in near by existing
tunnel wall during every
blasting to record the blasting
amplitude and frequency of
shock wave.
Inducespolarityofsignal
Longitudinal geophone (L)
Vertical geophone (V)
Transverse geophone (T)
The arrows indicate positive and negative ground motion represented by waveforms
TIME
+
+
+
-
-
-
+
T
+ V
+
L
-
-
-
Event
Standard Transducer
Ground Vibrations
V= Vertical
T= Transverse
L=Longitudinal
Microphone
Air Pressure
Monitoring Device
Limiting/Safe Value
PPV= 10mm/sec.
Noise = 146 dB
The summary of blast vibration
and Fast Fourier Transform
Analysis (FFT)
PPV = 4.572 mm/s< 10mm/sec.
Noise = 106.0 dB < 146 dB
Administrative Challenge
STATUS OF LAW AND ORDER CONDITION AS REFLECTION IN NEWS
PAPER (Dec. 2017)
पश्चिम स िंहभूम में िाईबा ा के पोड़ाहाट जिंगल के ोनुवा
थाना के कु दाबुरु गािंव के पा नक् सलयों ने िार ट्रैक्टर और
एक जे ीबी मशीन में आग लगा दी. आज ोमवार दोपहर
एक बजे के करीब नक् सलयों ने के नाल के ननमााण में ठेका
किं पनी के काम लगे इन भारी वाहनों व मशीन में आग लगाई.
घटना की जानकारी समलने के बाद िाईबा ा ए पी अनीश
गुप्ता और ऑपरेशन असभयान ए पी मनीष रमन िाईबा ा
े घटना स्थल पर पहुिंिे. दोनों पुसल अधिकाररयों ने घटना
स्थल पर पहुिंि जािंि की और पा के लोगों े पूछताछ की.
उन्हें घटना के बारे में कु छ महत्वपूणा जानकारी समली.
िाईबा ा ए पी ने अनीश गुप्ता ने बताया कक भाकपा
माओवादी के कमािंडर जीवन किं डुलना के दस्ते ने लेवी के सलए
घटना को अिंजाम ददया है.घटना के बारे में बताया गया कक
के नाल का ननमााण काया स्थल पर दोपहर एक बजे अिानक
बड़ी िंख्या में हधथयारों े लै नक् ली पिंहुिे और वाहनों में
आग लगा दी.
Law and Order is still an issue.
Execution in LWE area
• LWE – notified by Government of Jharkhand.
• Past History – armed miscreants attacked tunnel
camp. 19 nos. earth moving equipments,
excavators, compactors etc. were burnt at the
tunnel site.
• It has happened twice in the section.
• No Storage of explosive was permitted earlier.
• Subsequently after meeting of CRB with Hon’ble
CM Jharkhand on 06.12.2017, additional forces
have been deployed and night working has also
been permitted.
Work is being executed under 100% security cover of SAP posted
by State Government of Jharkhand
MOVEMENT AND STORAGE OF EXPLOSIVE
• The technical challenge of ensuring safety of the existing tunnel has
been met by using Vibration Monitoring System under the supervision
of CSIR – CIMFR.
• Technique is basically to have the delay introduced in sequence of
blasting so that peak particle velocity of shock waves generated after
blasting should not exceed the permissible limit in the existing nearby
tunnel with train operation in place.
• The administrative challenge of execution in maoist area has been
resolved by having regular meetings with the senior officials of
Government of Jharkhand and under the 100% protection of the force.
• The tunnel work is likely to be completed by March, 2018 which was
the most critical part of the project and the section is being
commissioned in coming few months to benefit in de-congestion of
the Howrah – Mumbai HDN route.
• For the first time in Indian Railways, this monitoring system has been
used to ensure safety of the existing tunnel while executing a new
tunnel for double line or third line project.
CONCLUSION
Team Work
TEAMWORK divides the TASK
and multiplies the SUCCESS
THANK YOU
31

More Related Content

What's hot

Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machineVISHAL KUMAR SINGH
 
Bucket wheel excavator ppt
Bucket wheel excavator pptBucket wheel excavator ppt
Bucket wheel excavator pptknowledge
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingMOHAMMED SOHEL AHMED
 
Blasting Vibration Assessment of Slopes_HKIE
Blasting Vibration Assessment of Slopes_HKIEBlasting Vibration Assessment of Slopes_HKIE
Blasting Vibration Assessment of Slopes_HKIEKeith Kong
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling pptSuman Paul
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation openingJyoti Khatiwada
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in miningEder Reyes
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blastingParth Desani
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machinerutuldave
 
Distribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilationDistribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilationSafdar Ali
 
Working with Dragline
Working with DraglineWorking with Dragline
Working with DraglineVR M
 
gps system and application in mining
gps system and application in mininggps system and application in mining
gps system and application in miningSATYABRATA NAYAK
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKAKeith Kong
 
Types of ventilation system
Types of ventilation systemTypes of ventilation system
Types of ventilation systemPranjal Sao
 

What's hot (20)

Tunneling by tunnel boring machine
Tunneling by tunnel boring machineTunneling by tunnel boring machine
Tunneling by tunnel boring machine
 
Bucket wheel excavator ppt
Bucket wheel excavator pptBucket wheel excavator ppt
Bucket wheel excavator ppt
 
Rock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock DrillingRock Drilling and Types of Rock Drilling
Rock Drilling and Types of Rock Drilling
 
Blasting Vibration Assessment of Slopes_HKIE
Blasting Vibration Assessment of Slopes_HKIEBlasting Vibration Assessment of Slopes_HKIE
Blasting Vibration Assessment of Slopes_HKIE
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)NATM-Time cycle presentation (2)
NATM-Time cycle presentation (2)
 
Blasting Gallery Method
Blasting Gallery MethodBlasting Gallery Method
Blasting Gallery Method
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation opening
 
depllaring in coal mines
depllaring in coal minesdepllaring in coal mines
depllaring in coal mines
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Drilling in mining
Drilling in miningDrilling in mining
Drilling in mining
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Mechanics of blasting
Mechanics of blasting Mechanics of blasting
Mechanics of blasting
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Distribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilationDistribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilation
 
Working with Dragline
Working with DraglineWorking with Dragline
Working with Dragline
 
gps system and application in mining
gps system and application in mininggps system and application in mining
gps system and application in mining
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKA
 
Types of ventilation system
Types of ventilation systemTypes of ventilation system
Types of ventilation system
 

Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningJasmeet Singh Saluja
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptxSubratDash37
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Rajesh Prasad
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptabhishek kulkarni
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxAbdulMannan357156
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 

Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly. (20)

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.ppt
 
07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
07 soil-grout threadbar
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Tunneling
Tunneling Tunneling
Tunneling
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 

More from Rajesh Prasad

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Rajesh Prasad
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdfRajesh Prasad
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLRajesh Prasad
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 Rajesh Prasad
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfRajesh Prasad
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21Rajesh Prasad
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...Rajesh Prasad
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Rajesh Prasad
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Rajesh Prasad
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalRajesh Prasad
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...Rajesh Prasad
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Rajesh Prasad
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Rajesh Prasad
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Rajesh Prasad
 

More from Rajesh Prasad (20)

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West Bengal
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
 
The RVNL Story 2019
The RVNL Story 2019The RVNL Story 2019
The RVNL Story 2019
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 

Recently uploaded (20)

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 

PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.

  • 1. Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of S.E. Railway By Rajesh Prasad Executive Director Rail Vikas Nigam Limited
  • 2.  680 m long tunnel execution.  Monitoring of Vibration and Peak particle velocity in the adjoining tunnel.  Execution in LWE area. GOELKERA – MONOHARPUR 3RD LINE Length 27.5 Km Phase-I (Posoita to Manoharpur) 11.6 KM Phase –I Commissioned on 04.05.2016 Phase-II (Goelkera to Posoita) 15.9 KM SCOPE  RVNL Kolkata PIU is Implementing Agency  M/s Unity-Triveni-BCPL (JV) are main Contractor.  Central Institute of Mining & Fuel Research (CIMFR) Roorkee - DDC (Cost Rs. 80 Lakh)  M/s SNC-Lavalin - PMC. (Cost Rs. 2.7 Crores) AGENCIES INVOLVED TECHNICAL CHALLENGE  3rd Line tunnel very close to the existing tunnel (c/c 31 m) ADMINISTRATIVE CHALLENGE  LWE affected area.
  • 3. FEATURES IN TUNNEL EXECUTION  Curves in Tunnel alignment : 305m , straight with two curves of 3° in approach. Gradient - 1 in 100  Size and Shape of Tunnel:  Modified Horse Shoe shaped  Excavation Height – 8.041m. & Width – 7.365m.  Excavating by heading and benching method  Controlled blasting technique  Ventilation shaft  Steel rib support in portal and weak rock area  Steel fibre reinforced shotcrete (SFRS)  Rock bolt  Concrete Backfilling  LED lighting  Monitoring system (to ensure safety of the adjoining tunnel) for the first time in IR
  • 4. General complete cycle of tunnel excavation by drill and blast Drilling Survey Bolt Scale Dislodged Ventilate Blasting Loading
  • 5. ROCK BLASTING Desirable Effects Unwanted Effects • Breaking the rock mass into desired shapes & sizes. • Displacing the broken rock • High Production/Pull • Ground Vibration • Air-blast • Flyrock • Over-Breakage • Back break • Damage to Rock Mass • Cost escalation • Increased cycle time
  • 6. Rock strata encountered during execution tunnel PHYLLITE ROCK (Crack at 71º angle) QUARTZITE ROCK CARBONACEOUS SHALE
  • 7. Tunnel excavation by Blasting • The blast designs with MCD (Maximum Charged density) of 14.0kg. • Controlled blasting has been done under guidance and direction of DDC i.e CIMFR. • Heading & benching method due to poor rock condition where stand up time is not very high. • Controlled blasting technique for the excavation of tunnel, trolley refuge, ventilation shaft.
  • 8. • Tunnel heading portion is approx. 26 Sq.m. • Heading excavation is carried out by drilling (38 mm hole dia) with loading of emulsion explosive of dia 32mm and blasting with a maximum pull 1.8m. • Forepoles have been provided at immediate roof with the support of Steel Ribs. • Water seepage control - necessary arrangement of pumping of water. • Depending upon Rock mass stand-up time, immediate support of 100 mm thick reinforced shotcrete (SFRS) is being done by wet shotcrete machine. • Approx. 12 nos to 14 nos of Rock bolting (3 m length) @ 1.5m c / c in staggered way are provided. • After rock bolts erection, steel ribs of ISMB 200 are placed @ 0.6m c / c with 3.15 mm thick steel lagging before concrete back filling . • Cement grouting is done between back fill concrete and rock surface area . • Perforated PVC pipes are provided for weep holes at a spacing of 3.0 m interval in staggered way to take care of surface seepage . Heading Excavation
  • 9. • Area of tunnel benching portion is approx. 25 Sq.m. • Benching excavation is done when the heading face of tunnel is about 14 m to 15 m away. • Excavation of benching part is also carried out through drilling and blasting method with a maximum pull of 1.8 m by using controlled blasting as per blasting design. • After the benching, the side wall supports are fixed on wall beam of ISMB 200. • 100mm thickness of SFRS(Steel fibre reinforce shotcrete) is sprayed before erecting Rock bolts. • Minimum 4 to 6 nos. of rock bolts are provided below spring level (benching portion) of the spacing between rock surface and steel ribs and back filled with M20 Grade concrete by using concrete pump. • Cement grouting is done before placing perforated PVC weep holes. Benching
  • 10. Explosive: The latest generation emulsion explosive (power gel of ORICA make having 25 mm dia ,200 mm long and 125 gm by weight ) with 80-90% strength for blasting is used . The explosive is adequately sensitive, powerful and safe. For initiation of non-electric detonators (also termed as shock tube initiation system) of long delay is used. Afterwards Electric detonators with long delay series (excel series) is being used in underground tunnel blasting. 1.8 m deep blast hole is generally filled with 60% of emulsion explosive and remaining 40% length is filled by mud stick. LOADING OF EXPLOSIVE
  • 11. Electronic Detonator The sequence of delay blasting by choosing 1 to 12 delay series of LDD (Long Delayed Detonator). The placement of LDD’s in heading is shown below. By this, blastings were done in sequences and during each blasting amplitude of shock waves was reduced to keep it within permissible limit for safety of nearby existing tunnel. Cross section of ED
  • 12. Fixing of Electronic Detonator (LDD) for Blasting
  • 13. VENTILATION SHAFT A ventilation shaft (2.0 m dia) circular in shape at the centre of the tunnel, i.e. at ch. 6300m has been provided. The shaft is around 35m deep from exposed surface of mountain to feed fresh air inside tunnel as well as natural lighting to some extent.
  • 14. STEEL RIBS Specification of Steel Rib Support at Portal Area : Type of Steel Rib : ISHB 200 Weight per meter : 0.366 kN Cross-Section Area : 47.54 cm2 Spacing of rib : 100 cm at both the ends of tunnel Plain Shotcrete : M20 Steel rib supports have generally been used for the portal zone and inside the tunnel due to poor rock condition, except 160 m in patches where the rock support has been given by shotcreting only. ISHM 200 steel rib supports has been used. At back portion of steel rib & between the rock surface, the gap has been filled up by normal concrete so that full arch action could be generated for stability of tunnel.
  • 16. Specification of Shotcrete in the Tunnel Steel Fibre Reinforced Shortcrete (SFRS) of standard mix was used with 28 days UCS (Uniaxial Crushing Strength) of 50 Mpa and good bonding with the rock surface.
  • 18. SLOPE PROTECTION BY FIXING WIREMESH SLOPE PROTECTION BY FIXING ROCK BOLT SHOTCRETE AT APPROACHES
  • 19. Rock Bolt Specification of Rock Bolt in the Tunnel : Length : 3.0 m Diameter : 25mm tor steel Base Plate Size : 15 cm x 15 cm Thickness of Base Plate : 12mm Pullout Capacity of bolt : More than or equal to 15 tones fully grouted Spacing : Staggered systematic 1.5m centre to centre
  • 20. Monitoring System • Controlled blasting under guidance of DDC. • Monitoring system for measuring vibration in the existing tunnel during blasting of 3rd line. • Seismograph equipment was installed in near by existing tunnel wall during every blasting to record the blasting amplitude and frequency of shock wave.
  • 21. Inducespolarityofsignal Longitudinal geophone (L) Vertical geophone (V) Transverse geophone (T) The arrows indicate positive and negative ground motion represented by waveforms TIME + + + - - - + T + V + L - - - Event Standard Transducer Ground Vibrations V= Vertical T= Transverse L=Longitudinal Microphone Air Pressure Monitoring Device Limiting/Safe Value PPV= 10mm/sec. Noise = 146 dB
  • 22.
  • 23. The summary of blast vibration and Fast Fourier Transform Analysis (FFT) PPV = 4.572 mm/s< 10mm/sec. Noise = 106.0 dB < 146 dB
  • 24. Administrative Challenge STATUS OF LAW AND ORDER CONDITION AS REFLECTION IN NEWS PAPER (Dec. 2017) पश्चिम स िंहभूम में िाईबा ा के पोड़ाहाट जिंगल के ोनुवा थाना के कु दाबुरु गािंव के पा नक् सलयों ने िार ट्रैक्टर और एक जे ीबी मशीन में आग लगा दी. आज ोमवार दोपहर एक बजे के करीब नक् सलयों ने के नाल के ननमााण में ठेका किं पनी के काम लगे इन भारी वाहनों व मशीन में आग लगाई. घटना की जानकारी समलने के बाद िाईबा ा ए पी अनीश गुप्ता और ऑपरेशन असभयान ए पी मनीष रमन िाईबा ा े घटना स्थल पर पहुिंिे. दोनों पुसल अधिकाररयों ने घटना स्थल पर पहुिंि जािंि की और पा के लोगों े पूछताछ की. उन्हें घटना के बारे में कु छ महत्वपूणा जानकारी समली. िाईबा ा ए पी ने अनीश गुप्ता ने बताया कक भाकपा माओवादी के कमािंडर जीवन किं डुलना के दस्ते ने लेवी के सलए घटना को अिंजाम ददया है.घटना के बारे में बताया गया कक के नाल का ननमााण काया स्थल पर दोपहर एक बजे अिानक बड़ी िंख्या में हधथयारों े लै नक् ली पिंहुिे और वाहनों में आग लगा दी. Law and Order is still an issue.
  • 25. Execution in LWE area • LWE – notified by Government of Jharkhand. • Past History – armed miscreants attacked tunnel camp. 19 nos. earth moving equipments, excavators, compactors etc. were burnt at the tunnel site. • It has happened twice in the section. • No Storage of explosive was permitted earlier. • Subsequently after meeting of CRB with Hon’ble CM Jharkhand on 06.12.2017, additional forces have been deployed and night working has also been permitted.
  • 26. Work is being executed under 100% security cover of SAP posted by State Government of Jharkhand
  • 27. MOVEMENT AND STORAGE OF EXPLOSIVE
  • 28.
  • 29. • The technical challenge of ensuring safety of the existing tunnel has been met by using Vibration Monitoring System under the supervision of CSIR – CIMFR. • Technique is basically to have the delay introduced in sequence of blasting so that peak particle velocity of shock waves generated after blasting should not exceed the permissible limit in the existing nearby tunnel with train operation in place. • The administrative challenge of execution in maoist area has been resolved by having regular meetings with the senior officials of Government of Jharkhand and under the 100% protection of the force. • The tunnel work is likely to be completed by March, 2018 which was the most critical part of the project and the section is being commissioned in coming few months to benefit in de-congestion of the Howrah – Mumbai HDN route. • For the first time in Indian Railways, this monitoring system has been used to ensure safety of the existing tunnel while executing a new tunnel for double line or third line project. CONCLUSION
  • 30. Team Work TEAMWORK divides the TASK and multiplies the SUCCESS