The document describes a sample PMP exam question and answer about resource management. It provides a scenario where a project leader has ordered materials, equipment, and secured space to test a solar cell design. The question asks what has been accomplished by these efforts. The answer is that physical resource assignments have been made, which is an output of the Acquire Resources process and documents what materials, equipment, locations and other physical resources will be used in the project. The document encourages trying a free PMP exam simulator to practice more questions.