Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are leading a project to design a high-efficiency solar cell. The materials that you are acquiring for this
project include copper, silver, and silicon among others, and you have also ordered custom built
manufacturing equipment. Additionally, you have secured permission from the landlord to install a solar
array on the roof of the corporate office for testing, and reserved a conference room for daily stand-up
meetings. What is the result of your efforts?
A. Resource histogram
B. Resource management plan
C. Resource assignment matrix
D. Physical resource assignments
HINT: What output of the Acquire Resources process describes the physical resources reserved for the
project?
Question
3. The correct answer is D
It can be inferred from the question that the process of acquiring resources is being performed.
One of the outputs from the Acquire Resources process is physical resource assignments.
Documentation of the physical resource assignments records the material, equipment, supplies,
locations, and other physical resources that will be used during the project. Based on the
description provided by the question, the physical resource assignments is what has been
accomplished.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.