SlideShare a Scribd company logo
1 of 18
Download to read offline
By
R.NAGARAJAPRASATH, B.E(Mech), BOE
SHANTI GD ISPAT & POWER PVT LTD, CHATTISGARH
CFBC Vs AFBC
HEAT TRANSFER IN CFBC WATER
WALL
o Case Study On Husk Firing In CFBC
o Importance of loop seal air nozzle arrangement.
o Panel super heater failure in CFBC.
CASE STUDIES
The CFBC boiler was supplied by a Chinese company has been
operated for a year. Boiler was designed for 80% Rice husk + 20
% Indian coal / 100% Indian coal. Boiler parameters are 75 TPH,
90 Kg/cm2, 515 Deg C with the feed water temperature of 190
Deg C.
CASE STUDY ON HUSK FIRING IN CFBC
Cracks developed in cyclone outlet cone
CASE STUDY ON HUSK FIRING IN CFBC
CASE STUDY ON HUSK FIRING IN CFBC
CASE STUDY ON HUSK FIRING IN CFBC
IMPORTANCE OF LOOP SEAL AIR NOZZLE
ARRANGEMENT
Loop is mechanical device which transfers the un-combusted
(coarser) particles to the furnace, which was collected by cyclone.
It transfers the ash particles from low pressure cyclone to the high
pressure combustor. It protects the direct flow of flue gas from
furnace to cyclone.
There are two types of air nozzles were provided in loop seal. The
purpose of nozzle types is to shift the collected ash back to
furnace and also to control the gas bye-passing from furnace to
cyclone. Down leg side nozzles were provided for aeration
purpose only and in the riser leg side nozzles were provided for
fluidization purpose.
If loopseal air nozzles were erected in wrong manner then this
cause in boiler loading because ash will not transferred from
cyclone to furnace.
IMPORTANCE OF LOOP SEAL AIR NOZZLE
ARRANGEMENT
IMPORTANCE OF LOOP SEAL AIR NOZZLE
ARRANGEMENT
The is the philosophy of loop seal design by Foster wheeler.
IMPORTANCE OF LOOP SEAL AIR NOZZLE
ARRANGEMENT
The CFBC boiler was supplied by a Chinese company has been
operated for 3 years. Boiler was designed for 100%
Imported/Indian coal. Boiler parameters are 130 TPH, 100
Kg/cm2, 540 Deg C & feed water temperature is 180 Deg C. The
arrangement is shown in below
One and half year after commissioning they were faced frequent
failure in panel super heater tubes. Due to the frequent failure in
panel super heater tubes they can’t able to run the boiler more
than a month continuously. Especially failure was occurred in
bottom of super heater. Arrangement of panel super heater was
shown in photo-02. At the time of visit boiler was in operating
condition. However failed tubes were available for inspection. In
my presence boiler was stopped due to panel super heater failure,
boiler was inspected from inside.
PANEL SUPERHEATER FAILURE IN CFBC
PANEL SUPERHEATER FAILURE IN CFBC
Reason for Failure,
1. From the available failed tube, it
was understood that the anchoring
arrangement was not proper to hold
the refractory. They do not have the
anchors at bottom and at front.
2. Tubes are provided with 6mm dia x
30mm long studs.
3. Due to that insufficient anchoring,
refractory may fail from the first
firing itself. After refractory
falling, tubes were start eroding
from bottom.
PANEL SUPERHEATER FAILURE IN CFBC
Failed tubes, shows no anchors in
bend
New studs added with modified
arrangement.
PANEL SUPERHEATER FAILURE IN CFBC
Thickness measured in the outer coil during the shutdown time. Tube
thickness was observed 2.83mm against the original thickness of 5mm.
Recommendation,
1. For the proper holding of refractory, more studs were added
additionally with the existing stud arrangement.
2. New studs also with the same dimension.
3. Phosphate bonded high alumina castable was applied over a
coil up to the tip only. Phoscast will give better life in the high
velocity & high erosive zone also. This was practically
experienced in AFBC boilers.
PANEL SUPERHEATER FAILURE IN CFBC
SEE YOU WITH NEW
CASE STUDIES
THANK YOU !!!

More Related Content

What's hot

Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
Kongkiert Tankayura
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
SHIVAJI CHOUDHURY
 

What's hot (20)

Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
MILL performance.ppt
MILL performance.pptMILL performance.ppt
MILL performance.ppt
 
Circulating Fluidized Bed Boiler (cfb) training module
Circulating Fluidized Bed Boiler (cfb) training module Circulating Fluidized Bed Boiler (cfb) training module
Circulating Fluidized Bed Boiler (cfb) training module
 
WUXI MAKE CFBC BOILER COLD CYCLONE
WUXI MAKE CFBC BOILER COLD CYCLONEWUXI MAKE CFBC BOILER COLD CYCLONE
WUXI MAKE CFBC BOILER COLD CYCLONE
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
The Coal mill performance monitoring
The Coal mill performance monitoringThe Coal mill performance monitoring
The Coal mill performance monitoring
 
Boiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of LossesBoiler Efficiency Improvement through Analysis of Losses
Boiler Efficiency Improvement through Analysis of Losses
 
Air heater
Air heaterAir heater
Air heater
 
Boiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plantBoiler auxillaries in a coal fired power plant
Boiler auxillaries in a coal fired power plant
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater control
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Boiler circulation theory
Boiler circulation theoryBoiler circulation theory
Boiler circulation theory
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 

Viewers also liked

The technological properties of refractory
The technological properties of refractory The technological properties of refractory
The technological properties of refractory
Ahmed Abd Elmegeed
 

Viewers also liked (20)

Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Boiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP BoilerBoiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP Boiler
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
 
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient Steam Systems -
 
Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Boiler Water Treatment -
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
 
Boiler Performance Monitoring
Boiler Performance MonitoringBoiler Performance Monitoring
Boiler Performance Monitoring
 
Non mechanical valves
Non mechanical valvesNon mechanical valves
Non mechanical valves
 
Pengolahan keramik 1
Pengolahan keramik 1Pengolahan keramik 1
Pengolahan keramik 1
 
Optimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas AnalyserOptimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas Analyser
 
The technological properties of refractory
The technological properties of refractory The technological properties of refractory
The technological properties of refractory
 
Javanotes
JavanotesJavanotes
Javanotes
 
System design
System designSystem design
System design
 
Module 5 2010
Module 5 2010Module 5 2010
Module 5 2010
 

Similar to Case Studies on CFBC Boilers

Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agrium
Satria Sakata
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
Pooja Agarwal
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
Rohit Meena
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
drazil
 

Similar to Case Studies on CFBC Boilers (20)

Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boiler
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
 
Case studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthibanCase studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthiban
 
Aiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agriumAiche 42-024-primary reformer failure- agrium
Aiche 42-024-primary reformer failure- agrium
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
ppt. clg
ppt. clgppt. clg
ppt. clg
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
Failure in synthesis converter
Failure in synthesis converterFailure in synthesis converter
Failure in synthesis converter
 
boilers
boilersboilers
boilers
 
B.tech i eme u 2 steam boilers
B.tech i eme u 2 steam boilersB.tech i eme u 2 steam boilers
B.tech i eme u 2 steam boilers
 
B.tech i eme u 2 steam boilers
B.tech i eme u 2 steam boilersB.tech i eme u 2 steam boilers
B.tech i eme u 2 steam boilers
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 
Cochran Boiler
Cochran Boiler Cochran Boiler
Cochran Boiler
 
Cement Plant visit report with photographs
Cement Plant visit report with photographsCement Plant visit report with photographs
Cement Plant visit report with photographs
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 
Boiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yetBoiler & co generation presentation finished not yet
Boiler & co generation presentation finished not yet
 

Recently uploaded

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 

Recently uploaded (20)

Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 

Case Studies on CFBC Boilers

  • 1. By R.NAGARAJAPRASATH, B.E(Mech), BOE SHANTI GD ISPAT & POWER PVT LTD, CHATTISGARH
  • 3. HEAT TRANSFER IN CFBC WATER WALL
  • 4. o Case Study On Husk Firing In CFBC o Importance of loop seal air nozzle arrangement. o Panel super heater failure in CFBC. CASE STUDIES
  • 5. The CFBC boiler was supplied by a Chinese company has been operated for a year. Boiler was designed for 80% Rice husk + 20 % Indian coal / 100% Indian coal. Boiler parameters are 75 TPH, 90 Kg/cm2, 515 Deg C with the feed water temperature of 190 Deg C. CASE STUDY ON HUSK FIRING IN CFBC Cracks developed in cyclone outlet cone
  • 6. CASE STUDY ON HUSK FIRING IN CFBC
  • 7. CASE STUDY ON HUSK FIRING IN CFBC
  • 8. CASE STUDY ON HUSK FIRING IN CFBC
  • 9. IMPORTANCE OF LOOP SEAL AIR NOZZLE ARRANGEMENT
  • 10. Loop is mechanical device which transfers the un-combusted (coarser) particles to the furnace, which was collected by cyclone. It transfers the ash particles from low pressure cyclone to the high pressure combustor. It protects the direct flow of flue gas from furnace to cyclone. There are two types of air nozzles were provided in loop seal. The purpose of nozzle types is to shift the collected ash back to furnace and also to control the gas bye-passing from furnace to cyclone. Down leg side nozzles were provided for aeration purpose only and in the riser leg side nozzles were provided for fluidization purpose. If loopseal air nozzles were erected in wrong manner then this cause in boiler loading because ash will not transferred from cyclone to furnace. IMPORTANCE OF LOOP SEAL AIR NOZZLE ARRANGEMENT
  • 11. IMPORTANCE OF LOOP SEAL AIR NOZZLE ARRANGEMENT The is the philosophy of loop seal design by Foster wheeler.
  • 12. IMPORTANCE OF LOOP SEAL AIR NOZZLE ARRANGEMENT
  • 13. The CFBC boiler was supplied by a Chinese company has been operated for 3 years. Boiler was designed for 100% Imported/Indian coal. Boiler parameters are 130 TPH, 100 Kg/cm2, 540 Deg C & feed water temperature is 180 Deg C. The arrangement is shown in below One and half year after commissioning they were faced frequent failure in panel super heater tubes. Due to the frequent failure in panel super heater tubes they can’t able to run the boiler more than a month continuously. Especially failure was occurred in bottom of super heater. Arrangement of panel super heater was shown in photo-02. At the time of visit boiler was in operating condition. However failed tubes were available for inspection. In my presence boiler was stopped due to panel super heater failure, boiler was inspected from inside. PANEL SUPERHEATER FAILURE IN CFBC
  • 14. PANEL SUPERHEATER FAILURE IN CFBC Reason for Failure, 1. From the available failed tube, it was understood that the anchoring arrangement was not proper to hold the refractory. They do not have the anchors at bottom and at front. 2. Tubes are provided with 6mm dia x 30mm long studs. 3. Due to that insufficient anchoring, refractory may fail from the first firing itself. After refractory falling, tubes were start eroding from bottom.
  • 15. PANEL SUPERHEATER FAILURE IN CFBC Failed tubes, shows no anchors in bend New studs added with modified arrangement.
  • 16. PANEL SUPERHEATER FAILURE IN CFBC Thickness measured in the outer coil during the shutdown time. Tube thickness was observed 2.83mm against the original thickness of 5mm.
  • 17. Recommendation, 1. For the proper holding of refractory, more studs were added additionally with the existing stud arrangement. 2. New studs also with the same dimension. 3. Phosphate bonded high alumina castable was applied over a coil up to the tip only. Phoscast will give better life in the high velocity & high erosive zone also. This was practically experienced in AFBC boilers. PANEL SUPERHEATER FAILURE IN CFBC
  • 18. SEE YOU WITH NEW CASE STUDIES THANK YOU !!!