SlideShare a Scribd company logo
1 of 11
Download to read offline
Primary Reformer Failure 
The Agrium Fort Saskatchewan Nitrogen Operations experienced a massive reformer failure 
following a short maintenance outage and routine startup. The events which led up to the failure, 
the methodology, scheduling and alterations made to bring the reformer back online, and the 
safeguards incorporated to lessen future occurrences of this type of failure are discussed. 
D. H. Timbres and Mark McConnell 
Agrium Fort Saskatchewan, Alberta, Canada 
Introduction 
At the Agrium Fort Saskatchewan Nitrogen 
Operations in Fort Saskatchewan, Alberta, 
Canada on Nov. 16-17, 1998, a massive 
reformer failure was experienced. This failure followed 
a short maintenance outage and what was considered a 
routine plant restart. Almost all the catalyst tubes failed 
in the radiant section, and the air-steam preheat coil 
No. 1 (shield coil) was damaged. This resulted in 39 
days of lost production in the ammonia plant and 40 
days lost production in the urea plant. 
The events which lead up to the failure, the method-ology, 
scheduling and alterations made to bring the 
reformer furnace back on line, and the safeguards 
incorporated to lessen future occurrences of this type of 
failure are discussed in this article. 
Background 
Agrium Inc. is a leading global producer and mar-keter 
of fertilizer and a major retail supplier of agricul-tural 
products and services in both North America and 
Argentina. The Corporation produces and markets four 
primary groups of fertilizers: nitrogen, phosphate, 
potash, and sulfur. 
Agrium, Fort Saskatchewan Nitrogen Operations 
was commissioned in 1983 and produces ammonia and 
urea fertilizer for the Western Canadian and export 
markets. The site comprises a 1,000 metric ton per day 
nameplate Kellogg ammonia plant and a 907 metric ton 
per day Stamicarbon urea plant. Current operating 
capacities are 1,350 metric tons per day ammonia and 
1,280 metric tons per day urea. 
The primary reformer furnace in the ammonia plant 
is a Kellogg design with 260 radiant tubes, 5 radiant 
tube rows, with 52 tubes per row. The radiant tubes 
were HP-Nb modified material and installed over a 
period of 1991 to 1993, with the majority (207 out of 
260) of the tube installed new in 1993. The reformer 
furnace layout is shown in Figures 1 and 2. 
There are six arch burner rows with 22 burners per 
row for a total of 132 arch burners. In addition there are 
six tunnel burners, which are not operated, and 13 
steam superheater burners. 
The convection section consists of three coils in the 
"hot leg," the air-steam shield coil, the main air-steam 
coil, and the mixed feed preheat coil. In the "cold leg," 
there are four coils, the steam superheat coil, the 
feedgas coil, the boiler feed water preheat coil, and the 
fuel gas preheat coil. All aforementioned coils are in 
the exit heat direction. 
Primary Reformer Startup Procedure 
The plant procedure for startup consists of introduc-ing 
a nitrogen purge to the front-end by means of tem-porary 
hose connections to the following locations: 
• Purging the process gas line, 
• Purging the steam to process line, and 
AMMONIA TECHNICAL MANUAL 268 2002
Figure 1. Plant overview (primary reformer at left). 
Figure 2. Closeup of primary reformer furnace. 
AMMONIA TECHNICAL MANUAL 269 2002
ARCH BURNER FIRING PATTERN 
NORTH 
ROW #6 ROW #5 ROW #4 ROW #3 
61 
41 
51 
43 
53 
WEST 45 
55 
47 
57 
49 
59 
* • 33 
* 
• 5 
•• 
35 
•• 
9 
•• 
21 
•• 
17 
•• 
29 
•• 
25 
• 
• 1 
• • 13 
• • 66 
• 63 
• • 37 
•• 
11 
• 
• 39 
•• 
15 
•• 
7 
•• 
27 
•• 
3 
•• 
23 
•• 
31 
•• 
19 
• 
• 
• 20 
• 
• 32 
• • 24 
• • 4 
• 
• 28 
• 
• 8 
•• 
16 
•• 
36 
• 
• 12 
•• 38 
•• 
64 
ROW #2 
• 65 
• • 41 
• • 2 
•• 
26 
•• 
30 
• 
• 40 
•• 
18 
• 
• 10 
•• 
34 
•• 
6 
• 
• 22 
• 
ROW#1 
• 
• 60 
50 
58 
48 
• 56 
. EAST 
• 46 
•• 
54 
•• 
44 
• 
• 52 
• • 42 
• • 62 
SOUTH 
AFTER BURNER NUMBER 66 
IS REQUIRED WHEN ADDING 
IS LIT, NO SET 
ADDITIONALB 
PATTERN 
URNERS. 
Figure 3. Arch burner firing pattern. 
AMMONIA TECHNICAL MANUAL 270 2002
• Purging the steam to air coil line. 
The operators follow an arch burner-firing pattern 
(see Figure 3) with a warmup rate of 100°C/h 
(212°F/h). 
The radiant box is preheated by lighting specific arch 
burners between each of the radiant tube rows until the 
flue-gas temperature reaches 400°C (752°F), following 
which steam is introduced into the radiant tubes. By 
preheating, you prevent condensation of the steam on 
the cold tubes/catalyst. Also, you minimize tempera-ture 
shock of hot steam on cold catalyst. 
At a 400"C (752°F) flue-gas temperature, steam is 
introduced to the process at 40% rate. The temperature 
is then steadily increased by lighting more arch burners 
until the exit tube temperature reaches 700°C 
(1,292°F), at which point natural gas is introduced to 
the process. 
Additional arch burners are then lit. 
At 750-800°C (1,382-1,472°F) flue-gas temperature, 
air is introduced to the secondary reformer. When light 
off has been confirmed by a temperature rise across the 
secondary reformer, the system is gradually brought to 
up operating conditions. 
From Nov. 16 through Nov. 17, 1998, the primary 
reformer furnace was already in a warm condition with 
a flue-gas temperature of just under 400°C (752°F). 
Night shift was continuing to warm up and was getting 
ready to introduce steam at 400°C (752°F). 
The panel operator directed the field operator to light 
additional arch burners to warm up the reformer. The 
field operator did this exact operation a number of 
times over the next few hours. 
What was later discovered was that the field operator 
did not perform checks inside the radiant box after 
lighting the additional burners. That is, the field opera-tor 
did not visually look at the burner(s) that had been 
lit to confirm there was no flame impingement on the 
tubes and to visually confirm the tubes were not exces-sively 
hot. 
In addition, the panel operator was incorrectly 
observing the transfer header outlet temperature 
instead of the flue-gas temperature. 
So as additional arch burners were being lit, the tem-perature 
in the radiant box continued to rise, but, as yet, 
no steam had been introduced to the radiant tubes. 
At about 10:35 PM on Nov. 16, steam should have 
been introduced into the radiant tubes. 
At about 2:47 AM the next morning, the field opera-tors 
looked inside the radiant box, and observed the 
catalyst tubes were a glowing bright yellow and dis-continued 
firing. It was later noted that the flue-gas 
temperature had reached a maximum value of 1,071°C 
(1,960°F). [The melting point is typically quoted at 
about 1,343°C (2,426°F) and complete melting will be 
finished at 1,400°C (2,552°F), respectively known as 
the solidus and liquidus melting temperatures ("the 
range of melting"). It is probable that localized flue-gas 
temperatures were much higher than temperatures 
reported by thermocouples at the outlet of the radiant 
box. Uneven firing or the relatively high air leakage 
rate at low firing rates could cause this.] 
The time line for the temperature and number of 
burners lit is shown in Figure 4. 
Description of Damage 
Following a cool down of the primary reformer fur-nace, 
further observations within the radiant box 
showed that approximately 50% of the tubes had com-pletely 
failed. Tube failure was observed mainly at 
welds. Molten metal had solidified within the radiant 
tube catalyst. See Figures 5, 6 and 7. 
No risers had failed, but overheating was evident. 
See Figure 8. 
In the "hot leg" of the convection section, the air-steam 
preheat coil No. 1 (shield coil) showed evidence 
of overheating and distortion. See Figure 9 and 10. 
None of the tubes had ruptured, however. The air-steam 
No. 2 coil was intact with no evidence of damage, as 
was the mixed feed coil. 
In the "cold leg" of the convection section, none of 
the four coils (steam superheat, feedgas preheat, boiler 
feedwater preheat, and the fuel gas preheat coils) were 
damaged. 
Some minor damage was noted to the radiant furnace 
wall insulation and refractory. 
Repairs to Primary Reform Furnace 
On Nov. 17, 1998, a management team was assem-bled 
to conduct the demolition and repairs to the pri-mary 
reform furnace and air-steam preheat coil No. 1 
(shield coil), and to bring the plant online as soon as 
AMMONIA TECHNICAL MANUAL 271 2002
Timeline of the November 16-17,1998 Incident 
1200 
1000 - 
g 
S 
Nw16 Nov-16 Nov-16 Nov-16 Nov-16 Nov-16 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 
21:00 21:30 22:00 22:30 23:00 23:30 00:00 00:30 01:00 01:30 02:00 02:30 03:00 
Transfer Header Temperature (TI-2179) -Flue Gas Temperature (Tl-2119) • Number of Burners 
Figure 4. Time line for temperature and number of burners lit. 
Figure 5. Overview of failed radiant tubes. 
AMMONIA TECHNICAL MANUAL 272 2002
Figure 6. Closeup view of failed radiant tubes. 
Figure 7. Molten metal found within the radiant tube catalyst. 
AMMONIA TECHNICAL MANUAL 273 2002
Figure 8. Riser tubes (riser tube on right has been mechanically cut for 
removal). 
Figure 9. Overview of air-steam preheat coil No. 1 (shield coil) damage. 
AMMONIA TECHNICAL MANUAL 274 2002
Figure 10. Another overview of damage to air-steam preheat coil No. 1 (shield 
coil). 
possible. In addition, since a scheduled maintenance 
turnaround had been planned for the following June 
(1999), those additional maintenance items were 
brought forward for completion at the same time as the 
major repair. 
Because of the magnitude of the problem, Kellogg 
Brown and Root (KBR) were contacted for assistance. 
To oversee progress in procurement and expediting, an 
Agrium senior purchasing agent was placed in the 
KBR office in Houston. The senior purchasing agent 
traveled to KBR on November 18, 1998. The decision 
was made early hi the repair process to replace all 260 
radiant tubes, all 5 riser tubes, all 5 outlet manifolds, 
and all radiant tube spring hangers. This decision was 
made despite the observation that some radiant tubes 
still remained intact. Time was of the essence and the 
management team felt there was not time to test radiant 
tubes, riser and collection manifolds for usefulness. 
On Nov. 18, 1998 after senior Agrium management 
and Agrium's insurance agents had viewed the damage, 
blinding and scaffolding started as the first stage of 
demolition. A local contractor was hired to commence 
removal of damaged items from the radiant box. 
For the major work, a second local company was 
hired to set the stage for repairs, plus do additional 
work on the convection section of the furnace. 
By Nov. 21, 1998, KBR, with input from Agrium, 
had narrowed vendors for the cast radiant tubes, cast 
risers, and new cast collection headers to two vendors 
(one in the U.K. and the other in the U.S.). Two ven-dors 
were considered optimum due to the fast supply 
and delivery each offered. Placing the order with one 
vendor would have increased delivery time. 
Demolition was well underway at this point. 
On Nov. 22, 1998 a letter of intent was sent to the 
first vendor, and 114 radiant tubes, 6 risers, and 5 col-lection 
headers with the second vendor. This supplier 
provided 10 extra radiant tubes and one extra riser tube. 
The arrangement with the two suppliers guaranteed an 
initial receipt of radiant tubes by Dec. 10, 1998 (3 
weeks and two days after the incident) and final deliv-ery 
of materials by Dec. 20, (4.5 weeks after the inci-dent) 
allowing a staged-in repair. 
To help expedite the replacement radiant parts, the 
AMMONIA TECHNICAL MANUAL 275 2002
Agrium management team became aware very early on 
in the procurement process that one part of the radiant 
tube replacement was going to be a bottleneck. That 
part was the top of the radiant tube known as the tube 
top. The tube top is essentially the inlet section of the 
radiant tube, made entirely of wrought components. 
To meet early delivery schedules, the tube tops were 
removed from all damaged radiant tubes. As well, 
Agrium had in inventory 20 complete spare radiant 
tubes, and all the tube tops were cut off from the inven-tory 
tubes and sent to the vendors as well. The addi-tional 
tube tops were insurance against any unusable 
tube tops that might surface in inspection and/or 
assembly of the new replacement radiant tubes. 
Again, Agrium personnel were sent to the two 
respective vendors facilities to expedite manufacturing 
and delivery of radiant tubes, risers and collection 
headers. 
The transition assemblies (between riser and outlet 
transfer header) were contracted to a third vendor, and 
the air-steam preheat coil No. 1 (shield coil), including 
intermediate tube supports, was contracted to a fourth 
company. Both the latter were located in the U.S. and 
delivery was scheduled as soon as individual items 
were fabricated. Also, delivery was timed to coincide 
with the delivery of the cast radiant components. 
Due to some long-term process requirements for the 
radiant section of the furnace, replacement tubes were 
made with a slightly larger internal diameter (from 4.0 
in. ID to 4.3 in. ID) and the tube metallurgy of the radi-ant 
tubes was changed from HP-Nb modified to HP-Nb 
microalloy material. (This larger internal diameter 
change in the radiant tube decreased the pressure drop.) 
The riser tubes remained as HP-Nb modified materi-al 
with no alteration in physical dimensions. 
The outlet collection headers were altered from 
wrought Incoloy 800HT to the cast equivalent. 
In addition to the physical components, none of the 
radiant tube catalyst was recovered, and new replace-ment 
catalyst was purchased. The catalyst replacement 
was unidense loaded. To facilitate the quick delivery, 
the 156 radiant tubes from the U.K. vendor had to be 
air freighted to Canada hi three airfreight loads. A 
freight forwarder was hired to contract the Russian 
built planes to haul the materials to Canada. Figures 11, 
12 and 13 show the type of aircraft, the stacking of 
tubes hi the plane hold and the unloading of the radiant 
tubes at Edmonton, Alberta, Canada for transport to 
Fort Saskatchewan (a distance of 50 miles). 
Due to sequential delivery of items, all radiant tubes 
were individually stabbed into the furnace. See Figure 
14. There was no time for building harps outside the 
furnace and then installing completed harps into the 
furnace. 
The replacement schedule was organized for 2-10 h 
shifts 7 days a week, with 4 h for any X-ray work. All 
welded joints were X-rayed. 
Following installation of each complete row of radi-ant 
tubes (and riser and transition can assemblies), the 
catalyst was loaded into the radiant tubes and the pres-sure 
drop readings completed. This was done while 
construction continued on other rows, until all five 
rows of radiant tubes (and riser and transitions can 
assemblies) were completed. 
Following along with the repairs to the radiant sec-tion, 
the air-steam preheat coil No. 1 (shield coil) was 
repaired. 
All mechanical work was completed by Dec. 22, 
1998. 
Scaffolding and blinds were removed by Dec. 23, 
1998 and the major contractor demobilized. Preheating 
commenced Dec. 24, 1998, and, by early Dec. 26, 
1998, ammonia production began - just 39 days after 
the initial damage to the furnace. 
The job was completed with no lost tune injuries or 
serious medical injuries. 
Corrective Actions 
Following the repairs and startup of the plant opera-tions, 
a full enquiry was undertaken as to the cause of 
the failure. This enquiry resulted hi the following cor-rective 
actions: 
• It is mandatory to have an overall operations coor-dinator 
during startup. 
• It is mandatory to have two operators on the panel 
during startup. 
• Log books would be kept of each area of the plant 
to improve communication between crews. 
• Written procedures for lighting burners. 
• An automatic shutdown system was installed to 
protect against overheating during, startup. (The ammo-nia 
plant did have a high temperature shutdown system 
AMMONIA TECHNICAL MANUAL 276 2002
Figure 11. Russian cargo plane used to transport radiant tubes 
from U.K. to Canada. 
Figure 12. Packaging of radiant tubes in hold of Russian plane. 
Figure 13. Offloading of radiant tubes at Edmonton 
International Airport for transfer to Fort Saskatchewan. 
AMMONIA TECHNICAL MANUAL 277 2002
Figure 14. Stabbing of tubes into pri-mary 
reformer furnace. 
on the process side. As there was little flow from the 
nitrogen purge, this system did not "see" the high tem-peratures. 
The new system is designed specifically to 
look at flue-gas temperatures (voting system) and 
steam flow (voting system) and trip if temperature is 
too high with low steam flow). 
Closing Comments 
• The automatic protective systems in an ammonia 
plant may not adequately protect equipment during 
startup conditions. 
• Common practice at the Fort Saskatchewan plant 
was to rely on procedures to protect the plant during 
startup. 
• When relying on procedures, all necessary steps 
should be taken to ensure they will be correctly fol-lowed. 
• The importance of field checks must be reinforced 
to the operators. 
• If the negative consequences of a procedure not 
being followed are too great to accept, the need for 
additional layers of protection into the system should 
be considered. This could mean designing an automat-ic 
trip system. 
QUESTIONS AND ANSWERS 
Rob Gommans, Gommons Metallurgical Services: 
Were tubes protected from de-icing salts during road 
transport? 
D. EL Timbres, Agrium: Yes. For road transportation, 
all the catalyst tube openings were protected with 
flange protectors, and plastic caps over the inlet and 
outlet pigtails.The catalyst tube assembly was then 
placed into individual plastic bags, and finally loaded 
onto wooden bearing blocks, blocked and strapped 
down to the trailer. The load was further protected with 
a tarp over the total assemblies. For air transport, 
flange protectors and plastic caps protected the cata-lyst 
tube openings over the inlet and outlet pigtails. The 
assemblies were loaded onto wooden bearing blocks, 
blocked and strapped down. Following unloading onto 
road trailers at the airport; the load was tarped for 
transport to the plant site. 
AMMONIA TECHNICAL MANUAL 278 2002

More Related Content

What's hot

Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Gerard B. Hawkins
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube DesignGerard B. Hawkins
 
Primary Reforming Flowsheets
Primary Reforming FlowsheetsPrimary Reforming Flowsheets
Primary Reforming FlowsheetsGerard B. Hawkins
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Gerard B. Hawkins
 
Steam Reforming - Carbon Formation
Steam Reforming - Carbon FormationSteam Reforming - Carbon Formation
Steam Reforming - Carbon FormationGerard B. Hawkins
 
Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical OperationsGerard B. Hawkins
 
Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewGerard B. Hawkins
 
Secondary Reforming Flowsheets
Secondary Reforming FlowsheetsSecondary Reforming Flowsheets
Secondary Reforming FlowsheetsGerard B. Hawkins
 
Hydrogen Plant Flowsheet - Effects of Low Steam Ratio
Hydrogen Plant Flowsheet - Effects of Low Steam RatioHydrogen Plant Flowsheet - Effects of Low Steam Ratio
Hydrogen Plant Flowsheet - Effects of Low Steam RatioGerard B. Hawkins
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer newGowri Shankar
 
Low Temperature Shift Catalyst Reduction Procedure
Low Temperature Shift Catalyst Reduction ProcedureLow Temperature Shift Catalyst Reduction Procedure
Low Temperature Shift Catalyst Reduction ProcedureGerard B. Hawkins
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingGerard B. Hawkins
 
Steam Methane Reformer
Steam Methane ReformerSteam Methane Reformer
Steam Methane ReformerSoumya Ranjan
 
Theory of Carbon Formation in Steam Reforming
Theory of Carbon Formation in Steam Reforming Theory of Carbon Formation in Steam Reforming
Theory of Carbon Formation in Steam Reforming Gerard B. Hawkins
 
Catalyst Catastrophes in Syngas Production - I
Catalyst Catastrophes in Syngas Production - ICatalyst Catastrophes in Syngas Production - I
Catalyst Catastrophes in Syngas Production - IGerard B. Hawkins
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesGerard B. Hawkins
 
Catalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesCatalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesGerard B. Hawkins
 
Theory and Practice of Steam Reforming
Theory and Practice of Steam ReformingTheory and Practice of Steam Reforming
Theory and Practice of Steam ReformingGerard B. Hawkins
 

What's hot (20)

Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube Design
 
Primary Reforming Flowsheets
Primary Reforming FlowsheetsPrimary Reforming Flowsheets
Primary Reforming Flowsheets
 
Methanol Reformer Designs
Methanol Reformer DesignsMethanol Reformer Designs
Methanol Reformer Designs
 
Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers - Theory and Operation - Secondary Reformers -
Theory and Operation - Secondary Reformers -
 
Steam Reforming - Carbon Formation
Steam Reforming - Carbon FormationSteam Reforming - Carbon Formation
Steam Reforming - Carbon Formation
 
Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical Operations
 
Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive Review
 
Secondary Reforming Flowsheets
Secondary Reforming FlowsheetsSecondary Reforming Flowsheets
Secondary Reforming Flowsheets
 
Hydrogen Plant Flowsheet - Effects of Low Steam Ratio
Hydrogen Plant Flowsheet - Effects of Low Steam RatioHydrogen Plant Flowsheet - Effects of Low Steam Ratio
Hydrogen Plant Flowsheet - Effects of Low Steam Ratio
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer new
 
Low Temperature Shift Catalyst Reduction Procedure
Low Temperature Shift Catalyst Reduction ProcedureLow Temperature Shift Catalyst Reduction Procedure
Low Temperature Shift Catalyst Reduction Procedure
 
Steam Reforming - Poisons
Steam Reforming - PoisonsSteam Reforming - Poisons
Steam Reforming - Poisons
 
Steam Reforming - Catalyst Loading
Steam Reforming - Catalyst LoadingSteam Reforming - Catalyst Loading
Steam Reforming - Catalyst Loading
 
Steam Methane Reformer
Steam Methane ReformerSteam Methane Reformer
Steam Methane Reformer
 
Theory of Carbon Formation in Steam Reforming
Theory of Carbon Formation in Steam Reforming Theory of Carbon Formation in Steam Reforming
Theory of Carbon Formation in Steam Reforming
 
Catalyst Catastrophes in Syngas Production - I
Catalyst Catastrophes in Syngas Production - ICatalyst Catastrophes in Syngas Production - I
Catalyst Catastrophes in Syngas Production - I
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube Studies
 
Catalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer TubesCatalyst Breakage in Reformer Tubes
Catalyst Breakage in Reformer Tubes
 
Theory and Practice of Steam Reforming
Theory and Practice of Steam ReformingTheory and Practice of Steam Reforming
Theory and Practice of Steam Reforming
 

Viewers also liked

Introduction to Pre-reformer Flowsheet Options
Introduction to Pre-reformer Flowsheet OptionsIntroduction to Pre-reformer Flowsheet Options
Introduction to Pre-reformer Flowsheet OptionsGerard B. Hawkins
 
Improve fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyImprove fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyAshutosh Garg
 
Ppt fw hydrogen production
Ppt fw hydrogen productionPpt fw hydrogen production
Ppt fw hydrogen productionAshok Paliwal
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignGerard B. Hawkins
 
Ammonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator trainingAmmonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator trainingGerard B. Hawkins
 
SMR PRE-REFORMER DESIGN: Case Study
SMR PRE-REFORMER DESIGN: Case StudySMR PRE-REFORMER DESIGN: Case Study
SMR PRE-REFORMER DESIGN: Case StudyGerard B. Hawkins
 
An Introduction to Operations Management
An Introduction to Operations ManagementAn Introduction to Operations Management
An Introduction to Operations ManagementChristian Reinboth
 
Steam reforming - The Basics of Reforming
Steam reforming  - The Basics of ReformingSteam reforming  - The Basics of Reforming
Steam reforming - The Basics of ReformingGerard B. Hawkins
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming TechnologyGerard B. Hawkins
 
Hydrogen production in refinery
Hydrogen production in refineryHydrogen production in refinery
Hydrogen production in refineryAnupam Basu
 

Viewers also liked (11)

Introduction to Pre-reformer Flowsheet Options
Introduction to Pre-reformer Flowsheet OptionsIntroduction to Pre-reformer Flowsheet Options
Introduction to Pre-reformer Flowsheet Options
 
Improve fired heaters performance and reliabilty
Improve fired heaters performance and reliabiltyImprove fired heaters performance and reliabilty
Improve fired heaters performance and reliabilty
 
Ppt fw hydrogen production
Ppt fw hydrogen productionPpt fw hydrogen production
Ppt fw hydrogen production
 
Ammonia Industries
Ammonia IndustriesAmmonia Industries
Ammonia Industries
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
 
Ammonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator trainingAmmonia Synthesis Flowsheet - Operator training
Ammonia Synthesis Flowsheet - Operator training
 
SMR PRE-REFORMER DESIGN: Case Study
SMR PRE-REFORMER DESIGN: Case StudySMR PRE-REFORMER DESIGN: Case Study
SMR PRE-REFORMER DESIGN: Case Study
 
An Introduction to Operations Management
An Introduction to Operations ManagementAn Introduction to Operations Management
An Introduction to Operations Management
 
Steam reforming - The Basics of Reforming
Steam reforming  - The Basics of ReformingSteam reforming  - The Basics of Reforming
Steam reforming - The Basics of Reforming
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming Technology
 
Hydrogen production in refinery
Hydrogen production in refineryHydrogen production in refinery
Hydrogen production in refinery
 

Similar to Aiche 42-024-primary reformer failure- agrium

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptxrajneeshjauhari2
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerVENUS ENERGY AUDIT SYSTEM
 
Boiler efficiency & safety
Boiler efficiency & safetyBoiler efficiency & safety
Boiler efficiency & safetyRakeshBhowmick1
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...IRJET Journal
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 
Cement rotary kiln
Cement rotary kilnCement rotary kiln
Cement rotary kilnmkpq pasha
 
Cement rotary kiln questions & answers
Cement rotary kiln questions & answersCement rotary kiln questions & answers
Cement rotary kiln questions & answersNael Shabana
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfPrasadKandukuri4
 
Basically what is Locomotive boiler?
Basically what is Locomotive boiler?     Basically what is Locomotive boiler?
Basically what is Locomotive boiler? Pankaj Kumar Sharma
 
Iron Making Lecture Notes
Iron Making Lecture NotesIron Making Lecture Notes
Iron Making Lecture NotesFellowBuddy.com
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodBarhm Mohamad
 

Similar to Aiche 42-024-primary reformer failure- agrium (20)

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boiler
 
Boiler efficiency & safety
Boiler efficiency & safetyBoiler efficiency & safety
Boiler efficiency & safety
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...
IRJET-A Study Analysis and Performance of High Pressure Boilers With its Acce...
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Thermal power plants
Thermal power plantsThermal power plants
Thermal power plants
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
 
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdftopsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
 
Commissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdfCommissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdf
 
haldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup documenthaldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup document
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Cement rotary kiln
Cement rotary kilnCement rotary kiln
Cement rotary kiln
 
Cement rotary kiln questions & answers
Cement rotary kiln questions & answersCement rotary kiln questions & answers
Cement rotary kiln questions & answers
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 
Basically what is Locomotive boiler?
Basically what is Locomotive boiler?     Basically what is Locomotive boiler?
Basically what is Locomotive boiler?
 
Iron Making Lecture Notes
Iron Making Lecture NotesIron Making Lecture Notes
Iron Making Lecture Notes
 
Remaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element methodRemaining life assessment of refinery furnace tubes using finite element method
Remaining life assessment of refinery furnace tubes using finite element method
 

Aiche 42-024-primary reformer failure- agrium

  • 1. Primary Reformer Failure The Agrium Fort Saskatchewan Nitrogen Operations experienced a massive reformer failure following a short maintenance outage and routine startup. The events which led up to the failure, the methodology, scheduling and alterations made to bring the reformer back online, and the safeguards incorporated to lessen future occurrences of this type of failure are discussed. D. H. Timbres and Mark McConnell Agrium Fort Saskatchewan, Alberta, Canada Introduction At the Agrium Fort Saskatchewan Nitrogen Operations in Fort Saskatchewan, Alberta, Canada on Nov. 16-17, 1998, a massive reformer failure was experienced. This failure followed a short maintenance outage and what was considered a routine plant restart. Almost all the catalyst tubes failed in the radiant section, and the air-steam preheat coil No. 1 (shield coil) was damaged. This resulted in 39 days of lost production in the ammonia plant and 40 days lost production in the urea plant. The events which lead up to the failure, the method-ology, scheduling and alterations made to bring the reformer furnace back on line, and the safeguards incorporated to lessen future occurrences of this type of failure are discussed in this article. Background Agrium Inc. is a leading global producer and mar-keter of fertilizer and a major retail supplier of agricul-tural products and services in both North America and Argentina. The Corporation produces and markets four primary groups of fertilizers: nitrogen, phosphate, potash, and sulfur. Agrium, Fort Saskatchewan Nitrogen Operations was commissioned in 1983 and produces ammonia and urea fertilizer for the Western Canadian and export markets. The site comprises a 1,000 metric ton per day nameplate Kellogg ammonia plant and a 907 metric ton per day Stamicarbon urea plant. Current operating capacities are 1,350 metric tons per day ammonia and 1,280 metric tons per day urea. The primary reformer furnace in the ammonia plant is a Kellogg design with 260 radiant tubes, 5 radiant tube rows, with 52 tubes per row. The radiant tubes were HP-Nb modified material and installed over a period of 1991 to 1993, with the majority (207 out of 260) of the tube installed new in 1993. The reformer furnace layout is shown in Figures 1 and 2. There are six arch burner rows with 22 burners per row for a total of 132 arch burners. In addition there are six tunnel burners, which are not operated, and 13 steam superheater burners. The convection section consists of three coils in the "hot leg," the air-steam shield coil, the main air-steam coil, and the mixed feed preheat coil. In the "cold leg," there are four coils, the steam superheat coil, the feedgas coil, the boiler feed water preheat coil, and the fuel gas preheat coil. All aforementioned coils are in the exit heat direction. Primary Reformer Startup Procedure The plant procedure for startup consists of introduc-ing a nitrogen purge to the front-end by means of tem-porary hose connections to the following locations: • Purging the process gas line, • Purging the steam to process line, and AMMONIA TECHNICAL MANUAL 268 2002
  • 2. Figure 1. Plant overview (primary reformer at left). Figure 2. Closeup of primary reformer furnace. AMMONIA TECHNICAL MANUAL 269 2002
  • 3. ARCH BURNER FIRING PATTERN NORTH ROW #6 ROW #5 ROW #4 ROW #3 61 41 51 43 53 WEST 45 55 47 57 49 59 * • 33 * • 5 •• 35 •• 9 •• 21 •• 17 •• 29 •• 25 • • 1 • • 13 • • 66 • 63 • • 37 •• 11 • • 39 •• 15 •• 7 •• 27 •• 3 •• 23 •• 31 •• 19 • • • 20 • • 32 • • 24 • • 4 • • 28 • • 8 •• 16 •• 36 • • 12 •• 38 •• 64 ROW #2 • 65 • • 41 • • 2 •• 26 •• 30 • • 40 •• 18 • • 10 •• 34 •• 6 • • 22 • ROW#1 • • 60 50 58 48 • 56 . EAST • 46 •• 54 •• 44 • • 52 • • 42 • • 62 SOUTH AFTER BURNER NUMBER 66 IS REQUIRED WHEN ADDING IS LIT, NO SET ADDITIONALB PATTERN URNERS. Figure 3. Arch burner firing pattern. AMMONIA TECHNICAL MANUAL 270 2002
  • 4. • Purging the steam to air coil line. The operators follow an arch burner-firing pattern (see Figure 3) with a warmup rate of 100°C/h (212°F/h). The radiant box is preheated by lighting specific arch burners between each of the radiant tube rows until the flue-gas temperature reaches 400°C (752°F), following which steam is introduced into the radiant tubes. By preheating, you prevent condensation of the steam on the cold tubes/catalyst. Also, you minimize tempera-ture shock of hot steam on cold catalyst. At a 400"C (752°F) flue-gas temperature, steam is introduced to the process at 40% rate. The temperature is then steadily increased by lighting more arch burners until the exit tube temperature reaches 700°C (1,292°F), at which point natural gas is introduced to the process. Additional arch burners are then lit. At 750-800°C (1,382-1,472°F) flue-gas temperature, air is introduced to the secondary reformer. When light off has been confirmed by a temperature rise across the secondary reformer, the system is gradually brought to up operating conditions. From Nov. 16 through Nov. 17, 1998, the primary reformer furnace was already in a warm condition with a flue-gas temperature of just under 400°C (752°F). Night shift was continuing to warm up and was getting ready to introduce steam at 400°C (752°F). The panel operator directed the field operator to light additional arch burners to warm up the reformer. The field operator did this exact operation a number of times over the next few hours. What was later discovered was that the field operator did not perform checks inside the radiant box after lighting the additional burners. That is, the field opera-tor did not visually look at the burner(s) that had been lit to confirm there was no flame impingement on the tubes and to visually confirm the tubes were not exces-sively hot. In addition, the panel operator was incorrectly observing the transfer header outlet temperature instead of the flue-gas temperature. So as additional arch burners were being lit, the tem-perature in the radiant box continued to rise, but, as yet, no steam had been introduced to the radiant tubes. At about 10:35 PM on Nov. 16, steam should have been introduced into the radiant tubes. At about 2:47 AM the next morning, the field opera-tors looked inside the radiant box, and observed the catalyst tubes were a glowing bright yellow and dis-continued firing. It was later noted that the flue-gas temperature had reached a maximum value of 1,071°C (1,960°F). [The melting point is typically quoted at about 1,343°C (2,426°F) and complete melting will be finished at 1,400°C (2,552°F), respectively known as the solidus and liquidus melting temperatures ("the range of melting"). It is probable that localized flue-gas temperatures were much higher than temperatures reported by thermocouples at the outlet of the radiant box. Uneven firing or the relatively high air leakage rate at low firing rates could cause this.] The time line for the temperature and number of burners lit is shown in Figure 4. Description of Damage Following a cool down of the primary reformer fur-nace, further observations within the radiant box showed that approximately 50% of the tubes had com-pletely failed. Tube failure was observed mainly at welds. Molten metal had solidified within the radiant tube catalyst. See Figures 5, 6 and 7. No risers had failed, but overheating was evident. See Figure 8. In the "hot leg" of the convection section, the air-steam preheat coil No. 1 (shield coil) showed evidence of overheating and distortion. See Figure 9 and 10. None of the tubes had ruptured, however. The air-steam No. 2 coil was intact with no evidence of damage, as was the mixed feed coil. In the "cold leg" of the convection section, none of the four coils (steam superheat, feedgas preheat, boiler feedwater preheat, and the fuel gas preheat coils) were damaged. Some minor damage was noted to the radiant furnace wall insulation and refractory. Repairs to Primary Reform Furnace On Nov. 17, 1998, a management team was assem-bled to conduct the demolition and repairs to the pri-mary reform furnace and air-steam preheat coil No. 1 (shield coil), and to bring the plant online as soon as AMMONIA TECHNICAL MANUAL 271 2002
  • 5. Timeline of the November 16-17,1998 Incident 1200 1000 - g S Nw16 Nov-16 Nov-16 Nov-16 Nov-16 Nov-16 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 Nov-17 21:00 21:30 22:00 22:30 23:00 23:30 00:00 00:30 01:00 01:30 02:00 02:30 03:00 Transfer Header Temperature (TI-2179) -Flue Gas Temperature (Tl-2119) • Number of Burners Figure 4. Time line for temperature and number of burners lit. Figure 5. Overview of failed radiant tubes. AMMONIA TECHNICAL MANUAL 272 2002
  • 6. Figure 6. Closeup view of failed radiant tubes. Figure 7. Molten metal found within the radiant tube catalyst. AMMONIA TECHNICAL MANUAL 273 2002
  • 7. Figure 8. Riser tubes (riser tube on right has been mechanically cut for removal). Figure 9. Overview of air-steam preheat coil No. 1 (shield coil) damage. AMMONIA TECHNICAL MANUAL 274 2002
  • 8. Figure 10. Another overview of damage to air-steam preheat coil No. 1 (shield coil). possible. In addition, since a scheduled maintenance turnaround had been planned for the following June (1999), those additional maintenance items were brought forward for completion at the same time as the major repair. Because of the magnitude of the problem, Kellogg Brown and Root (KBR) were contacted for assistance. To oversee progress in procurement and expediting, an Agrium senior purchasing agent was placed in the KBR office in Houston. The senior purchasing agent traveled to KBR on November 18, 1998. The decision was made early hi the repair process to replace all 260 radiant tubes, all 5 riser tubes, all 5 outlet manifolds, and all radiant tube spring hangers. This decision was made despite the observation that some radiant tubes still remained intact. Time was of the essence and the management team felt there was not time to test radiant tubes, riser and collection manifolds for usefulness. On Nov. 18, 1998 after senior Agrium management and Agrium's insurance agents had viewed the damage, blinding and scaffolding started as the first stage of demolition. A local contractor was hired to commence removal of damaged items from the radiant box. For the major work, a second local company was hired to set the stage for repairs, plus do additional work on the convection section of the furnace. By Nov. 21, 1998, KBR, with input from Agrium, had narrowed vendors for the cast radiant tubes, cast risers, and new cast collection headers to two vendors (one in the U.K. and the other in the U.S.). Two ven-dors were considered optimum due to the fast supply and delivery each offered. Placing the order with one vendor would have increased delivery time. Demolition was well underway at this point. On Nov. 22, 1998 a letter of intent was sent to the first vendor, and 114 radiant tubes, 6 risers, and 5 col-lection headers with the second vendor. This supplier provided 10 extra radiant tubes and one extra riser tube. The arrangement with the two suppliers guaranteed an initial receipt of radiant tubes by Dec. 10, 1998 (3 weeks and two days after the incident) and final deliv-ery of materials by Dec. 20, (4.5 weeks after the inci-dent) allowing a staged-in repair. To help expedite the replacement radiant parts, the AMMONIA TECHNICAL MANUAL 275 2002
  • 9. Agrium management team became aware very early on in the procurement process that one part of the radiant tube replacement was going to be a bottleneck. That part was the top of the radiant tube known as the tube top. The tube top is essentially the inlet section of the radiant tube, made entirely of wrought components. To meet early delivery schedules, the tube tops were removed from all damaged radiant tubes. As well, Agrium had in inventory 20 complete spare radiant tubes, and all the tube tops were cut off from the inven-tory tubes and sent to the vendors as well. The addi-tional tube tops were insurance against any unusable tube tops that might surface in inspection and/or assembly of the new replacement radiant tubes. Again, Agrium personnel were sent to the two respective vendors facilities to expedite manufacturing and delivery of radiant tubes, risers and collection headers. The transition assemblies (between riser and outlet transfer header) were contracted to a third vendor, and the air-steam preheat coil No. 1 (shield coil), including intermediate tube supports, was contracted to a fourth company. Both the latter were located in the U.S. and delivery was scheduled as soon as individual items were fabricated. Also, delivery was timed to coincide with the delivery of the cast radiant components. Due to some long-term process requirements for the radiant section of the furnace, replacement tubes were made with a slightly larger internal diameter (from 4.0 in. ID to 4.3 in. ID) and the tube metallurgy of the radi-ant tubes was changed from HP-Nb modified to HP-Nb microalloy material. (This larger internal diameter change in the radiant tube decreased the pressure drop.) The riser tubes remained as HP-Nb modified materi-al with no alteration in physical dimensions. The outlet collection headers were altered from wrought Incoloy 800HT to the cast equivalent. In addition to the physical components, none of the radiant tube catalyst was recovered, and new replace-ment catalyst was purchased. The catalyst replacement was unidense loaded. To facilitate the quick delivery, the 156 radiant tubes from the U.K. vendor had to be air freighted to Canada hi three airfreight loads. A freight forwarder was hired to contract the Russian built planes to haul the materials to Canada. Figures 11, 12 and 13 show the type of aircraft, the stacking of tubes hi the plane hold and the unloading of the radiant tubes at Edmonton, Alberta, Canada for transport to Fort Saskatchewan (a distance of 50 miles). Due to sequential delivery of items, all radiant tubes were individually stabbed into the furnace. See Figure 14. There was no time for building harps outside the furnace and then installing completed harps into the furnace. The replacement schedule was organized for 2-10 h shifts 7 days a week, with 4 h for any X-ray work. All welded joints were X-rayed. Following installation of each complete row of radi-ant tubes (and riser and transition can assemblies), the catalyst was loaded into the radiant tubes and the pres-sure drop readings completed. This was done while construction continued on other rows, until all five rows of radiant tubes (and riser and transitions can assemblies) were completed. Following along with the repairs to the radiant sec-tion, the air-steam preheat coil No. 1 (shield coil) was repaired. All mechanical work was completed by Dec. 22, 1998. Scaffolding and blinds were removed by Dec. 23, 1998 and the major contractor demobilized. Preheating commenced Dec. 24, 1998, and, by early Dec. 26, 1998, ammonia production began - just 39 days after the initial damage to the furnace. The job was completed with no lost tune injuries or serious medical injuries. Corrective Actions Following the repairs and startup of the plant opera-tions, a full enquiry was undertaken as to the cause of the failure. This enquiry resulted hi the following cor-rective actions: • It is mandatory to have an overall operations coor-dinator during startup. • It is mandatory to have two operators on the panel during startup. • Log books would be kept of each area of the plant to improve communication between crews. • Written procedures for lighting burners. • An automatic shutdown system was installed to protect against overheating during, startup. (The ammo-nia plant did have a high temperature shutdown system AMMONIA TECHNICAL MANUAL 276 2002
  • 10. Figure 11. Russian cargo plane used to transport radiant tubes from U.K. to Canada. Figure 12. Packaging of radiant tubes in hold of Russian plane. Figure 13. Offloading of radiant tubes at Edmonton International Airport for transfer to Fort Saskatchewan. AMMONIA TECHNICAL MANUAL 277 2002
  • 11. Figure 14. Stabbing of tubes into pri-mary reformer furnace. on the process side. As there was little flow from the nitrogen purge, this system did not "see" the high tem-peratures. The new system is designed specifically to look at flue-gas temperatures (voting system) and steam flow (voting system) and trip if temperature is too high with low steam flow). Closing Comments • The automatic protective systems in an ammonia plant may not adequately protect equipment during startup conditions. • Common practice at the Fort Saskatchewan plant was to rely on procedures to protect the plant during startup. • When relying on procedures, all necessary steps should be taken to ensure they will be correctly fol-lowed. • The importance of field checks must be reinforced to the operators. • If the negative consequences of a procedure not being followed are too great to accept, the need for additional layers of protection into the system should be considered. This could mean designing an automat-ic trip system. QUESTIONS AND ANSWERS Rob Gommans, Gommons Metallurgical Services: Were tubes protected from de-icing salts during road transport? D. EL Timbres, Agrium: Yes. For road transportation, all the catalyst tube openings were protected with flange protectors, and plastic caps over the inlet and outlet pigtails.The catalyst tube assembly was then placed into individual plastic bags, and finally loaded onto wooden bearing blocks, blocked and strapped down to the trailer. The load was further protected with a tarp over the total assemblies. For air transport, flange protectors and plastic caps protected the cata-lyst tube openings over the inlet and outlet pigtails. The assemblies were loaded onto wooden bearing blocks, blocked and strapped down. Following unloading onto road trailers at the airport; the load was tarped for transport to the plant site. AMMONIA TECHNICAL MANUAL 278 2002