SlideShare a Scribd company logo
1 of 81
Download to read offline
Structural Design of bridge
and Culvert
SDE. Prabhat Kumar Jha
Department of Road
9841360244
Structural design of bridge:
• various types of bridges, selection and type of bridges and
economic span length,
• types of loads, forces and stresses, live load, impact load,
wind load, longitudinal forces, lateral loads, centrifugal
force,
• width of roadway and footway, general design
requirements,requirements,
• solid slab bridges, deck girder bridges, B.M. in slab
supported on four edges, distribution of live loads on
longitudinal beams, method of distribution coefficients,
Courbon’s method,
• design of a T- beam bridge, balanced cantilever bridge,
Design of box culvert
What is a bridge?
• A bridge is a structure that spans a divide
such as:
– A stream/river/ravine/valley
– Railroad track/roadway/waterway
• The traffic that uses a bridge may include:
– Pedestrian or cycle traffic
– Vehicular or rail traffic– Vehicular or rail traffic
– Water/gas pipes
– A combination of all the above
700 A.D. Asia700 A.D. AsiaNatural BridgesNatural Bridges
Clapper Bridge
Tree trunk
Stone
History of Bridge DevelopmentHistory of Bridge Development
Great Stone Bridge in China
Low Bridge
Shallow Arch
100 B.C. Romans100 B.C. Romans
Stone
The Arch
Natural
Cement
Roman Arch Bridge
Shallow Arch
1300 A.D. Renaissance1300 A.D. Renaissance
Strength of
Materials
Mathematical
Theories
Development of
Metal
First Cast-Iron Bridge
Coalbrookdale,
England
1800 A.D.1800 A.D.
History of Bridge DevelopmentHistory of Bridge Development
Truss Bridges
Mechanics of
Design
1900 A.D.1900 A.D.
Prestressed
Concrete
Steel
2000 A.D.2000 A.D.
Coalbrookdale,
England
Britannia Tubular
Bridge
1850 A.D.1850 A.D.
Wrought Iron
Suspension Bridges
Use of Steel for
the suspending
cables
1920 A.D.1920 A.D.
Steel
•Type of Bridge
Based on Materials
RCC Bridge
Prestessed concrete Bridge
Steel Bridge
Timber Bridge
Based on Inter-Span relation
Simply Supported Bridge
Continuous Bridge
Cantilever Bridge
Based on Structural Behavior
RCC T-Girder Bridge (Max. 25m)
Steel Truss Bridge (Max. 30-100m)
Bow String Girder Bridge (Max. 30-35m)
Arch Bridge (Max. 35-200m)
Balanced Cantilever Bridge (Max. 30-60m)
Suspension Bridge (Max. 400-1200m)
Cable Stayed Bridge (Max. 200-600m)
Rigid Frame Bridge (Max. 25m)
•Type of Bridge
Based on Function
Aqueduct
Pedestrian Bridge
Road Bridge
Railway Bridge
Pipeline Bridge
Based on Length / Span
Culvert : Length up to 6 m
Minor Bridge : When length ≤ 50 m (with span ≤ 25 m )
Major Bridge : When span >25 m or length >50 m (with smaller spans)
Special Bridge : Bridges that require special design considerations, whose
construction features
(e.g. concrete girder bridges with >50m span, steel trusses >
100m span, arch bridges, suspension bridges, cable-stayed bridges and other
nonstandard
According to the position of the bridge floor relative to the superstructure :
deck, through, half-through etc.
According to method of construction : pin-connected, riveted, welded etc.
bridges).
Basic Components of a Bridge
The two basic parts are:
• Substructure - includes the piers, the abutments and the
foundations.
• Superstructure - consists of the deck structure itself, which
support the direct loads due to traffic and all the other
permanent and variable leads to which the structure ispermanent and variable leads to which the structure is
subjected.
• The connection between the substructure and the
superstructure is usually made through bearings. However,
rigid connections between the piers (and sometimes the
abutments) may be adopted, particularly in frame bridges with
tall (flexible) piers.
Basic Components of a Bridge
Typical Beam/Girder Bridge
A Typical Single Span Bridge
• Because the truss is a hollow skeletal
structure, the roadway may pass over or
even through the structure allowing for
clearance below the bridge often not
Truss Bridges
clearance below the bridge often not
possible with other bridge types
• Warren Truss
– The Warren truss pattern features a series of isoceles or
equilateral triangles. In contrast to the Pratt and Howe
patterns, the diagonals alternate in direction.
– Warren trusses are typically used in spans of between 150-
Truss Bridges
– Warren trusses are typically used in spans of between 150-
300 feet
– The most common truss. For smaller spans, no vertical
members are used lending the structure a simple look. For
longer spans vertical members are added providing extra
strength
Truss Bridges
• Pratt Truss
– The Pratt truss design contains a downward pointing
V in the center with parallel diagonals on each side.
– Except for those diagonal members near the center,
all the diagonal members are subject to tensionall the diagonal members are subject to tension
forces only while the shorter vertical members handle
the compressive forces. This allows for thinner
diagonal members resulting in a more economic
design.
• Howe Truss
– The Howe truss pattern features an upward pointing
V formed by the central diagonals with parallel
diagonals on either side. Unlike the Pratt pattern the
diagonals will be in compression when loaded
Truss Bridges
diagonals will be in compression when loaded
– It is the opposite of the Pratt truss. The diagonal
members face in the opposite direction and handle
compressive forces. This makes it very uneconomic
design for steel bridges and is rarely used.
• Warren Truss
Build Your Bridge!
• Pratt Truss
• Howe Truss
Types of Trusses
K-Truss
Whipple Bowstring
Types of Trusses
Bollman
Cuts
Cross Overs – Each time a line crosses another line you will need to
make a cut – On one line for this bridge a minimum of 12 cuts will
need to be made!
Town Lattice
Arch Bridges
• Arches used a curved structure
which provides a high
resistance to bending forces.
• Both ends are fixed in the
horizontal direction (no
horizontal movement allowed
in the bearings).in the bearings).
• Arches can only be used
where ground is solid and
stable.
• Hingeless arch is very stiff and
suffers less deflection.
• Two-hinged arch uses hinged
bearings which allow rotation
and most commonly used for
steel arches and very
economical design.
Hinge-less Arch
Two hinged Arch
Arch Bridges
• The three-hinged arch
adds an additional hinge at
the top and suffers very
little movement in either
foundation, butfoundation, but
experiences more
deflection. Rarely used.
• The tied arch allows
construction even if the
ground is not solid enough
to deal with horizontal
forces.
Three-hinged Arch
Tied Arch
Simple Supported Bridge Arch Bridge
Cable Stayed Bridge
Suspension Bridge
Balanced Cantilever Bridge
FACTORS CONSIDERED IN DECIDINGFACTORS CONSIDERED IN DECIDING
BRIDGE TYPEBRIDGE TYPE
••Geometric Conditions of the SiteGeometric Conditions of the Site
••Subsurface Conditions of the SiteSubsurface Conditions of the Site
••Functional RequirementsFunctional Requirements
••AestheticsAesthetics••AestheticsAesthetics
••Economics and Ease of MaintenanceEconomics and Ease of Maintenance
••Construction and Erection ConsiderationConstruction and Erection Consideration
••Legal ConsiderationsLegal Considerations
Selection of Type of Bridge
Principle : The entire completed structure should be the most suitable to carry
the desired traffic , adequate strong to support the incident loads, economical
and aesthetically pleasing.
Factors :
1. Hydraulic Factors and River Regime
: Linear Waterway, Scour Depth, x-section at Bridge axis
Ex:- LW > 25m and deep gorge : Steel Truss Bridge or Plate Girder or Arch
Bridge
Ex:- If the scour depth more than 5-7m from Ground Level and Open
Foundation is uneconomical : Steel Truss Bridge
2. Topography and Soil Conditions:
Ex:- Rocky Bank with favorable geological condition may be an ideal site for Arch
Bridge
Ex:- Weak Soil Condition, Simply Supported Bridge rather than Continuous Bridge
Factors :
3.A high level structure with uninterrupted traffic as on a National Highway and need
to replace the no. of piers may necessitate a cantilever bridge or a cable stayed
bridge or a series of Simply Supported truss bridge:
4. Large navigational clearances required may dictate the use of particular type such
as Arch Bridge, Cantilever Bridges, cable stayed construction or suspension bridge.
5.The climate and environmental conditions would preclude the use of some type and
require some others.
Ex:- Corrosive Environment , Never Steel BridgeEx:- Corrosive Environment , Never Steel Bridge
6.Shortage of Fund may necessitate the adoption of a submersible bridge instead of
a high level bridge on a road with low volume of traffic.
Ex:- Vented Causeway
7.Type of Traffic restricts choice of type .
Ex:- For Railway most preferred choice is Steel truss Bridge
8.The personal preferences or Company Specialization of designer / construction
firms.
Es:- Hulas always try to design Steel Truss Bridge under Design-Build Contract
9.Availability of Material
Ex:- Remote Hilly region : RCC Bridge truss bridge is last choice.
10.Economy
Cost of Sub-structure more or less equal to Cost of Superstructure
•Economic Span of Bridge
Thumb:ForRCCSlabBridge:leconomic=1.5H
ForSteelTrussBridge:Leconomic=3H
Thumb:ForRCCSlabBridge:leconomic=1.5H
ForSteelTrussBridge:Leconomic=3H
Choice of Location of Bridge Site
In broader sense, the key factors to be
considered:
1. Hydrological and River Morphological
FactorsFactors
2. Geological and Geotechnical Factors
3. Social and Economic Factors
4. Safety Factors
Choice of Location of Bridge Site
A multi disciplinary expert team selects axis based on :-
1. The reach of the river should be straight so min.
disturbance effects on flow due to structures
2. The river in the reach should have a regime flow free of
whirls, eddies and excessive to avoid excessive scour
and construction difficulties
3. The site should have firm high banks that are fairly
inerodable to avoid breaching of the approachesinerodable to avoid breaching of the approaches
4. The site on a meandering river should be a nodal point to
avoid normal shifting of region
5. The approaches for the bank should secure enough to
flash flood / design flood
6. Approaches bank should not be too high or too expensive
to build
7. The site should have reasonable proximity to the main
road.
Choice of Location of Bridge Site
8.Site requiring minimum recurring maintenance costs
9.Bridge site and approach slope should be stable and
favorable rock orientation
10.The crossing should provide the shortest possible
line of communication between Demand area and
Supply Area as otherwise its usage will be very muchSupply Area as otherwise its usage will be very much
limited and the intensity of usages will be less.
11.The bridge length should be Shortest and Safe
Practically, the site selection is a matter of judgment.
Various alternatives satisfying many conditions as
possible have to be chosen and put to the economic
test before detailed investigations for a chosen site are
undertaken
A Typical Single Span Bridge
Typical Beam/Girder Bridge
Basic Components of a Bridge
Basic Components of a Bridge
The two basic parts are:
• Substructure - includes the piers, the abutments and
the foundations.
• Superstructure - consists of the deck structure itself,
which support the direct loads due to traffic and all the
other permanent and variable leads to which the
which support the direct loads due to traffic and all the
other permanent and variable leads to which the
structure is subjected.
• The connection between the substructure and the
superstructure is usually made through bearings.
However, rigid connections between the piers (and
sometimes the abutments) may be adopted, particularly
in frame bridges with tall (flexible) piers.
Bridge LoadingsBridge Loadings
IRC 6:2014 : Standard Specifications and Code of Practice for
Road Bridge / Section II “Load and Stresses”
Type of Loads
1.Dead Load : of Bridge Components
2.Live Load : Class A, B, AA,
3.Impact Load
4.Wind Load
5.Longitudinal Force
6.Centrifugal Force6.Centrifugal Force
7.Buoyancy Force
8.Water Current Force
9.Thermal Force
10.Deformation Force due to material property change
11.Earth Pressure Load
12.Seismic Force
1.Dead Load : of Bridge Components
Load = Volume x Density
Concrete : 25 KN/sqm
Asphalt : 22 KN/sqm
Steel : 78.50 KN/sqm
Live Load : Class A for All permanent Bridge
8 Axles and Total train length = 25m
Mini. Distance between two successive trains = 18.5m
Live Load : Class A….
Live Load : Class B for temporary Bridge
8 Axles and Total train length = 25m
Mini. Distance between two successive trains =
18.5m
Live Load : Class B
Live Load : 70R (Wheel) Vehicle
For Slab /
Transverse
Analysis
Live Load : 70R (Track) Vehicle
C
=1.2m
Wind Load
Dynamic Load but normally approximated to static
load uniformly distributed over the vertical plane /
elevation area
450 kg/sqm
Longitudinal ForceLongitudinal Force
Due to vehicle Braking and Accelerating while passing
the Bridge.
Approximated to 20% of Lane Load applied at 1.2m
above the level of deck
transfer to substructure through bearing
Centrifugal Force
For a bridge on horizontal curve, CF developed while vehicle
passing it.
C = Live Load x (Velocity)^2 / (127 x Radius of Curve) at 2m
above the deck Level.
Buoyancy Force
Under water bridge structure can suffer from buoyance force for
very large structure and result in undermining effect.
BF = w x H (Upward)
Water Current Force
Horizontal forces are exerted on submerged
part of sub-structures because of water
current, max at top of surface and linearly
reduces to ZERO at bed level.
k = Constant depend on shape of Pier
•Type of Loads (IRC 6:2000)
Thermal Force
Tensile forces developed due to temperature fluctuating in temperature at Bearing
LevelLevel
Deformation Force
Due to change in material properties and geometry
: shrinkage, creep
Ka Value :
Max. 0.297
Min. 0.266
Seismic Force
Vertical Seismic Coefficient = 0.75 x Horizontal Seismic coefficient
Seismic Force is not considered simultaneously with Wind Force
Loads
Superstructure
Foundation /
Substructure
For T-Girder
/Box Girder
For Truss For All type
1.Dead Load : of Bridge Components
1.Live Load : Class A, AA, Pedestrian
1.Impact Load
1.Wind Load
1.Longitudinal Force1.Longitudinal Force
1.Centrifugal Force Occasional
1.Buoyancy Force
1.Water Current Force
1.Thermal Force
1.Deformation Force due to material
property change
1.Earth Pressure Load
1.Seismic Force
NEPAL BRIDGE STANDARDS-2067
DESIGN DISCHARGE
• All permanent bridges shall be designed
for a discharge of 100 yrs. return period.
For the calculation of design dischargeFor the calculation of design discharge
empirical formulas especially developed
for other catchments shall not be used.
NEPAL BRIDGE STANDARDS-2067
4.0 BRIDGE LOADINGS
4.1 ROAD BRIDGE LOADINGS
• All permanent road bridges in Nepal shall
be designed as per IRC loadings orbe designed as per IRC loadings or
AASHTO loadings. All design shall be
carried out in accordance to IRC
standards for bridges unless otherwise
specified in this document.
NEPAL BRIDGE STANDARDS-2067
5.0 GEOMETRIC STANDARDS
5.1 CARRIAGEWAY
• All bridges in Highways and Urban Roads shall
be designed with a minimum carriageway widthbe designed with a minimum carriageway width
of 7.5m.
• All bridges in Feeder Roads shall be designed
with a minimum carriageway width of 6.0m.
• No permanent bridge shall be designed with a
carriageway width of less than 6.0m except on
minor (district and village) roads having length
less than 25m.
NEPAL BRIDGE STANDARDS-2067
5.2 FOOTPATH
• Footpaths shall be provided on all bridges
located at settlement areas or on areas of high
movement of pedestrian traffic. They should bemovement of pedestrian traffic. They should be
separated from the vehicular traffic by safety
curbs (in rural areas) and by raised footpath or
curbs (in urban areas).The width of the footpath
should be decided according to projection of
pedestrian traffic, however, a minimum clear
width(excluding the width of railings) of 1.0
m footpaths to be provided, where necessary.
NEPAL BRIDGE STANDARDS-2067
6.0 CLEARANCES
6.1 VERTICAL CLEARANCE
• The vertical clearance of structures shall be,
• For all roads not less than 4.75 m for through• For all roads not less than 4.75 m for through
structures
• Overhead wires, poles etc shall be at least 7.0 m
above the highest point of the road surface.
NEPAL BRIDGE STANDARDS-2067
7.0 BRIDGE CLASSIFICATION
Classification of bridges shall be as follows:
Culvert : Length up to 6 m
Minor Bridge : When length 50 m (with span 25 m )Minor Bridge : When length 50 m (with span 25 m )
Major Bridge : When span >25 m or length >50 m(with
smaller spans)
Special Bridge : Bridges that require special design
considerations, whose construction features(e.g.
concrete girder bridges with >50m span, steel trusses >
100m span, arch bridges, suspension bridges, cable-
stayed bridges and other nonstandard bridges).
NEPAL BRIDGE STANDARDS-2067
General Design Requirements
•Design Discharge 100yr Return Period
•Linear Waterway
•Bridge Span and Length
•Vertical Clearances
•Max. Scour depth•Max. Scour depth
•Width of Carriageway and Footpath
•Bridge Superstructure Selection
•Geotechnical Investigation
•Bridge Foundation Selection
•Concept of Design : Working Load, Limit State Design
1.5 class a,b
1.5 class a,b
1.5 class a,b
1.5 class a,b

More Related Content

What's hot

Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaKhyati Saggu
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge pptSAI KIRAN
 
basics of civil engineering
basics of civil engineeringbasics of civil engineering
basics of civil engineeringChirag Bhanagale
 
Ppt bridges & types
Ppt bridges & typesPpt bridges & types
Ppt bridges & typespratik vanam
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast T.Naga Anusha
 
Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of BridgesAIT Solutions
 
BRIEF STUDY OF IRC STANDARD CODES
BRIEF STUDY OF IRC STANDARD CODESBRIEF STUDY OF IRC STANDARD CODES
BRIEF STUDY OF IRC STANDARD CODESJayvant Choudhary
 
Rebound hammer test (non destructive test
Rebound hammer test (non destructive testRebound hammer test (non destructive test
Rebound hammer test (non destructive testAyaz khan
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge EngineeringKHUSHBU SHAH
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionBathla Tuition Centre
 
Bridge
Bridge Bridge
Bridge illpa
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failuresSunil Kumar Meena
 
Non destructive testing in civil engineering
Non destructive testing in civil engineeringNon destructive testing in civil engineering
Non destructive testing in civil engineeringMAADASWAMY U
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey buildingSivaji Djpk
 

What's hot (20)

Inspection and maintenance of bridges In India
Inspection and maintenance of bridges In IndiaInspection and maintenance of bridges In India
Inspection and maintenance of bridges In India
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
basics of civil engineering
basics of civil engineeringbasics of civil engineering
basics of civil engineering
 
Ppt bridges & types
Ppt bridges & typesPpt bridges & types
Ppt bridges & types
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Bridges
BridgesBridges
Bridges
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
 
Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of Bridges
 
BRIEF STUDY OF IRC STANDARD CODES
BRIEF STUDY OF IRC STANDARD CODESBRIEF STUDY OF IRC STANDARD CODES
BRIEF STUDY OF IRC STANDARD CODES
 
Rebound hammer test (non destructive test
Rebound hammer test (non destructive testRebound hammer test (non destructive test
Rebound hammer test (non destructive test
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
Bridge
Bridge Bridge
Bridge
 
flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failures
 
Non destructive testing in civil engineering
Non destructive testing in civil engineeringNon destructive testing in civil engineering
Non destructive testing in civil engineering
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
 

Similar to 1.5 class a,b

Bridge introduction-8th-civil
Bridge introduction-8th-civilBridge introduction-8th-civil
Bridge introduction-8th-civilAssad ULlah
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminarAbhinav Pateriya
 
CHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engCHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engabdi beder
 
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Mohamed Yassin
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridgesMadujith Sagara
 
Bridge Engg
Bridge Engg Bridge Engg
Bridge Engg bickycivil
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptxMayuriPatel90
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfabhinavbharat9
 
Bridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptxBridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptxmayuray
 

Similar to 1.5 class a,b (20)

Bridge introduction-8th-civil
Bridge introduction-8th-civilBridge introduction-8th-civil
Bridge introduction-8th-civil
 
bridges overview.pptx
bridges overview.pptxbridges overview.pptx
bridges overview.pptx
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
bridges overview.pdf
bridges overview.pdfbridges overview.pdf
bridges overview.pdf
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
 
Bridge intr.ppt
Bridge intr.pptBridge intr.ppt
Bridge intr.ppt
 
CHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design engCHapter 1 introduction to bridge design eng
CHapter 1 introduction to bridge design eng
 
Bridge Engg1.ppt
Bridge Engg1.pptBridge Engg1.ppt
Bridge Engg1.ppt
 
bridges.ppt
bridges.pptbridges.ppt
bridges.ppt
 
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
Bridges Functionality and Aesthetics
Bridges Functionality and AestheticsBridges Functionality and Aesthetics
Bridges Functionality and Aesthetics
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridges
 
Bridge Engg
Bridge Engg Bridge Engg
Bridge Engg
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Bridge
BridgeBridge
Bridge
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdf
 
Bridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptxBridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptx
 

More from Mani Das

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1Mani Das
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067Mani Das
 
1.5 class c,d,e
1.5 class c,d,e1.5 class c,d,e
1.5 class c,d,eMani Das
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asstMani Das
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete noteMani Das
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 averageMani Das
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classificationMani Das
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chartMani Das
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoningMani Das
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogyMani Das
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrologyMani Das
 
High way
High wayHigh way
High wayMani Das
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport convertedMani Das
 
Group d converted
Group d convertedGroup d converted
Group d convertedMani Das
 
9.epp
9.epp9.epp
9.eppMani Das
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicueMani Das
 
7.surveying
7.surveying7.surveying
7.surveyingMani Das
 
6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costingMani Das
 
5.economics
5.economics5.economics
5.economicsMani Das
 
4. construction management
4. construction management4. construction management
4. construction managementMani Das
 

More from Mani Das (20)

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
 
1.5 class c,d,e
1.5 class c,d,e1.5 class c,d,e
1.5 class c,d,e
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asst
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 average
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classification
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chart
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoning
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogy
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrology
 
High way
High wayHigh way
High way
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport converted
 
Group d converted
Group d convertedGroup d converted
Group d converted
 
9.epp
9.epp9.epp
9.epp
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicue
 
7.surveying
7.surveying7.surveying
7.surveying
 
6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costing
 
5.economics
5.economics5.economics
5.economics
 
4. construction management
4. construction management4. construction management
4. construction management
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 

1.5 class a,b

  • 1. Structural Design of bridge and Culvert SDE. Prabhat Kumar Jha Department of Road 9841360244
  • 2. Structural design of bridge: • various types of bridges, selection and type of bridges and economic span length, • types of loads, forces and stresses, live load, impact load, wind load, longitudinal forces, lateral loads, centrifugal force, • width of roadway and footway, general design requirements,requirements, • solid slab bridges, deck girder bridges, B.M. in slab supported on four edges, distribution of live loads on longitudinal beams, method of distribution coefficients, Courbon’s method, • design of a T- beam bridge, balanced cantilever bridge, Design of box culvert
  • 3. What is a bridge? • A bridge is a structure that spans a divide such as: – A stream/river/ravine/valley – Railroad track/roadway/waterway • The traffic that uses a bridge may include: – Pedestrian or cycle traffic – Vehicular or rail traffic– Vehicular or rail traffic – Water/gas pipes – A combination of all the above
  • 4. 700 A.D. Asia700 A.D. AsiaNatural BridgesNatural Bridges Clapper Bridge Tree trunk Stone History of Bridge DevelopmentHistory of Bridge Development Great Stone Bridge in China Low Bridge Shallow Arch 100 B.C. Romans100 B.C. Romans Stone The Arch Natural Cement Roman Arch Bridge Shallow Arch 1300 A.D. Renaissance1300 A.D. Renaissance Strength of Materials Mathematical Theories Development of Metal
  • 5. First Cast-Iron Bridge Coalbrookdale, England 1800 A.D.1800 A.D. History of Bridge DevelopmentHistory of Bridge Development Truss Bridges Mechanics of Design 1900 A.D.1900 A.D. Prestressed Concrete Steel 2000 A.D.2000 A.D. Coalbrookdale, England Britannia Tubular Bridge 1850 A.D.1850 A.D. Wrought Iron Suspension Bridges Use of Steel for the suspending cables 1920 A.D.1920 A.D. Steel
  • 6. •Type of Bridge Based on Materials RCC Bridge Prestessed concrete Bridge Steel Bridge Timber Bridge Based on Inter-Span relation Simply Supported Bridge Continuous Bridge Cantilever Bridge Based on Structural Behavior RCC T-Girder Bridge (Max. 25m) Steel Truss Bridge (Max. 30-100m) Bow String Girder Bridge (Max. 30-35m) Arch Bridge (Max. 35-200m) Balanced Cantilever Bridge (Max. 30-60m) Suspension Bridge (Max. 400-1200m) Cable Stayed Bridge (Max. 200-600m) Rigid Frame Bridge (Max. 25m)
  • 7. •Type of Bridge Based on Function Aqueduct Pedestrian Bridge Road Bridge Railway Bridge Pipeline Bridge Based on Length / Span Culvert : Length up to 6 m Minor Bridge : When length ≤ 50 m (with span ≤ 25 m ) Major Bridge : When span >25 m or length >50 m (with smaller spans) Special Bridge : Bridges that require special design considerations, whose construction features (e.g. concrete girder bridges with >50m span, steel trusses > 100m span, arch bridges, suspension bridges, cable-stayed bridges and other nonstandard According to the position of the bridge floor relative to the superstructure : deck, through, half-through etc. According to method of construction : pin-connected, riveted, welded etc. bridges).
  • 8.
  • 9.
  • 10. Basic Components of a Bridge The two basic parts are: • Substructure - includes the piers, the abutments and the foundations. • Superstructure - consists of the deck structure itself, which support the direct loads due to traffic and all the other permanent and variable leads to which the structure ispermanent and variable leads to which the structure is subjected. • The connection between the substructure and the superstructure is usually made through bearings. However, rigid connections between the piers (and sometimes the abutments) may be adopted, particularly in frame bridges with tall (flexible) piers.
  • 13. A Typical Single Span Bridge
  • 14. • Because the truss is a hollow skeletal structure, the roadway may pass over or even through the structure allowing for clearance below the bridge often not Truss Bridges clearance below the bridge often not possible with other bridge types
  • 15. • Warren Truss – The Warren truss pattern features a series of isoceles or equilateral triangles. In contrast to the Pratt and Howe patterns, the diagonals alternate in direction. – Warren trusses are typically used in spans of between 150- Truss Bridges – Warren trusses are typically used in spans of between 150- 300 feet – The most common truss. For smaller spans, no vertical members are used lending the structure a simple look. For longer spans vertical members are added providing extra strength
  • 16. Truss Bridges • Pratt Truss – The Pratt truss design contains a downward pointing V in the center with parallel diagonals on each side. – Except for those diagonal members near the center, all the diagonal members are subject to tensionall the diagonal members are subject to tension forces only while the shorter vertical members handle the compressive forces. This allows for thinner diagonal members resulting in a more economic design.
  • 17. • Howe Truss – The Howe truss pattern features an upward pointing V formed by the central diagonals with parallel diagonals on either side. Unlike the Pratt pattern the diagonals will be in compression when loaded Truss Bridges diagonals will be in compression when loaded – It is the opposite of the Pratt truss. The diagonal members face in the opposite direction and handle compressive forces. This makes it very uneconomic design for steel bridges and is rarely used.
  • 18. • Warren Truss Build Your Bridge! • Pratt Truss • Howe Truss
  • 22. Cuts Cross Overs – Each time a line crosses another line you will need to make a cut – On one line for this bridge a minimum of 12 cuts will need to be made!
  • 24. Arch Bridges • Arches used a curved structure which provides a high resistance to bending forces. • Both ends are fixed in the horizontal direction (no horizontal movement allowed in the bearings).in the bearings). • Arches can only be used where ground is solid and stable. • Hingeless arch is very stiff and suffers less deflection. • Two-hinged arch uses hinged bearings which allow rotation and most commonly used for steel arches and very economical design. Hinge-less Arch Two hinged Arch
  • 25. Arch Bridges • The three-hinged arch adds an additional hinge at the top and suffers very little movement in either foundation, butfoundation, but experiences more deflection. Rarely used. • The tied arch allows construction even if the ground is not solid enough to deal with horizontal forces. Three-hinged Arch Tied Arch
  • 26. Simple Supported Bridge Arch Bridge Cable Stayed Bridge Suspension Bridge Balanced Cantilever Bridge
  • 27. FACTORS CONSIDERED IN DECIDINGFACTORS CONSIDERED IN DECIDING BRIDGE TYPEBRIDGE TYPE ••Geometric Conditions of the SiteGeometric Conditions of the Site ••Subsurface Conditions of the SiteSubsurface Conditions of the Site ••Functional RequirementsFunctional Requirements ••AestheticsAesthetics••AestheticsAesthetics ••Economics and Ease of MaintenanceEconomics and Ease of Maintenance ••Construction and Erection ConsiderationConstruction and Erection Consideration ••Legal ConsiderationsLegal Considerations Selection of Type of Bridge Principle : The entire completed structure should be the most suitable to carry the desired traffic , adequate strong to support the incident loads, economical and aesthetically pleasing.
  • 28. Factors : 1. Hydraulic Factors and River Regime : Linear Waterway, Scour Depth, x-section at Bridge axis Ex:- LW > 25m and deep gorge : Steel Truss Bridge or Plate Girder or Arch Bridge Ex:- If the scour depth more than 5-7m from Ground Level and Open Foundation is uneconomical : Steel Truss Bridge 2. Topography and Soil Conditions: Ex:- Rocky Bank with favorable geological condition may be an ideal site for Arch Bridge Ex:- Weak Soil Condition, Simply Supported Bridge rather than Continuous Bridge
  • 29. Factors : 3.A high level structure with uninterrupted traffic as on a National Highway and need to replace the no. of piers may necessitate a cantilever bridge or a cable stayed bridge or a series of Simply Supported truss bridge: 4. Large navigational clearances required may dictate the use of particular type such as Arch Bridge, Cantilever Bridges, cable stayed construction or suspension bridge. 5.The climate and environmental conditions would preclude the use of some type and require some others. Ex:- Corrosive Environment , Never Steel BridgeEx:- Corrosive Environment , Never Steel Bridge 6.Shortage of Fund may necessitate the adoption of a submersible bridge instead of a high level bridge on a road with low volume of traffic. Ex:- Vented Causeway 7.Type of Traffic restricts choice of type . Ex:- For Railway most preferred choice is Steel truss Bridge 8.The personal preferences or Company Specialization of designer / construction firms. Es:- Hulas always try to design Steel Truss Bridge under Design-Build Contract
  • 30. 9.Availability of Material Ex:- Remote Hilly region : RCC Bridge truss bridge is last choice. 10.Economy Cost of Sub-structure more or less equal to Cost of Superstructure
  • 31. •Economic Span of Bridge Thumb:ForRCCSlabBridge:leconomic=1.5H ForSteelTrussBridge:Leconomic=3H Thumb:ForRCCSlabBridge:leconomic=1.5H ForSteelTrussBridge:Leconomic=3H
  • 32. Choice of Location of Bridge Site In broader sense, the key factors to be considered: 1. Hydrological and River Morphological FactorsFactors 2. Geological and Geotechnical Factors 3. Social and Economic Factors 4. Safety Factors
  • 33. Choice of Location of Bridge Site A multi disciplinary expert team selects axis based on :- 1. The reach of the river should be straight so min. disturbance effects on flow due to structures 2. The river in the reach should have a regime flow free of whirls, eddies and excessive to avoid excessive scour and construction difficulties 3. The site should have firm high banks that are fairly inerodable to avoid breaching of the approachesinerodable to avoid breaching of the approaches 4. The site on a meandering river should be a nodal point to avoid normal shifting of region 5. The approaches for the bank should secure enough to flash flood / design flood 6. Approaches bank should not be too high or too expensive to build 7. The site should have reasonable proximity to the main road.
  • 34. Choice of Location of Bridge Site 8.Site requiring minimum recurring maintenance costs 9.Bridge site and approach slope should be stable and favorable rock orientation 10.The crossing should provide the shortest possible line of communication between Demand area and Supply Area as otherwise its usage will be very muchSupply Area as otherwise its usage will be very much limited and the intensity of usages will be less. 11.The bridge length should be Shortest and Safe Practically, the site selection is a matter of judgment. Various alternatives satisfying many conditions as possible have to be chosen and put to the economic test before detailed investigations for a chosen site are undertaken
  • 35. A Typical Single Span Bridge
  • 38. Basic Components of a Bridge The two basic parts are: • Substructure - includes the piers, the abutments and the foundations. • Superstructure - consists of the deck structure itself, which support the direct loads due to traffic and all the other permanent and variable leads to which the which support the direct loads due to traffic and all the other permanent and variable leads to which the structure is subjected. • The connection between the substructure and the superstructure is usually made through bearings. However, rigid connections between the piers (and sometimes the abutments) may be adopted, particularly in frame bridges with tall (flexible) piers.
  • 40. IRC 6:2014 : Standard Specifications and Code of Practice for Road Bridge / Section II “Load and Stresses” Type of Loads 1.Dead Load : of Bridge Components 2.Live Load : Class A, B, AA, 3.Impact Load 4.Wind Load 5.Longitudinal Force 6.Centrifugal Force6.Centrifugal Force 7.Buoyancy Force 8.Water Current Force 9.Thermal Force 10.Deformation Force due to material property change 11.Earth Pressure Load 12.Seismic Force
  • 41. 1.Dead Load : of Bridge Components Load = Volume x Density Concrete : 25 KN/sqm Asphalt : 22 KN/sqm Steel : 78.50 KN/sqm
  • 42. Live Load : Class A for All permanent Bridge 8 Axles and Total train length = 25m Mini. Distance between two successive trains = 18.5m
  • 43. Live Load : Class A….
  • 44.
  • 45. Live Load : Class B for temporary Bridge 8 Axles and Total train length = 25m Mini. Distance between two successive trains = 18.5m
  • 46. Live Load : Class B
  • 47. Live Load : 70R (Wheel) Vehicle For Slab / Transverse Analysis
  • 48. Live Load : 70R (Track) Vehicle C =1.2m
  • 49.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57. Wind Load Dynamic Load but normally approximated to static load uniformly distributed over the vertical plane / elevation area 450 kg/sqm Longitudinal ForceLongitudinal Force Due to vehicle Braking and Accelerating while passing the Bridge. Approximated to 20% of Lane Load applied at 1.2m above the level of deck transfer to substructure through bearing
  • 58. Centrifugal Force For a bridge on horizontal curve, CF developed while vehicle passing it. C = Live Load x (Velocity)^2 / (127 x Radius of Curve) at 2m above the deck Level. Buoyancy Force Under water bridge structure can suffer from buoyance force for very large structure and result in undermining effect. BF = w x H (Upward)
  • 59. Water Current Force Horizontal forces are exerted on submerged part of sub-structures because of water current, max at top of surface and linearly reduces to ZERO at bed level. k = Constant depend on shape of Pier
  • 60. •Type of Loads (IRC 6:2000) Thermal Force Tensile forces developed due to temperature fluctuating in temperature at Bearing LevelLevel Deformation Force Due to change in material properties and geometry : shrinkage, creep
  • 61. Ka Value : Max. 0.297 Min. 0.266
  • 62.
  • 63.
  • 64.
  • 65.
  • 66.
  • 67. Seismic Force Vertical Seismic Coefficient = 0.75 x Horizontal Seismic coefficient Seismic Force is not considered simultaneously with Wind Force
  • 68.
  • 69. Loads Superstructure Foundation / Substructure For T-Girder /Box Girder For Truss For All type 1.Dead Load : of Bridge Components 1.Live Load : Class A, AA, Pedestrian 1.Impact Load 1.Wind Load 1.Longitudinal Force1.Longitudinal Force 1.Centrifugal Force Occasional 1.Buoyancy Force 1.Water Current Force 1.Thermal Force 1.Deformation Force due to material property change 1.Earth Pressure Load 1.Seismic Force
  • 70. NEPAL BRIDGE STANDARDS-2067 DESIGN DISCHARGE • All permanent bridges shall be designed for a discharge of 100 yrs. return period. For the calculation of design dischargeFor the calculation of design discharge empirical formulas especially developed for other catchments shall not be used.
  • 71. NEPAL BRIDGE STANDARDS-2067 4.0 BRIDGE LOADINGS 4.1 ROAD BRIDGE LOADINGS • All permanent road bridges in Nepal shall be designed as per IRC loadings orbe designed as per IRC loadings or AASHTO loadings. All design shall be carried out in accordance to IRC standards for bridges unless otherwise specified in this document.
  • 72. NEPAL BRIDGE STANDARDS-2067 5.0 GEOMETRIC STANDARDS 5.1 CARRIAGEWAY • All bridges in Highways and Urban Roads shall be designed with a minimum carriageway widthbe designed with a minimum carriageway width of 7.5m. • All bridges in Feeder Roads shall be designed with a minimum carriageway width of 6.0m. • No permanent bridge shall be designed with a carriageway width of less than 6.0m except on minor (district and village) roads having length less than 25m.
  • 73. NEPAL BRIDGE STANDARDS-2067 5.2 FOOTPATH • Footpaths shall be provided on all bridges located at settlement areas or on areas of high movement of pedestrian traffic. They should bemovement of pedestrian traffic. They should be separated from the vehicular traffic by safety curbs (in rural areas) and by raised footpath or curbs (in urban areas).The width of the footpath should be decided according to projection of pedestrian traffic, however, a minimum clear width(excluding the width of railings) of 1.0 m footpaths to be provided, where necessary.
  • 74. NEPAL BRIDGE STANDARDS-2067 6.0 CLEARANCES 6.1 VERTICAL CLEARANCE • The vertical clearance of structures shall be, • For all roads not less than 4.75 m for through• For all roads not less than 4.75 m for through structures • Overhead wires, poles etc shall be at least 7.0 m above the highest point of the road surface.
  • 75. NEPAL BRIDGE STANDARDS-2067 7.0 BRIDGE CLASSIFICATION Classification of bridges shall be as follows: Culvert : Length up to 6 m Minor Bridge : When length 50 m (with span 25 m )Minor Bridge : When length 50 m (with span 25 m ) Major Bridge : When span >25 m or length >50 m(with smaller spans) Special Bridge : Bridges that require special design considerations, whose construction features(e.g. concrete girder bridges with >50m span, steel trusses > 100m span, arch bridges, suspension bridges, cable- stayed bridges and other nonstandard bridges).
  • 77. General Design Requirements •Design Discharge 100yr Return Period •Linear Waterway •Bridge Span and Length •Vertical Clearances •Max. Scour depth•Max. Scour depth •Width of Carriageway and Footpath •Bridge Superstructure Selection •Geotechnical Investigation •Bridge Foundation Selection •Concept of Design : Working Load, Limit State Design