SlideShare a Scribd company logo
1 of 6
Download to read offline
SUNIL KUMAR YADAV 1
All type and none type question answer
Construction management 12%
From RKS
1. Public works must be of very good quality, because :
a) It is paid in higher rate
b) Project are of higher priority
c) Users are generally public and maintenance is timely difficulty and costly
d) All of above
2. The conception of idea for any construction work is the responsibility of:
a) Owner
b) Engineer
c) Contractor
d) All of these
3. The process of calculating the resources requirement of a project is known as:
a) Scheduling
b) Coordinating
c) Resources aggregation
d) All of these
4. A milestone chart :*
a) Depicts the delay of job
b) Shows the interdependency of various jobs
c) Shows the events in chronological but not in a logical sequence
d) All of the above
5. Milestone chart is an important over :
a) Bar chart
b) PERT
c) CPM
d) All the these
6. Crashing to the project means :
a) Reducing the time of completion by spending more resource
b) Reducing the cost of project by delaying the time of completion
c) Reducing the project size to save the resources
d) All the above
7. Bar chart suitable for:**
a) Large project
b) Major project
c) Minor project
d) All of these
8. Which of the following is an activity :*
a) Concrete cured
b) Wall plastered
c) Excavation for foundation
d) All of the above
9. The bar chart technique is commonly used because it :
a) Is simple to draw and easy to understand
b) Indicates progress clearly
c) Is useful for cost and quality control
d) All the above
10. If the variation amount is in between 10% to 15% of the original contract value then
approval of the variation of cost is done by: *
a) Project manager b) Site in charge
SUNIL KUMAR YADAV 2
c) Department head d) All of the above
11. In Nepal which of the following act contains the provision of health and safety of the
worker
a) Contract Act
b) Industry Act
c) Labour Act
d) All of above
12. In the construction industry arbitration method is used for :*
a) Inviting the tender
b) Opening the tender
c) Awarding the tender
d) None of these
13. Muster roll consist of :
a) Estimating the cost of the project
b) List of material in site
c) List of equipment
d) None of above
14. Which of the following mode of selection is related to procurement of goods?
a) QCBS
b) QBS
c) CBS
d) NONE
D PRADAD
15. The type of construction in which more equipment are used is known as capital intensive
while the construction in which more human labours are used is called :
a) Machine intensive
b) Labour intensive
c) Capital intensive
d) All of the above
16. The main disadvantage of line organization is:
a) Monopoly at top level
b) Rigid structure
c) Delay in communication
d) All of the above
17. The upper portion of horizontal bars in a bar chart indicates
a) Total duration for completion of an activity
b) Progress of work in the specified time
c) Due duration for the completion of an activity
d) All of the above
18. The interrelationship between the functional elements of a programme is achieved
through:
a) Work break down structure
b) Bar charts
c) Gantt chart
d) All of the above
19. PERT technique of network analysis is use full for :
a) Small project
b) Large project
c) Research and development
project
d) All of the above
20. Bar chart is used for minor project ,CPM is used for repetitive work while PERT is used
for:
a) Repetitive type of work
b) Limited time and unlimited resources type of work
c) Uncertainty time and research type of work
d) All of the above
21. For a curve large the variance :
a) Grater will be the uncertainty
SUNIL KUMAR YADAV 3
b) Smaller will be the uncertainty
c) Not related with the uncertainty
d) All of the above
22. The occurrence of the staring of an activity is:
a) Head event
b) Tail event
c) Dual role event
d) All of the above
23. The occurrence of the completion of an activity is called it’s :
a) Head event
b) Tail event
c) Dual role event
d) All of the above
24. CPM adopts :
a) Deterministic approach
b) Probabilistic approach
c) Fantastic approach
d) All of the above
25. In CPM “forward pass” and “backward pass” are used to calculate ………..respectively.
a) Earliest expected time and latest allowable time
b) Latest allowable time and earliest expected time
c) To check float and slack
d) All of the above
26. A fictious activity with zero duration and no cost used to maintain the sequential order of
the activities in network is known as a :
a) Restraint
b) Dummy activity
c) Event
d) All of the above
27. Free float is the :
a) Portion of independent float
b) Portion of positive total float
c) Portion of interfacing float
d) All of the above
28. In CPM :
a) Time optimization is given prime importance
b) Cost optimization is given prime importance
c) Cost is directly proportional to time
d) All of the above
29. Which method is known as minimum cost or maximum time schedules methods :
a) PERT
b) CPM
c) Bar chart
d) All of the above
30. Higher standers deviations means :
a) Lower uncertainty
b) Medium uncertainty
c) Higher uncertainty
d) All of the above
31. Which one is not required for sealed quotation?
a) Rate
b) Bidding
c) Quantity
d) All of the above
32. If a contractor is found corrupt for tender work then what should be done by the
concerned office
a) His tender is canceled
b) Way to legal count
c) Fine is charged
d) All of the above
33. Local tender is not favorable due to following reasons :
SUNIL KUMAR YADAV 4
a) Unknown about foreign material
b) Most of the material used locally
c) Engineer or site in charge pressured
d) all of the above
34. Generally in GON office, what is the main intention of office chief :
a) Direct purchase
b) Bidding
c) Sealed quotation
d) All of the above
35. The most critical stage of a construction is construction of :
a) Foundation
b) Plinth level
c) Beams and slab
d) All of the above
36. If the height of the frequency distribution underneath is equal to unity then curve is
known as :
a) Normal distribution curve
b) Skew curve
c) Probability distribution curve
d) All of the above
37. The increase in price of materials during the construction is called :
a) Escalation
b) Descalation
c) Devaluation
d) All of the above
38. In many project responsibility of safety is given to:
a) Contractor
b) Clint
c) Individual
d) All of the above
39. Evaluation of of work is done to get as well as reform the expected output. the type of
evaluation which is done before the implementation is known as :
a) Ex –ante
b) On –going
c) Ex –post
d) All of the above
40. Due to omission of any component of the project the cost of project :
a) Increase
b) Decrease
c) Constant
d) All of the above
41. Indirect cost of the project :
a) Decrease with duration
b) Decrease up to optimum duration and then increase with duration
c) Increase with duration
d) All of the above
42. An offer in writing to execute some specified civil works at certain rates within a fixed
time under certain conditions of contract is :
a) Contract
b) Bid
c) Proposal
d) All of the above
43. The purposes of preparing job layout for a construction project is :
a) More economical method of working
b) Reduction in wastage and determination of materials
c) Higher productivity from labour and machinery
d) All of the above
44. Choose the incorrect statement :
a) Arrow representing activity in CPM network is drawn without any scale
SUNIL KUMAR YADAV 5
b) Head of an activity represents the finish of an activity
c) Tail of an activity represents the start of an activity
d) None of the above
45. The activity which consumes maximum time is called :
a) Critical activity
b) Non critical activity
c) Super critical activity
d) None of the above
46. The activity which consumes maximum time is called :
e) Event
f) Node
g) Critical
h) None of the above
R Agar
47. Which one of the following represents an event?
a) Concrete cured
b) Fixing of door
c) Plastering of wall
d) Selecting sites
e) All the above
48. Pick up the incorrect statement from following
a) The difference between the earliest start time and latest finish time of any activity , is
the maximum time available for the activity
b) The difference between the maximum time available for the job and actual time it
consumes is called total float
c) The difference between the latest start time and earliest start time of any activity , is
called total float
d) The difference between the earliest finish time of an activity and the earliest start time
of it’s succession activity is called free float of the activity
e) None of these
All the best
SUNIL KUMAR YADAV 6
Answer:
1 B 11 C 21 A 31 B 41 C
2 A 12 D 22 B 32 A 42 A
3 C 13 D 23 A 33 C 43 B
4 C 14 D 24 A 34 A 44 D
5 A 15 B 25 A 35 A 45 D
6 A 16 A 26 B 36 A 46 D
7 C 17 B 27 B 37 A 47 A
8 C 18 A 28 B 38 A 48 E
9 A 19 C 29 B 39 A
10 C 20 C 30 C 40 B

More Related Content

Similar to Construction Management Questions

6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costingMani Das
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2Narayan Mane
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
Mine Rescue and Safety Engineering.pdf
Mine Rescue and Safety Engineering.pdfMine Rescue and Safety Engineering.pdf
Mine Rescue and Safety Engineering.pdffazl ullah
 
150013826 pmp-questions
150013826 pmp-questions150013826 pmp-questions
150013826 pmp-questionsnirmanpatel
 
150013826 pmp-questions - copy (3)
150013826 pmp-questions - copy (3)150013826 pmp-questions - copy (3)
150013826 pmp-questions - copy (3)nirmanpatel
 
150013826 pmp-questions - copy (2)
150013826 pmp-questions - copy (2)150013826 pmp-questions - copy (2)
150013826 pmp-questions - copy (2)nirmanpatel
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Suma Kamadod
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...Suma Kamadod
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Suma Kamadod
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...Suma Kamadod
 
Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...Suma Kamadod
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Suma Kamadod
 
Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Suma Kamadod
 
Project Management - _____________ generates ideas for quality improvements...
Project Management -   _____________ generates ideas for quality improvements...Project Management -   _____________ generates ideas for quality improvements...
Project Management - _____________ generates ideas for quality improvements...Suma Kamadod
 
Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Suma Kamadod
 

Similar to Construction Management Questions (20)

ME REVIEWER
ME REVIEWERME REVIEWER
ME REVIEWER
 
6.eastimating and costing
6.eastimating and costing6.eastimating and costing
6.eastimating and costing
 
Project Management
Project ManagementProject Management
Project Management
 
cm qsn.pdf
cm qsn.pdfcm qsn.pdf
cm qsn.pdf
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
Mine Rescue and Safety Engineering.pdf
Mine Rescue and Safety Engineering.pdfMine Rescue and Safety Engineering.pdf
Mine Rescue and Safety Engineering.pdf
 
150013826 pmp-questions
150013826 pmp-questions150013826 pmp-questions
150013826 pmp-questions
 
150013826 pmp-questions - copy (3)
150013826 pmp-questions - copy (3)150013826 pmp-questions - copy (3)
150013826 pmp-questions - copy (3)
 
150013826 pmp-questions - copy (2)
150013826 pmp-questions - copy (2)150013826 pmp-questions - copy (2)
150013826 pmp-questions - copy (2)
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...
 
Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...
 
Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...Project Management - Complication to the critical path represents the formati...
Project Management - Complication to the critical path represents the formati...
 
Project Management - _____________ generates ideas for quality improvements...
Project Management -   _____________ generates ideas for quality improvements...Project Management -   _____________ generates ideas for quality improvements...
Project Management - _____________ generates ideas for quality improvements...
 
Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...Project Management - Initiating involves developing a project charter and pre...
Project Management - Initiating involves developing a project charter and pre...
 

More from Mani Das

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1Mani Das
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,bMani Das
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067Mani Das
 
1.5 class c,d,e
1.5 class c,d,e1.5 class c,d,e
1.5 class c,d,eMani Das
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asstMani Das
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete noteMani Das
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 averageMani Das
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classificationMani Das
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chartMani Das
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoningMani Das
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogyMani Das
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrologyMani Das
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport convertedMani Das
 
Group d converted
Group d convertedGroup d converted
Group d convertedMani Das
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicueMani Das
 
7.surveying
7.surveying7.surveying
7.surveyingMani Das
 
3.structure engineering
3.structure engineering3.structure engineering
3.structure engineeringMani Das
 
2.concrete technology
2.concrete technology2.concrete technology
2.concrete technologyMani Das
 

More from Mani Das (20)

201911121130435dca470798b5a1
201911121130435dca470798b5a1201911121130435dca470798b5a1
201911121130435dca470798b5a1
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
Nepal bridge standards 2067
Nepal bridge standards 2067Nepal bridge standards 2067
Nepal bridge standards 2067
 
1.5 class c,d,e
1.5 class c,d,e1.5 class c,d,e
1.5 class c,d,e
 
Survey handsout question for sub er and asst
Survey handsout question for sub er and asstSurvey handsout question for sub er and asst
Survey handsout question for sub er and asst
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
 
Chapter 5 average
Chapter 5 averageChapter 5 average
Chapter 5 average
 
Chap 2 classification
Chap 2 classificationChap 2 classification
Chap 2 classification
 
Chap 1 table chart
Chap 1 table chartChap 1 table chart
Chap 1 table chart
 
Chap 1 arithmetical reasoning
Chap 1 arithmetical reasoningChap 1 arithmetical reasoning
Chap 1 arithmetical reasoning
 
Chap 1 analogy
Chap 1 analogyChap 1 analogy
Chap 1 analogy
 
Irrigation and hydrology
Irrigation and hydrologyIrrigation and hydrology
Irrigation and hydrology
 
High way
High wayHigh way
High way
 
Group c airport converted
Group c airport convertedGroup c airport converted
Group c airport converted
 
Group d converted
Group d convertedGroup d converted
Group d converted
 
9.epp
9.epp9.epp
9.epp
 
8.drawing technicue
8.drawing technicue8.drawing technicue
8.drawing technicue
 
7.surveying
7.surveying7.surveying
7.surveying
 
3.structure engineering
3.structure engineering3.structure engineering
3.structure engineering
 
2.concrete technology
2.concrete technology2.concrete technology
2.concrete technology
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Construction Management Questions

  • 1. SUNIL KUMAR YADAV 1 All type and none type question answer Construction management 12% From RKS 1. Public works must be of very good quality, because : a) It is paid in higher rate b) Project are of higher priority c) Users are generally public and maintenance is timely difficulty and costly d) All of above 2. The conception of idea for any construction work is the responsibility of: a) Owner b) Engineer c) Contractor d) All of these 3. The process of calculating the resources requirement of a project is known as: a) Scheduling b) Coordinating c) Resources aggregation d) All of these 4. A milestone chart :* a) Depicts the delay of job b) Shows the interdependency of various jobs c) Shows the events in chronological but not in a logical sequence d) All of the above 5. Milestone chart is an important over : a) Bar chart b) PERT c) CPM d) All the these 6. Crashing to the project means : a) Reducing the time of completion by spending more resource b) Reducing the cost of project by delaying the time of completion c) Reducing the project size to save the resources d) All the above 7. Bar chart suitable for:** a) Large project b) Major project c) Minor project d) All of these 8. Which of the following is an activity :* a) Concrete cured b) Wall plastered c) Excavation for foundation d) All of the above 9. The bar chart technique is commonly used because it : a) Is simple to draw and easy to understand b) Indicates progress clearly c) Is useful for cost and quality control d) All the above 10. If the variation amount is in between 10% to 15% of the original contract value then approval of the variation of cost is done by: * a) Project manager b) Site in charge
  • 2. SUNIL KUMAR YADAV 2 c) Department head d) All of the above 11. In Nepal which of the following act contains the provision of health and safety of the worker a) Contract Act b) Industry Act c) Labour Act d) All of above 12. In the construction industry arbitration method is used for :* a) Inviting the tender b) Opening the tender c) Awarding the tender d) None of these 13. Muster roll consist of : a) Estimating the cost of the project b) List of material in site c) List of equipment d) None of above 14. Which of the following mode of selection is related to procurement of goods? a) QCBS b) QBS c) CBS d) NONE D PRADAD 15. The type of construction in which more equipment are used is known as capital intensive while the construction in which more human labours are used is called : a) Machine intensive b) Labour intensive c) Capital intensive d) All of the above 16. The main disadvantage of line organization is: a) Monopoly at top level b) Rigid structure c) Delay in communication d) All of the above 17. The upper portion of horizontal bars in a bar chart indicates a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above 18. The interrelationship between the functional elements of a programme is achieved through: a) Work break down structure b) Bar charts c) Gantt chart d) All of the above 19. PERT technique of network analysis is use full for : a) Small project b) Large project c) Research and development project d) All of the above 20. Bar chart is used for minor project ,CPM is used for repetitive work while PERT is used for: a) Repetitive type of work b) Limited time and unlimited resources type of work c) Uncertainty time and research type of work d) All of the above 21. For a curve large the variance : a) Grater will be the uncertainty
  • 3. SUNIL KUMAR YADAV 3 b) Smaller will be the uncertainty c) Not related with the uncertainty d) All of the above 22. The occurrence of the staring of an activity is: a) Head event b) Tail event c) Dual role event d) All of the above 23. The occurrence of the completion of an activity is called it’s : a) Head event b) Tail event c) Dual role event d) All of the above 24. CPM adopts : a) Deterministic approach b) Probabilistic approach c) Fantastic approach d) All of the above 25. In CPM “forward pass” and “backward pass” are used to calculate ………..respectively. a) Earliest expected time and latest allowable time b) Latest allowable time and earliest expected time c) To check float and slack d) All of the above 26. A fictious activity with zero duration and no cost used to maintain the sequential order of the activities in network is known as a : a) Restraint b) Dummy activity c) Event d) All of the above 27. Free float is the : a) Portion of independent float b) Portion of positive total float c) Portion of interfacing float d) All of the above 28. In CPM : a) Time optimization is given prime importance b) Cost optimization is given prime importance c) Cost is directly proportional to time d) All of the above 29. Which method is known as minimum cost or maximum time schedules methods : a) PERT b) CPM c) Bar chart d) All of the above 30. Higher standers deviations means : a) Lower uncertainty b) Medium uncertainty c) Higher uncertainty d) All of the above 31. Which one is not required for sealed quotation? a) Rate b) Bidding c) Quantity d) All of the above 32. If a contractor is found corrupt for tender work then what should be done by the concerned office a) His tender is canceled b) Way to legal count c) Fine is charged d) All of the above 33. Local tender is not favorable due to following reasons :
  • 4. SUNIL KUMAR YADAV 4 a) Unknown about foreign material b) Most of the material used locally c) Engineer or site in charge pressured d) all of the above 34. Generally in GON office, what is the main intention of office chief : a) Direct purchase b) Bidding c) Sealed quotation d) All of the above 35. The most critical stage of a construction is construction of : a) Foundation b) Plinth level c) Beams and slab d) All of the above 36. If the height of the frequency distribution underneath is equal to unity then curve is known as : a) Normal distribution curve b) Skew curve c) Probability distribution curve d) All of the above 37. The increase in price of materials during the construction is called : a) Escalation b) Descalation c) Devaluation d) All of the above 38. In many project responsibility of safety is given to: a) Contractor b) Clint c) Individual d) All of the above 39. Evaluation of of work is done to get as well as reform the expected output. the type of evaluation which is done before the implementation is known as : a) Ex –ante b) On –going c) Ex –post d) All of the above 40. Due to omission of any component of the project the cost of project : a) Increase b) Decrease c) Constant d) All of the above 41. Indirect cost of the project : a) Decrease with duration b) Decrease up to optimum duration and then increase with duration c) Increase with duration d) All of the above 42. An offer in writing to execute some specified civil works at certain rates within a fixed time under certain conditions of contract is : a) Contract b) Bid c) Proposal d) All of the above 43. The purposes of preparing job layout for a construction project is : a) More economical method of working b) Reduction in wastage and determination of materials c) Higher productivity from labour and machinery d) All of the above 44. Choose the incorrect statement : a) Arrow representing activity in CPM network is drawn without any scale
  • 5. SUNIL KUMAR YADAV 5 b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 45. The activity which consumes maximum time is called : a) Critical activity b) Non critical activity c) Super critical activity d) None of the above 46. The activity which consumes maximum time is called : e) Event f) Node g) Critical h) None of the above R Agar 47. Which one of the following represents an event? a) Concrete cured b) Fixing of door c) Plastering of wall d) Selecting sites e) All the above 48. Pick up the incorrect statement from following a) The difference between the earliest start time and latest finish time of any activity , is the maximum time available for the activity b) The difference between the maximum time available for the job and actual time it consumes is called total float c) The difference between the latest start time and earliest start time of any activity , is called total float d) The difference between the earliest finish time of an activity and the earliest start time of it’s succession activity is called free float of the activity e) None of these All the best
  • 6. SUNIL KUMAR YADAV 6 Answer: 1 B 11 C 21 A 31 B 41 C 2 A 12 D 22 B 32 A 42 A 3 C 13 D 23 A 33 C 43 B 4 C 14 D 24 A 34 A 44 D 5 A 15 B 25 A 35 A 45 D 6 A 16 A 26 B 36 A 46 D 7 C 17 B 27 B 37 A 47 A 8 C 18 A 28 B 38 A 48 E 9 A 19 C 29 B 39 A 10 C 20 C 30 C 40 B