SlideShare a Scribd company logo
1 of 4
Download to read offline
G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and
                   Applications (IJERA) ISSN: 2248-9622 www.ijera.com
                     Vol. 3, Issue 1, January -February 2013, pp.533-536
 Back flashover Analysis Improvement of a 220KV Transmission
                             Line
                                G.Radhika1, Dr.M.Suryakalavathi2
              1
                  (Department of Electrical & Electronics Engineering, VNR VJIET. Hyderabad - 90)
                    2
                      (Department of Electrical & Electronics Engineering, JNTU Hyderabad - 85)


ABSTRACT
         The performance of a power system                 outages and damage of equipment. Because of high
mainly depends on the performance of the                   frequency range associated with lightning transients
transmission lines for which continues operation           phenomena, adequate electrical models are required
of transmission lines without sudden outages is            for which reasons, and simulation studies require
important for the performance in the view point            detailed modeling of the lightning phenomena and of
of power delivery as well as system stability.             the network components, including towers and
Lightning effects on transmission lines are one of         insulators that are not usually considered in the other
the major reasons which lead to sudden line                models. Hence the method used to analyze the
outages. The objective of this paper is to design a        increase in voltage due to lightning was done by
220kV transmission model, which includes all the           using the application called PSCAD/ EMTDC.
components of the Transmission line with a surge                     Back flashover occurs when lightning
of 100KA, 4/10 µs. Tower with two OHGW was                 stroke terminates on the overhead ground wire or
taken in this work. Back flash over mechanism is           tower. A stroke that so terminates forces currents to
modeled and triggered to the existing system by            flow down the tower and out on the ground wires.
an external control module with powerful                   Thus voltages are built up across the line insulation.
electrical tool PSCAD/EMTDC. Metal Oxide                   If these voltages equal or exceed the line critical
transmission line arresters were used in this work         flashover voltage (CFO), flashover occurs. Study on
as a solution for the back flashover. However,             back flashover is very important to evaluate
considering acceptable probabilistic failure as            lightning performance as majority of lightning
one outage per year per 100km line length, and             strokes terminate on shield wire than phase
suggested basic insulation level (BIL) of 1050KV,          conductor. The objective is to protect the power
the arrester rating was calculated to be 196KV             system equipments from Back flashover [6]. As per
and its parametric determination for a one                 analysis the occurrence of faults is more in overhead
column arrester with an overall length of 1.45             transmission lines, so this paper study is mainly
meters is done. Simulation is carried out by               based on transmission line protection rather than
placing line arresters in one phase and recovering         other equipments. The ideal approach to study the
the string voltage without interrupting power to           transient phenomena in a power system is to capture
the consumers.                                             and record the transients using wide bandwidth
                                                           transducers and recording equipment and then
Keywords - Back flash over, Line Arresters,                analyze those waveforms [8].
Transmission lines,       Tower   footing resistance,
PSCASD/ EMTDC.                                             II.MODELING                  OF          FOOTING
                                                           RESISTANCE
I. INTRODUCTION                                               Tower footing resistance is determined using
         Lightning could causes the traveling waves        current dependence of tower footing resistance [1,
to different devices connected to both sides of            4].
transmission line and causes temporary over voltage         Tower footing resistance is given by
                                                                   𝐑𝟎
in transmission line system which is harmful for            𝐑𝐭 =                                   (1)
                                                                      𝐈
insulators of lines and devices connected to the                  𝟏+
                                                                       𝐈𝐠
transmission line. Thus it is essential to investigate a
lightning surge for a reliable operation of a power              1 E
                                                           Ig = 2Π R 0 ρ                            (2)
                                                                     2
system, because the lightning surge over voltage is                    0
dominant factor for the insulation design of power         Where, parameters
system and protection of equipment in power system            Rt = tower footing resistance,
and substation. Whenever lightning strikes the top of      R0= tower footing resistance at low current and low
a transmission tower, a lightning current flows down       frequency,
to the bottom of the tower and causes a tower              I = lightning current, kA,
voltage to raise and results in a back-flashover           Ig = limiting current, kA,
across an arc horn. This causes transmission line          ρ = soil resistivity, Pm,



                                                                                                  533 | P a g e
G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and
                        Applications (IJERA) ISSN: 2248-9622 www.ijera.com
                           Vol. 3, Issue 1, January -February 2013, pp.533-536
E0 = soil ionization gradient,                          IV. Modeling of Back flashover
(≈300kV/m)                                                         Line insulators from tower to conductors
Tower footing resistance depends on                      can be represented as a capacitor. In this study, the
1. Type of electrode configuration                       tower to conductor has equivalent capacitor of 80 pf
2. Soil resistivity                                      per unit. The transient-voltage withstands level of a
Soil resistivity has the following ranges                power apparatus is not a unique number [1]. An
                                                         apparatus may withstand a high transient voltage
Table 1: Soil Resistivity of                             which has a short duration even it has failed to
             Sea water              10 Ωm                withstand a lower transient voltage with longer
                                                         duration.       This characteristic of the insulator is
             Moist soil             100 Ωm               known as the volt-time characteristic of the
                                    1000                 insulation however, simplified expression for the
             Loose soil and clay                         insulator voltage withstands capability can be
                                    Ωm
                                                         calculated as
                                    >100                                 𝐾2
             Rock                                         𝑉𝑓𝑜 = 𝐾1 + 𝑡 0.75              (7)
                                    Ωm
                                                         Where, Vfo is a flashover voltage (kV),
         Tower with one OHGW leads to high               K1 is 400*L, and K2 is 710*L,
overvoltage across insulator compared to two             L is insulator length, (meter),
OHGW [6]. If the tower footing resistance is high        t is elapsed time after lightning stroke, μs
then occurrence of back flash over is also high and                The back flashover mechanism of the
vice- versa because of which we considered two           insulators can be represented by volt-time curves.
OHGW transmission system in this paper.                  Whenever back flashover occurs, a parallel switch is
                                                         applied and also if the voltage across the insulator
III. Modeling of Insulator                               exceeds the insulator voltage withstand capability,
            The insulator string model can be based on   the back flashover occurs. The back flashover is
the leader progression model. Streamers propagate        simulated by closing the parallel switch. Once the
along the insulator string when the applied voltage      back flashover occurs, the voltage across insulator
exceeds the corona inception voltage, if the voltage     goes down to zero [2].
remains high enough these streamers will become a
leader channel. A flashover occurs when the leader       V. Modeling of the tower
crosses the gap between the cross-arm and the                      The configuration of a transmission line
conductor [7]. The total time to flashover can be        tower depends on:
expressed as                                             (a) The length of the insulator assembly.
Tt = tc+ts+tl                        (3)                 (b) The minimum clearances to be maintained
Where,                                                   between conductors and between conductor and
 tc is the corona inception time,                        tower.
 ts is the streamer propagation time,                    (c) The location of ground wire or wires with respect
 tl is the leader propagation time.                      to the outermost conductor.
                                                         (d) The mid span clearance required from
Usually tc is neglected, while ts is calculated as       considerations of the dynamic behavior of
          𝐸50                                            conductors and lightning protection of the line.
𝑡𝑠 =                               (4)
       1.2𝐸−0.95𝐸50                                      (e) The minimum clearance of the lower conductor
The leader propagation time tl, can be obtained using    above ground level.
𝑑𝑙                    𝑣 𝑡
     = 𝑘∗ 𝑣 𝑡 ∗             − 𝐸      (5)                           From     safety considerations,        power
𝑑𝑡                    𝑔−𝑙
Where,                                                   conductors along the route of the transmission line
 V (t) is the voltage across the gap,                    should maintain clearances to ground in open
g is the gap length,                                     country, national highway, rivers, railway tracks,
L is the leader length,                                  tele-communication lines, other power lines etc. as
E is the critical leader inception gradient and k is a   laid down in the Indian Electricity Rule or standards
leader coefficient and is given in reference.            or code of practice in vogue. Minimum permissible
The insulator (string) voltage is given by               ground clearance for a 220KV as per IE Rules, 1956,
Vins = Vcnt- - Vb                     (6)                Rule 77(4) is 7.01m. The maximum working tension
Where,                                                   under stringent loading conditions shall not exceed
       Vcnt = cross arm voltage                          50 percent of the ultimate tensile strength or
       Vb = line voltage                                 conductor. Sag-Tension computations made for final
The number of insulating discs used for a 220KV          stringing of the conductors therefore must ensure
tower are14 as per the IEEE standards.                   that factor of safety of 2 and 4 are obtainable under
                                                         maximum loading condition and every day loading
                                                         condition, respectively.



                                                                                                534 | P a g e
G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and
                  Applications (IJERA) ISSN: 2248-9622 www.ijera.com
                   Vol. 3, Issue 1, January -February 2013, pp.533-536
VI. Selection of Transmission Lightening        provide protection against back flashovers . Since
Arrestors                                       the line has to be protected from back flashovers,
          A line arrester is a one which reduce the      effective operation of the breakers is essential. To
risk of insulator flashover during surge events          control the operation of the two breakers in the sub-
[7].Arrestor Voltage rating shall not be less than       circuit logic was implemented. With this we have
product of system highest voltage x co-efficient of      designed one insulator. Three such insulators were
earthing [6].                                            designed as per the tower sub-circuit. As our model
In a 220 kV effectively earthed system                   includes three such towers, we have designed a
Highest system voltage               = 245 KV            model with three towers in it.
Co-efficient of earthing             = 80%
Arrestor voltage rating = 245x0.8 = 196 KV.
In this paper, only the electrical parameters of the
arrester are taken for the modeling.

VII. Proposed Model of 220KV Transmission
System and Results
          The below model shows a 220KV
transmission system with two wires, whose sub-
circuit of the tower further consistutes of five sub-
circuits. These five sub-circuits includes the three
insulator strings and the two cross arms as shown in
the figure. These five sub-circuits have to be
designed seperately. Over the system a lightning
surge of 100KA was induced and the resulting
simulation was carried out in powerful electrical tool
PSCAD.                                                   Figure: 3 Tower Sub Circuit




                                                         Figure: 4 Tower voltage




Figure: 1 Proposed Model


                                                         Figure: 5 String Voltage

                                                                   As the string voltage become zero, which
                                                         means that an arc is being formed. This means that
                                                         flashover is occuring. Hence, that particular line is
                                                         going to the outage state. This is undesirable as it
                                                         interrupts the power supply to the consumers. So we
Figure: 2 Output of Phase B                              take the next set of observations with the Line
                                                         Arrestor turned ON along with flashover in all the
         The sub circit of the tower structure shown     three phases. The wave form with flash over and
below, to which when flashover is turned ON, the         arrestor turned ON on phase B are observed:
outputs of tower, line and string voltages can also be
observed below. The insulator sub-circuit has metal
oxide surge arresters as a part of the circuit to



                                                                                               535 | P a g e
G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and
                      Applications (IJERA) ISSN: 2248-9622 www.ijera.com
                        Vol. 3, Issue 1, January -February 2013, pp.533-536
                                                                   Engineering and Application, ICHVE ,
                                                                   2008, 9-12 Nov.
                                                            [4].   C.J.Coelho Teixera and A. Machado e
                                                                   Moura, “Study of the Back Flashover
                                                                   Phenomena in Overhead Transmission
                                                                   Lines using the EMTP”, IEEE PES
                                                                   Transmission and Distribution Conference
                                                                   and Exposition, Latin America, TDC 06,
                                                                   IEEE/PES.
                                                            [5].   M.H.Shwehdi, “Computation of Lightning
Figure: 6 Recovered String Voltage after placing                   Flashovers and Back Flashover Voltage
TLA.                                                               Levels on 230KV Transmission        Lines”,
                                                                   2nd IEEE International conference on
VIII. CONCLUSION                                                   Power and Energy (PECon 08), December
          The tower footing resistance is an                       1-3, 2008, Johor Baharu, Malaysia.
extremely important parameter in determination of           [6].   Akihiro Ametani,        Naoto Nagaoka,
lightning flashover rates which was taken as 10Ω in                Toshihisa Funabashi and Nagahiro Inoue,
this work for all the towers.. The lower the tower                 “Tower Structure Effect on a Back-
footing resistance, the more negative reflections                  Flashover Phase”. International Conference
produced from tower base towards the tower top and                 on Power      Systems Transients (IPST’05)
these hence help to lower the peak voltage at the                  Montreal, Canada, June 19-23, 2005.
tower top. Soil resistivity also plays a very important     [7].   Mohd Z.A Ab Kadir, Zawati Mohd Nawi
role in determining lightning flashover rates which                and Junainah Sardi “Numerical Modeling
was 100 Ωm and relative ground permeability was                    and Simulation       in Electro Magnetic
1.0 in this work. Surge arrester selection plays vital             Transient Program for Estimating      Line
key role in arresting the insulator flashovers which               Back Flashover Performance” Engineering
was calcualted to be 196KV in this work. The                       Letters, 18:4, EL_18_4_04, Advance
placement of transmission line arrestors and design                Online Publication: 23 November 2010.
of arrestor is crucial in arresting the flashovers.         [8].   Manitoba HVDC Research Centre,
From the above simulated resulsts, when arrester and               “Introduction to PSCAD/EMTDCV 4.0,”
flashover were OFF the tower voltage, string voltage               Manitoba Research Centre Inc. 2003.
were normal and when flashvoer was ON and
arrester was OFF the string voltge of phase B was         BIOGRAPHY OF AUTHORS
gone outage as seen in Fig.5 which is undesirable as
it interrupts the power supply to the consumers.
Hence when arrester was ON in phase B, the string
voltage of phase B was recovered as shown in Fig. 6.
Hence by placing one arrestor on each phase and
by using two ground wires, we can completely                            Mrs.G.Radhika is working as Senior
eliminate the flashover, which means zero                 Assistant Professor in Electrical and Electronics
probability of flashovers.                                Engineering Department at VNR Vignana Jyothi
                                                          Institute of Engineering and Technology,
REFERENCES                                                Hyderabad, India. She is pursuing her Ph.D at
  [1].     P. Yadee and S. Premrudeepreechacharn,         J.N.T.University Hyderabad.
           “Analysis of Tower Footing Resistance
           Effected Back Flashover across Insulator
           in a Transmission System” International
           Conference on Power Systems Transients
           (IPST’07) in Lyon, France on June 4-7,
           2007
  [2].     M. Kizilcay and C. Neumann “Back                           Dr.M.Suryakalavathi is professor in
           Flashover Analysis for 110KV Lines at          Electrical and Electronics Engineering Department
           Multi-Circuit Overhead Line Towers”            at Jawaharlal Nehru Technological University
           International Conference on Power Systems      Hyderabad, India. She received her Ph.D from
           Transients (IPST’07) in Lyon, France on        J.N.T.University Hyderabad and Post Doctoral
           June 4-7, 2007                                 degree from prestigious Carnegie Melon University
  [3].     P. Liu, G.N. Wu, B. Sui, R.F. Li and X.B.      U.S.A.
           Kao, “Modeling Lightning Performance of
           Transmission Systems using       PSCAD”
           International Conference on High Voltage



                                                                                               536 | P a g e

More Related Content

What's hot

Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line BasicsJohn Williams
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission linesHamzaAbbas43
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performancefiraoltemesgen1
 
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...IJAPEJOURNAL
 
Presentation topic is transmission line
Presentation topic is transmission linePresentation topic is transmission line
Presentation topic is transmission linemd muzahidul haque
 
Lecture 09 transmission lines
Lecture 09   transmission linesLecture 09   transmission lines
Lecture 09 transmission linesbhaavan22
 
EE8402 Transmission and Distribution
EE8402 Transmission and DistributionEE8402 Transmission and Distribution
EE8402 Transmission and Distributionrmkceteee
 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides barularumugam09
 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basicsbhaavan22
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentGilberto Mejía
 
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Gilberto Mejía
 
Microwave engineering full
Microwave engineering fullMicrowave engineering full
Microwave engineering fulllieulieuw
 
Types of transmission lines
Types of transmission linesTypes of transmission lines
Types of transmission linesSelf-employed
 
Microwave propagation in ferrites 23
Microwave propagation in ferrites 23Microwave propagation in ferrites 23
Microwave propagation in ferrites 23HIMANSHU DIWAKAR
 

What's hot (20)

Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line Basics
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
Overvoltages 1
Overvoltages 1Overvoltages 1
Overvoltages 1
 
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
Towards An Accurate Modeling of Frequency-dependent Wind Farm Components Unde...
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
 
Presentation topic is transmission line
Presentation topic is transmission linePresentation topic is transmission line
Presentation topic is transmission line
 
Lecture 09 transmission lines
Lecture 09   transmission linesLecture 09   transmission lines
Lecture 09 transmission lines
 
EE8402 Transmission and Distribution
EE8402 Transmission and DistributionEE8402 Transmission and Distribution
EE8402 Transmission and Distribution
 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides b
 
K046016266
K046016266K046016266
K046016266
 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basics
 
Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
 
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
Swartley b santinia_maled_jaccinob-destructive-arcong-of-insulated-joints-in-...
 
[IJET V2I2P26] Authors: Pruthak C. Chauhan., Rinkesh S. Kansara, Mukesh P. Pa...
[IJET V2I2P26] Authors: Pruthak C. Chauhan., Rinkesh S. Kansara, Mukesh P. Pa...[IJET V2I2P26] Authors: Pruthak C. Chauhan., Rinkesh S. Kansara, Mukesh P. Pa...
[IJET V2I2P26] Authors: Pruthak C. Chauhan., Rinkesh S. Kansara, Mukesh P. Pa...
 
Microwave engineering full
Microwave engineering fullMicrowave engineering full
Microwave engineering full
 
Chap2 s11b
Chap2 s11bChap2 s11b
Chap2 s11b
 
Lec transmission line
Lec transmission lineLec transmission line
Lec transmission line
 
Types of transmission lines
Types of transmission linesTypes of transmission lines
Types of transmission lines
 
Microwave propagation in ferrites 23
Microwave propagation in ferrites 23Microwave propagation in ferrites 23
Microwave propagation in ferrites 23
 

Viewers also liked

E xpresionismo abstracto
E xpresionismo abstractoE xpresionismo abstracto
E xpresionismo abstractosilvia PEREZ
 
Práctica de word
Práctica de wordPráctica de word
Práctica de wordUTPL
 
Utpl
UtplUtpl
Utpl69sky
 
Prevención de la adicción al alcoholismo
Prevención de la adicción al alcoholismoPrevención de la adicción al alcoholismo
Prevención de la adicción al alcoholismoJuan Yoplac Huaman
 
Realidad nacional y ambiental
Realidad nacional y ambientalRealidad nacional y ambiental
Realidad nacional y ambientalJhoanaRamirez
 
Planificação
PlanificaçãoPlanificação
Planificaçãocmtu cmtu
 
Semana Cultural Científica
Semana Cultural CientíficaSemana Cultural Científica
Semana Cultural CientíficaJeniferRibeiiro
 
Fase de planificación belkys
Fase de planificación belkysFase de planificación belkys
Fase de planificación belkysbelkisrodriguez
 
Trabajo de las fuentes de alimentacion
Trabajo de las fuentes de alimentacionTrabajo de las fuentes de alimentacion
Trabajo de las fuentes de alimentacionKelly Soto
 
Practica de word
Practica de wordPractica de word
Practica de wordcarluzsal
 
Desarrollo de la actividad numero 2
Desarrollo de la actividad numero 2Desarrollo de la actividad numero 2
Desarrollo de la actividad numero 2Kelly Soto
 
Por que duvidam da evolução
Por que duvidam da evoluçãoPor que duvidam da evolução
Por que duvidam da evoluçãoNelson Hfilho
 

Viewers also liked (20)

Cc31523526
Cc31523526Cc31523526
Cc31523526
 
E xpresionismo abstracto
E xpresionismo abstractoE xpresionismo abstracto
E xpresionismo abstracto
 
Práctica de word
Práctica de wordPráctica de word
Práctica de word
 
Práctica de word
Práctica de wordPráctica de word
Práctica de word
 
Utpl
UtplUtpl
Utpl
 
Prevención de la adicción al alcoholismo
Prevención de la adicción al alcoholismoPrevención de la adicción al alcoholismo
Prevención de la adicción al alcoholismo
 
Realidad nacional y ambiental
Realidad nacional y ambientalRealidad nacional y ambiental
Realidad nacional y ambiental
 
Ser fuerte
Ser fuerteSer fuerte
Ser fuerte
 
Planificação
PlanificaçãoPlanificação
Planificação
 
Semana Cultural Científica
Semana Cultural CientíficaSemana Cultural Científica
Semana Cultural Científica
 
Fase de planificación belkys
Fase de planificación belkysFase de planificación belkys
Fase de planificación belkys
 
Trabajo de las fuentes de alimentacion
Trabajo de las fuentes de alimentacionTrabajo de las fuentes de alimentacion
Trabajo de las fuentes de alimentacion
 
Equação2grau
Equação2grauEquação2grau
Equação2grau
 
Presentacion natalia
Presentacion nataliaPresentacion natalia
Presentacion natalia
 
Practica de word
Practica de wordPractica de word
Practica de word
 
Tics uab
Tics uabTics uab
Tics uab
 
Ni plan de exportación
Ni plan de exportaciónNi plan de exportación
Ni plan de exportación
 
Desarrollo de la actividad numero 2
Desarrollo de la actividad numero 2Desarrollo de la actividad numero 2
Desarrollo de la actividad numero 2
 
Por que duvidam da evolução
Por que duvidam da evoluçãoPor que duvidam da evolução
Por que duvidam da evolução
 
Nonita
NonitaNonita
Nonita
 

Similar to Ce31533536

COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINEIRJET Journal
 
Light Triggering Thyristor for HVDC and other Applications
Light Triggering Thyristor for HVDC and other ApplicationsLight Triggering Thyristor for HVDC and other Applications
Light Triggering Thyristor for HVDC and other ApplicationsIDES Editor
 
SUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptxSUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptxHimanshuShrivastava74
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...IJERA Editor
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...IJERA Editor
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptJatmylHarnero1
 
WIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION ProjectWIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION Projectsagnikchoudhury
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?Fang Sam
 
Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...IDES Editor
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Lineijtsrd
 
TRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptxTRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptxSatish Pydimarla
 
01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdfThien Phan Bản
 
Wireless power transmission
Wireless power transmissionWireless power transmission
Wireless power transmissionVishnu V.m
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptAhmed Ramadan
 

Similar to Ce31533536 (20)

COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINECOMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
COMPENSATION OF FAULT RESISTANCE IN DISTANCE RELAY FOR LONG TRANSMISSION LINE
 
Light Triggering Thyristor for HVDC and other Applications
Light Triggering Thyristor for HVDC and other ApplicationsLight Triggering Thyristor for HVDC and other Applications
Light Triggering Thyristor for HVDC and other Applications
 
SUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptxSUBSTATION DESIGN powerpoint presentation.pptx
SUBSTATION DESIGN powerpoint presentation.pptx
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...
 
Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...Calculation and comparison of circuit breaker parameters in Power World Simul...
Calculation and comparison of circuit breaker parameters in Power World Simul...
 
Short-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.pptShort-Circuit calculation -Ppt-Slides - Copy.ppt
Short-Circuit calculation -Ppt-Slides - Copy.ppt
 
Transmission Line
Transmission LineTransmission Line
Transmission Line
 
Study tour to optcl
Study tour to optclStudy tour to optcl
Study tour to optcl
 
WIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION ProjectWIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION Project
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?
 
H010526975
H010526975H010526975
H010526975
 
Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...Performance of quadrilateral relay on EHV transmission line protection during...
Performance of quadrilateral relay on EHV transmission line protection during...
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
 
Transient Suppressors
Transient SuppressorsTransient Suppressors
Transient Suppressors
 
TRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptxTRANSMISSION LINES and capacity.pptx
TRANSMISSION LINES and capacity.pptx
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf01-120917022737-phpapp02.pdf
01-120917022737-phpapp02.pdf
 
Wireless power transmission
Wireless power transmissionWireless power transmission
Wireless power transmission
 
Introduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.pptIntroduction-to-MV-Design-Guide.ppt
Introduction-to-MV-Design-Guide.ppt
 
00103262
0010326200103262
00103262
 

Ce31533536

  • 1. G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and Applications (IJERA) ISSN: 2248-9622 www.ijera.com Vol. 3, Issue 1, January -February 2013, pp.533-536 Back flashover Analysis Improvement of a 220KV Transmission Line G.Radhika1, Dr.M.Suryakalavathi2 1 (Department of Electrical & Electronics Engineering, VNR VJIET. Hyderabad - 90) 2 (Department of Electrical & Electronics Engineering, JNTU Hyderabad - 85) ABSTRACT The performance of a power system outages and damage of equipment. Because of high mainly depends on the performance of the frequency range associated with lightning transients transmission lines for which continues operation phenomena, adequate electrical models are required of transmission lines without sudden outages is for which reasons, and simulation studies require important for the performance in the view point detailed modeling of the lightning phenomena and of of power delivery as well as system stability. the network components, including towers and Lightning effects on transmission lines are one of insulators that are not usually considered in the other the major reasons which lead to sudden line models. Hence the method used to analyze the outages. The objective of this paper is to design a increase in voltage due to lightning was done by 220kV transmission model, which includes all the using the application called PSCAD/ EMTDC. components of the Transmission line with a surge Back flashover occurs when lightning of 100KA, 4/10 µs. Tower with two OHGW was stroke terminates on the overhead ground wire or taken in this work. Back flash over mechanism is tower. A stroke that so terminates forces currents to modeled and triggered to the existing system by flow down the tower and out on the ground wires. an external control module with powerful Thus voltages are built up across the line insulation. electrical tool PSCAD/EMTDC. Metal Oxide If these voltages equal or exceed the line critical transmission line arresters were used in this work flashover voltage (CFO), flashover occurs. Study on as a solution for the back flashover. However, back flashover is very important to evaluate considering acceptable probabilistic failure as lightning performance as majority of lightning one outage per year per 100km line length, and strokes terminate on shield wire than phase suggested basic insulation level (BIL) of 1050KV, conductor. The objective is to protect the power the arrester rating was calculated to be 196KV system equipments from Back flashover [6]. As per and its parametric determination for a one analysis the occurrence of faults is more in overhead column arrester with an overall length of 1.45 transmission lines, so this paper study is mainly meters is done. Simulation is carried out by based on transmission line protection rather than placing line arresters in one phase and recovering other equipments. The ideal approach to study the the string voltage without interrupting power to transient phenomena in a power system is to capture the consumers. and record the transients using wide bandwidth transducers and recording equipment and then Keywords - Back flash over, Line Arresters, analyze those waveforms [8]. Transmission lines, Tower footing resistance, PSCASD/ EMTDC. II.MODELING OF FOOTING RESISTANCE I. INTRODUCTION Tower footing resistance is determined using Lightning could causes the traveling waves current dependence of tower footing resistance [1, to different devices connected to both sides of 4]. transmission line and causes temporary over voltage Tower footing resistance is given by 𝐑𝟎 in transmission line system which is harmful for 𝐑𝐭 = (1) 𝐈 insulators of lines and devices connected to the 𝟏+ 𝐈𝐠 transmission line. Thus it is essential to investigate a lightning surge for a reliable operation of a power 1 E Ig = 2Π R 0 ρ (2) 2 system, because the lightning surge over voltage is 0 dominant factor for the insulation design of power Where, parameters system and protection of equipment in power system Rt = tower footing resistance, and substation. Whenever lightning strikes the top of R0= tower footing resistance at low current and low a transmission tower, a lightning current flows down frequency, to the bottom of the tower and causes a tower I = lightning current, kA, voltage to raise and results in a back-flashover Ig = limiting current, kA, across an arc horn. This causes transmission line ρ = soil resistivity, Pm, 533 | P a g e
  • 2. G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and Applications (IJERA) ISSN: 2248-9622 www.ijera.com Vol. 3, Issue 1, January -February 2013, pp.533-536 E0 = soil ionization gradient, IV. Modeling of Back flashover (≈300kV/m) Line insulators from tower to conductors Tower footing resistance depends on can be represented as a capacitor. In this study, the 1. Type of electrode configuration tower to conductor has equivalent capacitor of 80 pf 2. Soil resistivity per unit. The transient-voltage withstands level of a Soil resistivity has the following ranges power apparatus is not a unique number [1]. An apparatus may withstand a high transient voltage Table 1: Soil Resistivity of which has a short duration even it has failed to Sea water 10 Ωm withstand a lower transient voltage with longer duration. This characteristic of the insulator is Moist soil 100 Ωm known as the volt-time characteristic of the 1000 insulation however, simplified expression for the Loose soil and clay insulator voltage withstands capability can be Ωm calculated as >100 𝐾2 Rock 𝑉𝑓𝑜 = 𝐾1 + 𝑡 0.75 (7) Ωm Where, Vfo is a flashover voltage (kV), Tower with one OHGW leads to high K1 is 400*L, and K2 is 710*L, overvoltage across insulator compared to two L is insulator length, (meter), OHGW [6]. If the tower footing resistance is high t is elapsed time after lightning stroke, μs then occurrence of back flash over is also high and The back flashover mechanism of the vice- versa because of which we considered two insulators can be represented by volt-time curves. OHGW transmission system in this paper. Whenever back flashover occurs, a parallel switch is applied and also if the voltage across the insulator III. Modeling of Insulator exceeds the insulator voltage withstand capability, The insulator string model can be based on the back flashover occurs. The back flashover is the leader progression model. Streamers propagate simulated by closing the parallel switch. Once the along the insulator string when the applied voltage back flashover occurs, the voltage across insulator exceeds the corona inception voltage, if the voltage goes down to zero [2]. remains high enough these streamers will become a leader channel. A flashover occurs when the leader V. Modeling of the tower crosses the gap between the cross-arm and the The configuration of a transmission line conductor [7]. The total time to flashover can be tower depends on: expressed as (a) The length of the insulator assembly. Tt = tc+ts+tl (3) (b) The minimum clearances to be maintained Where, between conductors and between conductor and tc is the corona inception time, tower. ts is the streamer propagation time, (c) The location of ground wire or wires with respect tl is the leader propagation time. to the outermost conductor. (d) The mid span clearance required from Usually tc is neglected, while ts is calculated as considerations of the dynamic behavior of 𝐸50 conductors and lightning protection of the line. 𝑡𝑠 = (4) 1.2𝐸−0.95𝐸50 (e) The minimum clearance of the lower conductor The leader propagation time tl, can be obtained using above ground level. 𝑑𝑙 𝑣 𝑡 = 𝑘∗ 𝑣 𝑡 ∗ − 𝐸 (5) From safety considerations, power 𝑑𝑡 𝑔−𝑙 Where, conductors along the route of the transmission line V (t) is the voltage across the gap, should maintain clearances to ground in open g is the gap length, country, national highway, rivers, railway tracks, L is the leader length, tele-communication lines, other power lines etc. as E is the critical leader inception gradient and k is a laid down in the Indian Electricity Rule or standards leader coefficient and is given in reference. or code of practice in vogue. Minimum permissible The insulator (string) voltage is given by ground clearance for a 220KV as per IE Rules, 1956, Vins = Vcnt- - Vb (6) Rule 77(4) is 7.01m. The maximum working tension Where, under stringent loading conditions shall not exceed Vcnt = cross arm voltage 50 percent of the ultimate tensile strength or Vb = line voltage conductor. Sag-Tension computations made for final The number of insulating discs used for a 220KV stringing of the conductors therefore must ensure tower are14 as per the IEEE standards. that factor of safety of 2 and 4 are obtainable under maximum loading condition and every day loading condition, respectively. 534 | P a g e
  • 3. G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and Applications (IJERA) ISSN: 2248-9622 www.ijera.com Vol. 3, Issue 1, January -February 2013, pp.533-536 VI. Selection of Transmission Lightening provide protection against back flashovers . Since Arrestors the line has to be protected from back flashovers, A line arrester is a one which reduce the effective operation of the breakers is essential. To risk of insulator flashover during surge events control the operation of the two breakers in the sub- [7].Arrestor Voltage rating shall not be less than circuit logic was implemented. With this we have product of system highest voltage x co-efficient of designed one insulator. Three such insulators were earthing [6]. designed as per the tower sub-circuit. As our model In a 220 kV effectively earthed system includes three such towers, we have designed a Highest system voltage = 245 KV model with three towers in it. Co-efficient of earthing = 80% Arrestor voltage rating = 245x0.8 = 196 KV. In this paper, only the electrical parameters of the arrester are taken for the modeling. VII. Proposed Model of 220KV Transmission System and Results The below model shows a 220KV transmission system with two wires, whose sub- circuit of the tower further consistutes of five sub- circuits. These five sub-circuits includes the three insulator strings and the two cross arms as shown in the figure. These five sub-circuits have to be designed seperately. Over the system a lightning surge of 100KA was induced and the resulting simulation was carried out in powerful electrical tool PSCAD. Figure: 3 Tower Sub Circuit Figure: 4 Tower voltage Figure: 1 Proposed Model Figure: 5 String Voltage As the string voltage become zero, which means that an arc is being formed. This means that flashover is occuring. Hence, that particular line is going to the outage state. This is undesirable as it interrupts the power supply to the consumers. So we Figure: 2 Output of Phase B take the next set of observations with the Line Arrestor turned ON along with flashover in all the The sub circit of the tower structure shown three phases. The wave form with flash over and below, to which when flashover is turned ON, the arrestor turned ON on phase B are observed: outputs of tower, line and string voltages can also be observed below. The insulator sub-circuit has metal oxide surge arresters as a part of the circuit to 535 | P a g e
  • 4. G.Radhika, Dr.M.Suryakalavathi / International Journal of Engineering Research and Applications (IJERA) ISSN: 2248-9622 www.ijera.com Vol. 3, Issue 1, January -February 2013, pp.533-536 Engineering and Application, ICHVE , 2008, 9-12 Nov. [4]. C.J.Coelho Teixera and A. Machado e Moura, “Study of the Back Flashover Phenomena in Overhead Transmission Lines using the EMTP”, IEEE PES Transmission and Distribution Conference and Exposition, Latin America, TDC 06, IEEE/PES. [5]. M.H.Shwehdi, “Computation of Lightning Figure: 6 Recovered String Voltage after placing Flashovers and Back Flashover Voltage TLA. Levels on 230KV Transmission Lines”, 2nd IEEE International conference on VIII. CONCLUSION Power and Energy (PECon 08), December The tower footing resistance is an 1-3, 2008, Johor Baharu, Malaysia. extremely important parameter in determination of [6]. Akihiro Ametani, Naoto Nagaoka, lightning flashover rates which was taken as 10Ω in Toshihisa Funabashi and Nagahiro Inoue, this work for all the towers.. The lower the tower “Tower Structure Effect on a Back- footing resistance, the more negative reflections Flashover Phase”. International Conference produced from tower base towards the tower top and on Power Systems Transients (IPST’05) these hence help to lower the peak voltage at the Montreal, Canada, June 19-23, 2005. tower top. Soil resistivity also plays a very important [7]. Mohd Z.A Ab Kadir, Zawati Mohd Nawi role in determining lightning flashover rates which and Junainah Sardi “Numerical Modeling was 100 Ωm and relative ground permeability was and Simulation in Electro Magnetic 1.0 in this work. Surge arrester selection plays vital Transient Program for Estimating Line key role in arresting the insulator flashovers which Back Flashover Performance” Engineering was calcualted to be 196KV in this work. The Letters, 18:4, EL_18_4_04, Advance placement of transmission line arrestors and design Online Publication: 23 November 2010. of arrestor is crucial in arresting the flashovers. [8]. Manitoba HVDC Research Centre, From the above simulated resulsts, when arrester and “Introduction to PSCAD/EMTDCV 4.0,” flashover were OFF the tower voltage, string voltage Manitoba Research Centre Inc. 2003. were normal and when flashvoer was ON and arrester was OFF the string voltge of phase B was BIOGRAPHY OF AUTHORS gone outage as seen in Fig.5 which is undesirable as it interrupts the power supply to the consumers. Hence when arrester was ON in phase B, the string voltage of phase B was recovered as shown in Fig. 6. Hence by placing one arrestor on each phase and by using two ground wires, we can completely Mrs.G.Radhika is working as Senior eliminate the flashover, which means zero Assistant Professor in Electrical and Electronics probability of flashovers. Engineering Department at VNR Vignana Jyothi Institute of Engineering and Technology, REFERENCES Hyderabad, India. She is pursuing her Ph.D at [1]. P. Yadee and S. Premrudeepreechacharn, J.N.T.University Hyderabad. “Analysis of Tower Footing Resistance Effected Back Flashover across Insulator in a Transmission System” International Conference on Power Systems Transients (IPST’07) in Lyon, France on June 4-7, 2007 [2]. M. Kizilcay and C. Neumann “Back Dr.M.Suryakalavathi is professor in Flashover Analysis for 110KV Lines at Electrical and Electronics Engineering Department Multi-Circuit Overhead Line Towers” at Jawaharlal Nehru Technological University International Conference on Power Systems Hyderabad, India. She received her Ph.D from Transients (IPST’07) in Lyon, France on J.N.T.University Hyderabad and Post Doctoral June 4-7, 2007 degree from prestigious Carnegie Melon University [3]. P. Liu, G.N. Wu, B. Sui, R.F. Li and X.B. U.S.A. Kao, “Modeling Lightning Performance of Transmission Systems using PSCAD” International Conference on High Voltage 536 | P a g e