Abstract: -- This paper introduces Modeling of
a 3- Phase 132kv Gas Insulated Substation. Such over
voltages can cause mal functioning of protection circuits
and control circuits and also initiates faults and
influence on other components such as
transformers. For designing a substation it is essential to
know the maximum value of VFTO. Hence studies are
carried out on estimation of the VFTO levels. For this
purpose MATLAB 7.8 can be used. In MATLAB 7.8
simulation a suitable equivalent circuit is necessary for
each component of the substation. Analysis of Very Fast
Transient Overvoltage has been carried out using
MATLAB7.8 for various switching conditions in a 3-
phase 132kV gas insulated substation.
Keywords— , MATLAB 7.8 software and Control
circuitry,Gas Insulated Substation (GIS), Very Fast
Transient overvoltages, Switching operations, 3
phase fault
I. INTRODUCTION
Gas Insulated Substations (GIS) have found a broad
range of applications in power systems over the last
three decades because of their high reliability, easy
maintenance, small ground space requirement etc.. In
our country also, a few GIS units have been in operation
and a large number of units are under various stages of
installation[1].
GIS is based on the principle of operation of complete
enclosure of all energized or live parts in a metallic
encapsulation, which shields them from the external
environment[2]. Compressed SF6 gas, which has
excellent electrical insulating properties, is employed as
the insulating medium between the encapsulation and
the energized parts. Gas Insulated Substations have a
grounded outer sheath enclosing the high voltage inner
conductor unlike conventional equipment whose closest
ground is the earth surface[3][4].
The Basic Insulation Level (BIL) required for a Gas
Insulated Substation (GIS) is different from that of the
conventional substation because of certain unique
properties of the former[5]. Gas insulated bus has a
surge impedance (70
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
Ohm) more than that of the conventional oil filled cables,
but much less than that of a over head line (300 – 400
Ohms)[6].
In addition, the GIS is totally enclosed and therefore is
free from any atmospheric contamination. Hence, in
general the GIS permit lower BIL rating than the
conventional one. A GIS requires less number of
lightning arresters than a conventional one[7].
The representation of bushing is important for
simulating the fast transients. Generally, the transit time
through a bushing is comparable to or greater than the
rise time of GIS generated transients. For this reason,
bushings cannot be considered as a lumped element in
estimating the VFTO level.
The generation of fast transients can be classified into
two types. They are due to the following:
a) Dis-connector switch operation
b) Faults between Bus bar and Enclosure
In case of 3-phase fault, the voltage collapse at the fault
location occurs in a similar way as in dis-connector gap
during re-striking. By this event, step shape traveling
surges are injected. For such a surge source inside GIS,
two surges traveling in opposite directions are
generated. However, if voltage collapse occurs at the
open end of GIS, only single surge propagates on the
bus[8].
During recent field tests on a 132KV substation,
measurements were made of the trapped charge left
when a DS was opened onto a floating section of
switchgear. Numerous measurements led to the
conclusion that for this switch, a potential of 0.1 – 0.2p.u
is left on the floating section and that this result is
consistent [9][10].
II. ESTIMATION OF 132KV GAS INSULATED
SUBSTATION
During the switching operation of the circuit, the
transients are developed. By the calculated values of the
circuit parameters in previous chapter, the equivalent
circuits are constructed by using MATLAB 7.8
software. By using the circuits the transients are
calculated for different lengths of Gas insulated
substation. The transients are also calculated during the
faults with and without load at different distances.
1− 𝑟2
𝑡
During the current operation of dis-connector
switch in a GIS, re-strikes(pre-strikes) occur because of
low speed of the dis-connector switch moving contact,
hence Very fast
Transient Over voltage are developed. These VFTO‘s
are
An
d
%Z
X* I
V
X %Z*
V
I
caused by switching operations and 3-phase fault in
132KvGIS . Using MATLAB of the equivalent models is
developed.
A. Spacers capacitance
The spacer existed with finite thickness and develops
some amount of capacitance in addition with existed
capacitance. Spacers are used for supporting the inner
conductor with reference to the outer enclosure. They are
made with Alumina filled epoxy material whose relative
permittivity (εr) is 4.
B. Calculation of short circuit inductance
&Resistance:
But X 2* *f *L
L
X
2* *f
D. Inductance calculation
The inductance of the bus duct can be calculated by
using the formula [8] given below, where r1, r2, r3, r4,
are the radii of the conductors in the order of
decreasing magnitude and ‗l‘ is the length of the
section.
𝑙𝑛 (𝑟1) + 𝑙𝑛 (𝑟2) + 𝑙𝑛 (𝑟4)
+
= 0.001 × 𝑙 × l 𝑟3
𝑟2 2 𝑟1 𝑟3
Assuming a short circuit fault level of 1000 MVA for
220KV system voltage, inductance and resistance are
calculated as follows:
2 ×
(𝑟1)
𝗁 (𝑟1)
× 𝑙𝑛 (𝑟1 − 1)
𝑟2
l
Iph
S
Vph
And %Z
X* I
V
Calculation of variable arc resistance:
The Variable arc resistance is calculated using the
formula:
𝑅 =
𝐾𝑇 ×𝑙
𝑞 + 𝑖(𝑡)𝑑𝑡
X %Z*
V
I Where,
0 ∫0
But X 2* *f *L
𝐾𝑇 = Toepler‘s constant
= 0.005 volt.sec/mt for SF6 under
uniform fieldconditions
L = spark length in meters
L
X
2* *f
𝑞0 = Initial charge or charge at the instant of
breakdownT = spark collapse time in sec.
The value of time varying spark resistance R(t) is
C. Calculation of Inductance due to Load (Transformer):
For 600MVA,, 220KV transformer with 10%
impedanceand 0.8 power factor the inductance is
calculated as follows:
*V*I*Cos P
calculated until it reaches a value of 1 to 3 ohms. The
integral in the denominator sums up the absolute
value of current ‗i‘ through the resistance R(t) over the
time beginning at breakdown inception. Thus, it
corresponds to the charge conducted through the
spark channel up to time ‗t‘.
Initial charge qo is an important parameter while
considering the non-uniform fields. But the field
between the dis- connector contacts is almost uniform.
Therefore qo is very small.
I
3 *V *Cos
2
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1468
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
Fig 1. Equivalent circuit of GIS
Fig. 2. Equivalent circuit for 10mtrs. Length in a 3 -phase
to132kv GIS
Fig. 3. MATLAB circuit for 10mtrs length in a 3-phase to 132KV GIS
Fig. 4. Sub Circuit of 132 kV GIS
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1469
II. EQUIVALENT CIRCUIT FOR 132KV GIS SYSTEM
shown below figure 1 & 2. S.no Load
side
Voltage
(p.u)
Magnitude of the
voltages (p.u)
Rise Time
(Nano secs)
VR
phase
VY
phase
VB
Phase
tr ty tb
1 1.0 2.41 2.40 2.42 10 09 10
2 0.9 2.36 2.36 2.33 11 12 11
3 0.8 2.23 2.22 2.21 12 11 12
4 0.7 2.03 2.04 2.03 11 10 11
5 0.6 2.04 2.05 2.02 13 12 13
6 0.5 1.79 1.78 1.77 12 11 11
7 0.4 1.71 1.70 1.69 11 10 12
8 0.3 1.61 1.60 1.62 12 11 11
9 0.2 1.48 1.47 1.46 10 11 10
10 0.1 1.36 1.35 1.36 09 10 11
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
The GIS bushing is represented by a capacitance of
200pf. The resistance of 1 ohm spark channel is connected
in series with circuit breaker. MATLAB Circuit for 10 mtrs.
length in a3-phase 132Kv GIS shown in the fig. 3 and Sub
Circuit of 132 kV GIS fig.4.
The proposed method implemented on MATLAB 7.8.
the voltage before and after circuit breaker is taken to be
1.0
p.u and -1.0pu as the most enormous condition but
depending on the time of closing of circuit breaker the
magnitude of the voltage on the load side changes.
For different values of voltages on the load side the
magnitudes and rise time of the voltage wave are
calculated keeping source side voltages as constant as
1.0p.u the values are tabulated in table I.
Similarly by changing the magnitudes of the voltage
on the source side, keeping voltage on load side constant at
1.0p.u. Then the transient due to variation of voltage on
source side obtained. The values are tabulated in Table II.
This circuit is divided into three sections of
1mtr, 4mtrs and 5mtrs respectively from load side and by
using the circuit
The Fast transient over voltages are generated not
only due to switching operations but also due to 3- phase
fault in 132Kv GIS .The bus duct is dividing into three
sections of length from load side.
S.no Load
side
Voltag
e(p.u)
Magnitude of
thevoltages
(p.u)
Rise Time
(Nano
secs)
VR
phas
e
VY
phas
e
VB
phas
e
tr ty tb
1 -1.0 2.42 2.40 2.43 11 12 11
2 -0.9 2.34 2.33 2.34 13 14 12
3 -0.8 2.22 2.22 2.23 09 10 11
4 -0.7 2.12 2.15 2.18 11 12 11
5 -0.6 1.87 1.84 1.86 12 11 11
6 -0.5 1.84 1.82 1.82 11 10 10
7 -0.4 1.70 1.71 1.70 12 10 11
8 -0.3 1.63 1.64 1.62 10 11 10
9 -0.2 1.45 1.43 1.42 11 10 11
10 -0.1 1.39 1.40 1.39 09 10 09
TABLE II
TRANSIENTS DUE TO VARIATION OF VOLTAGE ON
SOURCE SIDE
TABLE I
TRANSIENT DUE TO VARIATION OF VOLTAGE ON
LODE SIDE
III. RESULTS AND DISCUSSION
Fig. 5 Current waveform during closing operation of CB
for 10mts length in a 3-phase 132kv GIS
The various current and transient voltage at different
positions in a 3-phase 132kv GIS for the first switching
operation presented in results.
The variable arc resistance is calculated by using the
Toepler‘s formula. The inductance of the bus bar is found out
from the diameters of conductors and enclosure. The bus
capacitance is calculated using formula for concentric
cylinders.
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1470
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
The maximum values of VFTO, the MATLAB7.8 software is
used and a simulation is carried out by designing suitable
equipment circuits and its models are developed. The main
advantages of such models are used to enable the transient
analysis in GIS.
During closed operation, the current through the resistance
of the circuit breaker is shown in fig.5 From the graph it was
found the maximum current is 35A at a rise time of 14ns.The
transients due to closing of the circuit breaker are calculated
as shown in fig 6. From this graph, the peak voltages
obtained are 2.44, 2.43 and 2.44p.u at rise times of 69,
68.69ns respectively.
Fig 6 Transient voltage wave from during closing
operationof CB for 10mts length in a 3-phase
132kv GIS
To introduce current chopping the circuit breaker is
opened. The transients obtained during opening
operation are shown in Fig 6.4. From the graph, the
maximum voltages obtained are 1.23, 1.22 and 1.21p.u. at
rise times of 61,60,and 61ns respectively. MATLAB Circuit
for 10mtrs. Length in a 3- phase 220kv GIS shown in the
fig 3
.
Fig. 7 Transient voltage waveform during opening
operationof CB for 10mts length in a 3-phase
132kv GIS
Assuming a second re-strike occurs the transients are
calculated by closing another switch at the time maximum
voltage difference occurs across the circuit breaker. The
transients obtained due to second re-strike are shown in
Fig 8
The transients due to switching operations and line
to enclosure faults with fixed arc resistance for
different lengths of GIS are found. Transients are
calculated along with load and it was observed that the
transients obtained in 5mts length GIS will effect the
system more than that obtained in 10mts length GIS.
As the distance between the fault point and load
increases during fault analysis the magnitudes and rise
times of the transients also increases.
and 2.54 p.u at arise time of 122,121 and
123ns respectively.
The magnitudes and rise times of 10mts length
GIS aretabulated in the table III.
Fig.8 Transient voltage waveform during second
re-strikes
From the graph, the maximum voltages obtained is
2.51, 2.52
for 10mts length in a 3-phase 132kv GIS
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1471
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072
THE ANALYSIS VALUES ARE TABULATED AS FOLLOWS:
Mode of
operatio
n
Magnitude
of
voltages(p.u
)
Rise
time
(Nano
sec)
VR
phase
VY
phase
VB
phase
tr ty tb
During
closing
operation
2.44 2.43 2.44 69 68 69
During
opening
operatio
n
1.23 1.22 1.21 61 60 61
During
secondre-
strike
2.51 2.52 2.54 122 121 123
TABL E III
III. CONCLUSION
The fast transient over voltages that are
obtained due to switching operations in GIS are
simulated.. It is observed that the peak magnitudes are
26% to 30% higher in case of disconnector switch
closing operation. With effective design and use of the
same can effectively reduce the steepness and
maximum peak of VFTO generated.
The fast transient over voltages are obtained due to
switching operations and short-circuit faults are
studied. The transients are calculated initially with
fixed arc resistance and then variable arc resistance.
The variable arc resistance is calculated by using
Toepler‘s formulae. Transients along with load and
without load are also estimated.
IV. REFERENCES:
[1] S. Nishiwaki, Y. Kanno, S. Sato, E. Haginomori, S.
Yamashita, and S. Yanabu, ―Ground Fault by Re-striking
Surge of SF6 Gas insulated Disconnecting Switch and Its
Synthetic Tests,‖ – Transactions on Power Apparatus
and Systems, vol. PAS-102, No. 1, pp. 219-227, 1983.
[2] N. Fujimoto and S. A. Boggs, ―Characteristics of GIS
Disconnector-induced Short Rise time Transients
Incident on Externally Connected Power System
Components,‖IEEE 87 WM 185-2,New Orleans, Feb.
1987.
[3] W. Boeck and W. Taschner, ―Insulating Behavior of
SF6 with and without Solid Insulation in Case of Fast
Transients,‖ CIGRE Paper No.1547, Aug. 1986.
Transactions on Power Systems, vol. PWRD- 1, No. 2, pp.
95-101, 1983.
[4] R. Witzman, ―Fast Transients in Gas Insulated
Substations (GIS)
– Modeling Of Different GIS Components,‖ Fifth
International Symposium on High Voltage Engineering,
No. 12.06, 1987.
[5] J. Lewis, B. M. Pryor, C. J. Jones, T. Irwin,
―Disconnector Operations in Gas Insulated Substations
Over voltage Studies and Tests Associated with a 420 kV
Installation‖, CIGRE,Vol. 11, 1988, paper 33.09, pages 1-
8
[6] M.kondalu, G.Sreekanthreddy, Dr. P.S.
subramanyam,‖ Analysis and Calculation of very fast
transient over voltages in 220kv gas insulated Substation
International Journal of Engineering &techsciencevol
2(4) 2011
[7] M.kondalu, , Dr. P.S. subramanyam ―Estimation of
Re-striking Transient Over voltages in a 3-phase 132kv
Gas Insulated substation published in International
journal of Advanced Research in Computer Engineering
& Technology Issue4-Volume1-series1,pages 22-27
,June- 2012
[8] M.kondalu, , Dr. P.S. subramanyam ―Calculation of
Transients at Different Distances in a single phase 220kv
Gas Insulated substation published in International
journal of Advanced Research in Computer Engineering
& Technology Issue4-Volume1pages 28-33 – June-2012
[9] H. Hiesinger,RWitzmann. Very fast Transient
Breakdown at a needle Shaped Protrusion, IX Int.
Conf. on Gas Dis. and Their Appli. Sep 1988.
[10] M.kondalu, G.Sreekanthreddy, Dr.
P.S. subramanyam,‖ Estimation Transient overvoltages
in gas insulated bus duct from 220kv gas insulated
substation‖, International journal of Computer
applications, (0975-8887) volume 20-no.8 april 2011.
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1472

More Related Content

Similar to Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation

Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationseSAT Publishing House
 
Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationseSAT Journals
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingeSAT Publishing House
 
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEEXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEijiert bestjournal
 
final year project report
final year project reportfinal year project report
final year project reportAnuj Kumar
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatoreSAT Journals
 
Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Bérengère VIGNAUX
 
Analysis and Modeling of Transformerless Photovoltaic Inverter Systems
Analysis and Modeling of Transformerless Photovoltaic Inverter SystemsAnalysis and Modeling of Transformerless Photovoltaic Inverter Systems
Analysis and Modeling of Transformerless Photovoltaic Inverter SystemsIJMER
 
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...IRJET Journal
 
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...IRJET Journal
 
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...IJRES Journal
 
Step up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor DriveStep up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor DriveEditor IJMTER
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...IAEME Publication
 
IRJET- Design and Implementation of Isolated Multi-Output Flyback Converter
IRJET- Design and Implementation of Isolated Multi-Output Flyback ConverterIRJET- Design and Implementation of Isolated Multi-Output Flyback Converter
IRJET- Design and Implementation of Isolated Multi-Output Flyback ConverterIRJET Journal
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthingPankaj Chakraborty
 
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...IRJET Journal
 
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...ecij
 

Similar to Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation (20)

Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substations
 
Analsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substationsAnalsis of very fast transient over voltages in gas insulated substations
Analsis of very fast transient over voltages in gas insulated substations
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module using
 
Kd3418211827
Kd3418211827Kd3418211827
Kd3418211827
 
Du36723729
Du36723729Du36723729
Du36723729
 
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEEXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
 
final year project report
final year project reportfinal year project report
final year project report
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulator
 
Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks
 
Design of Low Voltage and High Speed Double-Tail Dynamic Comparator for Low P...
Design of Low Voltage and High Speed Double-Tail Dynamic Comparator for Low P...Design of Low Voltage and High Speed Double-Tail Dynamic Comparator for Low P...
Design of Low Voltage and High Speed Double-Tail Dynamic Comparator for Low P...
 
Analysis and Modeling of Transformerless Photovoltaic Inverter Systems
Analysis and Modeling of Transformerless Photovoltaic Inverter SystemsAnalysis and Modeling of Transformerless Photovoltaic Inverter Systems
Analysis and Modeling of Transformerless Photovoltaic Inverter Systems
 
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
 
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
Protection of 3-Phase Induction Motor Fed from 3-Phase Inverter Using Rogowsk...
 
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
PID Compensator Control Scheme of Synchronous Buck DC-DC Converter with ZVS L...
 
Step up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor DriveStep up DC-DC Impedance source network based PMDC Motor Drive
Step up DC-DC Impedance source network based PMDC Motor Drive
 
Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...Study of the impact on the protection plan of a pv production integrated to t...
Study of the impact on the protection plan of a pv production integrated to t...
 
IRJET- Design and Implementation of Isolated Multi-Output Flyback Converter
IRJET- Design and Implementation of Isolated Multi-Output Flyback ConverterIRJET- Design and Implementation of Isolated Multi-Output Flyback Converter
IRJET- Design and Implementation of Isolated Multi-Output Flyback Converter
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthing
 
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...
Zero-Current-Switching Current-Fed Half-Bridge Isolated DC/DC Converter for F...
 
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...
Improved Control Strategy for Low Voltage Ride Through Capability of DFIG wit...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation

  • 1. © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1467 Modeling andAnalysis of a 3-Phase 132kv GasInsulated Substation Lalit Patil1 , Jigisha Ahirrao2, Mangesh Mondhe3 & Roshni Patil4 ------------------------------------------------------------------------***------------------------------------------------------------------------ Abstract: -- This paper introduces Modeling of a 3- Phase 132kv Gas Insulated Substation. Such over voltages can cause mal functioning of protection circuits and control circuits and also initiates faults and influence on other components such as transformers. For designing a substation it is essential to know the maximum value of VFTO. Hence studies are carried out on estimation of the VFTO levels. For this purpose MATLAB 7.8 can be used. In MATLAB 7.8 simulation a suitable equivalent circuit is necessary for each component of the substation. Analysis of Very Fast Transient Overvoltage has been carried out using MATLAB7.8 for various switching conditions in a 3- phase 132kV gas insulated substation. Keywords— , MATLAB 7.8 software and Control circuitry,Gas Insulated Substation (GIS), Very Fast Transient overvoltages, Switching operations, 3 phase fault I. INTRODUCTION Gas Insulated Substations (GIS) have found a broad range of applications in power systems over the last three decades because of their high reliability, easy maintenance, small ground space requirement etc.. In our country also, a few GIS units have been in operation and a large number of units are under various stages of installation[1]. GIS is based on the principle of operation of complete enclosure of all energized or live parts in a metallic encapsulation, which shields them from the external environment[2]. Compressed SF6 gas, which has excellent electrical insulating properties, is employed as the insulating medium between the encapsulation and the energized parts. Gas Insulated Substations have a grounded outer sheath enclosing the high voltage inner conductor unlike conventional equipment whose closest ground is the earth surface[3][4]. The Basic Insulation Level (BIL) required for a Gas Insulated Substation (GIS) is different from that of the conventional substation because of certain unique properties of the former[5]. Gas insulated bus has a surge impedance (70 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 Ohm) more than that of the conventional oil filled cables, but much less than that of a over head line (300 – 400 Ohms)[6]. In addition, the GIS is totally enclosed and therefore is free from any atmospheric contamination. Hence, in general the GIS permit lower BIL rating than the conventional one. A GIS requires less number of lightning arresters than a conventional one[7]. The representation of bushing is important for simulating the fast transients. Generally, the transit time through a bushing is comparable to or greater than the rise time of GIS generated transients. For this reason, bushings cannot be considered as a lumped element in estimating the VFTO level. The generation of fast transients can be classified into two types. They are due to the following: a) Dis-connector switch operation b) Faults between Bus bar and Enclosure In case of 3-phase fault, the voltage collapse at the fault location occurs in a similar way as in dis-connector gap during re-striking. By this event, step shape traveling surges are injected. For such a surge source inside GIS, two surges traveling in opposite directions are generated. However, if voltage collapse occurs at the open end of GIS, only single surge propagates on the bus[8]. During recent field tests on a 132KV substation, measurements were made of the trapped charge left when a DS was opened onto a floating section of switchgear. Numerous measurements led to the conclusion that for this switch, a potential of 0.1 – 0.2p.u is left on the floating section and that this result is consistent [9][10]. II. ESTIMATION OF 132KV GAS INSULATED SUBSTATION During the switching operation of the circuit, the transients are developed. By the calculated values of the circuit parameters in previous chapter, the equivalent circuits are constructed by using MATLAB 7.8 software. By using the circuits the transients are calculated for different lengths of Gas insulated substation. The transients are also calculated during the faults with and without load at different distances.
  • 2. 1− 𝑟2 𝑡 During the current operation of dis-connector switch in a GIS, re-strikes(pre-strikes) occur because of low speed of the dis-connector switch moving contact, hence Very fast Transient Over voltage are developed. These VFTO‘s are An d %Z X* I V X %Z* V I caused by switching operations and 3-phase fault in 132KvGIS . Using MATLAB of the equivalent models is developed. A. Spacers capacitance The spacer existed with finite thickness and develops some amount of capacitance in addition with existed capacitance. Spacers are used for supporting the inner conductor with reference to the outer enclosure. They are made with Alumina filled epoxy material whose relative permittivity (εr) is 4. B. Calculation of short circuit inductance &Resistance: But X 2* *f *L L X 2* *f D. Inductance calculation The inductance of the bus duct can be calculated by using the formula [8] given below, where r1, r2, r3, r4, are the radii of the conductors in the order of decreasing magnitude and ‗l‘ is the length of the section. 𝑙𝑛 (𝑟1) + 𝑙𝑛 (𝑟2) + 𝑙𝑛 (𝑟4) + = 0.001 × 𝑙 × l 𝑟3 𝑟2 2 𝑟1 𝑟3 Assuming a short circuit fault level of 1000 MVA for 220KV system voltage, inductance and resistance are calculated as follows: 2 × (𝑟1) 𝗁 (𝑟1) × 𝑙𝑛 (𝑟1 − 1) 𝑟2 l Iph S Vph And %Z X* I V Calculation of variable arc resistance: The Variable arc resistance is calculated using the formula: 𝑅 = 𝐾𝑇 ×𝑙 𝑞 + 𝑖(𝑡)𝑑𝑡 X %Z* V I Where, 0 ∫0 But X 2* *f *L 𝐾𝑇 = Toepler‘s constant = 0.005 volt.sec/mt for SF6 under uniform fieldconditions L = spark length in meters L X 2* *f 𝑞0 = Initial charge or charge at the instant of breakdownT = spark collapse time in sec. The value of time varying spark resistance R(t) is C. Calculation of Inductance due to Load (Transformer): For 600MVA,, 220KV transformer with 10% impedanceand 0.8 power factor the inductance is calculated as follows: *V*I*Cos P calculated until it reaches a value of 1 to 3 ohms. The integral in the denominator sums up the absolute value of current ‗i‘ through the resistance R(t) over the time beginning at breakdown inception. Thus, it corresponds to the charge conducted through the spark channel up to time ‗t‘. Initial charge qo is an important parameter while considering the non-uniform fields. But the field between the dis- connector contacts is almost uniform. Therefore qo is very small. I 3 *V *Cos 2 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1468
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 Fig 1. Equivalent circuit of GIS Fig. 2. Equivalent circuit for 10mtrs. Length in a 3 -phase to132kv GIS Fig. 3. MATLAB circuit for 10mtrs length in a 3-phase to 132KV GIS Fig. 4. Sub Circuit of 132 kV GIS © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1469
  • 4. II. EQUIVALENT CIRCUIT FOR 132KV GIS SYSTEM shown below figure 1 & 2. S.no Load side Voltage (p.u) Magnitude of the voltages (p.u) Rise Time (Nano secs) VR phase VY phase VB Phase tr ty tb 1 1.0 2.41 2.40 2.42 10 09 10 2 0.9 2.36 2.36 2.33 11 12 11 3 0.8 2.23 2.22 2.21 12 11 12 4 0.7 2.03 2.04 2.03 11 10 11 5 0.6 2.04 2.05 2.02 13 12 13 6 0.5 1.79 1.78 1.77 12 11 11 7 0.4 1.71 1.70 1.69 11 10 12 8 0.3 1.61 1.60 1.62 12 11 11 9 0.2 1.48 1.47 1.46 10 11 10 10 0.1 1.36 1.35 1.36 09 10 11 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 The GIS bushing is represented by a capacitance of 200pf. The resistance of 1 ohm spark channel is connected in series with circuit breaker. MATLAB Circuit for 10 mtrs. length in a3-phase 132Kv GIS shown in the fig. 3 and Sub Circuit of 132 kV GIS fig.4. The proposed method implemented on MATLAB 7.8. the voltage before and after circuit breaker is taken to be 1.0 p.u and -1.0pu as the most enormous condition but depending on the time of closing of circuit breaker the magnitude of the voltage on the load side changes. For different values of voltages on the load side the magnitudes and rise time of the voltage wave are calculated keeping source side voltages as constant as 1.0p.u the values are tabulated in table I. Similarly by changing the magnitudes of the voltage on the source side, keeping voltage on load side constant at 1.0p.u. Then the transient due to variation of voltage on source side obtained. The values are tabulated in Table II. This circuit is divided into three sections of 1mtr, 4mtrs and 5mtrs respectively from load side and by using the circuit The Fast transient over voltages are generated not only due to switching operations but also due to 3- phase fault in 132Kv GIS .The bus duct is dividing into three sections of length from load side. S.no Load side Voltag e(p.u) Magnitude of thevoltages (p.u) Rise Time (Nano secs) VR phas e VY phas e VB phas e tr ty tb 1 -1.0 2.42 2.40 2.43 11 12 11 2 -0.9 2.34 2.33 2.34 13 14 12 3 -0.8 2.22 2.22 2.23 09 10 11 4 -0.7 2.12 2.15 2.18 11 12 11 5 -0.6 1.87 1.84 1.86 12 11 11 6 -0.5 1.84 1.82 1.82 11 10 10 7 -0.4 1.70 1.71 1.70 12 10 11 8 -0.3 1.63 1.64 1.62 10 11 10 9 -0.2 1.45 1.43 1.42 11 10 11 10 -0.1 1.39 1.40 1.39 09 10 09 TABLE II TRANSIENTS DUE TO VARIATION OF VOLTAGE ON SOURCE SIDE TABLE I TRANSIENT DUE TO VARIATION OF VOLTAGE ON LODE SIDE III. RESULTS AND DISCUSSION Fig. 5 Current waveform during closing operation of CB for 10mts length in a 3-phase 132kv GIS The various current and transient voltage at different positions in a 3-phase 132kv GIS for the first switching operation presented in results. The variable arc resistance is calculated by using the Toepler‘s formula. The inductance of the bus bar is found out from the diameters of conductors and enclosure. The bus capacitance is calculated using formula for concentric cylinders. © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1470
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 The maximum values of VFTO, the MATLAB7.8 software is used and a simulation is carried out by designing suitable equipment circuits and its models are developed. The main advantages of such models are used to enable the transient analysis in GIS. During closed operation, the current through the resistance of the circuit breaker is shown in fig.5 From the graph it was found the maximum current is 35A at a rise time of 14ns.The transients due to closing of the circuit breaker are calculated as shown in fig 6. From this graph, the peak voltages obtained are 2.44, 2.43 and 2.44p.u at rise times of 69, 68.69ns respectively. Fig 6 Transient voltage wave from during closing operationof CB for 10mts length in a 3-phase 132kv GIS To introduce current chopping the circuit breaker is opened. The transients obtained during opening operation are shown in Fig 6.4. From the graph, the maximum voltages obtained are 1.23, 1.22 and 1.21p.u. at rise times of 61,60,and 61ns respectively. MATLAB Circuit for 10mtrs. Length in a 3- phase 220kv GIS shown in the fig 3 . Fig. 7 Transient voltage waveform during opening operationof CB for 10mts length in a 3-phase 132kv GIS Assuming a second re-strike occurs the transients are calculated by closing another switch at the time maximum voltage difference occurs across the circuit breaker. The transients obtained due to second re-strike are shown in Fig 8 The transients due to switching operations and line to enclosure faults with fixed arc resistance for different lengths of GIS are found. Transients are calculated along with load and it was observed that the transients obtained in 5mts length GIS will effect the system more than that obtained in 10mts length GIS. As the distance between the fault point and load increases during fault analysis the magnitudes and rise times of the transients also increases. and 2.54 p.u at arise time of 122,121 and 123ns respectively. The magnitudes and rise times of 10mts length GIS aretabulated in the table III. Fig.8 Transient voltage waveform during second re-strikes From the graph, the maximum voltages obtained is 2.51, 2.52 for 10mts length in a 3-phase 132kv GIS © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1471
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 08 | Aug 2022 www.irjet.net p-ISSN: 2395-0072 THE ANALYSIS VALUES ARE TABULATED AS FOLLOWS: Mode of operatio n Magnitude of voltages(p.u ) Rise time (Nano sec) VR phase VY phase VB phase tr ty tb During closing operation 2.44 2.43 2.44 69 68 69 During opening operatio n 1.23 1.22 1.21 61 60 61 During secondre- strike 2.51 2.52 2.54 122 121 123 TABL E III III. CONCLUSION The fast transient over voltages that are obtained due to switching operations in GIS are simulated.. It is observed that the peak magnitudes are 26% to 30% higher in case of disconnector switch closing operation. With effective design and use of the same can effectively reduce the steepness and maximum peak of VFTO generated. The fast transient over voltages are obtained due to switching operations and short-circuit faults are studied. The transients are calculated initially with fixed arc resistance and then variable arc resistance. The variable arc resistance is calculated by using Toepler‘s formulae. Transients along with load and without load are also estimated. IV. REFERENCES: [1] S. Nishiwaki, Y. Kanno, S. Sato, E. Haginomori, S. Yamashita, and S. Yanabu, ―Ground Fault by Re-striking Surge of SF6 Gas insulated Disconnecting Switch and Its Synthetic Tests,‖ – Transactions on Power Apparatus and Systems, vol. PAS-102, No. 1, pp. 219-227, 1983. [2] N. Fujimoto and S. A. Boggs, ―Characteristics of GIS Disconnector-induced Short Rise time Transients Incident on Externally Connected Power System Components,‖IEEE 87 WM 185-2,New Orleans, Feb. 1987. [3] W. Boeck and W. Taschner, ―Insulating Behavior of SF6 with and without Solid Insulation in Case of Fast Transients,‖ CIGRE Paper No.1547, Aug. 1986. Transactions on Power Systems, vol. PWRD- 1, No. 2, pp. 95-101, 1983. [4] R. Witzman, ―Fast Transients in Gas Insulated Substations (GIS) – Modeling Of Different GIS Components,‖ Fifth International Symposium on High Voltage Engineering, No. 12.06, 1987. [5] J. Lewis, B. M. Pryor, C. J. Jones, T. Irwin, ―Disconnector Operations in Gas Insulated Substations Over voltage Studies and Tests Associated with a 420 kV Installation‖, CIGRE,Vol. 11, 1988, paper 33.09, pages 1- 8 [6] M.kondalu, G.Sreekanthreddy, Dr. P.S. subramanyam,‖ Analysis and Calculation of very fast transient over voltages in 220kv gas insulated Substation International Journal of Engineering &techsciencevol 2(4) 2011 [7] M.kondalu, , Dr. P.S. subramanyam ―Estimation of Re-striking Transient Over voltages in a 3-phase 132kv Gas Insulated substation published in International journal of Advanced Research in Computer Engineering & Technology Issue4-Volume1-series1,pages 22-27 ,June- 2012 [8] M.kondalu, , Dr. P.S. subramanyam ―Calculation of Transients at Different Distances in a single phase 220kv Gas Insulated substation published in International journal of Advanced Research in Computer Engineering & Technology Issue4-Volume1pages 28-33 – June-2012 [9] H. Hiesinger,RWitzmann. Very fast Transient Breakdown at a needle Shaped Protrusion, IX Int. Conf. on Gas Dis. and Their Appli. Sep 1988. [10] M.kondalu, G.Sreekanthreddy, Dr. P.S. subramanyam,‖ Estimation Transient overvoltages in gas insulated bus duct from 220kv gas insulated substation‖, International journal of Computer applications, (0975-8887) volume 20-no.8 april 2011. © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1472