“Construction Quality Management on Site”
Rizwan Showket1
1M. Tech (CTM) Scholar from Desh Bhagat University Punjab
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract Rome wasn’t built in a day. All that magnificent and painstakingly wrought architecture wouldn’thaveenduredthetest
of time and wowed generations after generation had it not been for a well mapped out strategy, workmanship and quality. The
same holds true even for a construction project. To be able to bring it to fruition, it needs constructionproject management, hasto
be meticulously planned and executed from ground up. It needs to progress steadily under the experienced tutelageof peoplewho
know their trade and can pull through any challenging situation. The Quality ManagementSystem(QMS)inconstructionindustry
refers to quality planning, quality assurance, quality control. The main goal of construction industryistoensurethatconstruction
projects are successfully completed within the constraints ofbestquality, statedperiodandatminimumpossiblecost. Theresearch
based on QMS recommended that constructioncompaniesshouldcreateaflexibleandconduciveorganizationalatmospherewhich
encourages the development of quality management system in all aspects of theirwork. Thequestionnairesurveyhasbeencarried
out in the present study by taking interviews of participants of project. This paper describes the analysis of data collected during
interviews & questionnaires with Sr. Quality Engineers, Contractors and Clients.
Key Words: Independent Inspections, QA/AC, Quality Edge, Management
1. INTRODUCTION
Quality in construction industry can be defined as the attainment of acceptable levels of performance from construction
activities. This performance would be attained when the activity meets or exceeds the requirement of the client or the owner.
The quality of any product or service is achieved when it conforms to the desired specifications. Construction projects are
always expected to create a balance between cost, time and quality. It is possible to have high quality and low cost, but at the
expense of time, and conversely to have high quality and a fast project, but at a cost. High quality is not always the primary
objective for the client; however, it is extremely important to a successful project. An appropriate level of quality could be
determined during all phases of the construction project. Specially, construction and commissioning are two critical phases
where the project could impact by its operability, availability, reliability, and maintainability of a facility. Ultimately, a facility
with a good construction quality program and minimal defects is more likely to have a smooth and trouble-freetransitioninto
the commissioning and qualification phase of the project.
Achieving quality in construction industry in long run is a tough issue and has been a problem. Inefficient or no practice of
quality management procedures will result in great loss of time, money, material, resources. Poor quality in construction
projects is a common phenomenon in the world [3]. Further, [4] stated that the satisfaction of quality level in the construction
projects has not been achieved and, it is a serious problem. However, most of the countries have been evolved to implement
quality standards to ensure construction quality. Therefore, it is necessary to investigate the importance of quality for
construction project success. Hence, the purpose of this research is to determine the importance of quality for construction
project success. The framework of quality for construction project success is developed accordingly.
1.1 QC/QA:
Quality control and quality assurance are used interchangeably; however,inconstruction,they’retwoseparatepartsofquality
system management. Without one or the other, the quality system won’t be as effective.
Quality assurance is the planning and systemic activities implemented in a quality system to fill quality requirements. So
quality assurance is looking at the quality requirements and making a plan to meet requirements. Qualitycontrol isthehands-
on part of quality assurance. It is the observation of techniquesandactivitiesused tofulfill therequirementsandplanssetforth
by quality assurance. While quality control is often a part of operations, QC isn’t an effective quality management system.
1.2 Independent Inspections:
Carry out independent inspections at all stages of building in process or at completion stage
 Benefits - Provides a tool to objectively assess the performance of site teams including the contractor and the project
management team. This in turn helps to get the desired output from the site team.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 337
 Snap Audits: This is done using a special mobile app developed in-house. This app is compatible with any android
smart phones. These audits can be customized to specific requirements of a client.
The information collected during independent inspection services is based onobservationsmadeatwork aswell assecondary
data based on documentation available onsite. The coverage of snap audits include:
 Quality Audits
 Safety audits
 Cost and Material Consumption Audits
 Audit of management system
 Insurance audits for Risk assessment and inherent defect insurance liability.
1.3 Quality Edge:
Quality Edge is a quarterly magazine dedicated to quality, safety and environmental aspects of the Architecture, Engineering
and Construction (AEC) industry. It is a knowledge portal with the objective of improving the knowledge baseofArchitectural
and Civil Engineering Community on the latest developments,
The highlight of Quality Edge is that we that explore a different subject in detail every time, presenting its varied facets, new
thoughts, innovative projects and events.
2.0 Literature Review
A recently published study (Bou-Llusar et al., 2009) reviews the variety of definitions of TQM available in the literature
(Oakland, 2000; Dale, 2003; Eriksson and Garvare, 2005) and concludes that it is a management approach which prescribes
guidelines for organizations to operate and achieve high performance. Mathews,Ueno, Kekale,Repka,Pereira andSilva (2001)
divided quality tools and techniques that are in support of quality programs into three main types, i.e., hard quality tools,
mixing methods and soft methods. Hard quality tools are formal quality systems, documented quality systems, quality costs,
control charts, and statistical sampling standards. Mixing methods are strategy and action plans review, flexibility of
organization structure, control charts, quality circles, and quality planning tools. Soft methods are training, customer
satisfaction surveys, regular contact with vendors and external organizations, actions to optimize environment impact,
empowerment, self-assessment, and benchmarking. Taylor et al. (2003) concluded that senior managers’ involvement,
understanding and customer focus are essential antecedents of TQM success. Samson et al. (1999) described that leadership
and human resources management are among strong predictors of performance TQM practices. On construction related
research, Low et al. (2004) commented that top management commitment as one of the elements that would reflect TQM
performance measures in construction firms. Chin et al. (2003) found that top management commitment is the most critical
factor for the successful implementation of ISO 9000. ISO 9000 deals with the fundamentals of quality management systems
(Quality Standard, 2008; Tsim et al, 2002), including the eight management principles (Quality Standard, 2008; Beattie and
Sohal, 1999; Tsim et al, 2002) on which the family of standards is based. ISO 9001 deals with the requirements that
organization wishing to meet the standard they have to fulfill. In order to integrate the quality management system withinthe
context of construction management, the need to study the elements in standard guidelines of quality management system is
essential to ensure the standardization of the quality management system is successful.
According to Lydia (2010), the guidelines to ensure the quality in planning are:
 Ensure that all relevant parties involvedincludingconsultants,subcontractorsandsuppliersareincludedinthetask of
quality planning for the project
 Establish and define the purpose of the quality system.
 In the plan, minimize the effort required to amend copies of documents
 Set up a quality system development team so that the team can produce an effective plan
 Ensure that throughout the quality planning task constantly focused on the customer requirements.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 338
3. RESEARCH METHODOLOGY
The methodology for the work consists of two step model. The first step is questioning by mail to highly experienced quality
engineers and second step is Quality control and quality assurance on site. In the firststepthequestionswill beaskedto senior
Quality Engineers/Sr. Project Managers of different companies regarding implementation of Quality Management on siteand
we will know their personal review and finally we will collect all data by mail and make a final list.
Second step is we will make appointment with Sr. Project managers/Sr.QualityEngineerswith experiencenotlessthanfifteen
years and ask them some selected question on quality management. The number of questions will be asked to them and the
various optional points for some questions are provided. The respondents has to rate these points on five- point rating scale.
The scale description is as “5= Very Strong, 4= Strong, 3= Moderate, 2= Less, 1= Very less”.Intheanalysisofdata all the options
of questions have been studied and the findings have mentioned in the subsequent section of paper.
3.1 DATA COLLECTION &ANALYSIS through Mail:
Table 1: Details of Some senior Quality Engineers/Sr. Project Managers
S. No Name Designation Mail Address Experience Company name Mail received
1 Devender
Kumar
Singh
Sr. Project
Manager
Devendra.jmc@gmail.com 27 years JMC Projects
Limited India
4-July2019
2 Sourabh
Kishor
Pinku
Sr. Quality
Engineer
sourabhkishorpinku@gma
il.com
15 years Mahagun India Pvt
Ltd
4-July2019
3 VedPrakash
Soni
Deputy
Project
Manager
Ved2soni@gmail.com 18 years JMC Projects
Limited India
4-July2019
4 Satay
Prakash
Chaudhary
Project
Manager
spchoudhary02@gmail.co
m
28 years JMC Projects
Limited India
8-July2019
5 Mosin Khan Quality
Engineer
Mosin.k@cqra.com 7 years CQRA Pvt Ltd 5-July2019
Table 2: Some Questions & Answers received from senior Quality Engineers/Sr. Project Managers through mail.
S
no
Name Question Answers (1) Question Answers (2) Question Answers (3)
How To implement
Quality on site?
Obstacles in the implementations
of Quality Management on site?
Personal Reviews?
1 Devender Kumar
Singh
1)Enough Resources
2) Team Work
3)Skilled labors
1). Rigid Attitude of high
management.
2) Lack of Education and training.
3) Lack of resources
1)team work
2)good material
3) Skilled manpower.
4) Work according to drawing
5)technical staff
2 Sourabh Kishore
Pinku
1) Better internal
communication
2) Consistent products.
3)ImproveDocumentation
availability.
1) Emphasis on short term objects.
2) too much documents commitment
3) Lack of employees understanding
1) Focus on Quality Standards.
2)WorkAccordingtoDrawing.
3) Training to technical and
non-technical staff.
3 Ved Prakash Soni 1)Skilled Manpower
2) Sufficient Resources.
3) Awareness of work
1) Improper Knowledge
2) Lack of implementation of Indian
standards.
3) Time Bond Project
1)awareness of quality
2)skilled person
3) Documentation of work.
4) Supervision
4 Satay Prakash
Chaudhary
1)Set a Multi discipline
team for each problem
2) Skilled Manpower
3)new techniques
1) Lack of understanding
2)minimum resources
3) Time period
1) Separate team for quality
engineers.
2) Work awareness.
3) Awareness of scope.
5 Mosin Khan 1) Skilled Mason 1). Poor quality of material 1) IS should be implemented
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 339
2) Good Communication
3) Newtech equipment’s
2) lack of employees commitment
3) Lack of expertise/resources
2) Well Qualified Engineers
3)Skilled Manpower
3.2 Mail Received from senior Quality Engineers/Sr. Project Managers:
Fig -1: some screenshots of mail received from senior Quality Engineers/Sr. Project Managers:
3.3 DATA COLLECTION &ANALYSIS through Interview:
Table 3: Some Questions & Answers asked during interview to senior Quality Engineers/Sr. Project Managers.
S. No Questions Answers
Weighted
Average
(A) QUALITY CONTROL ON SITE
Which of these wordsbest
define Quality?
60% says
Teamwork
30% says
Value of
money
5% says
Satisfying
customer
3% says
High Cost
"3”
Teamwork
1
Proper sampling and
testing on site? 100 % says yes "5"
2
Quality Control laboratory
at site 85% says yes "4.25"
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 340
3
Site review meetings with
staff 70% says yes "3.5"
4
Awareness of
Responsibilities 65% says yes "3.25"
(B) QUALITY MANAGEMENT DURING PLANNING
1
Coordination with all the
activities 81% says yes "4.1"
2 Notice Daily schedule 87% says yes "4.35"
3 Follow-Up meeting 90% says yes "4.5"
(C) OBSTACLES WORKING IN TEAM WITH RESPECT QUALITY
1
Rigid attitude of higher
management 71% says yes "3.55"
2
Emphasis on short term
objects 69% says yes "3.45"
3
Lack of Education and
training 80% says yes "4.0"
4 Lack of resources 85% says yes "4.25"
(D) TRAINING
1
Percentage of
managerial/supervisory
staff undergone through
training 90% says yes "4.5"
2
Percentage of non-
managerial/Technical
staff undergone through
training 65% says yes "3.25"
(E) OTHER
1 Order of Importance Safety-1 Cost-2 Quality-3 Time-4
2
Percentage of employees
who are aware of the
importance of Quality? 70% says yes "3.5"
The above analysis includes calculation of percentage wise weightage:
E.g. if the answer is 90%=90/100= 0.90/2= 4.5 out of 5
There are several methods for analysis of data but for this work I have used simple mathematicsi.e.Arithmeticmean=someof
observation /no of observations.
4.0 DISCUSSIONS & FINDINGS
As stated first I have made two type of question set, with 25 short questions asked during interview and three important
questions given to them (hardcopy) for mail, after a while I received reply from their side through mail attached above.
Question asked to them during interview contains set of series like initially I asked them about the quality control measure
used on construction site is the quality of workmanship in all construction activities followed by proper sampling and testing
on site, Quality Control laboratory at site, Site review meetings with staff, Awareness of Responsibilities etc.thenIaskedthem
about Quality management during planning followed by Coordination with all the activities, Notice Daily schedule, Follow-Up
meeting etc we discussed Obstacles working in team with respect Quality followed by Rigid attitude of higher management,
Emphasis on short term objects, Lack of Education and training, Lack of resources then finally I asked them about Training
followed by Percentage of managerial/supervisory staff undergonethroughtraining, Percentageof non-managerial/Technical
staff undergone through training, other QuestionsaskedtothemarePercentageofemployeeswhoareawareofthe importance
of Quality etc. I got different answers from different Project managers/Sr. Quality Engineers with little variation then I
segregate all the answers with respect to Percentage and made a scale description as “5= Very Strong, 4=Strong,3= Moderate,
2= Less, 1= Very less”.
Table 4: Arithmetic mean of all observations.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 341
s
no Description
observation
1
observation
2
observation
3
observation
4 Mean
Average
weightage
1
QUALITY
CONTROL ON
SITE 5 4.25 3.5 3.25 4 verystrong
2
QUALITY
MANAGEMENT
DURING
PLANNING 4.1 4.35 4.5 4.316 verystrong
3
OBSTACLES
WORKING IN
TEAM WITH
RESPECT
QUALITY 3.55 3.45 4 4.25 3.812 Strong
4 TRAINING 4.5 3.25 3.875 Strong
5.0 CONCLUSIONS
Very strongly respondent’s responses as observe regular schedule for the quality control measure used at site is quality of
workmanship in all activities. Very strongly respondent’s responses as observe regular schedule for Quality management
during planning. Obstacles working in team with respect Quality is Strong. Also, respondents have very strongly given to
Training.
After study of all above points through mail and interview i reached the following concluding remarks as below:
 Better internal communication and team work on Quality Control.
 Proper sampling and testing and Quality Control laboratory at site.
 Awareness of Responsibilities and duties on site.
 Suitable quality control method for the project.
 Training to technical and non-technical staff with Focus on Quality Standards.
 Set a Team for Quality Engineers on site.
REFERENCES
1) Pravin P. Mane, Dr. Jalindar R. Patil Proceedings of the Civil Engineering PG Conference 2015, Held at MAEER’s MIT, Pune-
411038, 24-25 April 2015
[1] AbdulAziz A.B. and Tawfiq, H.A. (1999). ISO 9000 QualityStandardsinConstruction,Journal ofManagementin Engineering,
Nov/Dec, pp. 41.
[2] Abdul Rahim, A.H et al. (2004). Integration of Safety, Health, Environment and Quality (SHEQ) Management System in
Construction: A Review. Jurnal Kejuruteraan Awam, Vol 16(1): 24-37, pp. 14.
[3] Arditi, D. and Gunaydin, H.M. (1998), “Factors that affect process quality in the life cycle of building projects”, Journal of
Construction Engineering and Management, ASCE, Vol. 124 No. 3, pp. 194-203.
[4] Chin, K. S., & Choi, T. W. (2003). Construction in Hong Kong: Success factors for ISO 9000 implementation. Journal of
Construction Engineering and Management, November/December, 599-609.
[5] Checkland, P.B. & Scholes, J. (1990) Soft Systems Methodology in Action. Chichester: John Wiley & Sons. Proceedings ofthe
Civil Engineering PG Conference 2015, Held at MAEER’s MIT, Pune-411038, 24-25 April 2015. Advances and Research inCivil
Engineering and Technology - Construction Management 326
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 342
[6] Giles, R. 1997. ISO 9000 perspective for construction industry in the UK. Training for Quality, Vol. 5 No. 4, pp 178-181. [7]
ISO. (2004) The ISO survey of ISO 9001:2000 and ISO 14001 certificates 2003.
BIOGRAPHIES
Rizwan Showket
M. Tech (CTM) Scholar from Desh
Bhagat University Punjab.
BLOGhttp://rizwanshowket.blogspot.co
m/

More Related Content

What's hot

IRJET- Application of BIM as a Model for Quality Management
IRJET- Application of BIM as a Model for Quality ManagementIRJET- Application of BIM as a Model for Quality Management
IRJET- Application of BIM as a Model for Quality ManagementIRJET Journal
 
Total Quality Management Benefits and Barriers in Construction Industry
Total Quality Management Benefits and Barriers in Construction IndustryTotal Quality Management Benefits and Barriers in Construction Industry
Total Quality Management Benefits and Barriers in Construction IndustryDr. Amarjeet Singh
 
Software quality assurance lecture 1
Software quality assurance lecture 1Software quality assurance lecture 1
Software quality assurance lecture 1Abdul Basit
 
Total construction quality management by mobile technology mtech
Total construction quality management by mobile technology   mtechTotal construction quality management by mobile technology   mtech
Total construction quality management by mobile technology mtechStephen Au
 
Hidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) ConstructionHidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) ConstructionGAURAV. H .TANDON
 
Ch 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleCh 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleKittitouch Suteeca
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Quality : Concept & Overview for Construction Projects.
Quality : Concept & Overview for Construction Projects.Quality : Concept & Overview for Construction Projects.
Quality : Concept & Overview for Construction Projects.Sanjay Mishra
 
Lecture 05 Software Quality Management
Lecture 05 Software Quality ManagementLecture 05 Software Quality Management
Lecture 05 Software Quality ManagementAchmad Solichin
 
Software Quality Analyst and Software Quality Management
Software Quality Analyst and Software Quality ManagementSoftware Quality Analyst and Software Quality Management
Software Quality Analyst and Software Quality Managementنور شزننا
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deletedSanjana Khound
 
Quality software management
Quality software managementQuality software management
Quality software managementArun Kumar
 

What's hot (20)

IRJET- Application of BIM as a Model for Quality Management
IRJET- Application of BIM as a Model for Quality ManagementIRJET- Application of BIM as a Model for Quality Management
IRJET- Application of BIM as a Model for Quality Management
 
Total Quality Management Benefits and Barriers in Construction Industry
Total Quality Management Benefits and Barriers in Construction IndustryTotal Quality Management Benefits and Barriers in Construction Industry
Total Quality Management Benefits and Barriers in Construction Industry
 
Software quality assurance lecture 1
Software quality assurance lecture 1Software quality assurance lecture 1
Software quality assurance lecture 1
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Total construction quality management by mobile technology mtech
Total construction quality management by mobile technology   mtechTotal construction quality management by mobile technology   mtech
Total construction quality management by mobile technology mtech
 
Quality concept
Quality concept Quality concept
Quality concept
 
106 quality assurance
106 quality assurance106 quality assurance
106 quality assurance
 
Quality Assurance in Software Ind.
Quality Assurance in Software Ind.Quality Assurance in Software Ind.
Quality Assurance in Software Ind.
 
Hidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) ConstructionHidden Horrors of Shoddy ( Poor Quality) Construction
Hidden Horrors of Shoddy ( Poor Quality) Construction
 
Ch 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycleCh 7 integrating quality activities in the projectlife cycle
Ch 7 integrating quality activities in the projectlife cycle
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Quality : Concept & Overview for Construction Projects.
Quality : Concept & Overview for Construction Projects.Quality : Concept & Overview for Construction Projects.
Quality : Concept & Overview for Construction Projects.
 
Lecture 05 Software Quality Management
Lecture 05 Software Quality ManagementLecture 05 Software Quality Management
Lecture 05 Software Quality Management
 
Software Quality Analyst and Software Quality Management
Software Quality Analyst and Software Quality ManagementSoftware Quality Analyst and Software Quality Management
Software Quality Analyst and Software Quality Management
 
Contractor Best Practices in Construction Quality Assurance
Contractor Best Practices in Construction Quality AssuranceContractor Best Practices in Construction Quality Assurance
Contractor Best Practices in Construction Quality Assurance
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deleted
 
Quality plan
Quality planQuality plan
Quality plan
 
Quality management
Quality managementQuality management
Quality management
 
17 1st review
17 1st review17 1st review
17 1st review
 
Quality software management
Quality software managementQuality software management
Quality software management
 

Similar to Construction Quality Management on Site

QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYQUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYIAEME Publication
 
Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...IRJET Journal
 
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET Journal
 
IRJET- Study on Quality Control of Project Management System
IRJET-  	  Study on Quality Control of Project Management SystemIRJET-  	  Study on Quality Control of Project Management System
IRJET- Study on Quality Control of Project Management SystemIRJET Journal
 
Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...eSAT Journals
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET Journal
 
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
2.08 quality management 1
2.08 quality management 12.08 quality management 1
2.08 quality management 1reddvise
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...IRJET Journal
 
Quality Control Report
Quality Control ReportQuality Control Report
Quality Control ReportEzevillo Zim
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM Mital Damani
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Dr. Amarjeet Singh
 

Similar to Construction Quality Management on Site (20)

USE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
USE OF ANDROID TOOL FOR QUALITY CONSTRUCTIONUSE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
USE OF ANDROID TOOL FOR QUALITY CONSTRUCTION
 
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERYQUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
QUALITY MANAGEMENT PRACTICES OF CONTRACTING FIRMS IN BUILDING PROJECT DELIVERY
 
Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...Quality management at construction projects: Case study of a stormwater netwo...
Quality management at construction projects: Case study of a stormwater netwo...
 
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
 
IRJET- Study on Quality Control of Project Management System
IRJET-  	  Study on Quality Control of Project Management SystemIRJET-  	  Study on Quality Control of Project Management System
IRJET- Study on Quality Control of Project Management System
 
Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...Study on negligence of quality assurance and proposing an effective framework...
Study on negligence of quality assurance and proposing an effective framework...
 
IRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction IndustryIRJET-Quality Benchmarking in Construction Industry
IRJET-Quality Benchmarking in Construction Industry
 
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...
ESTABLISHING QUALITY STANDARDS IN HIGH RISE BUILDING IN ACCORDANCE TO PRE, DU...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
KENA PRE.pptx
KENA PRE.pptxKENA PRE.pptx
KENA PRE.pptx
 
2.08 quality management 1
2.08 quality management 12.08 quality management 1
2.08 quality management 1
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...
IRJET- A Study on Quality Management System and Customer Satisfaction in Cons...
 
Quality Control Report
Quality Control ReportQuality Control Report
Quality Control Report
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 

Recently uploaded (20)

What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 

Construction Quality Management on Site

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 336 “Construction Quality Management on Site” Rizwan Showket1 1M. Tech (CTM) Scholar from Desh Bhagat University Punjab ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract Rome wasn’t built in a day. All that magnificent and painstakingly wrought architecture wouldn’thaveenduredthetest of time and wowed generations after generation had it not been for a well mapped out strategy, workmanship and quality. The same holds true even for a construction project. To be able to bring it to fruition, it needs constructionproject management, hasto be meticulously planned and executed from ground up. It needs to progress steadily under the experienced tutelageof peoplewho know their trade and can pull through any challenging situation. The Quality ManagementSystem(QMS)inconstructionindustry refers to quality planning, quality assurance, quality control. The main goal of construction industryistoensurethatconstruction projects are successfully completed within the constraints ofbestquality, statedperiodandatminimumpossiblecost. Theresearch based on QMS recommended that constructioncompaniesshouldcreateaflexibleandconduciveorganizationalatmospherewhich encourages the development of quality management system in all aspects of theirwork. Thequestionnairesurveyhasbeencarried out in the present study by taking interviews of participants of project. This paper describes the analysis of data collected during interviews & questionnaires with Sr. Quality Engineers, Contractors and Clients. Key Words: Independent Inspections, QA/AC, Quality Edge, Management 1. INTRODUCTION Quality in construction industry can be defined as the attainment of acceptable levels of performance from construction activities. This performance would be attained when the activity meets or exceeds the requirement of the client or the owner. The quality of any product or service is achieved when it conforms to the desired specifications. Construction projects are always expected to create a balance between cost, time and quality. It is possible to have high quality and low cost, but at the expense of time, and conversely to have high quality and a fast project, but at a cost. High quality is not always the primary objective for the client; however, it is extremely important to a successful project. An appropriate level of quality could be determined during all phases of the construction project. Specially, construction and commissioning are two critical phases where the project could impact by its operability, availability, reliability, and maintainability of a facility. Ultimately, a facility with a good construction quality program and minimal defects is more likely to have a smooth and trouble-freetransitioninto the commissioning and qualification phase of the project. Achieving quality in construction industry in long run is a tough issue and has been a problem. Inefficient or no practice of quality management procedures will result in great loss of time, money, material, resources. Poor quality in construction projects is a common phenomenon in the world [3]. Further, [4] stated that the satisfaction of quality level in the construction projects has not been achieved and, it is a serious problem. However, most of the countries have been evolved to implement quality standards to ensure construction quality. Therefore, it is necessary to investigate the importance of quality for construction project success. Hence, the purpose of this research is to determine the importance of quality for construction project success. The framework of quality for construction project success is developed accordingly. 1.1 QC/QA: Quality control and quality assurance are used interchangeably; however,inconstruction,they’retwoseparatepartsofquality system management. Without one or the other, the quality system won’t be as effective. Quality assurance is the planning and systemic activities implemented in a quality system to fill quality requirements. So quality assurance is looking at the quality requirements and making a plan to meet requirements. Qualitycontrol isthehands- on part of quality assurance. It is the observation of techniquesandactivitiesused tofulfill therequirementsandplanssetforth by quality assurance. While quality control is often a part of operations, QC isn’t an effective quality management system. 1.2 Independent Inspections: Carry out independent inspections at all stages of building in process or at completion stage  Benefits - Provides a tool to objectively assess the performance of site teams including the contractor and the project management team. This in turn helps to get the desired output from the site team.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 337  Snap Audits: This is done using a special mobile app developed in-house. This app is compatible with any android smart phones. These audits can be customized to specific requirements of a client. The information collected during independent inspection services is based onobservationsmadeatwork aswell assecondary data based on documentation available onsite. The coverage of snap audits include:  Quality Audits  Safety audits  Cost and Material Consumption Audits  Audit of management system  Insurance audits for Risk assessment and inherent defect insurance liability. 1.3 Quality Edge: Quality Edge is a quarterly magazine dedicated to quality, safety and environmental aspects of the Architecture, Engineering and Construction (AEC) industry. It is a knowledge portal with the objective of improving the knowledge baseofArchitectural and Civil Engineering Community on the latest developments, The highlight of Quality Edge is that we that explore a different subject in detail every time, presenting its varied facets, new thoughts, innovative projects and events. 2.0 Literature Review A recently published study (Bou-Llusar et al., 2009) reviews the variety of definitions of TQM available in the literature (Oakland, 2000; Dale, 2003; Eriksson and Garvare, 2005) and concludes that it is a management approach which prescribes guidelines for organizations to operate and achieve high performance. Mathews,Ueno, Kekale,Repka,Pereira andSilva (2001) divided quality tools and techniques that are in support of quality programs into three main types, i.e., hard quality tools, mixing methods and soft methods. Hard quality tools are formal quality systems, documented quality systems, quality costs, control charts, and statistical sampling standards. Mixing methods are strategy and action plans review, flexibility of organization structure, control charts, quality circles, and quality planning tools. Soft methods are training, customer satisfaction surveys, regular contact with vendors and external organizations, actions to optimize environment impact, empowerment, self-assessment, and benchmarking. Taylor et al. (2003) concluded that senior managers’ involvement, understanding and customer focus are essential antecedents of TQM success. Samson et al. (1999) described that leadership and human resources management are among strong predictors of performance TQM practices. On construction related research, Low et al. (2004) commented that top management commitment as one of the elements that would reflect TQM performance measures in construction firms. Chin et al. (2003) found that top management commitment is the most critical factor for the successful implementation of ISO 9000. ISO 9000 deals with the fundamentals of quality management systems (Quality Standard, 2008; Tsim et al, 2002), including the eight management principles (Quality Standard, 2008; Beattie and Sohal, 1999; Tsim et al, 2002) on which the family of standards is based. ISO 9001 deals with the requirements that organization wishing to meet the standard they have to fulfill. In order to integrate the quality management system withinthe context of construction management, the need to study the elements in standard guidelines of quality management system is essential to ensure the standardization of the quality management system is successful. According to Lydia (2010), the guidelines to ensure the quality in planning are:  Ensure that all relevant parties involvedincludingconsultants,subcontractorsandsuppliersareincludedinthetask of quality planning for the project  Establish and define the purpose of the quality system.  In the plan, minimize the effort required to amend copies of documents  Set up a quality system development team so that the team can produce an effective plan  Ensure that throughout the quality planning task constantly focused on the customer requirements.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 338 3. RESEARCH METHODOLOGY The methodology for the work consists of two step model. The first step is questioning by mail to highly experienced quality engineers and second step is Quality control and quality assurance on site. In the firststepthequestionswill beaskedto senior Quality Engineers/Sr. Project Managers of different companies regarding implementation of Quality Management on siteand we will know their personal review and finally we will collect all data by mail and make a final list. Second step is we will make appointment with Sr. Project managers/Sr.QualityEngineerswith experiencenotlessthanfifteen years and ask them some selected question on quality management. The number of questions will be asked to them and the various optional points for some questions are provided. The respondents has to rate these points on five- point rating scale. The scale description is as “5= Very Strong, 4= Strong, 3= Moderate, 2= Less, 1= Very less”.Intheanalysisofdata all the options of questions have been studied and the findings have mentioned in the subsequent section of paper. 3.1 DATA COLLECTION &ANALYSIS through Mail: Table 1: Details of Some senior Quality Engineers/Sr. Project Managers S. No Name Designation Mail Address Experience Company name Mail received 1 Devender Kumar Singh Sr. Project Manager Devendra.jmc@gmail.com 27 years JMC Projects Limited India 4-July2019 2 Sourabh Kishor Pinku Sr. Quality Engineer sourabhkishorpinku@gma il.com 15 years Mahagun India Pvt Ltd 4-July2019 3 VedPrakash Soni Deputy Project Manager Ved2soni@gmail.com 18 years JMC Projects Limited India 4-July2019 4 Satay Prakash Chaudhary Project Manager spchoudhary02@gmail.co m 28 years JMC Projects Limited India 8-July2019 5 Mosin Khan Quality Engineer Mosin.k@cqra.com 7 years CQRA Pvt Ltd 5-July2019 Table 2: Some Questions & Answers received from senior Quality Engineers/Sr. Project Managers through mail. S no Name Question Answers (1) Question Answers (2) Question Answers (3) How To implement Quality on site? Obstacles in the implementations of Quality Management on site? Personal Reviews? 1 Devender Kumar Singh 1)Enough Resources 2) Team Work 3)Skilled labors 1). Rigid Attitude of high management. 2) Lack of Education and training. 3) Lack of resources 1)team work 2)good material 3) Skilled manpower. 4) Work according to drawing 5)technical staff 2 Sourabh Kishore Pinku 1) Better internal communication 2) Consistent products. 3)ImproveDocumentation availability. 1) Emphasis on short term objects. 2) too much documents commitment 3) Lack of employees understanding 1) Focus on Quality Standards. 2)WorkAccordingtoDrawing. 3) Training to technical and non-technical staff. 3 Ved Prakash Soni 1)Skilled Manpower 2) Sufficient Resources. 3) Awareness of work 1) Improper Knowledge 2) Lack of implementation of Indian standards. 3) Time Bond Project 1)awareness of quality 2)skilled person 3) Documentation of work. 4) Supervision 4 Satay Prakash Chaudhary 1)Set a Multi discipline team for each problem 2) Skilled Manpower 3)new techniques 1) Lack of understanding 2)minimum resources 3) Time period 1) Separate team for quality engineers. 2) Work awareness. 3) Awareness of scope. 5 Mosin Khan 1) Skilled Mason 1). Poor quality of material 1) IS should be implemented
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 339 2) Good Communication 3) Newtech equipment’s 2) lack of employees commitment 3) Lack of expertise/resources 2) Well Qualified Engineers 3)Skilled Manpower 3.2 Mail Received from senior Quality Engineers/Sr. Project Managers: Fig -1: some screenshots of mail received from senior Quality Engineers/Sr. Project Managers: 3.3 DATA COLLECTION &ANALYSIS through Interview: Table 3: Some Questions & Answers asked during interview to senior Quality Engineers/Sr. Project Managers. S. No Questions Answers Weighted Average (A) QUALITY CONTROL ON SITE Which of these wordsbest define Quality? 60% says Teamwork 30% says Value of money 5% says Satisfying customer 3% says High Cost "3” Teamwork 1 Proper sampling and testing on site? 100 % says yes "5" 2 Quality Control laboratory at site 85% says yes "4.25"
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 340 3 Site review meetings with staff 70% says yes "3.5" 4 Awareness of Responsibilities 65% says yes "3.25" (B) QUALITY MANAGEMENT DURING PLANNING 1 Coordination with all the activities 81% says yes "4.1" 2 Notice Daily schedule 87% says yes "4.35" 3 Follow-Up meeting 90% says yes "4.5" (C) OBSTACLES WORKING IN TEAM WITH RESPECT QUALITY 1 Rigid attitude of higher management 71% says yes "3.55" 2 Emphasis on short term objects 69% says yes "3.45" 3 Lack of Education and training 80% says yes "4.0" 4 Lack of resources 85% says yes "4.25" (D) TRAINING 1 Percentage of managerial/supervisory staff undergone through training 90% says yes "4.5" 2 Percentage of non- managerial/Technical staff undergone through training 65% says yes "3.25" (E) OTHER 1 Order of Importance Safety-1 Cost-2 Quality-3 Time-4 2 Percentage of employees who are aware of the importance of Quality? 70% says yes "3.5" The above analysis includes calculation of percentage wise weightage: E.g. if the answer is 90%=90/100= 0.90/2= 4.5 out of 5 There are several methods for analysis of data but for this work I have used simple mathematicsi.e.Arithmeticmean=someof observation /no of observations. 4.0 DISCUSSIONS & FINDINGS As stated first I have made two type of question set, with 25 short questions asked during interview and three important questions given to them (hardcopy) for mail, after a while I received reply from their side through mail attached above. Question asked to them during interview contains set of series like initially I asked them about the quality control measure used on construction site is the quality of workmanship in all construction activities followed by proper sampling and testing on site, Quality Control laboratory at site, Site review meetings with staff, Awareness of Responsibilities etc.thenIaskedthem about Quality management during planning followed by Coordination with all the activities, Notice Daily schedule, Follow-Up meeting etc we discussed Obstacles working in team with respect Quality followed by Rigid attitude of higher management, Emphasis on short term objects, Lack of Education and training, Lack of resources then finally I asked them about Training followed by Percentage of managerial/supervisory staff undergonethroughtraining, Percentageof non-managerial/Technical staff undergone through training, other QuestionsaskedtothemarePercentageofemployeeswhoareawareofthe importance of Quality etc. I got different answers from different Project managers/Sr. Quality Engineers with little variation then I segregate all the answers with respect to Percentage and made a scale description as “5= Very Strong, 4=Strong,3= Moderate, 2= Less, 1= Very less”. Table 4: Arithmetic mean of all observations.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 341 s no Description observation 1 observation 2 observation 3 observation 4 Mean Average weightage 1 QUALITY CONTROL ON SITE 5 4.25 3.5 3.25 4 verystrong 2 QUALITY MANAGEMENT DURING PLANNING 4.1 4.35 4.5 4.316 verystrong 3 OBSTACLES WORKING IN TEAM WITH RESPECT QUALITY 3.55 3.45 4 4.25 3.812 Strong 4 TRAINING 4.5 3.25 3.875 Strong 5.0 CONCLUSIONS Very strongly respondent’s responses as observe regular schedule for the quality control measure used at site is quality of workmanship in all activities. Very strongly respondent’s responses as observe regular schedule for Quality management during planning. Obstacles working in team with respect Quality is Strong. Also, respondents have very strongly given to Training. After study of all above points through mail and interview i reached the following concluding remarks as below:  Better internal communication and team work on Quality Control.  Proper sampling and testing and Quality Control laboratory at site.  Awareness of Responsibilities and duties on site.  Suitable quality control method for the project.  Training to technical and non-technical staff with Focus on Quality Standards.  Set a Team for Quality Engineers on site. REFERENCES 1) Pravin P. Mane, Dr. Jalindar R. Patil Proceedings of the Civil Engineering PG Conference 2015, Held at MAEER’s MIT, Pune- 411038, 24-25 April 2015 [1] AbdulAziz A.B. and Tawfiq, H.A. (1999). ISO 9000 QualityStandardsinConstruction,Journal ofManagementin Engineering, Nov/Dec, pp. 41. [2] Abdul Rahim, A.H et al. (2004). Integration of Safety, Health, Environment and Quality (SHEQ) Management System in Construction: A Review. Jurnal Kejuruteraan Awam, Vol 16(1): 24-37, pp. 14. [3] Arditi, D. and Gunaydin, H.M. (1998), “Factors that affect process quality in the life cycle of building projects”, Journal of Construction Engineering and Management, ASCE, Vol. 124 No. 3, pp. 194-203. [4] Chin, K. S., & Choi, T. W. (2003). Construction in Hong Kong: Success factors for ISO 9000 implementation. Journal of Construction Engineering and Management, November/December, 599-609. [5] Checkland, P.B. & Scholes, J. (1990) Soft Systems Methodology in Action. Chichester: John Wiley & Sons. Proceedings ofthe Civil Engineering PG Conference 2015, Held at MAEER’s MIT, Pune-411038, 24-25 April 2015. Advances and Research inCivil Engineering and Technology - Construction Management 326
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 07 | July 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 342 [6] Giles, R. 1997. ISO 9000 perspective for construction industry in the UK. Training for Quality, Vol. 5 No. 4, pp 178-181. [7] ISO. (2004) The ISO survey of ISO 9001:2000 and ISO 14001 certificates 2003. BIOGRAPHIES Rizwan Showket M. Tech (CTM) Scholar from Desh Bhagat University Punjab. BLOGhttp://rizwanshowket.blogspot.co m/