International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1042
An Empirical Investigation into the Origins and Causes of Variation
Orders in Construction Projects
Ansuman Pati
Architect, Student (MBA-CPM), School of Construction, RICS School of Built Environment
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Construction projects are intricate and one-of-
a-kind procedures. Because of the dynamic nature of the
construction sector, it is nearly impossible to foresee
anything ahead of time. The initial strategy for the project
and the terms of the contract can undergo major shifts,
which can result in variations. Cost and time overruns are
the result of those differences. The majority ofvariationsare
observed to be caused by the human component. This study
describes the variations produced by construction project
stakeholders. It alsoemphasizesconcernsinindustryculture
and their impact on the number of variations. Although it is
an excellent practice to adequately plan all projects,changes
in circumstances need that flexibility to be maintained.
Measures should ideally be able to perform under both
expected and unexpected conditions, striking a balance
between precision and flexibility. The primary goal of this
study was to investigate the reasons for variation and to
advocate for the need for flexibility in contracts.
Key Words: Construction, Variations, Stakeholders,
Costs, Time.
1. INTRODUCTION
A construction contract is a contract thatcanberenegotiated
between the two parties involved in the project. The parties
to a contract may freely begin variation orders within the
scope of the works if the contract contains contractual
clauses pertaining to modifications. However, this does not
relieve the parties of any obligation to amend the original
contract in any way. Additions, deletions, adjustments, and
substitutions are all examples of what can be included in
variation orders in relation to the quality, quantity, and
schedule of the works. If there were no contractual terms,
the construction contractor would have to agree to build
exactly the structure that was depicted on the plans and
reflected in the invoices for the total amountthatwasagreed
upon for the contract, without making any modifications.
Because it is difficult for clients to envisage the ultimate
product they purchase, some variation should be expected
(Love 2002:19).
The drawback of the variation clause, on the other hand, is
that architects are less likely to put their intentions in
writing before signing the contract since they know the
variation clause will allow them to finalizetheirplansduring
the contract's term (Wainwright & Wood 1983:11).
Another disadvantage of the variation clause is that it
encourages clients toaltertheirmindsandstartconstruction
projects before adequately considering their project
requirements. (Finsen 1999:109).
Contractors, on the otherhand,are primarilyconcerned with
construction costs and their decrease.Therealitythat clients
or their agents may be causes of greater building expensesis
rarely acknowledged. Clients and consultants frequently
overlook the fact that issuing a large number of variation
orders leadstoincreasedconstructioncosts.(Ndihokubwayo,
Ruben & Haupt, Theo. (2008)).
Provisions for changes in contracts allowcontractingparties
to initiate variation orders within the scope of the work
without altering the original contract. (Ndihokubwayo and
Haupt 2008). Once a contract has been signed, its terms
cannot be amended unless the contract expressly allows for
it, and then only those changes that are plainly within the
contract's terms are permissible (Willis & Willis, 1980).
Variations and disagreements are fairly typical in building
projects, at work, and even in our daily lives (Arain and Low
2006). Variations are a typical occurrence in the
construction business, and they can cause time and cost
overruns as well as quality variations in both basic and
complex projects. Furthermore, change's indirect
consequences are important. Loss of productivity and
disruption of workflows and financial flows, as Bower
(2000) suggests, are examples of indirect consequencesthat
can lead to lower morale, claims, and disputes between
parties. (Chantawarangul, K., Suanpaga, W., Yazdani, S.,
Vimonsatit, V., and Singh, A. (Eds.))
Ssegawa et al.(2002) goes on to say that the existence of
contract variation clauses proves that no project can be
finished without adjustments. As a result, variation is a
persistent issue in the building business. Although it is ideal
if all projects are completely planned, changes in
circumstances(suchastheclient'soperational environment)
need maintaining flexibility. Failure to respond to
environmental influences may have an impact on the
project's output's appropriateness. (Hughes 1989). Project
measures including plans, processes, organizations,
contracts, and information systems should ideally be able to
perform in both expected and unexpected circumstances.
(Gilbreath 1986).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1043
These measures should strike a balance betweentheneed to
be exact and firm while still allowing for some wiggle room.
Projects in the construction industry are typically procured
using conventional contract forms. Although contract law
may be traced back to the roots of standard formsinmodern
commercial operations, there are differences between the
traditional paradigm of a single exchange transaction and
certain types of contracts, such as those in the building and
engineering industries. Some construction and engineering
projects take a long time to complete; they are not one-time
contracts. This causes issues since the impact of external
pressures on the construction process cannot be adequately
predicted or calculated. As a result, the output's
appropriateness is compromised. In the end, a reasonable
deal may out to be burdensome due to changing
circumstances. (Bell 1989: 195-220).
As a consequence of this, modifications are necessary in
order to take into account the shifting conditions that have
an impact on the process of building. The contractor, on the
other hand, is not obligated to comply with any alteration
request. Any deviation from the scope of work that a
contractor has committed to performing requires a newand
separate agreement. (Powell-SmithandSims1983,Murdoch
and Hughes 1992). Many scholars have emphasized thatit is
more advisable to includefuture-orientedterms becauseitis
difficult to finish all components of a contract prior to its
start.
2. Hypotheses
The hypotheses that will be evaluated in this investigation
are as follows:
 H1. Construction contracts are generally
one-sided in nature.
 H2. Non-flexibility nature of variation
clause in the contract document.
2.1 H1. Construction contracts are generally one-
sided in nature.
In large construction projects, the owner is the primary
source of variation. The most common reason for variations
is the owner's change of plans. This could be explained in
one of three ways. To begin with, the owner was not
involved in the design process. Given the positive or active
participation of the owner indicated in the first conclusion,
this is unlikely. The owner, on the other hand, did not
comprehend or see the design. The owner maynotbeable to
read drawings since the designer did not make the design
obvious. Third, it's just a mental shift that ignores the
negative consequences of changes. The findings revealed
that the owner can make changes as a result of financial
difficulties.
Construction contracts are usually written by the owner or
his agent (consultant) andincludethesubjectcontentaswell
as the terms and conditions. Typically, the construction
contract is jeopardized of (Alaa and Gorold 1993) :
Agreement Form for Bids
Standard specs or general circumstances
Distinctive provisions
Plansaddenda
Construction contracts must also include a compensation
mechanism, which is commonly classified as illustrated in
the figure.
Early detection of potential claims and disputes is one
method of completing a project that is free of issues. Simply
designing and executing a contract that attempts to shift the
risk of delays and expenses tothecontractorwill notprevent
disputes (Navigant Construction Forum, 2015). Contractors
and their legal counsel will almost certainly find a method to
circumvent such contract provisions. "What one guy can
invent, another man can circumvent," as the adage goes.
Before either the owners or the contractors can deal with a
conflict, they must both realize that one is on the way. The
parties to a contract are frequently in a conflict before they
realize it, according to experience.
"There is nothing permanent except change," declared
Heraclitus, an ancient Greek philosopher. This adage is still
true today, especially when a major project is being built.
Change orders are frequentlyderided byprojectowners,and
some even begin new projects by telling their contractor,
"There will be no change orders on this job!" Owners that
have this mindset are missing the point. The owner, not the
contractor, benefits from the contract's Changes provision.
The Adjustments clause gives the owner the flexibility to
change their minds, make changes to the work in progress,
modify the project to meet the owner's changing demands,
and so on. It's impossible to avoid change. As a result, before
starting a new project, the owner should assess theirchange
management system both internally and in the contract
agreements.
The Owner Announces "There Will Be No Change Orders on
This Project" at the Pre-Construction Meeting – For the
contractor, this is a clear early warning sign of potential
claims and disputes, as it indicates that the owner has
unrealistic design and construction expectationsand/orhas
not read their own contract. Constructivealterations,delays,
and constructive suspensions of work disputeddifferingsite
condition claims, and constructive acceleration is all claims
and conflicts that are likely to arise as a result of this
mindset.
A disadvantage of the variation clause is that it encourages
clients to alter their minds and start construction projects
before adequately considering their project requirements
(Finsen 1999:109).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1044
Contractors, on the otherhand,are primarilyconcerned with
construction costs and their decrease.Therealitythatclients
or their agents may be causes of greater building expensesis
rarely acknowledged. Clients and consultants frequently
overlook the fact that filing several change orders increases
construction expenses. For example, a client with a deadline
may desire construction to begin on-site when the design is
still in the early stages. Construction work may overlap the
design in some situations, forcing the contractor to wait for
the exact design. As a result, some projects are placed on
hold, while others are aborted or demolished.
(Adnan Enshassi, Faisal Arain & Sadi Al‐Raee, 2011)
commented that the link between ranking by owner and
contractor is substantial, whereas the correlations between
ranking by consultant and owner and consultant and
contractor are weak.
Therefore, the hypothesis that construction contracts are
generally one-sided in nature cannot be rejected.
2.2 Non-flexible nature of the variation clause in
the contract document.
Although it is ideal if all projects are well-planned, changes
in circumstances need maintaining flexibility. As a result,
specific phrases in contracts are introduced that allow for
revisions to the specification. However, allegations that
variations are the cause of delays, conflicts, and conflict in
the construction processhavecompletelyovershadowed the
benefit of contractual flexibility. Some of the debates are
over the amount of compensation that should be paid,
whether in terms of time or money. Contracts should be
written to reflect the needs of the parties in changing
conditions if these issues are to be avoided. Given restricted
rationality and opportunism, it is preferable to provide the
parties the option to negotiate over contract provisions that
are incompatible with their (changing) needs. In actuality,
the response of clients to the surroundings should dictate
the design of building projects. Failure to respond to
environmental influences may have an impact on the
project's output's appropriateness. (Hughes 1989). Project
measures including plans, processes, organizations,
contracts, and information systems should ideally be able to
perform in both expected and unexpected circumstances.
(Gilbreath 1986). These measures should strike a balance
between the need to be exact and firmwhilestill allowingfor
some wiggle room. Projects in the construction industry are
typically procured using conventional contract forms.
Although contract law can be traced back to the origins of
standard forms in modern business operations, there are
variations between building and engineering contracts and
the traditional paradigm of a single exchange transaction.
Some construction and engineering projectstakea longtime
to complete; they are not one-time contracts. This causes
issues since the impact of external pressures on the
construction process cannot be adequately predicted or
calculated. As a result, adjustments are required to reflect
the changing circumstances that affect the construction
process. Variations have been cited as a source of
disagreements and/or conflicts (Gardiner and Simmons
1992 & 1995, Wood 1975), partly as a result of delays
(Bromilow 1970, NEDO 1983) and interruption (Banwell
1964, Ireland 1985), which result in cost overruns.
Variations have also been blamed for the decline in output
(Latham 1994, Moselhi et al. 1990). The stigmatization of
variations has therefore led to their rigid nature in the
contract document.
3. CONCLUSION
The paper demonstrated that there is a substantial amount
of evidence in the literature to support the veracity of the
following claim: Variation is almost unavoidable in any
construction claim. Given the competitive nature of the
construction industry, many contractors suffer as a result of
the one-sided character of contracts and the non-flexible
nature of contract variation clauses. Because a trade-off
between price and performance is the norm, rigid variation
clauses invariably harm quality. As a result of the
construction industry's culture of variation claims, the
'agility' of the construction process is nearly hardtoachieve.
However, it should be noted that the sector is aware of its
internal issues, and much work is being done to mitigate the
hazards associated with construction variations.
REFERENCES
[1] Arain, F. M.; Low, S. P. 2006. Developers' Views of
Potential Causes of Variation Orders for Institutional
Buildings in Singapore, Architectural Science Review
49(1): 59–74.
[2] Alaa, Z. and O. Garold, 1993. Early Warning Signs of
Project Variations, Oklahoma State University/CII
Source Document No. 91, Finland: 37–49.
[3] Adnan Enshassi , Faisal Arain & Sadi Al‐Raee (2010)
Causes of variation ordersin constructionprojectsinthe
Gaza Strip, Journal of Civil Engineering and
Management, 16:4, 540–551.
[4] Banwell, H. (1964) The placing and management of
contracts for building and civil engineering works:
report of the committee. London, HMSO.
[5] Bell, J. (1989) The effect of changes in circumstances on
long-term contracts: English report. In: Harris, D. and
Tallon, D. (eds.) Contract Law Today. Oxford: Clarendon
Press.
[6] Bromilow, F.J. (1970) The nature and extent of
variations tobuildingcontracts.TheBuildingEconomist,
9(3), 93-104, 112.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1045
[7] Chantawarangul, K., Suanpaga, W., Yazdani, S.,
Vimonsatit, V., and Singh, A. (Eds.). Tan, W., Practical
Research Methods 2nd Ed., Singapore: Prentice Hall,
2002.
[8] Finsen, E. 1999. The Building Contract - A Commentary
on the JBCC Agreements, 1st ed., Cape Town: Juta & Co,
Ltd.
[9] Gardiner, P.D. and Simmons, J.E.L. (1995) Case
explorations in construction conflict management.
Construction Management and Economics,13,219-234.
[10] Gilbreath, R.D. (1986) Winning at project management:
what works, what fails and why.NewYork:John Wiley &
Sons.
[11] Hughes, W.P. (1989) Organizational analysis of building
projects. Unpublished Ph.D. dissertation. Liverpool
Polytechnic.
[12] Latham, M. (1994) Constructing the team:final reportof
the government/industry review of procurement and
contractual arrangement in the UK construction
industry. London: HMSO.
[13] Love, P.E.D. 2002. Influence of Project Type and
Procurement Method on Rework Costs in Building
Construction Projects, Journal of Construction
Engineering and Management, 128(1), 1-29.
[14] Navigant Construction Forum, 2015. A Crystal Ball –
Early Warning Signs of Construction Claims & Disputes,
4-6.
[15] Ndihokubwayo, Ruben & Haupt, Theo.
(2008). Uncovering the Origins of Variation Orders.
[16] Powell-Smith, V. and Sims, J. (1983) Building contract
claims. London: Granada.
[17] Ssegawa, J. K., Mfolwe, K. M., Makuke, B., and Kutua, B.,
Construction Variations: A Scourge or a Necessity?
Proceedings of the First International ConferenceofCIB
W107, Cape Town, South Africa, 2002.
[18] Wainwright, W.H. & Wood A.A.B. 1983. Variation and
Final Account Procedure, 4th ed. Hutchinson: Nelson
Thornes ltd.
[19] Willis, A.J. & Willis, C.J. 1980, ‘Practice and Procedure of
the Quantity Surveyor’, 8th ed. London: Granada.
BIOGRAPHY
Ansuman Pati graduated from the
Manipal School ofArchitectureand
Planning. As an Architect with 2
years of experience in the Built
Environment Industry, he is
currently pursing MBA in
Construction Project Management
from the Royal Institute of
Chartered Surveyors, School of
Built Environment.

More Related Content

Similar to An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects

A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...Sarah Adams
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectIRJET Journal
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectIOSR Journals
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 SigmaDimitrios Kordas
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsIRJET Journal
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver bookmoodlyd
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Behold The Construction Contract
Behold The Construction ContractBehold The Construction Contract
Behold The Construction ContractGarrettLudwig
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 

Similar to An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects (20)

A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
FIDIC 2019
FIDIC 2019FIDIC 2019
FIDIC 2019
 
Fidic db-yellow-book
Fidic db-yellow-bookFidic db-yellow-book
Fidic db-yellow-book
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver book
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Behold The Construction Contract
Behold The Construction ContractBehold The Construction Contract
Behold The Construction Contract
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Determinative forum - 19 August
Determinative forum - 19 AugustDeterminative forum - 19 August
Determinative forum - 19 August
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1042 An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects Ansuman Pati Architect, Student (MBA-CPM), School of Construction, RICS School of Built Environment ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Construction projects are intricate and one-of- a-kind procedures. Because of the dynamic nature of the construction sector, it is nearly impossible to foresee anything ahead of time. The initial strategy for the project and the terms of the contract can undergo major shifts, which can result in variations. Cost and time overruns are the result of those differences. The majority ofvariationsare observed to be caused by the human component. This study describes the variations produced by construction project stakeholders. It alsoemphasizesconcernsinindustryculture and their impact on the number of variations. Although it is an excellent practice to adequately plan all projects,changes in circumstances need that flexibility to be maintained. Measures should ideally be able to perform under both expected and unexpected conditions, striking a balance between precision and flexibility. The primary goal of this study was to investigate the reasons for variation and to advocate for the need for flexibility in contracts. Key Words: Construction, Variations, Stakeholders, Costs, Time. 1. INTRODUCTION A construction contract is a contract thatcanberenegotiated between the two parties involved in the project. The parties to a contract may freely begin variation orders within the scope of the works if the contract contains contractual clauses pertaining to modifications. However, this does not relieve the parties of any obligation to amend the original contract in any way. Additions, deletions, adjustments, and substitutions are all examples of what can be included in variation orders in relation to the quality, quantity, and schedule of the works. If there were no contractual terms, the construction contractor would have to agree to build exactly the structure that was depicted on the plans and reflected in the invoices for the total amountthatwasagreed upon for the contract, without making any modifications. Because it is difficult for clients to envisage the ultimate product they purchase, some variation should be expected (Love 2002:19). The drawback of the variation clause, on the other hand, is that architects are less likely to put their intentions in writing before signing the contract since they know the variation clause will allow them to finalizetheirplansduring the contract's term (Wainwright & Wood 1983:11). Another disadvantage of the variation clause is that it encourages clients toaltertheirmindsandstartconstruction projects before adequately considering their project requirements. (Finsen 1999:109). Contractors, on the otherhand,are primarilyconcerned with construction costs and their decrease.Therealitythat clients or their agents may be causes of greater building expensesis rarely acknowledged. Clients and consultants frequently overlook the fact that issuing a large number of variation orders leadstoincreasedconstructioncosts.(Ndihokubwayo, Ruben & Haupt, Theo. (2008)). Provisions for changes in contracts allowcontractingparties to initiate variation orders within the scope of the work without altering the original contract. (Ndihokubwayo and Haupt 2008). Once a contract has been signed, its terms cannot be amended unless the contract expressly allows for it, and then only those changes that are plainly within the contract's terms are permissible (Willis & Willis, 1980). Variations and disagreements are fairly typical in building projects, at work, and even in our daily lives (Arain and Low 2006). Variations are a typical occurrence in the construction business, and they can cause time and cost overruns as well as quality variations in both basic and complex projects. Furthermore, change's indirect consequences are important. Loss of productivity and disruption of workflows and financial flows, as Bower (2000) suggests, are examples of indirect consequencesthat can lead to lower morale, claims, and disputes between parties. (Chantawarangul, K., Suanpaga, W., Yazdani, S., Vimonsatit, V., and Singh, A. (Eds.)) Ssegawa et al.(2002) goes on to say that the existence of contract variation clauses proves that no project can be finished without adjustments. As a result, variation is a persistent issue in the building business. Although it is ideal if all projects are completely planned, changes in circumstances(suchastheclient'soperational environment) need maintaining flexibility. Failure to respond to environmental influences may have an impact on the project's output's appropriateness. (Hughes 1989). Project measures including plans, processes, organizations, contracts, and information systems should ideally be able to perform in both expected and unexpected circumstances. (Gilbreath 1986).
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1043 These measures should strike a balance betweentheneed to be exact and firm while still allowing for some wiggle room. Projects in the construction industry are typically procured using conventional contract forms. Although contract law may be traced back to the roots of standard formsinmodern commercial operations, there are differences between the traditional paradigm of a single exchange transaction and certain types of contracts, such as those in the building and engineering industries. Some construction and engineering projects take a long time to complete; they are not one-time contracts. This causes issues since the impact of external pressures on the construction process cannot be adequately predicted or calculated. As a result, the output's appropriateness is compromised. In the end, a reasonable deal may out to be burdensome due to changing circumstances. (Bell 1989: 195-220). As a consequence of this, modifications are necessary in order to take into account the shifting conditions that have an impact on the process of building. The contractor, on the other hand, is not obligated to comply with any alteration request. Any deviation from the scope of work that a contractor has committed to performing requires a newand separate agreement. (Powell-SmithandSims1983,Murdoch and Hughes 1992). Many scholars have emphasized thatit is more advisable to includefuture-orientedterms becauseitis difficult to finish all components of a contract prior to its start. 2. Hypotheses The hypotheses that will be evaluated in this investigation are as follows:  H1. Construction contracts are generally one-sided in nature.  H2. Non-flexibility nature of variation clause in the contract document. 2.1 H1. Construction contracts are generally one- sided in nature. In large construction projects, the owner is the primary source of variation. The most common reason for variations is the owner's change of plans. This could be explained in one of three ways. To begin with, the owner was not involved in the design process. Given the positive or active participation of the owner indicated in the first conclusion, this is unlikely. The owner, on the other hand, did not comprehend or see the design. The owner maynotbeable to read drawings since the designer did not make the design obvious. Third, it's just a mental shift that ignores the negative consequences of changes. The findings revealed that the owner can make changes as a result of financial difficulties. Construction contracts are usually written by the owner or his agent (consultant) andincludethesubjectcontentaswell as the terms and conditions. Typically, the construction contract is jeopardized of (Alaa and Gorold 1993) : Agreement Form for Bids Standard specs or general circumstances Distinctive provisions Plansaddenda Construction contracts must also include a compensation mechanism, which is commonly classified as illustrated in the figure. Early detection of potential claims and disputes is one method of completing a project that is free of issues. Simply designing and executing a contract that attempts to shift the risk of delays and expenses tothecontractorwill notprevent disputes (Navigant Construction Forum, 2015). Contractors and their legal counsel will almost certainly find a method to circumvent such contract provisions. "What one guy can invent, another man can circumvent," as the adage goes. Before either the owners or the contractors can deal with a conflict, they must both realize that one is on the way. The parties to a contract are frequently in a conflict before they realize it, according to experience. "There is nothing permanent except change," declared Heraclitus, an ancient Greek philosopher. This adage is still true today, especially when a major project is being built. Change orders are frequentlyderided byprojectowners,and some even begin new projects by telling their contractor, "There will be no change orders on this job!" Owners that have this mindset are missing the point. The owner, not the contractor, benefits from the contract's Changes provision. The Adjustments clause gives the owner the flexibility to change their minds, make changes to the work in progress, modify the project to meet the owner's changing demands, and so on. It's impossible to avoid change. As a result, before starting a new project, the owner should assess theirchange management system both internally and in the contract agreements. The Owner Announces "There Will Be No Change Orders on This Project" at the Pre-Construction Meeting – For the contractor, this is a clear early warning sign of potential claims and disputes, as it indicates that the owner has unrealistic design and construction expectationsand/orhas not read their own contract. Constructivealterations,delays, and constructive suspensions of work disputeddifferingsite condition claims, and constructive acceleration is all claims and conflicts that are likely to arise as a result of this mindset. A disadvantage of the variation clause is that it encourages clients to alter their minds and start construction projects before adequately considering their project requirements (Finsen 1999:109).
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1044 Contractors, on the otherhand,are primarilyconcerned with construction costs and their decrease.Therealitythatclients or their agents may be causes of greater building expensesis rarely acknowledged. Clients and consultants frequently overlook the fact that filing several change orders increases construction expenses. For example, a client with a deadline may desire construction to begin on-site when the design is still in the early stages. Construction work may overlap the design in some situations, forcing the contractor to wait for the exact design. As a result, some projects are placed on hold, while others are aborted or demolished. (Adnan Enshassi, Faisal Arain & Sadi Al‐Raee, 2011) commented that the link between ranking by owner and contractor is substantial, whereas the correlations between ranking by consultant and owner and consultant and contractor are weak. Therefore, the hypothesis that construction contracts are generally one-sided in nature cannot be rejected. 2.2 Non-flexible nature of the variation clause in the contract document. Although it is ideal if all projects are well-planned, changes in circumstances need maintaining flexibility. As a result, specific phrases in contracts are introduced that allow for revisions to the specification. However, allegations that variations are the cause of delays, conflicts, and conflict in the construction processhavecompletelyovershadowed the benefit of contractual flexibility. Some of the debates are over the amount of compensation that should be paid, whether in terms of time or money. Contracts should be written to reflect the needs of the parties in changing conditions if these issues are to be avoided. Given restricted rationality and opportunism, it is preferable to provide the parties the option to negotiate over contract provisions that are incompatible with their (changing) needs. In actuality, the response of clients to the surroundings should dictate the design of building projects. Failure to respond to environmental influences may have an impact on the project's output's appropriateness. (Hughes 1989). Project measures including plans, processes, organizations, contracts, and information systems should ideally be able to perform in both expected and unexpected circumstances. (Gilbreath 1986). These measures should strike a balance between the need to be exact and firmwhilestill allowingfor some wiggle room. Projects in the construction industry are typically procured using conventional contract forms. Although contract law can be traced back to the origins of standard forms in modern business operations, there are variations between building and engineering contracts and the traditional paradigm of a single exchange transaction. Some construction and engineering projectstakea longtime to complete; they are not one-time contracts. This causes issues since the impact of external pressures on the construction process cannot be adequately predicted or calculated. As a result, adjustments are required to reflect the changing circumstances that affect the construction process. Variations have been cited as a source of disagreements and/or conflicts (Gardiner and Simmons 1992 & 1995, Wood 1975), partly as a result of delays (Bromilow 1970, NEDO 1983) and interruption (Banwell 1964, Ireland 1985), which result in cost overruns. Variations have also been blamed for the decline in output (Latham 1994, Moselhi et al. 1990). The stigmatization of variations has therefore led to their rigid nature in the contract document. 3. CONCLUSION The paper demonstrated that there is a substantial amount of evidence in the literature to support the veracity of the following claim: Variation is almost unavoidable in any construction claim. Given the competitive nature of the construction industry, many contractors suffer as a result of the one-sided character of contracts and the non-flexible nature of contract variation clauses. Because a trade-off between price and performance is the norm, rigid variation clauses invariably harm quality. As a result of the construction industry's culture of variation claims, the 'agility' of the construction process is nearly hardtoachieve. However, it should be noted that the sector is aware of its internal issues, and much work is being done to mitigate the hazards associated with construction variations. REFERENCES [1] Arain, F. M.; Low, S. P. 2006. Developers' Views of Potential Causes of Variation Orders for Institutional Buildings in Singapore, Architectural Science Review 49(1): 59–74. [2] Alaa, Z. and O. Garold, 1993. Early Warning Signs of Project Variations, Oklahoma State University/CII Source Document No. 91, Finland: 37–49. [3] Adnan Enshassi , Faisal Arain & Sadi Al‐Raee (2010) Causes of variation ordersin constructionprojectsinthe Gaza Strip, Journal of Civil Engineering and Management, 16:4, 540–551. [4] Banwell, H. (1964) The placing and management of contracts for building and civil engineering works: report of the committee. London, HMSO. [5] Bell, J. (1989) The effect of changes in circumstances on long-term contracts: English report. In: Harris, D. and Tallon, D. (eds.) Contract Law Today. Oxford: Clarendon Press. [6] Bromilow, F.J. (1970) The nature and extent of variations tobuildingcontracts.TheBuildingEconomist, 9(3), 93-104, 112.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1045 [7] Chantawarangul, K., Suanpaga, W., Yazdani, S., Vimonsatit, V., and Singh, A. (Eds.). Tan, W., Practical Research Methods 2nd Ed., Singapore: Prentice Hall, 2002. [8] Finsen, E. 1999. The Building Contract - A Commentary on the JBCC Agreements, 1st ed., Cape Town: Juta & Co, Ltd. [9] Gardiner, P.D. and Simmons, J.E.L. (1995) Case explorations in construction conflict management. Construction Management and Economics,13,219-234. [10] Gilbreath, R.D. (1986) Winning at project management: what works, what fails and why.NewYork:John Wiley & Sons. [11] Hughes, W.P. (1989) Organizational analysis of building projects. Unpublished Ph.D. dissertation. Liverpool Polytechnic. [12] Latham, M. (1994) Constructing the team:final reportof the government/industry review of procurement and contractual arrangement in the UK construction industry. London: HMSO. [13] Love, P.E.D. 2002. Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects, Journal of Construction Engineering and Management, 128(1), 1-29. [14] Navigant Construction Forum, 2015. A Crystal Ball – Early Warning Signs of Construction Claims & Disputes, 4-6. [15] Ndihokubwayo, Ruben & Haupt, Theo. (2008). Uncovering the Origins of Variation Orders. [16] Powell-Smith, V. and Sims, J. (1983) Building contract claims. London: Granada. [17] Ssegawa, J. K., Mfolwe, K. M., Makuke, B., and Kutua, B., Construction Variations: A Scourge or a Necessity? Proceedings of the First International ConferenceofCIB W107, Cape Town, South Africa, 2002. [18] Wainwright, W.H. & Wood A.A.B. 1983. Variation and Final Account Procedure, 4th ed. Hutchinson: Nelson Thornes ltd. [19] Willis, A.J. & Willis, C.J. 1980, ‘Practice and Procedure of the Quantity Surveyor’, 8th ed. London: Granada. BIOGRAPHY Ansuman Pati graduated from the Manipal School ofArchitectureand Planning. As an Architect with 2 years of experience in the Built Environment Industry, he is currently pursing MBA in Construction Project Management from the Royal Institute of Chartered Surveyors, School of Built Environment.