An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects
•
0 likes
•
3 views
IRJET Journal
Follow
https://www.irjet.net/archives/V9/i7/IRJET-V9I7200.pdf
Read less
Read more
Engineering
Report
Share
Report
Share
1 of 4
Download now
Download to read offline
Recommended
Assignment 1 Complete
Assignment 1 Complete
John Ashton
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
IAEME Publication
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
Alexander Decker
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
Alexander Decker
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
Financial management of construction contracts
Financial management of construction contracts
idnobleg77
Construction Law Presentation
Construction Law Presentation
elliotfus
Recommended
Assignment 1 Complete
Assignment 1 Complete
John Ashton
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
IAEME Publication
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
Alexander Decker
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
Alexander Decker
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
Financial management of construction contracts
Financial management of construction contracts
idnobleg77
Construction Law Presentation
Construction Law Presentation
elliotfus
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
Sarah Adams
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
IRJET Journal
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
Dimitrios Kordas
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
FIDIC 2019
FIDIC 2019
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
Fidic db-yellow-book
Fidic db-yellow-book
Vedants Sharma
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET Journal
TOPIC7.pdf
TOPIC7.pdf
HASMANIRA
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
IRJET Journal
Fi dic silver book
Fi dic silver book
moodlyd
Chapter 1- Procurement management
Chapter 1- Procurement management
Delhi Technological University
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
IOSR Journals
Literature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
Behold The Construction Contract
Behold The Construction Contract
GarrettLudwig
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
George Wilkinson
Determinative forum - 19 August
Determinative forum - 19 August
Resolution Institute
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
More Related Content
Similar to An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
Sarah Adams
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
IRJET Journal
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
IOSR Journals
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
Dimitrios Kordas
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
FIDIC 2019
FIDIC 2019
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
Fidic db-yellow-book
Fidic db-yellow-book
Vedants Sharma
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET Journal
TOPIC7.pdf
TOPIC7.pdf
HASMANIRA
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
IRJET Journal
Fi dic silver book
Fi dic silver book
moodlyd
Chapter 1- Procurement management
Chapter 1- Procurement management
Delhi Technological University
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
IOSR Journals
Literature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
Behold The Construction Contract
Behold The Construction Contract
GarrettLudwig
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
George Wilkinson
Determinative forum - 19 August
Determinative forum - 19 August
Resolution Institute
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
Similar to An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects
(20)
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
FIDIC 2019
FIDIC 2019
Fidic db-yellow-book
Fidic db-yellow-book
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
TOPIC7.pdf
TOPIC7.pdf
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Risk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
Fi dic silver book
Fi dic silver book
Chapter 1- Procurement management
Chapter 1- Procurement management
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
Literature review on_ extension of time
Literature review on_ extension of time
Behold The Construction Contract
Behold The Construction Contract
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
Determinative forum - 19 August
Determinative forum - 19 August
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
More from IRJET Journal
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
React based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
More from IRJET Journal
(20)
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
React based fullstack edtech web application
React based fullstack edtech web application
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Recently uploaded
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
rakeshbaidya232001
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
purnimasatapathy1234
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
Call Girls in Nagpur High Profile
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
ranjana rawat
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur High Profile
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Asutosh Ranjan
Internship report on mechanical engineering
Internship report on mechanical engineering
malavadedarshan25
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
rehmti665
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
ssuser5c9d4b1
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
null - The Open Security Community
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Suman Mia
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
ranjana rawat
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
upamatechverse
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
9953056974 Low Rate Call Girls In Saket, Delhi NCR
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Dr.Costas Sachpazis
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
hassan khalil
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
RajaP95
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
KurinjimalarL3
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Mark Billinghurst
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Anamika Sarkar
Recently uploaded
(20)
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Internship report on mechanical engineering
Internship report on mechanical engineering
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects
1.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1042 An Empirical Investigation into the Origins and Causes of Variation Orders in Construction Projects Ansuman Pati Architect, Student (MBA-CPM), School of Construction, RICS School of Built Environment ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Construction projects are intricate and one-of- a-kind procedures. Because of the dynamic nature of the construction sector, it is nearly impossible to foresee anything ahead of time. The initial strategy for the project and the terms of the contract can undergo major shifts, which can result in variations. Cost and time overruns are the result of those differences. The majority ofvariationsare observed to be caused by the human component. This study describes the variations produced by construction project stakeholders. It alsoemphasizesconcernsinindustryculture and their impact on the number of variations. Although it is an excellent practice to adequately plan all projects,changes in circumstances need that flexibility to be maintained. Measures should ideally be able to perform under both expected and unexpected conditions, striking a balance between precision and flexibility. The primary goal of this study was to investigate the reasons for variation and to advocate for the need for flexibility in contracts. Key Words: Construction, Variations, Stakeholders, Costs, Time. 1. INTRODUCTION A construction contract is a contract thatcanberenegotiated between the two parties involved in the project. The parties to a contract may freely begin variation orders within the scope of the works if the contract contains contractual clauses pertaining to modifications. However, this does not relieve the parties of any obligation to amend the original contract in any way. Additions, deletions, adjustments, and substitutions are all examples of what can be included in variation orders in relation to the quality, quantity, and schedule of the works. If there were no contractual terms, the construction contractor would have to agree to build exactly the structure that was depicted on the plans and reflected in the invoices for the total amountthatwasagreed upon for the contract, without making any modifications. Because it is difficult for clients to envisage the ultimate product they purchase, some variation should be expected (Love 2002:19). The drawback of the variation clause, on the other hand, is that architects are less likely to put their intentions in writing before signing the contract since they know the variation clause will allow them to finalizetheirplansduring the contract's term (Wainwright & Wood 1983:11). Another disadvantage of the variation clause is that it encourages clients toaltertheirmindsandstartconstruction projects before adequately considering their project requirements. (Finsen 1999:109). Contractors, on the otherhand,are primarilyconcerned with construction costs and their decrease.Therealitythat clients or their agents may be causes of greater building expensesis rarely acknowledged. Clients and consultants frequently overlook the fact that issuing a large number of variation orders leadstoincreasedconstructioncosts.(Ndihokubwayo, Ruben & Haupt, Theo. (2008)). Provisions for changes in contracts allowcontractingparties to initiate variation orders within the scope of the work without altering the original contract. (Ndihokubwayo and Haupt 2008). Once a contract has been signed, its terms cannot be amended unless the contract expressly allows for it, and then only those changes that are plainly within the contract's terms are permissible (Willis & Willis, 1980). Variations and disagreements are fairly typical in building projects, at work, and even in our daily lives (Arain and Low 2006). Variations are a typical occurrence in the construction business, and they can cause time and cost overruns as well as quality variations in both basic and complex projects. Furthermore, change's indirect consequences are important. Loss of productivity and disruption of workflows and financial flows, as Bower (2000) suggests, are examples of indirect consequencesthat can lead to lower morale, claims, and disputes between parties. (Chantawarangul, K., Suanpaga, W., Yazdani, S., Vimonsatit, V., and Singh, A. (Eds.)) Ssegawa et al.(2002) goes on to say that the existence of contract variation clauses proves that no project can be finished without adjustments. As a result, variation is a persistent issue in the building business. Although it is ideal if all projects are completely planned, changes in circumstances(suchastheclient'soperational environment) need maintaining flexibility. Failure to respond to environmental influences may have an impact on the project's output's appropriateness. (Hughes 1989). Project measures including plans, processes, organizations, contracts, and information systems should ideally be able to perform in both expected and unexpected circumstances. (Gilbreath 1986).
2.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1043 These measures should strike a balance betweentheneed to be exact and firm while still allowing for some wiggle room. Projects in the construction industry are typically procured using conventional contract forms. Although contract law may be traced back to the roots of standard formsinmodern commercial operations, there are differences between the traditional paradigm of a single exchange transaction and certain types of contracts, such as those in the building and engineering industries. Some construction and engineering projects take a long time to complete; they are not one-time contracts. This causes issues since the impact of external pressures on the construction process cannot be adequately predicted or calculated. As a result, the output's appropriateness is compromised. In the end, a reasonable deal may out to be burdensome due to changing circumstances. (Bell 1989: 195-220). As a consequence of this, modifications are necessary in order to take into account the shifting conditions that have an impact on the process of building. The contractor, on the other hand, is not obligated to comply with any alteration request. Any deviation from the scope of work that a contractor has committed to performing requires a newand separate agreement. (Powell-SmithandSims1983,Murdoch and Hughes 1992). Many scholars have emphasized thatit is more advisable to includefuture-orientedterms becauseitis difficult to finish all components of a contract prior to its start. 2. Hypotheses The hypotheses that will be evaluated in this investigation are as follows: H1. Construction contracts are generally one-sided in nature. H2. Non-flexibility nature of variation clause in the contract document. 2.1 H1. Construction contracts are generally one- sided in nature. In large construction projects, the owner is the primary source of variation. The most common reason for variations is the owner's change of plans. This could be explained in one of three ways. To begin with, the owner was not involved in the design process. Given the positive or active participation of the owner indicated in the first conclusion, this is unlikely. The owner, on the other hand, did not comprehend or see the design. The owner maynotbeable to read drawings since the designer did not make the design obvious. Third, it's just a mental shift that ignores the negative consequences of changes. The findings revealed that the owner can make changes as a result of financial difficulties. Construction contracts are usually written by the owner or his agent (consultant) andincludethesubjectcontentaswell as the terms and conditions. Typically, the construction contract is jeopardized of (Alaa and Gorold 1993) : Agreement Form for Bids Standard specs or general circumstances Distinctive provisions Plansaddenda Construction contracts must also include a compensation mechanism, which is commonly classified as illustrated in the figure. Early detection of potential claims and disputes is one method of completing a project that is free of issues. Simply designing and executing a contract that attempts to shift the risk of delays and expenses tothecontractorwill notprevent disputes (Navigant Construction Forum, 2015). Contractors and their legal counsel will almost certainly find a method to circumvent such contract provisions. "What one guy can invent, another man can circumvent," as the adage goes. Before either the owners or the contractors can deal with a conflict, they must both realize that one is on the way. The parties to a contract are frequently in a conflict before they realize it, according to experience. "There is nothing permanent except change," declared Heraclitus, an ancient Greek philosopher. This adage is still true today, especially when a major project is being built. Change orders are frequentlyderided byprojectowners,and some even begin new projects by telling their contractor, "There will be no change orders on this job!" Owners that have this mindset are missing the point. The owner, not the contractor, benefits from the contract's Changes provision. The Adjustments clause gives the owner the flexibility to change their minds, make changes to the work in progress, modify the project to meet the owner's changing demands, and so on. It's impossible to avoid change. As a result, before starting a new project, the owner should assess theirchange management system both internally and in the contract agreements. The Owner Announces "There Will Be No Change Orders on This Project" at the Pre-Construction Meeting – For the contractor, this is a clear early warning sign of potential claims and disputes, as it indicates that the owner has unrealistic design and construction expectationsand/orhas not read their own contract. Constructivealterations,delays, and constructive suspensions of work disputeddifferingsite condition claims, and constructive acceleration is all claims and conflicts that are likely to arise as a result of this mindset. A disadvantage of the variation clause is that it encourages clients to alter their minds and start construction projects before adequately considering their project requirements (Finsen 1999:109).
3.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1044 Contractors, on the otherhand,are primarilyconcerned with construction costs and their decrease.Therealitythatclients or their agents may be causes of greater building expensesis rarely acknowledged. Clients and consultants frequently overlook the fact that filing several change orders increases construction expenses. For example, a client with a deadline may desire construction to begin on-site when the design is still in the early stages. Construction work may overlap the design in some situations, forcing the contractor to wait for the exact design. As a result, some projects are placed on hold, while others are aborted or demolished. (Adnan Enshassi, Faisal Arain & Sadi Al‐Raee, 2011) commented that the link between ranking by owner and contractor is substantial, whereas the correlations between ranking by consultant and owner and consultant and contractor are weak. Therefore, the hypothesis that construction contracts are generally one-sided in nature cannot be rejected. 2.2 Non-flexible nature of the variation clause in the contract document. Although it is ideal if all projects are well-planned, changes in circumstances need maintaining flexibility. As a result, specific phrases in contracts are introduced that allow for revisions to the specification. However, allegations that variations are the cause of delays, conflicts, and conflict in the construction processhavecompletelyovershadowed the benefit of contractual flexibility. Some of the debates are over the amount of compensation that should be paid, whether in terms of time or money. Contracts should be written to reflect the needs of the parties in changing conditions if these issues are to be avoided. Given restricted rationality and opportunism, it is preferable to provide the parties the option to negotiate over contract provisions that are incompatible with their (changing) needs. In actuality, the response of clients to the surroundings should dictate the design of building projects. Failure to respond to environmental influences may have an impact on the project's output's appropriateness. (Hughes 1989). Project measures including plans, processes, organizations, contracts, and information systems should ideally be able to perform in both expected and unexpected circumstances. (Gilbreath 1986). These measures should strike a balance between the need to be exact and firmwhilestill allowingfor some wiggle room. Projects in the construction industry are typically procured using conventional contract forms. Although contract law can be traced back to the origins of standard forms in modern business operations, there are variations between building and engineering contracts and the traditional paradigm of a single exchange transaction. Some construction and engineering projectstakea longtime to complete; they are not one-time contracts. This causes issues since the impact of external pressures on the construction process cannot be adequately predicted or calculated. As a result, adjustments are required to reflect the changing circumstances that affect the construction process. Variations have been cited as a source of disagreements and/or conflicts (Gardiner and Simmons 1992 & 1995, Wood 1975), partly as a result of delays (Bromilow 1970, NEDO 1983) and interruption (Banwell 1964, Ireland 1985), which result in cost overruns. Variations have also been blamed for the decline in output (Latham 1994, Moselhi et al. 1990). The stigmatization of variations has therefore led to their rigid nature in the contract document. 3. CONCLUSION The paper demonstrated that there is a substantial amount of evidence in the literature to support the veracity of the following claim: Variation is almost unavoidable in any construction claim. Given the competitive nature of the construction industry, many contractors suffer as a result of the one-sided character of contracts and the non-flexible nature of contract variation clauses. Because a trade-off between price and performance is the norm, rigid variation clauses invariably harm quality. As a result of the construction industry's culture of variation claims, the 'agility' of the construction process is nearly hardtoachieve. However, it should be noted that the sector is aware of its internal issues, and much work is being done to mitigate the hazards associated with construction variations. REFERENCES [1] Arain, F. M.; Low, S. P. 2006. Developers' Views of Potential Causes of Variation Orders for Institutional Buildings in Singapore, Architectural Science Review 49(1): 59–74. [2] Alaa, Z. and O. Garold, 1993. Early Warning Signs of Project Variations, Oklahoma State University/CII Source Document No. 91, Finland: 37–49. [3] Adnan Enshassi , Faisal Arain & Sadi Al‐Raee (2010) Causes of variation ordersin constructionprojectsinthe Gaza Strip, Journal of Civil Engineering and Management, 16:4, 540–551. [4] Banwell, H. (1964) The placing and management of contracts for building and civil engineering works: report of the committee. London, HMSO. [5] Bell, J. (1989) The effect of changes in circumstances on long-term contracts: English report. In: Harris, D. and Tallon, D. (eds.) Contract Law Today. Oxford: Clarendon Press. [6] Bromilow, F.J. (1970) The nature and extent of variations tobuildingcontracts.TheBuildingEconomist, 9(3), 93-104, 112.
4.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1045 [7] Chantawarangul, K., Suanpaga, W., Yazdani, S., Vimonsatit, V., and Singh, A. (Eds.). Tan, W., Practical Research Methods 2nd Ed., Singapore: Prentice Hall, 2002. [8] Finsen, E. 1999. The Building Contract - A Commentary on the JBCC Agreements, 1st ed., Cape Town: Juta & Co, Ltd. [9] Gardiner, P.D. and Simmons, J.E.L. (1995) Case explorations in construction conflict management. Construction Management and Economics,13,219-234. [10] Gilbreath, R.D. (1986) Winning at project management: what works, what fails and why.NewYork:John Wiley & Sons. [11] Hughes, W.P. (1989) Organizational analysis of building projects. Unpublished Ph.D. dissertation. Liverpool Polytechnic. [12] Latham, M. (1994) Constructing the team:final reportof the government/industry review of procurement and contractual arrangement in the UK construction industry. London: HMSO. [13] Love, P.E.D. 2002. Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects, Journal of Construction Engineering and Management, 128(1), 1-29. [14] Navigant Construction Forum, 2015. A Crystal Ball – Early Warning Signs of Construction Claims & Disputes, 4-6. [15] Ndihokubwayo, Ruben & Haupt, Theo. (2008). Uncovering the Origins of Variation Orders. [16] Powell-Smith, V. and Sims, J. (1983) Building contract claims. London: Granada. [17] Ssegawa, J. K., Mfolwe, K. M., Makuke, B., and Kutua, B., Construction Variations: A Scourge or a Necessity? Proceedings of the First International ConferenceofCIB W107, Cape Town, South Africa, 2002. [18] Wainwright, W.H. & Wood A.A.B. 1983. Variation and Final Account Procedure, 4th ed. Hutchinson: Nelson Thornes ltd. [19] Willis, A.J. & Willis, C.J. 1980, ‘Practice and Procedure of the Quantity Surveyor’, 8th ed. London: Granada. BIOGRAPHY Ansuman Pati graduated from the Manipal School ofArchitectureand Planning. As an Architect with 2 years of experience in the Built Environment Industry, he is currently pursing MBA in Construction Project Management from the Royal Institute of Chartered Surveyors, School of Built Environment.
Download now