CONS5Q25 Assignment 3 Praveen Premkumar as at 25th
August 2009
Student ID: 1213020
2.0Common Types of Construction Contracts and Standard Conditions of
Contract
The common type of procurement option of construction contract in the building industry
is mainly lump sum contracts. It is described that procurement is a generic term used to
“getting” building. (C. Prigg, personal communication, July 28, 2009)
The common types of construction contracts are as follows:
i) Lump sum contract
ii) Cost plus contract
iii) Re-measured contracts based on schedule of quantities
iv) Management contracts
v) Negotiated contracts
vi) Selective tendering
vii) Serial tendering
viii) Design and Build Contract
The following standard Conditions of Contract used in a medium sized construction
project are:
i) New Zealand Standard (NZS) 3910: 1987 Conditions of Contract for Building and
Civil Engineering Construction (for contractors and engineers)
ii) NZS 3915:2005 Conditions of Contract for Building and Civil Engineering
Construction (Where No Person is Appointed to Act as Engineer to the Contract)
iii) FIDIC Conditions of Contract for Construction, Multilateral Development Bank
(MDB) Harmonised E (duties of the engineer, the role of the architect and the
engineer)
iv) The Joints Contract Tribunal (JCT) Conditions of Contract for Building Works,
used in UK
v) New Zealand Institute of Architects (NZIA) General Conditions of Contract
vi) Registered Master Builders’ Federation General Conditions of Contract
In 1st
April 2003 the Construction Contracts Act 2002 legislative requirements came into
effect “construction work’ allows i.e. process to be followed that ensures owners pay
main contractors on time and main contractors pay subcontractors on time and
subcontractors pay sub subcontractors (identify the contractual chain) relationship with
whom it is dealt and so on.
Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology
13/10/2009
4
CONS5Q25 Assignment 3 Praveen Premkumar as at 25th
August 2009
Student ID: 1213020
All theses types of contracts are based on particular conditions of contract. In NZ, the
standard conditions of contract is mainly we use NZS and SCC SF 2007 4th
edition
produced by architects. The contract document comprises of the drawings, schedule of
quantities (if available), specifications and conditions of contract. In practice, as
contractors we need a building consent and the design team when putting out a tender
will need to occupy a building consent. It is believed without a building consent a
company can be fined or even shutdown.
NZS 3910 is a document issued by New Zealand standards especially designed for
contract administration. This document is comprised with schedules, conditions of
tendering and conditions that assist the main contractors, subcontractors, architect (the
engineer) and the client. By listing a set of conditions that shows the responsibilities and
the contractual obligations of parties involved in the construction, is beneficial for the
proper construction, completion and maintenance of the project because it is clear for
everyone to identify their scope and commitment to the project. As the proposed building
is situated in downtown Auckland, the construction methodology and the excess
restriction become a challenge for the parties involved. As a result of this challenge, there
maybe disputes arising among the parties involved. On such occurrence, the ‘Conditions
of Contract’ illustrate various options to overcome the problem.
In the building industry, most of the construction works are being awarded to contractors
by the process of tendering to obtain a competitive price. In order, to make it fair and
reasonable to all those bidding for a particular tender, there are conditions listed in the
document NZS 3910, enabling them to understand the procedures in submitting a tender.
This is where there are ambiguities in the tender documents, the architect issues
explanatory notices to the bidders.
In the absence of such clarifications, the bidders may not be able to price the document.
These issues are addressed under ‘Conditions of Tendering’ for mutual benefits.
Submission of a tender is an offer for client’s acceptance, which will form a legal
contract. The procedure for submission, acceptation and notification are listed in the
document for the beneficial of all parties.
In the building industry, in a design and build contract the client enters into a contract
with a contractor in which the contractor undertakes the activity to both design and build
a building, within the parameter of the initial design proposed. The contract normally
includes sketch plans and outline specification. However, it can include the brief
(performance based contract). The following steps should be undertaken:
• Feasibility study
• Selection of Design & Build Contractor
• Sketch Plan
• Developed design upon agreement on price
Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology
13/10/2009
5
CONS5Q25 Assignment 3 Praveen Premkumar as at 25th
August 2009
Student ID: 1213020
• Construction drawings
• Construction phase
In relation to the above, the client also assembles team of advisors such as hiring project
manager to conduct process and brief, quantity surveyor for establishment of budget and
lawyer to propose contractual arrangements. Also thus it is important to call for proposals
by sending to short list capable design and build contractors. The responses should
include for statement of capability, sketch plan and pricing structure. The typical process
also mainly depends on the selection of preferred contractor, negotiations regarding
design and price, design and price finalised and contract signed and construction
drawings and construction take place i.e. certification of progress payments by project
manager or QS; certification variations and time extension in accordance with contract by
project manager; certification of practical completion etc. by project manager.
For cost plus job, the contractor gets to prepare and put price on what he prefers.
However, there is an uncertainty, which is a disqualification for this type of contract as
the anticipated final account may be unknown.
The lists of parties involved in a project are:
• Client
• Design team
• Builder
• Subcontractor
• Suppliers of goods and services, etc
•
These people will be required in various contracts to interact information between each
other prior to the project progressing. The background information of people is important
to us in the construction industry. The functional requirements between designer and
client have been identified.
Moreover the above types of contract and the Conditions of Contract suit the type of
construction, which will be more desirable and appropriate for the selection of
construction. Nevertheless, in tradition it is the advisor to the client who will propose the
contract type and the conditions more relevant to the type of construction.
Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology
13/10/2009
6

More Related Content

What's hot

Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract managementVISHAKA BOTHRA
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 

What's hot (20)

Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
contract management, stages of contract management
 contract management, stages of contract management contract management, stages of contract management
contract management, stages of contract management
 
Construction contract
Construction contract Construction contract
Construction contract
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Contract
Contract Contract
Contract
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 

Viewers also liked

Construction contract
Construction contractConstruction contract
Construction contractAqsa Shafique
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Types of construction
Types of constructionTypes of construction
Types of constructionPralhad Kore
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 
Types of construction
Types of constructionTypes of construction
Types of constructionvigyanashram
 
A contract is a legally binding agreement or relationship that exists between...
A contract is a legally binding agreement or relationship that exists between...A contract is a legally binding agreement or relationship that exists between...
A contract is a legally binding agreement or relationship that exists between...chelliah selvavishnu
 
Types of contract
Types of contractTypes of contract
Types of contractSweetp999
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011photomatt
 

Viewers also liked (14)

Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Types of construction
Types of constructionTypes of construction
Types of construction
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Contracts
ContractsContracts
Contracts
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Types of conract
Types of conractTypes of conract
Types of conract
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Types of construction
Types of constructionTypes of construction
Types of construction
 
A contract is a legally binding agreement or relationship that exists between...
A contract is a legally binding agreement or relationship that exists between...A contract is a legally binding agreement or relationship that exists between...
A contract is a legally binding agreement or relationship that exists between...
 
Types of contract
Types of contractTypes of contract
Types of contract
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 

Similar to 3.0 Common Types of Construction Contracts & Standard Conditions of Contract Est1 Sem2 '09

contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.pptssuser32da691
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03ypinada
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver bookmoodlyd
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1reddvise
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 

Similar to 3.0 Common Types of Construction Contracts & Standard Conditions of Contract Est1 Sem2 '09 (20)

contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver book
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
2.12 procurement management 1
2.12  procurement management 12.12  procurement management 1
2.12 procurement management 1
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Matrix207
Matrix207Matrix207
Matrix207
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 

3.0 Common Types of Construction Contracts & Standard Conditions of Contract Est1 Sem2 '09

  • 1. CONS5Q25 Assignment 3 Praveen Premkumar as at 25th August 2009 Student ID: 1213020 2.0Common Types of Construction Contracts and Standard Conditions of Contract The common type of procurement option of construction contract in the building industry is mainly lump sum contracts. It is described that procurement is a generic term used to “getting” building. (C. Prigg, personal communication, July 28, 2009) The common types of construction contracts are as follows: i) Lump sum contract ii) Cost plus contract iii) Re-measured contracts based on schedule of quantities iv) Management contracts v) Negotiated contracts vi) Selective tendering vii) Serial tendering viii) Design and Build Contract The following standard Conditions of Contract used in a medium sized construction project are: i) New Zealand Standard (NZS) 3910: 1987 Conditions of Contract for Building and Civil Engineering Construction (for contractors and engineers) ii) NZS 3915:2005 Conditions of Contract for Building and Civil Engineering Construction (Where No Person is Appointed to Act as Engineer to the Contract) iii) FIDIC Conditions of Contract for Construction, Multilateral Development Bank (MDB) Harmonised E (duties of the engineer, the role of the architect and the engineer) iv) The Joints Contract Tribunal (JCT) Conditions of Contract for Building Works, used in UK v) New Zealand Institute of Architects (NZIA) General Conditions of Contract vi) Registered Master Builders’ Federation General Conditions of Contract In 1st April 2003 the Construction Contracts Act 2002 legislative requirements came into effect “construction work’ allows i.e. process to be followed that ensures owners pay main contractors on time and main contractors pay subcontractors on time and subcontractors pay sub subcontractors (identify the contractual chain) relationship with whom it is dealt and so on. Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology 13/10/2009 4
  • 2. CONS5Q25 Assignment 3 Praveen Premkumar as at 25th August 2009 Student ID: 1213020 All theses types of contracts are based on particular conditions of contract. In NZ, the standard conditions of contract is mainly we use NZS and SCC SF 2007 4th edition produced by architects. The contract document comprises of the drawings, schedule of quantities (if available), specifications and conditions of contract. In practice, as contractors we need a building consent and the design team when putting out a tender will need to occupy a building consent. It is believed without a building consent a company can be fined or even shutdown. NZS 3910 is a document issued by New Zealand standards especially designed for contract administration. This document is comprised with schedules, conditions of tendering and conditions that assist the main contractors, subcontractors, architect (the engineer) and the client. By listing a set of conditions that shows the responsibilities and the contractual obligations of parties involved in the construction, is beneficial for the proper construction, completion and maintenance of the project because it is clear for everyone to identify their scope and commitment to the project. As the proposed building is situated in downtown Auckland, the construction methodology and the excess restriction become a challenge for the parties involved. As a result of this challenge, there maybe disputes arising among the parties involved. On such occurrence, the ‘Conditions of Contract’ illustrate various options to overcome the problem. In the building industry, most of the construction works are being awarded to contractors by the process of tendering to obtain a competitive price. In order, to make it fair and reasonable to all those bidding for a particular tender, there are conditions listed in the document NZS 3910, enabling them to understand the procedures in submitting a tender. This is where there are ambiguities in the tender documents, the architect issues explanatory notices to the bidders. In the absence of such clarifications, the bidders may not be able to price the document. These issues are addressed under ‘Conditions of Tendering’ for mutual benefits. Submission of a tender is an offer for client’s acceptance, which will form a legal contract. The procedure for submission, acceptation and notification are listed in the document for the beneficial of all parties. In the building industry, in a design and build contract the client enters into a contract with a contractor in which the contractor undertakes the activity to both design and build a building, within the parameter of the initial design proposed. The contract normally includes sketch plans and outline specification. However, it can include the brief (performance based contract). The following steps should be undertaken: • Feasibility study • Selection of Design & Build Contractor • Sketch Plan • Developed design upon agreement on price Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology 13/10/2009 5
  • 3. CONS5Q25 Assignment 3 Praveen Premkumar as at 25th August 2009 Student ID: 1213020 • Construction drawings • Construction phase In relation to the above, the client also assembles team of advisors such as hiring project manager to conduct process and brief, quantity surveyor for establishment of budget and lawyer to propose contractual arrangements. Also thus it is important to call for proposals by sending to short list capable design and build contractors. The responses should include for statement of capability, sketch plan and pricing structure. The typical process also mainly depends on the selection of preferred contractor, negotiations regarding design and price, design and price finalised and contract signed and construction drawings and construction take place i.e. certification of progress payments by project manager or QS; certification variations and time extension in accordance with contract by project manager; certification of practical completion etc. by project manager. For cost plus job, the contractor gets to prepare and put price on what he prefers. However, there is an uncertainty, which is a disqualification for this type of contract as the anticipated final account may be unknown. The lists of parties involved in a project are: • Client • Design team • Builder • Subcontractor • Suppliers of goods and services, etc • These people will be required in various contracts to interact information between each other prior to the project progressing. The background information of people is important to us in the construction industry. The functional requirements between designer and client have been identified. Moreover the above types of contract and the Conditions of Contract suit the type of construction, which will be more desirable and appropriate for the selection of construction. Nevertheless, in tradition it is the advisor to the client who will propose the contract type and the conditions more relevant to the type of construction. Est1 Assignment Pt.3 2-2009.xls C: UNITEC Institute of Technology 13/10/2009 6