1) Increased loading of existing grid assets is possible through end-of-pipe solutions to gain 15% efficiency, tailor-made solutions for bottlenecks, reassessing continuous load capabilities, and additional dynamic and cyclic load tests. 2) Thermal limits of equipment must be considered, as time constants for cooling are on the scale of seconds to hours and hot spots are crucial at high currents. 3) Metering and protection equipment can be impacted by temporary overloads if current and thermal limits are exceeded, which could cause measuring errors, compliance issues, and protection relay operation.