SlideShare a Scribd company logo
1 of 48
Download to read offline
By: Chandan Kumar, Deputy Manager
ERLDC,POSOCO
Power System Stability Issues and
Remedial Action
“Electricity is really just organized lightning”
-George Carlin
“When the laws of Economics and Physics collide, Physics always wins”
-George C. Loehr
Power System Reliability
Reliability
SecurityAdequacy
• Adequacy relates to the existence of sufficient facilities within the system to satisfy the consumer load
demand at all times.
• Security relates to the ability to withstand sudden disturbances
Reliability of a power system refers to the probability of its satisfactory operation over the long run. It denotes the
ability to supply adequate electric service on a nearly continuous basis, with few interruptions over an extended time
period
- IEEE Paper on Terms & Definitions, 2004
11-Jan-19 ERLDC, POSOCO 3
Power System Reliability
The North American Electric Reliability Corporation (NERC) defines two components of
system reliability:
• Adequacy – Having sufficient resources to provide customers with a continuous supply
of electricity at the proper voltage and frequency, virtually all of the time. “Resources”
refers to a combination of electricity generating and transmission facilities, which
produce and deliver electricity; and “demand-response” programs, which reduce
customer demand for electricity.
• Security – The ability of the bulk power system to withstand sudden, unexpected
disturbances such as short circuits, or unanticipated loss of system elements due to
natural or man-made causes.
Power system is operated in a reliable and secure manner so that system stability
is not endangered.
Contd….
11-Jan-19 ERLDC, POSOCO 4
Power System Stability
Angle stability Voltage stability
Small signal stability Transient stability Large disturbance Small disturbance
Mid term Long term
Study period up to
10 secs
Study period up to
several minutes
Study period up to
tens of minutes
Power System Stability
Frequency stability
11-Jan-19 ERLDC, POSOCO 5
• Maintaining Frequency Closer to Nominal Frequency (50 Hz)
1. Frequency Stability
50 Hz
Generation Load
11-Jan-19 ERLDC, POSOCO 6
 To arrest change in frequency, control actions are required
 Frequency Control can be divided into three overlapping windows of time
 Primary Frequency Control
 Control provided by Interconnection
 Secondary Frequency Control (AGC)
 Control provided by individual control area
 Tertiary Frequency Control
 Control provided by individual control area in coordination with other control areas
Frequency Control
11-Jan-19 ERLDC, POSOCO 7
Frequency Control Actions
df/dt,
UFLS/SP
S
Depletion of Network/Tripping
AGC
Generator
Governor
System
Operator
Power System
Emergency
Control/
Defensive
Mechanism
𝑑𝑓
𝑑𝑡
𝑓
∆𝑝
∆𝑓
∆𝑓
𝑈𝑠𝑒𝑐
𝑈 𝑝𝑟𝑖
𝑈𝑓
Demand side controlGeneration side control
∆𝑝 + 𝒌∆𝑓
𝐴𝐶𝐸
∆𝑝
Source: Royal Institute,KTH, EMS
11-Jan-19 ERLDC, POSOCO 8
• Keeping Adequate Synchronizing and Damping Torque in system to
reach new equilibrium point after any small/Large disturbance.
• Lack of Synchronizing Torque : The disturbance on the system is quite severe
and sudden and the machine is unable to maintain synchronism under the
impact of this disturbance.
• Lack of Damping Torque : For inadequate amount of damping torque, the
rotor angle undergoes oscillations with increasing amplitude.
2. Angular Stability
11-Jan-19 ERLDC, POSOCO 9
11-Jan-19 ERLDC, POSOCO 10
Source : https://nptel.ac.in/courses/108107028/module6/lecture1/lecture1.pdf
• Delayed Fault Clearance Near to CGPL
Power Plant.
• Tc > Critical Clearing Time for CGPL Units
• Generator not able to Push Active power
to System due to Fault and over
speed/accelerate
• Leading to pole slip and out of step
protection operation.
• Centre of swing lies in CGPL causing
instability.
• All Outgoing lines tripped on Power
Swing Protection.
Lack of Synchronizing Torque : Pole Slip/Out of Step
11-Jan-19 ERLDC, POSOCO 11
Fig: CGPL Voltage from Simulation
11-Jan-19 ERLDC, POSOCO 12
• Ensuring adequate number of lines for full evacuation of power.
• Ensuring Angular separation between adjacent nodes are within limit.
• Checking Stability under various criteria through simulation.
• Using Fast Acting System protection Scheme to reduce the
accelerating power available in the system to maintain
synchronization.
• Finding Critical clearing time (tc) for various operating scenario and
having suitable remedial scheme.
• Improving voltage profile by dynamic Reactive support under large
disturbance.
• Reducing Angular difference in case of contingencies by reducing load/
generation.
Remedial Action
11-Jan-19 ERLDC, POSOCO 13
Lack of Damping Torque : Low Frequency Oscillation
11-Jan-19 ERLDC, POSOCO 14
• Ensuring adequate number of lines for full evacuation of power.
• Ensuring Angular separation between adjacent nodes are within
limit.
• PSS to be properly tuned and verified with tests.
• Using Fast Acting System protection Scheme to reduce
generation and grid stress.
• Tuning of HVDC/FACTS Power Oscillation Damping (POD)
Controller.
Remedial Action
11-Jan-19 ERLDC, POSOCO 15
• Maintain steady acceptable voltages at all buses in the system
• System enters a state of voltage instability during a disturbance
or increase in load demand
• Reason : Inability of a power system to meet the demand for
reactive power.
• Remedial Action :
• Ensure Voltage Stability study for Load rich areas
• Adequate Reactive Support Margin availability
• Ensuring N-1 and N-1-1 Reliability criteria
• Implement UVLS Scheme
3. Voltage Stability
11-Jan-19 ERLDC, POSOCO 16
11-Jan-19 ERLDC, POSOCO 17
• Voltage Collapse at Agartala due
to loss of reactive Support from
400 kV System.
• Voltage dependent load got
stalled in Tripura Power System
and Bangladesh (North Camila)
Voltage Dip During Fault And FIDVR
• Induction Motor : Power Requirement depend on Frequency and Voltage.
• Air conditioning Load and Industrial Motor Load : Either Stall (In absence or protection) or Trip
(Thermal/Under Voltage/LVRT Protection) during voltage dip
• They will start quickly after Stall and trip and draws huge reactive power.
• Fault induced Load Loss (FILL) : A Major Portion of Load Can trip or Stall during fault and come
back slowly after fault clearance
• If the LVRT protection is not there and large amount of load stall under fault : After fault
clearance, it requires large reactive power from the system to run (Its Induction Motor)
• Fault Induced Delayed Voltage Recovery (FIDVR) : Large reactive power is drawn, Voltage
remains low for large duration and additional load trip specially which have LVRT.
11-Jan-19 ERLDC, POSOCO 18
 3 Phase Symmetrical 220 kV Bus Fault near Industrial Load
Centres In Maharashtra.
 Delayed Fault clearance (Voltage Reduced by 50 %)
 Around 1000 MW load was lost.
 No report of loss in terms of lines/ICT tripping at
distribution/transmission level.
 Key Learning :
• No Tripping is observed yet frequency increased
indicating large quantum of load loss.
• Load Loss can occur when fault is severe and delayed
clearance is there. (Not FIDVR Case)
• Surprise for System Operator.
Case Study 1 : Padghe Event
Voltage
Demand and
Frequency
11-Jan-19 ERLDC, POSOCO 19
• Summer Season : High Concentration of Air
condition load in Delhi and nearby area.
• Phase to Phase Fault on 400 kV Transmission
line near Delhi and delayed fault clearance.
• Fault clearance is delayed.
• 3700 MW load was lost based on SCADA and
PMU data. High Shoot up in frequency.
• No report of loss in terms of lines/ICT tripping
at distribution level.
• Slow Voltage recovery and FIDVR Characteristic
Observed.
Case Study 2 : 400 kV Bawana – Mundka - II tripping event (FIDVR)
Voltage
11-Jan-19 ERLDC, POSOCO 20
Angular Separation in Grid and frequency
Increased Drastically
Northern Region Demand Reduced by Large
Quantum
11-Jan-19 ERLDC, POSOCO 21
FIDVR or Severe Fault Causing Load Loss becoming frequent and act as a challenge for System
Operator.
Characteristic of Such Events
• Any phase to phase or three phase of fault at 220 kV and above level near to load centers :
• Severe nature
• Cause load loss due to tripping of induction motor load on overcurrent/under voltage protection.
• Delayed fault clearance makes it more severe as causes more load loss.
• FIDVR event
• Occur during the summer season when load are majorly of single phase AC units’ load.
• Occur during severe fault near to the load centers along with its delayed clearance from the system.
• Followed by a sharp rise in frequency due to load loss and quick recovery with 5-20 minutes.
11-Jan-19 ERLDC, POSOCO 22
• Treatment of Distorted Voltage : Erroneous Frequency Calculation can result in
Tripping of the Inverter (Solar Plant)
• Wind Related LVRT protection setting for DFIG based Turbine having crowbar
arrangement : Limitation with How many times LVRT will operate within a
duration of time.
• Protection Coordination and Islanding
Some Key Issues with Renewable & Inverters
11-Jan-19 ERLDC, POSOCO 23
Thanks 
chandan@posoco.in
11-Jan-19 ERLDC, POSOCO 24
Defense Mechanism
11-Jan-19 ERLDC, POSOCO 25
1. Operational States of the Grid
Normal
• Equality Constraint : Load+Loss=Generation
• Inequality Constraint : All Parameters within Safe limit
11-Jan-19 ERLDC, POSOCO 26
• Normal state :All system variables are within the normal operating range
• Alert state : Security level falls below a certain limit of adequacy because of a
Event
• Emergency state : Severe disturbance
• In Extremis : Cascading outages
• Restorative state
1. Operational States of the Grid
11-Jan-19 ERLDC, POSOCO 27
• Ultimate Objective is to not reach the IN EXTREMIS State of Operation.
• Each Level having its own defense mechanism for returning back to previous state.
• Normal state :
• Operational Standards : CEA Standard and IEGC
• Operational Ranges for System Parameters : CEA Standard and IEGC
• Operational Criteria : IEGC and Operational Procedure
• Alert state :
• Primary , Secondary and Tertiary Control
• Automatic Control from FACTS/HVDC devices
• Load Generation Redispatch
• Manual Load Shedding and Generation Revival
• Under Voltage Load Shedding Scheme
1. Operational States of the Grid
11-Jan-19 ERLDC, POSOCO 28
• Emergency State
• System Protection Scheme
• Load Trimming Scheme
• Generation Reduction Scheme
• In Extremis
• Under Frequency Load Shedding Scheme
• ROCOF based Load Shedding Scheme
• Islanding Scheme
• Unintended System Separation
• Restorative state
• Black Start and Island Synchronization
2. Operational States of the Grid
11-Jan-19 ERLDC, POSOCO 29
2. Need of Defense Mechanism
Power System Operate with following Contingencies in Real Time:
• N : No Element is Out
• N-1: One Important element is Out
• N-1-1 : One element is out followed by other element
• N-K: Multiple elements are out
Real Time Operators ensure that there is no additional insecure operation
after these outages/contingencies. All Electrical Parameters are within their
prescribed band.
11-Jan-19 ERLDC, POSOCO 30
However, System Can go from N state to
N-K with Events/Contingencies
That’s why there is a need of Defense Mechanism
2. Need of Defense Mechanism
11-Jan-19 ERLDC, POSOCO 31
3. Defense Mechanism and Types
• Need of Some Mechanism to recover the system back to Normal State of Operation.
• Mechanism placed in Grid for Recovering System from Alert/Emergency/ In Extremis
State are called Defense Mechanism for Power System.
• Automated Mechanism
• Quick recovery (Response Time is in millisecond to few seconds)
• Fast, Logic Based, Measurement Based, Reliable.
• Action can be Local or Global depending on design.
• Act as last line of defense before system go for blackout or cascaded tripping.
11-Jan-19 ERLDC, POSOCO 32
Defense Mechanism Can be Classified as :
• Based on Type of Action : Generation, Load, HVDC Set Point, FACTS.
• Based on Area of Action : Local and Global
• Based on Parameter : Frequency Based, Voltage Based, Current Based, Active
and Reactive Flow Based
• Based on Time : Instantaneous, Time delayed
3. Defense Mechanism and Types
11-Jan-19 ERLDC, POSOCO 33
3.Defense Mechanism in Indian Power System
• Dynamic Control of HVDC/FACTS, PSS Of Generators
• System Protection Scheme (SPS)
• Automated Under Voltage Load Shedding (AUVLS)
• ICT Load trimming Scheme (LTS)
• Automated Under Frequency load Shedding (AUFLS) and ROCOF based Load
Shedding
• Islanding Scheme
11-Jan-19 ERLDC, POSOCO 34
4.a. Dynamic Control of HVDC/FACTS, PSS Of Generators
• HVDC/FACTS are having dynamic control which depending of criteria provide
response to reduce the impact of event.
• Frequency Controller of HVDC
• Sub-synchronous Torsional Interaction(SSTI) Controller of HVDC
• Power Oscillation Damping (POD) of HVDC/FACTS
• Dynamic Reactive Support from SVC/STATCOM
11-Jan-19 ERLDC, POSOCO 35
4.a. Dynamic Control of HVDC/FACTS, PSS Of GeneratorsTalcher-KolarHVDCFrequencyController
11-Jan-19 ERLDC, POSOCO 36
4.a. Dynamic Control of HVDC/FACTS, PSS Of Generators
t/s
-5 0 5 10 15 20 25 30 35
P_LINE1 NA/MW
0
50
100
150
200
t/s
-5 0 5 10 15 20 25 30 35
POD_OUT_DX NA/PU
-0.0
0.2
0.4
t/s
-5 0 5 10 15 20 25 30 35
X_REF_MOM NA/PU
0.75
1.00
1.25
1.50
t/s
-5 0 5 10 15 20 25 30 35
XAPP_R R/PU
0.0
0.5
1.0
1.5
t/s
-5 0 5 10 15 20 25 30 35
XAPP_Y Y/PU
0.0
0.5
1.0
1.5
t/s
-5 0 5 10 15 20 25 30 35
XAPP_B B/PU
0.0
0.5
1.0
1.5
t/s
-5 0 5 10 15 20 25 30 35
P_SWING NA/MW
0
25
50
75
t/s
-5 0 5 10 15 20 25 30 35
ABS_P_SWING NA/MW
0
25
50
75
t/s
-5 0 5 10 15 20 25 30 35
AB
BP_STRAT_ON
POD_ON
POD_CBP
RaipurTCSCPODController
11-Jan-19 ERLDC, POSOCO 37
4.b. Automatic Under Voltage Load Shedding Scheme
• Power systems today are much more susceptible
to voltage collapses as increasingly depend on
generation sources that are located remotely from
load centers.
• UVLS relays are meant for shedding of load when
the voltage is going below the operational lower
limit in order to avoid voltage collapse.
• IEGC 5.2.t Mandates : All Users, CTU and STUs shall
provide adequate voltage control measures
through voltage relay as finalized by RPC, to
prevent voltage collapse. and shall ensure its
effective application to prevent voltage collapse/
cascade tripping.
11-Jan-19 ERLDC, POSOCO 38
Basic Design Criteria :
1. Designed to coordinate with protective devices and control schemes for momentary
voltage dips, sustained faults, low voltages caused by stalled air conditioners, etc.
2. The time delay should be in seconds, not in cycles
3. Must be on Bus VTs and coordinate with ICT/Lines Load Trimming Scheme.
4. Voltage pick-up points to set reasonably higher than the “nose point” P-V nose curve.
5. Enough load shed to bring voltages to minimum operating voltage levels or higher
Example Setting for UVLS
In case of two stage operation
• Alarm: If Voltage < 375 kV ; Stage 1: If Voltage < 372 kV for 5 sec; Stage 2: If Voltage < 370 kV for 10 Sec
In case of Single stage operation
• If Voltage < 370 kV for 5 seconds
4.b. Automatic Under Voltage Load Shedding Scheme
11-Jan-19 ERLDC, POSOCO 39
4.c. Load trimming Scheme (LTS)
• These are also SPS which are local in nature and has designated purpose of
saving elements getting overloaded due to contingencies.
• Implementation for Line and ICT to avoid overloading.
• Several Such LTS scheme are there in Various States across India.
• Their operation during contingencies helps in arresting the event
widespread.
• Basically Designed using Overcurrent Feature of the Relays with PLCC as
Communication Media.
• Need of Coordination between various LTS is very much necessary in an
interconnected system (One LTS Impacts Others): On two occasions
Kolhapur ICTs (3 Nos) and Karad ICTs (3 Nos) tripped One iCT tripping
even after the LTS operation due to Non-Coordination.
11-Jan-19 ERLDC, POSOCO 40
• Frequency should be within prescribed band of 49.9-50.05 Hz.
• However, Frequency will fall rapidly with System Islanding/Large
generation complex loss.
• AUFLS and ROCOF (df/dt) based automated load shedding are ways to
arrest gradual as well as fast fall in frequency in the system (Frequency fall
Arrester)
• ROCOF based relay arrest the fast fall in frequency while AUFLS will restrict the
frequency above a certain limit.
• AUFLS is global phenomenon and load shedding occurs as per design in the
complete synchronized grid While ROCOF based load shedding quantum caries
with nearness to Frequency related event source.
• Quantum of such Load connected with AUFLS and df/dt relay changes with system
size and connectivity.
4.d. AUFLS and ROCOF Relays for Load Shedding
11-Jan-19 ERLDC, POSOCO 41
Last AUFLS Operation :
Separation of NEW and SR Grid
on 24 May 2015 during High
import by Southern Region.
4.d. AUFLS and ROCOF Relays for Load Shedding
11-Jan-19 ERLDC, POSOCO 42
CGPL Event 12 March 2014
UMPP Loss Largest Contingency in the System
ROCOF Operated in Gujarat (636 MW) and
Maharashtra (334)
4.d. AUFLS and ROCOF Relays for Load Shedding
ROCOF Relay Operated.
11-Jan-19 ERLDC, POSOCO 43
49.9 Hz
ROCOF Relay operation in Gujarat on 18 Jan 2017
• Cause : Momentary Cessation of Full HVDC Mundra
Power Order of 2500 MW to Zero and Auto-Restart to
2500 MW in 10 ms interval causing Large swing in WR
and NR (See Frequency Plot)
• Root Cause : Simultaneous DC line Fault (Rare
Contingency)
• ROCOF operated in Gujarat System near Mundra : 486
MW load Loss
• PMU indicated ROCOF above 0.4 Hz/Sec (Highest Value
of ROCOF)
4.d. AUFLS and ROCOF Relays for Load Shedding
11-Jan-19 ERLDC, POSOCO 44
• When The system is moving towards in Extremis and Blackout , its desirable to
split system having load/generation balance in Island for faster restoration.
• It’s the Last Measure : Islanding should take place only when all other defense
plan have been allowed their full opportunity to bring back and maintain system
integrity and still the health of integrated system is on path of deteoriation
towards failure.
• Large Number of Islanding Scheme is Not Suitable for Integrated Grid.
• Operational frequency band for pre-islanding defense mechanism and islanding
frequency band sufficiently apart : Help in taking care of continued fall of
frequency during the interval between relay pick-up and breaker opening.
• IEGC 5.2.n
4.e. Islanding Scheme
11-Jan-19 ERLDC, POSOCO 45
• Islanding to Occur : When all other defense plan ( fault clearance, SPS action, UFLS and df/dt
load shedding etc.) have been allowed their final operational opportunity and the system is
still on the path of deterioration towards collapse.
• Islanding not to Occur : If there is still a chance that a distressed system can be brought back
to emergency condition (or alert condition or normal condition) with operation of the
mechanism planed for integrated and interconnected states of Grid.
• Frequency Band Setting for Islanding
• Devised for Part of system which have Load generation balance : Preserve those areas which
inherently are in a position to achieve load generation balance post islanding.
To be Reviewed after 2 Years
Ramakrishna Committee Recommendation
4.e. Islanding Scheme
11-Jan-19 ERLDC, POSOCO 46
• Generally Implemented for only those sub-parts of network :
• Connect to rest of grid in an electrically radial manner with only a few
interconnecting lines
• Have their own load generation balance to a large extent, requiring comparatively
smaller exchanges with rest of the grid.
• Features to be incorporated In Islanding Scheme
• Adequate automated mechanism for achieving load generation balance.
• Frequency control of islanded subsystem: Sufficient number/capacity of generating
units in on free governor mode of operation in the island.
• Load connection/disconnection should be possible remotely from the dispatch
centre of the islanded sub-system.
• Health of Monitoring System for all equipment in island System should be good.
4.e. Islanding Scheme
11-Jan-19 ERLDC, POSOCO 47
MumbaiIslandingScheme
TROMBAY 220 KV
TROMBAY 110 KV
SALSETTE 110 KV
KALYAN 110 KV
SALSETTE 220 KV
BORIVALI 110 KV
BORIVALI 220 KV
UFR - 47.9 Hz
RPUF – 48.0 Hz
RPUF - 47.9 Hz
UFR - 47.9 Hz
UFR - 47.9 Hz
RPUF - 47.7 Hz
47.9Hz RPUF - 47.9 Hz
UFR - 47.9 Hz
UFR - 47.6 Hz
AAREY
VERSOVA
DAHANU
UFR - 47.9 Hz
MSETCL
Tata Power
R-infra
UFR - 47.9 Hz
GHODBUNDER
TROMBAY
KALWA
BORIVLI
BOISAR
BORIVLI
UFR - 47.9 Hz
UFR - 47.9 Hz
UFR - 47.9 Hz
4.e. Islanding Scheme
11-Jan-19 ERLDC, POSOCO 48

More Related Content

What's hot

Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties ahmedgoun
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNINGNishaDangi99
 
Static excitation-system
Static excitation-systemStatic excitation-system
Static excitation-systemDeepak Jha
 
Reactive power and voltage control
Reactive power and voltage controlReactive power and voltage control
Reactive power and voltage controlSourabh sharma
 
Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy Chandan Kumar
 
Smart grid problems in general
Smart grid problems in generalSmart grid problems in general
Smart grid problems in generalAimal Achakzai
 
Exp 8 (1)8. Load-frequency dynamics of single area power system
Exp 8 (1)8.	Load-frequency dynamics of single area power systemExp 8 (1)8.	Load-frequency dynamics of single area power system
Exp 8 (1)8. Load-frequency dynamics of single area power systemShweta Yadav
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power systemsneh pratap singh
 
Transmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsTransmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsWriteKraft Dissertations
 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis proceduresrini09
 
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)Rohit vijay
 

What's hot (20)

Generator protection
Generator protectionGenerator protection
Generator protection
 
Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
POWER SYSTEM PLANNING
POWER SYSTEM PLANNINGPOWER SYSTEM PLANNING
POWER SYSTEM PLANNING
 
Reactive power management in india
Reactive power  management in indiaReactive power  management in india
Reactive power management in india
 
Harmonics
HarmonicsHarmonics
Harmonics
 
Earthing system
Earthing system   Earthing system
Earthing system
 
Static excitation-system
Static excitation-systemStatic excitation-system
Static excitation-system
 
Reactive power and voltage control
Reactive power and voltage controlReactive power and voltage control
Reactive power and voltage control
 
Reactive power management
Reactive power managementReactive power management
Reactive power management
 
Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy Grid Restoration Challneges and Strategy
Grid Restoration Challneges and Strategy
 
Procedure cable testing
Procedure cable testingProcedure cable testing
Procedure cable testing
 
Smart grid problems in general
Smart grid problems in generalSmart grid problems in general
Smart grid problems in general
 
Exp 8 (1)8. Load-frequency dynamics of single area power system
Exp 8 (1)8.	Load-frequency dynamics of single area power systemExp 8 (1)8.	Load-frequency dynamics of single area power system
Exp 8 (1)8. Load-frequency dynamics of single area power system
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
6.05 _dimensionamento
6.05  _dimensionamento6.05  _dimensionamento
6.05 _dimensionamento
 
Transmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operationsTransmission congestion management in deregulated power system operations
Transmission congestion management in deregulated power system operations
 
Petersen coil
Petersen coilPetersen coil
Petersen coil
 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis procedure
 
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
POWER QUALITY ISSUES (POWER SYSTEM AND POWER ELECTRONICS)
 

Similar to Power system stability issues and Defence Mechanism in Indian Grid

Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability IssuesChandan Kumar
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemChandan Kumar
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...theijes
 
ppt nrel.pptx
ppt  nrel.pptxppt  nrel.pptx
ppt nrel.pptxgulie
 
Island Detection and Control Techniques
Island Detection and Control Techniques Island Detection and Control Techniques
Island Detection and Control Techniques Tanveer Riaz
 
tanveerppt-170427091913.pdf
tanveerppt-170427091913.pdftanveerppt-170427091913.pdf
tanveerppt-170427091913.pdfgulie
 
Smart Power Grid Monitoring System
Smart Power Grid Monitoring SystemSmart Power Grid Monitoring System
Smart Power Grid Monitoring SystemImane Haf
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarBhushan Kumbhalkar
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...IRJET Journal
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfPowerSystemDynamicsS
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. katoAgrey Kato
 
windfarmgridissues.pdf
windfarmgridissues.pdfwindfarmgridissues.pdf
windfarmgridissues.pdfsundeepsiddula
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issuesRohil Kumar
 
Power quality improvement techniques
Power quality improvement techniquesPower quality improvement techniques
Power quality improvement techniquessahid raja khan
 
Interconnection power system
Interconnection power systemInterconnection power system
Interconnection power systemNovia Putri
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Presentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfPresentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfHASSAN527910
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET Journal
 
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSLOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSEditor IJMTER
 

Similar to Power system stability issues and Defence Mechanism in Indian Grid (20)

Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability Issues
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power System
 
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
Fault Ride-Through of DFIG Wind Turbine by DVR Using Synchronous Reference Fr...
 
ppt nrel.pptx
ppt  nrel.pptxppt  nrel.pptx
ppt nrel.pptx
 
Island Detection and Control Techniques
Island Detection and Control Techniques Island Detection and Control Techniques
Island Detection and Control Techniques
 
tanveerppt-170427091913.pdf
tanveerppt-170427091913.pdftanveerppt-170427091913.pdf
tanveerppt-170427091913.pdf
 
Smart Power Grid Monitoring System
Smart Power Grid Monitoring SystemSmart Power Grid Monitoring System
Smart Power Grid Monitoring System
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkar
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. kato
 
windfarmgridissues.pdf
windfarmgridissues.pdfwindfarmgridissues.pdf
windfarmgridissues.pdf
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issues
 
Power quality improvement techniques
Power quality improvement techniquesPower quality improvement techniques
Power quality improvement techniques
 
Interconnection power system
Interconnection power systemInterconnection power system
Interconnection power system
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Presentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdfPresentation-on-NPCC-by-Salman-Gul_4.pdf
Presentation-on-NPCC-by-Salman-Gul_4.pdf
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
 
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMSLOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
LOW VOLTAGE RIDE - THROUGH CAPABILITY OF WIND FARMS
 

More from Chandan Kumar

Substation and It's Equipment
Substation and It's Equipment Substation and It's Equipment
Substation and It's Equipment Chandan Kumar
 
Challenges and Best Practices : Indian Grid Management
Challenges and Best Practices : Indian Grid Management Challenges and Best Practices : Indian Grid Management
Challenges and Best Practices : Indian Grid Management Chandan Kumar
 
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...Chandan Kumar
 
Selection of Reference Node and Angular Baselining using Synchrophasors Meas...
Selection of Reference Node and Angular  Baselining using Synchrophasors Meas...Selection of Reference Node and Angular  Baselining using Synchrophasors Meas...
Selection of Reference Node and Angular Baselining using Synchrophasors Meas...Chandan Kumar
 
Comparison of analytical methods of analysing linear induction motors
Comparison of analytical methods of analysing linear induction motors Comparison of analytical methods of analysing linear induction motors
Comparison of analytical methods of analysing linear induction motors Chandan Kumar
 
WAMS Analytical Approach
WAMS Analytical Approach WAMS Analytical Approach
WAMS Analytical Approach Chandan Kumar
 
Smart grid- Indian Perspective
Smart grid- Indian PerspectiveSmart grid- Indian Perspective
Smart grid- Indian PerspectiveChandan Kumar
 
Short Term Open Access in inter state transmission
Short Term Open Access in inter state transmissionShort Term Open Access in inter state transmission
Short Term Open Access in inter state transmissionChandan Kumar
 
‌Intergration of wind farms in indian transmission system
‌Intergration of wind farms in indian transmission system‌Intergration of wind farms in indian transmission system
‌Intergration of wind farms in indian transmission systemChandan Kumar
 
Hybrid energy system ,ge edison challenege 2009
Hybrid energy system ,ge edison challenege 2009Hybrid energy system ,ge edison challenege 2009
Hybrid energy system ,ge edison challenege 2009Chandan Kumar
 
Analysis of space charge controlled electric field 1
Analysis of space charge controlled electric field 1Analysis of space charge controlled electric field 1
Analysis of space charge controlled electric field 1Chandan Kumar
 
Static test study on linear induction motor iccee
Static test study on linear induction motor icceeStatic test study on linear induction motor iccee
Static test study on linear induction motor icceeChandan Kumar
 
Major blackout in the world
Major blackout in the worldMajor blackout in the world
Major blackout in the worldChandan Kumar
 

More from Chandan Kumar (13)

Substation and It's Equipment
Substation and It's Equipment Substation and It's Equipment
Substation and It's Equipment
 
Challenges and Best Practices : Indian Grid Management
Challenges and Best Practices : Indian Grid Management Challenges and Best Practices : Indian Grid Management
Challenges and Best Practices : Indian Grid Management
 
Utilization of Synchrophasors during Synchronization and Operation of Large ...
Utilization of Synchrophasors during  Synchronization and Operation of Large ...Utilization of Synchrophasors during  Synchronization and Operation of Large ...
Utilization of Synchrophasors during Synchronization and Operation of Large ...
 
Selection of Reference Node and Angular Baselining using Synchrophasors Meas...
Selection of Reference Node and Angular  Baselining using Synchrophasors Meas...Selection of Reference Node and Angular  Baselining using Synchrophasors Meas...
Selection of Reference Node and Angular Baselining using Synchrophasors Meas...
 
Comparison of analytical methods of analysing linear induction motors
Comparison of analytical methods of analysing linear induction motors Comparison of analytical methods of analysing linear induction motors
Comparison of analytical methods of analysing linear induction motors
 
WAMS Analytical Approach
WAMS Analytical Approach WAMS Analytical Approach
WAMS Analytical Approach
 
Smart grid- Indian Perspective
Smart grid- Indian PerspectiveSmart grid- Indian Perspective
Smart grid- Indian Perspective
 
Short Term Open Access in inter state transmission
Short Term Open Access in inter state transmissionShort Term Open Access in inter state transmission
Short Term Open Access in inter state transmission
 
‌Intergration of wind farms in indian transmission system
‌Intergration of wind farms in indian transmission system‌Intergration of wind farms in indian transmission system
‌Intergration of wind farms in indian transmission system
 
Hybrid energy system ,ge edison challenege 2009
Hybrid energy system ,ge edison challenege 2009Hybrid energy system ,ge edison challenege 2009
Hybrid energy system ,ge edison challenege 2009
 
Analysis of space charge controlled electric field 1
Analysis of space charge controlled electric field 1Analysis of space charge controlled electric field 1
Analysis of space charge controlled electric field 1
 
Static test study on linear induction motor iccee
Static test study on linear induction motor icceeStatic test study on linear induction motor iccee
Static test study on linear induction motor iccee
 
Major blackout in the world
Major blackout in the worldMajor blackout in the world
Major blackout in the world
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 

Power system stability issues and Defence Mechanism in Indian Grid

  • 1. By: Chandan Kumar, Deputy Manager ERLDC,POSOCO Power System Stability Issues and Remedial Action
  • 2. “Electricity is really just organized lightning” -George Carlin “When the laws of Economics and Physics collide, Physics always wins” -George C. Loehr
  • 3. Power System Reliability Reliability SecurityAdequacy • Adequacy relates to the existence of sufficient facilities within the system to satisfy the consumer load demand at all times. • Security relates to the ability to withstand sudden disturbances Reliability of a power system refers to the probability of its satisfactory operation over the long run. It denotes the ability to supply adequate electric service on a nearly continuous basis, with few interruptions over an extended time period - IEEE Paper on Terms & Definitions, 2004 11-Jan-19 ERLDC, POSOCO 3
  • 4. Power System Reliability The North American Electric Reliability Corporation (NERC) defines two components of system reliability: • Adequacy – Having sufficient resources to provide customers with a continuous supply of electricity at the proper voltage and frequency, virtually all of the time. “Resources” refers to a combination of electricity generating and transmission facilities, which produce and deliver electricity; and “demand-response” programs, which reduce customer demand for electricity. • Security – The ability of the bulk power system to withstand sudden, unexpected disturbances such as short circuits, or unanticipated loss of system elements due to natural or man-made causes. Power system is operated in a reliable and secure manner so that system stability is not endangered. Contd…. 11-Jan-19 ERLDC, POSOCO 4
  • 5. Power System Stability Angle stability Voltage stability Small signal stability Transient stability Large disturbance Small disturbance Mid term Long term Study period up to 10 secs Study period up to several minutes Study period up to tens of minutes Power System Stability Frequency stability 11-Jan-19 ERLDC, POSOCO 5
  • 6. • Maintaining Frequency Closer to Nominal Frequency (50 Hz) 1. Frequency Stability 50 Hz Generation Load 11-Jan-19 ERLDC, POSOCO 6
  • 7.  To arrest change in frequency, control actions are required  Frequency Control can be divided into three overlapping windows of time  Primary Frequency Control  Control provided by Interconnection  Secondary Frequency Control (AGC)  Control provided by individual control area  Tertiary Frequency Control  Control provided by individual control area in coordination with other control areas Frequency Control 11-Jan-19 ERLDC, POSOCO 7
  • 8. Frequency Control Actions df/dt, UFLS/SP S Depletion of Network/Tripping AGC Generator Governor System Operator Power System Emergency Control/ Defensive Mechanism 𝑑𝑓 𝑑𝑡 𝑓 ∆𝑝 ∆𝑓 ∆𝑓 𝑈𝑠𝑒𝑐 𝑈 𝑝𝑟𝑖 𝑈𝑓 Demand side controlGeneration side control ∆𝑝 + 𝒌∆𝑓 𝐴𝐶𝐸 ∆𝑝 Source: Royal Institute,KTH, EMS 11-Jan-19 ERLDC, POSOCO 8
  • 9. • Keeping Adequate Synchronizing and Damping Torque in system to reach new equilibrium point after any small/Large disturbance. • Lack of Synchronizing Torque : The disturbance on the system is quite severe and sudden and the machine is unable to maintain synchronism under the impact of this disturbance. • Lack of Damping Torque : For inadequate amount of damping torque, the rotor angle undergoes oscillations with increasing amplitude. 2. Angular Stability 11-Jan-19 ERLDC, POSOCO 9
  • 10. 11-Jan-19 ERLDC, POSOCO 10 Source : https://nptel.ac.in/courses/108107028/module6/lecture1/lecture1.pdf
  • 11. • Delayed Fault Clearance Near to CGPL Power Plant. • Tc > Critical Clearing Time for CGPL Units • Generator not able to Push Active power to System due to Fault and over speed/accelerate • Leading to pole slip and out of step protection operation. • Centre of swing lies in CGPL causing instability. • All Outgoing lines tripped on Power Swing Protection. Lack of Synchronizing Torque : Pole Slip/Out of Step 11-Jan-19 ERLDC, POSOCO 11
  • 12. Fig: CGPL Voltage from Simulation 11-Jan-19 ERLDC, POSOCO 12
  • 13. • Ensuring adequate number of lines for full evacuation of power. • Ensuring Angular separation between adjacent nodes are within limit. • Checking Stability under various criteria through simulation. • Using Fast Acting System protection Scheme to reduce the accelerating power available in the system to maintain synchronization. • Finding Critical clearing time (tc) for various operating scenario and having suitable remedial scheme. • Improving voltage profile by dynamic Reactive support under large disturbance. • Reducing Angular difference in case of contingencies by reducing load/ generation. Remedial Action 11-Jan-19 ERLDC, POSOCO 13
  • 14. Lack of Damping Torque : Low Frequency Oscillation 11-Jan-19 ERLDC, POSOCO 14
  • 15. • Ensuring adequate number of lines for full evacuation of power. • Ensuring Angular separation between adjacent nodes are within limit. • PSS to be properly tuned and verified with tests. • Using Fast Acting System protection Scheme to reduce generation and grid stress. • Tuning of HVDC/FACTS Power Oscillation Damping (POD) Controller. Remedial Action 11-Jan-19 ERLDC, POSOCO 15
  • 16. • Maintain steady acceptable voltages at all buses in the system • System enters a state of voltage instability during a disturbance or increase in load demand • Reason : Inability of a power system to meet the demand for reactive power. • Remedial Action : • Ensure Voltage Stability study for Load rich areas • Adequate Reactive Support Margin availability • Ensuring N-1 and N-1-1 Reliability criteria • Implement UVLS Scheme 3. Voltage Stability 11-Jan-19 ERLDC, POSOCO 16
  • 17. 11-Jan-19 ERLDC, POSOCO 17 • Voltage Collapse at Agartala due to loss of reactive Support from 400 kV System. • Voltage dependent load got stalled in Tripura Power System and Bangladesh (North Camila)
  • 18. Voltage Dip During Fault And FIDVR • Induction Motor : Power Requirement depend on Frequency and Voltage. • Air conditioning Load and Industrial Motor Load : Either Stall (In absence or protection) or Trip (Thermal/Under Voltage/LVRT Protection) during voltage dip • They will start quickly after Stall and trip and draws huge reactive power. • Fault induced Load Loss (FILL) : A Major Portion of Load Can trip or Stall during fault and come back slowly after fault clearance • If the LVRT protection is not there and large amount of load stall under fault : After fault clearance, it requires large reactive power from the system to run (Its Induction Motor) • Fault Induced Delayed Voltage Recovery (FIDVR) : Large reactive power is drawn, Voltage remains low for large duration and additional load trip specially which have LVRT. 11-Jan-19 ERLDC, POSOCO 18
  • 19.  3 Phase Symmetrical 220 kV Bus Fault near Industrial Load Centres In Maharashtra.  Delayed Fault clearance (Voltage Reduced by 50 %)  Around 1000 MW load was lost.  No report of loss in terms of lines/ICT tripping at distribution/transmission level.  Key Learning : • No Tripping is observed yet frequency increased indicating large quantum of load loss. • Load Loss can occur when fault is severe and delayed clearance is there. (Not FIDVR Case) • Surprise for System Operator. Case Study 1 : Padghe Event Voltage Demand and Frequency 11-Jan-19 ERLDC, POSOCO 19
  • 20. • Summer Season : High Concentration of Air condition load in Delhi and nearby area. • Phase to Phase Fault on 400 kV Transmission line near Delhi and delayed fault clearance. • Fault clearance is delayed. • 3700 MW load was lost based on SCADA and PMU data. High Shoot up in frequency. • No report of loss in terms of lines/ICT tripping at distribution level. • Slow Voltage recovery and FIDVR Characteristic Observed. Case Study 2 : 400 kV Bawana – Mundka - II tripping event (FIDVR) Voltage 11-Jan-19 ERLDC, POSOCO 20
  • 21. Angular Separation in Grid and frequency Increased Drastically Northern Region Demand Reduced by Large Quantum 11-Jan-19 ERLDC, POSOCO 21
  • 22. FIDVR or Severe Fault Causing Load Loss becoming frequent and act as a challenge for System Operator. Characteristic of Such Events • Any phase to phase or three phase of fault at 220 kV and above level near to load centers : • Severe nature • Cause load loss due to tripping of induction motor load on overcurrent/under voltage protection. • Delayed fault clearance makes it more severe as causes more load loss. • FIDVR event • Occur during the summer season when load are majorly of single phase AC units’ load. • Occur during severe fault near to the load centers along with its delayed clearance from the system. • Followed by a sharp rise in frequency due to load loss and quick recovery with 5-20 minutes. 11-Jan-19 ERLDC, POSOCO 22
  • 23. • Treatment of Distorted Voltage : Erroneous Frequency Calculation can result in Tripping of the Inverter (Solar Plant) • Wind Related LVRT protection setting for DFIG based Turbine having crowbar arrangement : Limitation with How many times LVRT will operate within a duration of time. • Protection Coordination and Islanding Some Key Issues with Renewable & Inverters 11-Jan-19 ERLDC, POSOCO 23
  • 26. 1. Operational States of the Grid Normal • Equality Constraint : Load+Loss=Generation • Inequality Constraint : All Parameters within Safe limit 11-Jan-19 ERLDC, POSOCO 26
  • 27. • Normal state :All system variables are within the normal operating range • Alert state : Security level falls below a certain limit of adequacy because of a Event • Emergency state : Severe disturbance • In Extremis : Cascading outages • Restorative state 1. Operational States of the Grid 11-Jan-19 ERLDC, POSOCO 27
  • 28. • Ultimate Objective is to not reach the IN EXTREMIS State of Operation. • Each Level having its own defense mechanism for returning back to previous state. • Normal state : • Operational Standards : CEA Standard and IEGC • Operational Ranges for System Parameters : CEA Standard and IEGC • Operational Criteria : IEGC and Operational Procedure • Alert state : • Primary , Secondary and Tertiary Control • Automatic Control from FACTS/HVDC devices • Load Generation Redispatch • Manual Load Shedding and Generation Revival • Under Voltage Load Shedding Scheme 1. Operational States of the Grid 11-Jan-19 ERLDC, POSOCO 28
  • 29. • Emergency State • System Protection Scheme • Load Trimming Scheme • Generation Reduction Scheme • In Extremis • Under Frequency Load Shedding Scheme • ROCOF based Load Shedding Scheme • Islanding Scheme • Unintended System Separation • Restorative state • Black Start and Island Synchronization 2. Operational States of the Grid 11-Jan-19 ERLDC, POSOCO 29
  • 30. 2. Need of Defense Mechanism Power System Operate with following Contingencies in Real Time: • N : No Element is Out • N-1: One Important element is Out • N-1-1 : One element is out followed by other element • N-K: Multiple elements are out Real Time Operators ensure that there is no additional insecure operation after these outages/contingencies. All Electrical Parameters are within their prescribed band. 11-Jan-19 ERLDC, POSOCO 30
  • 31. However, System Can go from N state to N-K with Events/Contingencies That’s why there is a need of Defense Mechanism 2. Need of Defense Mechanism 11-Jan-19 ERLDC, POSOCO 31
  • 32. 3. Defense Mechanism and Types • Need of Some Mechanism to recover the system back to Normal State of Operation. • Mechanism placed in Grid for Recovering System from Alert/Emergency/ In Extremis State are called Defense Mechanism for Power System. • Automated Mechanism • Quick recovery (Response Time is in millisecond to few seconds) • Fast, Logic Based, Measurement Based, Reliable. • Action can be Local or Global depending on design. • Act as last line of defense before system go for blackout or cascaded tripping. 11-Jan-19 ERLDC, POSOCO 32
  • 33. Defense Mechanism Can be Classified as : • Based on Type of Action : Generation, Load, HVDC Set Point, FACTS. • Based on Area of Action : Local and Global • Based on Parameter : Frequency Based, Voltage Based, Current Based, Active and Reactive Flow Based • Based on Time : Instantaneous, Time delayed 3. Defense Mechanism and Types 11-Jan-19 ERLDC, POSOCO 33
  • 34. 3.Defense Mechanism in Indian Power System • Dynamic Control of HVDC/FACTS, PSS Of Generators • System Protection Scheme (SPS) • Automated Under Voltage Load Shedding (AUVLS) • ICT Load trimming Scheme (LTS) • Automated Under Frequency load Shedding (AUFLS) and ROCOF based Load Shedding • Islanding Scheme 11-Jan-19 ERLDC, POSOCO 34
  • 35. 4.a. Dynamic Control of HVDC/FACTS, PSS Of Generators • HVDC/FACTS are having dynamic control which depending of criteria provide response to reduce the impact of event. • Frequency Controller of HVDC • Sub-synchronous Torsional Interaction(SSTI) Controller of HVDC • Power Oscillation Damping (POD) of HVDC/FACTS • Dynamic Reactive Support from SVC/STATCOM 11-Jan-19 ERLDC, POSOCO 35
  • 36. 4.a. Dynamic Control of HVDC/FACTS, PSS Of GeneratorsTalcher-KolarHVDCFrequencyController 11-Jan-19 ERLDC, POSOCO 36
  • 37. 4.a. Dynamic Control of HVDC/FACTS, PSS Of Generators t/s -5 0 5 10 15 20 25 30 35 P_LINE1 NA/MW 0 50 100 150 200 t/s -5 0 5 10 15 20 25 30 35 POD_OUT_DX NA/PU -0.0 0.2 0.4 t/s -5 0 5 10 15 20 25 30 35 X_REF_MOM NA/PU 0.75 1.00 1.25 1.50 t/s -5 0 5 10 15 20 25 30 35 XAPP_R R/PU 0.0 0.5 1.0 1.5 t/s -5 0 5 10 15 20 25 30 35 XAPP_Y Y/PU 0.0 0.5 1.0 1.5 t/s -5 0 5 10 15 20 25 30 35 XAPP_B B/PU 0.0 0.5 1.0 1.5 t/s -5 0 5 10 15 20 25 30 35 P_SWING NA/MW 0 25 50 75 t/s -5 0 5 10 15 20 25 30 35 ABS_P_SWING NA/MW 0 25 50 75 t/s -5 0 5 10 15 20 25 30 35 AB BP_STRAT_ON POD_ON POD_CBP RaipurTCSCPODController 11-Jan-19 ERLDC, POSOCO 37
  • 38. 4.b. Automatic Under Voltage Load Shedding Scheme • Power systems today are much more susceptible to voltage collapses as increasingly depend on generation sources that are located remotely from load centers. • UVLS relays are meant for shedding of load when the voltage is going below the operational lower limit in order to avoid voltage collapse. • IEGC 5.2.t Mandates : All Users, CTU and STUs shall provide adequate voltage control measures through voltage relay as finalized by RPC, to prevent voltage collapse. and shall ensure its effective application to prevent voltage collapse/ cascade tripping. 11-Jan-19 ERLDC, POSOCO 38
  • 39. Basic Design Criteria : 1. Designed to coordinate with protective devices and control schemes for momentary voltage dips, sustained faults, low voltages caused by stalled air conditioners, etc. 2. The time delay should be in seconds, not in cycles 3. Must be on Bus VTs and coordinate with ICT/Lines Load Trimming Scheme. 4. Voltage pick-up points to set reasonably higher than the “nose point” P-V nose curve. 5. Enough load shed to bring voltages to minimum operating voltage levels or higher Example Setting for UVLS In case of two stage operation • Alarm: If Voltage < 375 kV ; Stage 1: If Voltage < 372 kV for 5 sec; Stage 2: If Voltage < 370 kV for 10 Sec In case of Single stage operation • If Voltage < 370 kV for 5 seconds 4.b. Automatic Under Voltage Load Shedding Scheme 11-Jan-19 ERLDC, POSOCO 39
  • 40. 4.c. Load trimming Scheme (LTS) • These are also SPS which are local in nature and has designated purpose of saving elements getting overloaded due to contingencies. • Implementation for Line and ICT to avoid overloading. • Several Such LTS scheme are there in Various States across India. • Their operation during contingencies helps in arresting the event widespread. • Basically Designed using Overcurrent Feature of the Relays with PLCC as Communication Media. • Need of Coordination between various LTS is very much necessary in an interconnected system (One LTS Impacts Others): On two occasions Kolhapur ICTs (3 Nos) and Karad ICTs (3 Nos) tripped One iCT tripping even after the LTS operation due to Non-Coordination. 11-Jan-19 ERLDC, POSOCO 40
  • 41. • Frequency should be within prescribed band of 49.9-50.05 Hz. • However, Frequency will fall rapidly with System Islanding/Large generation complex loss. • AUFLS and ROCOF (df/dt) based automated load shedding are ways to arrest gradual as well as fast fall in frequency in the system (Frequency fall Arrester) • ROCOF based relay arrest the fast fall in frequency while AUFLS will restrict the frequency above a certain limit. • AUFLS is global phenomenon and load shedding occurs as per design in the complete synchronized grid While ROCOF based load shedding quantum caries with nearness to Frequency related event source. • Quantum of such Load connected with AUFLS and df/dt relay changes with system size and connectivity. 4.d. AUFLS and ROCOF Relays for Load Shedding 11-Jan-19 ERLDC, POSOCO 41
  • 42. Last AUFLS Operation : Separation of NEW and SR Grid on 24 May 2015 during High import by Southern Region. 4.d. AUFLS and ROCOF Relays for Load Shedding 11-Jan-19 ERLDC, POSOCO 42
  • 43. CGPL Event 12 March 2014 UMPP Loss Largest Contingency in the System ROCOF Operated in Gujarat (636 MW) and Maharashtra (334) 4.d. AUFLS and ROCOF Relays for Load Shedding ROCOF Relay Operated. 11-Jan-19 ERLDC, POSOCO 43
  • 44. 49.9 Hz ROCOF Relay operation in Gujarat on 18 Jan 2017 • Cause : Momentary Cessation of Full HVDC Mundra Power Order of 2500 MW to Zero and Auto-Restart to 2500 MW in 10 ms interval causing Large swing in WR and NR (See Frequency Plot) • Root Cause : Simultaneous DC line Fault (Rare Contingency) • ROCOF operated in Gujarat System near Mundra : 486 MW load Loss • PMU indicated ROCOF above 0.4 Hz/Sec (Highest Value of ROCOF) 4.d. AUFLS and ROCOF Relays for Load Shedding 11-Jan-19 ERLDC, POSOCO 44
  • 45. • When The system is moving towards in Extremis and Blackout , its desirable to split system having load/generation balance in Island for faster restoration. • It’s the Last Measure : Islanding should take place only when all other defense plan have been allowed their full opportunity to bring back and maintain system integrity and still the health of integrated system is on path of deteoriation towards failure. • Large Number of Islanding Scheme is Not Suitable for Integrated Grid. • Operational frequency band for pre-islanding defense mechanism and islanding frequency band sufficiently apart : Help in taking care of continued fall of frequency during the interval between relay pick-up and breaker opening. • IEGC 5.2.n 4.e. Islanding Scheme 11-Jan-19 ERLDC, POSOCO 45
  • 46. • Islanding to Occur : When all other defense plan ( fault clearance, SPS action, UFLS and df/dt load shedding etc.) have been allowed their final operational opportunity and the system is still on the path of deterioration towards collapse. • Islanding not to Occur : If there is still a chance that a distressed system can be brought back to emergency condition (or alert condition or normal condition) with operation of the mechanism planed for integrated and interconnected states of Grid. • Frequency Band Setting for Islanding • Devised for Part of system which have Load generation balance : Preserve those areas which inherently are in a position to achieve load generation balance post islanding. To be Reviewed after 2 Years Ramakrishna Committee Recommendation 4.e. Islanding Scheme 11-Jan-19 ERLDC, POSOCO 46
  • 47. • Generally Implemented for only those sub-parts of network : • Connect to rest of grid in an electrically radial manner with only a few interconnecting lines • Have their own load generation balance to a large extent, requiring comparatively smaller exchanges with rest of the grid. • Features to be incorporated In Islanding Scheme • Adequate automated mechanism for achieving load generation balance. • Frequency control of islanded subsystem: Sufficient number/capacity of generating units in on free governor mode of operation in the island. • Load connection/disconnection should be possible remotely from the dispatch centre of the islanded sub-system. • Health of Monitoring System for all equipment in island System should be good. 4.e. Islanding Scheme 11-Jan-19 ERLDC, POSOCO 47
  • 48. MumbaiIslandingScheme TROMBAY 220 KV TROMBAY 110 KV SALSETTE 110 KV KALYAN 110 KV SALSETTE 220 KV BORIVALI 110 KV BORIVALI 220 KV UFR - 47.9 Hz RPUF – 48.0 Hz RPUF - 47.9 Hz UFR - 47.9 Hz UFR - 47.9 Hz RPUF - 47.7 Hz 47.9Hz RPUF - 47.9 Hz UFR - 47.9 Hz UFR - 47.6 Hz AAREY VERSOVA DAHANU UFR - 47.9 Hz MSETCL Tata Power R-infra UFR - 47.9 Hz GHODBUNDER TROMBAY KALWA BORIVLI BOISAR BORIVLI UFR - 47.9 Hz UFR - 47.9 Hz UFR - 47.9 Hz 4.e. Islanding Scheme 11-Jan-19 ERLDC, POSOCO 48