SlideShare a Scribd company logo
Advance Construction Technology in Civil
Engineering
Bhishma Bhatti M.Tech (IEM)
Assistant Professor
Babaria Institute of Technology
What mean by Advance construction technology?
• Term ‘Advance construction technology’ covers wide range of
modern construction technology and also deals with latest
developments in,
• Material technology
• Quantity surveying
• Facility management
• Structure analysis and design
• Construction equipment
• Basically it relates with terms,
• Material
• Manpower
• Time
• Efficiency of work
• Reduction in time
• Less amount of manpower
• Quality in construction
• Value for money
• Sustainability
• Reduction of construction waste
• Improved ease of construction
Key benefits Advance construction technology
Slip Formwork
Introduction
• Slip-form construction is a method for Building large towers or bridges from
Concrete.
• The name refers to the moving form the concrete is poured into, which moves
along the project as the previously poured concrete hardens behind it. The
technique has also been applied to road construction.
• Vertical slip-form relies on the quick-setting properties of concrete requiring a
balance between early strength gain and workability. Concrete needs to be
workable enough to be placed to the formwork and strong enough to develop
early strength so that the form can slip upwards without any disturbance to the
freshly placed concrete.
• A notable use of the method was the Skylon Tower in Niagara Falls, Ontario,
which was completed in 1965. The technique was soon utilized to build the Inco
Super stack in Sudbury, Ontario and the CN Tower in Toronto. It is the most
common method for construction of tall buildings in Australia.
• From foundation to rooftop of even the very tallest projects, with the system’s
hydraulic jacks, installing steel reinforcement and pouring concrete become
much easier and faster, plus can be more efficiently controlled to assure the
highest quality finished cement structure.
• SLIPFORM technology virtually eliminates unnecessary waste and
hazards, making this construction system even more efficient an economical.
Overview
• Method of vertically extruding a reinforced concrete section and is suitable
for construction of core walls in high-rise structures – lift shafts, stair shafts,
towers.
• The formwork rises continuously, at a rate of about 300 mm per hour,
supporting itself on the core and not relying on support or access from other
parts of the building or permanent works.
• Allows for the continuous pouring of concrete into walls of a structure and
only stops when the full required height of the structure has been achived.
• The height of the formwork is designed in such a way that while the top of
the formwork is being filled by concrete the lowest layer of concrete
poured earlier has already gained an initial set. When the formwork is
moved upwards the concrete that is then exposed remains firm.
Components
Steps
1. Assembly can Only Start Once The Foundations Are In Place and the wall
starter is in correct alignment.
2. Slip form shuttering is aligned with the help of yokes.
3. Horizontal crossbeams connect the yokes.
4. Hydraulic jacks are attached to these Crossbeams for simultaneous
upward movement.
5. Height of the slip form ranges from meters
Structural concerns
Precautions
RELATIONBETWEENCONCRETESETTINGTIMEANDSLIPFORMRATE
• It iscalculatedbyusingthefollowing
• equation:
• Vs =(H1-H2) / (ts–tt)
• Where
• Vs–slip-form rate (mm/ h)
• H1=the distancefrom the top of the slip- form
panelto the averagecuringfront (mm)
• H2=Thedistancefrom the top of theslip-
form panelto averagefreeboard(mm)
• Ts=setting time(h)
• Tt =Timefrom mixing concrete toplacing
ADVANTAGES:
• A major cost of concrete structure construction is the required formwork to retain the
concrete till it can be safely de-shuttered and be able to support itself and other imposed loads.
• The formwork needs to be continually removed to newer locations and then re- erected.
• In the case of slip form building, the formwork is erected only once and remains intact until the
entire structure is completed.
• The formwork system is easy to clean and reuse with little formwork waste generated
compared to traditional formwork
• Climbing formwork systems offer simplicity, safety and cost effectiveness for certain high-rise
building structures
Formwork system
• DUO can be used for foundations, walls and
columns as well as for slabs and beams.
• The system is characterized by the extremely
simple handling and the minimum number of
different system components.
• Increases finishing of external surface.
Duo
• Particularly lightweight panel formwork made of techno-polymers for
forming walls, columns, slabs.
• High degree of resistance against all environmental influences; 100%
recyclable
• Elements with heights of 60 cm and 135 cm as well as up to 90 cm widths
• Max. permissible fresh concrete pressure: 50 kN/m² (for walls)
• Max. permissible fresh concrete pressure: 80 kN/m² (for columns and
wall sections)
• Low-noise assembly without requiring a hammer.
• Fast and easy to assemble
Technical Detail
VARIO GT 24 Girder
Wall Formwork
• With girder wall formwork, the arrangement of the
individual system components can be freely
selected. As a result, the VARIO GT 24 can be
adapted to suit all geometries and requirements of
project.
• Flexible wall formwork with the main components:
GT 24 Formwork Girder, SRZ / SRZ / SRU Steel
Walers, formlining and related connecting parts
• Project-related planning and assembly.
• Used in Bridge abutments, Retaining wall,
Architectural concrete parts.
• Flexible panel heights, determined by the length of the GT 24 Girder
(standard lengths 0.90 m to 6.00 m in 30 cm increments; special lengths up
to 17.80 m)
• Minimizing the number of formwork girders due to their high bending
rigidity and load-bearing capacity
• Project-specifific construction, adaptable for accommodating a very high
maximum fresh concrete pressure
• Elongated holes in the steel walers and panel couplings allow 100 %
tension and compression-proof panel connections resulting in tight panel
joints.
Technical Detail
COLUMN FORMWORK
LICO Column Formwork
• Cost-effective column formwork
with simply constructed steel frames for working
without the use of a crane
• Easy and simple assembly
with only 3 panel heights and connecting means
which are permanently attached to the panels and
cannot be lost
• Ring bolts on all panels
serve as load bearing points for moving with the
crane as well as for panel connections when
extending
• For square and rectangular cross-sections from 20 cm x 20 cm up to 60 cm
x 60 cm in 5 cm increments
• Larger cross-sections with additional ties
• Height adjustments up to maximum 4.50 m in 50 cm increments with 3
different panel heights (0.50 m / 1.00 m / 3.00 m)
• Panel connection when extending by means of ring bolts on the panels that
also serve as crane suspension
• Maximum permissible fresh concrete pressure 80 kN/m²
• With working and concreting platforms
TECHNICAL DETAIL
QUATTRO Column
Formwork
Time-saving shuttering and striking
with panels which can be tightened or separated
with only a few simple steps.
Fast moving
of complete units with the crane, or optionally by
hand with 4 transportation wheels for heights up to
3.50 m
For enhanced surface qualities
due to the plastic form lining being screwed on at
the rear
TECHNICAL DETAIL
• For square or rectangular cross-sections from 20 cm x 20 cm up to 60
cm x 60 cm in 5 cm increments
• Height adjustments up to 4.50 m in 25 cm increments with 4 different
panel heights (0.50 m / 1.25 m / 2.75 m / 3.50 m)
• Panel connections when extending through ring bolts that also serve
as crane suspension
• Maximum permissible fresh concrete pressure 80 kN/m²
• With working and concreting platforms as well as access ladders
RAPID Column Formwork
• For architectural concrete surfaces without
any impressions
with freely-selectable, clamped formlining
• Also for sharp-edged column cross-sections
with suitably milled formlining
• Fast basic assembly
due to lightweight aluminum panels along
with a simple clamping principle for the fi xing
of formlining
• For square and rectangular cross-sections continuously up to 60 cm x 60 cm (58 cm for
sharp edges)
• Cross-sections from 85 cm x 85 cm up to 130 cm x 130 cm with waler for bracing and
additional anchor
• Height adjustments up to maximum 8.10 m in 30 cm increments with 3 different panel
heights (0.60 m / 2.10 m / 3.00 m)
• Panel connection when extending the frames with bolts (factory fitted) in the top
column strut
• Maximum permissible fresh concrete pressure 120 kN/m²
• With working and concreting platforms as well as access ladders
TECHNICAL DETAIL
SRS Circular Column
Formwork
• With tight panel joints and ability to accommodate high
fresh concrete pressures, the steel SRS Circular Column
Formwork produces the highest quality concrete surfaces
• Fast assembly
with two column halves and integrated tie yoke with self-
cleaning hexagonal thread
• Best concrete surfaces
due to the high production quality of the steel formwork
• Safe and reliable logistics
due to integrated stacking aids for easy stacking and safe
positioning of the panels during transport
• For circular columns with diameters from 25 cm to 70 cm in 5 cm increments
• Special sizes with up to 120 cm diameters available
• Panel heights up to 8.40 m depending on the diameter, extendable in 30 cm
increments
• Panel connection when extending through ring bolts on the panels that also
serve as crane suspension
• Maximum permissible fresh concrete pressure 150 kN/m²
• With working and concreting platforms as well as access ladders
TECHNICAL DETAIL
GRIDFLEX Grid Element Slab Formwork
• The flexible, efficient slab formwork for simplest assembly with highest work
safety.
• GRIDFLEX is used for constructing residential and multi-storey buildings.
• The standard element weighs only 20 kg,
• Slab formwork with walk-on aluminium girder grid for formlining of choice
• For slab thicknesses up to 33 cm, or with additional middle support of the element up
to 67 cm
• Lightweight components – the standard element weighs only 20 kg
• Only 2 system components required for each standard field (Prop Head and
GRIDFLEX Standard Element)
TECHNICAL DETAIL
The assembly sequence is very simple: hook-in element, push into position with the
shuttering aid, attach slab prop and position vertically.
MULTIFLEX Girder Slab Formwork
Overview
• The main components of the MULTIFLEX are the VT 20K or GT 24 Formwork
Girders. As the main and cross beams, their position and spacing as well as the
formlining can be freely selected, MULTIFLEX provides maximum flexibility for a
wide range of requirements.
• Girder slab formwork consisting of main and cross beams for the formlining of choice
• Project-specific selection of the formwork girders and their spacing
• For slab thicknesses of up to 100 cm with GT 24 Formwork Girders, for slab
thicknesses up to 50 cm with VT 20K Formwork Girders
• Adapting the individual component weights in accordance with the boundary
conditions
• Tilt-resistant support of the cross beams on the main beams through the use of Flex
clips
TECHNICAL DETAIL
SKYDECK Panelized Slab Formwork
Overview
• SKYDECK´s range of applications extends from residential construction through to
industrial construction projects with thicker slabs. With extensive range of accessories,
the slab formwork is ideally suited for markets with very high safety standards.
• Panel slab formwork with lightweight aluminium system components including
formlining
• For slab thicknesses up to 42 cm (with 225 cm main beam) or with 150 cm
main beam and 75 cm panel width for slab thicknesses up to 109 cm
• With lightweight individual components (panels and main beams weigh only
15.5 kg respectively)
• Systematic assembly sequence whereby the size of the panel dictates the prop
position
• Only 0.29 props per m² of slab formwork
• Through the change in the direction of the panel, fifi ller areas are reduced to
a minimum
Technical detailTECHNICAL DETAIL
• SKYDECK for easy and safe
assembly. The panels lock
in place in the teeth and
don’t sway anymore. Also
unskilled staff can learn to
handle it very quickly.
One blow of the hammer releases the drophead; in the process, the formwork is
lowered by 6 cm. Main beams and panels can then be struck.
• Basically, this method involves the continuous placing of concrete in a shallow
mold having the same plan as the building to be constructed.
• The working deck which is jacked slowly upwards at a controlled rate until
the required elevation is reached.
This Photo by Unknown Author is licensed under CC BY-NC-ND

More Related Content

What's hot

Types of formwork
Types of formworkTypes of formwork
Types of formwork
Aglaia Connect
 
Precast construction
Precast constructionPrecast construction
Precast construction
Divya Vishnoi
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
Abhishek Gupta
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
Divya Vishnoi
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
AbhishekM45
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
nishant patyal
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ASHOK KUMAR TIWARY
 
Defects in buildings & remedies
Defects in buildings & remediesDefects in buildings & remedies
Defects in buildings & remedies
SOUMYA KHANDELWAL
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
Prabhat chhirolya
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
Shailja km
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
Surhan Fatima
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
adarshkaushik6
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
Shivangi Saini
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
Sandeep Jain
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
Atul Verma
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
Darshit
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
ppt_master
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
Akshay Revekar
 
Roof truss
Roof trussRoof truss
Roof truss
Pankajkumar Singh
 

What's hot (20)

Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Prefabrication construction
Prefabrication constructionPrefabrication construction
Prefabrication construction
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Prefabrication​ structure ppt
Prefabrication​ structure pptPrefabrication​ structure ppt
Prefabrication​ structure ppt
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Defects in buildings & remedies
Defects in buildings & remediesDefects in buildings & remedies
Defects in buildings & remedies
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 
Slabs and types
Slabs and typesSlabs and types
Slabs and types
 
Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Defects in construction
Defects in constructionDefects in construction
Defects in construction
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Roof truss
Roof trussRoof truss
Roof truss
 

Similar to Advance Formwork System (PERI FORMWORK SYSTEM)

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
national building code
national building codenational building code
national building code
Ruhiya Garg
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
ssuserc0bf9b
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
RMD Kwikform Ltd
 
tall.pptx
tall.pptxtall.pptx
tall.pptx
Sougata Das
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
tivar rose
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
DP NITHIN
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
Abdul Rahman
 
Ertf
ErtfErtf
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
Anirudh Gupta
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
Deepak Pradhan
 
Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.
Integrated Design
 
Flat slab design
Flat slab designFlat slab design
Flat slab design
Moussa Rili
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
sravan kumar chilamakuri
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
ssuserc0bf9b
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
Prasad Thanthratey
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
Yazid Hamoda
 

Similar to Advance Formwork System (PERI FORMWORK SYSTEM) (20)

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
national building code
national building codenational building code
national building code
 
Form-woks-additional.pptx
Form-woks-additional.pptxForm-woks-additional.pptx
Form-woks-additional.pptx
 
Trulift presentation
Trulift presentationTrulift presentation
Trulift presentation
 
tall.pptx
tall.pptxtall.pptx
tall.pptx
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Ertf
ErtfErtf
Ertf
 
Precast modular structures
Precast modular structuresPrecast modular structures
Precast modular structures
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.Final presentation by Akramul masum from southeast university bangladesh.
Final presentation by Akramul masum from southeast university bangladesh.
 
Flat slab design
Flat slab designFlat slab design
Flat slab design
 
Mivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnologyMivan form wok - aluminium formwork shuttering tecnology
Mivan form wok - aluminium formwork shuttering tecnology
 
Chapters-3,4,5.pptx
Chapters-3,4,5.pptxChapters-3,4,5.pptx
Chapters-3,4,5.pptx
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 

Recently uploaded

ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 

Recently uploaded (20)

ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 

Advance Formwork System (PERI FORMWORK SYSTEM)

  • 1. Advance Construction Technology in Civil Engineering Bhishma Bhatti M.Tech (IEM) Assistant Professor Babaria Institute of Technology
  • 2. What mean by Advance construction technology? • Term ‘Advance construction technology’ covers wide range of modern construction technology and also deals with latest developments in, • Material technology • Quantity surveying • Facility management • Structure analysis and design • Construction equipment • Basically it relates with terms, • Material • Manpower • Time
  • 3. • Efficiency of work • Reduction in time • Less amount of manpower • Quality in construction • Value for money • Sustainability • Reduction of construction waste • Improved ease of construction Key benefits Advance construction technology
  • 5. Introduction • Slip-form construction is a method for Building large towers or bridges from Concrete. • The name refers to the moving form the concrete is poured into, which moves along the project as the previously poured concrete hardens behind it. The technique has also been applied to road construction. • Vertical slip-form relies on the quick-setting properties of concrete requiring a balance between early strength gain and workability. Concrete needs to be workable enough to be placed to the formwork and strong enough to develop early strength so that the form can slip upwards without any disturbance to the freshly placed concrete.
  • 6.
  • 7. • A notable use of the method was the Skylon Tower in Niagara Falls, Ontario, which was completed in 1965. The technique was soon utilized to build the Inco Super stack in Sudbury, Ontario and the CN Tower in Toronto. It is the most common method for construction of tall buildings in Australia. • From foundation to rooftop of even the very tallest projects, with the system’s hydraulic jacks, installing steel reinforcement and pouring concrete become much easier and faster, plus can be more efficiently controlled to assure the highest quality finished cement structure. • SLIPFORM technology virtually eliminates unnecessary waste and hazards, making this construction system even more efficient an economical.
  • 8.
  • 9.
  • 10. Overview • Method of vertically extruding a reinforced concrete section and is suitable for construction of core walls in high-rise structures – lift shafts, stair shafts, towers. • The formwork rises continuously, at a rate of about 300 mm per hour, supporting itself on the core and not relying on support or access from other parts of the building or permanent works. • Allows for the continuous pouring of concrete into walls of a structure and only stops when the full required height of the structure has been achived.
  • 11. • The height of the formwork is designed in such a way that while the top of the formwork is being filled by concrete the lowest layer of concrete poured earlier has already gained an initial set. When the formwork is moved upwards the concrete that is then exposed remains firm.
  • 12.
  • 13.
  • 15. Steps 1. Assembly can Only Start Once The Foundations Are In Place and the wall starter is in correct alignment. 2. Slip form shuttering is aligned with the help of yokes. 3. Horizontal crossbeams connect the yokes. 4. Hydraulic jacks are attached to these Crossbeams for simultaneous upward movement. 5. Height of the slip form ranges from meters
  • 16.
  • 19. RELATIONBETWEENCONCRETESETTINGTIMEANDSLIPFORMRATE • It iscalculatedbyusingthefollowing • equation: • Vs =(H1-H2) / (ts–tt) • Where • Vs–slip-form rate (mm/ h) • H1=the distancefrom the top of the slip- form panelto the averagecuringfront (mm) • H2=Thedistancefrom the top of theslip- form panelto averagefreeboard(mm) • Ts=setting time(h) • Tt =Timefrom mixing concrete toplacing
  • 20. ADVANTAGES: • A major cost of concrete structure construction is the required formwork to retain the concrete till it can be safely de-shuttered and be able to support itself and other imposed loads. • The formwork needs to be continually removed to newer locations and then re- erected. • In the case of slip form building, the formwork is erected only once and remains intact until the entire structure is completed. • The formwork system is easy to clean and reuse with little formwork waste generated compared to traditional formwork • Climbing formwork systems offer simplicity, safety and cost effectiveness for certain high-rise building structures
  • 22. • DUO can be used for foundations, walls and columns as well as for slabs and beams. • The system is characterized by the extremely simple handling and the minimum number of different system components. • Increases finishing of external surface. Duo
  • 23. • Particularly lightweight panel formwork made of techno-polymers for forming walls, columns, slabs. • High degree of resistance against all environmental influences; 100% recyclable • Elements with heights of 60 cm and 135 cm as well as up to 90 cm widths • Max. permissible fresh concrete pressure: 50 kN/m² (for walls) • Max. permissible fresh concrete pressure: 80 kN/m² (for columns and wall sections) • Low-noise assembly without requiring a hammer. • Fast and easy to assemble Technical Detail
  • 24.
  • 25.
  • 26. VARIO GT 24 Girder Wall Formwork • With girder wall formwork, the arrangement of the individual system components can be freely selected. As a result, the VARIO GT 24 can be adapted to suit all geometries and requirements of project. • Flexible wall formwork with the main components: GT 24 Formwork Girder, SRZ / SRZ / SRU Steel Walers, formlining and related connecting parts • Project-related planning and assembly. • Used in Bridge abutments, Retaining wall, Architectural concrete parts.
  • 27. • Flexible panel heights, determined by the length of the GT 24 Girder (standard lengths 0.90 m to 6.00 m in 30 cm increments; special lengths up to 17.80 m) • Minimizing the number of formwork girders due to their high bending rigidity and load-bearing capacity • Project-specifific construction, adaptable for accommodating a very high maximum fresh concrete pressure • Elongated holes in the steel walers and panel couplings allow 100 % tension and compression-proof panel connections resulting in tight panel joints. Technical Detail
  • 28.
  • 30. LICO Column Formwork • Cost-effective column formwork with simply constructed steel frames for working without the use of a crane • Easy and simple assembly with only 3 panel heights and connecting means which are permanently attached to the panels and cannot be lost • Ring bolts on all panels serve as load bearing points for moving with the crane as well as for panel connections when extending
  • 31. • For square and rectangular cross-sections from 20 cm x 20 cm up to 60 cm x 60 cm in 5 cm increments • Larger cross-sections with additional ties • Height adjustments up to maximum 4.50 m in 50 cm increments with 3 different panel heights (0.50 m / 1.00 m / 3.00 m) • Panel connection when extending by means of ring bolts on the panels that also serve as crane suspension • Maximum permissible fresh concrete pressure 80 kN/m² • With working and concreting platforms TECHNICAL DETAIL
  • 32. QUATTRO Column Formwork Time-saving shuttering and striking with panels which can be tightened or separated with only a few simple steps. Fast moving of complete units with the crane, or optionally by hand with 4 transportation wheels for heights up to 3.50 m For enhanced surface qualities due to the plastic form lining being screwed on at the rear
  • 33. TECHNICAL DETAIL • For square or rectangular cross-sections from 20 cm x 20 cm up to 60 cm x 60 cm in 5 cm increments • Height adjustments up to 4.50 m in 25 cm increments with 4 different panel heights (0.50 m / 1.25 m / 2.75 m / 3.50 m) • Panel connections when extending through ring bolts that also serve as crane suspension • Maximum permissible fresh concrete pressure 80 kN/m² • With working and concreting platforms as well as access ladders
  • 34. RAPID Column Formwork • For architectural concrete surfaces without any impressions with freely-selectable, clamped formlining • Also for sharp-edged column cross-sections with suitably milled formlining • Fast basic assembly due to lightweight aluminum panels along with a simple clamping principle for the fi xing of formlining
  • 35. • For square and rectangular cross-sections continuously up to 60 cm x 60 cm (58 cm for sharp edges) • Cross-sections from 85 cm x 85 cm up to 130 cm x 130 cm with waler for bracing and additional anchor • Height adjustments up to maximum 8.10 m in 30 cm increments with 3 different panel heights (0.60 m / 2.10 m / 3.00 m) • Panel connection when extending the frames with bolts (factory fitted) in the top column strut • Maximum permissible fresh concrete pressure 120 kN/m² • With working and concreting platforms as well as access ladders TECHNICAL DETAIL
  • 36. SRS Circular Column Formwork • With tight panel joints and ability to accommodate high fresh concrete pressures, the steel SRS Circular Column Formwork produces the highest quality concrete surfaces • Fast assembly with two column halves and integrated tie yoke with self- cleaning hexagonal thread • Best concrete surfaces due to the high production quality of the steel formwork • Safe and reliable logistics due to integrated stacking aids for easy stacking and safe positioning of the panels during transport
  • 37. • For circular columns with diameters from 25 cm to 70 cm in 5 cm increments • Special sizes with up to 120 cm diameters available • Panel heights up to 8.40 m depending on the diameter, extendable in 30 cm increments • Panel connection when extending through ring bolts on the panels that also serve as crane suspension • Maximum permissible fresh concrete pressure 150 kN/m² • With working and concreting platforms as well as access ladders TECHNICAL DETAIL
  • 38. GRIDFLEX Grid Element Slab Formwork
  • 39. • The flexible, efficient slab formwork for simplest assembly with highest work safety. • GRIDFLEX is used for constructing residential and multi-storey buildings. • The standard element weighs only 20 kg,
  • 40. • Slab formwork with walk-on aluminium girder grid for formlining of choice • For slab thicknesses up to 33 cm, or with additional middle support of the element up to 67 cm • Lightweight components – the standard element weighs only 20 kg • Only 2 system components required for each standard field (Prop Head and GRIDFLEX Standard Element) TECHNICAL DETAIL
  • 41. The assembly sequence is very simple: hook-in element, push into position with the shuttering aid, attach slab prop and position vertically.
  • 43. Overview • The main components of the MULTIFLEX are the VT 20K or GT 24 Formwork Girders. As the main and cross beams, their position and spacing as well as the formlining can be freely selected, MULTIFLEX provides maximum flexibility for a wide range of requirements.
  • 44. • Girder slab formwork consisting of main and cross beams for the formlining of choice • Project-specific selection of the formwork girders and their spacing • For slab thicknesses of up to 100 cm with GT 24 Formwork Girders, for slab thicknesses up to 50 cm with VT 20K Formwork Girders • Adapting the individual component weights in accordance with the boundary conditions • Tilt-resistant support of the cross beams on the main beams through the use of Flex clips TECHNICAL DETAIL
  • 46. Overview • SKYDECK´s range of applications extends from residential construction through to industrial construction projects with thicker slabs. With extensive range of accessories, the slab formwork is ideally suited for markets with very high safety standards.
  • 47. • Panel slab formwork with lightweight aluminium system components including formlining • For slab thicknesses up to 42 cm (with 225 cm main beam) or with 150 cm main beam and 75 cm panel width for slab thicknesses up to 109 cm • With lightweight individual components (panels and main beams weigh only 15.5 kg respectively) • Systematic assembly sequence whereby the size of the panel dictates the prop position • Only 0.29 props per m² of slab formwork • Through the change in the direction of the panel, fifi ller areas are reduced to a minimum Technical detailTECHNICAL DETAIL
  • 48. • SKYDECK for easy and safe assembly. The panels lock in place in the teeth and don’t sway anymore. Also unskilled staff can learn to handle it very quickly.
  • 49. One blow of the hammer releases the drophead; in the process, the formwork is lowered by 6 cm. Main beams and panels can then be struck.
  • 50. • Basically, this method involves the continuous placing of concrete in a shallow mold having the same plan as the building to be constructed. • The working deck which is jacked slowly upwards at a controlled rate until the required elevation is reached.
  • 51. This Photo by Unknown Author is licensed under CC BY-NC-ND

Editor's Notes

  1. Due to Advanced equipments