SlideShare a Scribd company logo
1 of 4
Download to read offline
Title of this process is "The Project Life Cycle (Phases)"
The project manager and project team have one shared goal: to carry out the work of the project
for the purpose of meeting the project’s objectives. Every project has a beginning, a middle
period during which activities move the project toward completion, and an ending.
A standard project typically has the following four major phases: initiation, planning,
implementation, and closure. Taken together, these phases represent the path a project takes from
the beginning to its end and are generally referred to as the project “life cycle.”
Initiation Phase
During the first phases, the initiation phase, the project objective is identified; this can be a
business problem or opportunity. An appropriate response to the objective of the project is
documented with recommended solution options. A feasibility study is conducted to investigate
whether each option addresses the project objective and a final recommended solution is
determined. Issues of feasibility (“can we do the project?”) and justification (“should we do the
project?”) are addressed.
Once the recommended solution is approved, a project is initiated to deliver the approved
solution and a project manager is appointed. Approval is then sought by the project manager to
move onto the detailed planning phase.
Planning Phase
The planning phase, is where the project solution is further developed in as much detail as
possible and the steps necessary to meet the project’s objective are planned. In this step, the team
identifies all of the work to be done. The project’s tasks and resource requirements are identified,
along with the strategy for producing them.
A project plan is created outlining the activities, tasks, dependencies, and timeframes. The
project manager coordinates the preparation of a project budget by providing cost estimates for
the labor, equipment, and materials costs. The budget is used to monitor and control cost
expenditures during project implementation.
Implementation (Execution) Phase
During the third phase, the implementation phase, the project plan is put into motion and the
work of the project is performed. It is important to maintain control and communicate as needed
during implementation. Progress is continuously monitored and appropriate adjustments are
made and recorded as variances from the original plan.
Throughout this step, project sponsors and other key stakeholders should be kept informed of the
project’s status according to the agreed-on frequency and format of communication. The plan
should be updated and published on a regular basis.
Status reports should always emphasize the anticipated end point in terms of cost, schedule, and
quality of deliverables. Each project deliverable produced should be reviewed for quality and
measured against the acceptance criteria. Once all of the deliverables have been produced and
the customer has accepted the final solution, the project is ready for closure.
Closing Phase
During the final closure, or completion phase, the emphasis is on releasing the final deliverables
to the customer, handing over project documentation to the business, terminating supplier
contracts, releasing project resources, and communicating the closure of the project to all
stakeholders. The last remaining step is to conduct lessons-learned studies to examine what went
well and what didn’t. Through this type of analysis, the wisdom of experience is transferred back
to the project organization, which will help future project teams.
Example: Project Phases on a Large Multinational Project
A U.S. construction company won a contract to design and build the first copper mine in
northern Argentina. There was no existing infrastructure for either the mining industry or large
construction projects in this part of South America.
The closeout phase included turning over the newly constructed plant to the operations team of
the client.
A punch list of a few remaining construction items was developed and those items completed.
The office in Catamarca was closed, the office in Buenos Aries archived all the project
documents, and the Chilean office was already working on the next project.
The accounting books were reconciled and closed, final reports written and distributed, and the
project manager started on a new project.
Solution
Title of this process is "The Project Life Cycle (Phases)"
The project manager and project team have one shared goal: to carry out the work of the project
for the purpose of meeting the project’s objectives. Every project has a beginning, a middle
period during which activities move the project toward completion, and an ending.
A standard project typically has the following four major phases: initiation, planning,
implementation, and closure. Taken together, these phases represent the path a project takes from
the beginning to its end and are generally referred to as the project “life cycle.”
Initiation Phase
During the first phases, the initiation phase, the project objective is identified; this can be a
business problem or opportunity. An appropriate response to the objective of the project is
documented with recommended solution options. A feasibility study is conducted to investigate
whether each option addresses the project objective and a final recommended solution is
determined. Issues of feasibility (“can we do the project?”) and justification (“should we do the
project?”) are addressed.
Once the recommended solution is approved, a project is initiated to deliver the approved
solution and a project manager is appointed. Approval is then sought by the project manager to
move onto the detailed planning phase.
Planning Phase
The planning phase, is where the project solution is further developed in as much detail as
possible and the steps necessary to meet the project’s objective are planned. In this step, the team
identifies all of the work to be done. The project’s tasks and resource requirements are identified,
along with the strategy for producing them.
A project plan is created outlining the activities, tasks, dependencies, and timeframes. The
project manager coordinates the preparation of a project budget by providing cost estimates for
the labor, equipment, and materials costs. The budget is used to monitor and control cost
expenditures during project implementation.
Implementation (Execution) Phase
During the third phase, the implementation phase, the project plan is put into motion and the
work of the project is performed. It is important to maintain control and communicate as needed
during implementation. Progress is continuously monitored and appropriate adjustments are
made and recorded as variances from the original plan.
Throughout this step, project sponsors and other key stakeholders should be kept informed of the
project’s status according to the agreed-on frequency and format of communication. The plan
should be updated and published on a regular basis.
Status reports should always emphasize the anticipated end point in terms of cost, schedule, and
quality of deliverables. Each project deliverable produced should be reviewed for quality and
measured against the acceptance criteria. Once all of the deliverables have been produced and
the customer has accepted the final solution, the project is ready for closure.
Closing Phase
During the final closure, or completion phase, the emphasis is on releasing the final deliverables
to the customer, handing over project documentation to the business, terminating supplier
contracts, releasing project resources, and communicating the closure of the project to all
stakeholders. The last remaining step is to conduct lessons-learned studies to examine what went
well and what didn’t. Through this type of analysis, the wisdom of experience is transferred back
to the project organization, which will help future project teams.
Example: Project Phases on a Large Multinational Project
A U.S. construction company won a contract to design and build the first copper mine in
northern Argentina. There was no existing infrastructure for either the mining industry or large
construction projects in this part of South America.
The closeout phase included turning over the newly constructed plant to the operations team of
the client.
A punch list of a few remaining construction items was developed and those items completed.
The office in Catamarca was closed, the office in Buenos Aries archived all the project
documents, and the Chilean office was already working on the next project.
The accounting books were reconciled and closed, final reports written and distributed, and the
project manager started on a new project.

More Related Content

Similar to Title of this process is The Project Life Cycle (Phases)The pr.pdf

Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
farouq umar
 
Project management professional
Project management professionalProject management professional
Project management professional
Reema
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptx
lexfred55
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1
Loren Schwappach
 
Project planning
Project planningProject planning
Project planning
Shaikh Zain
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
Odekunle Sakiru
 

Similar to Title of this process is The Project Life Cycle (Phases)The pr.pdf (20)

Project management
Project managementProject management
Project management
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
project managementUnit 1.pdf
project managementUnit 1.pdfproject managementUnit 1.pdf
project managementUnit 1.pdf
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Project management professional
Project management professionalProject management professional
Project management professional
 
Project Management
Project ManagementProject Management
Project Management
 
Construction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptxConstruction-Project-cycle-and-organization.pptx
Construction-Project-cycle-and-organization.pptx
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Unit-4.pptx
Unit-4.pptxUnit-4.pptx
Unit-4.pptx
 
Aaqib
AaqibAaqib
Aaqib
 
Project management
Project managementProject management
Project management
 
Project planning
Project planningProject planning
Project planning
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
The Complete Guide to Project Management Life Cycle Phases.pdf
The Complete Guide to Project Management Life Cycle Phases.pdfThe Complete Guide to Project Management Life Cycle Phases.pdf
The Complete Guide to Project Management Life Cycle Phases.pdf
 
Ngo’s project management
Ngo’s project managementNgo’s project management
Ngo’s project management
 

More from arakalamkah11

1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
arakalamkah11
 
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
arakalamkah11
 
Light is a form of energy that can be released by.pdf
                     Light is a form of energy that can be released by.pdf                     Light is a form of energy that can be released by.pdf
Light is a form of energy that can be released by.pdf
arakalamkah11
 
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
arakalamkah11
 
Youre looking for Ka, the dissociation constant.pdf
                     Youre looking for Ka, the dissociation constant.pdf                     Youre looking for Ka, the dissociation constant.pdf
Youre looking for Ka, the dissociation constant.pdf
arakalamkah11
 
remote operating system installationRemote Installation Services (.pdf
remote operating system installationRemote Installation Services (.pdfremote operating system installationRemote Installation Services (.pdf
remote operating system installationRemote Installation Services (.pdf
arakalamkah11
 
solutionA=  1    1    0    4    3    1    2    0 .pdf
solutionA=  1    1    0    4    3    1    2    0 .pdfsolutionA=  1    1    0    4    3    1    2    0 .pdf
solutionA=  1    1    0    4    3    1    2    0 .pdf
arakalamkah11
 
Q1). Gene therapy is an experimental approach to treat the disease b.pdf
Q1). Gene therapy is an experimental approach to treat the disease b.pdfQ1). Gene therapy is an experimental approach to treat the disease b.pdf
Q1). Gene therapy is an experimental approach to treat the disease b.pdf
arakalamkah11
 
package s3; Copy paste this Java Template and save it as Emer.pdf
package s3;  Copy paste this Java Template and save it as Emer.pdfpackage s3;  Copy paste this Java Template and save it as Emer.pdf
package s3; Copy paste this Java Template and save it as Emer.pdf
arakalamkah11
 
Our body is having two line defence system against pathogens.Pathoge.pdf
Our body is having two line defence system against pathogens.Pathoge.pdfOur body is having two line defence system against pathogens.Pathoge.pdf
Our body is having two line defence system against pathogens.Pathoge.pdf
arakalamkah11
 

More from arakalamkah11 (20)

Particulars $Amount Direct materials 64452 Direct Labour (1332.pdf
    Particulars $Amount   Direct materials 64452   Direct Labour (1332.pdf    Particulars $Amount   Direct materials 64452   Direct Labour (1332.pdf
Particulars $Amount Direct materials 64452 Direct Labour (1332.pdf
 
Decrease in inventory Source of cash $   440 Decrease in account.pdf
    Decrease in inventory Source of cash $   440   Decrease in account.pdf    Decrease in inventory Source of cash $   440   Decrease in account.pdf
Decrease in inventory Source of cash $   440 Decrease in account.pdf
 
Diamond is sp3 covalent. It makes for bonds to ne.pdf
                     Diamond is sp3 covalent. It makes for bonds to ne.pdf                     Diamond is sp3 covalent. It makes for bonds to ne.pdf
Diamond is sp3 covalent. It makes for bonds to ne.pdf
 
Too low. If you do not dry the sodium thiosulfate.pdf
                     Too low. If you do not dry the sodium thiosulfate.pdf                     Too low. If you do not dry the sodium thiosulfate.pdf
Too low. If you do not dry the sodium thiosulfate.pdf
 
1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
1. A bus is a bunch of wires used to connect multiple subsystems. Bu.pdf
 
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
1. E) The vapor pressure of a liquid.Increasing attractive intermo.pdf
 
Light is a form of energy that can be released by.pdf
                     Light is a form of energy that can be released by.pdf                     Light is a form of energy that can be released by.pdf
Light is a form of energy that can be released by.pdf
 
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
1) Presence of jaws with paired fins in fish helps to feed them. Fin.pdf
 
Youre looking for Ka, the dissociation constant.pdf
                     Youre looking for Ka, the dissociation constant.pdf                     Youre looking for Ka, the dissociation constant.pdf
Youre looking for Ka, the dissociation constant.pdf
 
Okay so dipole-dipole interactions would occur be.pdf
                     Okay so dipole-dipole interactions would occur be.pdf                     Okay so dipole-dipole interactions would occur be.pdf
Okay so dipole-dipole interactions would occur be.pdf
 
remote operating system installationRemote Installation Services (.pdf
remote operating system installationRemote Installation Services (.pdfremote operating system installationRemote Installation Services (.pdf
remote operating system installationRemote Installation Services (.pdf
 
The answer is A) Pol II, with twelve subunits on its own, is capable.pdf
The answer is A) Pol II, with twelve subunits on its own, is capable.pdfThe answer is A) Pol II, with twelve subunits on its own, is capable.pdf
The answer is A) Pol II, with twelve subunits on its own, is capable.pdf
 
solutionA=  1    1    0    4    3    1    2    0 .pdf
solutionA=  1    1    0    4    3    1    2    0 .pdfsolutionA=  1    1    0    4    3    1    2    0 .pdf
solutionA=  1    1    0    4    3    1    2    0 .pdf
 
Q1). Gene therapy is an experimental approach to treat the disease b.pdf
Q1). Gene therapy is an experimental approach to treat the disease b.pdfQ1). Gene therapy is an experimental approach to treat the disease b.pdf
Q1). Gene therapy is an experimental approach to treat the disease b.pdf
 
Solution Three modes of DNA replication 1) Semi conservative.pdf
Solution Three modes of DNA replication 1) Semi conservative.pdfSolution Three modes of DNA replication 1) Semi conservative.pdf
Solution Three modes of DNA replication 1) Semi conservative.pdf
 
package s3; Copy paste this Java Template and save it as Emer.pdf
package s3;  Copy paste this Java Template and save it as Emer.pdfpackage s3;  Copy paste this Java Template and save it as Emer.pdf
package s3; Copy paste this Java Template and save it as Emer.pdf
 
Our body is having two line defence system against pathogens.Pathoge.pdf
Our body is having two line defence system against pathogens.Pathoge.pdfOur body is having two line defence system against pathogens.Pathoge.pdf
Our body is having two line defence system against pathogens.Pathoge.pdf
 
Once neurons are produced, they migrate and modify to form six layer.pdf
Once neurons are produced, they migrate and modify to form six layer.pdfOnce neurons are produced, they migrate and modify to form six layer.pdf
Once neurons are produced, they migrate and modify to form six layer.pdf
 
PDU is called Protocol Data Unit.It consists of user data and protoc.pdf
PDU is called Protocol Data Unit.It consists of user data and protoc.pdfPDU is called Protocol Data Unit.It consists of user data and protoc.pdf
PDU is called Protocol Data Unit.It consists of user data and protoc.pdf
 
1.A hole is the absence of an electron in a particular place in an a.pdf
1.A hole is the absence of an electron in a particular place in an a.pdf1.A hole is the absence of an electron in a particular place in an a.pdf
1.A hole is the absence of an electron in a particular place in an a.pdf
 

Recently uploaded

Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
CaitlinCummins3
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
中 央社
 

Recently uploaded (20)

24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
24 ĐỀ THAM KHẢO KÌ THI TUYỂN SINH VÀO LỚP 10 MÔN TIẾNG ANH SỞ GIÁO DỤC HẢI DƯ...
 
Supporting Newcomer Multilingual Learners
Supporting Newcomer  Multilingual LearnersSupporting Newcomer  Multilingual Learners
Supporting Newcomer Multilingual Learners
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical Principles
 
An Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge AppAn Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge App
 
An overview of the various scriptures in Hinduism
An overview of the various scriptures in HinduismAn overview of the various scriptures in Hinduism
An overview of the various scriptures in Hinduism
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management
 
How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17
 
ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)ESSENTIAL of (CS/IT/IS) class 07 (Networks)
ESSENTIAL of (CS/IT/IS) class 07 (Networks)
 
UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024UChicago CMSC 23320 - The Best Commit Messages of 2024
UChicago CMSC 23320 - The Best Commit Messages of 2024
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio App
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
MOOD STABLIZERS DRUGS.pptx
MOOD     STABLIZERS           DRUGS.pptxMOOD     STABLIZERS           DRUGS.pptx
MOOD STABLIZERS DRUGS.pptx
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
PSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptxPSYPACT- Practicing Over State Lines May 2024.pptx
PSYPACT- Practicing Over State Lines May 2024.pptx
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
Major project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategiesMajor project report on Tata Motors and its marketing strategies
Major project report on Tata Motors and its marketing strategies
 
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽會考英聽
 

Title of this process is The Project Life Cycle (Phases)The pr.pdf

  • 1. Title of this process is "The Project Life Cycle (Phases)" The project manager and project team have one shared goal: to carry out the work of the project for the purpose of meeting the project’s objectives. Every project has a beginning, a middle period during which activities move the project toward completion, and an ending. A standard project typically has the following four major phases: initiation, planning, implementation, and closure. Taken together, these phases represent the path a project takes from the beginning to its end and are generally referred to as the project “life cycle.” Initiation Phase During the first phases, the initiation phase, the project objective is identified; this can be a business problem or opportunity. An appropriate response to the objective of the project is documented with recommended solution options. A feasibility study is conducted to investigate whether each option addresses the project objective and a final recommended solution is determined. Issues of feasibility (“can we do the project?”) and justification (“should we do the project?”) are addressed. Once the recommended solution is approved, a project is initiated to deliver the approved solution and a project manager is appointed. Approval is then sought by the project manager to move onto the detailed planning phase. Planning Phase The planning phase, is where the project solution is further developed in as much detail as possible and the steps necessary to meet the project’s objective are planned. In this step, the team identifies all of the work to be done. The project’s tasks and resource requirements are identified, along with the strategy for producing them. A project plan is created outlining the activities, tasks, dependencies, and timeframes. The project manager coordinates the preparation of a project budget by providing cost estimates for the labor, equipment, and materials costs. The budget is used to monitor and control cost expenditures during project implementation. Implementation (Execution) Phase During the third phase, the implementation phase, the project plan is put into motion and the work of the project is performed. It is important to maintain control and communicate as needed during implementation. Progress is continuously monitored and appropriate adjustments are made and recorded as variances from the original plan. Throughout this step, project sponsors and other key stakeholders should be kept informed of the project’s status according to the agreed-on frequency and format of communication. The plan should be updated and published on a regular basis. Status reports should always emphasize the anticipated end point in terms of cost, schedule, and
  • 2. quality of deliverables. Each project deliverable produced should be reviewed for quality and measured against the acceptance criteria. Once all of the deliverables have been produced and the customer has accepted the final solution, the project is ready for closure. Closing Phase During the final closure, or completion phase, the emphasis is on releasing the final deliverables to the customer, handing over project documentation to the business, terminating supplier contracts, releasing project resources, and communicating the closure of the project to all stakeholders. The last remaining step is to conduct lessons-learned studies to examine what went well and what didn’t. Through this type of analysis, the wisdom of experience is transferred back to the project organization, which will help future project teams. Example: Project Phases on a Large Multinational Project A U.S. construction company won a contract to design and build the first copper mine in northern Argentina. There was no existing infrastructure for either the mining industry or large construction projects in this part of South America. The closeout phase included turning over the newly constructed plant to the operations team of the client. A punch list of a few remaining construction items was developed and those items completed. The office in Catamarca was closed, the office in Buenos Aries archived all the project documents, and the Chilean office was already working on the next project. The accounting books were reconciled and closed, final reports written and distributed, and the project manager started on a new project. Solution Title of this process is "The Project Life Cycle (Phases)" The project manager and project team have one shared goal: to carry out the work of the project for the purpose of meeting the project’s objectives. Every project has a beginning, a middle period during which activities move the project toward completion, and an ending. A standard project typically has the following four major phases: initiation, planning, implementation, and closure. Taken together, these phases represent the path a project takes from the beginning to its end and are generally referred to as the project “life cycle.” Initiation Phase During the first phases, the initiation phase, the project objective is identified; this can be a business problem or opportunity. An appropriate response to the objective of the project is documented with recommended solution options. A feasibility study is conducted to investigate whether each option addresses the project objective and a final recommended solution is
  • 3. determined. Issues of feasibility (“can we do the project?”) and justification (“should we do the project?”) are addressed. Once the recommended solution is approved, a project is initiated to deliver the approved solution and a project manager is appointed. Approval is then sought by the project manager to move onto the detailed planning phase. Planning Phase The planning phase, is where the project solution is further developed in as much detail as possible and the steps necessary to meet the project’s objective are planned. In this step, the team identifies all of the work to be done. The project’s tasks and resource requirements are identified, along with the strategy for producing them. A project plan is created outlining the activities, tasks, dependencies, and timeframes. The project manager coordinates the preparation of a project budget by providing cost estimates for the labor, equipment, and materials costs. The budget is used to monitor and control cost expenditures during project implementation. Implementation (Execution) Phase During the third phase, the implementation phase, the project plan is put into motion and the work of the project is performed. It is important to maintain control and communicate as needed during implementation. Progress is continuously monitored and appropriate adjustments are made and recorded as variances from the original plan. Throughout this step, project sponsors and other key stakeholders should be kept informed of the project’s status according to the agreed-on frequency and format of communication. The plan should be updated and published on a regular basis. Status reports should always emphasize the anticipated end point in terms of cost, schedule, and quality of deliverables. Each project deliverable produced should be reviewed for quality and measured against the acceptance criteria. Once all of the deliverables have been produced and the customer has accepted the final solution, the project is ready for closure. Closing Phase During the final closure, or completion phase, the emphasis is on releasing the final deliverables to the customer, handing over project documentation to the business, terminating supplier contracts, releasing project resources, and communicating the closure of the project to all stakeholders. The last remaining step is to conduct lessons-learned studies to examine what went well and what didn’t. Through this type of analysis, the wisdom of experience is transferred back to the project organization, which will help future project teams. Example: Project Phases on a Large Multinational Project A U.S. construction company won a contract to design and build the first copper mine in northern Argentina. There was no existing infrastructure for either the mining industry or large
  • 4. construction projects in this part of South America. The closeout phase included turning over the newly constructed plant to the operations team of the client. A punch list of a few remaining construction items was developed and those items completed. The office in Catamarca was closed, the office in Buenos Aries archived all the project documents, and the Chilean office was already working on the next project. The accounting books were reconciled and closed, final reports written and distributed, and the project manager started on a new project.