SlideShare a Scribd company logo
1 of 26
PCAPP Update
25 June 2014
Safety
As of May 31, 2014
PCAPP staff has accomplished:
 765 Safe Work Days
 4,307, 831 Safe Work Hours
 VPP Application Submitted
2
Staffing – 1,034 employees
3
 Bechtel Pueblo Team
non-manual: 973
Pueblo
–260 Pueblo County hires
– 53 Colorado hires
–660 From Other Locations
 Construction Workers:
61
–Bechtel direct-hire – 28
–Subcontractor
personnel – 33
Staffing Update
Pueblo County Recruiting
Efforts:
June 24-
Colorado Technical University –
Career Fair (Colorado Springs)
July 8th-
Resume Writing Workshop #3,
Pueblo Workforce Center
Hires v. Vacancies Pueblo County Applicants v. Hires
PCAPP Staffing Actuals
0
20
40
60
80
100
New Hires Pueblo
County
New Hires from
Colorado
New Hires from
Other (Includes
Transfers)
Positions Filled
Note: Bechtel had 23 Interns start
on June 2nd – of the 23, 4 interns
were local hires
0
10
20
30
40
50
60
70
80
90
100
Filled Positions
Filled Positions
containing Pueblo
County Applicants
Pueblo County New
Hires
Note: Bechtel had 23
Interns start on June 2nd – of
the 23, 4 interns were local
hires
0
200
400
600
800
1000
1200
1400
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Dec-13
Jan-14
Feb-14
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
Jul-15
Aug-15
Sep-15
StartOps
Medical
Maintenance
Ops Support
Operations
Laboratory
Other
Actuals
1168
4
Summer Interns Begin Work
5
Touring the site are 24 interns who started on June 2. Four
interns attend Colorado State University (CSU), CSU-Pueblo,
University of Colorado, University of Northern Colorado.
Recruiting Efforts
6
Above, a local resident attends a
Resume Writing Workshop in April. The
next one is scheduled for July 8 at the
Pueblo Workforce Center.
PCAPP SYSTEMIZATION - 55% COMPLETE
APB 67%
ERB 66%
BTA 59%
As of May 2014
System Complete
UTILITIES 86%
HVAC 82%
FACILITIES 82%
7
FOR OFFICIAL USE ONLY
Mar May Jul Sep Nov Jan 2015 Mar May Jul Sep
8
- Baseline
2014 Mar May Jul Sep Nov
Jan
2015
Mar May Jul Sep 2015
120 days
HVAC Test &
Balance
24 March 2014 - 21 July 2014
56 days
ERB Provisional Ops 30 September 2014 - 24 November 2014
28 days
Yard Provisional Ops 17 July 2014 - 13 August 2014
56 days
APB Provisional Ops 25 November 2014 - 19 January 2015
21 days
Integrated SYS Testing 20 January 2015 - 9 February 2015
30 days
Final HVAC 10 February 2015 - 11 March 2015
105 days
Optimization 12 March 2015 - 24 June 2015
56 days
BTA Provisional Ops 19 November 2014 - 13 January 2015
14 days
IOD 25 June 2015 - 8 July 2015
14 days
Fix Cat 1 Findings 9 July 2015 - 22 July 2015
60 days
Endorsement 23 July 2015 –
20 September 2015
START 21 September 2015
Systemization Schedule Overview
FOR OFFICIAL USE ONLY
IAO ORR Status
ORR work is paced by Systemization work.
Data as of 18-June-2014
ORR Documents
Total
Required
Issued for
Completion
Board
Reviewed
Board Accepted
Affidavits 386 240 68 44
CRADS 386 26 0 0
9
Munitions Service Magazines
10
Operators test for forklift operations and munitions
movement in one of the Munitions Service Magazines.
Testing will determine storage amounts and capabilities.
Agent Processing Building
11
Operations staff will take hydrolysate samples from this
glovebox. Treaty inspectors will ensure that the mustard
agent has been destroyed according to treaty standards.
Enhanced Reconfiguration Building
12
Workers are preparing for a System Demonstration Plan for the
Explosion Containment Rooms. As a result, the feed conveyor,
pictured above, which is part of the Projectile Mortar
Disassembly system, will be turned over to Operations to begin
the Optimization phase of the process.
BSII Executive Visit
13
Bechtel Systems and Infrastructure, Inc. President Craig
Albert recently took a tour of the PCAPP facility. Startup
Specialist Bill Baugh explains the systemization process for
the Munitions Treatment Unit.
PCAPP Teams Walk for A Cause
14
More than $6,200 was raised for the American Cancer
Society’s Relay for Life on June 6. A total of 34
employees formed three teams to walk.
15
June 2014 Construction Update
Change House
Environmental
Enclosure #1
Environmental
Enclosure #3
Laboratory
PCAPP EDS Site Overview
16
PCAPP EDS Safety
As of May 31, the PCAPP
EDS project staff has
accomplished:
 70 Safe Work Days
 8,037 Safe Work Hours
17
On the level. Bricks and boards and plenty
of patience make each module both
horizontal and (as needed) parallel with its
mate as units are installed on site.
PCAPP EDS Construction
Staffing –41 employees
 Construction
 Workers: 8
–Subcontractor
personnel – 33
An electrician measures a metal support
beam for an electrical control panel that will
supply power to an Environmental Enclosure.
18
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
DESIGN START (DEC 2013)
SITE DESIGN COMPLETE (MAR 2014)
CONSTRUCTION STARTS (27 MAR 2014)
CONSTRUCTION COMPLETE (OCT 2014)
E-DAY – EDS START OF
AGENT OPERATIONS (OCT 2014)
CONSTRUCTION CONTRACT AWARD (NOV 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
PCAPP EDS Schedule
(JPME-P Working Schedule)
CONCRETE POURS BEGIN (17 APR 2014)
MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)
BEGIN TO ARRIVE (29 MAY 2014)
MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL
ENCLOSURES ARRIVE (JUN 2014)
ARRIVAL OF FIRST EDS UNIT (AUG 2014)
19
PCAPP EDS Permitting Progress
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)
STATE APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (7 MAR 2014)
SITE CONSTRUCTION START (27MAR 2014)
APPROVAL OF CLASS III MODIFICATION
FOR OPERATIONS (SEP 2014)
E-DAY – EDS START OF AGENT
OPERATIONS (OCT 2014)
PCD RCRA PERMIT RENEWED (JAN 2014)
SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
APPROVAL OF CD FOR OPERATIONS
(OCT 2014)
COUNTY APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (26 MAR 2014)
RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)
20
Site Progress
21
Before. These four sections were among the first modules to arrive May 29,
signaling the start of vertical construction and changing the look of the PCAPP
EDS site.
Site Progress
22
After. Seamed together, the separate units join as one structure that will comprise
the PCAPP EDS Command Post. Other units now arrived and installed include the
Change House and Treaty Trailer. The Entry Control Facility and Dilute Laboratory
are close behind.
Site Progress
23
The first of
the two
Environ-
mental
Enclosures
that will
house the
PCAPP EDS
units arrived
on June 19.
Within three
days, the
metal super-
structure
was up and
fabric pulled
tight over the
frame.
Site Progress
24
EDS just
became a bit
more real for
PCAPP workers,
who can now
see the first
Environmental
Enclosure (inset
above) from the
PSB parking lot.
25
PCAPP EDS Construction
Questions?
26

More Related Content

What's hot (12)

Eric Cavazza and Brian Bradley, PA DEP, "An Analysis of PAs Accelerated Respo...
Eric Cavazza and Brian Bradley, PA DEP, "An Analysis of PAs Accelerated Respo...Eric Cavazza and Brian Bradley, PA DEP, "An Analysis of PAs Accelerated Respo...
Eric Cavazza and Brian Bradley, PA DEP, "An Analysis of PAs Accelerated Respo...
 
May 2014 Construction Update PCAPP EDS
May 2014 Construction Update PCAPP EDSMay 2014 Construction Update PCAPP EDS
May 2014 Construction Update PCAPP EDS
 
Slide9 mp psht6of6
Slide9 mp psht6of6Slide9 mp psht6of6
Slide9 mp psht6of6
 
DS-17-031 Discuss Impact Fees
DS-17-031 Discuss Impact FeesDS-17-031 Discuss Impact Fees
DS-17-031 Discuss Impact Fees
 
Constraints Identification; Routing Analysis Using FME
Constraints Identification; Routing Analysis Using FMEConstraints Identification; Routing Analysis Using FME
Constraints Identification; Routing Analysis Using FME
 
Producing a Perfect PV Fleet Forecast At What Cost?
Producing a Perfect PV Fleet Forecast At What Cost?Producing a Perfect PV Fleet Forecast At What Cost?
Producing a Perfect PV Fleet Forecast At What Cost?
 
MPI Power Project September - Current Overview
MPI Power Project September - Current OverviewMPI Power Project September - Current Overview
MPI Power Project September - Current Overview
 
PCAPP Update 29 May 2013
PCAPP Update 29 May 2013PCAPP Update 29 May 2013
PCAPP Update 29 May 2013
 
Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3
 
Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...
 
Maps Make Sense for Xmas - Jon Hawkins
Maps Make Sense for Xmas - Jon HawkinsMaps Make Sense for Xmas - Jon Hawkins
Maps Make Sense for Xmas - Jon Hawkins
 
DS-16-147 DEAAG Project Update
DS-16-147 DEAAG Project UpdateDS-16-147 DEAAG Project Update
DS-16-147 DEAAG Project Update
 

Similar to PCAPP Update 25 June 2014

May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfSteve Desroches
 
Forecasting Fine Grained Air Quality Based on Big Data
Forecasting Fine Grained Air Quality Based on Big DataForecasting Fine Grained Air Quality Based on Big Data
Forecasting Fine Grained Air Quality Based on Big DataWei-Yuan Chang
 
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...DPrestin1
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Studysaranshshah
 
Get Dr. CV Raman University Review which are Genuine
Get Dr. CV Raman University Review which are GenuineGet Dr. CV Raman University Review which are Genuine
Get Dr. CV Raman University Review which are GenuineDr C.V Raman University
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxNaziaBashar
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projectsEssam Lotffy, PMP®, CCP®
 
Hidden opportunities: managing demand for a more sustainable energy infrastru...
Hidden opportunities: managing demand for a more sustainable energy infrastru...Hidden opportunities: managing demand for a more sustainable energy infrastru...
Hidden opportunities: managing demand for a more sustainable energy infrastru...Buildings Alive
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plantNihar Routray
 

Similar to PCAPP Update 25 June 2014 (20)

PCAPP Update 30 April 2014
PCAPP Update 30 April 2014PCAPP Update 30 April 2014
PCAPP Update 30 April 2014
 
PCAPP Update 30 October 2013
PCAPP Update 30 October 2013PCAPP Update 30 October 2013
PCAPP Update 30 October 2013
 
PCAPP Update 26 February 2014
PCAPP Update 26 February 2014PCAPP Update 26 February 2014
PCAPP Update 26 February 2014
 
May 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdfMay 26 LRSC - Trillium Line Extension.pdf
May 26 LRSC - Trillium Line Extension.pdf
 
Himachal may, 2014
Himachal  may, 2014Himachal  may, 2014
Himachal may, 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Forecasting Fine Grained Air Quality Based on Big Data
Forecasting Fine Grained Air Quality Based on Big DataForecasting Fine Grained Air Quality Based on Big Data
Forecasting Fine Grained Air Quality Based on Big Data
 
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
Manufacturing Flow Time Reduction using Digital Twins and Operations Excellen...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Chhattisgarh
ChhattisgarhChhattisgarh
Chhattisgarh
 
TUNING OF DC MOTOR BY USING PSO & PID
TUNING OF DC MOTOR BY USING PSO & PIDTUNING OF DC MOTOR BY USING PSO & PID
TUNING OF DC MOTOR BY USING PSO & PID
 
CRT/N Introduction - RTKC Milestones
CRT/N  Introduction - RTKC MilestonesCRT/N  Introduction - RTKC Milestones
CRT/N Introduction - RTKC Milestones
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
 
The Pueblo Plant: A Year in Review 2013
The Pueblo Plant: A Year in Review 2013The Pueblo Plant: A Year in Review 2013
The Pueblo Plant: A Year in Review 2013
 
Get Dr. CV Raman University Review which are Genuine
Get Dr. CV Raman University Review which are GenuineGet Dr. CV Raman University Review which are Genuine
Get Dr. CV Raman University Review which are Genuine
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptx
 
Cgwb
CgwbCgwb
Cgwb
 
Controling productivity in construction projects
Controling productivity in construction projectsControling productivity in construction projects
Controling productivity in construction projects
 
Hidden opportunities: managing demand for a more sustainable energy infrastru...
Hidden opportunities: managing demand for a more sustainable energy infrastru...Hidden opportunities: managing demand for a more sustainable energy infrastru...
Hidden opportunities: managing demand for a more sustainable energy infrastru...
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plant
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 
Economic Development Working Group Update
Economic Development Working Group UpdateEconomic Development Working Group Update
Economic Development Working Group Update
 
Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012Blue Grass Chemical Activity Update 12 September 2012
Blue Grass Chemical Activity Update 12 September 2012
 

Recently uploaded

World Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - IntroductionWorld Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - IntroductionChristina Parmionova
 
Tennessee DOT- TEVI Plan coordination & EV
Tennessee DOT- TEVI Plan coordination & EVTennessee DOT- TEVI Plan coordination & EV
Tennessee DOT- TEVI Plan coordination & EVRPO America
 
Topical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsxTopical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsxAnbr Cama
 
Harbin-Gross-Spring2022.pdf Yale Historical Review
Harbin-Gross-Spring2022.pdf Yale Historical ReviewHarbin-Gross-Spring2022.pdf Yale Historical Review
Harbin-Gross-Spring2022.pdf Yale Historical Reviewyalehistoricalreview
 
International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.Christina Parmionova
 
IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024Energy for One World
 
Securing the Future | Public Good App House
Securing the Future | Public Good App HouseSecuring the Future | Public Good App House
Securing the Future | Public Good App HouseTechSoup
 
Finland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspectiveFinland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspectiveKristian Wahlbeck
 
Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438ahcitycouncil
 
Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...Christina Parmionova
 
WhenWomenTakeControl.pdf Yale Historical Review
WhenWomenTakeControl.pdf Yale Historical ReviewWhenWomenTakeControl.pdf Yale Historical Review
WhenWomenTakeControl.pdf Yale Historical Reviewyalehistoricalreview
 
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...VICTOR MAESTRE RAMIREZ
 
Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.Christina Parmionova
 
Item # 9- 2nd Qtr Financial & Inv. Report
Item # 9- 2nd Qtr Financial & Inv. ReportItem # 9- 2nd Qtr Financial & Inv. Report
Item # 9- 2nd Qtr Financial & Inv. Reportahcitycouncil
 
PPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. ReportPPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. Reportahcitycouncil
 
Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...ResolutionFoundation
 
PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438ahcitycouncil
 
Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.Christina Parmionova
 
Plant health, safe trade and digital technology.
Plant health, safe trade and digital technology.Plant health, safe trade and digital technology.
Plant health, safe trade and digital technology.Christina Parmionova
 
Electric vehicle infrastructure in rural areas
Electric vehicle infrastructure in rural areasElectric vehicle infrastructure in rural areas
Electric vehicle infrastructure in rural areasRPO America
 

Recently uploaded (20)

World Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - IntroductionWorld Wildlife Crime Report 2024 - Introduction
World Wildlife Crime Report 2024 - Introduction
 
Tennessee DOT- TEVI Plan coordination & EV
Tennessee DOT- TEVI Plan coordination & EVTennessee DOT- TEVI Plan coordination & EV
Tennessee DOT- TEVI Plan coordination & EV
 
Topical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsxTopical Guide for RID 3830 Public Image Training Series.ppsx
Topical Guide for RID 3830 Public Image Training Series.ppsx
 
Harbin-Gross-Spring2022.pdf Yale Historical Review
Harbin-Gross-Spring2022.pdf Yale Historical ReviewHarbin-Gross-Spring2022.pdf Yale Historical Review
Harbin-Gross-Spring2022.pdf Yale Historical Review
 
International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.
 
IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024
 
Securing the Future | Public Good App House
Securing the Future | Public Good App HouseSecuring the Future | Public Good App House
Securing the Future | Public Good App House
 
Finland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspectiveFinland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspective
 
Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438Item # 7-8 - 6900 Broadway P&Z Case # 438
Item # 7-8 - 6900 Broadway P&Z Case # 438
 
Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...Value, protect, respect and invest in our nuses for a sustainable future for ...
Value, protect, respect and invest in our nuses for a sustainable future for ...
 
WhenWomenTakeControl.pdf Yale Historical Review
WhenWomenTakeControl.pdf Yale Historical ReviewWhenWomenTakeControl.pdf Yale Historical Review
WhenWomenTakeControl.pdf Yale Historical Review
 
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
Introduction to The Guidelines for the Long-term Sustainability of Outer Spac...
 
Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.Our nurses, our future. The economic power of care.
Our nurses, our future. The economic power of care.
 
Item # 9- 2nd Qtr Financial & Inv. Report
Item # 9- 2nd Qtr Financial & Inv. ReportItem # 9- 2nd Qtr Financial & Inv. Report
Item # 9- 2nd Qtr Financial & Inv. Report
 
PPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. ReportPPT Item # 9 2ndQTR Financial & Inv. Report
PPT Item # 9 2ndQTR Financial & Inv. Report
 
Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...
 
PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438PPT Item # 7&8 6900 Broadway P&Z Case # 438
PPT Item # 7&8 6900 Broadway P&Z Case # 438
 
Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.Characterizing wildlife trafficking and associated crime.
Characterizing wildlife trafficking and associated crime.
 
Plant health, safe trade and digital technology.
Plant health, safe trade and digital technology.Plant health, safe trade and digital technology.
Plant health, safe trade and digital technology.
 
Electric vehicle infrastructure in rural areas
Electric vehicle infrastructure in rural areasElectric vehicle infrastructure in rural areas
Electric vehicle infrastructure in rural areas
 

PCAPP Update 25 June 2014

  • 2. Safety As of May 31, 2014 PCAPP staff has accomplished:  765 Safe Work Days  4,307, 831 Safe Work Hours  VPP Application Submitted 2
  • 3. Staffing – 1,034 employees 3  Bechtel Pueblo Team non-manual: 973 Pueblo –260 Pueblo County hires – 53 Colorado hires –660 From Other Locations  Construction Workers: 61 –Bechtel direct-hire – 28 –Subcontractor personnel – 33
  • 4. Staffing Update Pueblo County Recruiting Efforts: June 24- Colorado Technical University – Career Fair (Colorado Springs) July 8th- Resume Writing Workshop #3, Pueblo Workforce Center Hires v. Vacancies Pueblo County Applicants v. Hires PCAPP Staffing Actuals 0 20 40 60 80 100 New Hires Pueblo County New Hires from Colorado New Hires from Other (Includes Transfers) Positions Filled Note: Bechtel had 23 Interns start on June 2nd – of the 23, 4 interns were local hires 0 10 20 30 40 50 60 70 80 90 100 Filled Positions Filled Positions containing Pueblo County Applicants Pueblo County New Hires Note: Bechtel had 23 Interns start on June 2nd – of the 23, 4 interns were local hires 0 200 400 600 800 1000 1200 1400 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 StartOps Medical Maintenance Ops Support Operations Laboratory Other Actuals 1168 4
  • 5. Summer Interns Begin Work 5 Touring the site are 24 interns who started on June 2. Four interns attend Colorado State University (CSU), CSU-Pueblo, University of Colorado, University of Northern Colorado.
  • 6. Recruiting Efforts 6 Above, a local resident attends a Resume Writing Workshop in April. The next one is scheduled for July 8 at the Pueblo Workforce Center.
  • 7. PCAPP SYSTEMIZATION - 55% COMPLETE APB 67% ERB 66% BTA 59% As of May 2014 System Complete UTILITIES 86% HVAC 82% FACILITIES 82% 7 FOR OFFICIAL USE ONLY
  • 8. Mar May Jul Sep Nov Jan 2015 Mar May Jul Sep 8 - Baseline 2014 Mar May Jul Sep Nov Jan 2015 Mar May Jul Sep 2015 120 days HVAC Test & Balance 24 March 2014 - 21 July 2014 56 days ERB Provisional Ops 30 September 2014 - 24 November 2014 28 days Yard Provisional Ops 17 July 2014 - 13 August 2014 56 days APB Provisional Ops 25 November 2014 - 19 January 2015 21 days Integrated SYS Testing 20 January 2015 - 9 February 2015 30 days Final HVAC 10 February 2015 - 11 March 2015 105 days Optimization 12 March 2015 - 24 June 2015 56 days BTA Provisional Ops 19 November 2014 - 13 January 2015 14 days IOD 25 June 2015 - 8 July 2015 14 days Fix Cat 1 Findings 9 July 2015 - 22 July 2015 60 days Endorsement 23 July 2015 – 20 September 2015 START 21 September 2015 Systemization Schedule Overview FOR OFFICIAL USE ONLY
  • 9. IAO ORR Status ORR work is paced by Systemization work. Data as of 18-June-2014 ORR Documents Total Required Issued for Completion Board Reviewed Board Accepted Affidavits 386 240 68 44 CRADS 386 26 0 0 9
  • 10. Munitions Service Magazines 10 Operators test for forklift operations and munitions movement in one of the Munitions Service Magazines. Testing will determine storage amounts and capabilities.
  • 11. Agent Processing Building 11 Operations staff will take hydrolysate samples from this glovebox. Treaty inspectors will ensure that the mustard agent has been destroyed according to treaty standards.
  • 12. Enhanced Reconfiguration Building 12 Workers are preparing for a System Demonstration Plan for the Explosion Containment Rooms. As a result, the feed conveyor, pictured above, which is part of the Projectile Mortar Disassembly system, will be turned over to Operations to begin the Optimization phase of the process.
  • 13. BSII Executive Visit 13 Bechtel Systems and Infrastructure, Inc. President Craig Albert recently took a tour of the PCAPP facility. Startup Specialist Bill Baugh explains the systemization process for the Munitions Treatment Unit.
  • 14. PCAPP Teams Walk for A Cause 14 More than $6,200 was raised for the American Cancer Society’s Relay for Life on June 6. A total of 34 employees formed three teams to walk.
  • 16. Change House Environmental Enclosure #1 Environmental Enclosure #3 Laboratory PCAPP EDS Site Overview 16
  • 17. PCAPP EDS Safety As of May 31, the PCAPP EDS project staff has accomplished:  70 Safe Work Days  8,037 Safe Work Hours 17 On the level. Bricks and boards and plenty of patience make each module both horizontal and (as needed) parallel with its mate as units are installed on site.
  • 18. PCAPP EDS Construction Staffing –41 employees  Construction  Workers: 8 –Subcontractor personnel – 33 An electrician measures a metal support beam for an electrical control panel that will supply power to an Environmental Enclosure. 18
  • 19. NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone DESIGN START (DEC 2013) SITE DESIGN COMPLETE (MAR 2014) CONSTRUCTION STARTS (27 MAR 2014) CONSTRUCTION COMPLETE (OCT 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) CONSTRUCTION CONTRACT AWARD (NOV 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) PCAPP EDS Schedule (JPME-P Working Schedule) CONCRETE POURS BEGIN (17 APR 2014) MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.) BEGIN TO ARRIVE (29 MAY 2014) MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL ENCLOSURES ARRIVE (JUN 2014) ARRIVAL OF FIRST EDS UNIT (AUG 2014) 19
  • 20. PCAPP EDS Permitting Progress NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013) STATE APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (7 MAR 2014) SITE CONSTRUCTION START (27MAR 2014) APPROVAL OF CLASS III MODIFICATION FOR OPERATIONS (SEP 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) PCD RCRA PERMIT RENEWED (JAN 2014) SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) APPROVAL OF CD FOR OPERATIONS (OCT 2014) COUNTY APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (26 MAR 2014) RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013) 20
  • 21. Site Progress 21 Before. These four sections were among the first modules to arrive May 29, signaling the start of vertical construction and changing the look of the PCAPP EDS site.
  • 22. Site Progress 22 After. Seamed together, the separate units join as one structure that will comprise the PCAPP EDS Command Post. Other units now arrived and installed include the Change House and Treaty Trailer. The Entry Control Facility and Dilute Laboratory are close behind.
  • 23. Site Progress 23 The first of the two Environ- mental Enclosures that will house the PCAPP EDS units arrived on June 19. Within three days, the metal super- structure was up and fabric pulled tight over the frame.
  • 24. Site Progress 24 EDS just became a bit more real for PCAPP workers, who can now see the first Environmental Enclosure (inset above) from the PSB parking lot.