Project mgmt set up of cement plant

4,653 views

Published on

Published in: Business, Technology
  • Be the first to comment

Project mgmt set up of cement plant

  1. 1. Set up of Cement plantforBUNIYAD Cement Limited.Thumdi, Surat (Gujarat)<br />Team Members :<br />Abhishek Saxena (BLP012)<br />NiharRoutray (BLP022)<br />Abhishek Kumar (BLP038)<br />Shankar Narayan (BLP039)<br />Kushal Prakash (BLP061)<br />
  2. 2. Brief Introduction<br /><ul><li>Setting up of ClinkerisationPlant LM 63.3+3C based on dry process and Vertical Roller Mill (VRM) technology.
  3. 3. All units in the upstream and downstream of the VRM will be designed for an installed cement production capacity of 270/303(OPC/PPC) tph.
  4. 4. The total annual output of cement will be about 3.3 mtpa(average of 300 working days basis)</li></li></ul><li>Project Goals<br /><ul><li>Installation and commission of VRM LM 63.3+3C for BUNIYAD cements Ltd.
  5. 5. Follow best practices in procurement, supplies, services and logistics.
  6. 6. Ensure employee and client satisfaction.
  7. 7. Train the employees of BUNIYAD cements Ltd</li></li></ul><li> Scope of Work<br /><ul><li> Engineering work of Loesche mills
  8. 8. Procurement and delivery of all the equipments
  9. 9. Supervision of installation and commissioning activities
  10. 10. Verification of all statutory documents and NOC</li></li></ul><li>Project Plan<br /><ul><li>Statement of Work
  11. 11. Roles and Responsibilities
  12. 12. Work breakdown structure
  13. 13. Project Schedule
  14. 14. Communication Plan</li></li></ul><li>Statement of Work<br />To setup, test and commission major and auxiliary assemblies of Cement Plant<br />
  15. 15. Roles and Responsibilities<br />
  16. 16. Work Breakdown Structure<br /><ul><li> The complete project has been divided into 26 major tasks .
  17. 17. These tasks have been further divided into subtasks.</li></li></ul><li>ProjectSchedule<br />Start Date - 10th February, 2011<br />End Date - 20th October, 2011<br />Major Project Milestone<br /> <br /><ul><li>Supply of all materials and auxiliaries 06-Jan-2011
  18. 18. Startup of civil work 14- Feb-2011
  19. 19. Startup of installation 15-Mar-2011
  20. 20. Commissioning both hot and cold 10-Oct-2011
  21. 21. Quality Check 11-Oct-2011</li></li></ul><li>Communication Plan<br />
  22. 22. Execution<br /><ul><li> Process Flow
  23. 23. Installation
  24. 24. Commissioning</li></ul> Cold Commissioning<br /> Hot Commissioning<br /> Quality Control<br /><ul><li> Maintenance
  25. 25. Manage people & Resources
  26. 26. Scope Creep
  27. 27. Hold meetings</li></li></ul><li>Monitoring and Controlling<br /><ul><li>Measure Performance
  28. 28. Create forecasts
  29. 29. Perform Quality Control
  30. 30. Perform Risk Audits</li></li></ul><li>Project Closure<br /><ul><li>Gain formal acceptance
  31. 31. Complete final performance report
  32. 32. Update Lessons learnt and Knowledge acquired during the project
  33. 33. Release resources</li></li></ul><li>Exhibit<br />