2. Safety
As of March 31, 2014
PCAPP staff has accomplished:
704 Safe Work Days
3,870,185 Safe Work Hours
VPP Application Submitted
2
3. Staffing – 1,002 employees
3
Bechtel Pueblo Team
non-manual: 908
Pueblo
–211 Pueblo County hires
– 56 Colorado hires
–641 From Other Locations
Construction Workers:
94
–Bechtel direct-hire – 60
–Subcontractor
personnel – 34
4. PCAPP Staffing
Pueblo County Recruiting Efforts:
April 9
Pueblo Community College –
Career Fair
April 15
Resume Writing Workshop #2 –
Workforce Center
Hires v. Vacancies Pueblo County Applicants v. Hires
PCAPP Staffing Actuals
0
10
20
30
40
50
New Hires Pueblo
County
New Hires from
Colorado
New Hires from Other
(Includes Transfers)
Positions Filled
0
5
10
15
20
25
30
35
40
45
Sept Oct Nov De Jan Feb
Filled Positions
Filled Positions
containing Pueblo
County Applicants
Pueblo County New
Hires
758
781
814
862
868
911
946
987
1014
0
200
400
600
800
1000
1200
Jul-13
Aug-13
Sep-13
Oct-13
Nov-13
Dec-13
Jan-14
Feb-14
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
Jul-15
Aug-15
Sep-15
StartOps
Medical
Maintenance
Ops Support
Operations
Laboratory
Other
Actuals
4
5. Recruiting Efforts
5
Third-in-a-Series. This ad, which ran March 3-
10, features ordnance tech positions.
A total of 15 local job seekers attended the
Resume Writing Workshop on April 15.
6. Supporting Sustained Operations
Investing in our Personnel
Providing accountability/leadership
training as an extension of project
focus on performance excellence
Training includes four leadership
focus areas
• Accountability/Human Performance
Initiative at PCAPP - everyone plays a part
in mission success, 704 complete
• PCAPP Leadership Skills – Supervisor’s role
in effectively leading, 168 Supervisors (14
groups) complete
• Leadership Exploration and Development –
Introduce leadership skills and discuss their
role as influencers, begins in May
• Applied Leadership Skills – Managers role
as leaders and development of future
leaders, summer 2014
6
7. Minor work scope remains; none on critical path
• Completion of task 5 heat trace scope
• Completion of fire protection and detection equipment installation
• Installation of demilitarization protective ensemble (DPE) radio system
• Installation of the secured site-wide radio system
• Catenary wiring (site lightning protection)
Much of the remaining work scope is administrative
• Acceptance of the turnover packages
• Submission of Facility Construction Certification (FCC) packages
Construction workforce scheduled to demobilize ~June
Construction is Out of the Way
7
8. PCAPP Systemization - 52% Complete
8
APB 65%
ERB 57%
BTA 55%
As of March 2014
System Complete
UTILITIES 85%
HVAC 82%
FACILITIES 81%
9. Mar May Jul Sep Nov Jan 2015 Mar May Jul Sep
Systemization Schedule Overview
9
2014 Jun Aug Oct Dec
Feb
2015
Apr Jun Aug 2015
116 days
HVAC Test &
Balance
11 June 2014 - 4 October 2014
47 days
ERB Provisional Ops 10 October 2014 - 25 November 2014
28 days
Yard Provisional Ops 08 November 2014 - 05 December 2014
56 days
APB Provisional Ops 26 November 2014 - 20 January 2015
21 days
Integrated SYS Testing 24 January 2015 - 13 February 2015
30 days
Final HVAC 14 February 2015 - 15 March 2015
105 days
Optimization 16 March 2015 - 28 June 2015
56 days
BTA Provisional Ops 26 March 2015 - 20 May 2015
14 days
IOD 29 June 2015 - 12 July 2015
14 days
Fix Cat 1 Findings 13 July 2015 - 26 July 2015
60 days
Endorsement
27 July 2015 –
24 September 2015
START 24 September 2015
10. Training Facility
10
Toxic Area Training has begun at the Training Facility. Games
and puzzles are used to familiarize students with the dexterity,
vision, ergonomic and communication limitations associated
with working in Demilitarization Protective Ensemble suits.
11. Enhanced Reconfiguration Building
11
In the Parts Monitoring Enclosure room, workers
inspect the bursters and lugs that were removed from
ACWA Test Equipment.
12. Agent Processing Building
12
Going through systemization testing is the Munitions Washout
System. The testing process will make sure everything is aligned
with the Control Room and the systems “talk” to each other.
13. Weisbrod Family Fun Day
13
This Bechtel Pueblo Team-sponsored event attracted hundreds
of youngsters to the Weisbrod Aircraft Museum on their last day
of Spring Break to learn more about science, technology,
engineering and mathematics.
14. Walk A Mile In Her Shoes
14
PCAPP Employees spearheaded this Bechtel Pueblo Team-
sponsored event on April 12 to raise money for Pueblo Rape
Crisis Services. More than $3,400 was raised!
15. April 2014 Construction Update
15
This pre-construction photo of the PCAPP EDS site between the two igloos
was taken March 20, 2014. Just beyond it you can see the construction
trailer and the rough work that had already started on the parking area that
will serve the site.
16. April 2014 Construction Update
16
That same patch of ground on April 22 showed significant progress. Since
construction began on March 27, the three pads, two of which will be home to
the Environmental Enclosures that will house the EDS units, are already
graded with concrete foundations poured, putting the site on track for
completion later this summer.
18. PCAPP EDS Site Overview
18
Change House
Environmental
Enclosure #1
Environmental
Enclosure #3
Laboratory
19. PCAPP EDS Safety
As of March 31, the
PCAPP EDS project staff
has accomplished:
15 Safe Work Days
755 Safe Work Hours
19
Workers smooth concrete after the
first pour on the site on April 17th.
This effort helped lay the foundation
for Environmental Enclosure #1.
20. PCAPP EDS Construction
Staffing –17 employees
20
Construction
Workers: 6
–Subcontractor
personnel – 11
A worker measures lumber before cutting.
The board will become part of the forms
being built for the concrete pour set for
Environmental Enclosure #3
21. NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
DESIGN START (DEC 2013)
SITE DESIGN COMPLETE (MAR 2014)
CONSTRUCTION START (27 MAR 2014)
CONSTRUCTION COMPLETE (AUGUST 2014)
E-DAY – EDS START OF
AGENT OPERATIONS (OCT 2014)
CONSTRUCTION CONTRACT AWARD (NOV 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
PCAPP EDS Schedule
(JPME Working Schedule)
21
22. PCAPP EDS Permitting Progress
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)
STATE APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (7 MAR 2014)
SITE CONSTRUCTION START (27MAR 2014)
APPROVAL OF CLASS III MODIFICATION
FOR OPERATIONS (AUG 2014)
E-DAY – EDS START OF AGENT
OPERATIONS (OCT 2014)
PCD RCRA PERMIT RENEWED (JAN 2014)
SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
APPROVAL OF CD FOR OPERATIONS (TBD)
22
COUNTY APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (26 MAR 2014)
RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)
23. Site Progress
23
Elsewhere,
PCAPP EDS
construction
workers braved
wind gusts of
up to 50 miles
per hour while
working to cut a
crossover road
The road, seen here three days after work began, will serve to
reroute vehicles from H11 and H10 Street after actual site
construction closes the road to through traffic.
24. EDS Community Outreach
24
Working to keep stakeholders informed, PCAPP Site Project Manager Bruce
Huenefeld met with the Board of Directors for the Pueblo City-County Health
Department on April 23 to both brief and answer questions on the PCAPP
EDS System. Huenefeld looks forward to doing the same for Health
Department staff later this summer .