SlideShare a Scribd company logo
1 of 30
Download to read offline
https://msmemon.wordpress.com/scmlab/
Replacement Models
and
Maintenance Analysis
Dr. M. S. Memon
Department of Industrial Engineering & Management
Mehran University of Engineering & Technology,
Jamshoro, Pakistan
• Organizations providing goods/services use several facilities like equipment
and machinery which are directly required in their operations.
• In addition to these facilities, there are several other items which are
necessary to facilitate the functioning of organizations.
• All such facilities should be continuously monitored for their efficient
functioning; otherwise, the quality of service will be poor. Besides the
quality of service of the facilities, the cost of their operation and
maintenance would increase with the passage of time.
• Hence, it is an absolute necessity to maintain the equipment in good
operating conditions with economical cost.
• Thus, we need an integrated approach to minimize the cost of maintenance.
In certain cases, the equipment will be obsolete over a period of time.
INTRODUCTION
• If a firm wants to be in the same business competitively, it has
to take decision on whether to replace the old equipment or to
retain it by taking the cost of maintenance and operation into
account.
• There are two basic reasons for considering the replacement of
an equipment—physical impairment of the various parts or
obsolescence of the equipment.
INTRODUCTION
• Sometimes, the capacity of existing facilities may be inadequate
to meet the current demand. Under such situation, the following
alternatives will be considered.
– Replacement of the existing equipment with a new one.
– Augmenting the existing one with an additional equipment.
INTRODUCTION
• Maintenance activity can be classified into two types:
preventive maintenance and breakdown maintenance.
– Preventive maintenance (PM) is the periodical inspection and service
activities which are aimed to detect potential failures and perform
minor adjustments or repairs which will prevent major operating
problems in future.
– Breakdown maintenance is the repair which is generally done after the
equipment has attained down state. It is often of an emergency nature
which will have associated penalty in terms of expediting cost of
maintenance and down time cost of equipment.
TYPES OF MAINTENANCE
• Preventive maintenance will reduce such cost up to a point. Beyond
that point, the cost of preventive maintenance will be more when
compared to the breakdown maintenance cost.
• The total cost, which is the sum of the preventive maintenance cost
and the breakdown maintenance cost, will go on decreasing with an
increase in the level of maintenance up to a point.
• Beyond that point, the total cost will start increasing.
• The level of maintenance corresponding to the minimum total cost
is the optimal level of maintenance.
• The concepts are demonstrated in Fig. 8.1.
TYPES OF MAINTENANCE
TYPES OF MAINTENANCE
• Replacement study can be classified into two categories:
a) Replacement of assets that deteriorate with time (Replacement due to
gradual failure, or wear and tear of the components of the machines).
• This can be further classified into the following types:
i. Determination of economic life of an asset.
ii. Replacement of an existing asset with a new asset.
b) Simple probabilistic model for assets which fail completely
(replacement due to sudden failure).
TYPES OF REPLACEMENT PROBLEM
• Any asset will have the following cost components:
– Capital recovery cost (average first cost), computed from the first
cost (purchase price) of the machine.
– Average operating and maintenance cost (O & M cost)
– Total cost which is the sum of capital recovery cost (average first
cost) and average maintenance cost.
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
• From Fig. it is clear that the capital recovery cost (average first
cost) goes on decreasing with the life of the machine and the
average operating and maintenance cost goes on increasing with the
life of the machine.
• From the beginning, the total cost continues to decrease up to a
particular life and then it starts increasing.
• The point where the total cost is minimum is called the economic
life of the machine.
• If the interest rate is more than zero per cent, then we use interest
formulas to determine the economic life.
• A firm is considering replacement of an equipment, whose first
cost is Rs. 4,000 and the scrap value is negligible at the end of
any year.
• Based on experience, it was found that the maintenance cost is
zero during the first year and it increases by Rs. 200 every year
thereafter.
a) When should the equipment be replaced if i = 0%?
b) When should the equipment be replaced if i = 12%?
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
• The following table gives the operation cost, maintenance cost and salvage value
at the end of every year of a machine whose purchase value is Rs. 20,000.
• Find the economic life of the machine assuming interest rate, i = 15%.
EXAMPLE 8.2
EXAMPLE 8.2
EXAMPLE 8.2
EXAMPLE 8.2
• In this section, the concept of comparison of replacement of an
existing asset with a new asset is presented.
• In this analysis, the annual equivalent cost of each alternative
should be computed first.
• Then the alternative which has the least cost should be selected
as the best alternative. Before discussing details, some
preliminary concepts which are essential for this type of
replacement analysis are presented.
REPLACEMENT OF EXISTING ASSET WITH A NEW ASSET
Capital Recovery with Return
Capital Recovery with Return
• If an existing equipment is considered for replacement with a new
equipment, then the existing equipment is known as the defender and the
new equipment is known as challenger.
• Assume that an equipment has been purchased about three years back for
Rs. 5,00,000 and it is considered for replacement with a new equipment.
The supplier of the new equipment will take the old one for some money,
say, Rs. 3,00,000.
• This should be treated as the present value of the existing Equipment and it
should be considered for all further economic analysis. The purchase value
of the existing equipment before three years is now known as sunk cost, and
it should not be considered for further analysis.
Concept of Challenger and Defender
• Two years ago, a machine was purchased at a cost of Rs.
2,00,000 to be useful for eight years. Its salvage value at the
end of its life is Rs. 25,000. The annual maintenance cost is Rs.
25,000. The market value of the present machine is Rs.
1,20,000. Now, a new machine to cater to the need of the
present machine is available at Rs. 1,50,000 to be useful for six
years. Its annual maintenance cost is Rs. 14,000. The salvage
value of the new machine is Rs. 20,000. Using an interest rate
of 12%, find whether it is worth replacing the present machine
with the new machine.
EXAMPLE 8.3
EXAMPLE 8.3
• The cash flow diagram of the present machine is illustrated in
Fig. 8.4. The annual maintenance cost for the preceding periods
are not shown in this figure.
EXAMPLE 8.3
EXAMPLE 8.3
EXAMPLE 8.3
• A diesel engine was installed 10 years ago at a cost of Rs. 50,000. It has a
present realizable market value of Rs. 15,000.
• If kept, it can be expected to last five years more, with operating and
maintenance cost of Rs. 14,000 per year and to have a salvage value of Rs.
8,000 at the end of the fifth year. This engine can be replaced with an
improved version costing Rs. 65,000 which has an expected life of 20
years.
• This improved version will have an estimated annual operating and
maintenance cost of Rs. 9,000 and ultimate salvage value of Rs. 13,000.
• Using an interest rate of 15%, make an annual equivalent cost analysis to
determine whether to keep or replace the old engine.
EXAMPLE 8.4

More Related Content

What's hot

Replacement Theory
Replacement TheoryReplacement Theory
Replacement TheoryNilam Kabra
 
Machine hour reate
Machine hour reateMachine hour reate
Machine hour reateJoseph Mary
 
Chapter 8 The Procurement of Equipment
Chapter 8 The Procurement of EquipmentChapter 8 The Procurement of Equipment
Chapter 8 The Procurement of EquipmentTran Thang
 
Elementary Economic Analysis
Elementary Economic AnalysisElementary Economic Analysis
Elementary Economic AnalysisPrabu U
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering EconomicsP Manimaran
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTConstruction Mechanizer
 
Replacement theory
Replacement theoryReplacement theory
Replacement theorySAI SANTHOSH
 
Concept of Efficiency- Engineering Economics
Concept of Efficiency- Engineering Economics Concept of Efficiency- Engineering Economics
Concept of Efficiency- Engineering Economics Dr Naim R Kidwai
 
Economic analysis
Economic analysis Economic analysis
Economic analysis SharyuMahale
 
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisSadegh Tabatabaei
 
COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)Archit Aditya
 
Life cycle cost example
Life cycle cost exampleLife cycle cost example
Life cycle cost exampleHuzaifa Sajid
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Shail Nakum
 

What's hot (19)

Replacement Theory
Replacement TheoryReplacement Theory
Replacement Theory
 
Machine hour reate
Machine hour reateMachine hour reate
Machine hour reate
 
Replacement
ReplacementReplacement
Replacement
 
Chapter 8 The Procurement of Equipment
Chapter 8 The Procurement of EquipmentChapter 8 The Procurement of Equipment
Chapter 8 The Procurement of Equipment
 
Elementary Economic Analysis
Elementary Economic AnalysisElementary Economic Analysis
Elementary Economic Analysis
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering Economics
 
Choosing a Vehicle
Choosing a VehicleChoosing a Vehicle
Choosing a Vehicle
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
 
Costcurves
CostcurvesCostcurves
Costcurves
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
Concept of Efficiency- Engineering Economics
Concept of Efficiency- Engineering Economics Concept of Efficiency- Engineering Economics
Concept of Efficiency- Engineering Economics
 
Economic analysis
Economic analysis Economic analysis
Economic analysis
 
A Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost AnalysisA Model for Life-Cycle Benefit and Cost Analysis
A Model for Life-Cycle Benefit and Cost Analysis
 
Engineering economics and finance
Engineering economics and financeEngineering economics and finance
Engineering economics and finance
 
COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)
 
Vision of construction mechanizer
Vision of construction mechanizerVision of construction mechanizer
Vision of construction mechanizer
 
Life cycle cost example
Life cycle cost exampleLife cycle cost example
Life cycle cost example
 
Total cost of ownership1
Total cost of ownership1Total cost of ownership1
Total cost of ownership1
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)
 

Similar to Chap5 engeco

Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysisAhsanKhan837024
 
MG6863-Unit-4.pdf
MG6863-Unit-4.pdfMG6863-Unit-4.pdf
MG6863-Unit-4.pdfnallak1
 
Replacement and Maintenance Analysis
Replacement and Maintenance AnalysisReplacement and Maintenance Analysis
Replacement and Maintenance AnalysisPrabu U
 
Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Balamurugan Subburaj
 
Replacement Analysis Outsiders and Insiders.pptx
Replacement Analysis Outsiders and Insiders.pptxReplacement Analysis Outsiders and Insiders.pptx
Replacement Analysis Outsiders and Insiders.pptxAthar739197
 
maintanancemanagement-140709234319-phpapp02.pptx
maintanancemanagement-140709234319-phpapp02.pptxmaintanancemanagement-140709234319-phpapp02.pptx
maintanancemanagement-140709234319-phpapp02.pptxJagjotSinghRandhawa
 
Replacement theory
Replacement theoryReplacement theory
Replacement theoryVILAS ADOLE
 
Lecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsLecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsSasiK25
 
Cost calculation of cnc machining operation
Cost calculation of cnc machining operationCost calculation of cnc machining operation
Cost calculation of cnc machining operationAbdul Kader
 
Power plant economics
Power plant economicsPower plant economics
Power plant economicsTarek Erin
 
Replacement theory
Replacement theoryReplacement theory
Replacement theoryR A Shah
 
How to design a machine?
How to design a machine?How to design a machine?
How to design a machine?swargpatel283
 

Similar to Chap5 engeco (20)

Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysis
 
Operations REsearch
Operations REsearchOperations REsearch
Operations REsearch
 
MG6863-Unit-4.pdf
MG6863-Unit-4.pdfMG6863-Unit-4.pdf
MG6863-Unit-4.pdf
 
Replacement and Maintenance Analysis
Replacement and Maintenance AnalysisReplacement and Maintenance Analysis
Replacement and Maintenance Analysis
 
Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863
 
Seminar _5.pptx
Seminar _5.pptxSeminar _5.pptx
Seminar _5.pptx
 
unit-6 (1).pdf
unit-6 (1).pdfunit-6 (1).pdf
unit-6 (1).pdf
 
Replacement Analysis Outsiders and Insiders.pptx
Replacement Analysis Outsiders and Insiders.pptxReplacement Analysis Outsiders and Insiders.pptx
Replacement Analysis Outsiders and Insiders.pptx
 
replacementtheory.pptx
replacementtheory.pptxreplacementtheory.pptx
replacementtheory.pptx
 
maintanancemanagement-140709234319-phpapp02.pptx
maintanancemanagement-140709234319-phpapp02.pptxmaintanancemanagement-140709234319-phpapp02.pptx
maintanancemanagement-140709234319-phpapp02.pptx
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
Lecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsLecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipments
 
Cost calculation of cnc machining operation
Cost calculation of cnc machining operationCost calculation of cnc machining operation
Cost calculation of cnc machining operation
 
Replacement Strategies
Replacement StrategiesReplacement Strategies
Replacement Strategies
 
Power plant economics
Power plant economicsPower plant economics
Power plant economics
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Energy management
Energy managementEnergy management
Energy management
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
How to design a machine?
How to design a machine?How to design a machine?
How to design a machine?
 

More from abidiqbal55

Network theorems chapter 9
Network theorems chapter 9Network theorems chapter 9
Network theorems chapter 9abidiqbal55
 
Method of analysis chapter 8
Method of analysis chapter 8Method of analysis chapter 8
Method of analysis chapter 8abidiqbal55
 
Method of analysis chapter 8 final
Method of analysis chapter 8 finalMethod of analysis chapter 8 final
Method of analysis chapter 8 finalabidiqbal55
 
Inductors chapter 11
Inductors chapter 11Inductors chapter 11
Inductors chapter 11abidiqbal55
 
Capacitor chapter 10
Capacitor chapter 10Capacitor chapter 10
Capacitor chapter 10abidiqbal55
 
Ac series parallel chapter 13
Ac series parallel chapter 13Ac series parallel chapter 13
Ac series parallel chapter 13abidiqbal55
 
10 150316005543-conversion-gate01
10 150316005543-conversion-gate0110 150316005543-conversion-gate01
10 150316005543-conversion-gate01abidiqbal55
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01abidiqbal55
 
8 150316005531-conversion-gate01
8 150316005531-conversion-gate018 150316005531-conversion-gate01
8 150316005531-conversion-gate01abidiqbal55
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01abidiqbal55
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01abidiqbal55
 
5moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate015moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate01abidiqbal55
 
5 150316005456-conversion-gate01
5 150316005456-conversion-gate015 150316005456-conversion-gate01
5 150316005456-conversion-gate01abidiqbal55
 
4 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate014 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate01abidiqbal55
 
3 150316005311-conversion-gate01
3 150316005311-conversion-gate013 150316005311-conversion-gate01
3 150316005311-conversion-gate01abidiqbal55
 
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate012 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01abidiqbal55
 
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate011 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate01abidiqbal55
 

More from abidiqbal55 (18)

Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Network theorems chapter 9
Network theorems chapter 9Network theorems chapter 9
Network theorems chapter 9
 
Method of analysis chapter 8
Method of analysis chapter 8Method of analysis chapter 8
Method of analysis chapter 8
 
Method of analysis chapter 8 final
Method of analysis chapter 8 finalMethod of analysis chapter 8 final
Method of analysis chapter 8 final
 
Inductors chapter 11
Inductors chapter 11Inductors chapter 11
Inductors chapter 11
 
Capacitor chapter 10
Capacitor chapter 10Capacitor chapter 10
Capacitor chapter 10
 
Ac series parallel chapter 13
Ac series parallel chapter 13Ac series parallel chapter 13
Ac series parallel chapter 13
 
10 150316005543-conversion-gate01
10 150316005543-conversion-gate0110 150316005543-conversion-gate01
10 150316005543-conversion-gate01
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01
 
8 150316005531-conversion-gate01
8 150316005531-conversion-gate018 150316005531-conversion-gate01
8 150316005531-conversion-gate01
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01
 
5moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate015moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate01
 
5 150316005456-conversion-gate01
5 150316005456-conversion-gate015 150316005456-conversion-gate01
5 150316005456-conversion-gate01
 
4 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate014 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate01
 
3 150316005311-conversion-gate01
3 150316005311-conversion-gate013 150316005311-conversion-gate01
3 150316005311-conversion-gate01
 
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate012 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
 
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate011 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
 

Recently uploaded

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Chap5 engeco

  • 1. https://msmemon.wordpress.com/scmlab/ Replacement Models and Maintenance Analysis Dr. M. S. Memon Department of Industrial Engineering & Management Mehran University of Engineering & Technology, Jamshoro, Pakistan
  • 2. • Organizations providing goods/services use several facilities like equipment and machinery which are directly required in their operations. • In addition to these facilities, there are several other items which are necessary to facilitate the functioning of organizations. • All such facilities should be continuously monitored for their efficient functioning; otherwise, the quality of service will be poor. Besides the quality of service of the facilities, the cost of their operation and maintenance would increase with the passage of time. • Hence, it is an absolute necessity to maintain the equipment in good operating conditions with economical cost. • Thus, we need an integrated approach to minimize the cost of maintenance. In certain cases, the equipment will be obsolete over a period of time. INTRODUCTION
  • 3. • If a firm wants to be in the same business competitively, it has to take decision on whether to replace the old equipment or to retain it by taking the cost of maintenance and operation into account. • There are two basic reasons for considering the replacement of an equipment—physical impairment of the various parts or obsolescence of the equipment. INTRODUCTION
  • 4. • Sometimes, the capacity of existing facilities may be inadequate to meet the current demand. Under such situation, the following alternatives will be considered. – Replacement of the existing equipment with a new one. – Augmenting the existing one with an additional equipment. INTRODUCTION
  • 5. • Maintenance activity can be classified into two types: preventive maintenance and breakdown maintenance. – Preventive maintenance (PM) is the periodical inspection and service activities which are aimed to detect potential failures and perform minor adjustments or repairs which will prevent major operating problems in future. – Breakdown maintenance is the repair which is generally done after the equipment has attained down state. It is often of an emergency nature which will have associated penalty in terms of expediting cost of maintenance and down time cost of equipment. TYPES OF MAINTENANCE
  • 6. • Preventive maintenance will reduce such cost up to a point. Beyond that point, the cost of preventive maintenance will be more when compared to the breakdown maintenance cost. • The total cost, which is the sum of the preventive maintenance cost and the breakdown maintenance cost, will go on decreasing with an increase in the level of maintenance up to a point. • Beyond that point, the total cost will start increasing. • The level of maintenance corresponding to the minimum total cost is the optimal level of maintenance. • The concepts are demonstrated in Fig. 8.1. TYPES OF MAINTENANCE
  • 8. • Replacement study can be classified into two categories: a) Replacement of assets that deteriorate with time (Replacement due to gradual failure, or wear and tear of the components of the machines). • This can be further classified into the following types: i. Determination of economic life of an asset. ii. Replacement of an existing asset with a new asset. b) Simple probabilistic model for assets which fail completely (replacement due to sudden failure). TYPES OF REPLACEMENT PROBLEM
  • 9. • Any asset will have the following cost components: – Capital recovery cost (average first cost), computed from the first cost (purchase price) of the machine. – Average operating and maintenance cost (O & M cost) – Total cost which is the sum of capital recovery cost (average first cost) and average maintenance cost. DETERMINATION OF ECONOMIC LIFE OF AN ASSET
  • 10. DETERMINATION OF ECONOMIC LIFE OF AN ASSET
  • 11. DETERMINATION OF ECONOMIC LIFE OF AN ASSET • From Fig. it is clear that the capital recovery cost (average first cost) goes on decreasing with the life of the machine and the average operating and maintenance cost goes on increasing with the life of the machine. • From the beginning, the total cost continues to decrease up to a particular life and then it starts increasing. • The point where the total cost is minimum is called the economic life of the machine. • If the interest rate is more than zero per cent, then we use interest formulas to determine the economic life.
  • 12. • A firm is considering replacement of an equipment, whose first cost is Rs. 4,000 and the scrap value is negligible at the end of any year. • Based on experience, it was found that the maintenance cost is zero during the first year and it increases by Rs. 200 every year thereafter. a) When should the equipment be replaced if i = 0%? b) When should the equipment be replaced if i = 12%? EXAMPLE 8.1
  • 17. • The following table gives the operation cost, maintenance cost and salvage value at the end of every year of a machine whose purchase value is Rs. 20,000. • Find the economic life of the machine assuming interest rate, i = 15%. EXAMPLE 8.2
  • 21. • In this section, the concept of comparison of replacement of an existing asset with a new asset is presented. • In this analysis, the annual equivalent cost of each alternative should be computed first. • Then the alternative which has the least cost should be selected as the best alternative. Before discussing details, some preliminary concepts which are essential for this type of replacement analysis are presented. REPLACEMENT OF EXISTING ASSET WITH A NEW ASSET
  • 24. • If an existing equipment is considered for replacement with a new equipment, then the existing equipment is known as the defender and the new equipment is known as challenger. • Assume that an equipment has been purchased about three years back for Rs. 5,00,000 and it is considered for replacement with a new equipment. The supplier of the new equipment will take the old one for some money, say, Rs. 3,00,000. • This should be treated as the present value of the existing Equipment and it should be considered for all further economic analysis. The purchase value of the existing equipment before three years is now known as sunk cost, and it should not be considered for further analysis. Concept of Challenger and Defender
  • 25. • Two years ago, a machine was purchased at a cost of Rs. 2,00,000 to be useful for eight years. Its salvage value at the end of its life is Rs. 25,000. The annual maintenance cost is Rs. 25,000. The market value of the present machine is Rs. 1,20,000. Now, a new machine to cater to the need of the present machine is available at Rs. 1,50,000 to be useful for six years. Its annual maintenance cost is Rs. 14,000. The salvage value of the new machine is Rs. 20,000. Using an interest rate of 12%, find whether it is worth replacing the present machine with the new machine. EXAMPLE 8.3
  • 27. • The cash flow diagram of the present machine is illustrated in Fig. 8.4. The annual maintenance cost for the preceding periods are not shown in this figure. EXAMPLE 8.3
  • 30. • A diesel engine was installed 10 years ago at a cost of Rs. 50,000. It has a present realizable market value of Rs. 15,000. • If kept, it can be expected to last five years more, with operating and maintenance cost of Rs. 14,000 per year and to have a salvage value of Rs. 8,000 at the end of the fifth year. This engine can be replaced with an improved version costing Rs. 65,000 which has an expected life of 20 years. • This improved version will have an estimated annual operating and maintenance cost of Rs. 9,000 and ultimate salvage value of Rs. 13,000. • Using an interest rate of 15%, make an annual equivalent cost analysis to determine whether to keep or replace the old engine. EXAMPLE 8.4