SlideShare a Scribd company logo
1 of 12
A Model for Life-Cycle
Benefit and Cost Analysis of
Highway Projects
Amin Zoroufi Sadegh Tabatabaei
Ali Zahedi Rabih Ataya
Aseel Ibsais Xiaoxi Xia
INTRODUCTION
 Economic analysis is a critical component of a project evaluation methodology that considers all
key quantitative and qualitative impacts of highway investments. It allows highway agencies to
identify, quantify, and value the economic benefits and costs of highway projects over a multiyear
timeframe.
 This research was conducted to provide the Indiana Department of Transportation (INDOT) with a
uniform economic analysis methodology.
 As a result of this research, an Excel based computer program, the Indiana Highway Economic
Evaluation Model (IHEEM), was developed to evaluate highway investment projects. The Model
applies the methodology of life-cycle benefit cost analysis to perform economic analysis for
proposed highway projects.
 A probabilistic model was developed in IHEEM to provide an alternative option for economic
analysis in addition to the deterministic model.
IHEEM METHODOLOGY & PARAMETERS
 The commonly applied economic analysis methods for highway projects are based on the estimated mean values of
related parameters. These methods do not consider the uncertainties of the input parameters and therefore are
considered deterministic approaches.
 A probabilistic approach includes uncertainties into the economic analysis process, some of the cost and benefit
items are treated as random variables with estimated statistic characteristics, such as distributions, means, standard
variances and coefficient of variation (CV). Traffic volume and construction cost are the main factors that
significantly affect life-cycle costs and benefits. Therefore, they are treated as random variables.
 Because of the large dispersions of the construction costs, the regression method was applied to establish the
relationship between construction costs and roadway lengths of highway projects.
 Highways are classified as interstate, multilane highway, and two-lane highway.
 Vehicle classification includes three vehicle groups: passenger cars, single unit trucks, and combination trucks.
 Analysis Period is the period of time during which the current and future costs and benefits for the specific project
will be evaluated. The analysis period should be long enough to include the initial construction, routine maintenance
activities, and at least one subsequent rehabilitation activity.
 The discount rate value used by the highway agencies ranges from 3 percent to 5 percent. We use 4% in this case
study.
 The cost-effective performance measures in terms of Net Present Value (NPV) and Benefit Cost Ratio (BCR) are
calculated for the whole analysis period.
IHEEM METHODOLOGY & PARAMETERS
 Internal rate of return (IRR) is the interest rate at which a zero NPV is reached at the end of the analysis
period. An IRR is obtained by changing the interest rate in the economic analysis while other input
items remain unchanged.
 Life-cycle costs and benefits are the sum of all the costs and benefits within the analysis period
expressed in the present value of money.
 The benefits are treated as positive values and the costs are treated as negative values. If the total
values of the sum of all costs and benefits, which is also called the Net Present Value (NPV), are
positive, then the proposed project is economically justified to build. Otherwise, the project is not
economically justified to build.
C o s t B e n e f i t s
Investment Capital Travel time savings
Operating & maintenance Economic development
Preservation costs Improvement in air
quality
IHEEM MODEL FEATURES
 IHEEM model is an Excel based computer software.
 A tool for performing an economic evaluation for highway investment projects by applying the life-
cycle benefit cost analysis.
 The model calculates each module of agency (Public/Private) costs and user (Society) benefits for
each year using specified methods.
 The software includes various modules to process the complicated analysis and calculations. Each
module contains default values, formulas, benefit and cost values, traffic attributes, and highway
conditions. The default values were obtained from the historical data and recognized reliable results.
The software provides the flexibility for users to overwrite the default values.
 For input requirements in IHEEM, users need to collect the basic as well as specific project data
depending on the project type.
IHEEM- SOFTWARE INPUT & OUTPUT
Life-cycle
cost &
benefits in
terms of
NPV
Benefit-
cost ratio
(BCR)
IRR
Itemized
Benefits
• Travel Time Savings
• VOC Savings
• Accidents Cost Savings
(Safety Benefits)
OUTPUT
Basic
assumption
Inputs
• Discount Rate
• Analysis Period
• Area Type (Urban/Rural)
General
Inputs
• Project Cost
• O/M Annual Costs
• Traffic Volume
• Annual Traffic Growth
Rate
• Number of Crashes
• Free Flow Speed
Specific
Inputs
• Pavement IRI
• Highway Length &
width
• Number of Lanes
• Length of Detour
INPUT
IHEEM MODEL FEATURES
 In IHEEM software, there are eight sheets that are interconnected in order to perform the
complicated computation tasks for the economic analysis. The eight sheets are Input, Parameters,
Agency Cost, Travel Time Savings, Vehicle Operating Costs Savings, Crash reduction Savings,
Output Deterministic and Output-Probabilistic.
 The following figure illustrates a typical highway improvement project’s cash flow. The benefit
values are denoted with the upward arrows and the cost values are denoted with the downward
arrows. The benefits and costs in Fig. 6 are in the constant dollar values.
An APPLICATION EXAMPLE
 Highway project improvement.
 3.9-mile section of an interstate highway located in Northern California. The proposed project was
to add two new lanes to the existing eight lanes to increase the traffic capacity of the frequently
congested roadway section.
 The Input information is listed in the following Table:
An APPLICATION EXAMPLE
 With the Input from the previous table, the IHEEM software generates the following economic analysis results:
 The output information indicates that if the project is constructed, the expected NPV is $548.7 million and
the benefit/cost ratio is 4.42 within the 20-year analysis period. Therefore, this proposed improvement
project is economically justified to build.
CONCLUSION
 IHEEM software is a powerful and convenient tool for evaluating highway investment projects.
 Highway agencies make use of measures such as the net present value of costs and benefits,
benefit-cost ratio, or the internal rate of return to compare different competing alternatives. The
alternative that gives the highest net present value, benefit-cost ratio or return on investment is
selected and is placed to be funded, programmed, and eventually implemented.
THANK YOU!!

More Related Content

What's hot

LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGS
LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGSLIFE CYCLE COST CALCULATION MODELS FOR BUILDINGS
LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGSSharan Thampi J
 
Life cycle costing_calculation_tool
Life cycle costing_calculation_toolLife cycle costing_calculation_tool
Life cycle costing_calculation_toolDemid Odkhuu
 
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDING
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDINGLIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDING
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDINGEdge Hill University
 
Life cycle costing
Life cycle costingLife cycle costing
Life cycle costingJessy Chong
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Shail Nakum
 
Types Of Costs (Economics & Management Purpose)
Types Of Costs (Economics & Management Purpose)Types Of Costs (Economics & Management Purpose)
Types Of Costs (Economics & Management Purpose)KHORASIYA DEVANSU
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering EconomicsP Manimaran
 
Life cycle cost example
Life cycle cost exampleLife cycle cost example
Life cycle cost exampleHuzaifa Sajid
 
Cost benefit analysis converted
Cost benefit analysis convertedCost benefit analysis converted
Cost benefit analysis convertedsaheli chakraborty
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.pptAsha A
 
Performance Management - ACCA - F5
Performance Management - ACCA - F5Performance Management - ACCA - F5
Performance Management - ACCA - F5Jessy Chong
 
The basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mbaThe basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mbaBabasab Patil
 

What's hot (20)

Project life cycle costing
Project life cycle costing Project life cycle costing
Project life cycle costing
 
Life cycle costing
Life cycle costingLife cycle costing
Life cycle costing
 
LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGS
LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGSLIFE CYCLE COST CALCULATION MODELS FOR BUILDINGS
LIFE CYCLE COST CALCULATION MODELS FOR BUILDINGS
 
Life cycle costing_calculation_tool
Life cycle costing_calculation_toolLife cycle costing_calculation_tool
Life cycle costing_calculation_tool
 
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDING
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDINGLIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDING
LIFE CYCLE COST (LCC) FOR SUSTAINABLE BUILDING
 
Life cycle costing
Life cycle costingLife cycle costing
Life cycle costing
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)
 
Presentation maintenance (lcc)
Presentation maintenance (lcc)Presentation maintenance (lcc)
Presentation maintenance (lcc)
 
Life cycle costing
Life cycle costingLife cycle costing
Life cycle costing
 
Types Of Costs (Economics & Management Purpose)
Types Of Costs (Economics & Management Purpose)Types Of Costs (Economics & Management Purpose)
Types Of Costs (Economics & Management Purpose)
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 
MG6863 Engineering Economics
MG6863 Engineering EconomicsMG6863 Engineering Economics
MG6863 Engineering Economics
 
Life cycle cost example
Life cycle cost exampleLife cycle cost example
Life cycle cost example
 
Cost benefit analysis converted
Cost benefit analysis convertedCost benefit analysis converted
Cost benefit analysis converted
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
UNIT – I.ppt
UNIT – I.pptUNIT – I.ppt
UNIT – I.ppt
 
Cost concepts and design
Cost concepts and designCost concepts and design
Cost concepts and design
 
Performance Management - ACCA - F5
Performance Management - ACCA - F5Performance Management - ACCA - F5
Performance Management - ACCA - F5
 
The basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mbaThe basics of cost analysis ppt @ mba
The basics of cost analysis ppt @ mba
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 

Similar to A Model for Life-Cycle Benefit and Cost Analysis

Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...IOSR Journals
 
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET Journal
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...IOSR Journals
 
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptxShahidRahman37
 
PAVEMENT DESIGN BY USING GEOTEXTILE
 PAVEMENT DESIGN BY USING GEOTEXTILE  PAVEMENT DESIGN BY USING GEOTEXTILE
PAVEMENT DESIGN BY USING GEOTEXTILE IAEME Publication
 
6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdfTanmay209179
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...IJERA Editor
 
2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptxYogeshShah95
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential BuildingIRJET Journal
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Sok-Tharath CHREUNG
 
CARIFY – Predicting Car Maintenance Costs Using Artificial Intelligence
CARIFY – Predicting Car Maintenance Costs Using Artificial IntelligenceCARIFY – Predicting Car Maintenance Costs Using Artificial Intelligence
CARIFY – Predicting Car Maintenance Costs Using Artificial IntelligenceIRJET Journal
 
Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case StudySandra Ahn
 
The Application TCO Journey
The Application TCO JourneyThe Application TCO Journey
The Application TCO JourneyPete Hidalgo
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 

Similar to A Model for Life-Cycle Benefit and Cost Analysis (20)

Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...Linear modeling in Transportation problem: Need of reliable Public transporta...
Linear modeling in Transportation problem: Need of reliable Public transporta...
 
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
IRJET- Economic Analysis of NH-48 (Four Lanning of Hassan to Maranahally Sect...
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx
428096463-EVALUATING-TRANSPORTATION-ALTERNATIVES-ppt-pptx.pptx
 
PAVEMENT DESIGN BY USING GEOTEXTILE
 PAVEMENT DESIGN BY USING GEOTEXTILE  PAVEMENT DESIGN BY USING GEOTEXTILE
PAVEMENT DESIGN BY USING GEOTEXTILE
 
6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf6 ECON ANalysis for project appraisal.pdf
6 ECON ANalysis for project appraisal.pdf
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
 
2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx2. Economic Analysis Concepts.pptx
2. Economic Analysis Concepts.pptx
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential Building
 
Economic Impact Analysis
Economic Impact AnalysisEconomic Impact Analysis
Economic Impact Analysis
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106
 
CARIFY – Predicting Car Maintenance Costs Using Artificial Intelligence
CARIFY – Predicting Car Maintenance Costs Using Artificial IntelligenceCARIFY – Predicting Car Maintenance Costs Using Artificial Intelligence
CARIFY – Predicting Car Maintenance Costs Using Artificial Intelligence
 
Urban Local Bodies Case Study
Urban Local Bodies Case StudyUrban Local Bodies Case Study
Urban Local Bodies Case Study
 
The Application TCO Journey
The Application TCO JourneyThe Application TCO Journey
The Application TCO Journey
 
Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...Comparison of available Methods to Estimate Effort, Performance and Cost with...
Comparison of available Methods to Estimate Effort, Performance and Cost with...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 

A Model for Life-Cycle Benefit and Cost Analysis

  • 1. A Model for Life-Cycle Benefit and Cost Analysis of Highway Projects Amin Zoroufi Sadegh Tabatabaei Ali Zahedi Rabih Ataya Aseel Ibsais Xiaoxi Xia
  • 2.
  • 3. INTRODUCTION  Economic analysis is a critical component of a project evaluation methodology that considers all key quantitative and qualitative impacts of highway investments. It allows highway agencies to identify, quantify, and value the economic benefits and costs of highway projects over a multiyear timeframe.  This research was conducted to provide the Indiana Department of Transportation (INDOT) with a uniform economic analysis methodology.  As a result of this research, an Excel based computer program, the Indiana Highway Economic Evaluation Model (IHEEM), was developed to evaluate highway investment projects. The Model applies the methodology of life-cycle benefit cost analysis to perform economic analysis for proposed highway projects.  A probabilistic model was developed in IHEEM to provide an alternative option for economic analysis in addition to the deterministic model.
  • 4. IHEEM METHODOLOGY & PARAMETERS  The commonly applied economic analysis methods for highway projects are based on the estimated mean values of related parameters. These methods do not consider the uncertainties of the input parameters and therefore are considered deterministic approaches.  A probabilistic approach includes uncertainties into the economic analysis process, some of the cost and benefit items are treated as random variables with estimated statistic characteristics, such as distributions, means, standard variances and coefficient of variation (CV). Traffic volume and construction cost are the main factors that significantly affect life-cycle costs and benefits. Therefore, they are treated as random variables.  Because of the large dispersions of the construction costs, the regression method was applied to establish the relationship between construction costs and roadway lengths of highway projects.  Highways are classified as interstate, multilane highway, and two-lane highway.  Vehicle classification includes three vehicle groups: passenger cars, single unit trucks, and combination trucks.  Analysis Period is the period of time during which the current and future costs and benefits for the specific project will be evaluated. The analysis period should be long enough to include the initial construction, routine maintenance activities, and at least one subsequent rehabilitation activity.  The discount rate value used by the highway agencies ranges from 3 percent to 5 percent. We use 4% in this case study.  The cost-effective performance measures in terms of Net Present Value (NPV) and Benefit Cost Ratio (BCR) are calculated for the whole analysis period.
  • 5. IHEEM METHODOLOGY & PARAMETERS  Internal rate of return (IRR) is the interest rate at which a zero NPV is reached at the end of the analysis period. An IRR is obtained by changing the interest rate in the economic analysis while other input items remain unchanged.  Life-cycle costs and benefits are the sum of all the costs and benefits within the analysis period expressed in the present value of money.  The benefits are treated as positive values and the costs are treated as negative values. If the total values of the sum of all costs and benefits, which is also called the Net Present Value (NPV), are positive, then the proposed project is economically justified to build. Otherwise, the project is not economically justified to build. C o s t B e n e f i t s Investment Capital Travel time savings Operating & maintenance Economic development Preservation costs Improvement in air quality
  • 6. IHEEM MODEL FEATURES  IHEEM model is an Excel based computer software.  A tool for performing an economic evaluation for highway investment projects by applying the life- cycle benefit cost analysis.  The model calculates each module of agency (Public/Private) costs and user (Society) benefits for each year using specified methods.  The software includes various modules to process the complicated analysis and calculations. Each module contains default values, formulas, benefit and cost values, traffic attributes, and highway conditions. The default values were obtained from the historical data and recognized reliable results. The software provides the flexibility for users to overwrite the default values.  For input requirements in IHEEM, users need to collect the basic as well as specific project data depending on the project type.
  • 7. IHEEM- SOFTWARE INPUT & OUTPUT Life-cycle cost & benefits in terms of NPV Benefit- cost ratio (BCR) IRR Itemized Benefits • Travel Time Savings • VOC Savings • Accidents Cost Savings (Safety Benefits) OUTPUT Basic assumption Inputs • Discount Rate • Analysis Period • Area Type (Urban/Rural) General Inputs • Project Cost • O/M Annual Costs • Traffic Volume • Annual Traffic Growth Rate • Number of Crashes • Free Flow Speed Specific Inputs • Pavement IRI • Highway Length & width • Number of Lanes • Length of Detour INPUT
  • 8. IHEEM MODEL FEATURES  In IHEEM software, there are eight sheets that are interconnected in order to perform the complicated computation tasks for the economic analysis. The eight sheets are Input, Parameters, Agency Cost, Travel Time Savings, Vehicle Operating Costs Savings, Crash reduction Savings, Output Deterministic and Output-Probabilistic.  The following figure illustrates a typical highway improvement project’s cash flow. The benefit values are denoted with the upward arrows and the cost values are denoted with the downward arrows. The benefits and costs in Fig. 6 are in the constant dollar values.
  • 9. An APPLICATION EXAMPLE  Highway project improvement.  3.9-mile section of an interstate highway located in Northern California. The proposed project was to add two new lanes to the existing eight lanes to increase the traffic capacity of the frequently congested roadway section.  The Input information is listed in the following Table:
  • 10. An APPLICATION EXAMPLE  With the Input from the previous table, the IHEEM software generates the following economic analysis results:  The output information indicates that if the project is constructed, the expected NPV is $548.7 million and the benefit/cost ratio is 4.42 within the 20-year analysis period. Therefore, this proposed improvement project is economically justified to build.
  • 11. CONCLUSION  IHEEM software is a powerful and convenient tool for evaluating highway investment projects.  Highway agencies make use of measures such as the net present value of costs and benefits, benefit-cost ratio, or the internal rate of return to compare different competing alternatives. The alternative that gives the highest net present value, benefit-cost ratio or return on investment is selected and is placed to be funded, programmed, and eventually implemented.