   Hextable School, near Swanley, Kent has an enviable reputation as a centre of excellence for the
    performing arts.

   This case study describes how the Hextable Dance project moved from being unaffordable to reality,
    through the effective application of VE techniques.

   This project was started 10 years ago but stalled because the design, although innovative, was expected
    to exceed the available construction budget of £2.1m by 20% (about £420,000).


Issues faced by project team prior to Study:

   Two earlier schemes had failed and the current proposal exceeded the budget by 20%

   Due to the nature of the funding arrangements, finances were fixed and could not be increased

   The project team was unclear as to the precise nature of the client’s requirements.
Study & Approach
Study:

  As capital cost was a major concern, team recommended re-evaluating the project to focus on
   function.
 As saving one-fifth of the construction cost within the constraints of an existing design was likely
   to be an unrealistic target.
Approach:

   Identification of important functions – key value drivers – which ranged from delivery of the
    project to functions required of the completed building

Functions Including:

   Keeping within funding requirements

   Optimising the use of space

   Delivering functionality to match the school’s curriculum requirements.
Cont…

   With a clear understanding of the client’s needs, the team viewed the project from a functional
    perspective and identifyed opportunities for stretching the constraints of the existing design.

   Enabled the team to put forward innovative design solutions, without compromising the client’s
    requirements.

New Ideas Implemented:

   To lay the building over only one storey.

   The innovative roof structure and double-height studio ceiling
     retained by moving upper level areas to the ground floor, removing
     stairs and corridor space, so improving the building’s efficiency.

   To give areas multiple functionality, thus increasing flexibility and
     allowing two dance studios to be combined into one.
Lessons learned

   Involving all key stakeholders in the VM study was very important when defining value. It allowed
    stakeholders to buy into the process and ensured their needs were met.

   The architects’ full support made the VM process much more effective. They were willing to take
    suggestions from the project team and quickly put forward relevant options.

   Willingness by the team to return to the client’s core requirements and to reassess the required
    functionality opened the project to increased creativity by removing unnecessary constraints.



VE Implementation:

    A Value Engineering approach facilitated an innovative design solution that permitted the
    construction of a previously unaffordable project by reducing costs by £420,000.

   New design met the budget with no loss of aesthetic quality or functionality

More Related Content

What's hot

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
Pang Khai Shuen
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
ahmong4
 

What's hot (20)

ECA presentation
ECA presentationECA presentation
ECA presentation
 
ECA Presentation
ECA PresentationECA Presentation
ECA Presentation
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Contract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction PracticeContract implementation and management phase in Malaysia Construction Practice
Contract implementation and management phase in Malaysia Construction Practice
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
EPC CONTRACTS-CPWD.pdf
EPC CONTRACTS-CPWD.pdfEPC CONTRACTS-CPWD.pdf
EPC CONTRACTS-CPWD.pdf
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
 
A STUDY ON SOCIO-ECONOMIC CONDITIONS OF SLUM HOUSEHOLDS WITH SPECIAL REFERENC...
A STUDY ON SOCIO-ECONOMIC CONDITIONS OF SLUM HOUSEHOLDS WITH SPECIAL REFERENC...A STUDY ON SOCIO-ECONOMIC CONDITIONS OF SLUM HOUSEHOLDS WITH SPECIAL REFERENC...
A STUDY ON SOCIO-ECONOMIC CONDITIONS OF SLUM HOUSEHOLDS WITH SPECIAL REFERENC...
 
Project report on construction of house/hotel/hostel
Project report on construction of house/hotel/hostelProject report on construction of house/hotel/hostel
Project report on construction of house/hotel/hostel
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
ECA form
ECA formECA form
ECA form
 
CASE STUDY OF BUILDING SERVICES IN PUBLIC BUILDINGS
CASE STUDY OF BUILDING SERVICES IN PUBLIC BUILDINGSCASE STUDY OF BUILDING SERVICES IN PUBLIC BUILDINGS
CASE STUDY OF BUILDING SERVICES IN PUBLIC BUILDINGS
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 

Similar to Case study on hextable dance project

Waitakere Central Presentation 23 April 2010 V8 Final
Waitakere Central Presentation 23 April 2010 V8 FinalWaitakere Central Presentation 23 April 2010 V8 Final
Waitakere Central Presentation 23 April 2010 V8 Final
challengeprojects
 
Demonstration case studies
Demonstration case studiesDemonstration case studies
Demonstration case studies
parkerjce
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovations
saif hasan
 
21st Century Education Sis Bfe Mena 2011
21st Century Education Sis Bfe Mena 201121st Century Education Sis Bfe Mena 2011
21st Century Education Sis Bfe Mena 2011
espie77
 
Formations project
Formations project Formations project
Formations project
IETI SD
 

Similar to Case study on hextable dance project (20)

Workplace 2.0
Workplace 2.0Workplace 2.0
Workplace 2.0
 
Waitakere Central Presentation 23 April 2010 V8 Final
Waitakere Central Presentation 23 April 2010 V8 FinalWaitakere Central Presentation 23 April 2010 V8 Final
Waitakere Central Presentation 23 April 2010 V8 Final
 
Demonstration case studies
Demonstration case studiesDemonstration case studies
Demonstration case studies
 
COTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative FutureCOTE Top Ten: Intelligent Design for a Restorative Future
COTE Top Ten: Intelligent Design for a Restorative Future
 
The Open University Construction Framework 2008 2011 Proving
The Open University Construction Framework 2008   2011 ProvingThe Open University Construction Framework 2008   2011 Proving
The Open University Construction Framework 2008 2011 Proving
 
Michelle Jepp 15
Michelle Jepp 15Michelle Jepp 15
Michelle Jepp 15
 
122 value engineering
122 value engineering122 value engineering
122 value engineering
 
Cve presentation slide
Cve presentation slideCve presentation slide
Cve presentation slide
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovations
 
Energy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample ProjectsEnergy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample Projects
 
CWong Resume
CWong ResumeCWong Resume
CWong Resume
 
Innovations in Sustainable Design and Construction for London's Future.pdf
Innovations in Sustainable Design and Construction for London's Future.pdfInnovations in Sustainable Design and Construction for London's Future.pdf
Innovations in Sustainable Design and Construction for London's Future.pdf
 
Heather\'s Resume
Heather\'s  ResumeHeather\'s  Resume
Heather\'s Resume
 
21st Century Education Sis Bfe Mena 2011
21st Century Education Sis Bfe Mena 201121st Century Education Sis Bfe Mena 2011
21st Century Education Sis Bfe Mena 2011
 
ILP Scotland webinar: Edinburgh’s 64,000 energy efficient project
ILP Scotland webinar: Edinburgh’s 64,000 energy efficient projectILP Scotland webinar: Edinburgh’s 64,000 energy efficient project
ILP Scotland webinar: Edinburgh’s 64,000 energy efficient project
 
Formations project
Formations project Formations project
Formations project
 
Formation`s project
Formation`s projectFormation`s project
Formation`s project
 
Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Disrupting Thinking to Enable Innovation
Disrupting Thinking to Enable InnovationDisrupting Thinking to Enable Innovation
Disrupting Thinking to Enable Innovation
 

Recently uploaded

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
SanaAli374401
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Recently uploaded (20)

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 

Case study on hextable dance project

  • 1. Case study on Hextable Dance project Summary:  Hextable School, near Swanley, Kent has an enviable reputation as a centre of excellence for the performing arts.  This case study describes how the Hextable Dance project moved from being unaffordable to reality, through the effective application of VE techniques.  This project was started 10 years ago but stalled because the design, although innovative, was expected to exceed the available construction budget of £2.1m by 20% (about £420,000). Issues faced by project team prior to Study:  Two earlier schemes had failed and the current proposal exceeded the budget by 20%  Due to the nature of the funding arrangements, finances were fixed and could not be increased  The project team was unclear as to the precise nature of the client’s requirements.
  • 2. Study & Approach Study:  As capital cost was a major concern, team recommended re-evaluating the project to focus on function.  As saving one-fifth of the construction cost within the constraints of an existing design was likely to be an unrealistic target. Approach:  Identification of important functions – key value drivers – which ranged from delivery of the project to functions required of the completed building Functions Including:  Keeping within funding requirements  Optimising the use of space  Delivering functionality to match the school’s curriculum requirements.
  • 3. Cont…  With a clear understanding of the client’s needs, the team viewed the project from a functional perspective and identifyed opportunities for stretching the constraints of the existing design.  Enabled the team to put forward innovative design solutions, without compromising the client’s requirements. New Ideas Implemented:  To lay the building over only one storey.  The innovative roof structure and double-height studio ceiling retained by moving upper level areas to the ground floor, removing stairs and corridor space, so improving the building’s efficiency.  To give areas multiple functionality, thus increasing flexibility and allowing two dance studios to be combined into one.
  • 4. Lessons learned  Involving all key stakeholders in the VM study was very important when defining value. It allowed stakeholders to buy into the process and ensured their needs were met.  The architects’ full support made the VM process much more effective. They were willing to take suggestions from the project team and quickly put forward relevant options.  Willingness by the team to return to the client’s core requirements and to reassess the required functionality opened the project to increased creativity by removing unnecessary constraints. VE Implementation:  A Value Engineering approach facilitated an innovative design solution that permitted the construction of a previously unaffordable project by reducing costs by £420,000.  New design met the budget with no loss of aesthetic quality or functionality