1. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
CV OF Mr . NEMER AKRAM K. ABUHAJAR
Position: MEP Project /Operation Manager
Name : Nemer Akram K. AbuhajarName : Nemer Akram K. Abuhajar
Nationality : Jordanian
Passport No. : I 377698
Date of Birth : July 1970
Education Qualification : B.Sc. In Electrical Engineering
Year of Graduation : 1994
Computer Literacy : Microsoft office, AutoCAD.
Overall Experience : 21 years
With LDevino as Operations Manager : with effect f rom July 2016
CV/ (Nemer Abuhajar) Page 1 of 6
2. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
Managerial and Technical Skill s :
(Office Works )
Directing, handling and effectively controlling the project activities
(Basic, detail and construction Engineering, Procurement,
Construction/Revamping. Pre -commissioning, Commissioning, till
start-up and performance test) from inception to the start -upstart-up and performance test) from inception to the start -up
Supporting the field (site) on Technical and Contractual problems and
issues.
Surveying and reporting the technical issues related to operation and
maintenance problems
Technical and commercial evaluation, alignment and preparing the
advising report for tender commodities (Piping, Vessel tanks, Rotating
Equipment, ELV, LV, MV, and HV Systems , Instruments & Control
Systems , Fire Alarm and Fire Fighting Systems and HVAC Systems.
Follow -up the supplier technical clarifications.
Participating in formulating and issuing the contracts, same as well
monitoring and providing efficient contract management for contract
terms, coming with the purview of the company projects through
optimal strategies an d plans.
Ensuring that the enquiry documents bids summaries and contracts are
as per company policy.as per company policy.
Monitoring and review the plan, schedules, physical progress and
resource utilization.
Identifying the trends, considering implications, analyzing variance and
recommending corrective action.
Organizing the meetings and participating in negotiations related to
the project activities at each phase.
Check and controlling the invoices for the contractors and suppliers.
Following up the procurement activities (e xpediting, forwarding and
shipping)
Controlling budget and issuing the monthly reports.
Optimization of hired resources, third party agencies by timely control
and expediting.
(Site Works )
Manage projects and coordinate the works of licensors, Engineering
CV/ (Nemer Abuhajar) Page 2 of 6
Manage projects and coordinate the works of licensors, Engineering
Consultants and sub-contractors. Ensuring the timely completion of
the project as per project quality standards and budget.
Control and review of the project drawings and specifications during
engineering as well as the construction phases.
Ensuring adhe rence to the quality procedures and the safety rules of
the company.
Ensuring project execution as per the contract terms and conditions.
3. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
Major Projects
A - With Aljaber Engineering LLC Qatar (2007 2016)
(1)
Project : EPIC for Wet Utilities Distr. Network for Supp. Serv. Area Ph. I &Project : EPIC for Wet Utilities Distr. Network for Supp. Serv. Area Ph. I &
II and Main Net. For Ongoing Dev. at West End Ras Laffan
Piping, Equipment Installation, M EP
Client : Qatar Petroleum
Position : Project Manager
Responsibilities : Management of Mechanical Electrical Instrumentation &
Controls, Testing, commissioning and startup of total Project .
(2)
Project : Reconstruction of Roads and Infrastructure in Mesaieed
Community Area
Client : Qatar Petroleum
Position : Project Manager
Responsibilities : HV and LV cabling, Street lighting
(3)
Project : Qatalum Project Installation of Above Ground Metal
Piping, Equipment Installation, M EP
Client : SNC Lavalin
Position : Project Manager
Responsibilities : Mechanical Electrical Instrumentation &
Controls, Testing, Pre -Commissioning, and commissioning of
total Project
(4)
Project : Epic for upgrading of existing Gabbro Berth Crane Facilities at
Mesaieed Port
Client : Qatar Petroleum
CV/ (Nemer Abuhajar) Page 3 of 6
Client : Qatar Petroleum
Position : Project Manager
Responsibilitie s : Mechanical Electrical Instrumentation &
Controls, Testing, Pre -Commissioning, and commissioning of
total Project
4. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
A- With Industrial Construction Co. Ltd Jordan (1995 2007)
(1 )
Project : Rehabilitation and upgrading of the Ore beneficiation andProject : Rehabilitation and upgrading of the Ore beneficiation and
material handling plants including operation & maintenance.
Owner : Jordan Phosphate Mines Co.
Main Contractor : CONSORTIUM Koch/SOFREMINES .
Year : 2004 - 2007 .
Position : Project Manager
Project Type : 1- Structural Steel Mechanical Equipment
Electrical Instrumentation & Controls .
2-
and Process Plant.
(2 )
Project : Aqaba KOH Storage and Shipping Facilities (Contract No. 23).
Owner : Jordan Bromine Company (JBC).Owner : Jordan Bromine Company (JBC).
Main Contractor : Industrial Construction Company.
Year : 2004.
Position : Project Manager
Project Type : Mechanical Electrical Instrumentation & Controls.
Design and Build of two metal tanks (2133m
3
each )for the storage of potassium hydroxide
(50% KOH), associated mechanical, electrical and instrumentation works.
Supply and installation of above ground stainless steel pipeline ( 6km) from pump station to
the export je tty.
(3 )
Project : MEREN Silica Sand Project. Plant Construction Package (3A).
Owner : The Middle East Regional Development Enterprise (MEREN).
CV/ (Nemer Abuhajar) Page 4 of 6
Owner : The Middle East Regional Development Enterprise (MEREN).
Main Contractor : CODE JV Industrial Construction Company.
Year : 2003 -2004 .
Position : Project Manager
Contract Value : US$ 611582 (Electro - Mechanical).
Project Type : Structural Steel Mechanical Electrical Instrumentation &
Controls.
5. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
(4 )
Project : Deir Alla - Zai - Amman Water Expansion Project -128/2000.
Owner : Water Authority of Jordan (WAJ).
Main Contractor : The Arab Contractors (Outhman Ahmad Outhman).
Year : 2000 - 2003 .
Position : Project Manager
Project Type : Mechanical
Installation of 22 7Km of 60" welded steel pipeline from Zai up to Dabouq
reservoir i ncluding HS testing, calibration pigging, and Cathodic protection.
(5 )
Contract :
Owner : Ministry of Water & Irrigation.
Main Contractor : Giovanola Freres S.A.
Year : 2000.
Position : Construction Manager
Project Type : Mechanical
Erection, sand blasting and painting of steel bottom outlets including hydraulically
actuated gates, motorized valves and piping at: Mujib , Wala, Tannur Irrigation Dams.actuated gates, motorized valves and piping at: Mujib , Wala, Tannur Irrigation Dams.
(6 )
Project : Salt Pans Dredging Works - Dead Sea.
Owner : Arab Potash Co.
Main Contractor : HAM Dredging and Marine.
Year : 1999.
Position : Construction Manager
Project Type : Mechanical.
Fabrication and welding of submerged Steel pipe lines 700 mm in diam eter.
(7 )
Contract : Fine Separation Plant Contract No. 155 F / 97.
CV/ (Nemer Abuhajar) Page 5 of 6
Contract : Fine Separation Plant Contract No. 155 F / 97.
Owner : Jordan Phosphate Mines Co.
Main Contractor : Industrial Construction Company.
Year : 1997.
Position : Construction Manager
Project Type : Structural Steel Mechanical Electrical Instrumentation &
Controls.
6. Nemer Abuhajar
Mobile no.: +974 5586 4772
E- mail: nabuhajar@gmail.com
Turn Key erection of the steel structures, mechanical and electrical equipment as follows:
Centrifugal Separator, cyclones, draught fan, de -dusting bag filter , steel duct work , belt
and screw conveyors.
(8 )
Contract : DAP Fertilizer Warehouse Reconstruction Tripper Conveyor.
Owner : Jordan Phosphate Mines Co. - Fertilizer Complex.Owner : Jordan Phosphate Mines Co. - Fertilizer Complex.
Main Contractor : Koch Transporttechnick
Year : 1996.
Position : Project Engineer
Project Type : Structural Steel Mechanical Electrical Instrumentation &
Controls.
The turnkey erection of the structural steel, elevated conveyors, traveling tripper cars,
chutes and gates .
(9 )
Contract : 59/95 F 9 E - Rehab Power Station.
Owner : Jordan Electrical Authority.
Main Contractor : Marubeni Corporation.
Year : 1997.Year : 1997.
Position : Project Engineer
Project Type : Structural Steel Mechanical Electrical Instrumentation &
Controls.
Erection of One 100 Mega Watt simple cycle gas turbine power station, Fuel oil unloading
and forwarding, cooling tower, 15 kV isolated phase bus , 15 kV - 132 kV, 150 MW step up
transformer, 132 kV underground cables and 132 kV substation .
(10 )
Contract : 32 F / 95 - Drying Plant
Owner : Jordan Phosphate Mines Co.
Main Contractor : Industrial Construction Company.
Year : 1995 - 1996 .
Position : Site Engineer
Project Type : Structural Steel Mechanical Electrical Instrumentation &
CV/ (Nemer Abuhajar) Page 6 of 6
Project Type : Structural Steel Mechanical Electrical Instrumentation &
Controls.
Erection of Two drying kilns , belt conveyor s, receiving bunker s, 4000 M3 heavy fuel steel
tank of with hea ters, pump house and insulated hot fuel delivery steel pipe line.