SlideShare a Scribd company logo
1 of 22
Download to read offline
0
Domer Lozano Javier
Block 5 Lot 18 Champaca Street Maligaya Park Subdivision Novaliches, Quezon City
Mobile No. +966506993894/+639273433903
Email Address: boytoydomer@yahoo.com/boytoydomer@gmail.com
ELECTRICAL ENGINEER
PROFESSIONAL WORK EXPERIENCE
CAREER SUMMARY
10+ years of work experience in the field of Electrical Power System and Mechanical
works. Knowledge in design & construction activities of Oil, Gas, and Water
Rehabilitation, primary and secondary overhead power distribution lines, installation and
maintenance of Electrical & Instrument such as Motor Operated Valves, electric
motors, motor control system, lightning systems, high medium and low voltage Switch
Gears, Transformers & Switch Racks specialized in distribution control panel and
remote control. Knowledge in implementation of Cathode Protection/Civil works,
Telecommunication works, Security System Facilities works, Design & Engineering.
EDUCATIONAL ATTAINMENT
College : Cagayan State University
Bachelor of Science in Electrical Engineering
1999 – 2005
Other Course : Industrial Motor Control
National Polytechnic Institute
November 9 – 23 2005
Secondary : Our Lady of Snows Academy
1995 - 1999
Tertiary : Sabino T. Acorda Central School
1988 – 1994
PERSONAL DATA
Age & Date of Birth : 33 years old & September 05, 1981
Nationality : Filipino
Sex : Male
Height : 5’7 ½”
Weight : 165 lbs.
Civil Status : Married
Wife : Lailanie B. Javier
Religion : Roman Catholic
Position Title : Electrical Design Engineer
Company : Saudi Engineering Group International
Saihati Building King Abdul Aziz Street
P.O. Box 5289 - Dammam, K.S.A.
Under supply contract with WorleyParsons Engineering
Consultancies Company
Al-Jazira Building King Abdullah Bin Abdul Aziz Road
P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A.
Project Title : Upgrade Offshore Security Facility (Kingdom Wide)
(BI #10-01377).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : June 29, 2015 up to Present
 Estimating material, construction, and labor costs, and project
timescale.
 Develop engineering projects analysis to include preliminary design,
calculations, budget analysis, life cycle costs plus equipment selection.
 Cost and weight targets must be managed and met.
Position Title : Electrical Design Engineer
Company : Saudi Engineering Group International
Saihati Building King Abdul Aziz Street
P.O. Box 5289 - Dammam, K.S.A.
Under supply contract with WorleyParsons Engineering
Consultancies Company
Al-Jazira Building King Abdullah Bin Abdul Aziz Road
P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A.
Project Title : Yanbu Refinery Project MC – 2 TETRA Radio System
(Contract Job Code # 403011-00334).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : April 16, 2015 up to Present
 Develop engineering projects analysis to include preliminary design,
calculations, budget analysis, life cycle costs plus equipment selection.
 Estimating material, construction, and labor costs, and project
timescales.
 Create and amend own drawings on Auto CAD 2D & micro station
version-8.
 Voltage drop and Cables sizing summary and adequacy calculation for
UPS and circuit breakers.
 Review designs development for conformance with applicable codes,
utilizing engineering standards along with good engineering practices.
 Manage own portfolio of design work, on time and within budget.
 Ensure compliance and offer recommendations for Health, Safety &
Environmental issues relating to technical activities,
 Maintain an on-going awareness of national and international standards of
technical expertise, reporting back any significant changes.
 Cost and weight targets must be managed and met.
 Follow and contribute to the development of the Best Practice guidelines
as laid out in quality documentation.
Record of employment;
Position Title : Lead Electrical Engineer
Company : Saudi Engineering Group International
Saihati Building King Abdul Aziz Street
P.O. Box 5289 - Dammam, K.S.A.
Client : Maaden Aluminium Company (MAC) Central of Engineering
Inclusive Date : November 04, 2014 up to April 02, 2015
Duties and responsibilities;
 Create detailed technical engineering specifications for the production team
to ensure the product’s functionality and that it meets the specific required
standards of performance. Required specifications for electrical control
system and equipment’s for use across many sectors, including:
 Refinery Aluminum Plant
 Rolling Mill Aluminum Plant
 Smelter Aluminum Plant
Modification fore Electrical Works:
Position Title : Electrical Lead Engineer
Project Title : Provide power supply for Crimping Machine in CE &
Maintenance Workshop
(MOC Request no. MA-CE-MOC-0001).
Inclusive Date : December 12, 2014 to February 16, 2015
Project Title : Installation of NCB ATM
(MOC Request no. MA-CE-MOC-0002).
Inclusive Date : July 16, 2014 to up March 04, 2015
Project Title : 3 Phase Power Supply to new Kitchen Equipment in MA Admin
Canteen
(MOC Request no. MA-CE-MOC-0003).
Inclusive Date : November 12, 2014 to up Present
Project Title : Identification of Useable Breakers in 2 Sub Stations for use Air
Monitoring Stations in Natural Gas Line (NGL)
(MOC Request no. MA-CE-MOC-0004).
Inclusive Date : August 18, 2014 to up Present
Project Title : Modification of UPS (11KVA) in Admin/IT Room
(MOC Request no. MA-CE-MOC-0005).
Inclusive Date : January 28, 2015 to February 16, 2015
Project Title : Install 2 Additional Power Sockets in Display Chiller and Hot
Cabinets and Provide 3 New Power Points in Salad Preparation
Area in MA Admin Canteen
(MOC Request no. MA-CE-MOC-0006 & 0007).
Inclusive Date : February 09, 2015 to up March 31, 2015
Project Title : To Build 3 Storage Room under Stair and 01 Mail Storage Room
along Corridor in MA Admin Ground Flour
(MOC Request no. MA-CE-MOC-0008).
Inclusive Date : January 06, 2015 to up March 23, 2015
Project Title : To Build 3 Storage Rooms and Expansion of HR/General
Services Department 4 Offices in MA Admin Building Area
(MOC Request no. MA-CE-MOC-0010).
Inclusive Date : February 17, 2015 to up Present
Project Title : To provide power for Air Compressor and 6 power outlets for
Fire Trucks Charger in Fire Station/Security Command Center
(MOC Request no. MA-CE-MOC-0011 & 0013).
Inclusive Date : February 24, 2015 to up Present
Project Title : To Build Gypsum Partition and Door opening on the wall to
make new Office Facility in CE & M Building 1/Floor
(MOC Request no. MA-CE-MOC-0012).
Inclusive Date : March 03, 2015 to up Present
Project Title : Permanent connection for Oxyfuel Machine in CE & M
Workshop 1/Floor
(MOC Request no. MA-CE-MOC-0014).
Inclusive Date : March 14, 2015 to up Present
Project Title : Electrical Connection for Welding Machine in CE & M
Workshop 1/Floor
(MOC Request no. MA-CE-MOC-0015).
Inclusive Date : March 14, 2015 to up Present
Project Title : Installation of 480VSocket connection for Welding Machine in
CE & M Workshop 1/Floor
(MOC Request no. MA-CE-MOC-0016).
Inclusive Date : March 14, 2015 to up Present
Project Title : Provide power supply to new Hydraulic Column Lift in
CE & M Workshop Ground Floor
(MOC Request no. MA-CE-MOC-0020).
Inclusive Date : March 11, 2015 up to Present
Project Title : Installation of 8 Cameras in MA Main Clinic
(MOC Request no. MA-CE-MOC-0021).
Inclusive Date : March 25, 2015 up to Present
Project Title : Installation of 4 Additional Light in CE File Room
(MOC Request no. MA-CE-MOC-0022).
Inclusive Date : March 30, 2015 up to April 0, 2015
Duties and responsibilities;
 Make site visits to ascertain detailed information related to the design and
planning of a project.
 Preparing for scope of work of the project.
 Manage own portfolio of design work, on time and within budget.
 Proven ability in the supervision and management of a team with regard to
all aspects from Master plan, Concept, Preliminary and Final Design
stages, including single line diagrams, panel schedules, electrical
schematics diagram.
 Estimates, prepares and assigns the resources such as manpower,
materials, consumables, equipment, tools, etc., required for all electrical
and related works prior to execution.
 Monitoring and Supervise to install of electrical cable, electrical main
distribution panels, non-fusible disconnect switch air circuit breaker,
convenient outlet and lay out electrical cables including necessary
conduiting.
 Voltage drop and Cables sizing summary and adequacy calculation for
UPS and circuit breakers.
 Lead in the implementation of innovative design solutions using the latest
industry standards considering quality, safety and sustainability as a
minimum.
 Preparing for Management of Change (MOC) and Minor Plant Monitoring
Request (MPMR) to get signatory for designation person.
 Preparing for Pre Startup Safety Review (PSSR) Form, Minor Plant
Modification – Close Out Form and Minor Plant Modification – Turn
Over Checklist.
 Testing and Commissioning of Electrical panel boards and convenient
outlet ready for startup.
 Take responsibility for all technical aspects of electrical / building services
work performed by the company from the inception stage through to final
completion of projects and client handover.
 Completion of project and documents shall turn over to the engineering
document controller.
 Direct report to Project Manager for the status of works.
Position Title : Electrical Design Engineer
Company : Saudi Engineering Group International
Saihati Building King Abdul Aziz Street
P.O. Box 5289 - Dammam, K.S.A.
Under supply contract with WorleyParsons Engineering
Consultancies Company
Al-Jazira Building King Abdullah Bin Abdul Aziz Road
P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A.
Project Title : Replacement of Telephone Switches Kingdom Wide
(BI–10–000246, Contract # 6600028287).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : July 28, 2013 to November 03, 2014
Project Title : Rabigh Phase II Petrochemical UPS System Project by Petrofac
(Contract Job Code: 6600028287).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : September 01, 2013 to May 15, 2014
Project Title : Rabigh Phase II Petrochemical Permanent Facilities UPS System
Sirti by Project (Contract Job Code: 0-5361-20-0000).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : December 29, 2013 to May 15, 2014
Project Title : Design for Abu Safah SCADA/RTU Communication Network
Upgrade (BI-1003040-0001).
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : April 06, 2014 to May 15, 2014
Duties and responsibilities;
 Make site visits to ascertain detailed information related to the design and
planning of a project.
 Manage own portfolio of design work, on time and within budget.
 Take responsibility for all technical aspects of electrical / building services
work performed by the company from the inception stage through to final
completion of projects and client handover.
 Manage the calculation for DC Rectifier Systems, Inverter Systems, UPS
System.
 Create and amend own drawings on Auto CAD 2D & micro station
version-8.
 Liaising with structural engineers, architects, surveyors etc.
 Estimating material, construction, and labor costs, and project
timescales.
 Preparing for engineering mark ups for the design, and issued for
Check Print & Squad Check ready for Issued for Construction.
 Voltage drop and Cables sizing summary and adequacy calculation for
UPS and circuit breakers.
 Ensure compliance and offer recommendations for Health, Safety &
Environmental issues relating to technical activities,
 Maintain an on-going awareness of national and international standards of
technical expertise, reporting back any significant changes.
 Assist the operating units to undertake design assignments, i.e. schematic
and detailed design of installations/schemes within the remit of the
jobholder's specialist skill area.
 Develop engineering projects analysis to include preliminary design,
calculations, budget analysis, life cycle costs plus equipment selection.
 Use AutoCAD and calculations software as part of the design process.
 Assist in the preparation of drawings of high quality in Micro station for
the infrastructure disciplines.
 Cost and weight targets must be managed and met.
 Follow and contribute to the development of the Best Practice guidelines
as laid out in quality documentation
 The selection and application of materials and processes appropriate to
each design element.
 Lead in the implementation of innovative design solutions using the latest
industry standards considering quality, safety and sustainability as a
minimum.
 Review designs development for conformance with applicable codes,
utilizing engineering standards along with good engineering practices.
Record of employment;
Position Title : Site Engineer (Self Employed)
Project Title : 3 Story Building & 2 Story Building in Maligaya Park
Subdivision Novaliches, Quezon City
Subject : Electrical work
Inclusive Date : August 25, 2012 to February 10, 2013
Duties and responsibilities;
 Directly responsible for the safety of all electrical groups’ personnel of the
project by ensuring that the project execution will be done according to all
applicable health, safety, sanitary and environmental standards.
 Assign targets for accomplishments and ensure targets are met on daily
basis for all electrical groups at site.
 Coordinates all parties involved in the planning, design, and construction
process.
 To identify and recommend opportunities to improve the range, quality
and cost effectiveness of services to the client.
 Ensures that the facilities are maintained and repaired in a cost effective
manner, with consideration given to quality and customer service.
 Prioritize and resolve all technical problems within minimum amount of
time and cost.
 Must be able to demonstrate leadership and influencing skills.
 Has overall responsibility for the planning, management, coordinating and
construction project and will work closely with a range of other
professional during the contract progress.
 Proven ability in the supervision and management of a team with regard to
all aspects from Master plan, Concept, Preliminary and Final Design
stages, including single line diagrams, panel schedules, electrical
schematics diagram.
 Installation of electrical main distribution panels, air circuit breaker,
convenient outlet, electrical metallic tubing pipe, flexible hose and lay -
out electrical cables.
 Termination of cables and testing commissioning of electrical panel
boards and convenient outlet ready for startup.
 Coordinate with site in charge and make sure that all activities are in
accordance with standard drawings and Philippines Electrical Codes
(PEC) standard and specification.
 Providing indigent professional advice and guidance.
 Ensuring that the quality standards and all health and safety checks are
adhered to.
 Coordinate to the owner for the payment of accomplished project.
 Develops conceptual plans and budgets for facilities project to support
fiscal decision making.
 Prepare for requests for proposal and conducts all necessary meeting to
facilitate hiring architectural and construction management services.
 Monitors and reports on all phases of planning and construction.
Record of employment;
Position Title : Project Engineer (Self Employed)
Company : Kashmir Line Contracting Company
Block 5 Lot-18 Champaca St. Maligaya park subdivision,
Quezon City
Project Title : 8 Doors Building in Ugong, Valenzuela City Philippines
Subject : Electrical Works
Inclusive Date : July 20, 2012 to September 26, 2012
Duties and responsibilities;
 Has overall responsibility for the planning, management, coordinating and
construction project and will work closely with a range of other
professional during the contract progress.
 Proven ability in the supervision and management of a team with regard to
all aspects from Master plan, Concept, Preliminary and Final Design
stages, including single line diagrams, panel schedules, electrical
schematics diagram
 Installation of electrical main distribution panels, air circuit breaker,
convenient outlet and lay out electrical cables.
 Testing and Commissioning of Electrical panel boards and convenient
outlet ready for startup.
 Coordinate with site in charge and make sure that all activities are in
accordance with standard drawings and Philippines Electrical Codes
(PEC) standard and specification.
 Providing indigent professional advice and guidance.
 Ensuring that the quality standards and all health and safety checks are
adhered to.
 Coordinate to the owner for the payment of accomplished project.
 Develops conceptual plans and budgets for facilities project to support
fiscal decision making.
 Prepare for requests for proposal and conducts all necessary meeting to
facilitate hiring architectural and construction management services.
 Monitors and reports on all phases of planning and construction.
 Proven ability in the supervision and management of a team with regard to
all aspects from Master plan, Concept, Preliminary and Final Design
stages, including single line diagrams, panel schedules, electrical
schematics diagram.
 Installation of electrical main distribution panels, air circuit breaker,
convenient outlet, electrical metallic tubing pipe, flexible hose and lay -
out electrical cables.
 Termination of cables and testing commissioning of electrical panel
boards and convenient outlet ready for startup.
Record of employment;
Position Title : Project Engineer / Senior Electrical Engineer
Company : Seas of Technology Contracting Company
Al – Khobar, 31952 Eastern Province, P.O. Box 31668, K.S.A
Project Title : Replacement of Data Network Equipment BI-10-00074
Kingdom Wide, Saudi Arabia (Tele-Communication &
Electrical Works)
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : September 28, 2010 to July 13, 2012
Duties and responsibilities;
 Has overall responsibility for the planning, management, coordinating and
construction project and will work closely with a range of other
professional during the contract progress.
 Estimates, prepares and assigns the resources such as manpower,
materials, consumables, equipment, tools, etc., required for all electrical
and related works prior to execution.
 Attending pre - site and on – site meeting during the contract, liaising of
range of other professionals involved with the project in Saudi Aramco
and Saudi Electric Company.
 Providing indigent professional advice and guidance.
 Ensuring that the quality standards and all health and safety checks are
adhered to.
 Develops conceptual plans and budgets for facilities project to support
fiscal decision making.
 Coordinates with the proponent groups and building committees to
facilitate the rational facility planning, budgeting and scheduling.
 Prepare for requests for proposal and conducts all necessary meeting to
facilitate hiring architectural and construction management services.
 Monitors and reports on all phases of planning and construction.
 Conduct site surveys, Prepare plans, lay out and designs.
 Coordinates all parties involved in the planning, design, and construction
process.
 Develops and maintains facility project budgets.
 Conduct pre-construction conference, review bids, is recommends award
of contract.
 Check plans estimating the bill of quantity; send the quotation to the
suppliers, clients and purchasing of materials, equipment for conformity
with specifications.
 Reviews contract plans and specifications for compliance with appropriate
building codes and project requirements.
 Receives pay request for professional consultants and contractors and
approved for payments.
 Monitors and facilitates resolution of construction contract disputes and
claims.
 Monitors construction contract close-out and maintain documentation
files.
 Monitor the announcement projects of Saudi Electric Company (SEC) in
their website.
 Assists in development of new standards of practice for Project
Management activities.
 Skill in reading and interpreting plans and specifications and to compare
with them construction progress.
 In case of emergency, I should be able to solve problems for his team
members.
 Knowledge of current status of costs of new construction, escalation
factors, and market trends.
 Knowledge of building codes and standards of practice.
 Must suggest new policies and modifications in order to reform the nature
of work.
 It is his prime most duty to participate in meetings, discussions, project
site visits, workshops and hearings.
 Must has keep preparing status reports and presenting them to higher
managing authorities for scrutinizing.
 Monitor the installation of Access Data Network Equipments in North
Area, Central Region & Western Region.
 Monitor the installation of PROCURVE Switch, HP 3500yl-24G-PWR
(J8692A).
 Monitor the installation of PROCURVE Switch, HP 5406zl Intelligent
Edge (J8697A).
 Monitor the installation of PROCURVE Switch, HP 8212zl Switch Base
System (J8715B).
 Monitor the installation of Remote Serial Router (RSR), Cisco 3945, &
Multi – Mode Extender (MME), MACS ET-CB20.
 Monitor the installation of Cube IT Cabinet, 12RU & 7 feet.
Record of employment;
Position Title : Project Manager
Company : Sumitomo Corporation
Seas of Technology Contracting Company
Al–Khobar, 31952 Eastern Province P.O. Box 31668, K.S.A.
Project Title : Manifa (Civil & Electrical Works, BI-10-00450-006)
: Manifa Communication SCADA/RTU & Security Systems
Projects (GOSP Plant)
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : April 5, 2010 up to September 25, 2011
Duties and responsibilities;
 Knowledge of estimating the cost and bill of quantity for the project.
 Monitoring and execute the work of our teams and preparing the report to
submit in the meeting.
 Must has keep preparing status reports and presenting them to higher
managing authorities for scrutinizing.
 Has overall responsibility for the planning, management, coordinating and
construction project and will work closely with a range of other
professional during the contract progress.
 Representing the interest of the Clients.
 Attending pre - site and on – site meeting during the contract, liaising of
range of other professionals involved with the project.
 Direct reporting to the Chief of Executive Officer for update and progress
report of the project.
 Ensuring that the quality standards and all health and safety checks are
adhered to.
 Keeping track of progress and ensuring that the project is on time and on
budget.
 Prepare for requests for proposal and conducts all necessary meeting to
facilitate hiring architectural and construction management services.
 Monitors and reports on all phases of planning and construction.
 Coordinates all parties involved in the planning, design, and construction
process.
 Prepares contracts change orders and monitors their execution.
 Costs estimate the additional work and preparing for change order to the
contractor.
 Reviews contract plans and specifications for compliance with appropriate
building codes and project requirements.
 Monitors and facilitates resolution of construction contract disputes and
claims.
 Monitors construction contract close-out and maintain documentation
files.
 Skill in reading and interpreting plans and specifications and to compare
with them construction progress.
 Knowledge of facilities planning and construction management processes
and procedures.
 Prepares contracts change orders and monitors their execution.
 Knowledge of laws governing construction contracts and contracting.
 Knowledge of construction materials and methods.
 Knowledge of supervisory practices and principles.
 It is his prime most duty to participate in meetings, discussions, project
site visits, workshops and hearings.
 Must determine the resources required for the purpose of production.
 Responsible for Health, Safety and Environment (HSE) of my people
while working on job sites as well as on the quality and man hour safety.
Record of employment;
Position Title : Electrical Engineer QA/QC Inspector
Company : Abdulla Fuoad Holding Company
Industrial Security & System Division
P.O. Box 257 Damman 31411 K.S.A
Project Title : King Abdullah University Science and Technology
(Communication Security System & Facilities)
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : January 20, 2009 to January 20, 2010
Duties and responsibilities;
 Direct responsible for the materials inspection delivered on the job site
base on SAMSS and Saudi Aramco standard.
 Assist to the QA/QC Manager for preparation Inspection Assignment
Package, Construction method statement of Material Submittal.
 Coordinates and monitoring that the location of HVAC and MVAC power
cables that installed as per Drawing of Issued for Construction (IFC) that
approved by Aramco Standard.
 Preparing of Ready for Inspection (RFI) Check list.
 Prepare inspection schedule for the planned quality activities during the
procurement, construction and pre - commissioning work phases.
 Conduct of inspection and test of electrical and civil works.
 Preparing of BOQ and Technical Query for Request for Approval (RFA)
Checklist as per Aramco Standard.
 Preparing for the Technical Query (TQ) for the new drawing, red line
drawing and submit to the Aramco office of Project Management Team.
 Maintain and monitor the implementation of approved QA/QC
procedures, Inspection plan and Construction Work Methods.
 Monitors daily site progress and evaluate the project schedule,
construction workmanship including QA/QC issues, procurement
activities and status.
 Monitoring of High, Medium Voltage and Low Voltage cables for
meggering resistance test and splicing.
 Monitoring, Pre-Commissioning of High Voltage Step–Up and Step–
Down Transformers and high potential test as per Aramco procedures.
 Coordinate the implementation of commissioning plan with
Commissioning lead at site.
Responsible for ensuring timely completion of commissioning progress
 Conduct and Inspection the termination of High and Medium voltage
power cables to the transformers.
 Monitoring of installation of Radar and termination of power cables.
 Calculated the power cables schedule for Voltage drop and Load schedule
as per Aramco Standard for additional works.
 Experienced in reading and following electrical program as per Aramco
Standard.
 Monitoring and assembled of Walkthrough machine and installation of X-
Ray machines and Radio Frequency Identification (RFID) License Plate
Readers System (LPRS), Arm Barriers, Card Readers, Hydraulic Crash
Barriers.
 Coordinate to the Project Inspector Division (PID) and inspect the location
of Card readers, Magnetic Door Lock, Door Strike, and Snap Shot
Cameras, Hydraulic Crash Barrier and Metal Detector.
 Expedite the connectivity of Fiber Optic cables to the Cisco Switch.
 Ensure availability of critical materials, expedite material issues,
coordinate and push company buyers to deliver critical materials as soon
as possible.
 Ensure material traceability keeping of vendor inspection certificates,
purchase orders, materials receipt records and calibration certificates.
 Conduct and inspection upon arrival of the materials to the lay down yard
prepare materials receiving report and attach inspection checklist and
testing report.
 Ensure commitment of site material deliveries.
 Expedite the technical issues to facilitate construction phase.
 Ensure all works done by construction supervisions are all within client
specifications engineering standards, materials specifications scope of
works and contract amendments.
 Monitoring of field activities lay down yard and issues Non Conformance
Report against non – complying and proposed corrective action.
 Monitoring of continuity testing for Medium and Low voltage power and
control cables.
 Conduct an inspection for Fusion Bonded Epoxy coated rebar's (FBE).
Reinforcing steel, embedded item form closures for Cameras and
Microwaves foundation.
 Coordinates the location of Compaction Testing Test to the PID.
 Coordinates the location of Lean concrete for ready for concrete casting
pouring.
 Conduct an inspection for the coming of the new delivery materials as per
the Bill of Quantity (BOQ) ordered.
 Monitoring of concrete casting pouring for Cameras and Microwaves
foundations.
 To prepare updated daily accomplishment reports of the team.
 Knowledge of estimating, budgeting, scheduling practices.
 Set-up and operate test equipment to evaluate of development parts.
 Assembles and system under simulated operating conditions and record
result.
 Review and update all construction drawing prior to the start of electrical
and civil works construction for installation activities.
 Concrete Moisture Field Test of Cameras and Microwaves foundation
ready for applying of Bitumen coating.
 Monitoring and installation of Cameras, Microwaves Intrusion Detection
Systems poles.
 Perform miscellaneous duties as directed by Site Manager/Project
Manager.
 Coordinate the locations of Camera's and Microwaves Intrusion Detection
System (MIDS) Foundation as per Aramco Standard drawing.
 Answering inspections to the owners RFI in line with approved
procedures, specifications, codes and standards or site technical queries
and field change design issued by engineering. Follow-up owner’s
inspection plans and approved inspection procedures. Keep the original
required documentation of inspections in order to document the works
provided. Specify if the owner works status is endorsed and inform them
about any encountered aspects the job.
 Inspection of the HVAC, MVAC & LVAC cables installation, start-up, air
balancing, pre-commissioning and commissioning of the Electrical System
and building service scope.
 Clearing of generated Punch List Items, as well as leading and provide
details to subcontractor on how to clear punch list on easy manner of work
execution.
 Review, comment and recommend approval on contractor’s shop
drawings, technical field queries, Method Statements, Inspection and Test
Plans
 Monitoring and installation of Pan Tilt Zoom (PTZ) & Dome,
Fixed cameras, Microwaves Intrusion Detection Systems, Ex–Ray
Machine and ID Budging.
Record of Employment;
Position Title : Electrical & Mechanical Site Supervisor
Company : Skope Technology Incorporated
Unit 202, 2nd
Floor 1st
Midland Condo
109 Gamboa St. Legaspi Village, Makati City, Philippines
Project Title : Fire Alarm Protection
Client : Silver City/Auto Mall Center
Inclusive Date : July10, 2008 to December 23, 2008
Duties and responsibilities;
 Supervise and Installation of 1” - 6” diameter pipe schedule 40 - 80
fabricated and welding.
 Supervise and installation of gate valves and supervisory switch to the
pipe.
 Monitoring and installation of electrical cables to the supervisory switch
and termination.
 Trained or informs the employees of new work methods and procedures,
changes in safety regulations, work policies and electrical codes and
standards.
 Plans and develops work schedules, equipment usage schedules, priority
of electrical expenditures and procedures for equipment and appliance
maintenance.
 Reviews plans for future buildings and inspects new buildings to ensure
compatibility with existing electrical codes and maintenance standards.
 Supervise and Installation of Fire Hose Cabinet Protection (FHCP) as per
drawing.
 Conduct an inspection for testing of electrical and mechanical works.
 To prepare updated daily accomplishment reports of the team.
 Set-up and operate test equipment to evaluate of development parts.
 Assembles and system under simulated operating conditions and record
result.
 Supervise and assisting the electrical and mechanical foreman in
performing the meggering and testing of cables.
 Prepared design of electrical and mechanical system and other electrical
equipments.
 Review and update all construction drawings prior to the start of
mechanical and electrical construction for installation activities.
 Monitoring and sand blasting of pipe for final coating.
Record of employment;
Position Title : Electrical Foreman
Company : R.H. Al–Marri & Sons Company
P.O. Box 1 Abqaiq 31992 K.S.A.
Project Title : Khursaniyah Pipelines and Communication Rehabilitation
Client : Saudi Arabian Oil Company (ARAMCO)
Inclusive Date : February 4, 2006 to May 10, 2008
Duties and responsibilities;
 Experienced in reading and following electrical program.
 Knowledgeable in executing plans and procedures of preventive and
corrective maintenance.
 Knowledge of electrical applications for high and low voltage electrical
systems.
 Ability to connect and repair the electrical devices according to diagram
such as contractors, photocell, limit switches, thermal overload relay,
relay, motors and other electrical component.
 Responsible for the installation of galvanic and magnesium anode
according to Aramco standard procedures.
 Responsible for the installation & termination of outdoor type switch low
voltage, digital and analog box, (MOV) motor operated valve, 9M – 12M
Poles outdoor type lightning fixture.
 Conduct an Earth resistance testing for ground cables.
 Monitoring for excavation of trenches, laying for underground cables.
 Cable Laying of Power and Instrument cables to the cable tray as per
Saudi Aramco Standard.
 Installation & Termination of digital and analog junction box.
 Installation & Termination of transmitters such as temperature indicator,
flow indicator, pressure indicator, and pressure gauges.
 Competent in operating Hand-Control machine like electric threading
machine, hydraulic knock out puncher, hydraulic crimper and hydraulic
bearing machine.
 Installation & fabricated using hydraulic machines of PVC coated and
RGS conduit to the Switch Rack.
 Fabricated and assembled of Impulse stainless steel tube for Pressure
indicator transmitter (PIT) and Flow indicator transmitter (FIT).
 Installation of electrical main distribution panels, bus bars, air circuit
breaker, cable tray and lay out electrical cables.
 Impulse tubing of stainless steel for Pressure Indicator Transmitter (PIT)
and Flow Indicator Transmitter (FIT).
 Installation of Uninterrupted Power Supply (UPS) Battery from Remote
Terminal Units (RTU) and termination.
 Installation of motor for air handling units, contractor’s timer, limit
switches, water booster pump, sewage pump, compressor for chiller and
electrical termination.
 Installation of motor control with double speed Wye, Delta connection.
 Performs preventive and corrective maintenance for stand by generator
and automatic transfer switchgear.
 Installation of electrical main distribution panel.
 Installation of Main Control Circuit Breakers (MCCB) and monitoring for
Pre – Commissioning.
 Meggering of insulation resistance and testing of power, instrument, and
grounding cables.
 Installation of cable tray as per Issued for Construction (IFC) drawing.
 Facilitate all implementation works regarding electrical and
instrumentation scope of works.
 Monitoring and Installation of Switch Rack & Transformer.
 Monitoring and Pre – Commissioning of Switch rack.
 Installation of galvanic anode for 1- pin station & 3 – pin station to the
given lateral pipes as per drawing.
 Cad welding of cables for cathode protection in the lateral pipes and
termination.
Record of employment;
Position : Project Engineer & Electrical Site Supervisor
Company : Skope Technology Incorporated
Unit 202 2nd
floor 1st
midland Condo 109 Gamboa St. Legaspi
Village, Makati City Philippines
Project Title : Building Construction & Structures Projects
Inclusive Date : April 28, 2005 to January 20, 2006
Duties and responsibilities;
 Build, calibrate, maintain, troubleshoot, and repair electrical instruments
and testing equipments.
 Responsible to assure performance of the work within scope, also comply
the specification and standard drawings.
 Proven ability in the supervision and management of a team with regard
to all aspects from Master plan, Concept, Preliminary and Final Design
stages, including single line diagrams, panel schedules, electrical
schematics and communication plans.
 Coordinate with site in charge and make sure that all activities are in
accordance with standard drawings and Philippines Electrical Codes
(PEC) standard and specification.
 Conduct meggering test and other electrical test such as lightning,
grounding, and metering equipment testing as per specification
requirements and approved procedure.
 Knowledge of electrical installation including substation, power, lighting,
cabling, wiring and grounding and an understanding of installation
specifications and ability to conduct demand load calculations.
 Set up and operate test equipment to evaluate performance of development
parts, assemblies, and system under simulated operating conditions and
record results.
 Conduct inspection for quality control and assurance programs, reporting
findings and recommendations.
 Knowledge of electrical installation including substation, power, lighting,
cabling, wiring and grounding and an understanding of installation
specifications and ability to conduct demand load calculations.
 Supervise and assist Electrical Foreman and Electricians in performing
megger testing on cables, transformer oil circuit breaker, bushing current
and potential transformer and also performed oil circuit breaker and
transformer oil testing.
 Prepared design of electrical distribution system including lighting, power
outlets, motors, fire alarm system, and other electrical equipment.
 Prepares construction contracts and monitor their execution and
distribution.
 Use AutoCAD and calculations software as part of the design process.
SUMMARY OF VARIOUS PROJECTS COMPLETED
Project Title : Provide power supply for Crimping Machine in CE &
Maintenance Warehouse
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00001).
Project Title : Installation of NCB ATM
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00002).
Project Title : 3 Phase power supply to new Kitchen Equipment in MA
Admin Canteen
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00003).
Project Title : Identification of Useable Breakers in 2 Sub Stations for use
Air Monitoring Stations
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00004).
Project Title : Modification of UPS 11 KVA in Admin/IT Room
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00005).
Project Title : Install 2 Additional power Sockets in Display Chiller, Hot
Cabinets and provide 3 New Power Points in Salad
preparation Area in MA Admin Canteen
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00006 & 0007).
Project Title : To Build 3 Storage Rooms under Stair and 01 Mail Storage
Room along Corridor in MA Admin Ground Floor
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00008).
Project Title : To Build 3 Store Rooms & Expansions of HR/General
Service Department Office in MA Admin Building Area.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00010).
Project Title : To Provide power for Air Compressor and 6 Power outlets
for Fire Trucks Charger in Fire Station/Security Command
Center.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00011 & 0013).
Project Title : To Build Gypsum Partition and Door opening on the wall to
make new Office Facility in CE & M Building Ground Floor.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00012).
Project Title : Permanent connection for Oxyfuel Machine in CE & M
Building Ground Floor.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00014).
Project Title : Electrical Connection for Welding Machine in CE & M
Building Ground Floor.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00015).
Project Title : Installation of 480VSocket connection for Welding Machine
in CE & M Building Ground Floor.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00016).
Project Title : Provide power supply to new Hydraulic Column Lift in CE
& M Building Ground Floor.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00020).
Project Title : Installation of 8 Cameras in MA Main Clinic.
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00021).
Project Title : Installation of 4 Additional Light in Central Engineering
Department in File Room First Floor
Ma’aden Aluminum Company (MOC Request no. MA-CE-
MOC-00022).
Project Title : Replace Telephone Switches Kingdom Wide (BI-10-
000246) Rabigh Phase II Petrochemical Project
(Contract # 6600028287) (Electrical Works) K.S.A.
Subject : Communication & Security Projects, Worley Parsons
Project Title : Rabigh Phase II Petrochemical UPS System Project by
Petrofac (Contract Job Code: 6600028287).
Project Title : Rabigh Phase II Petrochemical Permanent Facilities UPS
System Sirti by Project (Contract Job Code: 0 – 5361 –
20- 0000).
Project Title : Design for Abu Safah SCADA/RTU Communication
Network Upgrade (BI-1003040-0001).
Project Title : Replacement of Data Network Equipment, BI-10-00074
Subject : Tele-communication & Electrical work Kingdom Wide
Project Title : Manifa (Civil & Electrical Works, BI-10-00450-006)
(Manifa, K.S.A.) .
Subject : Industrial Security System Division
Project Title : King Abdullah University Sciences
and Technology (KAUST-Thuwal, Jeddah K.S.A.)
Subject : Industrial Security System Division
Project Title : Silver / Auto Mall Center
Subject : Mechanical and Electrical Works for Bldg. 1 & 3
Project Title : Khursaniyah Pipelines and Communication
Projects (Khursaniyah, K.S.A.)
Subject : 16” Oil Pipelines and Scraper Area for Electrical &
Instruments.
Project Title : Star pacific Bldg.
Subject : Electrical Ducting and Civil Works Bldg. Level# 20 & 21
Project Title : Pasig City General Hospital, Pasig City, Philippines
Subject : Electrical Facilities & CCTV Projects
Bldg. Level 1, 2, 3, 4 up to 5
Project Title : Smart Tower
Ayala Makati, Philippines
Subject : Electrical and Communication Projects
Bldg. Level 53, Level 54 to Level 55
Project Title : Banco De Oro, Makati City, Philippines
Subject : Construction of Electrical & Communication Facilities
Projects
PROFESSIONAL LICENSE / AFFILIATION
 Member of the Saudi Council of Engineers (ID No. 215058)
TRAININGS AND SEMINARS
 Helicopter Underwater Escape Training (HUET)
Gulf Technical & Safety Training Center (GTSC)
Location: P.O. Box: 3599 2nd
Industrial Area, Dammam Gulf Technical & Safety
Training Compound, Saudi Arabia
Date: September 09, 2014 valid until September 08, 2017
 Work Permit Receiver Certificate (Saudi Aramco)
Southern Area Industrial Training Division
Location: Box: 5653 Abqaiq, Saudi Arabia
Date: February 27, 2012 until February 27, 2014 (Expired)
 QC Inspector Aramco Approved
Reference No. SC-KAUST–ARAMCO-0697
 In-House Quality Training Program
Saudi Aramco Desktop Standard Version 2007
Location: Sumitomo Conference Room, Kaust Site, Thuwal, K.S.A.
Date: June 25, 2009
 In-House Quality Training Program
Schedule “Q” As Applied in Saudi Aramco LSTK Projects
Location: Sumitomo Conference Room, Kaust Site, Thuwal, K.S.A.
Date: June 15, 2009
CERTIFICATES
 Helicopter Underwater Escape Training Certificate (HUET)
 Saudi Aramco Safety Certificate
 Aramco ID No. 8983193
 Aramco Certificate
 Seas of Technology Contracting Company
 Abdullah Fuoad Holding Company
 Saudi Aramco Work Permit Receiver Certificate
 R.H. Al-Marri Sons @ Company
 Skope Technology Incorporated
 National Polytechnic Institute
 Valid Saudi Driving License
 Philippines Driving License (Code # 1,2,3)
OTHER SKILLS
 Computer Literate
 Light and Heavy Vehicle Driver
 Impulse Tubing of Stainless Steel
 Mechanical Works
 Cathode Protection
 GTAW and SMAW
 Civil Works
 Microsoft Word, Excel, PowerPoint, Windows 95, 98,2000,2003,2005,2007,2012
 Operating System, AutoCAD 2003,20005,2007
 Bentleys Micro Station Version 7 & 8
 Communication Security System Facilities Works
 Planning and Scheduling
 Tele – Communication Works
April 2004 to May 2004 Engineering Aid On Job Training (OJT):
Skope Technology Incorporated
Unit 202 2nd
floor 1st
Midland Condo 109
Gamboa Street. Legaspi Village
Makati City Philippines
SCHOOL SCHOLARSHIP
Cagayan Provincial Government Scholarships (CPGS) since year 1999 up to 2005.
LANGUAGE SPOKEN
 English
 Arabic (Common use)
 Tagalog (Pilipino)
CHARACTER REFERENCES
Engr. Emmanuel Jotojot Engr. Isagani Torres
QC Manager Sr. Project Inspector
Sumitomo Corporation, KSA Electrical Inspector Group
Email:Emmanuel.jotojot@sumitomo-kaust.com KAUST-PIS/PID
Engr. Antonino Mendoza Engr. Jimmy Hatamosa
SR. Telecommunication Engineer SR. Project Inspector
WorleyParsons Engineering Consultancies Co. Communication Inspector Group
Email:Antonino.mendoza@worleyparsons.com KAUST-PIS/PID
I hereby certify that the above information’s are true and correct to the best of my
knowledge and belief.
___________________
Domer L. Javier

More Related Content

What's hot

Naveed Electrical Cv2
Naveed Electrical Cv2Naveed Electrical Cv2
Naveed Electrical Cv2Naveed Akhtar
 
Nawaz CV as of 10-Jan- 16
Nawaz CV as of 10-Jan- 16Nawaz CV as of 10-Jan- 16
Nawaz CV as of 10-Jan- 16mujahid nawaz
 
FAWZEY CV LATEST UPDATE-3
FAWZEY CV LATEST  UPDATE-3FAWZEY CV LATEST  UPDATE-3
FAWZEY CV LATEST UPDATE-3fawzey mukhtar
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016Sher Chuhan
 
Prem CV Oct 2015
Prem CV Oct 2015Prem CV Oct 2015
Prem CV Oct 2015Prem Kumar
 
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)Mark Rodas
 
CV-Sandeep Kumar Updated
CV-Sandeep Kumar UpdatedCV-Sandeep Kumar Updated
CV-Sandeep Kumar UpdatedSANDEEP KUMAR
 
Shameem Ahamed - Electrical Engineer
Shameem Ahamed - Electrical EngineerShameem Ahamed - Electrical Engineer
Shameem Ahamed - Electrical EngineerShameem Ahamed
 
Sameh Youssef _Electrical Engineer_CV
Sameh Youssef _Electrical Engineer_CVSameh Youssef _Electrical Engineer_CV
Sameh Youssef _Electrical Engineer_CVSameh Youssef
 
CV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerCV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerMuhammed Salahuddeen
 

What's hot (20)

resume mike 1
resume mike 1resume mike 1
resume mike 1
 
Naveed Electrical Cv2
Naveed Electrical Cv2Naveed Electrical Cv2
Naveed Electrical Cv2
 
Nawaz CV as of 10-Jan- 16
Nawaz CV as of 10-Jan- 16Nawaz CV as of 10-Jan- 16
Nawaz CV as of 10-Jan- 16
 
Abdelmagid Abdel Aziz
Abdelmagid Abdel AzizAbdelmagid Abdel Aziz
Abdelmagid Abdel Aziz
 
RICHARD HEATH-CV3a
RICHARD HEATH-CV3aRICHARD HEATH-CV3a
RICHARD HEATH-CV3a
 
KEVIN DAVID MORTON cv
KEVIN DAVID MORTON cvKEVIN DAVID MORTON cv
KEVIN DAVID MORTON cv
 
FAWZEY CV LATEST UPDATE-3
FAWZEY CV LATEST  UPDATE-3FAWZEY CV LATEST  UPDATE-3
FAWZEY CV LATEST UPDATE-3
 
jamespickering
jamespickeringjamespickering
jamespickering
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Prem CV Oct 2015
Prem CV Oct 2015Prem CV Oct 2015
Prem CV Oct 2015
 
Michael%20Weir-3
Michael%20Weir-3Michael%20Weir-3
Michael%20Weir-3
 
John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016
 
Update profile 2015
Update profile 2015Update profile 2015
Update profile 2015
 
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)
Resume _ Engr. Mark Joseph R. Rodas _ April 2015 (1)
 
CV-Sandeep Kumar Updated
CV-Sandeep Kumar UpdatedCV-Sandeep Kumar Updated
CV-Sandeep Kumar Updated
 
Shameem Ahamed - Electrical Engineer
Shameem Ahamed - Electrical EngineerShameem Ahamed - Electrical Engineer
Shameem Ahamed - Electrical Engineer
 
VK-Resume
VK-ResumeVK-Resume
VK-Resume
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
Sameh Youssef _Electrical Engineer_CV
Sameh Youssef _Electrical Engineer_CVSameh Youssef _Electrical Engineer_CV
Sameh Youssef _Electrical Engineer_CV
 
CV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerCV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection Engineer
 

Viewers also liked

Viewers also liked (20)

AMM_Resume_160620
AMM_Resume_160620AMM_Resume_160620
AMM_Resume_160620
 
Resume of Mr. Alzen T. Octaviano
Resume of Mr. Alzen T. OctavianoResume of Mr. Alzen T. Octaviano
Resume of Mr. Alzen T. Octaviano
 
Fatima gamal mansour CV
Fatima gamal mansour CVFatima gamal mansour CV
Fatima gamal mansour CV
 
Diosdado CV (updated)(1)
Diosdado CV (updated)(1)Diosdado CV (updated)(1)
Diosdado CV (updated)(1)
 
RESUME OF ALI AL-NASSER, PMT HSE SUPERVISOR.compressed
RESUME OF ALI AL-NASSER, PMT HSE SUPERVISOR.compressedRESUME OF ALI AL-NASSER, PMT HSE SUPERVISOR.compressed
RESUME OF ALI AL-NASSER, PMT HSE SUPERVISOR.compressed
 
Pradeep s (resume)
Pradeep s (resume)Pradeep s (resume)
Pradeep s (resume)
 
1 update resume for electrical engineer
1  update resume for electrical engineer1  update resume for electrical engineer
1 update resume for electrical engineer
 
Eng.yehia ali cv
Eng.yehia  ali  cvEng.yehia  ali  cv
Eng.yehia ali cv
 
Malik updated cv
Malik updated cvMalik updated cv
Malik updated cv
 
Electricidad99electronica
Electricidad99electronicaElectricidad99electronica
Electricidad99electronica
 
RESUME-LEONICO ACOLENTAVA JR
RESUME-LEONICO ACOLENTAVA JRRESUME-LEONICO ACOLENTAVA JR
RESUME-LEONICO ACOLENTAVA JR
 
rayan saleh alhujari
rayan saleh alhujarirayan saleh alhujari
rayan saleh alhujari
 
Nizami cv
Nizami cvNizami cv
Nizami cv
 
MY CV SALEH2016
MY CV SALEH2016MY CV SALEH2016
MY CV SALEH2016
 
Shahzad Ahmed CV
Shahzad Ahmed CVShahzad Ahmed CV
Shahzad Ahmed CV
 
SAUDI ARAMCO ID's
SAUDI ARAMCO ID'sSAUDI ARAMCO ID's
SAUDI ARAMCO ID's
 
CV Dodo NEW
CV Dodo NEWCV Dodo NEW
CV Dodo NEW
 
BRUNO B AMBITO RESUME,NEW UPDATE.DOC
BRUNO B AMBITO RESUME,NEW UPDATE.DOCBRUNO B AMBITO RESUME,NEW UPDATE.DOC
BRUNO B AMBITO RESUME,NEW UPDATE.DOC
 
s.n.dubey
s.n.dubeys.n.dubey
s.n.dubey
 
CV MUTHURAJ MUTHIAH SAFETY OFFICER WORK PERMIT RECEIVER ROAD SAFETY OFFICER ...
CV MUTHURAJ MUTHIAH SAFETY OFFICER  WORK PERMIT RECEIVER ROAD SAFETY OFFICER ...CV MUTHURAJ MUTHIAH SAFETY OFFICER  WORK PERMIT RECEIVER ROAD SAFETY OFFICER ...
CV MUTHURAJ MUTHIAH SAFETY OFFICER WORK PERMIT RECEIVER ROAD SAFETY OFFICER ...
 

Similar to Electrical Engineer Resume: 10+ Years Experience in Saudi Arabia

VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEVIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEvijayabaskar v
 
Saibal Datta_CV15122015
Saibal Datta_CV15122015Saibal Datta_CV15122015
Saibal Datta_CV15122015Saibal Datta
 
Electl Engr_Updated CV_Jesnar Odjinar
Electl Engr_Updated CV_Jesnar OdjinarElectl Engr_Updated CV_Jesnar Odjinar
Electl Engr_Updated CV_Jesnar OdjinarJesnar Odjinar
 
Sutharvinu - Electrical Design engineer
Sutharvinu - Electrical Design engineerSutharvinu - Electrical Design engineer
Sutharvinu - Electrical Design engineerSuthar Vinu
 
ELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEsekar palani
 
Ahmed_Mohammed
Ahmed_MohammedAhmed_Mohammed
Ahmed_Mohammedahmed ali
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland
 
Rana Maqsood Alam Resume (E&I)
Rana Maqsood Alam  Resume (E&I)Rana Maqsood Alam  Resume (E&I)
Rana Maqsood Alam Resume (E&I)rana maqsood
 
Rana maqsood alam resume (e&i) and construction
Rana maqsood alam  resume (e&i) and constructionRana maqsood alam  resume (e&i) and construction
Rana maqsood alam resume (e&i) and constructionrana maqsood
 
consultant eng Ali sman CV A 11
consultant eng Ali sman CV A 11consultant eng Ali sman CV A 11
consultant eng Ali sman CV A 11Ali Elamin
 
Sandher Updated Resume15
Sandher Updated Resume15Sandher Updated Resume15
Sandher Updated Resume15Sandher Subayno
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2 Alaa Ammar
 

Similar to Electrical Engineer Resume: 10+ Years Experience in Saudi Arabia (20)

VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEVIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
 
CV_WALEED
CV_WALEEDCV_WALEED
CV_WALEED
 
Saibal Datta_CV15122015
Saibal Datta_CV15122015Saibal Datta_CV15122015
Saibal Datta_CV15122015
 
MujibCV
MujibCVMujibCV
MujibCV
 
Electl Engr_Updated CV_Jesnar Odjinar
Electl Engr_Updated CV_Jesnar OdjinarElectl Engr_Updated CV_Jesnar Odjinar
Electl Engr_Updated CV_Jesnar Odjinar
 
Sutharvinu - Electrical Design engineer
Sutharvinu - Electrical Design engineerSutharvinu - Electrical Design engineer
Sutharvinu - Electrical Design engineer
 
ELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAE
 
Ahmed_Mohammed
Ahmed_MohammedAhmed_Mohammed
Ahmed_Mohammed
 
talhadiploma.doc
talhadiploma.doctalhadiploma.doc
talhadiploma.doc
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum Vitae
 
Muhammad Danish Rafiq
Muhammad Danish RafiqMuhammad Danish Rafiq
Muhammad Danish Rafiq
 
Ahmed abd elazim c.v
Ahmed abd elazim c.vAhmed abd elazim c.v
Ahmed abd elazim c.v
 
THOWFIC AHAMED CV
THOWFIC AHAMED CVTHOWFIC AHAMED CV
THOWFIC AHAMED CV
 
MANZAR_CVH
MANZAR_CVHMANZAR_CVH
MANZAR_CVH
 
Govind-CVC5
Govind-CVC5Govind-CVC5
Govind-CVC5
 
Rana Maqsood Alam Resume (E&I)
Rana Maqsood Alam  Resume (E&I)Rana Maqsood Alam  Resume (E&I)
Rana Maqsood Alam Resume (E&I)
 
Rana maqsood alam resume (e&i) and construction
Rana maqsood alam  resume (e&i) and constructionRana maqsood alam  resume (e&i) and construction
Rana maqsood alam resume (e&i) and construction
 
consultant eng Ali sman CV A 11
consultant eng Ali sman CV A 11consultant eng Ali sman CV A 11
consultant eng Ali sman CV A 11
 
Sandher Updated Resume15
Sandher Updated Resume15Sandher Updated Resume15
Sandher Updated Resume15
 
C V ALAA AMMAR 2
C V   ALAA AMMAR 2 C V   ALAA AMMAR 2
C V ALAA AMMAR 2
 

Electrical Engineer Resume: 10+ Years Experience in Saudi Arabia

  • 1. 0 Domer Lozano Javier Block 5 Lot 18 Champaca Street Maligaya Park Subdivision Novaliches, Quezon City Mobile No. +966506993894/+639273433903 Email Address: boytoydomer@yahoo.com/boytoydomer@gmail.com ELECTRICAL ENGINEER PROFESSIONAL WORK EXPERIENCE CAREER SUMMARY 10+ years of work experience in the field of Electrical Power System and Mechanical works. Knowledge in design & construction activities of Oil, Gas, and Water Rehabilitation, primary and secondary overhead power distribution lines, installation and maintenance of Electrical & Instrument such as Motor Operated Valves, electric motors, motor control system, lightning systems, high medium and low voltage Switch Gears, Transformers & Switch Racks specialized in distribution control panel and remote control. Knowledge in implementation of Cathode Protection/Civil works, Telecommunication works, Security System Facilities works, Design & Engineering. EDUCATIONAL ATTAINMENT College : Cagayan State University Bachelor of Science in Electrical Engineering 1999 – 2005 Other Course : Industrial Motor Control National Polytechnic Institute November 9 – 23 2005 Secondary : Our Lady of Snows Academy 1995 - 1999 Tertiary : Sabino T. Acorda Central School 1988 – 1994 PERSONAL DATA Age & Date of Birth : 33 years old & September 05, 1981 Nationality : Filipino Sex : Male Height : 5’7 ½” Weight : 165 lbs. Civil Status : Married Wife : Lailanie B. Javier Religion : Roman Catholic
  • 2. Position Title : Electrical Design Engineer Company : Saudi Engineering Group International Saihati Building King Abdul Aziz Street P.O. Box 5289 - Dammam, K.S.A. Under supply contract with WorleyParsons Engineering Consultancies Company Al-Jazira Building King Abdullah Bin Abdul Aziz Road P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A. Project Title : Upgrade Offshore Security Facility (Kingdom Wide) (BI #10-01377). Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : June 29, 2015 up to Present  Estimating material, construction, and labor costs, and project timescale.  Develop engineering projects analysis to include preliminary design, calculations, budget analysis, life cycle costs plus equipment selection.  Cost and weight targets must be managed and met. Position Title : Electrical Design Engineer Company : Saudi Engineering Group International Saihati Building King Abdul Aziz Street P.O. Box 5289 - Dammam, K.S.A. Under supply contract with WorleyParsons Engineering Consultancies Company Al-Jazira Building King Abdullah Bin Abdul Aziz Road P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A. Project Title : Yanbu Refinery Project MC – 2 TETRA Radio System (Contract Job Code # 403011-00334). Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : April 16, 2015 up to Present  Develop engineering projects analysis to include preliminary design, calculations, budget analysis, life cycle costs plus equipment selection.  Estimating material, construction, and labor costs, and project timescales.  Create and amend own drawings on Auto CAD 2D & micro station version-8.  Voltage drop and Cables sizing summary and adequacy calculation for UPS and circuit breakers.  Review designs development for conformance with applicable codes, utilizing engineering standards along with good engineering practices.  Manage own portfolio of design work, on time and within budget.  Ensure compliance and offer recommendations for Health, Safety & Environmental issues relating to technical activities,
  • 3.  Maintain an on-going awareness of national and international standards of technical expertise, reporting back any significant changes.  Cost and weight targets must be managed and met.  Follow and contribute to the development of the Best Practice guidelines as laid out in quality documentation. Record of employment; Position Title : Lead Electrical Engineer Company : Saudi Engineering Group International Saihati Building King Abdul Aziz Street P.O. Box 5289 - Dammam, K.S.A. Client : Maaden Aluminium Company (MAC) Central of Engineering Inclusive Date : November 04, 2014 up to April 02, 2015 Duties and responsibilities;  Create detailed technical engineering specifications for the production team to ensure the product’s functionality and that it meets the specific required standards of performance. Required specifications for electrical control system and equipment’s for use across many sectors, including:  Refinery Aluminum Plant  Rolling Mill Aluminum Plant  Smelter Aluminum Plant Modification fore Electrical Works: Position Title : Electrical Lead Engineer Project Title : Provide power supply for Crimping Machine in CE & Maintenance Workshop (MOC Request no. MA-CE-MOC-0001). Inclusive Date : December 12, 2014 to February 16, 2015 Project Title : Installation of NCB ATM (MOC Request no. MA-CE-MOC-0002). Inclusive Date : July 16, 2014 to up March 04, 2015 Project Title : 3 Phase Power Supply to new Kitchen Equipment in MA Admin Canteen (MOC Request no. MA-CE-MOC-0003). Inclusive Date : November 12, 2014 to up Present Project Title : Identification of Useable Breakers in 2 Sub Stations for use Air Monitoring Stations in Natural Gas Line (NGL) (MOC Request no. MA-CE-MOC-0004). Inclusive Date : August 18, 2014 to up Present Project Title : Modification of UPS (11KVA) in Admin/IT Room (MOC Request no. MA-CE-MOC-0005). Inclusive Date : January 28, 2015 to February 16, 2015 Project Title : Install 2 Additional Power Sockets in Display Chiller and Hot Cabinets and Provide 3 New Power Points in Salad Preparation
  • 4. Area in MA Admin Canteen (MOC Request no. MA-CE-MOC-0006 & 0007). Inclusive Date : February 09, 2015 to up March 31, 2015 Project Title : To Build 3 Storage Room under Stair and 01 Mail Storage Room along Corridor in MA Admin Ground Flour (MOC Request no. MA-CE-MOC-0008). Inclusive Date : January 06, 2015 to up March 23, 2015 Project Title : To Build 3 Storage Rooms and Expansion of HR/General Services Department 4 Offices in MA Admin Building Area (MOC Request no. MA-CE-MOC-0010). Inclusive Date : February 17, 2015 to up Present Project Title : To provide power for Air Compressor and 6 power outlets for Fire Trucks Charger in Fire Station/Security Command Center (MOC Request no. MA-CE-MOC-0011 & 0013). Inclusive Date : February 24, 2015 to up Present Project Title : To Build Gypsum Partition and Door opening on the wall to make new Office Facility in CE & M Building 1/Floor (MOC Request no. MA-CE-MOC-0012). Inclusive Date : March 03, 2015 to up Present Project Title : Permanent connection for Oxyfuel Machine in CE & M Workshop 1/Floor (MOC Request no. MA-CE-MOC-0014). Inclusive Date : March 14, 2015 to up Present Project Title : Electrical Connection for Welding Machine in CE & M Workshop 1/Floor (MOC Request no. MA-CE-MOC-0015). Inclusive Date : March 14, 2015 to up Present Project Title : Installation of 480VSocket connection for Welding Machine in CE & M Workshop 1/Floor (MOC Request no. MA-CE-MOC-0016). Inclusive Date : March 14, 2015 to up Present Project Title : Provide power supply to new Hydraulic Column Lift in CE & M Workshop Ground Floor (MOC Request no. MA-CE-MOC-0020). Inclusive Date : March 11, 2015 up to Present Project Title : Installation of 8 Cameras in MA Main Clinic (MOC Request no. MA-CE-MOC-0021). Inclusive Date : March 25, 2015 up to Present Project Title : Installation of 4 Additional Light in CE File Room (MOC Request no. MA-CE-MOC-0022). Inclusive Date : March 30, 2015 up to April 0, 2015
  • 5. Duties and responsibilities;  Make site visits to ascertain detailed information related to the design and planning of a project.  Preparing for scope of work of the project.  Manage own portfolio of design work, on time and within budget.  Proven ability in the supervision and management of a team with regard to all aspects from Master plan, Concept, Preliminary and Final Design stages, including single line diagrams, panel schedules, electrical schematics diagram.  Estimates, prepares and assigns the resources such as manpower, materials, consumables, equipment, tools, etc., required for all electrical and related works prior to execution.  Monitoring and Supervise to install of electrical cable, electrical main distribution panels, non-fusible disconnect switch air circuit breaker, convenient outlet and lay out electrical cables including necessary conduiting.  Voltage drop and Cables sizing summary and adequacy calculation for UPS and circuit breakers.  Lead in the implementation of innovative design solutions using the latest industry standards considering quality, safety and sustainability as a minimum.  Preparing for Management of Change (MOC) and Minor Plant Monitoring Request (MPMR) to get signatory for designation person.  Preparing for Pre Startup Safety Review (PSSR) Form, Minor Plant Modification – Close Out Form and Minor Plant Modification – Turn Over Checklist.  Testing and Commissioning of Electrical panel boards and convenient outlet ready for startup.  Take responsibility for all technical aspects of electrical / building services work performed by the company from the inception stage through to final completion of projects and client handover.  Completion of project and documents shall turn over to the engineering document controller.  Direct report to Project Manager for the status of works. Position Title : Electrical Design Engineer Company : Saudi Engineering Group International Saihati Building King Abdul Aziz Street P.O. Box 5289 - Dammam, K.S.A. Under supply contract with WorleyParsons Engineering Consultancies Company Al-Jazira Building King Abdullah Bin Abdul Aziz Road P.O. Box 31699, Al – Khobar, 31952 Eastern Province K.S.A. Project Title : Replacement of Telephone Switches Kingdom Wide (BI–10–000246, Contract # 6600028287). Client : Saudi Arabian Oil Company (ARAMCO)
  • 6. Inclusive Date : July 28, 2013 to November 03, 2014 Project Title : Rabigh Phase II Petrochemical UPS System Project by Petrofac (Contract Job Code: 6600028287). Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : September 01, 2013 to May 15, 2014 Project Title : Rabigh Phase II Petrochemical Permanent Facilities UPS System Sirti by Project (Contract Job Code: 0-5361-20-0000). Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : December 29, 2013 to May 15, 2014 Project Title : Design for Abu Safah SCADA/RTU Communication Network Upgrade (BI-1003040-0001). Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : April 06, 2014 to May 15, 2014 Duties and responsibilities;  Make site visits to ascertain detailed information related to the design and planning of a project.  Manage own portfolio of design work, on time and within budget.  Take responsibility for all technical aspects of electrical / building services work performed by the company from the inception stage through to final completion of projects and client handover.  Manage the calculation for DC Rectifier Systems, Inverter Systems, UPS System.  Create and amend own drawings on Auto CAD 2D & micro station version-8.  Liaising with structural engineers, architects, surveyors etc.  Estimating material, construction, and labor costs, and project timescales.  Preparing for engineering mark ups for the design, and issued for Check Print & Squad Check ready for Issued for Construction.  Voltage drop and Cables sizing summary and adequacy calculation for UPS and circuit breakers.  Ensure compliance and offer recommendations for Health, Safety & Environmental issues relating to technical activities,  Maintain an on-going awareness of national and international standards of technical expertise, reporting back any significant changes.  Assist the operating units to undertake design assignments, i.e. schematic and detailed design of installations/schemes within the remit of the jobholder's specialist skill area.  Develop engineering projects analysis to include preliminary design, calculations, budget analysis, life cycle costs plus equipment selection.  Use AutoCAD and calculations software as part of the design process.  Assist in the preparation of drawings of high quality in Micro station for the infrastructure disciplines.
  • 7.  Cost and weight targets must be managed and met.  Follow and contribute to the development of the Best Practice guidelines as laid out in quality documentation  The selection and application of materials and processes appropriate to each design element.  Lead in the implementation of innovative design solutions using the latest industry standards considering quality, safety and sustainability as a minimum.  Review designs development for conformance with applicable codes, utilizing engineering standards along with good engineering practices. Record of employment; Position Title : Site Engineer (Self Employed) Project Title : 3 Story Building & 2 Story Building in Maligaya Park Subdivision Novaliches, Quezon City Subject : Electrical work Inclusive Date : August 25, 2012 to February 10, 2013 Duties and responsibilities;  Directly responsible for the safety of all electrical groups’ personnel of the project by ensuring that the project execution will be done according to all applicable health, safety, sanitary and environmental standards.  Assign targets for accomplishments and ensure targets are met on daily basis for all electrical groups at site.  Coordinates all parties involved in the planning, design, and construction process.  To identify and recommend opportunities to improve the range, quality and cost effectiveness of services to the client.  Ensures that the facilities are maintained and repaired in a cost effective manner, with consideration given to quality and customer service.  Prioritize and resolve all technical problems within minimum amount of time and cost.  Must be able to demonstrate leadership and influencing skills.  Has overall responsibility for the planning, management, coordinating and construction project and will work closely with a range of other professional during the contract progress.  Proven ability in the supervision and management of a team with regard to all aspects from Master plan, Concept, Preliminary and Final Design stages, including single line diagrams, panel schedules, electrical schematics diagram.  Installation of electrical main distribution panels, air circuit breaker, convenient outlet, electrical metallic tubing pipe, flexible hose and lay - out electrical cables.  Termination of cables and testing commissioning of electrical panel boards and convenient outlet ready for startup.
  • 8.  Coordinate with site in charge and make sure that all activities are in accordance with standard drawings and Philippines Electrical Codes (PEC) standard and specification.  Providing indigent professional advice and guidance.  Ensuring that the quality standards and all health and safety checks are adhered to.  Coordinate to the owner for the payment of accomplished project.  Develops conceptual plans and budgets for facilities project to support fiscal decision making.  Prepare for requests for proposal and conducts all necessary meeting to facilitate hiring architectural and construction management services.  Monitors and reports on all phases of planning and construction. Record of employment; Position Title : Project Engineer (Self Employed) Company : Kashmir Line Contracting Company Block 5 Lot-18 Champaca St. Maligaya park subdivision, Quezon City Project Title : 8 Doors Building in Ugong, Valenzuela City Philippines Subject : Electrical Works Inclusive Date : July 20, 2012 to September 26, 2012 Duties and responsibilities;  Has overall responsibility for the planning, management, coordinating and construction project and will work closely with a range of other professional during the contract progress.  Proven ability in the supervision and management of a team with regard to all aspects from Master plan, Concept, Preliminary and Final Design stages, including single line diagrams, panel schedules, electrical schematics diagram  Installation of electrical main distribution panels, air circuit breaker, convenient outlet and lay out electrical cables.  Testing and Commissioning of Electrical panel boards and convenient outlet ready for startup.  Coordinate with site in charge and make sure that all activities are in accordance with standard drawings and Philippines Electrical Codes (PEC) standard and specification.  Providing indigent professional advice and guidance.  Ensuring that the quality standards and all health and safety checks are adhered to.  Coordinate to the owner for the payment of accomplished project.  Develops conceptual plans and budgets for facilities project to support fiscal decision making.  Prepare for requests for proposal and conducts all necessary meeting to facilitate hiring architectural and construction management services.  Monitors and reports on all phases of planning and construction.
  • 9.  Proven ability in the supervision and management of a team with regard to all aspects from Master plan, Concept, Preliminary and Final Design stages, including single line diagrams, panel schedules, electrical schematics diagram.  Installation of electrical main distribution panels, air circuit breaker, convenient outlet, electrical metallic tubing pipe, flexible hose and lay - out electrical cables.  Termination of cables and testing commissioning of electrical panel boards and convenient outlet ready for startup. Record of employment; Position Title : Project Engineer / Senior Electrical Engineer Company : Seas of Technology Contracting Company Al – Khobar, 31952 Eastern Province, P.O. Box 31668, K.S.A Project Title : Replacement of Data Network Equipment BI-10-00074 Kingdom Wide, Saudi Arabia (Tele-Communication & Electrical Works) Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : September 28, 2010 to July 13, 2012 Duties and responsibilities;  Has overall responsibility for the planning, management, coordinating and construction project and will work closely with a range of other professional during the contract progress.  Estimates, prepares and assigns the resources such as manpower, materials, consumables, equipment, tools, etc., required for all electrical and related works prior to execution.  Attending pre - site and on – site meeting during the contract, liaising of range of other professionals involved with the project in Saudi Aramco and Saudi Electric Company.  Providing indigent professional advice and guidance.  Ensuring that the quality standards and all health and safety checks are adhered to.  Develops conceptual plans and budgets for facilities project to support fiscal decision making.  Coordinates with the proponent groups and building committees to facilitate the rational facility planning, budgeting and scheduling.  Prepare for requests for proposal and conducts all necessary meeting to facilitate hiring architectural and construction management services.  Monitors and reports on all phases of planning and construction.  Conduct site surveys, Prepare plans, lay out and designs.  Coordinates all parties involved in the planning, design, and construction process.  Develops and maintains facility project budgets.  Conduct pre-construction conference, review bids, is recommends award of contract.
  • 10.  Check plans estimating the bill of quantity; send the quotation to the suppliers, clients and purchasing of materials, equipment for conformity with specifications.  Reviews contract plans and specifications for compliance with appropriate building codes and project requirements.  Receives pay request for professional consultants and contractors and approved for payments.  Monitors and facilitates resolution of construction contract disputes and claims.  Monitors construction contract close-out and maintain documentation files.  Monitor the announcement projects of Saudi Electric Company (SEC) in their website.  Assists in development of new standards of practice for Project Management activities.  Skill in reading and interpreting plans and specifications and to compare with them construction progress.  In case of emergency, I should be able to solve problems for his team members.  Knowledge of current status of costs of new construction, escalation factors, and market trends.  Knowledge of building codes and standards of practice.  Must suggest new policies and modifications in order to reform the nature of work.  It is his prime most duty to participate in meetings, discussions, project site visits, workshops and hearings.  Must has keep preparing status reports and presenting them to higher managing authorities for scrutinizing.  Monitor the installation of Access Data Network Equipments in North Area, Central Region & Western Region.  Monitor the installation of PROCURVE Switch, HP 3500yl-24G-PWR (J8692A).  Monitor the installation of PROCURVE Switch, HP 5406zl Intelligent Edge (J8697A).  Monitor the installation of PROCURVE Switch, HP 8212zl Switch Base System (J8715B).  Monitor the installation of Remote Serial Router (RSR), Cisco 3945, & Multi – Mode Extender (MME), MACS ET-CB20.  Monitor the installation of Cube IT Cabinet, 12RU & 7 feet. Record of employment; Position Title : Project Manager Company : Sumitomo Corporation Seas of Technology Contracting Company Al–Khobar, 31952 Eastern Province P.O. Box 31668, K.S.A.
  • 11. Project Title : Manifa (Civil & Electrical Works, BI-10-00450-006) : Manifa Communication SCADA/RTU & Security Systems Projects (GOSP Plant) Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : April 5, 2010 up to September 25, 2011 Duties and responsibilities;  Knowledge of estimating the cost and bill of quantity for the project.  Monitoring and execute the work of our teams and preparing the report to submit in the meeting.  Must has keep preparing status reports and presenting them to higher managing authorities for scrutinizing.  Has overall responsibility for the planning, management, coordinating and construction project and will work closely with a range of other professional during the contract progress.  Representing the interest of the Clients.  Attending pre - site and on – site meeting during the contract, liaising of range of other professionals involved with the project.  Direct reporting to the Chief of Executive Officer for update and progress report of the project.  Ensuring that the quality standards and all health and safety checks are adhered to.  Keeping track of progress and ensuring that the project is on time and on budget.  Prepare for requests for proposal and conducts all necessary meeting to facilitate hiring architectural and construction management services.  Monitors and reports on all phases of planning and construction.  Coordinates all parties involved in the planning, design, and construction process.  Prepares contracts change orders and monitors their execution.  Costs estimate the additional work and preparing for change order to the contractor.  Reviews contract plans and specifications for compliance with appropriate building codes and project requirements.  Monitors and facilitates resolution of construction contract disputes and claims.  Monitors construction contract close-out and maintain documentation files.  Skill in reading and interpreting plans and specifications and to compare with them construction progress.  Knowledge of facilities planning and construction management processes and procedures.  Prepares contracts change orders and monitors their execution.  Knowledge of laws governing construction contracts and contracting.  Knowledge of construction materials and methods.
  • 12.  Knowledge of supervisory practices and principles.  It is his prime most duty to participate in meetings, discussions, project site visits, workshops and hearings.  Must determine the resources required for the purpose of production.  Responsible for Health, Safety and Environment (HSE) of my people while working on job sites as well as on the quality and man hour safety. Record of employment; Position Title : Electrical Engineer QA/QC Inspector Company : Abdulla Fuoad Holding Company Industrial Security & System Division P.O. Box 257 Damman 31411 K.S.A Project Title : King Abdullah University Science and Technology (Communication Security System & Facilities) Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : January 20, 2009 to January 20, 2010 Duties and responsibilities;  Direct responsible for the materials inspection delivered on the job site base on SAMSS and Saudi Aramco standard.  Assist to the QA/QC Manager for preparation Inspection Assignment Package, Construction method statement of Material Submittal.  Coordinates and monitoring that the location of HVAC and MVAC power cables that installed as per Drawing of Issued for Construction (IFC) that approved by Aramco Standard.  Preparing of Ready for Inspection (RFI) Check list.  Prepare inspection schedule for the planned quality activities during the procurement, construction and pre - commissioning work phases.  Conduct of inspection and test of electrical and civil works.  Preparing of BOQ and Technical Query for Request for Approval (RFA) Checklist as per Aramco Standard.  Preparing for the Technical Query (TQ) for the new drawing, red line drawing and submit to the Aramco office of Project Management Team.  Maintain and monitor the implementation of approved QA/QC procedures, Inspection plan and Construction Work Methods.  Monitors daily site progress and evaluate the project schedule, construction workmanship including QA/QC issues, procurement activities and status.  Monitoring of High, Medium Voltage and Low Voltage cables for meggering resistance test and splicing.  Monitoring, Pre-Commissioning of High Voltage Step–Up and Step– Down Transformers and high potential test as per Aramco procedures.  Coordinate the implementation of commissioning plan with Commissioning lead at site. Responsible for ensuring timely completion of commissioning progress
  • 13.  Conduct and Inspection the termination of High and Medium voltage power cables to the transformers.  Monitoring of installation of Radar and termination of power cables.  Calculated the power cables schedule for Voltage drop and Load schedule as per Aramco Standard for additional works.  Experienced in reading and following electrical program as per Aramco Standard.  Monitoring and assembled of Walkthrough machine and installation of X- Ray machines and Radio Frequency Identification (RFID) License Plate Readers System (LPRS), Arm Barriers, Card Readers, Hydraulic Crash Barriers.  Coordinate to the Project Inspector Division (PID) and inspect the location of Card readers, Magnetic Door Lock, Door Strike, and Snap Shot Cameras, Hydraulic Crash Barrier and Metal Detector.  Expedite the connectivity of Fiber Optic cables to the Cisco Switch.  Ensure availability of critical materials, expedite material issues, coordinate and push company buyers to deliver critical materials as soon as possible.  Ensure material traceability keeping of vendor inspection certificates, purchase orders, materials receipt records and calibration certificates.  Conduct and inspection upon arrival of the materials to the lay down yard prepare materials receiving report and attach inspection checklist and testing report.  Ensure commitment of site material deliveries.  Expedite the technical issues to facilitate construction phase.  Ensure all works done by construction supervisions are all within client specifications engineering standards, materials specifications scope of works and contract amendments.  Monitoring of field activities lay down yard and issues Non Conformance Report against non – complying and proposed corrective action.  Monitoring of continuity testing for Medium and Low voltage power and control cables.  Conduct an inspection for Fusion Bonded Epoxy coated rebar's (FBE). Reinforcing steel, embedded item form closures for Cameras and Microwaves foundation.  Coordinates the location of Compaction Testing Test to the PID.  Coordinates the location of Lean concrete for ready for concrete casting pouring.  Conduct an inspection for the coming of the new delivery materials as per the Bill of Quantity (BOQ) ordered.  Monitoring of concrete casting pouring for Cameras and Microwaves foundations.  To prepare updated daily accomplishment reports of the team.  Knowledge of estimating, budgeting, scheduling practices.  Set-up and operate test equipment to evaluate of development parts.
  • 14.  Assembles and system under simulated operating conditions and record result.  Review and update all construction drawing prior to the start of electrical and civil works construction for installation activities.  Concrete Moisture Field Test of Cameras and Microwaves foundation ready for applying of Bitumen coating.  Monitoring and installation of Cameras, Microwaves Intrusion Detection Systems poles.  Perform miscellaneous duties as directed by Site Manager/Project Manager.  Coordinate the locations of Camera's and Microwaves Intrusion Detection System (MIDS) Foundation as per Aramco Standard drawing.  Answering inspections to the owners RFI in line with approved procedures, specifications, codes and standards or site technical queries and field change design issued by engineering. Follow-up owner’s inspection plans and approved inspection procedures. Keep the original required documentation of inspections in order to document the works provided. Specify if the owner works status is endorsed and inform them about any encountered aspects the job.  Inspection of the HVAC, MVAC & LVAC cables installation, start-up, air balancing, pre-commissioning and commissioning of the Electrical System and building service scope.  Clearing of generated Punch List Items, as well as leading and provide details to subcontractor on how to clear punch list on easy manner of work execution.  Review, comment and recommend approval on contractor’s shop drawings, technical field queries, Method Statements, Inspection and Test Plans  Monitoring and installation of Pan Tilt Zoom (PTZ) & Dome, Fixed cameras, Microwaves Intrusion Detection Systems, Ex–Ray Machine and ID Budging. Record of Employment; Position Title : Electrical & Mechanical Site Supervisor Company : Skope Technology Incorporated Unit 202, 2nd Floor 1st Midland Condo 109 Gamboa St. Legaspi Village, Makati City, Philippines Project Title : Fire Alarm Protection Client : Silver City/Auto Mall Center Inclusive Date : July10, 2008 to December 23, 2008 Duties and responsibilities;  Supervise and Installation of 1” - 6” diameter pipe schedule 40 - 80 fabricated and welding.  Supervise and installation of gate valves and supervisory switch to the pipe.
  • 15.  Monitoring and installation of electrical cables to the supervisory switch and termination.  Trained or informs the employees of new work methods and procedures, changes in safety regulations, work policies and electrical codes and standards.  Plans and develops work schedules, equipment usage schedules, priority of electrical expenditures and procedures for equipment and appliance maintenance.  Reviews plans for future buildings and inspects new buildings to ensure compatibility with existing electrical codes and maintenance standards.  Supervise and Installation of Fire Hose Cabinet Protection (FHCP) as per drawing.  Conduct an inspection for testing of electrical and mechanical works.  To prepare updated daily accomplishment reports of the team.  Set-up and operate test equipment to evaluate of development parts.  Assembles and system under simulated operating conditions and record result.  Supervise and assisting the electrical and mechanical foreman in performing the meggering and testing of cables.  Prepared design of electrical and mechanical system and other electrical equipments.  Review and update all construction drawings prior to the start of mechanical and electrical construction for installation activities.  Monitoring and sand blasting of pipe for final coating. Record of employment; Position Title : Electrical Foreman Company : R.H. Al–Marri & Sons Company P.O. Box 1 Abqaiq 31992 K.S.A. Project Title : Khursaniyah Pipelines and Communication Rehabilitation Client : Saudi Arabian Oil Company (ARAMCO) Inclusive Date : February 4, 2006 to May 10, 2008 Duties and responsibilities;  Experienced in reading and following electrical program.  Knowledgeable in executing plans and procedures of preventive and corrective maintenance.  Knowledge of electrical applications for high and low voltage electrical systems.  Ability to connect and repair the electrical devices according to diagram such as contractors, photocell, limit switches, thermal overload relay, relay, motors and other electrical component.  Responsible for the installation of galvanic and magnesium anode according to Aramco standard procedures.
  • 16.  Responsible for the installation & termination of outdoor type switch low voltage, digital and analog box, (MOV) motor operated valve, 9M – 12M Poles outdoor type lightning fixture.  Conduct an Earth resistance testing for ground cables.  Monitoring for excavation of trenches, laying for underground cables.  Cable Laying of Power and Instrument cables to the cable tray as per Saudi Aramco Standard.  Installation & Termination of digital and analog junction box.  Installation & Termination of transmitters such as temperature indicator, flow indicator, pressure indicator, and pressure gauges.  Competent in operating Hand-Control machine like electric threading machine, hydraulic knock out puncher, hydraulic crimper and hydraulic bearing machine.  Installation & fabricated using hydraulic machines of PVC coated and RGS conduit to the Switch Rack.  Fabricated and assembled of Impulse stainless steel tube for Pressure indicator transmitter (PIT) and Flow indicator transmitter (FIT).  Installation of electrical main distribution panels, bus bars, air circuit breaker, cable tray and lay out electrical cables.  Impulse tubing of stainless steel for Pressure Indicator Transmitter (PIT) and Flow Indicator Transmitter (FIT).  Installation of Uninterrupted Power Supply (UPS) Battery from Remote Terminal Units (RTU) and termination.  Installation of motor for air handling units, contractor’s timer, limit switches, water booster pump, sewage pump, compressor for chiller and electrical termination.  Installation of motor control with double speed Wye, Delta connection.  Performs preventive and corrective maintenance for stand by generator and automatic transfer switchgear.  Installation of electrical main distribution panel.  Installation of Main Control Circuit Breakers (MCCB) and monitoring for Pre – Commissioning.  Meggering of insulation resistance and testing of power, instrument, and grounding cables.  Installation of cable tray as per Issued for Construction (IFC) drawing.  Facilitate all implementation works regarding electrical and instrumentation scope of works.  Monitoring and Installation of Switch Rack & Transformer.  Monitoring and Pre – Commissioning of Switch rack.  Installation of galvanic anode for 1- pin station & 3 – pin station to the given lateral pipes as per drawing.  Cad welding of cables for cathode protection in the lateral pipes and termination.
  • 17. Record of employment; Position : Project Engineer & Electrical Site Supervisor Company : Skope Technology Incorporated Unit 202 2nd floor 1st midland Condo 109 Gamboa St. Legaspi Village, Makati City Philippines Project Title : Building Construction & Structures Projects Inclusive Date : April 28, 2005 to January 20, 2006 Duties and responsibilities;  Build, calibrate, maintain, troubleshoot, and repair electrical instruments and testing equipments.  Responsible to assure performance of the work within scope, also comply the specification and standard drawings.  Proven ability in the supervision and management of a team with regard to all aspects from Master plan, Concept, Preliminary and Final Design stages, including single line diagrams, panel schedules, electrical schematics and communication plans.  Coordinate with site in charge and make sure that all activities are in accordance with standard drawings and Philippines Electrical Codes (PEC) standard and specification.  Conduct meggering test and other electrical test such as lightning, grounding, and metering equipment testing as per specification requirements and approved procedure.  Knowledge of electrical installation including substation, power, lighting, cabling, wiring and grounding and an understanding of installation specifications and ability to conduct demand load calculations.  Set up and operate test equipment to evaluate performance of development parts, assemblies, and system under simulated operating conditions and record results.  Conduct inspection for quality control and assurance programs, reporting findings and recommendations.  Knowledge of electrical installation including substation, power, lighting, cabling, wiring and grounding and an understanding of installation specifications and ability to conduct demand load calculations.  Supervise and assist Electrical Foreman and Electricians in performing megger testing on cables, transformer oil circuit breaker, bushing current and potential transformer and also performed oil circuit breaker and transformer oil testing.  Prepared design of electrical distribution system including lighting, power outlets, motors, fire alarm system, and other electrical equipment.  Prepares construction contracts and monitor their execution and distribution.  Use AutoCAD and calculations software as part of the design process.
  • 18. SUMMARY OF VARIOUS PROJECTS COMPLETED Project Title : Provide power supply for Crimping Machine in CE & Maintenance Warehouse Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00001). Project Title : Installation of NCB ATM Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00002). Project Title : 3 Phase power supply to new Kitchen Equipment in MA Admin Canteen Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00003). Project Title : Identification of Useable Breakers in 2 Sub Stations for use Air Monitoring Stations Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00004). Project Title : Modification of UPS 11 KVA in Admin/IT Room Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00005). Project Title : Install 2 Additional power Sockets in Display Chiller, Hot Cabinets and provide 3 New Power Points in Salad preparation Area in MA Admin Canteen Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00006 & 0007). Project Title : To Build 3 Storage Rooms under Stair and 01 Mail Storage Room along Corridor in MA Admin Ground Floor Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00008). Project Title : To Build 3 Store Rooms & Expansions of HR/General Service Department Office in MA Admin Building Area. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00010). Project Title : To Provide power for Air Compressor and 6 Power outlets for Fire Trucks Charger in Fire Station/Security Command Center. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00011 & 0013). Project Title : To Build Gypsum Partition and Door opening on the wall to make new Office Facility in CE & M Building Ground Floor. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00012).
  • 19. Project Title : Permanent connection for Oxyfuel Machine in CE & M Building Ground Floor. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00014). Project Title : Electrical Connection for Welding Machine in CE & M Building Ground Floor. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00015). Project Title : Installation of 480VSocket connection for Welding Machine in CE & M Building Ground Floor. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00016). Project Title : Provide power supply to new Hydraulic Column Lift in CE & M Building Ground Floor. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00020). Project Title : Installation of 8 Cameras in MA Main Clinic. Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00021). Project Title : Installation of 4 Additional Light in Central Engineering Department in File Room First Floor Ma’aden Aluminum Company (MOC Request no. MA-CE- MOC-00022). Project Title : Replace Telephone Switches Kingdom Wide (BI-10- 000246) Rabigh Phase II Petrochemical Project (Contract # 6600028287) (Electrical Works) K.S.A. Subject : Communication & Security Projects, Worley Parsons Project Title : Rabigh Phase II Petrochemical UPS System Project by Petrofac (Contract Job Code: 6600028287). Project Title : Rabigh Phase II Petrochemical Permanent Facilities UPS System Sirti by Project (Contract Job Code: 0 – 5361 – 20- 0000). Project Title : Design for Abu Safah SCADA/RTU Communication Network Upgrade (BI-1003040-0001). Project Title : Replacement of Data Network Equipment, BI-10-00074 Subject : Tele-communication & Electrical work Kingdom Wide Project Title : Manifa (Civil & Electrical Works, BI-10-00450-006) (Manifa, K.S.A.) . Subject : Industrial Security System Division Project Title : King Abdullah University Sciences and Technology (KAUST-Thuwal, Jeddah K.S.A.)
  • 20. Subject : Industrial Security System Division Project Title : Silver / Auto Mall Center Subject : Mechanical and Electrical Works for Bldg. 1 & 3 Project Title : Khursaniyah Pipelines and Communication Projects (Khursaniyah, K.S.A.) Subject : 16” Oil Pipelines and Scraper Area for Electrical & Instruments. Project Title : Star pacific Bldg. Subject : Electrical Ducting and Civil Works Bldg. Level# 20 & 21 Project Title : Pasig City General Hospital, Pasig City, Philippines Subject : Electrical Facilities & CCTV Projects Bldg. Level 1, 2, 3, 4 up to 5 Project Title : Smart Tower Ayala Makati, Philippines Subject : Electrical and Communication Projects Bldg. Level 53, Level 54 to Level 55 Project Title : Banco De Oro, Makati City, Philippines Subject : Construction of Electrical & Communication Facilities Projects PROFESSIONAL LICENSE / AFFILIATION  Member of the Saudi Council of Engineers (ID No. 215058) TRAININGS AND SEMINARS  Helicopter Underwater Escape Training (HUET) Gulf Technical & Safety Training Center (GTSC) Location: P.O. Box: 3599 2nd Industrial Area, Dammam Gulf Technical & Safety Training Compound, Saudi Arabia Date: September 09, 2014 valid until September 08, 2017  Work Permit Receiver Certificate (Saudi Aramco) Southern Area Industrial Training Division Location: Box: 5653 Abqaiq, Saudi Arabia Date: February 27, 2012 until February 27, 2014 (Expired)  QC Inspector Aramco Approved Reference No. SC-KAUST–ARAMCO-0697  In-House Quality Training Program Saudi Aramco Desktop Standard Version 2007 Location: Sumitomo Conference Room, Kaust Site, Thuwal, K.S.A. Date: June 25, 2009  In-House Quality Training Program
  • 21. Schedule “Q” As Applied in Saudi Aramco LSTK Projects Location: Sumitomo Conference Room, Kaust Site, Thuwal, K.S.A. Date: June 15, 2009 CERTIFICATES  Helicopter Underwater Escape Training Certificate (HUET)  Saudi Aramco Safety Certificate  Aramco ID No. 8983193  Aramco Certificate  Seas of Technology Contracting Company  Abdullah Fuoad Holding Company  Saudi Aramco Work Permit Receiver Certificate  R.H. Al-Marri Sons @ Company  Skope Technology Incorporated  National Polytechnic Institute  Valid Saudi Driving License  Philippines Driving License (Code # 1,2,3) OTHER SKILLS  Computer Literate  Light and Heavy Vehicle Driver  Impulse Tubing of Stainless Steel  Mechanical Works  Cathode Protection  GTAW and SMAW  Civil Works  Microsoft Word, Excel, PowerPoint, Windows 95, 98,2000,2003,2005,2007,2012  Operating System, AutoCAD 2003,20005,2007  Bentleys Micro Station Version 7 & 8  Communication Security System Facilities Works  Planning and Scheduling  Tele – Communication Works April 2004 to May 2004 Engineering Aid On Job Training (OJT): Skope Technology Incorporated Unit 202 2nd floor 1st Midland Condo 109 Gamboa Street. Legaspi Village Makati City Philippines SCHOOL SCHOLARSHIP Cagayan Provincial Government Scholarships (CPGS) since year 1999 up to 2005. LANGUAGE SPOKEN  English  Arabic (Common use)  Tagalog (Pilipino)
  • 22. CHARACTER REFERENCES Engr. Emmanuel Jotojot Engr. Isagani Torres QC Manager Sr. Project Inspector Sumitomo Corporation, KSA Electrical Inspector Group Email:Emmanuel.jotojot@sumitomo-kaust.com KAUST-PIS/PID Engr. Antonino Mendoza Engr. Jimmy Hatamosa SR. Telecommunication Engineer SR. Project Inspector WorleyParsons Engineering Consultancies Co. Communication Inspector Group Email:Antonino.mendoza@worleyparsons.com KAUST-PIS/PID I hereby certify that the above information’s are true and correct to the best of my knowledge and belief. ___________________ Domer L. Javier