Maximo Oil and
Gas 7.6.1
Maximo HSE
Manager 7.6.1
Application
Overviews
Job Plans
Clone
Work Order
Work Order
Tracking
Changes to Work Order Tracking:
•New Completion and Reason for Work sections
•New Audit, Condition for Work, Operating Policy and
Assurance Activity fields
•Plans tab, changes to Work Reference Information
section
•Plans tab new Permit and Certificate Type and Risks
sections
•Plans tab, changes to Labor table window
•Related Records new Related Permits to Work and
Isolation Certificates tab and Related Operator Log
Entries table windows
•Changes to Failure Reporting tab
•New Work Details, Control of Work, Risks, Review Actions,
Preparation Activities and Test Results sub tabs
•New Regulation tab
•New Create actions
2
Work Order tab –
Completions
section and Audit
field
3
A work order can be
used to schedule an
audit. This field can also
be used to reference an
audit associated with a
Work Order
A work order can be
used to schedule an
audit. This field can also
be used to reference an
audit associated with a
Work Order
This section can be
used where a work
order is associated with
construction or
commissioning work
This section can be
used where a work
order is associated with
construction or
commissioning work
Work Order tab –
Reason for Work
section, Operating
Policy, Condition for
Work and Assurance
Activity fields
4
Operating Policy is used to
identify the maintenance
strategy with this work
and will normally be
populated from a Job Plan.
If the Operating Policy
record is checked as an
Assurance Activity the
Assurance Activity field
will be automatically
checked
Operating Policy is used to
identify the maintenance
strategy with this work
and will normally be
populated from a Job Plan.
If the Operating Policy
record is checked as an
Assurance Activity the
Assurance Activity field
will be automatically
checked
Condition for Work
associated with the
Work Order
Condition for Work
associated with the
Work Order
Reason for Work section takes
the Reason for Work field and
Asset/Location Priority to look
up Matrix Priority and Matrix
Index. These values can be
overridden as long as they are
valid Prioritization matrix values
Reason for Work section takes
the Reason for Work field and
Asset/Location Priority to look
up Matrix Priority and Matrix
Index. These values can be
overridden as long as they are
valid Prioritization matrix values
Plans tab –
Changes to Work
Reference
Information
section
5
Extra fields to
record as-fixed
values
Extra fields to
record as-fixed
values
Extra field to
record if a test
passes.
Extra field to
record if a test
passes.
Plans tab – Permit
and Certificate
Type and Risk
Assessment
sections
6
One type of permit and
one Risk Assessment
can be associated with
each Task
One type of permit and
one Risk Assessment
can be associated with
each Task
Plans tab –
Changes to Labor
table window
7
Required qualification can
be used as a reference
where planning is at Craft
level. If Labor is added to
the Task it will be
validated against Required
Qualification
Required qualification can
be used as a reference
where planning is at Craft
level. If Labor is added to
the Task it will be
validated against Required
Qualification
Related Records tab –
Related Permits to Work
and Isolation
Certificates, Related
Operator Log Entries
8
Additional table
windows for Permits to
Work and Isolation
Certificates and
Operator Log Entries
Additional table
windows for Permits to
Work and Isolation
Certificates and
Operator Log Entries
Failure Reporting
tab changes
9
These sections support
the failure reporting
guidelines set out in
ISO14224
These sections support
the failure reporting
guidelines set out in
ISO14224
Details tab – Work
Details sub tab
10
This section is read
only copied over from
the Location on the
Work Order
This section is read
only copied over from
the Location on the
Work Order
Use Review Required?
As a marker that the
work order needs to
be reviewed after
work is completed
Use Review Required?
As a marker that the
work order needs to
be reviewed after
work is completed
Details tab – Work
Details sub tab,
Work Details and
Production Impact
sections
11
Work Details section is
defaulted from the
Location on the Work
Order but can be edited
Work Details section is
defaulted from the
Location on the Work
Order but can be edited
An impact record can
be associated with the
Work Order or Loss
Quantity is editable
on the Work Order
An impact record can
be associated with the
Work Order or Loss
Quantity is editable
on the Work Order
Details tab -
Preparation
Activities sub tab
12
Use to identify Work
Order as a
preparation activity
associated with a
turnaround,
construction or
commissioning
activity
Use to identify Work
Order as a
preparation activity
associated with a
turnaround,
construction or
commissioning
activity
Specify the type of
preparation activity
and add context
Specify the type of
preparation activity
and add context
Audit record can be
linked here if used
to assess state of
preparedness
Audit record can be
linked here if used
to assess state of
preparedness
Details tab –
Preparation
Activities sub tab
13
Standard Actions or
Standard Action
Groups can be used to
create a checklist of
preparation activity
actions
Standard Actions or
Standard Action
Groups can be used to
create a checklist of
preparation activity
actions
Evaluate preparedness
and record decision
making with evidence
Evaluate preparedness
and record decision
making with evidence
Details tab -
Control of Work
14
Identify multiple
permits and certificates
associated with the
Work Order
Identify multiple
permits and certificates
associated with the
Work Order
Details tab – Risks
sub tab
15
A Work Order may
have one primary risk
assessment and
multiple
supplementary risk
assessments
A Work Order may
have one primary risk
assessment and
multiple
supplementary risk
assessments
Details tab -
Review Actions sub
tab
16
Review Actions on the
Work Order can be
used to support a
simplified risk
assessment process.
Review Actions on the
Work Order can be
used to support a
simplified risk
assessment process.
Details tab - Test
Results sub tab
17
Multiple test results can be
recorded on the work order
to support performance
standard verification and
recording of results of
construction and
commissioning tests
Multiple test results can be
recorded on the work order
to support performance
standard verification and
recording of results of
construction and
commissioning tests
Test Results sub
tab details
18
Multiple test results can be
recorded on the work order
to support performance
standard verification and
recording of results of
construction and
commissioning tests
Multiple test results can be
recorded on the work order
to support performance
standard verification and
recording of results of
construction and
commissioning tests
Regulations tab
19
Regulations are copied over
from Job Plans, Assets and
Locations associated with the
Work Order. They can also be
added directly onto the Work
Order
Regulations are copied over
from Job Plans, Assets and
Locations associated with the
Work Order. They can also be
added directly onto the Work
Order
Uncheck ‘Applies to Work
Order’ if the automatically
copied Regulation does
not apply to the Work
Order
Uncheck ‘Applies to Work
Order’ if the automatically
copied Regulation does
not apply to the Work
Order
New Create actions
20
Extra Create
Actions added to
the Work Order
Extra Create
Actions added to
the Work Order
Job Plans
Changes to Job Plans:
•Changes to Job Plans tab
•Changes to Job Plan Tasks
•Details tab with Control of Work, Risks, Review Actions,
Preparation Activities, Test Results sub tabs
•Regulation tab
•Create Risk Assessment Action
21
Job Plan tab –
Changes to Details
section
22
Reason for Work
and associated
Function
Reason for Work
and associated
Function
Only Template Audits may be
added to a Job Plan. If an
Operating Policy is added
which has Assurance Activity?
Checked then the Assurance
Activity field on Job Plan is
checked but can be edited
Only Template Audits may be
added to a Job Plan. If an
Operating Policy is added
which has Assurance Activity?
Checked then the Assurance
Activity field on Job Plan is
checked but can be edited
Job Plans tab –
Production Impact
section
23
Identify the outage consequence
of work performed based on this
Job Plan. This can be done by
linking an Impact record or
editing directly on the Job Plan.
A Location Profile can be
reference if the loss varies over
time.
Identify the outage consequence
of work performed based on this
Job Plan. This can be done by
linking an Impact record or
editing directly on the Job Plan.
A Location Profile can be
reference if the loss varies over
time.
Job Plan Tasks
24
An Operating Procedure can
be linked to each Job Plan
Task
An Operating Procedure can
be linked to each Job Plan
Task
A single permit and
certificate type and
risk assessment can be
associated at Task
level
A single permit and
certificate type and
risk assessment can be
associated at Task
level
Details tab –
Control of Work
sub tab
25
Multiple Permit and
Certificate Types can be
added at Job Plan
header level
Multiple Permit and
Certificate Types can be
added at Job Plan
header level
Details tab – Risks
sub tab
26
A Job Plan may have
one primary risk
assessment and
multiple
supplementary risk
assessments
A Job Plan may have
one primary risk
assessment and
multiple
supplementary risk
assessments
Details tab –
Review Actions sub
tab
27
Standard Actions or
Standard Actions
Groups can be added as
templates for Review
Actions on a Work
Order
Standard Actions or
Standard Actions
Groups can be added as
templates for Review
Actions on a Work
Order
Review Actions sub
tab – Review Action
Details
28
Review Action
Details showing
Review Item on a
Review Action
Review Action
Details showing
Review Item on a
Review Action
Details tab –
Preparation
Activities sub tab
29
Indicates that the Job Plan is
related to a preparation
activity
Indicates that the Job Plan is
related to a preparation
activity
Standard Actions and
Standard Action Groups
can be added to create
a preparation activity
checklist
Standard Actions and
Standard Action Groups
can be added to create
a preparation activity
checklist
Details tab – Test
Results sub tab
30
Test Results lines
can be added to
identify recording
of results required
on a Work Order
Test Results lines
can be added to
identify recording
of results required
on a Work Order
Regulations tab
31
Create Risk
Assessment Action
32

More Related Content

What's hot

Using IBM MAXIMO Safety Plans
Using IBM MAXIMO Safety PlansUsing IBM MAXIMO Safety Plans
Using IBM MAXIMO Safety PlansDuane Aritonang
 
Failure Codes in IBM Maximo Asset Management
Failure Codes in IBM Maximo Asset ManagementFailure Codes in IBM Maximo Asset Management
Failure Codes in IBM Maximo Asset ManagementRobert Zientara
 
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overview
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overviewMaximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overview
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overviewHelen Fisher
 
Classifications in IBM Maximo Asset Management
Classifications in IBM Maximo Asset ManagementClassifications in IBM Maximo Asset Management
Classifications in IBM Maximo Asset ManagementRobert Zientara
 
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey Overview
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey OverviewMaximo Oil and Gas 7.6.1 HSE: Audit & Survey Overview
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey OverviewHelen Fisher
 
Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Bruno Portaluri
 
Attachments in IBM Maximo Asset Management
Attachments in IBM Maximo Asset ManagementAttachments in IBM Maximo Asset Management
Attachments in IBM Maximo Asset ManagementRobert Zientara
 
IBM Maximo Tips & Tricks
IBM Maximo Tips & TricksIBM Maximo Tips & Tricks
IBM Maximo Tips & Tricksjohnnyg14
 
Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests
 Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests
Maximo Oil and Gas 7.6.1 HSE: Defects & Service RequestsHelen Fisher
 
201 ke59 criar centro de lucro dummy
201 ke59 criar centro de lucro dummy201 ke59 criar centro de lucro dummy
201 ke59 criar centro de lucro dummyCristiane Magalhães
 
Maximo - Building a Custom Query Management Application
Maximo - Building a Custom Query Management ApplicationMaximo - Building a Custom Query Management Application
Maximo - Building a Custom Query Management Applicationsthume
 
Maximo Oil and Gas 7.6.1 HSE: Overview
Maximo Oil and Gas 7.6.1 HSE: Overview Maximo Oil and Gas 7.6.1 HSE: Overview
Maximo Oil and Gas 7.6.1 HSE: Overview Helen Fisher
 
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsPlanning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsIBM Danmark
 
R12 india localization guide
R12 india localization guideR12 india localization guide
R12 india localization guidekingshuk_goswami
 
Meters in IBM Maximo Asset Management
Meters in IBM Maximo Asset ManagementMeters in IBM Maximo Asset Management
Meters in IBM Maximo Asset ManagementRobert Zientara
 
Oracle Compensation Management
Oracle Compensation ManagementOracle Compensation Management
Oracle Compensation ManagementHussain Abbas
 

What's hot (20)

Using IBM MAXIMO Safety Plans
Using IBM MAXIMO Safety PlansUsing IBM MAXIMO Safety Plans
Using IBM MAXIMO Safety Plans
 
Failure Codes in IBM Maximo Asset Management
Failure Codes in IBM Maximo Asset ManagementFailure Codes in IBM Maximo Asset Management
Failure Codes in IBM Maximo Asset Management
 
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overview
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overviewMaximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overview
Maximo Oil and Gas 7.6.1 HSE: Action Tracking & Operational Actions overview
 
Classifications in IBM Maximo Asset Management
Classifications in IBM Maximo Asset ManagementClassifications in IBM Maximo Asset Management
Classifications in IBM Maximo Asset Management
 
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey Overview
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey OverviewMaximo Oil and Gas 7.6.1 HSE: Audit & Survey Overview
Maximo Oil and Gas 7.6.1 HSE: Audit & Survey Overview
 
Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Maximo Roadmap - September 2019
Maximo Roadmap - September 2019
 
Attachments in IBM Maximo Asset Management
Attachments in IBM Maximo Asset ManagementAttachments in IBM Maximo Asset Management
Attachments in IBM Maximo Asset Management
 
Maximo 7.6.0.8
Maximo 7.6.0.8Maximo 7.6.0.8
Maximo 7.6.0.8
 
IBM Maximo Tips & Tricks
IBM Maximo Tips & TricksIBM Maximo Tips & Tricks
IBM Maximo Tips & Tricks
 
Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests
 Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests
Maximo Oil and Gas 7.6.1 HSE: Defects & Service Requests
 
201 ke59 criar centro de lucro dummy
201 ke59 criar centro de lucro dummy201 ke59 criar centro de lucro dummy
201 ke59 criar centro de lucro dummy
 
Maximo - Building a Custom Query Management Application
Maximo - Building a Custom Query Management ApplicationMaximo - Building a Custom Query Management Application
Maximo - Building a Custom Query Management Application
 
Maximo Oil and Gas 7.6.1 HSE: Overview
Maximo Oil and Gas 7.6.1 HSE: Overview Maximo Oil and Gas 7.6.1 HSE: Overview
Maximo Oil and Gas 7.6.1 HSE: Overview
 
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsPlanning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
 
Maximo overview
Maximo overviewMaximo overview
Maximo overview
 
R12 india localization guide
R12 india localization guideR12 india localization guide
R12 india localization guide
 
Meters in IBM Maximo Asset Management
Meters in IBM Maximo Asset ManagementMeters in IBM Maximo Asset Management
Meters in IBM Maximo Asset Management
 
5 retro pay_methods_i___ii_part_5
5 retro pay_methods_i___ii_part_55 retro pay_methods_i___ii_part_5
5 retro pay_methods_i___ii_part_5
 
Oracle Compensation Management
Oracle Compensation ManagementOracle Compensation Management
Oracle Compensation Management
 
Maximo Scheduler 7.5.1
Maximo Scheduler 7.5.1Maximo Scheduler 7.5.1
Maximo Scheduler 7.5.1
 

Similar to Maximo Oil and Gas 7.6.1 Job Plans Changes

Maximo Oil and Gas 7.6.1 HSE: Benefits & Losses
Maximo Oil and Gas 7.6.1 HSE: Benefits & LossesMaximo Oil and Gas 7.6.1 HSE: Benefits & Losses
Maximo Oil and Gas 7.6.1 HSE: Benefits & LossesHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Operating Policies
Maximo Oil and Gas 7.6.1 HSE: Operating PoliciesMaximo Oil and Gas 7.6.1 HSE: Operating Policies
Maximo Oil and Gas 7.6.1 HSE: Operating PoliciesHelen Fisher
 
2F9_S4HANA2020_BPD_EN_US.docx
2F9_S4HANA2020_BPD_EN_US.docx2F9_S4HANA2020_BPD_EN_US.docx
2F9_S4HANA2020_BPD_EN_US.docxArun Obilisetty
 
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overview
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overviewMaximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overview
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overviewHelen Fisher
 
Environment & Release Management
Environment & Release ManagementEnvironment & Release Management
Environment & Release Managementelliando dias
 
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview Helen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Bypass Management Overview
Maximo Oil and Gas 7.6.1 HSE: Bypass Management OverviewMaximo Oil and Gas 7.6.1 HSE: Bypass Management Overview
Maximo Oil and Gas 7.6.1 HSE: Bypass Management OverviewHelen Fisher
 
BCS 307 Lecture 8.pdf
BCS 307 Lecture 8.pdfBCS 307 Lecture 8.pdf
BCS 307 Lecture 8.pdfJohn119649
 
Parallel testing overview
Parallel testing overviewParallel testing overview
Parallel testing overviewBarbara Getter
 
Maximo Oil and Gas 7.6.1 HSE: Change Module Overview
Maximo Oil and Gas 7.6.1 HSE: Change Module OverviewMaximo Oil and Gas 7.6.1 HSE: Change Module Overview
Maximo Oil and Gas 7.6.1 HSE: Change Module OverviewHelen Fisher
 
Quality Management Cloud Tips and Tricks.pdf
Quality Management Cloud Tips and Tricks.pdfQuality Management Cloud Tips and Tricks.pdf
Quality Management Cloud Tips and Tricks.pdfAhmed831284
 
Brief About IMS, QMS, ISO 9001, 14001, 18001
Brief About IMS, QMS, ISO 9001, 14001, 18001Brief About IMS, QMS, ISO 9001, 14001, 18001
Brief About IMS, QMS, ISO 9001, 14001, 18001Chetan Rathi
 
Optimize your Change Management Process
Optimize your Change Management ProcessOptimize your Change Management Process
Optimize your Change Management ProcessJason Goncalves
 
Framework Change Impact Analysis
Framework Change Impact AnalysisFramework Change Impact Analysis
Framework Change Impact AnalysisAd Ghauri
 

Similar to Maximo Oil and Gas 7.6.1 Job Plans Changes (20)

Maximo Oil and Gas 7.6.1 HSE: Benefits & Losses
Maximo Oil and Gas 7.6.1 HSE: Benefits & LossesMaximo Oil and Gas 7.6.1 HSE: Benefits & Losses
Maximo Oil and Gas 7.6.1 HSE: Benefits & Losses
 
166427325 sap-a udit-management
166427325 sap-a udit-management166427325 sap-a udit-management
166427325 sap-a udit-management
 
Maximo Oil and Gas 7.6.1 HSE: Operating Policies
Maximo Oil and Gas 7.6.1 HSE: Operating PoliciesMaximo Oil and Gas 7.6.1 HSE: Operating Policies
Maximo Oil and Gas 7.6.1 HSE: Operating Policies
 
2F9_S4HANA2020_BPD_EN_US.docx
2F9_S4HANA2020_BPD_EN_US.docx2F9_S4HANA2020_BPD_EN_US.docx
2F9_S4HANA2020_BPD_EN_US.docx
 
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overview
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overviewMaximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overview
Maximo Oil and Gas 7.6.1 HSE: Standard Actions & Standard Action Groups overview
 
Environment & Release Management
Environment & Release ManagementEnvironment & Release Management
Environment & Release Management
 
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview
Maximo Oil and Gas 7.6.1 HSE: Locations & Assets Overview
 
Development Best Practices
Development Best PracticesDevelopment Best Practices
Development Best Practices
 
Maximo Oil and Gas 7.6.1 HSE: Bypass Management Overview
Maximo Oil and Gas 7.6.1 HSE: Bypass Management OverviewMaximo Oil and Gas 7.6.1 HSE: Bypass Management Overview
Maximo Oil and Gas 7.6.1 HSE: Bypass Management Overview
 
BCS 307 Lecture 8.pdf
BCS 307 Lecture 8.pdfBCS 307 Lecture 8.pdf
BCS 307 Lecture 8.pdf
 
Presentation1
Presentation1Presentation1
Presentation1
 
Parallel testing overview
Parallel testing overviewParallel testing overview
Parallel testing overview
 
iiBA babok onapage
iiBA babok onapageiiBA babok onapage
iiBA babok onapage
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Maximo Oil and Gas 7.6.1 HSE: Change Module Overview
Maximo Oil and Gas 7.6.1 HSE: Change Module OverviewMaximo Oil and Gas 7.6.1 HSE: Change Module Overview
Maximo Oil and Gas 7.6.1 HSE: Change Module Overview
 
Quality Management Cloud Tips and Tricks.pdf
Quality Management Cloud Tips and Tricks.pdfQuality Management Cloud Tips and Tricks.pdf
Quality Management Cloud Tips and Tricks.pdf
 
Brief About IMS, QMS, ISO 9001, 14001, 18001
Brief About IMS, QMS, ISO 9001, 14001, 18001Brief About IMS, QMS, ISO 9001, 14001, 18001
Brief About IMS, QMS, ISO 9001, 14001, 18001
 
094 Productivity Measurement
094 Productivity Measurement094 Productivity Measurement
094 Productivity Measurement
 
Optimize your Change Management Process
Optimize your Change Management ProcessOptimize your Change Management Process
Optimize your Change Management Process
 
Framework Change Impact Analysis
Framework Change Impact AnalysisFramework Change Impact Analysis
Framework Change Impact Analysis
 

More from Helen Fisher

Maximo - Management of Change (MOC) Implementation Best Practices
Maximo - Management of Change (MOC) Implementation Best PracticesMaximo - Management of Change (MOC) Implementation Best Practices
Maximo - Management of Change (MOC) Implementation Best PracticesHelen Fisher
 
MaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit SolutionMaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit SolutionHelen Fisher
 
MaxTECH Technical Training Presentation from MaximoWorld 2018
MaxTECH Technical Training Presentation from MaximoWorld 2018MaxTECH Technical Training Presentation from MaximoWorld 2018
MaxTECH Technical Training Presentation from MaximoWorld 2018Helen Fisher
 
Canadian Maximo User Group Technical Training - Maximo Reporting 201
Canadian Maximo User Group Technical Training - Maximo Reporting 201Canadian Maximo User Group Technical Training - Maximo Reporting 201
Canadian Maximo User Group Technical Training - Maximo Reporting 201Helen Fisher
 
Watson IoT at Think 2018
Watson IoT at Think 2018Watson IoT at Think 2018
Watson IoT at Think 2018Helen Fisher
 
IBM Maximo and ISO 55000
IBM Maximo and ISO 55000IBM Maximo and ISO 55000
IBM Maximo and ISO 55000Helen Fisher
 
BPD Zenith AMUG Presentation 2017
BPD Zenith AMUG Presentation 2017BPD Zenith AMUG Presentation 2017
BPD Zenith AMUG Presentation 2017Helen Fisher
 
IBM Maximo for utilities T&D
IBM Maximo for utilities T&DIBM Maximo for utilities T&D
IBM Maximo for utilities T&DHelen Fisher
 
Maximo mobile work management in the hospitality industry
Maximo mobile work management in the hospitality industryMaximo mobile work management in the hospitality industry
Maximo mobile work management in the hospitality industryHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overview
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overviewMaximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overview
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Change Module options
Maximo Oil and Gas 7.6.1 HSE: Change Module optionsMaximo Oil and Gas 7.6.1 HSE: Change Module options
Maximo Oil and Gas 7.6.1 HSE: Change Module optionsHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Solutions Overview
 Maximo Oil and Gas 7.6.1 HSE: Solutions Overview Maximo Oil and Gas 7.6.1 HSE: Solutions Overview
Maximo Oil and Gas 7.6.1 HSE: Solutions OverviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Asset List Routes
Maximo Oil and Gas 7.6.1 HSE: Asset List RoutesMaximo Oil and Gas 7.6.1 HSE: Asset List Routes
Maximo Oil and Gas 7.6.1 HSE: Asset List RoutesHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overview
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overviewMaximo Oil and Gas 7.6.1 HSE: Permit to Work Options overview
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate Types
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate TypesMaximo Oil and Gas 7.6.1 HSE: Permit & Certificate Types
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate TypesHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overview
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overviewMaximo Oil and Gas 7.6.1 HSE: Organizations & Products overview
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Operator Log overview
Maximo Oil and Gas 7.6.1 HSE: Operator Log overviewMaximo Oil and Gas 7.6.1 HSE: Operator Log overview
Maximo Oil and Gas 7.6.1 HSE: Operator Log overviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overview
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overviewMaximo Oil and Gas 7.6.1 HSE: Item master and purchasing overview
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overviewHelen Fisher
 
Maximo Oil and Gas 7.6.1 HSE: Isolation Management Overview
Maximo Oil and Gas 7.6.1 HSE: Isolation Management OverviewMaximo Oil and Gas 7.6.1 HSE: Isolation Management Overview
Maximo Oil and Gas 7.6.1 HSE: Isolation Management OverviewHelen Fisher
 

More from Helen Fisher (19)

Maximo - Management of Change (MOC) Implementation Best Practices
Maximo - Management of Change (MOC) Implementation Best PracticesMaximo - Management of Change (MOC) Implementation Best Practices
Maximo - Management of Change (MOC) Implementation Best Practices
 
MaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit SolutionMaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit Solution
 
MaxTECH Technical Training Presentation from MaximoWorld 2018
MaxTECH Technical Training Presentation from MaximoWorld 2018MaxTECH Technical Training Presentation from MaximoWorld 2018
MaxTECH Technical Training Presentation from MaximoWorld 2018
 
Canadian Maximo User Group Technical Training - Maximo Reporting 201
Canadian Maximo User Group Technical Training - Maximo Reporting 201Canadian Maximo User Group Technical Training - Maximo Reporting 201
Canadian Maximo User Group Technical Training - Maximo Reporting 201
 
Watson IoT at Think 2018
Watson IoT at Think 2018Watson IoT at Think 2018
Watson IoT at Think 2018
 
IBM Maximo and ISO 55000
IBM Maximo and ISO 55000IBM Maximo and ISO 55000
IBM Maximo and ISO 55000
 
BPD Zenith AMUG Presentation 2017
BPD Zenith AMUG Presentation 2017BPD Zenith AMUG Presentation 2017
BPD Zenith AMUG Presentation 2017
 
IBM Maximo for utilities T&D
IBM Maximo for utilities T&DIBM Maximo for utilities T&D
IBM Maximo for utilities T&D
 
Maximo mobile work management in the hospitality industry
Maximo mobile work management in the hospitality industryMaximo mobile work management in the hospitality industry
Maximo mobile work management in the hospitality industry
 
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overview
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overviewMaximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overview
Maximo Oil and Gas 7.6.1 HSE: Drilling and Completion Run Log overview
 
Maximo Oil and Gas 7.6.1 HSE: Change Module options
Maximo Oil and Gas 7.6.1 HSE: Change Module optionsMaximo Oil and Gas 7.6.1 HSE: Change Module options
Maximo Oil and Gas 7.6.1 HSE: Change Module options
 
Maximo Oil and Gas 7.6.1 HSE: Solutions Overview
 Maximo Oil and Gas 7.6.1 HSE: Solutions Overview Maximo Oil and Gas 7.6.1 HSE: Solutions Overview
Maximo Oil and Gas 7.6.1 HSE: Solutions Overview
 
Maximo Oil and Gas 7.6.1 HSE: Asset List Routes
Maximo Oil and Gas 7.6.1 HSE: Asset List RoutesMaximo Oil and Gas 7.6.1 HSE: Asset List Routes
Maximo Oil and Gas 7.6.1 HSE: Asset List Routes
 
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overview
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overviewMaximo Oil and Gas 7.6.1 HSE: Permit to Work Options overview
Maximo Oil and Gas 7.6.1 HSE: Permit to Work Options overview
 
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate Types
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate TypesMaximo Oil and Gas 7.6.1 HSE: Permit & Certificate Types
Maximo Oil and Gas 7.6.1 HSE: Permit & Certificate Types
 
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overview
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overviewMaximo Oil and Gas 7.6.1 HSE: Organizations & Products overview
Maximo Oil and Gas 7.6.1 HSE: Organizations & Products overview
 
Maximo Oil and Gas 7.6.1 HSE: Operator Log overview
Maximo Oil and Gas 7.6.1 HSE: Operator Log overviewMaximo Oil and Gas 7.6.1 HSE: Operator Log overview
Maximo Oil and Gas 7.6.1 HSE: Operator Log overview
 
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overview
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overviewMaximo Oil and Gas 7.6.1 HSE: Item master and purchasing overview
Maximo Oil and Gas 7.6.1 HSE: Item master and purchasing overview
 
Maximo Oil and Gas 7.6.1 HSE: Isolation Management Overview
Maximo Oil and Gas 7.6.1 HSE: Isolation Management OverviewMaximo Oil and Gas 7.6.1 HSE: Isolation Management Overview
Maximo Oil and Gas 7.6.1 HSE: Isolation Management Overview
 

Recently uploaded

Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Matt Ray
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEOrtus Solutions, Corp
 
CRM Contender Series: HubSpot vs. Salesforce
CRM Contender Series: HubSpot vs. SalesforceCRM Contender Series: HubSpot vs. Salesforce
CRM Contender Series: HubSpot vs. SalesforceBrainSell Technologies
 
Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Hr365.us smith
 
Introduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfIntroduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfFerryKemperman
 
英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作qr0udbr0
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesŁukasz Chruściel
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024StefanoLambiase
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsAhmed Mohamed
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmSujith Sukumaran
 
Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfStefano Stabellini
 
Implementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureImplementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureDinusha Kumarasiri
 
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte Germany
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte GermanySuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte Germany
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte GermanyChristoph Pohl
 
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样umasea
 
SpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at RuntimeSpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at Runtimeandrehoraa
 
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...Christina Lin
 
What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....kzayra69
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideChristina Lin
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfAlina Yurenko
 

Recently uploaded (20)

Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
Open Source Summit NA 2024: Open Source Cloud Costs - OpenCost's Impact on En...
 
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASEBATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
BATTLEFIELD ORM: TIPS, TACTICS AND STRATEGIES FOR CONQUERING YOUR DATABASE
 
CRM Contender Series: HubSpot vs. Salesforce
CRM Contender Series: HubSpot vs. SalesforceCRM Contender Series: HubSpot vs. Salesforce
CRM Contender Series: HubSpot vs. Salesforce
 
Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)Recruitment Management Software Benefits (Infographic)
Recruitment Management Software Benefits (Infographic)
 
Introduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdfIntroduction Computer Science - Software Design.pdf
Introduction Computer Science - Software Design.pdf
 
英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作英国UN学位证,北安普顿大学毕业证书1:1制作
英国UN学位证,北安普顿大学毕业证书1:1制作
 
Unveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New FeaturesUnveiling the Future: Sylius 2.0 New Features
Unveiling the Future: Sylius 2.0 New Features
 
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
Dealing with Cultural Dispersion — Stefano Lambiase — ICSE-SEIS 2024
 
Unveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML DiagramsUnveiling Design Patterns: A Visual Guide with UML Diagrams
Unveiling Design Patterns: A Visual Guide with UML Diagrams
 
Intelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalmIntelligent Home Wi-Fi Solutions | ThinkPalm
Intelligent Home Wi-Fi Solutions | ThinkPalm
 
2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva2.pdf Ejercicios de programación competitiva
2.pdf Ejercicios de programación competitiva
 
Xen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdfXen Safety Embedded OSS Summit April 2024 v4.pdf
Xen Safety Embedded OSS Summit April 2024 v4.pdf
 
Implementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with AzureImplementing Zero Trust strategy with Azure
Implementing Zero Trust strategy with Azure
 
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte Germany
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte GermanySuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte Germany
SuccessFactors 1H 2024 Release - Sneak-Peek by Deloitte Germany
 
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样
办理学位证(UQ文凭证书)昆士兰大学毕业证成绩单原版一模一样
 
SpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at RuntimeSpotFlow: Tracking Method Calls and States at Runtime
SpotFlow: Tracking Method Calls and States at Runtime
 
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
ODSC - Batch to Stream workshop - integration of Apache Spark, Cassandra, Pos...
 
What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....What are the key points to focus on before starting to learn ETL Development....
What are the key points to focus on before starting to learn ETL Development....
 
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop SlideBuilding Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
Building Real-Time Data Pipelines: Stream & Batch Processing workshop Slide
 
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdfGOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
GOING AOT WITH GRAALVM – DEVOXX GREECE.pdf
 

Maximo Oil and Gas 7.6.1 Job Plans Changes

  • 1. Maximo Oil and Gas 7.6.1 Maximo HSE Manager 7.6.1 Application Overviews Job Plans Clone Work Order
  • 2. Work Order Tracking Changes to Work Order Tracking: •New Completion and Reason for Work sections •New Audit, Condition for Work, Operating Policy and Assurance Activity fields •Plans tab, changes to Work Reference Information section •Plans tab new Permit and Certificate Type and Risks sections •Plans tab, changes to Labor table window •Related Records new Related Permits to Work and Isolation Certificates tab and Related Operator Log Entries table windows •Changes to Failure Reporting tab •New Work Details, Control of Work, Risks, Review Actions, Preparation Activities and Test Results sub tabs •New Regulation tab •New Create actions 2
  • 3. Work Order tab – Completions section and Audit field 3 A work order can be used to schedule an audit. This field can also be used to reference an audit associated with a Work Order A work order can be used to schedule an audit. This field can also be used to reference an audit associated with a Work Order This section can be used where a work order is associated with construction or commissioning work This section can be used where a work order is associated with construction or commissioning work
  • 4. Work Order tab – Reason for Work section, Operating Policy, Condition for Work and Assurance Activity fields 4 Operating Policy is used to identify the maintenance strategy with this work and will normally be populated from a Job Plan. If the Operating Policy record is checked as an Assurance Activity the Assurance Activity field will be automatically checked Operating Policy is used to identify the maintenance strategy with this work and will normally be populated from a Job Plan. If the Operating Policy record is checked as an Assurance Activity the Assurance Activity field will be automatically checked Condition for Work associated with the Work Order Condition for Work associated with the Work Order Reason for Work section takes the Reason for Work field and Asset/Location Priority to look up Matrix Priority and Matrix Index. These values can be overridden as long as they are valid Prioritization matrix values Reason for Work section takes the Reason for Work field and Asset/Location Priority to look up Matrix Priority and Matrix Index. These values can be overridden as long as they are valid Prioritization matrix values
  • 5. Plans tab – Changes to Work Reference Information section 5 Extra fields to record as-fixed values Extra fields to record as-fixed values Extra field to record if a test passes. Extra field to record if a test passes.
  • 6. Plans tab – Permit and Certificate Type and Risk Assessment sections 6 One type of permit and one Risk Assessment can be associated with each Task One type of permit and one Risk Assessment can be associated with each Task
  • 7. Plans tab – Changes to Labor table window 7 Required qualification can be used as a reference where planning is at Craft level. If Labor is added to the Task it will be validated against Required Qualification Required qualification can be used as a reference where planning is at Craft level. If Labor is added to the Task it will be validated against Required Qualification
  • 8. Related Records tab – Related Permits to Work and Isolation Certificates, Related Operator Log Entries 8 Additional table windows for Permits to Work and Isolation Certificates and Operator Log Entries Additional table windows for Permits to Work and Isolation Certificates and Operator Log Entries
  • 9. Failure Reporting tab changes 9 These sections support the failure reporting guidelines set out in ISO14224 These sections support the failure reporting guidelines set out in ISO14224
  • 10. Details tab – Work Details sub tab 10 This section is read only copied over from the Location on the Work Order This section is read only copied over from the Location on the Work Order Use Review Required? As a marker that the work order needs to be reviewed after work is completed Use Review Required? As a marker that the work order needs to be reviewed after work is completed
  • 11. Details tab – Work Details sub tab, Work Details and Production Impact sections 11 Work Details section is defaulted from the Location on the Work Order but can be edited Work Details section is defaulted from the Location on the Work Order but can be edited An impact record can be associated with the Work Order or Loss Quantity is editable on the Work Order An impact record can be associated with the Work Order or Loss Quantity is editable on the Work Order
  • 12. Details tab - Preparation Activities sub tab 12 Use to identify Work Order as a preparation activity associated with a turnaround, construction or commissioning activity Use to identify Work Order as a preparation activity associated with a turnaround, construction or commissioning activity Specify the type of preparation activity and add context Specify the type of preparation activity and add context Audit record can be linked here if used to assess state of preparedness Audit record can be linked here if used to assess state of preparedness
  • 13. Details tab – Preparation Activities sub tab 13 Standard Actions or Standard Action Groups can be used to create a checklist of preparation activity actions Standard Actions or Standard Action Groups can be used to create a checklist of preparation activity actions Evaluate preparedness and record decision making with evidence Evaluate preparedness and record decision making with evidence
  • 14. Details tab - Control of Work 14 Identify multiple permits and certificates associated with the Work Order Identify multiple permits and certificates associated with the Work Order
  • 15. Details tab – Risks sub tab 15 A Work Order may have one primary risk assessment and multiple supplementary risk assessments A Work Order may have one primary risk assessment and multiple supplementary risk assessments
  • 16. Details tab - Review Actions sub tab 16 Review Actions on the Work Order can be used to support a simplified risk assessment process. Review Actions on the Work Order can be used to support a simplified risk assessment process.
  • 17. Details tab - Test Results sub tab 17 Multiple test results can be recorded on the work order to support performance standard verification and recording of results of construction and commissioning tests Multiple test results can be recorded on the work order to support performance standard verification and recording of results of construction and commissioning tests
  • 18. Test Results sub tab details 18 Multiple test results can be recorded on the work order to support performance standard verification and recording of results of construction and commissioning tests Multiple test results can be recorded on the work order to support performance standard verification and recording of results of construction and commissioning tests
  • 19. Regulations tab 19 Regulations are copied over from Job Plans, Assets and Locations associated with the Work Order. They can also be added directly onto the Work Order Regulations are copied over from Job Plans, Assets and Locations associated with the Work Order. They can also be added directly onto the Work Order Uncheck ‘Applies to Work Order’ if the automatically copied Regulation does not apply to the Work Order Uncheck ‘Applies to Work Order’ if the automatically copied Regulation does not apply to the Work Order
  • 20. New Create actions 20 Extra Create Actions added to the Work Order Extra Create Actions added to the Work Order
  • 21. Job Plans Changes to Job Plans: •Changes to Job Plans tab •Changes to Job Plan Tasks •Details tab with Control of Work, Risks, Review Actions, Preparation Activities, Test Results sub tabs •Regulation tab •Create Risk Assessment Action 21
  • 22. Job Plan tab – Changes to Details section 22 Reason for Work and associated Function Reason for Work and associated Function Only Template Audits may be added to a Job Plan. If an Operating Policy is added which has Assurance Activity? Checked then the Assurance Activity field on Job Plan is checked but can be edited Only Template Audits may be added to a Job Plan. If an Operating Policy is added which has Assurance Activity? Checked then the Assurance Activity field on Job Plan is checked but can be edited
  • 23. Job Plans tab – Production Impact section 23 Identify the outage consequence of work performed based on this Job Plan. This can be done by linking an Impact record or editing directly on the Job Plan. A Location Profile can be reference if the loss varies over time. Identify the outage consequence of work performed based on this Job Plan. This can be done by linking an Impact record or editing directly on the Job Plan. A Location Profile can be reference if the loss varies over time.
  • 24. Job Plan Tasks 24 An Operating Procedure can be linked to each Job Plan Task An Operating Procedure can be linked to each Job Plan Task A single permit and certificate type and risk assessment can be associated at Task level A single permit and certificate type and risk assessment can be associated at Task level
  • 25. Details tab – Control of Work sub tab 25 Multiple Permit and Certificate Types can be added at Job Plan header level Multiple Permit and Certificate Types can be added at Job Plan header level
  • 26. Details tab – Risks sub tab 26 A Job Plan may have one primary risk assessment and multiple supplementary risk assessments A Job Plan may have one primary risk assessment and multiple supplementary risk assessments
  • 27. Details tab – Review Actions sub tab 27 Standard Actions or Standard Actions Groups can be added as templates for Review Actions on a Work Order Standard Actions or Standard Actions Groups can be added as templates for Review Actions on a Work Order
  • 28. Review Actions sub tab – Review Action Details 28 Review Action Details showing Review Item on a Review Action Review Action Details showing Review Item on a Review Action
  • 29. Details tab – Preparation Activities sub tab 29 Indicates that the Job Plan is related to a preparation activity Indicates that the Job Plan is related to a preparation activity Standard Actions and Standard Action Groups can be added to create a preparation activity checklist Standard Actions and Standard Action Groups can be added to create a preparation activity checklist
  • 30. Details tab – Test Results sub tab 30 Test Results lines can be added to identify recording of results required on a Work Order Test Results lines can be added to identify recording of results required on a Work Order