DRIVING STRATEGIC TRANSFORMATION AT A
MAJOR INTERNATIONAL AIRPORT WITH
MAXIMO IN THE CLOUD
AGENDA
The Airport
The Situation
The Business Solution
Airport Achievements / Key
Outcomes
Lessons Learned
The Future Roadmap
AIRPORT PROFILE
Australia’s busiest airport
40 million passengers each year
3 passenger terminals
7 cargo terminals
$AUS1.2B revenue
PREVIOUS MAINTENANCE ARRANGEMENTS
Early 2000s
Single Management
Provider, plus its
own on site First
Response Team
2012 2012 & Beyond
End of Contract
review found a
reduced focus on
Asset Condition
A change was
needed to
refocus on Asset
improvement…
CHALLENGES
WITH THE
INCUMBENT
SYSTEM
Business
Goals
Human
Challenges
Technology
Enablers
BUSINESS
The system had become challenged in meeting the evolving
business needs of the airport:
No formalized frameworks
Inadequate reporting
Data integrity
Poor structure
Go back - we
don’t know what
we’re doing!
HUMAN
Processes were largely manual, ill defined or undocumented:
Call
Center
Airport
Stakeholders
FM First
Response
Team
FM Service
Contractor
Work
Orders
FM Calls
Service
Requests
Maximo
“The systems had
become full of
rubbish data!”
– On Site Team
Unscripted process Manual process
TECHNOLOGY
Responsibilities for the systems were unclear and there was a lack of co-ordinated
Continual Improvement of the Maximo system and processes.
FM Systems
Performance
Management
& Continual
Improvement
Operational
Support
A NEW APPROACH FOR STRATEGIC
TRANSFORMATION
Invest
Invest in its
specialized
airport assets
Retain
Retain ownership
and knowledge
of these assets
Improve
Improve asset
standards with a
program of
investment
Implement
Implement a
Managed FM
Business Solution
AIRPORT
SOLUTION
OBJECTIVES
 Full ownership and accountability
 Data integrity
 Build the asset knowledge
 Flexible design – future growth
 Performance Management
 Insightful reporting and analytics
 Access to industry best practice
FINDING THE
SOLUTION
The team had an active role:
Developing and documenting work
processes
Refining maintenance programs
Determining the best data structures,
naming conventions and workflows
to suit the business needs for the
future
Configuring a new instance of
Maximo
SYSTEM EXPANSION
ServiceArea&UserBase
Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8
HVAC
Aerobridges
Fire
Lifts
General Building
Non-FM Services
Aeronautical Ground
Lighting
Car 2
High Voltage
Water Treatment Plant
SCADA
Aeronautical Ground
Lighting
Car 2
High Voltage
Water Treatment Plant
SCADA
Grounds Maintenance
Property Services
Project Compliance
Terminal Presentation
HVAC
Aerobridges
Fire
Lifts
General Building
HVAC
Aerobridges
Fire
Lifts
General Building
ON-GOING MANAGEMENT
Performance
Management
Managed
FM Systems
FM Hub
Contact
Center,
Works/Data
Co-
ordination
Solution
Development
Maximo, XRM,
iBIM
The Airport
Airport Stakeholder
Groups
Infrastructure
and Services
Team
Operations
Teams
Project
Compliance
Terminal
Presentation
Team
Business
Continuity
NotificationNotification
smartNOTIFYsmartNOTIFY
ReportingReporting
COGNOS
smartINSIGHTS
COGNOS
smartINSIGHTS
Field AuditField Audit
smartAUDITsmartAUDIT
Airport
Corporate System
Corporate
Maximo
Corporate
Maximo
• IT
• FIDS
• Security
• Baggage
• Cameras
• eDirectory
• Phone
• Printers
• SACS
• Car Parks
• IT
• FIDS
• Security
• Baggage
• Cameras
• eDirectory
• Phone
• Printers
• SACS
• Car Parks
Oracle
Financials
Oracle
Financials
FM Service
Contractor Systems
Other
• General
• Cleaning
• T3
• General
• Cleaning
• T3
AMS
FM Service
Contractors
Other
Teams
MAXIMO
7.6
MAXIMO
7.6
FM Hub Support
Data Curation & Analysis
xRM
smartQUESTION
xRM
smartQUESTION
FM Hub
Contact Centre
ESBESB
MANAGEDFMBUSINESSSOLUTIONSYSTEMS
WHAT HAS THE
AIRPORT
ACHIEVED?
1. Increases in Asset Standards
2. Increases in Service
3. Improved Data Integrity and Process
Efficiencies
INCREASES IN ASSET
STANDARDS
1.Improved Asset
Availability:
50% reduction in
Aerobridge breakdowns pa
18% reduction in HVAC
breakdowns pa
INCREASES IN SERVICE
Contractors are more
responsive
Less Operational
Delays
Happier passengers
Reduced PM Backlog
TOTAL WORK SINCE INCEPTION
0
1000
2000
3000
4000
5000
6000
7000
Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3
2014 2015 2016 2017
Total Work Orders - All Types
CM
CW
GS
IV
PM
RM
Spike in Winter Months?
TOTAL WORK COMPLETED SINCE INCEPTION
0
1000
2000
3000
4000
5000
6000
Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3
2014 2015 2016 2017
Total Work Orders Completed by Year/Quarter
CM
CW
PM
RM
TERMINAL 2 - AEROBRIDGES
TOP 5 Faulted
Assets
Fault Cause
Asset Description No of Faults Component Operator
ABB ‐  T2 Gate 45 22 2 20
ABB ‐  T2 Gate 42 13 1 12
ABB ‐  T2 Gate 44 13 1 12
ABB ‐  T2 Gate 52 9 1 8
ABB ‐  T2 Gate 53 5 2 3
Terminal 2
TERMINAL 2 - BATHROOMS
TOP 5 Faulted
Assets
Asset Description No of Faults
BTH‐(M) ‐ T2 Foodcourt 81
BTH‐(F) ‐ T2 Foodcourt 51
BTH‐(F) ‐ T2 Gate 54 47
BTH‐(M) ‐ T2 Carousel 2 43
BTH‐(M) ‐ T2 Carousel 6 36
Terminal 2
Asset Detail
WORK BY LOCATION
IDENTIFIED/PLANNED WORK
(REMEDIAL)
0
10
20
30
40
50
60
70
Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3
2015 2016 2017
AeroBridge Identified/Planned Work Orders by Quarter by Priority
1
2
3
4
5
REPORTED/UNPLANNED WORK
(CORRECTIVE)
0
50
100
150
200
250
Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3
2014 2015 2016 2017
AeroBridge Reported/Unplanned Work Orders by Quarter by Priority
0
1
2
3
4
5
IDENTIFIED/PLANNED WORK
(REMEDIAL)
0
10
20
30
40
50
60
2014 2015 2016 2017
HVAC Identified/Planned Work Orders by Quarter by Priority
2
3
4
5
REPORTED/UNPLANNED WORK
(CORRECTIVE)
0
50
100
150
200
250
300
350
400
450
2014 2015 2016 2017
HVAC Reported/Unplanned Work Orders by Quarter by Priority
1
2
3
4
5
IDENTIFIED/PLANNED WORK
(REMEDIAL)
0
0.5
1
1.5
2
2.5
Qtr2 Qtr3 Qtr1 Qtr2
2016 2017
Airport Ground Lighting Identified/Planned by Quarter by Priority
1
2
3
REPORTED/UNPLANNED WORK
(CORRECTIVE)
0
20
40
60
80
100
120
140
160
Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3
2016 2017
Airport Ground Lighting Reported/Unplanned by Quarter by Priority
1
2
3
4
5
TERMINAL PRESENTATION – BEFORE & AFTER
0
5
10
15
20
2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October
Asset BATHROOM FIRE HVAC LIFTS LV-LIGHTING
Count of Asset and Audited by Year, Month and Asset
0
50
100
2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October
Asset BUILDINGS Count of Ref by Asset
BATHROOM
BUILDINGS
FIRE
HVAC
LV- LIGHTING
• Contractors more closely
monitoring/reviewing their
own performance
• Significant Reduction in non-
Building Terminal Presentation
Items
• Particularly Noticeable since the
commencement of Audits
• No Bathroom Items since July
• Minimal Fire/HVAC/Lifts/LV-
LightingAuditing
Commenced
IMPROVED DATA
INTEGRITY AND
PROCESS
EFFICIENCY
Business Solution expansion
Greater reliance on information based
management
Reduction in costs
WHAT IS NEXT?Maximo
Analytics
& Watson
Mobility
GISiBIM
IoT & Data
Integration
LESSONS
LEARNED
Choose who you partner with carefully
Play an active role in developing the
business processes together
Take an agile approach for the future
Many ways of doing the same thing in
Maximo - choose the way that ensures no
glass ceilings in the future
Understand what is the minimum viable
product for go live? Asset management is
a long journey
Founded in 1994, our Headquarters are
in the UK. We have global operations in
North America, Europe and Asia Pacific
– offering a 24x7 ‘Follow the Sun’
support service.
Highest level of IBM Accreditations
and Maximo Partner of the Year:
• Early adopters of Cloud
• Forward thinking solutions
• Trusted advisor to clients
Experience and capability to help
airport operators leverage data to
meet capacity demands, operate more
efficiency, address rising costs, and
differentiate their service.
BPD Zenith is an Enterprise Asset Management
partner for organizations worldwide.
Our solutions are purpose-built for specific
industries, providing complete platforms that are
designed to make the world work better.
THANK YOU FOR LISTENING.
ANY QUESTIONS?
Graeme Sharp CEO Asia Pacific
graeme.sharp@bpdzenith.com
+61 438 148 663
bpdzenith.com

BPD Zenith AMUG Presentation 2017

  • 1.
    DRIVING STRATEGIC TRANSFORMATIONAT A MAJOR INTERNATIONAL AIRPORT WITH MAXIMO IN THE CLOUD
  • 2.
    AGENDA The Airport The Situation TheBusiness Solution Airport Achievements / Key Outcomes Lessons Learned The Future Roadmap
  • 3.
    AIRPORT PROFILE Australia’s busiestairport 40 million passengers each year 3 passenger terminals 7 cargo terminals $AUS1.2B revenue
  • 4.
    PREVIOUS MAINTENANCE ARRANGEMENTS Early2000s Single Management Provider, plus its own on site First Response Team 2012 2012 & Beyond End of Contract review found a reduced focus on Asset Condition A change was needed to refocus on Asset improvement…
  • 5.
  • 6.
    BUSINESS The system hadbecome challenged in meeting the evolving business needs of the airport: No formalized frameworks Inadequate reporting Data integrity Poor structure Go back - we don’t know what we’re doing!
  • 7.
    HUMAN Processes were largelymanual, ill defined or undocumented: Call Center Airport Stakeholders FM First Response Team FM Service Contractor Work Orders FM Calls Service Requests Maximo “The systems had become full of rubbish data!” – On Site Team Unscripted process Manual process
  • 8.
    TECHNOLOGY Responsibilities for thesystems were unclear and there was a lack of co-ordinated Continual Improvement of the Maximo system and processes. FM Systems Performance Management & Continual Improvement Operational Support
  • 9.
    A NEW APPROACHFOR STRATEGIC TRANSFORMATION Invest Invest in its specialized airport assets Retain Retain ownership and knowledge of these assets Improve Improve asset standards with a program of investment Implement Implement a Managed FM Business Solution
  • 10.
    AIRPORT SOLUTION OBJECTIVES  Full ownershipand accountability  Data integrity  Build the asset knowledge  Flexible design – future growth  Performance Management  Insightful reporting and analytics  Access to industry best practice
  • 11.
    FINDING THE SOLUTION The teamhad an active role: Developing and documenting work processes Refining maintenance programs Determining the best data structures, naming conventions and workflows to suit the business needs for the future Configuring a new instance of Maximo
  • 12.
    SYSTEM EXPANSION ServiceArea&UserBase Q1 Q2Q3 Q4 Q5 Q6 Q7 Q8 HVAC Aerobridges Fire Lifts General Building Non-FM Services Aeronautical Ground Lighting Car 2 High Voltage Water Treatment Plant SCADA Aeronautical Ground Lighting Car 2 High Voltage Water Treatment Plant SCADA Grounds Maintenance Property Services Project Compliance Terminal Presentation HVAC Aerobridges Fire Lifts General Building HVAC Aerobridges Fire Lifts General Building
  • 13.
    ON-GOING MANAGEMENT Performance Management Managed FM Systems FMHub Contact Center, Works/Data Co- ordination Solution Development Maximo, XRM, iBIM
  • 14.
    The Airport Airport Stakeholder Groups Infrastructure andServices Team Operations Teams Project Compliance Terminal Presentation Team Business Continuity NotificationNotification smartNOTIFYsmartNOTIFY ReportingReporting COGNOS smartINSIGHTS COGNOS smartINSIGHTS Field AuditField Audit smartAUDITsmartAUDIT Airport Corporate System Corporate Maximo Corporate Maximo • IT • FIDS • Security • Baggage • Cameras • eDirectory • Phone • Printers • SACS • Car Parks • IT • FIDS • Security • Baggage • Cameras • eDirectory • Phone • Printers • SACS • Car Parks Oracle Financials Oracle Financials FM Service Contractor Systems Other • General • Cleaning • T3 • General • Cleaning • T3 AMS FM Service Contractors Other Teams MAXIMO 7.6 MAXIMO 7.6 FM Hub Support Data Curation & Analysis xRM smartQUESTION xRM smartQUESTION FM Hub Contact Centre ESBESB MANAGEDFMBUSINESSSOLUTIONSYSTEMS
  • 15.
    WHAT HAS THE AIRPORT ACHIEVED? 1.Increases in Asset Standards 2. Increases in Service 3. Improved Data Integrity and Process Efficiencies
  • 16.
    INCREASES IN ASSET STANDARDS 1.ImprovedAsset Availability: 50% reduction in Aerobridge breakdowns pa 18% reduction in HVAC breakdowns pa
  • 17.
    INCREASES IN SERVICE Contractorsare more responsive Less Operational Delays Happier passengers Reduced PM Backlog
  • 18.
    TOTAL WORK SINCEINCEPTION 0 1000 2000 3000 4000 5000 6000 7000 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 2014 2015 2016 2017 Total Work Orders - All Types CM CW GS IV PM RM Spike in Winter Months?
  • 19.
    TOTAL WORK COMPLETEDSINCE INCEPTION 0 1000 2000 3000 4000 5000 6000 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 2014 2015 2016 2017 Total Work Orders Completed by Year/Quarter CM CW PM RM
  • 20.
    TERMINAL 2 -AEROBRIDGES TOP 5 Faulted Assets Fault Cause Asset Description No of Faults Component Operator ABB ‐  T2 Gate 45 22 2 20 ABB ‐  T2 Gate 42 13 1 12 ABB ‐  T2 Gate 44 13 1 12 ABB ‐  T2 Gate 52 9 1 8 ABB ‐  T2 Gate 53 5 2 3 Terminal 2
  • 21.
    TERMINAL 2 -BATHROOMS TOP 5 Faulted Assets Asset Description No of Faults BTH‐(M) ‐ T2 Foodcourt 81 BTH‐(F) ‐ T2 Foodcourt 51 BTH‐(F) ‐ T2 Gate 54 47 BTH‐(M) ‐ T2 Carousel 2 43 BTH‐(M) ‐ T2 Carousel 6 36 Terminal 2 Asset Detail
  • 22.
  • 23.
    IDENTIFIED/PLANNED WORK (REMEDIAL) 0 10 20 30 40 50 60 70 Qtr1 Qtr2Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 2015 2016 2017 AeroBridge Identified/Planned Work Orders by Quarter by Priority 1 2 3 4 5
  • 24.
    REPORTED/UNPLANNED WORK (CORRECTIVE) 0 50 100 150 200 250 Qtr4 Qtr1Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 2014 2015 2016 2017 AeroBridge Reported/Unplanned Work Orders by Quarter by Priority 0 1 2 3 4 5
  • 25.
    IDENTIFIED/PLANNED WORK (REMEDIAL) 0 10 20 30 40 50 60 2014 20152016 2017 HVAC Identified/Planned Work Orders by Quarter by Priority 2 3 4 5
  • 26.
    REPORTED/UNPLANNED WORK (CORRECTIVE) 0 50 100 150 200 250 300 350 400 450 2014 20152016 2017 HVAC Reported/Unplanned Work Orders by Quarter by Priority 1 2 3 4 5
  • 27.
    IDENTIFIED/PLANNED WORK (REMEDIAL) 0 0.5 1 1.5 2 2.5 Qtr2 Qtr3Qtr1 Qtr2 2016 2017 Airport Ground Lighting Identified/Planned by Quarter by Priority 1 2 3
  • 28.
    REPORTED/UNPLANNED WORK (CORRECTIVE) 0 20 40 60 80 100 120 140 160 Qtr1 Qtr2Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 2016 2017 Airport Ground Lighting Reported/Unplanned by Quarter by Priority 1 2 3 4 5
  • 29.
    TERMINAL PRESENTATION –BEFORE & AFTER 0 5 10 15 20 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October Asset BATHROOM FIRE HVAC LIFTS LV-LIGHTING Count of Asset and Audited by Year, Month and Asset 0 50 100 2016 February 2016 March 2016 April 2016 May 2016 June 2016 July 2016 August 2016 September 2016 October Asset BUILDINGS Count of Ref by Asset BATHROOM BUILDINGS FIRE HVAC LV- LIGHTING • Contractors more closely monitoring/reviewing their own performance • Significant Reduction in non- Building Terminal Presentation Items • Particularly Noticeable since the commencement of Audits • No Bathroom Items since July • Minimal Fire/HVAC/Lifts/LV- LightingAuditing Commenced
  • 30.
    IMPROVED DATA INTEGRITY AND PROCESS EFFICIENCY BusinessSolution expansion Greater reliance on information based management Reduction in costs
  • 31.
    WHAT IS NEXT?Maximo Analytics &Watson Mobility GISiBIM IoT & Data Integration
  • 32.
    LESSONS LEARNED Choose who youpartner with carefully Play an active role in developing the business processes together Take an agile approach for the future Many ways of doing the same thing in Maximo - choose the way that ensures no glass ceilings in the future Understand what is the minimum viable product for go live? Asset management is a long journey
  • 33.
    Founded in 1994,our Headquarters are in the UK. We have global operations in North America, Europe and Asia Pacific – offering a 24x7 ‘Follow the Sun’ support service. Highest level of IBM Accreditations and Maximo Partner of the Year: • Early adopters of Cloud • Forward thinking solutions • Trusted advisor to clients Experience and capability to help airport operators leverage data to meet capacity demands, operate more efficiency, address rising costs, and differentiate their service. BPD Zenith is an Enterprise Asset Management partner for organizations worldwide. Our solutions are purpose-built for specific industries, providing complete platforms that are designed to make the world work better.
  • 34.
    THANK YOU FORLISTENING. ANY QUESTIONS? Graeme Sharp CEO Asia Pacific graeme.sharp@bpdzenith.com +61 438 148 663 bpdzenith.com