1. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
RESUMES OF KEY PERSONNEL
Name:
FARRUKH M CHUGHTAI
Proposed Position: CONST.MANAGE E&I Age: 58
Discipline: ELECTRICAL ENGINEER. Nationality: PAKISTANI
English Speaking Capability: VERY GOOD
Education:
School/University Dates in Attendance Degree/Certification
UET Lahore Pakistan
Distributed Control System
(DCS) training in Singapore
1993
1996
BSC in Electrical Engineering.
Certification in DCS Training.
Summary of Experience
Having more than 20 years of diversified experience in the field of Industrial Electrical (MV/LV),
instrumentation / Instrumentation works in construction of plants such as Petrochemicals, Cement
Plant, Gas Field, Infra Structure development Project at Jubail with communication & Cathodic
Protection Installation works for Structure, piping line and tanks in Pakistan and Saudi Arabia.
Detailed Job Description
Responsible for review the electrical design, power and control requirement.
Coordination with client and discuss technical issues review drawings and specification,
calculation & submittal approval.
Responsible for preparation of line diagram of the 13.8 Kv/34.5 KV distribution systems
including the emergency power supply and as built drawings. Responsible for the execution of
electrical works and assistance of commissioning of electrical equipment such as MV & LV
transformers Electrical panels, Motors, MCCs, Grounding, Cable laying and lighting works.
Preparation of electrical method statements, and as built drawings for electrical works.
Supervised the Cathodic protection works for the installation of impress current or sacrificial
system start up and preventive maintenance such as additional installation of anode beds
repair defective anode connection, DC rectifier(Oil immersed & Dry type) and bonding boxes,
and assistance in commissioning.
Prepared purchase requisition for major and minor electrical equipment MV/LV Transformers,
MV/LV SWGRS, 480V MCC, UPS equipments, DC Battery Charger, lighting panels.
Page 1 of 5
2. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
Responsible for the installation of field instrumentation fire alarm system, HVAC, control room
accessories such as installation of Patch Panels, PLC/DCS panels, Marshaling Cabinets,
communication through FO Cable etc.
---------------*****------------------
Specific Job Experience
Position : Construction Manager E&I
Employer : Petroleum, Chemicals and Mining Company Limited
Duration : (April 2013–August 2014)
Project Name : SWRO-4 project, Jubail.
EPC for the Medium voltage works.
worked for new development of 34.5 KV SEC Interface Substation 25MVA at SWRO-4 project
Jubail, Removal of existing 34.5 system(Cables and SWGRs) with the coordination of Saudi
Electricity Co. it includes the new Interface Substation Electrical design review, & to get the
approval of design from SEC along with installation of 34.5 KV Load Break Switches with GE
Relay MIFII type, Installation of 34.5 KV Cables, 34.5KV Switch Gear 34.5KV, 127VDC
battery charger with 8 hr Battery bank, AC Panels, DC Panels, lighting Panels, HVAC , fire
alarm System and to establish the 24V Hard wire communication of HVAC, Fire Alarm, with
Remote I/O Cabinet and the communication of Remote I/O cabinet with DCS through Fiber
Optic Cable.
Position : Construction Manager E&I
Employer : Petroleum, Chemicals and Mining Company Limited
Duration : (January 2010 – March 2013)
Project Name : Development of Infra St. facilities at Jubail-2 Phase-2 (065--C46R)
Responsible for to establish the Electrical Substation in Jubail-2 development of Infrastructure
facilities at Jubail-2 Phase-2 project. It includes the close coordination with Saudi Electricity
Co and to get approval for installation on of 34.5 KV load break switches (Type-3 Control &
GE-Relay MIFII), installation of MV Cables, 500KVA 34.5KV XFMR with metering. The SOW
includes the installation of LV cables & SWGR, LV-Panels for MOV and lighting panels at
different valve chambers with 2Nos 3.0KVA UPS, RTUs. Fire alarm system and to establish
FF-Bus, Profibus, Mod bus communication through FO Cables with DCS.
Position : Construction Manager E&I
Employer : Petroleum, Chemicals and Mining Company Limited
Duration : ( March 2006 - January 2010 )
Page 2 of 5
3. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
Project Name : Technical Services Department.
Worked at the proposal department in the main office & responsible for review the E&I work
for Bidding. This includes the estimation of electrical and instrumentation and CP work.
Position : Sr, Engineer E&I.
• Employer : Saudi Binladin Group-PCM
Duration : (June 2005 – February 2006)
Project Name : JUBAIL UNITED PETROCHEMICAL Complex.(JUPC)
The contract work includes the following.
Cathodic Protection work for the intake structure, tanks firehadrent with mechanical piping
and Oxygen Line.
Installation of Field instruments and cable laying Hexane tank.
Installation of control room equipment DCS panels, and Consoles.
Cable tray lighting and conduit works.
Assistance in commissioning works.
• Position : Sr, Engineer E&I.
• Employer : Saudi Binladin Group-PCM
• Duration : (June2002 - November2004)
• Project Name : SWC Wet Wells & pipes for Secondary Industries Park(185-C13)
JUBAIL.
Procurement and construction of seawater cooling laterals, surge tanks flow meter chambers
Outstations with water quality measurement equipment, ancillaries work includes but not
limited to the installation of sluice gates, Cathodic protection work etc.
The E&I work includes the upgrading the outstation#20 at SWC canal and construction of
three new outstations , installation of Cathodic protection work for Diversion chambers 1,2 &3
and Surge Tank A&B .Review RC CP design and installation of ribbon anodes for the
uncoated rebar protection. The Outstation work includes installation of area lighting , RTUs,
Analyzers for water quality measurement, MOV installation of sluice gates and installation of
ultrasonic transmitters at Seawater laterals for flow measurement and transferring of data to
control room through SCADA (Serial communication).
• Position : Sr, Engineer E&I.
• Employer : SBG-PCM
• Duration : (September2000 to May 2002)
Page 3 of 5
4. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
• Project Name : SWC SIPHON REPAIR & OFF TAKE STRUCTURE
PROJECT.JUBAIL.
Procurement const. and replacement of Siphon No.3 and 2 Off Take structure Cathodic
Protection works which includes but not limited to 2nos of precast concrete access bridge,
3.5Mtr dia pipes . The electrical works includes the upgrading the outstation#24 and
construction of new Outstation 24Aincluding the instrumentation installation inside the
outstation and relocation of Pad mounted transformer 34.5KV, 75KVA. The work also
includes the lighting work of the two off take structure flow chambers 24 & 24A field
instruments RTU, Analyzers for the water quality measurement, electrification and
instrumentation of sluice gates Installation of level swiches at flow measurement chambers
and the data transformer through RTU to SWC Control room through SCADA serial
communication.
the Cathodic Protection installation of the concrete Structures of the Diversion Chambers A,
B,C & SURGE tanks A & B having volume appox. (17mx12mx40m) and (17mx8mx36m)
respectively and to develop the communication Link between field to Royal Commission SWC
(Sea Water Cooling) Control room through (SCADA) Communication and to commission the
newly installed facilities.
• Position : Incharge E&I.
• Employer : Saudi Binladin Group –PCM Division
• Duration : (January 1999 to August 2000)
• Project Name : KEMYA MAJOR EXPENTION PROJECT JUBAIL(3 Major
Package)
Selected Underground Construction
Procurement and construction of Sea Water intake and outlet structures foundations for
equipments pipe racks firewater and sea water pipe line area drainage and paving and
distribution duct banks which includes but not limited to 40300M3 of excavation work, 3200
LM of FRP Piping installation and 320 MT of steel structure work.
OSBL Utilities Procurement and construction of FRP Seawater Distribution System from
RC Canal to the entire KEMYA site miscellaneous piping(i.e. potable water sanitary water oily
sewer and waste water) installation of sea water pumps and sluice gates communication
system and power cables which includes but not limited to the complete installation of
Medium voltage cables laying and terminations of seawater intake motors 4.16 KV and switch
gears at substations MV/LV and controls cable laying between the substations. This also
includes the installations of field instruments and ultrasonic flow transmitter at various
locations Upgrading the hardware of DCS of central control room as per new modified works.
Substation Building
Page 4 of 5
5. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
Procurement and construction of 5 No of substation building electrical materials (13.8
KV/4.16KV and 480V equipments (MV/LV switch gears MCCs, Transformers MV/LV, Bus
ducts, lighting panels and accessories) MV/LV Cable laying / termination of MV(4.16KV)
motors & at MCCs, Installation of Fire alarm system paging and public address system
installation of Instt. cabinets consoles indoor and outdoor lighting works.,
• Position : Sr. Engineer E&I.
• Employer : DESCON Engineering. Pakistan.
• Duration : (1993 to 1999)
• Project Name : Various Projects
Specific Duties and Responsibilities/Scope of Work:
Various Project sites in Pakistan:
Fauji Jordan Fertilizer Co. (Pakistan) – As Electrical and Instrumentation Engineer, the
main responsibility was laying of electrical cables installation (MV, LV), testing of electrical
equipment at the main power house with 2 x 13 MW GE Gas Turbines, HRSG, Waste heat
Boiler’s instrument installation, Fire alarm and paging system and installation of field
instruments at the power house gas turbine, utilities, cooling tower and Bagging area along
with Installation of DCS Panels, work stations commissioning of Elsag Belly Distributed
Control System (DCS) at utilities and Ammonia Plant.
Fauji Cement Co, Texila (Pakistan) – As Instrumentation and Electrical Engineer, was
responsible for installation of MV motors at Crushers, Cement mill, and the commissioning of
LV switchgears & MCCs at two sub-station and calibration of field instruments and fire alarm
system in side CCR along with the installation of PLC hardware at CCR.
Lucky Cement Co. D.I. Khan (Pakistan) – Responsible for the installation and
calibration of field instrumentation, installation and commissioning of FoxBoro DCS and fire
alarm system inside the control room
Kadun Wari Gas Fields (Pakistan) – As Instrumentation Engineer at the Gas-field,
under Foster Wheeler, UK, I was responsible for the installation and testing / calibration of
field instruments for Slug Catcher, Fin-fans and Control room Development.
Associated Cement Company, Wah (Pakistan) - as Electrical and Instrumentation
Engineer, responsible for the installation of field instrumentation and installation / testing of
electrical equipment in the MW switchgear and substations with the calibration of FL
smith/ABB.
Position: Operational Supervisor Duration: 1979 to 1984
Employer: Packages Ltd, Pakistan, FF Co.
Project: Lahore and Sadiq-Abad
Page 5 of 5
6. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
Specific Duties and Responsibilities/Scope of Work:
Worked as shift in-charge on Water Treatment Plant (Demineralization Unit) in Packages Ltd.
Lahore and Fauji Fertilizers Co. Pakistan. These plants produce mineral free water to be used
in Thermal Power Generation and Cooling Towers. These units consist of Pre treatment
Plant, Demineralization Units, Mix bed polishers and Waste water treatment plant.
Page 6 of 5
7. Petroleum, Chemicals and MiningPetroleum, Chemicals and Mining
Company LimitedCompany Limited
Project :
Client : Royal Commission for Jubail & Yanbu
Ref.
No.
:
Specific Duties and Responsibilities/Scope of Work:
Worked as shift in-charge on Water Treatment Plant (Demineralization Unit) in Packages Ltd.
Lahore and Fauji Fertilizers Co. Pakistan. These plants produce mineral free water to be used
in Thermal Power Generation and Cooling Towers. These units consist of Pre treatment
Plant, Demineralization Units, Mix bed polishers and Waste water treatment plant.
Page 6 of 5