SlideShare a Scribd company logo
1 of 38
Follow Alder Creek Solar at www.aldercreeksolar.com
or on Facebook at www.facebook.com/AlderCreekSolar/
17 GWproject portfolio
over 200professionals
1,300,000
acres under lease
founded in
2009
2,867MW
completed
By the Numbers
Our Core ValuesProject Portfolio
About Apex Clean Energy
Safety
Professionalism
Integrity
Sustainability
Entrepreneurship
The Best Projects in the Business
Apex Clean Energy has secured financing for over 5 GW of wind and solar projects across the United States, many of which are now
operating or under construction. Visit apexcleanenergy.com/projects to learn more about these and our other completed facilities.
Featured Project
Phantom Solar
The Defense Logistics Agency partnered with Apex in 2016,
resulting in a 28-year renewable energy supply agreement
serving Fort Hood, the largest active-duty armored post in the
United States.
Cotton Plains (50 MW, Texas)
Cameron (165 MW, Texas) Kay (299 MW, Oklahoma)
Aviator (525 MW, Texas)
As of April 2017, Apex’s facilities are
providing more than 50% of the
electricity at Fort Hood.
“The project at Fort Hood, the
Army’s first hybrid and largest
single renewable energy project to
date, is an excellent example of the
extraordinary results we can
achieve through collaboration.”
—Katherine Hammack, Assistant
Secretary of the Army for
Installations, Energy, and
Environment
Project Details
Capacity 15.4 MWAC / 19.6 MWDC
Technology
62,725 Canadian Solar
PV modules
ISO / RTO ERCOT
Owner
Northleaf Capital and
Apex Clean Energy
Construction
Manager
Apex Clean Energy
Asset
Manager
Apex Clean Energy
Industry Awards
Hoopeston (98 MW, Illinois)
Grant (152 MW, Oklahoma)
Alder Creek Solar Project Team
• Carmen O’Keefe –
Project Developer, Apex Clean Energy
• Brian O’Shea –
Public Engagement Manager, Apex Clean Energy
• Jessica Walsh –
Development Associate, Apex Clean Energy
• Brian Schwabenbauer –
Environmental Operations Manager, TRC
• Hayley Effler –
Environmental Permitting Project Manager, TRC
• Chris Moon –
Senior Electrical Engineer, Apex Clean Energy
Project Overview
Alder Creek Solar – Project Overview
Location:
Towns of Boonville and Forestport,
Oneida County, New York
Project Capacity:
150-200 MW (enough to power
approximately 21,000 homes)
Project Footprint:
Up to 1,000 acres
Targeted Operations Date:
Winter 2023
Project Area
Solar energy is an abundant, inexpensive, natural resource that
is not dependent on imported fuel from other states or countries.
Solar energy’s average
annual growth rate over
the past decade
Solar is already powering the United States,
but the potential is huge.
38.4
47.2
4.8
6.2
7.8
14.6
10.8
2013 2014 2015 2016 2017 2018–2020 2021–2025
Annual U.S. Solar Installations (GW)
projected
59%
Why Solar?
Why New York?
New York’s Solar AdvantageNew York Is 9th in Nation in Solar
The Empire State has driven investment in solar
• More than 325,000 homes in New York are powered by
solar energy
• The state has close to 2 GW of installed solar and
receives 1.67% of its electricity from solar power
• There are 989 solar companies in New York (117
manufacturers, 345 installers/developers, and 527 others)
• The total solar investment in New York to date is over
$5.1 billion.
• Prices have fallen 32% over the past five years
• The projected capacity in New York over the next five
years is 3,622 MW, which would rank the state as 7th in
the nation for solar energy.
“In 2014, we committed $1 billion to the local solar
industry—now employing the fourth largest statewide
solar workforce in the country—with the expectation
that REV (Reforming the Energy Vision) will drive a
subsidy-free solar market in New York within 10 years.”
—Richard L. Kauffman, Chairman of Energy and
Finance for New York, 2015 New York State Energy Plan
Solar Power Works
In New York Nationally
• With significant utility-scale development on the horizon,
New York's solar capacity is expected to grow by more than
185% over the next five years
• More than 9,700 people are employed in solar energy in
New York, making the state 4th in the nation for solar jobs
• 60 GW of solar capacity has been installed nationwide
• There are over 240,000 Americans working in solar,
more people than are employed in the entire fossil fuel
sector for electricity generation
• Nearly 2 million solar energy systems are operating in
the United States
SOLAR JOBS BY SECTOR
INSTALLATION
7,182
MANUFACTURING
508
WHOLESALE TRADE
AND DISTRIBUTION
1,049
OPERATIONS AND
MAINTENANCE
477
OTHER
514
12,582
62,987
66,448
86,202
111,166
112,685
211,469
242,343
U.S. ENERGY JOBS WITHIN
THE ELECTRICITY INDUSTRY (2019)
Solar
All Fossil Fuels
Natural Gas
Wind
Coal
Hydro
Nuclear
Oil
Solar provides
more jobs than
all fossil fuels
together
How Solar Power Works
How Solar Panels Work
Solar Energy
Electromagnetic energy transmitted from the sun (solar radiation). The
amount that reaches the earth is equal to one billionth of total solar
energy generated, or the equivalent of about 420 trillion kilowatt-hours.
Solar Resource
The amount of solar insolation a site receives, usually measured in
kWh/m2/day, which is equivalent to the number of peak sun hours.
Solar Power
Solar power is the conversion of solar energy into electricity
through a phenomenon called the photovoltaic effect.
Solar panels convert
sunlight into electricity
Where Does the Power Go?
To the Grid!
Electricity generated by Alder Creek Solar will go onto the state’s electrical grid by
connecting to the existing National Grid Chases Lake-Porter 230 kilovolt (kV)
power line located in Boonville.
From the grid, the power generated by
Alder Creek Solar could be used locally or
sent where it is needed depending on line
capacity, local generation, and demand.
So who uses the power?
DC Solar Array
DC Collection System
Inverter/Power Conversion Station
Project Collector Substation
The Albedo Effect
Increased reflectivity, or albedo, from the snow-covered ground can
also increase the efficiency of solar panels. There are even bifacial
modules that can allow a panel to generate electricity from both
sides to take advantage of this reflected solar radiation.
Solar Energy in Wintertime Do solar panels work in the wintertime?
Yes, they do! While reduced daylight hours affect how often
panels are generating electricity, you might be surprised to
learn that sunny, cold conditions actually increase efficiency for
solar panels compared to extremely hot climates, which can
reduce efficiency.
How does snow affect solar panels?
Solar panels can continue generating electricity even through a light coating
of snow because of a phenomenon called forward-scattering, where the
snow reflects photons from sunlight to generate energy.
Heavier snowfalls can still block generation, but because panels are often
significantly warmer than the ambient temperature and tilted at an angle,
snow will usually slide right off. As an added benefit, the snow often takes
any accumulated dust and dirt with it, cleaning the panel in the same way
that snow cleans your car’s windshield when it melts.
snowy ground
diffuse light
albedo
bifacial solar panel
What Happens When It’s Cloudy?
Fortunately for us, solar radiation still gets through to
warm up the Earth’s surface, even when it is cloudy.
Have you ever noticed how people can still end up
with a sunburn when skiing on a cloudy day? That’s
because up to 80% of the sun’s UV rays still pass
through the clouds.
Though solar panels primarily use visible and infrared
light, they can still generate electricity in cloudy
weather because there is visible and infrared light that
can penetrate the clouds and be captured by panels.
Studies have shown that solar panels can produce
as much as 25% of their usual output on a cloudy day
and even up to 10% of usual output with heavy clouds.
ozone layer
UVC
UVB
UVA
cloud cover
Shading
• The output current of the PV
module is a function of solar
irradiance, so a reduction in solar
irradiance as a result of partial or
complete shading will affect the
performance of the entire module
• Every cell in the string has to
operate at the current set by the
shaded cell
• We design array to reduce or
eliminate consistent shading
events
Tracking Systems
• Fixed Tilt
• Single-Axis Tracker
• Two-Axis Tracker
Safety Considerations
• Grounding Studies
o Step and touch potential
• TOV Studies
• Arch Flash Studies
• Ampacity Studies
• NFPA 70/NEC
NEC Article 705.10 “A permanent plaque or directory
denoting the location of all electric power source
disconnecting means on or in the premises shall be
installed at each service equipment location and at
the location(s) of the system disconnect(s) for all
electric power production sources capable of being
interconnected. The marking shall comply with
110.21(B).”
Emergency Response Preparedness
• Formal training for all project personnel
including first-aid training
• Development of emergency response plans
with local authorities
• Site specific training with local emergency
responders before and during operations,
including PV-specific emergency response
• Ongoing drills with local EMS and fire
professionals during operations covering
medical, fire, and other emergencies
• Article 10 requires specific plans in regards to
Public Safety and Emergency Response
(Exhibits 15, 18, and associated appendices)
Recycling Solar Panels
• With no moving parts, solar panels are durable and
are expected to function effectively for up to 40 years.
• At the end of a solar facility’s useful life (30 years on
average), panels can be removed and recycled.
• Alder Creek Solar will be required to fully fund a
decommissioning plan so local communities will not
bear any cost for removal of project assets (Article 10
application, Exhibit 29).
Up to 90% of the materials used in panels, much of
which is glass, are recyclable and can be
remanufactured into new panels.
76%
glass
10%
plastic
8%
aluminum
5%
silicon
1%
metals
The Recycling Process
Disassembly
of aluminum
and glass parts
95%
glass reused
thermal
processing
at 500°C
100%
metal reused
plastic cover
evaporates
reused as
heat source
physical
separation
of cell modules
etching
away of
silicon wafers
melting
broken
wafers
80%
modules
reused
85%
silicon
reused
The International Renewable Energy Agency projects that the
value of recovered materials could exceed $15 billion by 2050
and could be used to remanufacture two billion solar panels.
Article 10 Permitting Process
What is Article 10?
• Article 10 of the New York State Public Service Law defines a clear process for public
engagement in permitting large electric generating facilities.
• Applies to electric generating facilities with 25 MW generating capacity or more, including
renewable energy projects.
• Includes environmental justice and environmental and health requirements.
• Ensures broad public involvement opportunities throughout the process.
• Makes funds available to local parties and municipalities through an Intervenor Fund so
they can make an effective contribution to the proceedings.
• Requires the creation of a Public Involvement Program Plan, summarizing project
efforts to educate, inform, and involve the public in the permitting process.
Article 10 Process
Where are we now?
• Revised Public Involvement Program Plan submitted –
11/22/19
• This document can be found on our website and outlines our plans to
engage with area residents and stakeholders throughout the
development process. Hard copies are available at the Boonville Town
Hall, Forestport Town Hall, Erwin Library and Institute, and the
Woodgate Free Library.
• Preliminary Scoping Statement (PSS) – Spring 2020
• The PSS is a written document informing the Siting Board, other
public agencies, and the community about the project, including a
description of the proposed facility, potential environmental and health
impacts, proposed studies to evaluate those impacts, proposed
mitigation measures and reasonable alternatives to the project.
• After the PSS is submitted, intervenor funding becomes available for
local communities and stakeholders.
What is Intervenor Funding?
• Article 10 applicants are required to provide funds to be used
to defray certain expenses related to application review and
development of stipulations incurred by municipal and local
parties as they participate in the Article 10 process.
• These funds are distributed twice - once after the Preliminary
Scoping Statement (PSS) is submitted and once after the
application is submitted.
• The process of applying for the first round of intervenor
funding for Alder Creek Solar will begin after the PSS is filed.
• Amount of funds: The first round of intervenor funding is
equal to $350 per megawatt (MW) up to a cap of $200,000
What Goes Into an Article 10 Application?
List of Article 10 Exhibits
Exhibit 1: General Requirements Exhibit 11: Preliminary Design Drawings
Exhibit 2: Overview and Public Involvement Exhibit 12: Construction
Exhibit 3: Location of Facilities Exhibit 13: Real Property
Exhibit 4: Land Use Exhibit 14: Cost of Facilities
Exhibit 5: Electric System Effects Exhibit 15: Public Health and Safety
Exhibit 6: Wind Power Facilities (Not Applicable) Exhibit 16: Pollution Control Facilities (Not Applicable)
Exhibit 7: Natural Gas Power Facilities (Not Applicable) Exhibit 17: Air Emissions (Not Applicable)
Exhibit 8: Electric System Production Exhibit 18: Safety and Security
Exhibit 9: Alternatives Exhibit 19: Noise and Vibration
Exhibit 10: Consistency with Energy Planning Objectives Exhibit 20: Cultural Resources
What Goes Into an Article 10 Application? (Cont.)
List of Article 10 Exhibits (continued)
Exhibit 21: Geology, Seismology, Soils Exhibit 31: Local Laws and Ordinances
Exhibit 22: Terrestrial Ecology and Wetlands
(Includes field studies and analyses such as wetland and stream
delineations, vernal pool surveys, and winter raptor surveys)
Exhibit 32: State Laws and Regulations
Exhibit 23: Water Resources and Aquatic Ecology Exhibit 33: Other Applications and Filings
Exhibit 24: Visual Impacts
(Includes the Visual Impact Assessment and Photo Simulations)
Exhibit 34: Electric Interconnection
Exhibit 25: Impacts on Transportation Exhibit 35: Electric and Magnetic Fields
Exhibit 26: Effect on Communications Exhibit 36: Gas Interconnection (Not Applicable)
Exhibit 27: Socioeconomic Effects
(Includes an analysis of economic effects utilizing the National
Renewable Energy Laboratory’s Job and Economic Development
(JEDI) solar voltaic model)
Exhibit 37: Back-Up Fuel (Not Applicable)
Exhibit 28: Environmental Justice Exhibit 38: Water Interconnection (Not Applicable)
Exhibit 29: Site Restoration and Decommissioning Exhibit 39: Wastewater Interconnection (Not Applicable)
Exhibit 30: Nuclear Facilities (Not Applicable) Exhibit 40: Telecommunications Interconnection
Exhibit 41: Applications to Modify or Build Adjacent
(Not Applicable)
Studies Required for Article 10
• Wetlands, Waters and Streams (Exhibit 22):
• Wetland and Stream Delineation
• Vernal Pool Surveys
• Threatened and Endangered Species (Exhibit 22):
• Birds
• Winter Raptor Surveys
• Wildlife and Habitat (Exhibit 22)
• Invasive Species (Exhibit 22)
• Cultural Resources (Exhibit 20):
• Archaeological Resources
• Phase 1A/1B Study
• Historic Architecture
• Local Laws (Exhibit 31)
• Environmental Justice (Exhibit 28)
Studies Required for Article 10 (continued)
• Noise (Exhibit 19):
• Noise Impact Assessment
• Visual Effects (Exhibit 24):
• Visual Impact Assessment
• Viewshed Analysis
• Photo-simulations
• Shadow Flicker Analysis
• Glare Analysis
• Land Use Evaluation (Exhibit 4)
• Socioeconomic Effects (Exhibit 27)
• Geology, Seismology, and Soils (Exhibit 21)
• Safety and Security (Exhibit 18)
• Transportation (Exhibit 25)
• Site Decommissioning/Restoration (Exhibit 29)
• Communication Effects (Exhibit 26)
• Oils and Gas Infrastructure
Public & Community Engagement
Public & Community Engagement
• Public Meetings, Community Forums,
and Open Houses
• Town, County, and School District
Board Meetings
• Community Events
• Mailings
• In-person meetings and phone
conversations
• Online through our website
(www.aldercreeksolar.com) and Facebook
(@AlderCreekSolar)
As a community-focused company, we not only want to hear from you, but we
will be out in the community making ourselves available to answer questions
and gather feedback.
Let us know where else we can engage
with you and your neighbors!
Alder Creek Solar - Local Benefits
Local Economic Benefits
Some of the key estimates for the Alder Creek Solar project are below.
Local Revenue through Host Community Agreements and PILOT Agreements
Estimated $400,000 annually with inflation to the local taxing jurisdictions
Actual amounts and term dependent upon negotiations with Boonville and Forestport on Town Host Community
Agreements and Oneida County, Adirondack Central School District, and the two towns on PILOT Agreement.
Jobs
During construction:
• Between 125 and 200 construction jobs created directly by the project
During project operations (25+ years):
• 2 direct, long-term, local jobs employed for operations and maintenance of project
• Additional local subcontractors for site maintenance, including vegetative management, road repair, plowing,
substation/transformer/inverter maintenance, and module cleaning when needed.
Project Schedule (subject to change)
Outreach Dates
Preliminary Scoping Statement Submitted Spring 2020
Project Studies (Environmental & Wildlife, Ambient Noise, Viewshed Analysis,
Wetlands, Cultural & Historic Resources, Economic Impacts, Communications,
Decommissioning, and other applicable studies)
Present – Fall 2020
Public & Community Engagement (Public Meetings, Community Conversations,
Town Official Engagement, Ordinance Development, Host Community Agreement
and PILOT Agreement Negotiations)
Ongoing
Stipulations Period Spring 2020 – Fall 2020
Permit Application Late 2020
Initial Permit Review, Permit Deemed Complete Early 2021
Permit Hearings & Siting Board Review 2021
Siting Board Determination (Approval or Rejection of Application) Early 2022
Construction Commences Spring/Summer 2022
Construction Complete Fall 2023
Project Begins Operations Winter 2023
Follow Alder Creek Solar at www.aldercreeksolar.com
or on Facebook at www.facebook.com/AlderCreekSolar/

More Related Content

What's hot

Solar energy and Acid Rain Presentation
Solar energy and Acid Rain PresentationSolar energy and Acid Rain Presentation
Solar energy and Acid Rain PresentationMaheep Chhabra
 
Environmentalreviewpaper57371357
Environmentalreviewpaper57371357Environmentalreviewpaper57371357
Environmentalreviewpaper57371357Aun Ahsan
 
Innovative Applications Of Solar Energy
Innovative Applications Of Solar EnergyInnovative Applications Of Solar Energy
Innovative Applications Of Solar Energyswapnil_energy
 
Solar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus JägerSolar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus JägerUNICORNS IN TECH
 
Gem ppt-2-solar energy
Gem ppt-2-solar energyGem ppt-2-solar energy
Gem ppt-2-solar energyijcparish
 
Pusad solar power plant presentation (rev 7)
Pusad solar power plant presentation  (rev 7)Pusad solar power plant presentation  (rev 7)
Pusad solar power plant presentation (rev 7)California Free Solar
 
Desert Research Institute - Science Distilled - Batteries Included
Desert Research Institute - Science Distilled - Batteries IncludedDesert Research Institute - Science Distilled - Batteries Included
Desert Research Institute - Science Distilled - Batteries IncludedMeghan Collins
 
Solar energy presentation
Solar energy presentationSolar energy presentation
Solar energy presentationMalika Alix
 
Ken Zweibel | A Solar Solution
Ken Zweibel | A Solar SolutionKen Zweibel | A Solar Solution
Ken Zweibel | A Solar SolutionGW Solar Institute
 
Assignment - Building Integration of Solar Energy (Report)
Assignment - Building Integration of Solar Energy (Report)Assignment - Building Integration of Solar Energy (Report)
Assignment - Building Integration of Solar Energy (Report)Kai Yun Pang
 
Scott Sklar | The Stella Group
Scott Sklar | The Stella GroupScott Sklar | The Stella Group
Scott Sklar | The Stella GroupGW Solar Institute
 
Solar mission
Solar missionSolar mission
Solar missionkundana
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportAnkit Singh
 
Renewable Energy Sources Lecture Notes
Renewable Energy Sources Lecture NotesRenewable Energy Sources Lecture Notes
Renewable Energy Sources Lecture NotesFellowBuddy.com
 
Indian Scene_solar energy
Indian Scene_solar energyIndian Scene_solar energy
Indian Scene_solar energyBharath P
 

What's hot (18)

Solar energy and Acid Rain Presentation
Solar energy and Acid Rain PresentationSolar energy and Acid Rain Presentation
Solar energy and Acid Rain Presentation
 
Environmentalreviewpaper57371357
Environmentalreviewpaper57371357Environmentalreviewpaper57371357
Environmentalreviewpaper57371357
 
Innovative Applications Of Solar Energy
Innovative Applications Of Solar EnergyInnovative Applications Of Solar Energy
Innovative Applications Of Solar Energy
 
Solar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus JägerSolar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus Jäger
 
Solar power
Solar powerSolar power
Solar power
 
Gem ppt-2-solar energy
Gem ppt-2-solar energyGem ppt-2-solar energy
Gem ppt-2-solar energy
 
Pusad solar power plant presentation (rev 7)
Pusad solar power plant presentation  (rev 7)Pusad solar power plant presentation  (rev 7)
Pusad solar power plant presentation (rev 7)
 
Desert Research Institute - Science Distilled - Batteries Included
Desert Research Institute - Science Distilled - Batteries IncludedDesert Research Institute - Science Distilled - Batteries Included
Desert Research Institute - Science Distilled - Batteries Included
 
Solar energy presentation
Solar energy presentationSolar energy presentation
Solar energy presentation
 
Ken Zweibel | A Solar Solution
Ken Zweibel | A Solar SolutionKen Zweibel | A Solar Solution
Ken Zweibel | A Solar Solution
 
Assignment - Building Integration of Solar Energy (Report)
Assignment - Building Integration of Solar Energy (Report)Assignment - Building Integration of Solar Energy (Report)
Assignment - Building Integration of Solar Energy (Report)
 
Scott Sklar | The Stella Group
Scott Sklar | The Stella GroupScott Sklar | The Stella Group
Scott Sklar | The Stella Group
 
Solar mission
Solar missionSolar mission
Solar mission
 
Unesco solar panel
Unesco solar panelUnesco solar panel
Unesco solar panel
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transport
 
Renewable Energy Sources Lecture Notes
Renewable Energy Sources Lecture NotesRenewable Energy Sources Lecture Notes
Renewable Energy Sources Lecture Notes
 
Indian Scene_solar energy
Indian Scene_solar energyIndian Scene_solar energy
Indian Scene_solar energy
 
Light Up Nigeria Programme
Light Up Nigeria ProgrammeLight Up Nigeria Programme
Light Up Nigeria Programme
 

Similar to Alder Creek Solar February 2020 Public Information Meetings

Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic ProjectHarry Indig
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic ProjectHarry Indig
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solarmacsolar77
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solarmacsolar77
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solarmacsolar77
 
Solar-101-workshop-midwest-2018-small (1).pptx
Solar-101-workshop-midwest-2018-small (1).pptxSolar-101-workshop-midwest-2018-small (1).pptx
Solar-101-workshop-midwest-2018-small (1).pptxM. Muzammil Ejaz .
 
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptx
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptxESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptx
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptxNamanThakur20bee037
 
RenergyCo: Solar PV for Commercial Properties
RenergyCo: Solar PV for Commercial PropertiesRenergyCo: Solar PV for Commercial Properties
RenergyCo: Solar PV for Commercial Propertiesiandiamond
 
Solarize Syracuse workshop
Solarize Syracuse workshopSolarize Syracuse workshop
Solarize Syracuse workshopbriandominick
 
Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Daniel Davies
 
VISHAL INGALE.pptx
VISHAL INGALE.pptxVISHAL INGALE.pptx
VISHAL INGALE.pptxSumitSabale4
 
Solar-Investment-Case-MAC-Solar.pdf
Solar-Investment-Case-MAC-Solar.pdfSolar-Investment-Case-MAC-Solar.pdf
Solar-Investment-Case-MAC-Solar.pdfmacsolar77
 
Enhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightEnhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightIRJET Journal
 
Caddo Wind Virtual Public Meeting Presentation
Caddo Wind Virtual Public Meeting PresentationCaddo Wind Virtual Public Meeting Presentation
Caddo Wind Virtual Public Meeting PresentationHeritage Wind
 
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANT
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANTDESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANT
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANTvivatechijri
 
Bs solar energy report
Bs solar energy reportBs solar energy report
Bs solar energy reportSheng Zhe
 
Forecasting Solar Power by LSTM & DBN Techniques using ML
Forecasting Solar Power by LSTM & DBN Techniques using MLForecasting Solar Power by LSTM & DBN Techniques using ML
Forecasting Solar Power by LSTM & DBN Techniques using MLIRJET Journal
 
a study on customer awarness and attitude towards solar products
a study on customer awarness and attitude towards solar productsa study on customer awarness and attitude towards solar products
a study on customer awarness and attitude towards solar productsKushal Shah
 
Mastering solar planning & permits presentation 10182011
Mastering solar planning & permits presentation 10182011Mastering solar planning & permits presentation 10182011
Mastering solar planning & permits presentation 10182011Center for Sustainable Energy
 

Similar to Alder Creek Solar February 2020 Public Information Meetings (20)

Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic Project
 
Photovoltaic Project
Photovoltaic ProjectPhotovoltaic Project
Photovoltaic Project
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solar
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solar
 
Solar investment-case-mac-solar
Solar investment-case-mac-solarSolar investment-case-mac-solar
Solar investment-case-mac-solar
 
Solar-101-workshop-midwest-2018-small (1).pptx
Solar-101-workshop-midwest-2018-small (1).pptxSolar-101-workshop-midwest-2018-small (1).pptx
Solar-101-workshop-midwest-2018-small (1).pptx
 
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptx
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptxESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptx
ESTIMATION OF SOLAR ENERGY AVAILABILITY (1).pptx
 
RenergyCo: Solar PV for Commercial Properties
RenergyCo: Solar PV for Commercial PropertiesRenergyCo: Solar PV for Commercial Properties
RenergyCo: Solar PV for Commercial Properties
 
Solarize Syracuse workshop
Solarize Syracuse workshopSolarize Syracuse workshop
Solarize Syracuse workshop
 
Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216
 
VISHAL INGALE.pptx
VISHAL INGALE.pptxVISHAL INGALE.pptx
VISHAL INGALE.pptx
 
Detailed project report.pptx
Detailed project report.pptxDetailed project report.pptx
Detailed project report.pptx
 
Solar-Investment-Case-MAC-Solar.pdf
Solar-Investment-Case-MAC-Solar.pdfSolar-Investment-Case-MAC-Solar.pdf
Solar-Investment-Case-MAC-Solar.pdf
 
Enhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightEnhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlight
 
Caddo Wind Virtual Public Meeting Presentation
Caddo Wind Virtual Public Meeting PresentationCaddo Wind Virtual Public Meeting Presentation
Caddo Wind Virtual Public Meeting Presentation
 
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANT
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANTDESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANT
DESIGN AND FABRICATION OF FLOATING SOLAR POWER PLANT
 
Bs solar energy report
Bs solar energy reportBs solar energy report
Bs solar energy report
 
Forecasting Solar Power by LSTM & DBN Techniques using ML
Forecasting Solar Power by LSTM & DBN Techniques using MLForecasting Solar Power by LSTM & DBN Techniques using ML
Forecasting Solar Power by LSTM & DBN Techniques using ML
 
a study on customer awarness and attitude towards solar products
a study on customer awarness and attitude towards solar productsa study on customer awarness and attitude towards solar products
a study on customer awarness and attitude towards solar products
 
Mastering solar planning & permits presentation 10182011
Mastering solar planning & permits presentation 10182011Mastering solar planning & permits presentation 10182011
Mastering solar planning & permits presentation 10182011
 

More from Heritage Wind

Figure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaFigure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaHeritage Wind
 
Figure 6 1. Setbacks
Figure 6 1. SetbacksFigure 6 1. Setbacks
Figure 6 1. SetbacksHeritage Wind
 
Figure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaFigure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaHeritage Wind
 
Figure 4-2. Land Use Programs
Figure 4-2. Land Use ProgramsFigure 4-2. Land Use Programs
Figure 4-2. Land Use ProgramsHeritage Wind
 
Figure 4-1. Existing Land Use
Figure 4-1. Existing Land UseFigure 4-1. Existing Land Use
Figure 4-1. Existing Land UseHeritage Wind
 
Figure 3-3. Municipal Boundaries Temp Road Improvements
Figure 3-3. Municipal Boundaries Temp Road ImprovementsFigure 3-3. Municipal Boundaries Temp Road Improvements
Figure 3-3. Municipal Boundaries Temp Road ImprovementsHeritage Wind
 
Figure 3-2. Interconnection Location
Figure 3-2. Interconnection LocationFigure 3-2. Interconnection Location
Figure 3-2. Interconnection LocationHeritage Wind
 
Figure 3-1. Proposed Major Electric Generating Facility Location
Figure 3-1. Proposed Major Electric Generating Facility LocationFigure 3-1. Proposed Major Electric Generating Facility Location
Figure 3-1. Proposed Major Electric Generating Facility LocationHeritage Wind
 
Figure 2-2. Facility Layout
Figure 2-2. Facility LayoutFigure 2-2. Facility Layout
Figure 2-2. Facility LayoutHeritage Wind
 
Figure 28-1. Potential Environmental Justice Areas
Figure 28-1. Potential Environmental Justice AreasFigure 28-1. Potential Environmental Justice Areas
Figure 28-1. Potential Environmental Justice AreasHeritage Wind
 
Figure 23-2. Surface Waters
Figure 23-2. Surface WatersFigure 23-2. Surface Waters
Figure 23-2. Surface WatersHeritage Wind
 
Figure 22-3. Delineated Wetlands and Surface Waters
Figure 22-3. Delineated Wetlands and Surface WatersFigure 22-3. Delineated Wetlands and Surface Waters
Figure 22-3. Delineated Wetlands and Surface WatersHeritage Wind
 
Figure 22-2. Significant Natural Communities
Figure 22-2. Significant Natural CommunitiesFigure 22-2. Significant Natural Communities
Figure 22-2. Significant Natural CommunitiesHeritage Wind
 
Figure 22-1. Impact to Plant Communities (Part 2)
Figure 22-1. Impact to Plant Communities (Part 2)Figure 22-1. Impact to Plant Communities (Part 2)
Figure 22-1. Impact to Plant Communities (Part 2)Heritage Wind
 
Figure 22-1. Impact to Plant Communities (Part 1)
Figure 22-1. Impact to Plant Communities (Part 1)Figure 22-1. Impact to Plant Communities (Part 1)
Figure 22-1. Impact to Plant Communities (Part 1)Heritage Wind
 
Figure 21-3. Bedrock
Figure 21-3. BedrockFigure 21-3. Bedrock
Figure 21-3. BedrockHeritage Wind
 
Figure 21-2. Soil Types
Figure 21-2. Soil TypesFigure 21-2. Soil Types
Figure 21-2. Soil TypesHeritage Wind
 
Figure 19-1. Sensitive Receptor Locations
Figure 19-1. Sensitive Receptor LocationsFigure 19-1. Sensitive Receptor Locations
Figure 19-1. Sensitive Receptor LocationsHeritage Wind
 
Figure 15-1. Public Health and Safety Maps
Figure 15-1. Public Health and Safety MapsFigure 15-1. Public Health and Safety Maps
Figure 15-1. Public Health and Safety MapsHeritage Wind
 

More from Heritage Wind (20)

Figure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaFigure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study Area
 
Figure 6 1. Setbacks
Figure 6 1. SetbacksFigure 6 1. Setbacks
Figure 6 1. Setbacks
 
Figure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study AreaFigure 3.1-1. Visual Study Area
Figure 3.1-1. Visual Study Area
 
Figure 4-2. Land Use Programs
Figure 4-2. Land Use ProgramsFigure 4-2. Land Use Programs
Figure 4-2. Land Use Programs
 
Figure 4-1. Existing Land Use
Figure 4-1. Existing Land UseFigure 4-1. Existing Land Use
Figure 4-1. Existing Land Use
 
Figure 3-3. Municipal Boundaries Temp Road Improvements
Figure 3-3. Municipal Boundaries Temp Road ImprovementsFigure 3-3. Municipal Boundaries Temp Road Improvements
Figure 3-3. Municipal Boundaries Temp Road Improvements
 
Figure 3-2. Interconnection Location
Figure 3-2. Interconnection LocationFigure 3-2. Interconnection Location
Figure 3-2. Interconnection Location
 
Figure 3-1. Proposed Major Electric Generating Facility Location
Figure 3-1. Proposed Major Electric Generating Facility LocationFigure 3-1. Proposed Major Electric Generating Facility Location
Figure 3-1. Proposed Major Electric Generating Facility Location
 
Figure 2-2. Facility Layout
Figure 2-2. Facility LayoutFigure 2-2. Facility Layout
Figure 2-2. Facility Layout
 
Figure 28-1. Potential Environmental Justice Areas
Figure 28-1. Potential Environmental Justice AreasFigure 28-1. Potential Environmental Justice Areas
Figure 28-1. Potential Environmental Justice Areas
 
Figure 23-2. Surface Waters
Figure 23-2. Surface WatersFigure 23-2. Surface Waters
Figure 23-2. Surface Waters
 
Figure 22-3. Delineated Wetlands and Surface Waters
Figure 22-3. Delineated Wetlands and Surface WatersFigure 22-3. Delineated Wetlands and Surface Waters
Figure 22-3. Delineated Wetlands and Surface Waters
 
Figure 22-2. Significant Natural Communities
Figure 22-2. Significant Natural CommunitiesFigure 22-2. Significant Natural Communities
Figure 22-2. Significant Natural Communities
 
Figure 22-1. Impact to Plant Communities (Part 2)
Figure 22-1. Impact to Plant Communities (Part 2)Figure 22-1. Impact to Plant Communities (Part 2)
Figure 22-1. Impact to Plant Communities (Part 2)
 
Figure 22-1. Impact to Plant Communities (Part 1)
Figure 22-1. Impact to Plant Communities (Part 1)Figure 22-1. Impact to Plant Communities (Part 1)
Figure 22-1. Impact to Plant Communities (Part 1)
 
Figure 21-3. Bedrock
Figure 21-3. BedrockFigure 21-3. Bedrock
Figure 21-3. Bedrock
 
Figure 21-2. Soil Types
Figure 21-2. Soil TypesFigure 21-2. Soil Types
Figure 21-2. Soil Types
 
Figure 21-1. Slope
Figure 21-1. SlopeFigure 21-1. Slope
Figure 21-1. Slope
 
Figure 19-1. Sensitive Receptor Locations
Figure 19-1. Sensitive Receptor LocationsFigure 19-1. Sensitive Receptor Locations
Figure 19-1. Sensitive Receptor Locations
 
Figure 15-1. Public Health and Safety Maps
Figure 15-1. Public Health and Safety MapsFigure 15-1. Public Health and Safety Maps
Figure 15-1. Public Health and Safety Maps
 

Recently uploaded

OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )Pooja Nehwal
 

Recently uploaded (20)

OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
WhatsApp 📞 9892124323 ✅Call Girls In Juhu ( Mumbai )
 

Alder Creek Solar February 2020 Public Information Meetings

  • 1. Follow Alder Creek Solar at www.aldercreeksolar.com or on Facebook at www.facebook.com/AlderCreekSolar/
  • 2. 17 GWproject portfolio over 200professionals 1,300,000 acres under lease founded in 2009 2,867MW completed By the Numbers Our Core ValuesProject Portfolio About Apex Clean Energy Safety Professionalism Integrity Sustainability Entrepreneurship
  • 3. The Best Projects in the Business Apex Clean Energy has secured financing for over 5 GW of wind and solar projects across the United States, many of which are now operating or under construction. Visit apexcleanenergy.com/projects to learn more about these and our other completed facilities. Featured Project Phantom Solar The Defense Logistics Agency partnered with Apex in 2016, resulting in a 28-year renewable energy supply agreement serving Fort Hood, the largest active-duty armored post in the United States. Cotton Plains (50 MW, Texas) Cameron (165 MW, Texas) Kay (299 MW, Oklahoma) Aviator (525 MW, Texas) As of April 2017, Apex’s facilities are providing more than 50% of the electricity at Fort Hood. “The project at Fort Hood, the Army’s first hybrid and largest single renewable energy project to date, is an excellent example of the extraordinary results we can achieve through collaboration.” —Katherine Hammack, Assistant Secretary of the Army for Installations, Energy, and Environment Project Details Capacity 15.4 MWAC / 19.6 MWDC Technology 62,725 Canadian Solar PV modules ISO / RTO ERCOT Owner Northleaf Capital and Apex Clean Energy Construction Manager Apex Clean Energy Asset Manager Apex Clean Energy Industry Awards Hoopeston (98 MW, Illinois) Grant (152 MW, Oklahoma)
  • 4. Alder Creek Solar Project Team • Carmen O’Keefe – Project Developer, Apex Clean Energy • Brian O’Shea – Public Engagement Manager, Apex Clean Energy • Jessica Walsh – Development Associate, Apex Clean Energy • Brian Schwabenbauer – Environmental Operations Manager, TRC • Hayley Effler – Environmental Permitting Project Manager, TRC • Chris Moon – Senior Electrical Engineer, Apex Clean Energy
  • 6. Alder Creek Solar – Project Overview Location: Towns of Boonville and Forestport, Oneida County, New York Project Capacity: 150-200 MW (enough to power approximately 21,000 homes) Project Footprint: Up to 1,000 acres Targeted Operations Date: Winter 2023
  • 8. Solar energy is an abundant, inexpensive, natural resource that is not dependent on imported fuel from other states or countries. Solar energy’s average annual growth rate over the past decade Solar is already powering the United States, but the potential is huge. 38.4 47.2 4.8 6.2 7.8 14.6 10.8 2013 2014 2015 2016 2017 2018–2020 2021–2025 Annual U.S. Solar Installations (GW) projected 59% Why Solar?
  • 9. Why New York? New York’s Solar AdvantageNew York Is 9th in Nation in Solar The Empire State has driven investment in solar • More than 325,000 homes in New York are powered by solar energy • The state has close to 2 GW of installed solar and receives 1.67% of its electricity from solar power • There are 989 solar companies in New York (117 manufacturers, 345 installers/developers, and 527 others) • The total solar investment in New York to date is over $5.1 billion. • Prices have fallen 32% over the past five years • The projected capacity in New York over the next five years is 3,622 MW, which would rank the state as 7th in the nation for solar energy. “In 2014, we committed $1 billion to the local solar industry—now employing the fourth largest statewide solar workforce in the country—with the expectation that REV (Reforming the Energy Vision) will drive a subsidy-free solar market in New York within 10 years.” —Richard L. Kauffman, Chairman of Energy and Finance for New York, 2015 New York State Energy Plan
  • 10. Solar Power Works In New York Nationally • With significant utility-scale development on the horizon, New York's solar capacity is expected to grow by more than 185% over the next five years • More than 9,700 people are employed in solar energy in New York, making the state 4th in the nation for solar jobs • 60 GW of solar capacity has been installed nationwide • There are over 240,000 Americans working in solar, more people than are employed in the entire fossil fuel sector for electricity generation • Nearly 2 million solar energy systems are operating in the United States SOLAR JOBS BY SECTOR INSTALLATION 7,182 MANUFACTURING 508 WHOLESALE TRADE AND DISTRIBUTION 1,049 OPERATIONS AND MAINTENANCE 477 OTHER 514 12,582 62,987 66,448 86,202 111,166 112,685 211,469 242,343 U.S. ENERGY JOBS WITHIN THE ELECTRICITY INDUSTRY (2019) Solar All Fossil Fuels Natural Gas Wind Coal Hydro Nuclear Oil Solar provides more jobs than all fossil fuels together
  • 12. How Solar Panels Work Solar Energy Electromagnetic energy transmitted from the sun (solar radiation). The amount that reaches the earth is equal to one billionth of total solar energy generated, or the equivalent of about 420 trillion kilowatt-hours. Solar Resource The amount of solar insolation a site receives, usually measured in kWh/m2/day, which is equivalent to the number of peak sun hours. Solar Power Solar power is the conversion of solar energy into electricity through a phenomenon called the photovoltaic effect. Solar panels convert sunlight into electricity
  • 13. Where Does the Power Go? To the Grid! Electricity generated by Alder Creek Solar will go onto the state’s electrical grid by connecting to the existing National Grid Chases Lake-Porter 230 kilovolt (kV) power line located in Boonville. From the grid, the power generated by Alder Creek Solar could be used locally or sent where it is needed depending on line capacity, local generation, and demand. So who uses the power?
  • 18. The Albedo Effect Increased reflectivity, or albedo, from the snow-covered ground can also increase the efficiency of solar panels. There are even bifacial modules that can allow a panel to generate electricity from both sides to take advantage of this reflected solar radiation. Solar Energy in Wintertime Do solar panels work in the wintertime? Yes, they do! While reduced daylight hours affect how often panels are generating electricity, you might be surprised to learn that sunny, cold conditions actually increase efficiency for solar panels compared to extremely hot climates, which can reduce efficiency. How does snow affect solar panels? Solar panels can continue generating electricity even through a light coating of snow because of a phenomenon called forward-scattering, where the snow reflects photons from sunlight to generate energy. Heavier snowfalls can still block generation, but because panels are often significantly warmer than the ambient temperature and tilted at an angle, snow will usually slide right off. As an added benefit, the snow often takes any accumulated dust and dirt with it, cleaning the panel in the same way that snow cleans your car’s windshield when it melts. snowy ground diffuse light albedo bifacial solar panel
  • 19. What Happens When It’s Cloudy? Fortunately for us, solar radiation still gets through to warm up the Earth’s surface, even when it is cloudy. Have you ever noticed how people can still end up with a sunburn when skiing on a cloudy day? That’s because up to 80% of the sun’s UV rays still pass through the clouds. Though solar panels primarily use visible and infrared light, they can still generate electricity in cloudy weather because there is visible and infrared light that can penetrate the clouds and be captured by panels. Studies have shown that solar panels can produce as much as 25% of their usual output on a cloudy day and even up to 10% of usual output with heavy clouds. ozone layer UVC UVB UVA cloud cover
  • 20. Shading • The output current of the PV module is a function of solar irradiance, so a reduction in solar irradiance as a result of partial or complete shading will affect the performance of the entire module • Every cell in the string has to operate at the current set by the shaded cell • We design array to reduce or eliminate consistent shading events
  • 21. Tracking Systems • Fixed Tilt • Single-Axis Tracker • Two-Axis Tracker
  • 22. Safety Considerations • Grounding Studies o Step and touch potential • TOV Studies • Arch Flash Studies • Ampacity Studies • NFPA 70/NEC NEC Article 705.10 “A permanent plaque or directory denoting the location of all electric power source disconnecting means on or in the premises shall be installed at each service equipment location and at the location(s) of the system disconnect(s) for all electric power production sources capable of being interconnected. The marking shall comply with 110.21(B).”
  • 23. Emergency Response Preparedness • Formal training for all project personnel including first-aid training • Development of emergency response plans with local authorities • Site specific training with local emergency responders before and during operations, including PV-specific emergency response • Ongoing drills with local EMS and fire professionals during operations covering medical, fire, and other emergencies • Article 10 requires specific plans in regards to Public Safety and Emergency Response (Exhibits 15, 18, and associated appendices)
  • 24. Recycling Solar Panels • With no moving parts, solar panels are durable and are expected to function effectively for up to 40 years. • At the end of a solar facility’s useful life (30 years on average), panels can be removed and recycled. • Alder Creek Solar will be required to fully fund a decommissioning plan so local communities will not bear any cost for removal of project assets (Article 10 application, Exhibit 29). Up to 90% of the materials used in panels, much of which is glass, are recyclable and can be remanufactured into new panels. 76% glass 10% plastic 8% aluminum 5% silicon 1% metals The Recycling Process Disassembly of aluminum and glass parts 95% glass reused thermal processing at 500°C 100% metal reused plastic cover evaporates reused as heat source physical separation of cell modules etching away of silicon wafers melting broken wafers 80% modules reused 85% silicon reused The International Renewable Energy Agency projects that the value of recovered materials could exceed $15 billion by 2050 and could be used to remanufacture two billion solar panels.
  • 26. What is Article 10? • Article 10 of the New York State Public Service Law defines a clear process for public engagement in permitting large electric generating facilities. • Applies to electric generating facilities with 25 MW generating capacity or more, including renewable energy projects. • Includes environmental justice and environmental and health requirements. • Ensures broad public involvement opportunities throughout the process. • Makes funds available to local parties and municipalities through an Intervenor Fund so they can make an effective contribution to the proceedings. • Requires the creation of a Public Involvement Program Plan, summarizing project efforts to educate, inform, and involve the public in the permitting process.
  • 28. Where are we now? • Revised Public Involvement Program Plan submitted – 11/22/19 • This document can be found on our website and outlines our plans to engage with area residents and stakeholders throughout the development process. Hard copies are available at the Boonville Town Hall, Forestport Town Hall, Erwin Library and Institute, and the Woodgate Free Library. • Preliminary Scoping Statement (PSS) – Spring 2020 • The PSS is a written document informing the Siting Board, other public agencies, and the community about the project, including a description of the proposed facility, potential environmental and health impacts, proposed studies to evaluate those impacts, proposed mitigation measures and reasonable alternatives to the project. • After the PSS is submitted, intervenor funding becomes available for local communities and stakeholders.
  • 29. What is Intervenor Funding? • Article 10 applicants are required to provide funds to be used to defray certain expenses related to application review and development of stipulations incurred by municipal and local parties as they participate in the Article 10 process. • These funds are distributed twice - once after the Preliminary Scoping Statement (PSS) is submitted and once after the application is submitted. • The process of applying for the first round of intervenor funding for Alder Creek Solar will begin after the PSS is filed. • Amount of funds: The first round of intervenor funding is equal to $350 per megawatt (MW) up to a cap of $200,000
  • 30. What Goes Into an Article 10 Application? List of Article 10 Exhibits Exhibit 1: General Requirements Exhibit 11: Preliminary Design Drawings Exhibit 2: Overview and Public Involvement Exhibit 12: Construction Exhibit 3: Location of Facilities Exhibit 13: Real Property Exhibit 4: Land Use Exhibit 14: Cost of Facilities Exhibit 5: Electric System Effects Exhibit 15: Public Health and Safety Exhibit 6: Wind Power Facilities (Not Applicable) Exhibit 16: Pollution Control Facilities (Not Applicable) Exhibit 7: Natural Gas Power Facilities (Not Applicable) Exhibit 17: Air Emissions (Not Applicable) Exhibit 8: Electric System Production Exhibit 18: Safety and Security Exhibit 9: Alternatives Exhibit 19: Noise and Vibration Exhibit 10: Consistency with Energy Planning Objectives Exhibit 20: Cultural Resources
  • 31. What Goes Into an Article 10 Application? (Cont.) List of Article 10 Exhibits (continued) Exhibit 21: Geology, Seismology, Soils Exhibit 31: Local Laws and Ordinances Exhibit 22: Terrestrial Ecology and Wetlands (Includes field studies and analyses such as wetland and stream delineations, vernal pool surveys, and winter raptor surveys) Exhibit 32: State Laws and Regulations Exhibit 23: Water Resources and Aquatic Ecology Exhibit 33: Other Applications and Filings Exhibit 24: Visual Impacts (Includes the Visual Impact Assessment and Photo Simulations) Exhibit 34: Electric Interconnection Exhibit 25: Impacts on Transportation Exhibit 35: Electric and Magnetic Fields Exhibit 26: Effect on Communications Exhibit 36: Gas Interconnection (Not Applicable) Exhibit 27: Socioeconomic Effects (Includes an analysis of economic effects utilizing the National Renewable Energy Laboratory’s Job and Economic Development (JEDI) solar voltaic model) Exhibit 37: Back-Up Fuel (Not Applicable) Exhibit 28: Environmental Justice Exhibit 38: Water Interconnection (Not Applicable) Exhibit 29: Site Restoration and Decommissioning Exhibit 39: Wastewater Interconnection (Not Applicable) Exhibit 30: Nuclear Facilities (Not Applicable) Exhibit 40: Telecommunications Interconnection Exhibit 41: Applications to Modify or Build Adjacent (Not Applicable)
  • 32. Studies Required for Article 10 • Wetlands, Waters and Streams (Exhibit 22): • Wetland and Stream Delineation • Vernal Pool Surveys • Threatened and Endangered Species (Exhibit 22): • Birds • Winter Raptor Surveys • Wildlife and Habitat (Exhibit 22) • Invasive Species (Exhibit 22) • Cultural Resources (Exhibit 20): • Archaeological Resources • Phase 1A/1B Study • Historic Architecture • Local Laws (Exhibit 31) • Environmental Justice (Exhibit 28)
  • 33. Studies Required for Article 10 (continued) • Noise (Exhibit 19): • Noise Impact Assessment • Visual Effects (Exhibit 24): • Visual Impact Assessment • Viewshed Analysis • Photo-simulations • Shadow Flicker Analysis • Glare Analysis • Land Use Evaluation (Exhibit 4) • Socioeconomic Effects (Exhibit 27) • Geology, Seismology, and Soils (Exhibit 21) • Safety and Security (Exhibit 18) • Transportation (Exhibit 25) • Site Decommissioning/Restoration (Exhibit 29) • Communication Effects (Exhibit 26) • Oils and Gas Infrastructure
  • 34. Public & Community Engagement
  • 35. Public & Community Engagement • Public Meetings, Community Forums, and Open Houses • Town, County, and School District Board Meetings • Community Events • Mailings • In-person meetings and phone conversations • Online through our website (www.aldercreeksolar.com) and Facebook (@AlderCreekSolar) As a community-focused company, we not only want to hear from you, but we will be out in the community making ourselves available to answer questions and gather feedback. Let us know where else we can engage with you and your neighbors!
  • 36. Alder Creek Solar - Local Benefits Local Economic Benefits Some of the key estimates for the Alder Creek Solar project are below. Local Revenue through Host Community Agreements and PILOT Agreements Estimated $400,000 annually with inflation to the local taxing jurisdictions Actual amounts and term dependent upon negotiations with Boonville and Forestport on Town Host Community Agreements and Oneida County, Adirondack Central School District, and the two towns on PILOT Agreement. Jobs During construction: • Between 125 and 200 construction jobs created directly by the project During project operations (25+ years): • 2 direct, long-term, local jobs employed for operations and maintenance of project • Additional local subcontractors for site maintenance, including vegetative management, road repair, plowing, substation/transformer/inverter maintenance, and module cleaning when needed.
  • 37. Project Schedule (subject to change) Outreach Dates Preliminary Scoping Statement Submitted Spring 2020 Project Studies (Environmental & Wildlife, Ambient Noise, Viewshed Analysis, Wetlands, Cultural & Historic Resources, Economic Impacts, Communications, Decommissioning, and other applicable studies) Present – Fall 2020 Public & Community Engagement (Public Meetings, Community Conversations, Town Official Engagement, Ordinance Development, Host Community Agreement and PILOT Agreement Negotiations) Ongoing Stipulations Period Spring 2020 – Fall 2020 Permit Application Late 2020 Initial Permit Review, Permit Deemed Complete Early 2021 Permit Hearings & Siting Board Review 2021 Siting Board Determination (Approval or Rejection of Application) Early 2022 Construction Commences Spring/Summer 2022 Construction Complete Fall 2023 Project Begins Operations Winter 2023
  • 38. Follow Alder Creek Solar at www.aldercreeksolar.com or on Facebook at www.facebook.com/AlderCreekSolar/