SlideShare a Scribd company logo
1 of 22
DV 1x400 kV, 2x400 kV
TRANSMISSIONLINES WORKS
Contract Number:
Client:
Contractor Engineer:
Sub-Contractor:
CLEANING OF LAND SLIDE
ACCES TRACK AT 10
Method of Statement (Specific)
Document Number:
00 23/01/201 8 Approval Arber Dogani
REV DATE ISSUED FOR ISSUED BY HSE CHECKED BY QA/QC TD PM
Contractor
Engineer
□ □ □
DATE BY APPROVED REJECTED NA COMMENTS
Present document is property of the Ow ner and it is prohibited any copy and/or convey of its original copy w ith any means, before the w ritten
confirmation and approvalof the Company's legal representative.
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: 22/01/2018
Revision: 01
Page 2 of 22
REVISION TRACKING PAGE
Revision
Number
Revised
Page
Revision Date Description of Revision Prepared by
00 all 23/01/2018 Prepared and Published A.Dogani
Rev No. 01 02 03 04 05
Date
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 3 of 22
CONTENTS
1 PURPOSE..................................................................................................................................................................................5
2 SCOPE.......................................................................................................................................................................................5
3 DEFINITIONS ...........................................................................................................................................................................6
4 REFERENCES ............................................................................................................................................................................6
5 HEALTH, SAFETY, AND ENVIRONMENT CONSIDERATION.............................................................................................6
5.1 Requirements......................................................................................................................6
5.2 Team Members Trainings.....................................................................................................7
5.3 Tools and Equipment...........................................................................................................7
5.4 Weather Condition ..............................................................................................................8
5.5 Personal Protective Equipment(PPE)....................................................................................8
5.6 Communication...................................................................................................................8
5.7 Working time.......................................................................................................................8
5.8 First Aid and First Aider........................................................................................................8
5.9 Environmental Measures......................................................................................................9
5.10 Visitors or Vendor on site.....................................................................................................9
6 METHODOLOGY .....................................................................................................................................................................9
6.1 Description..........................................................................................................................9
6.2 Clearing and excavation Operations....................................................................................10
7 CONTRACTOR'S ORGANIZATION FOR ACCESS ROAD CONSTRUCTION....................................................................11
8 ATTACHMENT A - LOCATION MAP...................................................................................................................................12
9 ATTACHMENT B – PHOTOS................................................................................................................................................13
PHOTO 1 ..........................................................................................................................................................................................13
10 ATTACHMENT B/2 – PHOTOS ...........................................................................................................................................14
11 ATTACHMENT B/3 – PHOTOS ...........................................................................................................................................15
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 4 of 22
12 ATTACHMENT C - RISK ASSESSMENT SPECIFIC..............................................................................................................16
13 ATTACHMENT D - JOB HAZARD ANALYSIS .....................................................................................................................19
14 ATTACHMENT E – LAST MINUTE RISK ASSESSMENT....................................................................................................21
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 5 of 22
1 PURPOSE
To establish methodology on cleaning of land slide at at 10 required for construction of AT 10 and
towers 8 I, 8 u, 9 u (Appendix A - LOCATION MAP)
2 SCOPE
This procedure establishes description and guidelines for works performed during the removal of the
land slide near tower 9u.
Duration of the works is estimated to be 15 working days starting from receiving confirmation for
starting of the works. However final duration of the works, will be determined by field performance.
Will be used for these work:
Company:
2 Excavators, 2 operators, 2 workers (Wachman’s), 1 Lead Civil Engineer
Contractor:
1 Geologist
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 6 of 22
3 DEFINITIONS
- -Contractor Inginieria y Construccion
PM- Project Manager
DPM- Deputy Project Manager
4 REFERENCES
Health Safety and Environmental (HSE) Plan
 Chapter 6:
Point 6.1 ; Point 6.2 ;
 Chapter 10:
Point 10.1
 Chapter 11: Point 11.1.
 Chapter 12:Point 12,1
 Chapter 13: Points 13.1, 13.2, 13.3, 13.4, 13.5, 13.6, 13.8, 13.10.
Quality Assurance / Quality Control (QA/QC) Plan
5 HEALTH, SAFETY, AND ENVIRONMENT CONSIDERATION
5.1 Requirements
Before the Contractorstart constructionof access roadto towerlocationsthe requirements listedbelow
must be followed and completed.
1. All the crew must be trained for such activity;
2. RiskAssessment(RA)(Appendix C- RISKASSESSMENT) andJobHazardAnalysis(JHA) (Appendix
D - JOB HAZARDANALYSIS) mustbe prepared before any start of activity. JHA must be read and
signed by all the members of the crew before the activity starts;
3. Equipmentmustbe ingoodconditionandall safetydevices mustbe functional andactive during
all the time;
4. Last Minute Risk Assessment will be prepared and signed from HSE Lead and Lead Engineer
every day(No Works will be performed without LMRA)
5. Tools must be in good shape and not damaged or modified;
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 7 of 22
6. Housekeeping and working area must be clean in order to protect the Environment;
7. Communication (Radio);
8. Working time (8Hours).
5.2 Team Members Trainings
Team members must be trained in different disciplines to perform this activity.
 General induction training;
o HS&E Induction
o Environmental Awareness
o Emergency Response Plan Training
o Fire Fighting Training
o First Aid Training
o JHA/Risk Assessment
o HS&E Leadership
o Stop Works
o HS&E Assessments
o Accident/Incident Reporting & Investigation
o Near Miss Reporting
o Cost of Accidents
 Tools and equipment training;
 Watchman Daily Instruction
 PPE training;
 Equipments,
Only this category of workers should be working in Cleaning of Land Slide at AT 10 construction.
5.3 Tools and Equipment
 Tools must be in good condition and free from any damage;
 Only proper tool are allowed to use in this activity;
 Homemade tools are not allowed to use on site;
 Equipment must be in good condition and checked periodically;
 Only authorized operator must use them and to be shore that the equipment to be well
maintained;
 Radio communication
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 8 of 22
 Acoustic High Signal
 Where the equipmentissettle, the areashouldbe barricade byhighvisible safetytape andalso
warning signs must be put in order to inform the public about the work activity.
5.4 Weather Condition
It is not allowed to perform any activity during bad weather condition like;
 storm
 snow
No activity will be performed if equipment are not able to perform safe work because of weather
condition.
5.5 Personal Protective Equipment (PPE)
In order to prevent any injury or accident during the working time, we are forced by the HSE plan and
the AlbanianLaborLow to use the followingpersonal protective equipment during all the time on site.
 hard hat;
 gloves;
 safetyshoes;
 highvisible vest;
 Reflectivesigns.
 Acousticsignalization
All these PPEswill be usedandwearbyeveryone thatwill be partonthe workingsite.Visitorsshall wear
these PPEs (except reflective sign), as well.
5.6 Communication
In orderto have a safe working activity, the communication is a very important issue to be considered.
Workers are not allowed to use or talk on the phone when they are operating or guiding equipment.
Visible and acoustic signs must be used on site.
5.7 Working time
In order to have a safe work condition, road access activity will be performed only during day time. If
proper lighting is provided works can be performed by management decision.
5.8 First Aid and First Aider
Emergency numbers must be place in a visible table from everyone. First aid kit will be put in a place
where everyone may have access.
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 9 of 22
5.9 Environmental Measures
In order to keep a good environment on site, spill prevention must be present on site, garbage and
waste of food will be removed from site and deposited in safe waste area. All the area must be clean
and in good environment condition after work activity.
5.10 Visitors or Vendor on site
Visitors or Vendors are not allowed to enter on site until they have permission, however, visitors and
vendormust have a brief training before they go on site and also they should sign the attendance list.
6 METHODOLOGY
6.1 Description
Cleaning of land slide at access track at 10 will be done with these steps:
 We will beginthe excavationinzone 1, as it is rocky area during excavator work, it will create a
vibrationthatwill affectthe provocation of the surrounding area to see if there is any possible
movement,thisareaisthe safestpartcompact rockerwhere the excavatorwill work and in this
way does not endanger the vehicle and maneuver.
 If the terrain does not show any sign of new displacing, and after the Contractor Geologist
checks and gives OK we will continue with the second phase.
 Afteritwill be continuedwithZone 3 excavation, this area consists of dislocated rock material,
no compact rock,there are soil layers between the rock layers and vegetation and about 60-70
cm of soli above the surface.
Excavationinthiszone will startfromtowerNo.8 inthe directionof landslidebyharassingandrelieving
by 3m created by the land sliding, to see if we will have any possible slide or not.
 If everythinggoeswellandthe Geologisttogetherwiththe Engineeragreesthat the structure is
stable and there is certainty to enter that already cleaned area on both sides then we can
proceed with the cleansing of the rock massive.
 Excavatorsshouldworkwith interchange, only one at the same time during the excavations of
Zone 1 and 3, to avoid any possible incident and to react on time.
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 10 of 22
 For these typesof workwhere the dangerishigh,the escortingteamshave tobe equippedwith
acoustic signalizations and radio to signal the excavator maneuverer to immediately pull back
with the vehicle in case of sliding terrain.
Picture 1: Map of landslide and zones of work
6.2 Clearing and excavation Operations
1. Main contractor shall ensure all required permits are in place prior to the start of clearing and
excavation work operations.
2. Main contractor Geologistshall be presentduringall time toestablishif terrainconditionsallow
to proceed further with the works of clearing and excavations.l
3. The Contractor shall ensure compliance with environmental requirements such as silt fencing,
run-off protection, or dust limitations during clearing and grubbing operation.
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 11 of 22
7 CONTRACTOR'S ORGANIZATION FOR ACCESS ROAD CONSTRUCTION
ProjectManager (ErlirCompany)
Construction Manager (Klevi Kalemi)
Site Engineer (Anil Company)
Excavation Team (Surveyor,
Forman, Operator)
HSE Lead (Arber
Dogani)
Geologist(Contractor)
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 12 of 22
8 ATTACHMENT A - LOCATION MAP
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 13 of 22
9 ATTACHMENT B – PHOTOS
PHOTO1
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 14 of 22
10 ATTACHMENT B/2 – PHOTOS
PHOTO 2
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 15 of 22
11 ATTACHMENT B/3 – PHOTOS
PHOTO 3
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 16 of 22
12 ATTACHMENT C - RISK ASSESSMENT SPECIFIC
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 17 of 22
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 18 of 22
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 19 of 22
13 ATTACHMENT D - JOB HAZARD ANALYSIS
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 20 of 22
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 21 of 22
14 ATTACHMENT E – LAST MINUTE RISK ASSESSMENT
Method of Statement
Removal of land slide at
AT10
ISSUING DATE: __/01/2018
State ofissue: 00
Page 22 of 22

More Related Content

What's hot

HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC Rev 2 -.docx
HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC  Rev 2 -.docxHAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC  Rev 2 -.docx
HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC Rev 2 -.docxDwarika Bhushan Sharma
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statisticsArber Dogani
 
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docx
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docxFULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docx
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docxDwarika Bhushan Sharma
 
HSE Annual Performance
HSE Annual PerformanceHSE Annual Performance
HSE Annual PerformanceArun Kumar
 
Probabilistic Accuracy Bounds @ Papers We Love SF
Probabilistic Accuracy Bounds @ Papers We Love SFProbabilistic Accuracy Bounds @ Papers We Love SF
Probabilistic Accuracy Bounds @ Papers We Love SFAysylu Greenberg
 
Daily EHS Report Format-Rev 00_MPL (3).pptx
Daily EHS Report Format-Rev 00_MPL (3).pptxDaily EHS Report Format-Rev 00_MPL (3).pptx
Daily EHS Report Format-Rev 00_MPL (3).pptxsanjeevkumar2911
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdfBalamuruganD26
 
Heat stress program (management's role)
Heat stress program (management's role)Heat stress program (management's role)
Heat stress program (management's role)Saber Alam
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdfRafiullahKhan88
 
Job Hazard Analysis
Job Hazard AnalysisJob Hazard Analysis
Job Hazard AnalysisDan Junkins
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templatesDwarika Bhushan Sharma
 
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docx
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docxEXCAVATION PERMIT Form # HSEQ - EP Rev 3.docx
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docxDwarika Bhushan Sharma
 
Safety Officer Duties
Safety Officer DutiesSafety Officer Duties
Safety Officer DutiesTaqvi11
 
250361343 manta-to-richmond-simops-risk-matrix-final
250361343 manta-to-richmond-simops-risk-matrix-final250361343 manta-to-richmond-simops-risk-matrix-final
250361343 manta-to-richmond-simops-risk-matrix-finalWindy Martdianzah
 

What's hot (20)

HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC Rev 2 -.docx
HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC  Rev 2 -.docxHAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC  Rev 2 -.docx
HAZARDOUS SUBSTANCE CHECKLIST Form # HSEQ - HSC Rev 2 -.docx
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
 
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docx
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docxFULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docx
FULL BODY HARNESS INSPECTION RECORD Form # HSEQ - FBHIR Rev 2.docx
 
HSE Annual Performance
HSE Annual PerformanceHSE Annual Performance
HSE Annual Performance
 
Height work permit
Height work permitHeight work permit
Height work permit
 
HSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection PlanHSE Fire Prevention & Protection Plan
HSE Fire Prevention & Protection Plan
 
Probabilistic Accuracy Bounds @ Papers We Love SF
Probabilistic Accuracy Bounds @ Papers We Love SFProbabilistic Accuracy Bounds @ Papers We Love SF
Probabilistic Accuracy Bounds @ Papers We Love SF
 
Daily EHS Report Format-Rev 00_MPL (3).pptx
Daily EHS Report Format-Rev 00_MPL (3).pptxDaily EHS Report Format-Rev 00_MPL (3).pptx
Daily EHS Report Format-Rev 00_MPL (3).pptx
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
Sample risk assessment roadhaulage
Sample risk assessment   roadhaulageSample risk assessment   roadhaulage
Sample risk assessment roadhaulage
 
Heat stress program (management's role)
Heat stress program (management's role)Heat stress program (management's role)
Heat stress program (management's role)
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdf
 
Permit to work
Permit to workPermit to work
Permit to work
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
Job Hazard Analysis
Job Hazard AnalysisJob Hazard Analysis
Job Hazard Analysis
 
Internal EHS Audit check sheet
Internal EHS Audit check sheetInternal EHS Audit check sheet
Internal EHS Audit check sheet
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docx
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docxEXCAVATION PERMIT Form # HSEQ - EP Rev 3.docx
EXCAVATION PERMIT Form # HSEQ - EP Rev 3.docx
 
Safety Officer Duties
Safety Officer DutiesSafety Officer Duties
Safety Officer Duties
 
250361343 manta-to-richmond-simops-risk-matrix-final
250361343 manta-to-richmond-simops-risk-matrix-final250361343 manta-to-richmond-simops-risk-matrix-final
250361343 manta-to-richmond-simops-risk-matrix-final
 

Similar to Specific method of statmeents risk assessment -job hazard analysis for land slide

Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...Arber Dogani
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfNajiRaheem2
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...Arber Dogani
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and faAl-Amin Ahmed Nabin
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Iqbal Mohammad
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docAtif767782
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Andrew Louis
 
NESTLE ABAJI EIA PRESENTATION
NESTLE  ABAJI  EIA  PRESENTATIONNESTLE  ABAJI  EIA  PRESENTATION
NESTLE ABAJI EIA PRESENTATIONAdewunmi Okumodi
 
CV_John_Pennington_Recently updated
CV_John_Pennington_Recently updatedCV_John_Pennington_Recently updated
CV_John_Pennington_Recently updatedJohn Pennington
 
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...minte3
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015HaGun Gunawan
 
Appendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFAppendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFssuserfce39b
 

Similar to Specific method of statmeents risk assessment -job hazard analysis for land slide (20)

Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
Telehandler
TelehandlerTelehandler
Telehandler
 
MS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdfMS.CPS3 Carport to be designed and installed Rev0.pdf
MS.CPS3 Carport to be designed and installed Rev0.pdf
 
Emp
EmpEmp
Emp
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
 
NESTLE ABAJI EIA PRESENTATION
NESTLE  ABAJI  EIA  PRESENTATIONNESTLE  ABAJI  EIA  PRESENTATION
NESTLE ABAJI EIA PRESENTATION
 
CV_John_Pennington_Recently updated
CV_John_Pennington_Recently updatedCV_John_Pennington_Recently updated
CV_John_Pennington_Recently updated
 
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Appendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFAppendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDF
 

More from Arber Dogani

Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)Arber Dogani
 
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...Arber Dogani
 
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016Arber Dogani
 
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...Arber Dogani
 
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...Arber Dogani
 
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03Arber Dogani
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.doganiArber Dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...Arber Dogani
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber doganiArber Dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)Arber Dogani
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...Arber Dogani
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...Arber Dogani
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber doganiArber Dogani
 
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber doganiPlani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber doganiArber Dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesArber Dogani
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiArber Dogani
 
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018Arber Dogani
 
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimNew hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimArber Dogani
 
Basic harness awareness training albanian.
Basic harness awareness training albanian.Basic harness awareness training albanian.
Basic harness awareness training albanian.Arber Dogani
 
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Arber Dogani
 

More from Arber Dogani (20)

Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)
 
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
 
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
 
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
 
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
 
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
 
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber doganiPlani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punes
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.dogani
 
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
 
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimNew hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
 
Basic harness awareness training albanian.
Basic harness awareness training albanian.Basic harness awareness training albanian.
Basic harness awareness training albanian.
 
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

Specific method of statmeents risk assessment -job hazard analysis for land slide

  • 1. DV 1x400 kV, 2x400 kV TRANSMISSIONLINES WORKS Contract Number: Client: Contractor Engineer: Sub-Contractor: CLEANING OF LAND SLIDE ACCES TRACK AT 10 Method of Statement (Specific) Document Number: 00 23/01/201 8 Approval Arber Dogani REV DATE ISSUED FOR ISSUED BY HSE CHECKED BY QA/QC TD PM Contractor Engineer □ □ □ DATE BY APPROVED REJECTED NA COMMENTS Present document is property of the Ow ner and it is prohibited any copy and/or convey of its original copy w ith any means, before the w ritten confirmation and approvalof the Company's legal representative.
  • 2. Method of Statement Removal of land slide at AT10 ISSUING DATE: 22/01/2018 Revision: 01 Page 2 of 22 REVISION TRACKING PAGE Revision Number Revised Page Revision Date Description of Revision Prepared by 00 all 23/01/2018 Prepared and Published A.Dogani Rev No. 01 02 03 04 05 Date
  • 3. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 3 of 22 CONTENTS 1 PURPOSE..................................................................................................................................................................................5 2 SCOPE.......................................................................................................................................................................................5 3 DEFINITIONS ...........................................................................................................................................................................6 4 REFERENCES ............................................................................................................................................................................6 5 HEALTH, SAFETY, AND ENVIRONMENT CONSIDERATION.............................................................................................6 5.1 Requirements......................................................................................................................6 5.2 Team Members Trainings.....................................................................................................7 5.3 Tools and Equipment...........................................................................................................7 5.4 Weather Condition ..............................................................................................................8 5.5 Personal Protective Equipment(PPE)....................................................................................8 5.6 Communication...................................................................................................................8 5.7 Working time.......................................................................................................................8 5.8 First Aid and First Aider........................................................................................................8 5.9 Environmental Measures......................................................................................................9 5.10 Visitors or Vendor on site.....................................................................................................9 6 METHODOLOGY .....................................................................................................................................................................9 6.1 Description..........................................................................................................................9 6.2 Clearing and excavation Operations....................................................................................10 7 CONTRACTOR'S ORGANIZATION FOR ACCESS ROAD CONSTRUCTION....................................................................11 8 ATTACHMENT A - LOCATION MAP...................................................................................................................................12 9 ATTACHMENT B – PHOTOS................................................................................................................................................13 PHOTO 1 ..........................................................................................................................................................................................13 10 ATTACHMENT B/2 – PHOTOS ...........................................................................................................................................14 11 ATTACHMENT B/3 – PHOTOS ...........................................................................................................................................15
  • 4. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 4 of 22 12 ATTACHMENT C - RISK ASSESSMENT SPECIFIC..............................................................................................................16 13 ATTACHMENT D - JOB HAZARD ANALYSIS .....................................................................................................................19 14 ATTACHMENT E – LAST MINUTE RISK ASSESSMENT....................................................................................................21
  • 5. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 5 of 22 1 PURPOSE To establish methodology on cleaning of land slide at at 10 required for construction of AT 10 and towers 8 I, 8 u, 9 u (Appendix A - LOCATION MAP) 2 SCOPE This procedure establishes description and guidelines for works performed during the removal of the land slide near tower 9u. Duration of the works is estimated to be 15 working days starting from receiving confirmation for starting of the works. However final duration of the works, will be determined by field performance. Will be used for these work: Company: 2 Excavators, 2 operators, 2 workers (Wachman’s), 1 Lead Civil Engineer Contractor: 1 Geologist
  • 6. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 6 of 22 3 DEFINITIONS - -Contractor Inginieria y Construccion PM- Project Manager DPM- Deputy Project Manager 4 REFERENCES Health Safety and Environmental (HSE) Plan  Chapter 6: Point 6.1 ; Point 6.2 ;  Chapter 10: Point 10.1  Chapter 11: Point 11.1.  Chapter 12:Point 12,1  Chapter 13: Points 13.1, 13.2, 13.3, 13.4, 13.5, 13.6, 13.8, 13.10. Quality Assurance / Quality Control (QA/QC) Plan 5 HEALTH, SAFETY, AND ENVIRONMENT CONSIDERATION 5.1 Requirements Before the Contractorstart constructionof access roadto towerlocationsthe requirements listedbelow must be followed and completed. 1. All the crew must be trained for such activity; 2. RiskAssessment(RA)(Appendix C- RISKASSESSMENT) andJobHazardAnalysis(JHA) (Appendix D - JOB HAZARDANALYSIS) mustbe prepared before any start of activity. JHA must be read and signed by all the members of the crew before the activity starts; 3. Equipmentmustbe ingoodconditionandall safetydevices mustbe functional andactive during all the time; 4. Last Minute Risk Assessment will be prepared and signed from HSE Lead and Lead Engineer every day(No Works will be performed without LMRA) 5. Tools must be in good shape and not damaged or modified;
  • 7. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 7 of 22 6. Housekeeping and working area must be clean in order to protect the Environment; 7. Communication (Radio); 8. Working time (8Hours). 5.2 Team Members Trainings Team members must be trained in different disciplines to perform this activity.  General induction training; o HS&E Induction o Environmental Awareness o Emergency Response Plan Training o Fire Fighting Training o First Aid Training o JHA/Risk Assessment o HS&E Leadership o Stop Works o HS&E Assessments o Accident/Incident Reporting & Investigation o Near Miss Reporting o Cost of Accidents  Tools and equipment training;  Watchman Daily Instruction  PPE training;  Equipments, Only this category of workers should be working in Cleaning of Land Slide at AT 10 construction. 5.3 Tools and Equipment  Tools must be in good condition and free from any damage;  Only proper tool are allowed to use in this activity;  Homemade tools are not allowed to use on site;  Equipment must be in good condition and checked periodically;  Only authorized operator must use them and to be shore that the equipment to be well maintained;  Radio communication
  • 8. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 8 of 22  Acoustic High Signal  Where the equipmentissettle, the areashouldbe barricade byhighvisible safetytape andalso warning signs must be put in order to inform the public about the work activity. 5.4 Weather Condition It is not allowed to perform any activity during bad weather condition like;  storm  snow No activity will be performed if equipment are not able to perform safe work because of weather condition. 5.5 Personal Protective Equipment (PPE) In order to prevent any injury or accident during the working time, we are forced by the HSE plan and the AlbanianLaborLow to use the followingpersonal protective equipment during all the time on site.  hard hat;  gloves;  safetyshoes;  highvisible vest;  Reflectivesigns.  Acousticsignalization All these PPEswill be usedandwearbyeveryone thatwill be partonthe workingsite.Visitorsshall wear these PPEs (except reflective sign), as well. 5.6 Communication In orderto have a safe working activity, the communication is a very important issue to be considered. Workers are not allowed to use or talk on the phone when they are operating or guiding equipment. Visible and acoustic signs must be used on site. 5.7 Working time In order to have a safe work condition, road access activity will be performed only during day time. If proper lighting is provided works can be performed by management decision. 5.8 First Aid and First Aider Emergency numbers must be place in a visible table from everyone. First aid kit will be put in a place where everyone may have access.
  • 9. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 9 of 22 5.9 Environmental Measures In order to keep a good environment on site, spill prevention must be present on site, garbage and waste of food will be removed from site and deposited in safe waste area. All the area must be clean and in good environment condition after work activity. 5.10 Visitors or Vendor on site Visitors or Vendors are not allowed to enter on site until they have permission, however, visitors and vendormust have a brief training before they go on site and also they should sign the attendance list. 6 METHODOLOGY 6.1 Description Cleaning of land slide at access track at 10 will be done with these steps:  We will beginthe excavationinzone 1, as it is rocky area during excavator work, it will create a vibrationthatwill affectthe provocation of the surrounding area to see if there is any possible movement,thisareaisthe safestpartcompact rockerwhere the excavatorwill work and in this way does not endanger the vehicle and maneuver.  If the terrain does not show any sign of new displacing, and after the Contractor Geologist checks and gives OK we will continue with the second phase.  Afteritwill be continuedwithZone 3 excavation, this area consists of dislocated rock material, no compact rock,there are soil layers between the rock layers and vegetation and about 60-70 cm of soli above the surface. Excavationinthiszone will startfromtowerNo.8 inthe directionof landslidebyharassingandrelieving by 3m created by the land sliding, to see if we will have any possible slide or not.  If everythinggoeswellandthe Geologisttogetherwiththe Engineeragreesthat the structure is stable and there is certainty to enter that already cleaned area on both sides then we can proceed with the cleansing of the rock massive.  Excavatorsshouldworkwith interchange, only one at the same time during the excavations of Zone 1 and 3, to avoid any possible incident and to react on time.
  • 10. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 10 of 22  For these typesof workwhere the dangerishigh,the escortingteamshave tobe equippedwith acoustic signalizations and radio to signal the excavator maneuverer to immediately pull back with the vehicle in case of sliding terrain. Picture 1: Map of landslide and zones of work 6.2 Clearing and excavation Operations 1. Main contractor shall ensure all required permits are in place prior to the start of clearing and excavation work operations. 2. Main contractor Geologistshall be presentduringall time toestablishif terrainconditionsallow to proceed further with the works of clearing and excavations.l 3. The Contractor shall ensure compliance with environmental requirements such as silt fencing, run-off protection, or dust limitations during clearing and grubbing operation.
  • 11. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 11 of 22 7 CONTRACTOR'S ORGANIZATION FOR ACCESS ROAD CONSTRUCTION ProjectManager (ErlirCompany) Construction Manager (Klevi Kalemi) Site Engineer (Anil Company) Excavation Team (Surveyor, Forman, Operator) HSE Lead (Arber Dogani) Geologist(Contractor)
  • 12. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 12 of 22 8 ATTACHMENT A - LOCATION MAP
  • 13. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 13 of 22 9 ATTACHMENT B – PHOTOS PHOTO1
  • 14. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 14 of 22 10 ATTACHMENT B/2 – PHOTOS PHOTO 2
  • 15. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 15 of 22 11 ATTACHMENT B/3 – PHOTOS PHOTO 3
  • 16. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 16 of 22 12 ATTACHMENT C - RISK ASSESSMENT SPECIFIC
  • 17. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 17 of 22
  • 18. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 18 of 22
  • 19. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 19 of 22 13 ATTACHMENT D - JOB HAZARD ANALYSIS
  • 20. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 20 of 22
  • 21. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 21 of 22 14 ATTACHMENT E – LAST MINUTE RISK ASSESSMENT
  • 22. Method of Statement Removal of land slide at AT10 ISSUING DATE: __/01/2018 State ofissue: 00 Page 22 of 22