SlideShare a Scribd company logo
1 of 2
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management
Rev. Date: Rev. Date:
Revision: 0 Revision: 0
Page 1 of 2 HSEQ -Rev-01(Aug-2018)
No Specific Task Step Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1 EmergencyProcedure
 Emergency
Response;
 Uncontrolled emergency
responses;
5 5 25
i. Each ATC projectshall create a specific EmergencyResponse ManagementPlan
following requirements and Codes ofPractice contained below; Low
2
Access requirement for
EmergencyVehicles
 Police;
 Civil Defense;
 Ambulance;
(Including as per 2017
Fire Life Safety COP
Requirements)
 Access required by
emergencyvehicles
during incident;
 Emergencyvehicles not able to
access site in an emergency;
 Unable to attend to incidentdue to
blocked roads;
 Unable to reach incidentwith
equipment;
 Inadequate width of roads;
 Time delay in rescue,treatmentof
injured and fighting fire;
5 5
25
HIGH
ii. Access for use of Civil Defence apparatus shall be designated and provided atthe start of
the projectand maintained until completion;
iii. All ATC projectsites shall be designed to be accessible byCivil Defence apparatus by
means ofroadways having an all-weather driving service of not less than 6.1m of
unobstructed width;
iv. The roads shall have the ability to withstand the live loads offire apparatus of80 tons of
distributed load and have a minimum 4.5m ofboth vertical clearance and access gate
width and max. 10% grade;
v. Fire access shall not planned to be through basements or underpasses ofthe building
under construction;
vi. Dead end fire access roads in excess of45m in length shall be provided with approved U
turns (A minimum of 12m as per FLSCOP);
vii. A suitable location atthe site such as meeting room or office shall be designated as an
emergencycommand postand provided with plans,emergencyinformation,keys,
communications and equipment, etc.;
viii. The designated person (s) in charge of emergencyprocedure actions (Senior ATC site
management) shall respond to the designated location whenever fire occurs;
ix. Where access to or within a structure or an area is unduly difficultbecause ofsecured
openings or where immediate access is necessaryfor life-saving or firefighting purposes,
ATC shall ensure the Civil Defence personnel has access to a key box installed in an
accessible location;
x. The required width of access roadways shall notbe obstructed in any manner,including
obstruction by parked vehicles,storage of material and assemblypoints;
xi. Signs or other appropriate notices,or both, prohibiting obstruction shall be installed and
shall be maintained,worded ‘Parking Reserved for Civil Defence Fire Lane’;
xii. The access roadwayshall be extended to within 46m of all portions of the exterior walls of
the first story of any building under construction;
xiii. Where an access roadwaycannotbe adequatelyprovided, an approved fire protection
system or systems shall be provided and approved by the Civil Defence;
xiv. Where a bridge is required to be used as access,itshall be constructed and maintained
using design live loading sufficientto carry the imposed loads ofthe fire apparatus in
accordance with Fire Service Vehicle and Personnel Accessibility;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the w ork place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substitutedfor
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered aw ay w ith
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be w orn to safe guard against
hazards?Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Overall project Emergencyresponse specific to the size, location and complexity of
the area, including the requirements ofthe UAE Fire Life Safety Code of Practice
2017 Chapters 2 and 12. Use with RA 17 – Initial Site Set up;
Relevant Applicable MAS:
 00241 Fire Fighting Equipment;
 00236 Housekeeping;
Additional Training required: NOC’s Required for task:
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management
Rev. Date: Rev. Date:
Revision: 0 Revision: 0
Page 2 of 2 HSEQ -Rev-01(Aug-2018)
No Specific Task Step Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
3
Reverse Parking of
private vehicles office
areas
 Emergencysite
evacuation;
 Vehicle collision;
 Vehicle and pedestrian collision;
 Ineffective site evacuation, staff at
risk due to slow exit;
 Exits blocked;
4 3
12
HIGH
i. All vehicles will reverse park in designated areas,this will be communicated atinduction
and areas clearly signed;
ii. Security will monitor car parking areas for compliance;
Low
4
Project Vehicle Parking  Car Parking on
Construction Sites;
 Site access blocked;
 Emergencyvehicles not able to
access site in an emergency;
 Unable to attend to incident;
 Time delay in rescue,treatmentof
injured and fighting fire;
 Unauthorized parking;
4 4
16
HIGH
i. ATC will consider the exact location of vehicle parking on site set up, considering access
and egress,exit routes,restricted parking,potential drop zones etc.;
ii. All vehicles shall be parked a minimum of 20 feet (6.1m) from new buildings under
construction with the following exceptions;
iii. Vehicles that are parked temporarilyfor loading/unloading or other construction related
operations.However,such vehicles shall notbe left unattended;
iv. Private ATC staff vehicles may be parked in parking garages of projectsites if the
automatic fire sprinkler system is in service and vertical openings are protected;
5
Project EmergencySite
Exits  Emergencysite
egress;
 Ineffective site evacuation, staff
at risk due to slow exit;
 Blocked exits – egress
prevention;
 Incidentdue to poor exit lighting;
5 5
25
HIGH
i. All projects under construction shall have at least two unobstructed exits.All exits shall
be identified in the ProjectFire Plan;
ii. Where stairs and exit routes of a building are under construction,exterior temporary
steel stairs and exits shall be provided which lead directly to ground floor to the safety of
outside the building;
iii. In multi-storyconstruction,each level above the first story shall be provided with at least
two usable exit stairs after the floor decking is installed.The stairways shall be
continuous and discharge to grade level;
iv. Stairways serving more than two floor levels shall be enclosed (with openings
adequatelyprotected) after exterior walls/windows are in place;
v. Exit stairs shall be lighted and maintained clear ofdebris and construction materials at
all times except when one of the required exit stairs is under construction (i.e.installation
of gypsum board,painting,flooring etc.), but not more than two continuous floors ;
vi. All exit stairs shall be provided with stair identification signs to include the floor level, stair
designation,and exit path direction as required to provide for safe egress;
vii. Nighttime construction work shall notbe performed withoutadequate lighting in exits,
exit stairs and escape routes to safety outside the building;
6
Project Emergency
Communication
 Emergency
communication with
emergencyservices;
 Time delay in rescue,treatment
of injured and fighting fire;
4 4
16
HIGH
i. On commencing the project, ATC Senior Project Managementshall assess and decide
the exact means ofcommunication on the project,including additional site phones,two-
way radios etc.based on the location,complexity and size of the project;
ii. The agreed communication system shall be made up ofstrategicallyplaced equipment
and properly defined responsibilities.The emergencyresponse plan posted in a
conspicuous place on the projectmustidentify the designated equipmentand the people
to operate it;
iii. Emergencyphone numbers and the site address/location shall be posted beside all site
phones.On assessment,the location of any emergencyphones shall be clearlymarked;
iv. Instructions shall be issued for the immediate notification ofthe Civil Defence in case of
a fire emergency;
v. A system of communication shall be established with ATC Head Office to be used in the
event of an incident,including lines and means ofcontact. This will be identified in the
HSE EmergencyResponse Plan and sign posted in prominentareas;
Low
7
Project Assembly
points
 Emergencysite
egress;
 Ineffective head count – workers
left inside buildings;
4 4
16
HIGH
i. Designated exterior assemblypoints shall be established for all construction personnel to
relocate to upon evacuation. The assemblypoints shall also be identified in the Project
Fire Plan.
Low

More Related Content

What's hot

11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...Dwarika Bhushan Sharma
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templatesDwarika Bhushan Sharma
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at heightsankarnagar
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templatesDwarika Bhushan Sharma
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdfBalamuruganD26
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpointJomish John
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work trainingKarnav Rana
 

What's hot (20)

11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
Hira
HiraHira
Hira
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at height
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
 
4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates4 cofferdams (temporary works) risk assessment templates
4 cofferdams (temporary works) risk assessment templates
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpoint
 
Permit to Work Training
Permit to Work TrainingPermit to Work Training
Permit to Work Training
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 

Similar to 3 emergency management risk assessment templates

3 Emergency Management Risk Assessment Templates.docx
3 Emergency Management Risk Assessment Templates.docx3 Emergency Management Risk Assessment Templates.docx
3 Emergency Management Risk Assessment Templates.docxDwarika Bhushan Sharma
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docxDwarika Bhushan Sharma
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docxDwarika Bhushan Sharma
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...Dwarika Bhushan Sharma
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docxDwarika Bhushan Sharma
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docxDwarika Bhushan Sharma
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templatesDwarika Bhushan Sharma
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templatesDwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...Dwarika Bhushan Sharma
 

Similar to 3 emergency management risk assessment templates (20)

3 Emergency Management Risk Assessment Templates.docx
3 Emergency Management Risk Assessment Templates.docx3 Emergency Management Risk Assessment Templates.docx
3 Emergency Management Risk Assessment Templates.docx
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
28 Edge protection to open edges, shafts and risers Risk Assessment Templates...
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdfDwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdfDwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdfDwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdfDwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docxDwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxDwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxDwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxDwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxDwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxDwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxDwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxDwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docxDwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docDwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docDwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxDwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 

Recently uploaded (20)

ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 

3 emergency management risk assessment templates

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management Rev. Date: Rev. Date: Revision: 0 Revision: 0 Page 1 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 1 EmergencyProcedure  Emergency Response;  Uncontrolled emergency responses; 5 5 25 i. Each ATC projectshall create a specific EmergencyResponse ManagementPlan following requirements and Codes ofPractice contained below; Low 2 Access requirement for EmergencyVehicles  Police;  Civil Defense;  Ambulance; (Including as per 2017 Fire Life Safety COP Requirements)  Access required by emergencyvehicles during incident;  Emergencyvehicles not able to access site in an emergency;  Unable to attend to incidentdue to blocked roads;  Unable to reach incidentwith equipment;  Inadequate width of roads;  Time delay in rescue,treatmentof injured and fighting fire; 5 5 25 HIGH ii. Access for use of Civil Defence apparatus shall be designated and provided atthe start of the projectand maintained until completion; iii. All ATC projectsites shall be designed to be accessible byCivil Defence apparatus by means ofroadways having an all-weather driving service of not less than 6.1m of unobstructed width; iv. The roads shall have the ability to withstand the live loads offire apparatus of80 tons of distributed load and have a minimum 4.5m ofboth vertical clearance and access gate width and max. 10% grade; v. Fire access shall not planned to be through basements or underpasses ofthe building under construction; vi. Dead end fire access roads in excess of45m in length shall be provided with approved U turns (A minimum of 12m as per FLSCOP); vii. A suitable location atthe site such as meeting room or office shall be designated as an emergencycommand postand provided with plans,emergencyinformation,keys, communications and equipment, etc.; viii. The designated person (s) in charge of emergencyprocedure actions (Senior ATC site management) shall respond to the designated location whenever fire occurs; ix. Where access to or within a structure or an area is unduly difficultbecause ofsecured openings or where immediate access is necessaryfor life-saving or firefighting purposes, ATC shall ensure the Civil Defence personnel has access to a key box installed in an accessible location; x. The required width of access roadways shall notbe obstructed in any manner,including obstruction by parked vehicles,storage of material and assemblypoints; xi. Signs or other appropriate notices,or both, prohibiting obstruction shall be installed and shall be maintained,worded ‘Parking Reserved for Civil Defence Fire Lane’; xii. The access roadwayshall be extended to within 46m of all portions of the exterior walls of the first story of any building under construction; xiii. Where an access roadwaycannotbe adequatelyprovided, an approved fire protection system or systems shall be provided and approved by the Civil Defence; xiv. Where a bridge is required to be used as access,itshall be constructed and maintained using design live loading sufficientto carry the imposed loads ofthe fire apparatus in accordance with Fire Service Vehicle and Personnel Accessibility; RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the w ork place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substitutedfor a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered aw ay w ith guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be w orn to safe guard against hazards?Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1 Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Overall project Emergencyresponse specific to the size, location and complexity of the area, including the requirements ofthe UAE Fire Life Safety Code of Practice 2017 Chapters 2 and 12. Use with RA 17 – Initial Site Set up; Relevant Applicable MAS:  00241 Fire Fighting Equipment;  00236 Housekeeping; Additional Training required: NOC’s Required for task:
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Emergency Management Rev. Date: Rev. Date: Revision: 0 Revision: 0 Page 2 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 3 Reverse Parking of private vehicles office areas  Emergencysite evacuation;  Vehicle collision;  Vehicle and pedestrian collision;  Ineffective site evacuation, staff at risk due to slow exit;  Exits blocked; 4 3 12 HIGH i. All vehicles will reverse park in designated areas,this will be communicated atinduction and areas clearly signed; ii. Security will monitor car parking areas for compliance; Low 4 Project Vehicle Parking  Car Parking on Construction Sites;  Site access blocked;  Emergencyvehicles not able to access site in an emergency;  Unable to attend to incident;  Time delay in rescue,treatmentof injured and fighting fire;  Unauthorized parking; 4 4 16 HIGH i. ATC will consider the exact location of vehicle parking on site set up, considering access and egress,exit routes,restricted parking,potential drop zones etc.; ii. All vehicles shall be parked a minimum of 20 feet (6.1m) from new buildings under construction with the following exceptions; iii. Vehicles that are parked temporarilyfor loading/unloading or other construction related operations.However,such vehicles shall notbe left unattended; iv. Private ATC staff vehicles may be parked in parking garages of projectsites if the automatic fire sprinkler system is in service and vertical openings are protected; 5 Project EmergencySite Exits  Emergencysite egress;  Ineffective site evacuation, staff at risk due to slow exit;  Blocked exits – egress prevention;  Incidentdue to poor exit lighting; 5 5 25 HIGH i. All projects under construction shall have at least two unobstructed exits.All exits shall be identified in the ProjectFire Plan; ii. Where stairs and exit routes of a building are under construction,exterior temporary steel stairs and exits shall be provided which lead directly to ground floor to the safety of outside the building; iii. In multi-storyconstruction,each level above the first story shall be provided with at least two usable exit stairs after the floor decking is installed.The stairways shall be continuous and discharge to grade level; iv. Stairways serving more than two floor levels shall be enclosed (with openings adequatelyprotected) after exterior walls/windows are in place; v. Exit stairs shall be lighted and maintained clear ofdebris and construction materials at all times except when one of the required exit stairs is under construction (i.e.installation of gypsum board,painting,flooring etc.), but not more than two continuous floors ; vi. All exit stairs shall be provided with stair identification signs to include the floor level, stair designation,and exit path direction as required to provide for safe egress; vii. Nighttime construction work shall notbe performed withoutadequate lighting in exits, exit stairs and escape routes to safety outside the building; 6 Project Emergency Communication  Emergency communication with emergencyservices;  Time delay in rescue,treatment of injured and fighting fire; 4 4 16 HIGH i. On commencing the project, ATC Senior Project Managementshall assess and decide the exact means ofcommunication on the project,including additional site phones,two- way radios etc.based on the location,complexity and size of the project; ii. The agreed communication system shall be made up ofstrategicallyplaced equipment and properly defined responsibilities.The emergencyresponse plan posted in a conspicuous place on the projectmustidentify the designated equipmentand the people to operate it; iii. Emergencyphone numbers and the site address/location shall be posted beside all site phones.On assessment,the location of any emergencyphones shall be clearlymarked; iv. Instructions shall be issued for the immediate notification ofthe Civil Defence in case of a fire emergency; v. A system of communication shall be established with ATC Head Office to be used in the event of an incident,including lines and means ofcontact. This will be identified in the HSE EmergencyResponse Plan and sign posted in prominentareas; Low 7 Project Assembly points  Emergencysite egress;  Ineffective head count – workers left inside buildings; 4 4 16 HIGH i. Designated exterior assemblypoints shall be established for all construction personnel to relocate to upon evacuation. The assemblypoints shall also be identified in the Project Fire Plan. Low