SlideShare a Scribd company logo
1 of 19
Download to read offline
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 1 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Crane operator must be
trained, certified and
legally appointed.
Untrained and uncertified
crane operators can lead to
incidents causing injuries and
damage to property.
C 8
All crane operators must be trained by an
Accredited Institution and certified.
Untrained crane operators are
used.
Site Manager, Safety Officer
& Supervisory staff are to
enforce that Mobile cranes
are only operated by trained
and certified personnel.
Legal exposure due to Legal
appointments not being in
place.
C 18
Operators of Mobile Lifting Equipment
must be appointed as per the General
Machinery regulations.
Operators are not legally
appointed thus leading to Legal
non-compliance by the Company.
Site Manager & Safety
officer to ensure that all the
required legal appointments
are in place and filed as per
Company SHE Procedure
Manual
Rigger to be trained,
certified, legally appointed
and identified.
Untrained and uncertified
Riggers carrying out lifts that
require a qualified Rigger as
per the Company SHE
Procedure Manual can lead to
incidents causing injuries and
damage to property.
C 8
All Riggers must be trained by an
Accredited Institution and certified.
All Certified Riggers are to wear black
hardhats for identification purposes.
Unqualified Riggers are used to
carry out big lifts or complicated
lifts.
Site Manager & Supervisors
are to ensure that all lifts
that require a qualified
Rigger as per the Company
SHE Procedure Manual are
so carried out.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 2 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Rigger to be trained,
certified, legally appointed
and identified. (Conti.)
Legal exposure due to Legal
appointments not being in
place.
C 18
Qualified Riggers must be appointed as
per the General Machinery regulations.
Operators are not legally
appointed thus leading to Legal
non-compliance by the Company.
Site Manager & Safety
officer to ensure that all the
required legal appointments
are in place and filed as per
Company SHE Procedure
Manual
The correct overhead
crane for the mass of the
load is to be used.
Overloading crane can lead to
equipment failure.
C 13
The SWL displayed on the overhead crane
should be adhered to at all times.
The SWL of Cranes are ignored. Site Manager, Rigger and
Supervisor are to ensure
that the SWL of overhead
cranes are adhered.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 3 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
The correct overhead
crane for the mass of the
load is to be used. (Conti.)
Uncertified crane is used
which could lead to equipment
failure and subsequent
injuries and/or damage to
property.
B 9
All Lifting Equipment is to be tested and
certified by an Authorised Inspection
Authority once a year or when repaired or
modified. This includes all integral parts of
the said Lifting equipment e.g. hooks,
crane rope etc.
Each crane is to have is own Logbook as
set out in the Companies SHE Procedure
Manual.
Cranes are not tested and certified
as per the Legal requirement.
The Company Plant
Manager, Site Manager are
to ensure that these
requirements are met prior
to any Lifting Equipment
being put into service.
Pre-use check to be done
on overhead crane before
use.
Faulty lifting machinery can
lead to injuries and damage.
B 9
A pre-use check is to be done on the
crane by the operator and any faults must
be reported to the Site Manager.
The pre-use checklist is to be kept with the
operator for the period they are valid and
then to be handed to the Safety Officer for
the issue of a new checklist.
Daily pre-use checklist for cranes
are not done or not done correctly
Site Manager & Supervisor
is to ensure that the
operators meet the
requirements.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 4 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Pre-use check to be done
on overhead crane before
use. (Conti.)
Operator falling from elevated
area while doing pre-use
inspection.
C 13
Operator is to make use of the safe
access provided to overhead cranes. He is
also to make use of a safety harness so
that he can attach himself to secure
structure while on the elevated area.
He must ensure that he does not attach
himself to the any moving part of the
overhead crane or the crane rail.
Safe access is not used or the
operator fails to attach himself or
attaches himself incorrectly.
Site Manager and
supervisors are to ensure
that operators are trained in
the use of safety harness’s
and are attached correctly at
all times.
See Risk Assessment TH BREA 008 – Working On Elevated Areas for lists associated Tasks, Hazards, Risk Matrix, Control Measures
and Responsibilities.
Obtain lifting equipment
from the stores.
Incorrect lifting tackle is
obtained which could lead to
equipment failure and
subsequent injuries and
damages.
B 9
Only qualified Riggers or trained semi-
skilled riggers/banksman are to book out
rigging tackle.
Incompetent staff are permitted to
book out rigging equipment from
the stores.
Site Manager, Supervisor
and store man are to ensure
that this is complied with.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 5 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Obtain lifting equipment
from the stores. (Conti.)
Damaged equipment can lead
to equipment failure.
B 14
All lifting equipment is to be inspected and
certified annually by an Authorised
Inspection Authority.
All lifting equipment is to be numbered and
registered and is to be inspected monthly
by the Appointed Lifting Tackle Inspector
and colour coded as per the monthly
colour codes.
All user of lifting equipment are to do a pre
use inspection of the equipment prior to
use.
Lifting tackle is not inspected,
certified.
Site manager, Safety Officer
and Appointed Lifting Tackle
Inspector are to ensure that
this complied with.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 6 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Slinging of load and attach
guide ropes.
No qualified Rigger is used for
all major lifts or the load
presents a degree of difficulty.
B 9
A qualified rigger is to be used for all lifts
as specified in the Company’s SHE
Procedure Manual.
In the case of small lifts a trained semi
skilled rigger/banksman can be used.
The crane operator and rigger/semi-skilled
rigger can be the same person provided
that he has been trained to do both tasks
as stated earlier in this Risk Assessment.
Unqualified employees are
allowed to carry out major or
difficult lifts.
Site Manager and
Supervisors to ensure that
this does not occur.
The area is not barricaded off
and/or no symbolic signs used
B 5
When ever any lifting operation is taking
place the area is to be barricaded with
black& yellow barrication tape and no
entry signs put in place.
Rigger or semi-skilled rigger is to ensure
no-one enters the area and none of his
rigging team goes under the load.
No barrication is used or is
ignored by others.
Site Manager, Safety
Officer, Rigger and
supervisors to ensure that
this is in place.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 7 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Slinging of load and attach
guide ropes. (Conti.)
Incorrect slinging
methodology can lead to
equipment failure and/or load
failing.
C 13
Only qualified Riggers or trained semi-
skilled riggers/banksman are to sling
loads.
Incompetent staff carryout slinging
operations.
Site Manager, Riggers and
supervisors to ensure that
control measures are
adhered to.
No safe access is given to
staff to gain access to the top
of load to carry out rigging &
slinging operations
C 18
A ladder is to be used to obtain access to
the top of load.
Staff climb onto load without
proper and safe access or fail to
use the safe access provided.
Site Manager, Rigger are to
ensure that safe access is
available and used.
Hands caught in lifting tackle.
B 14
The use of PPE must be enforced at all
times.
Staff fail to use their PPE. Site Manager, Safety Officer
& Supervisory staff are to
enforce the use of PPE by
firstly educating staff and
then disciplinary action if
necessary.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 8 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Lift load to required
elevation.
Unbalanced load could lead to
lifting tackle failure and
uncontrolled lift.
B 9
The correct lifting methodology is to be
used by competently trained rigging crew.
The rigger or semi-skilled rigger is to
check all rigging and is to lift the load just
off the ground to check for the balance of
the load.
The load is not balanced correctly. Rigger, Semi-skilled riggers
and supervisors to ensure
that loads are balanced
before the lift takes place.
People walking under the load
B 5
The area is to be barricaded off and no
entry symbolic signs are to be used.
The Rigger or semi-skilled rigger is to use
a whistle to warn every one in the vicinity
that the load is being lifted in addition to
the overhead crane sirens.
No barrication or symbolic signs
are used or ignored.
The people in the area are not
warned of the intended lift.
Rigger, semi-skilled rigger
and supervisors are to
ensure that these measures
are in place.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 9 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Move load to position. The load can swing and
collide with existing structures.
B 14
Guide ropes are to be used during lifting
operations.
In the case of piping or loads that due to
their weight, shape and/or surface area
are prone to swing more than one guide
rope is to be used.
Guide ropes are to be used under the
direct instruction of the rigger or semi-
skilled rigger.
No guide ropes or insufficient
guide ropes are used.
Guide ropes not used correctly.
Rigger, semi-skilled rigger
and supervisors are to
ensure the use of guide
ropes.
Guide ropes can come into
contact with existing moving
machinery in the area and
lead to damage.
B 9
Ensure that the guide rope is long enough
so that it does not go into any moving
machinery and is under control at all times
or ensure that the load is lifted in such a
manner that the guide rope cannot come
into contact with any moving machinery.
No precautions are taken
regarding guide ropes.
Rigger/semi-skilled rigger,
supervisor and crane
operators are to ensure that
precautions are taken.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 10 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Move load to position.
(Conti.)
Where the crane operator and
Rigger/semi-skilled rigger are
not the same person,
instruction given to the crane
operator by different people
could lead to confusion and
have disastrous
consequences.
Poor communication between
Rigger and crane operator
could lead to confusion,
injuries and damage to
property.
B 5
Where the crane operator and
Rigger/semi-skilled rigger are not the
same person, only the Rigger/semi-skilled
rigger in charge of the lift is to give
instructions to the crane operator.
The Rigger or semi-skilled rigger and the
crane operator are to ensure that there is
proper communication between them at all
times. If visible or electronic
communication is interrupted, the crane
operator is to stop operations until
communication is re-established.
Everyone on the scene gives
instructions to the crane operator
or there is no proper
communication between
Rigger/semi-skilled rigger and
crane operator.
Rigger, semi-skilled rigger
and supervisors are to
ensure that these measures
are in place at all times.
Crane operator slipping or
tripping over loose objects in
his path.
B 14
The crane operator is to check the path
that he intends to walk while moving the
load to ensure that he cannot slip or trip
and fall.
Operator does not plan his path or
fails to inspect it.
Rigger/semi-skilled rigger (if
present) and the supervisor
is to ensure that operator
carries such inspection.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 11 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Lower the load very slowly
into position.
No safe access is given to
employees to gain access to
elevated areas where the load
is to be positioned. C 8
Employees are to gain safe access to
elevated areas by means of existing safe
access, scaffolding or boatswain chair.
The employees are then to use safety
harness either attached to approved
lifelines or a secure structure.
Staff climb onto elevated areas
without proper and safe access or
fail to use the safe access
provided.
Site Manager, Rigger are to
ensure that safe access is
available and used.
Employees awaiting the load
are not aware of the position
of the load.
D 17
Rigger or semi-skilled rigger is to ensure
that the employees awaiting the load are
aware of its position before lowering it into
position.
These employees are to use the guide
ropes to control the load.
The load is lowered into position
without awaiting employees being
aware of its position.
Rigger, semi-skilled rigger
and supervisors are to
ensure that these measures
are in place at all times.
Damaged caused to overhead
crane mechanism due to
pulling load to the sides from
the vertical angle.
B 9
No rigging will be done with overhead
cranes that will cause the ropes of the
crane to be pulled away from the vertical
angle of the rope. The overhead crane
ropes must be vertical at all times.
Loads are pulled to the sides while
suspended.
Site Manager, Rigger/semi-
skilled rigger, supervisor and
operators are to ensure that
this does not occur.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 12 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Lower the load very slowly
into position. (Conti.)
Hand or body parts being
injured due to employees
coming between the load and
its final resting place.
C 13
Employees must ensure that they do not
hold onto the load or climb onto it until it is
in position. Guide ropes are to be used.
If load is to be manhandled employees
must ensure that they have no body part
that can be jammed between the load and
the surrounding existing structures.
Employees fail to take precautions
against this hazard.
Rigger, semi-skilled rigger
and supervisors are to
ensure that employees are
aware of the hazards.
Hand injuries caused by sharp
edges of load.
A 10
The use of PPE must be enforced at all
times.
Staff fail to use their PPE. Site Manager, Safety Officer
& Supervisory staff are to
enforce the use of PPE by
firstly educating staff and
then disciplinary action if
necessary.
When in position, lifting
tackle slackened and
removed from load.
No safe access is given to
staff to gain access to the top
of load to remove lifting tackle
C 8
Employees are to gain safe access to top
of by means of existing safe access,
ladder or boatswain chair.
Staff climb onto load without
proper and safe access or fail to
use the safe access provided.
Site Manager, Rigger are to
ensure that safe access is
available and used.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 13 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
When in position, lifting
tackle slackened and
removed from load.
(Conti.)
Hands caught in lifting tackle.
B 14
The use of PPE must be enforced at all
times.
Staff fails to use their PPE. Site Manager, Safety Officer
& Supervisory staff are to
enforce the use of PPE by
firstly educating staff and
then disciplinary action if
necessary.
Lifting tackle gets hooked
when the crane repositions
boom.
C 13
Employees at the load must ensure that
lifting tackle is properly disengaged and
will not catch onto any item in the
immediate facility before notifying the
Rigger/semi-skilled rigger that the lifting
tackle can be lifted.
Employees are to ensure that lifting tackle
does not get damaged due to working in
haste.
No precautions are taken to
prevent lifting tackle getting
hooked or damaged.
Rigger, semi-skilled rigger
and supervisors to ensure
that all precautions are
taken.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 14 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD
CRANES
PROBABILITY
Common
Occurrences
Has
Happened
Could
Occur
Not likely
To occur
DATE:
Risk & Environmental
Assessment Register no: TH BREA 03 REV 03 A B C D
Risk Assessment Team:
6(1)/2.6.1 Contractors Signature: Multipart Fatality
SEVERITY
R500 000 & More 1 2 4 7
Fatal R200 000 TO R500 000 3 5 8 12
1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17
2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21
3. Minor Injury R10 000 & Less 15 19 22 24
4. High Risk
5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk
6. Low Risk
7.
For Quality Risk Refer to Work Instruction for the
Various Departments.
Task
Potential Hazard
and
Loss Exposure
Probability
Risk
Safety
Rating
Control Measures in place or to be
implemented
Short Comings
Persons responsible for
Implementation and
Supervision.
Return lifting tackle to
store when all lifting tasks
are completed.
Tackle left lying around can
lead to tripping hazard or
equipment can be damaged. A 15
Lifting tackle must be kept clean and
stored on suitable hooks and shelves off
the ground in a clean and dry area.
Lifting tackle is left lying around
and not stored correctly.
Site Manager, Safety
Officer, Riggers,
Supervisors and store man
are to ensure that this is
done.
Dragging of lifting tackle can
lead to damage to equipment.
A 15
Employees are to ensure that lifting tackle
is transported or carried is such a way that
it will not damage the equipment.
No care is taken to safe guard
lifting tackle.
Rigger, semi-skilled rigger
and supervisors to ensure
that all precautions are
taken.
Lock out the overhead
crane.
Unauthorised use of the crane
by incompetent employees.
B 9
If the overhead crane is not going to be
used any further the crane must be locked
out at the power source to prevent
unauthorised use thereof.
Unauthorised use of overhead
crane due to it not being locked
out.
Site Manager, Safety Officer
and Supervisor to ensure
that a lock out system is
implemented.
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 15 of 19
RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES
Risk & Environmental Assessment Register no: TH BREA 03 REV 03 SIGNIFICANCE EVALUATION
DATE: 11/10/05 6(1)/2.6.1 Contractors Signature: Legal Compliance Yes (1) No (20)
Extent Local (1) Site (2) Region (3) National (4)
Assessment Team: Duration Short Term (1) Medium term (2) Long Term (3) Permanent (4)
1. E. Silveiro Safety Co-ordinator/Officer: Intensity Low/Minor (1) Medium (2) Major (3) High (4)
2. R. Olwagen Probability Improbable (1) Probable (2) Highly probable (3) Definitely (4)
3. Stakeholders
Expectation
No Influence (1) Neutral (2) Negative Influence (3) Legal Implication
(4)
4. Accepted on behalf of Client:
5.
6. Significance
Value
Low 5-9 Medium 10 - 14 High 15 - 20
7. Accepted on behalf of Client:
8.
9.
Activity Environmental Aspect Environmental Impact L E D I P S SV
Control Measures to mitigate
Impact Persons
responsible
Use of the overhead
crane.
Energy consumption -
Electricity
Socio- economic effects
1 1 1 1 1 1 6
Only the amount electricity required to
complete the job is to be used.
Unnecessary use of the overhead
crane must be monitored. Equipment
and/or material that can be moved but
other effective means are to be used.
Supervisor is to
ensure that he
monitors and controls
this.
Reg. No. 2001002519/07
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 16 of 19
C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022
The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is
issued by TH’s HSE Head Office.
RISK &
ENVIRONMENTAL
ASSESSMENT FOR:
LIFTING OPERATIONS WITH OVERHEAD CRANES
METHOD STATEMENT
1. Crane operator must be trained, certified and legally appointed.
2. Rigger to be trained, certified, legally appointed and identified.
3. The correct overhead crane for the mass of the load is to be used.
4. Pre-use check to be done on overhead crane before use.
5. Obtain lifting equipment from the stores.
6. Slinging of load and attach guide ropes.
7. Lift load to required elevation.
8. Move load to position.
9. Lower the load very slowly into position.
10. When in position, lifting tackle slackened and removed from load.
11. Return lifting tackle to store when all lifting tasks are completed.
HAZARDS IDENTIFICATION
1.
Untrained and uncertified crane operators can lead to incidents causing injuries and
damage to property.
2. Legal exposure due to Legal appointments not being in place.
3.
Untrained and uncertified Riggers carrying out lifts that require a qualified Rigger as per the
Company SHE Procedure Manual can lead to incidents causing injuries and damage to
property.
4. Legal exposure due to Legal appointments not being in place.
5. Overloading crane can lead to equipment failure.
6.
Uncertified crane is used which could lead to equipment failure and subsequent injuries
and/or damage to property.
7. Faulty lifting machinery can lead to injuries and damage.
8. Operator falling from elevated area while doing pre-use inspection.
9.
See Risk Assessment TH BREA 008 – Working in Elevated Areas for lists associated
Hazards.
10.
Incorrect lifting tackle is obtained which could lead to equipment failure and subsequent
injuries and damages.
11. Damaged equipment can lead to equipment failure.
12. No qualified Rigger is used for all major lifts or the load presents a degree of difficulty.
13. The area is not barricaded off and/or no symbolic signs used
14. Incorrect slinging methodology can lead to equipment failure and/or load failing.
15.
No safe access is given to staff to gain access to the top of load to carry out rigging &
slinging operations
16. Hands caught in lifting tackle.
17. Unbalanced load could lead to lifting tackle failure and uncontrolled lift.
18. People walking under the load
19. The load can swing and collide with existing structures.
20.
Guide ropes can come into contact with existing moving machinery in the area and lead to
damage.
21. Where the crane operator and Rigger/semi-skilled rigger are not the same person,
Reg. No. 2001002519/07
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 17 of 19
C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022
The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is
issued by TH’s HSE Head Office.
instruction given to the crane operator by different people could lead to confusion and have
disastrous consequences.
22.
Poor communication between Rigger and crane operator could lead to confusion, injuries
and damage to property.
23. Crane operator slipping or tripping over loose objects in his path.
24.
No safe access is given to employees to gain access to elevated areas where the load is to
be positioned.
25. Employees awaiting the load are not aware of the position of the load.
26.
Damaged caused to overhead crane mechanism due to pulling load to the sides from the
vertical angle.
27.
Hand or body parts being injured due to employees coming between the load and its final
resting place.
28. Hand injuries caused by sharp edges of load.
29. No safe access is given to staff to gain access to the top of load to remove lifting tackle
30. Hands caught in lifting tackle.
31. Lifting tackle gets hooked when the crane repositions boom.
32. Tackle left lying around can lead to tripping hazard or equipment can be damaged.
33. Dragging of lifting tackle can lead to damage to equipment.
ENVIRONMENTAL ASPECTS
1. Energy consumption - Electricity
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 18 of 19
C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022
The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is
issued by TH’s HSE Head Office.
Proof of communication and training of Risk & Environmental Assessment and
Method statement for:
LIFTING OPERATIONS WITH OVERHEAD CRANES
SUPERVISOR:
PEOPLE PRESENT: DATE:
NAME SURNAME SIGNATURE
Reg. No. 2001002519/07
DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form
REVISION NO: 02 Page 19 of 19
C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022
The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is
issued by TH’s HSE Head Office.
Proof of communication and training of Risk & Environmental Assessment and
Method statement for:
LIFTING OPERATIONS WITH OVERHEAD CRANES
SUPERVISOR:
PEOPLE PRESENT: DATE:
NAME SURNAME SIGNATURE
Reg. No. 2001002519/07

More Related Content

What's hot

FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
Dwarika Bhushan Sharma
 
HIRA TRAINING PPT.pptx
HIRA  TRAINING PPT.pptxHIRA  TRAINING PPT.pptx
HIRA TRAINING PPT.pptx
MoolRaj3
 

What's hot (20)

Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates
 
Risk Assessment (Master).pdf
Risk Assessment (Master).pdfRisk Assessment (Master).pdf
Risk Assessment (Master).pdf
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
Working at heights training powerpoint
Working at heights training powerpointWorking at heights training powerpoint
Working at heights training powerpoint
 
Work At Height
Work At HeightWork At Height
Work At Height
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
 
Near miss report
Near miss reportNear miss report
Near miss report
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
HIRA TRAINING PPT.pptx
HIRA  TRAINING PPT.pptxHIRA  TRAINING PPT.pptx
HIRA TRAINING PPT.pptx
 

Similar to Risk Assessment Example.pdf

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
MohammedAliQazi
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
17 1 Drilling Operations Risk assessment
17 1 Drilling Operations Risk assessment17 1 Drilling Operations Risk assessment
17 1 Drilling Operations Risk assessment
FESTUS RICHARD SIAME
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Similar to Risk Assessment Example.pdf (20)

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
MC-SC-HSE-HIRA-000 Installation of Sanitary waste and venting piping system.docx
MC-SC-HSE-HIRA-000 Installation of Sanitary waste and venting piping system.docxMC-SC-HSE-HIRA-000 Installation of Sanitary waste and venting piping system.docx
MC-SC-HSE-HIRA-000 Installation of Sanitary waste and venting piping system.docx
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
17 1 Drilling Operations Risk assessment
17 1 Drilling Operations Risk assessment17 1 Drilling Operations Risk assessment
17 1 Drilling Operations Risk assessment
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 

Recently uploaded

Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 

Recently uploaded (20)

Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableNanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Nanded Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
BADDI 💋 Call Girl 9827461493 Call Girls in Escort service book now
BADDI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowBADDI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
BADDI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book nowKOTA 💋 Call Girl 9827461493 Call Girls in  Escort service book now
KOTA 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowSRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
SRI GANGANAGAR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
Bangalore Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Avai...
 
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableChandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Chandrapur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Solan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Solan Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableSolan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Solan Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTSJHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
JHARSUGUDA CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JHARSUGUDA ESCORTS
 

Risk Assessment Example.pdf

  • 1. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 1 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Crane operator must be trained, certified and legally appointed. Untrained and uncertified crane operators can lead to incidents causing injuries and damage to property. C 8 All crane operators must be trained by an Accredited Institution and certified. Untrained crane operators are used. Site Manager, Safety Officer & Supervisory staff are to enforce that Mobile cranes are only operated by trained and certified personnel. Legal exposure due to Legal appointments not being in place. C 18 Operators of Mobile Lifting Equipment must be appointed as per the General Machinery regulations. Operators are not legally appointed thus leading to Legal non-compliance by the Company. Site Manager & Safety officer to ensure that all the required legal appointments are in place and filed as per Company SHE Procedure Manual Rigger to be trained, certified, legally appointed and identified. Untrained and uncertified Riggers carrying out lifts that require a qualified Rigger as per the Company SHE Procedure Manual can lead to incidents causing injuries and damage to property. C 8 All Riggers must be trained by an Accredited Institution and certified. All Certified Riggers are to wear black hardhats for identification purposes. Unqualified Riggers are used to carry out big lifts or complicated lifts. Site Manager & Supervisors are to ensure that all lifts that require a qualified Rigger as per the Company SHE Procedure Manual are so carried out.
  • 2. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 2 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Rigger to be trained, certified, legally appointed and identified. (Conti.) Legal exposure due to Legal appointments not being in place. C 18 Qualified Riggers must be appointed as per the General Machinery regulations. Operators are not legally appointed thus leading to Legal non-compliance by the Company. Site Manager & Safety officer to ensure that all the required legal appointments are in place and filed as per Company SHE Procedure Manual The correct overhead crane for the mass of the load is to be used. Overloading crane can lead to equipment failure. C 13 The SWL displayed on the overhead crane should be adhered to at all times. The SWL of Cranes are ignored. Site Manager, Rigger and Supervisor are to ensure that the SWL of overhead cranes are adhered.
  • 3. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 3 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. The correct overhead crane for the mass of the load is to be used. (Conti.) Uncertified crane is used which could lead to equipment failure and subsequent injuries and/or damage to property. B 9 All Lifting Equipment is to be tested and certified by an Authorised Inspection Authority once a year or when repaired or modified. This includes all integral parts of the said Lifting equipment e.g. hooks, crane rope etc. Each crane is to have is own Logbook as set out in the Companies SHE Procedure Manual. Cranes are not tested and certified as per the Legal requirement. The Company Plant Manager, Site Manager are to ensure that these requirements are met prior to any Lifting Equipment being put into service. Pre-use check to be done on overhead crane before use. Faulty lifting machinery can lead to injuries and damage. B 9 A pre-use check is to be done on the crane by the operator and any faults must be reported to the Site Manager. The pre-use checklist is to be kept with the operator for the period they are valid and then to be handed to the Safety Officer for the issue of a new checklist. Daily pre-use checklist for cranes are not done or not done correctly Site Manager & Supervisor is to ensure that the operators meet the requirements.
  • 4. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 4 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Pre-use check to be done on overhead crane before use. (Conti.) Operator falling from elevated area while doing pre-use inspection. C 13 Operator is to make use of the safe access provided to overhead cranes. He is also to make use of a safety harness so that he can attach himself to secure structure while on the elevated area. He must ensure that he does not attach himself to the any moving part of the overhead crane or the crane rail. Safe access is not used or the operator fails to attach himself or attaches himself incorrectly. Site Manager and supervisors are to ensure that operators are trained in the use of safety harness’s and are attached correctly at all times. See Risk Assessment TH BREA 008 – Working On Elevated Areas for lists associated Tasks, Hazards, Risk Matrix, Control Measures and Responsibilities. Obtain lifting equipment from the stores. Incorrect lifting tackle is obtained which could lead to equipment failure and subsequent injuries and damages. B 9 Only qualified Riggers or trained semi- skilled riggers/banksman are to book out rigging tackle. Incompetent staff are permitted to book out rigging equipment from the stores. Site Manager, Supervisor and store man are to ensure that this is complied with.
  • 5. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 5 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Obtain lifting equipment from the stores. (Conti.) Damaged equipment can lead to equipment failure. B 14 All lifting equipment is to be inspected and certified annually by an Authorised Inspection Authority. All lifting equipment is to be numbered and registered and is to be inspected monthly by the Appointed Lifting Tackle Inspector and colour coded as per the monthly colour codes. All user of lifting equipment are to do a pre use inspection of the equipment prior to use. Lifting tackle is not inspected, certified. Site manager, Safety Officer and Appointed Lifting Tackle Inspector are to ensure that this complied with.
  • 6. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 6 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Slinging of load and attach guide ropes. No qualified Rigger is used for all major lifts or the load presents a degree of difficulty. B 9 A qualified rigger is to be used for all lifts as specified in the Company’s SHE Procedure Manual. In the case of small lifts a trained semi skilled rigger/banksman can be used. The crane operator and rigger/semi-skilled rigger can be the same person provided that he has been trained to do both tasks as stated earlier in this Risk Assessment. Unqualified employees are allowed to carry out major or difficult lifts. Site Manager and Supervisors to ensure that this does not occur. The area is not barricaded off and/or no symbolic signs used B 5 When ever any lifting operation is taking place the area is to be barricaded with black& yellow barrication tape and no entry signs put in place. Rigger or semi-skilled rigger is to ensure no-one enters the area and none of his rigging team goes under the load. No barrication is used or is ignored by others. Site Manager, Safety Officer, Rigger and supervisors to ensure that this is in place.
  • 7. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 7 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Slinging of load and attach guide ropes. (Conti.) Incorrect slinging methodology can lead to equipment failure and/or load failing. C 13 Only qualified Riggers or trained semi- skilled riggers/banksman are to sling loads. Incompetent staff carryout slinging operations. Site Manager, Riggers and supervisors to ensure that control measures are adhered to. No safe access is given to staff to gain access to the top of load to carry out rigging & slinging operations C 18 A ladder is to be used to obtain access to the top of load. Staff climb onto load without proper and safe access or fail to use the safe access provided. Site Manager, Rigger are to ensure that safe access is available and used. Hands caught in lifting tackle. B 14 The use of PPE must be enforced at all times. Staff fail to use their PPE. Site Manager, Safety Officer & Supervisory staff are to enforce the use of PPE by firstly educating staff and then disciplinary action if necessary.
  • 8. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 8 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Lift load to required elevation. Unbalanced load could lead to lifting tackle failure and uncontrolled lift. B 9 The correct lifting methodology is to be used by competently trained rigging crew. The rigger or semi-skilled rigger is to check all rigging and is to lift the load just off the ground to check for the balance of the load. The load is not balanced correctly. Rigger, Semi-skilled riggers and supervisors to ensure that loads are balanced before the lift takes place. People walking under the load B 5 The area is to be barricaded off and no entry symbolic signs are to be used. The Rigger or semi-skilled rigger is to use a whistle to warn every one in the vicinity that the load is being lifted in addition to the overhead crane sirens. No barrication or symbolic signs are used or ignored. The people in the area are not warned of the intended lift. Rigger, semi-skilled rigger and supervisors are to ensure that these measures are in place.
  • 9. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 9 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Move load to position. The load can swing and collide with existing structures. B 14 Guide ropes are to be used during lifting operations. In the case of piping or loads that due to their weight, shape and/or surface area are prone to swing more than one guide rope is to be used. Guide ropes are to be used under the direct instruction of the rigger or semi- skilled rigger. No guide ropes or insufficient guide ropes are used. Guide ropes not used correctly. Rigger, semi-skilled rigger and supervisors are to ensure the use of guide ropes. Guide ropes can come into contact with existing moving machinery in the area and lead to damage. B 9 Ensure that the guide rope is long enough so that it does not go into any moving machinery and is under control at all times or ensure that the load is lifted in such a manner that the guide rope cannot come into contact with any moving machinery. No precautions are taken regarding guide ropes. Rigger/semi-skilled rigger, supervisor and crane operators are to ensure that precautions are taken.
  • 10. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 10 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Move load to position. (Conti.) Where the crane operator and Rigger/semi-skilled rigger are not the same person, instruction given to the crane operator by different people could lead to confusion and have disastrous consequences. Poor communication between Rigger and crane operator could lead to confusion, injuries and damage to property. B 5 Where the crane operator and Rigger/semi-skilled rigger are not the same person, only the Rigger/semi-skilled rigger in charge of the lift is to give instructions to the crane operator. The Rigger or semi-skilled rigger and the crane operator are to ensure that there is proper communication between them at all times. If visible or electronic communication is interrupted, the crane operator is to stop operations until communication is re-established. Everyone on the scene gives instructions to the crane operator or there is no proper communication between Rigger/semi-skilled rigger and crane operator. Rigger, semi-skilled rigger and supervisors are to ensure that these measures are in place at all times. Crane operator slipping or tripping over loose objects in his path. B 14 The crane operator is to check the path that he intends to walk while moving the load to ensure that he cannot slip or trip and fall. Operator does not plan his path or fails to inspect it. Rigger/semi-skilled rigger (if present) and the supervisor is to ensure that operator carries such inspection.
  • 11. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 11 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Lower the load very slowly into position. No safe access is given to employees to gain access to elevated areas where the load is to be positioned. C 8 Employees are to gain safe access to elevated areas by means of existing safe access, scaffolding or boatswain chair. The employees are then to use safety harness either attached to approved lifelines or a secure structure. Staff climb onto elevated areas without proper and safe access or fail to use the safe access provided. Site Manager, Rigger are to ensure that safe access is available and used. Employees awaiting the load are not aware of the position of the load. D 17 Rigger or semi-skilled rigger is to ensure that the employees awaiting the load are aware of its position before lowering it into position. These employees are to use the guide ropes to control the load. The load is lowered into position without awaiting employees being aware of its position. Rigger, semi-skilled rigger and supervisors are to ensure that these measures are in place at all times. Damaged caused to overhead crane mechanism due to pulling load to the sides from the vertical angle. B 9 No rigging will be done with overhead cranes that will cause the ropes of the crane to be pulled away from the vertical angle of the rope. The overhead crane ropes must be vertical at all times. Loads are pulled to the sides while suspended. Site Manager, Rigger/semi- skilled rigger, supervisor and operators are to ensure that this does not occur.
  • 12. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 12 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Lower the load very slowly into position. (Conti.) Hand or body parts being injured due to employees coming between the load and its final resting place. C 13 Employees must ensure that they do not hold onto the load or climb onto it until it is in position. Guide ropes are to be used. If load is to be manhandled employees must ensure that they have no body part that can be jammed between the load and the surrounding existing structures. Employees fail to take precautions against this hazard. Rigger, semi-skilled rigger and supervisors are to ensure that employees are aware of the hazards. Hand injuries caused by sharp edges of load. A 10 The use of PPE must be enforced at all times. Staff fail to use their PPE. Site Manager, Safety Officer & Supervisory staff are to enforce the use of PPE by firstly educating staff and then disciplinary action if necessary. When in position, lifting tackle slackened and removed from load. No safe access is given to staff to gain access to the top of load to remove lifting tackle C 8 Employees are to gain safe access to top of by means of existing safe access, ladder or boatswain chair. Staff climb onto load without proper and safe access or fail to use the safe access provided. Site Manager, Rigger are to ensure that safe access is available and used.
  • 13. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 13 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. When in position, lifting tackle slackened and removed from load. (Conti.) Hands caught in lifting tackle. B 14 The use of PPE must be enforced at all times. Staff fails to use their PPE. Site Manager, Safety Officer & Supervisory staff are to enforce the use of PPE by firstly educating staff and then disciplinary action if necessary. Lifting tackle gets hooked when the crane repositions boom. C 13 Employees at the load must ensure that lifting tackle is properly disengaged and will not catch onto any item in the immediate facility before notifying the Rigger/semi-skilled rigger that the lifting tackle can be lifted. Employees are to ensure that lifting tackle does not get damaged due to working in haste. No precautions are taken to prevent lifting tackle getting hooked or damaged. Rigger, semi-skilled rigger and supervisors to ensure that all precautions are taken.
  • 14. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 14 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES PROBABILITY Common Occurrences Has Happened Could Occur Not likely To occur DATE: Risk & Environmental Assessment Register no: TH BREA 03 REV 03 A B C D Risk Assessment Team: 6(1)/2.6.1 Contractors Signature: Multipart Fatality SEVERITY R500 000 & More 1 2 4 7 Fatal R200 000 TO R500 000 3 5 8 12 1. E. Silveiro Serious injury R50 000 TO R200 000 6 9 13 17 2. R. Olwagen Safety Co-ordinator/Officer: Lost Time Injury R10 000 TO R50 000 10 14 18 21 3. Minor Injury R10 000 & Less 15 19 22 24 4. High Risk 5. Accepted on behalf of Client: Accepted on behalf of Client: Medium Risk 6. Low Risk 7. For Quality Risk Refer to Work Instruction for the Various Departments. Task Potential Hazard and Loss Exposure Probability Risk Safety Rating Control Measures in place or to be implemented Short Comings Persons responsible for Implementation and Supervision. Return lifting tackle to store when all lifting tasks are completed. Tackle left lying around can lead to tripping hazard or equipment can be damaged. A 15 Lifting tackle must be kept clean and stored on suitable hooks and shelves off the ground in a clean and dry area. Lifting tackle is left lying around and not stored correctly. Site Manager, Safety Officer, Riggers, Supervisors and store man are to ensure that this is done. Dragging of lifting tackle can lead to damage to equipment. A 15 Employees are to ensure that lifting tackle is transported or carried is such a way that it will not damage the equipment. No care is taken to safe guard lifting tackle. Rigger, semi-skilled rigger and supervisors to ensure that all precautions are taken. Lock out the overhead crane. Unauthorised use of the crane by incompetent employees. B 9 If the overhead crane is not going to be used any further the crane must be locked out at the power source to prevent unauthorised use thereof. Unauthorised use of overhead crane due to it not being locked out. Site Manager, Safety Officer and Supervisor to ensure that a lock out system is implemented.
  • 15. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 15 of 19 RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES Risk & Environmental Assessment Register no: TH BREA 03 REV 03 SIGNIFICANCE EVALUATION DATE: 11/10/05 6(1)/2.6.1 Contractors Signature: Legal Compliance Yes (1) No (20) Extent Local (1) Site (2) Region (3) National (4) Assessment Team: Duration Short Term (1) Medium term (2) Long Term (3) Permanent (4) 1. E. Silveiro Safety Co-ordinator/Officer: Intensity Low/Minor (1) Medium (2) Major (3) High (4) 2. R. Olwagen Probability Improbable (1) Probable (2) Highly probable (3) Definitely (4) 3. Stakeholders Expectation No Influence (1) Neutral (2) Negative Influence (3) Legal Implication (4) 4. Accepted on behalf of Client: 5. 6. Significance Value Low 5-9 Medium 10 - 14 High 15 - 20 7. Accepted on behalf of Client: 8. 9. Activity Environmental Aspect Environmental Impact L E D I P S SV Control Measures to mitigate Impact Persons responsible Use of the overhead crane. Energy consumption - Electricity Socio- economic effects 1 1 1 1 1 1 6 Only the amount electricity required to complete the job is to be used. Unnecessary use of the overhead crane must be monitored. Equipment and/or material that can be moved but other effective means are to be used. Supervisor is to ensure that he monitors and controls this. Reg. No. 2001002519/07
  • 16. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 16 of 19 C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022 The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is issued by TH’s HSE Head Office. RISK & ENVIRONMENTAL ASSESSMENT FOR: LIFTING OPERATIONS WITH OVERHEAD CRANES METHOD STATEMENT 1. Crane operator must be trained, certified and legally appointed. 2. Rigger to be trained, certified, legally appointed and identified. 3. The correct overhead crane for the mass of the load is to be used. 4. Pre-use check to be done on overhead crane before use. 5. Obtain lifting equipment from the stores. 6. Slinging of load and attach guide ropes. 7. Lift load to required elevation. 8. Move load to position. 9. Lower the load very slowly into position. 10. When in position, lifting tackle slackened and removed from load. 11. Return lifting tackle to store when all lifting tasks are completed. HAZARDS IDENTIFICATION 1. Untrained and uncertified crane operators can lead to incidents causing injuries and damage to property. 2. Legal exposure due to Legal appointments not being in place. 3. Untrained and uncertified Riggers carrying out lifts that require a qualified Rigger as per the Company SHE Procedure Manual can lead to incidents causing injuries and damage to property. 4. Legal exposure due to Legal appointments not being in place. 5. Overloading crane can lead to equipment failure. 6. Uncertified crane is used which could lead to equipment failure and subsequent injuries and/or damage to property. 7. Faulty lifting machinery can lead to injuries and damage. 8. Operator falling from elevated area while doing pre-use inspection. 9. See Risk Assessment TH BREA 008 – Working in Elevated Areas for lists associated Hazards. 10. Incorrect lifting tackle is obtained which could lead to equipment failure and subsequent injuries and damages. 11. Damaged equipment can lead to equipment failure. 12. No qualified Rigger is used for all major lifts or the load presents a degree of difficulty. 13. The area is not barricaded off and/or no symbolic signs used 14. Incorrect slinging methodology can lead to equipment failure and/or load failing. 15. No safe access is given to staff to gain access to the top of load to carry out rigging & slinging operations 16. Hands caught in lifting tackle. 17. Unbalanced load could lead to lifting tackle failure and uncontrolled lift. 18. People walking under the load 19. The load can swing and collide with existing structures. 20. Guide ropes can come into contact with existing moving machinery in the area and lead to damage. 21. Where the crane operator and Rigger/semi-skilled rigger are not the same person, Reg. No. 2001002519/07
  • 17. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 17 of 19 C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022 The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is issued by TH’s HSE Head Office. instruction given to the crane operator by different people could lead to confusion and have disastrous consequences. 22. Poor communication between Rigger and crane operator could lead to confusion, injuries and damage to property. 23. Crane operator slipping or tripping over loose objects in his path. 24. No safe access is given to employees to gain access to elevated areas where the load is to be positioned. 25. Employees awaiting the load are not aware of the position of the load. 26. Damaged caused to overhead crane mechanism due to pulling load to the sides from the vertical angle. 27. Hand or body parts being injured due to employees coming between the load and its final resting place. 28. Hand injuries caused by sharp edges of load. 29. No safe access is given to staff to gain access to the top of load to remove lifting tackle 30. Hands caught in lifting tackle. 31. Lifting tackle gets hooked when the crane repositions boom. 32. Tackle left lying around can lead to tripping hazard or equipment can be damaged. 33. Dragging of lifting tackle can lead to damage to equipment. ENVIRONMENTAL ASPECTS 1. Energy consumption - Electricity
  • 18. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 18 of 19 C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022 The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is issued by TH’s HSE Head Office. Proof of communication and training of Risk & Environmental Assessment and Method statement for: LIFTING OPERATIONS WITH OVERHEAD CRANES SUPERVISOR: PEOPLE PRESENT: DATE: NAME SURNAME SIGNATURE Reg. No. 2001002519/07
  • 19. DOCUMENT NO: HSED 18 TITLE: Risk & Environmental Assessment Form REVISION NO: 02 Page 19 of 19 C:Documents and SettingsEmidioMy DocumentsTH5.0Baseline Risk AssessmentsBREA 003 - Lifting Operations with Overhead Cranes2.doc Printed on: 14/01/2022 The validity of the format of this document will be 12 months from date of print, unless it is printed from TH’s HSE Head Office. The validity of the format will cease as soon as a new Revision is issued by TH’s HSE Head Office. Proof of communication and training of Risk & Environmental Assessment and Method statement for: LIFTING OPERATIONS WITH OVERHEAD CRANES SUPERVISOR: PEOPLE PRESENT: DATE: NAME SURNAME SIGNATURE Reg. No. 2001002519/07