PLANI EMERGJENCES |
PLANI EMERGJENCES
LINJA TRANSMETIMI
Dokumenti I prezantuar eshte prone e Arber Qamil Dogani dhe eshte e ndaluar kopjimi I tij /ose imitimi me qellim kopjimin.
00 22/07/2015 Aprovim A.Dogani E.Berisha E. Barhani A. Kompania
REV DATA LESHUAR PER Leshuar nga
Kontrolluar nga QA/QC Menanxher
Projekti
Administrator
KONTEKSTE
1. HYRJE
2. PERSHKRIMI I TERRENIT DHE PASQYRIMI I NDERTIMIT
3. MATERIALET E RREZIKSHME DHE MBETURINAT
4. REGULLAT DHE KERKESAT E LEJEVE PERKATESE
5. PLANI I AKSIONIT EMERGJENT
6. POLLUTION PREVENTION METHODS
7. KONTROLLI DHE MASAT E VENDOSURA
8. INSPEKTIME DHE REGJISTRIMI I TE DHENAVE
9. TRAJNIME
10. GRUPI GADISHMERISE EMRGJENTE
11. GRUPI I KRYQIT TE KUQ
Page 1
1 HYRJE
Ky Plan Emergjence eshte perpiluar per projektet e kompanive qe ndertojne linja
transmetimi te TL. Ky Plan ka për qëllim të siguroje metodat dhe procedurat për mbrojtjen
e mjedisit, shëndetit publik, si dhe për t'iu përgjigjur ndonjë incidenti të mundshëm, gjatë
ndërtimit të projekteve. Ky plan përfshin njoftime të mundshme që mund të ndikojnë ujërat
sipërfaqësore, nëntokësore te tokës dhe ajrit. Ky Plan gjithashtu përfshin metodat e
kontrollit, masat e parandalimit të ndotjes, inspektime dhe mbajtje të regjistrimeve dhe
kërkesat e trajnimit.
Të gjithë menaxherët dhe personeli mbikëqyrës në terren duhet të jetë i ditur në lidhje me
të gjitha aspektet e këtij plani. Ata duhet të sigurojnë zbatimin e tij, si dhe përputhshmërinë
lidhur me të, nga i gjithë personeli ndërtimit dhe nënkontraktorët. Ky Plan do të përfshihen
si dokument referimi në të gjitha kontratat me nenkontraktoret e lëshuara për projektet. I
gjithë personeli i ndërtimit duhet të trajnohen për derdhje te mundeshme te lendeve te
rrezikshme dhe parandalimin e ndotjes, kontrollin, dhe përgjigje.
Ky plan thekson masat parandaluese, si dhe aftësinë e reagimit në rast te ngjarjeve të
derdhjes ose të ndotjeve te ndryshme te mjedisit.Krijon shtigjet e komunikimit dhe
ndërfaqe me agjencitë rregullatore, kështu që ka linja të qarta të përgjegjësisë dhe
dokumentacionit efektiv. Edhe pse ky plan është paraqitur si një dokument më vete, ai në
fakt është një element i një programi të përgjithshëm të pajtueshmërisë mjedisore zbatohet
gjatë gjithë periudhës së ndërtimit.
2 PERSHKRIMI I TERRENIT DHE PASQYRIMI I NDERTIMIT
Zona ndërtimi e planifikuar shtrihet ______________________________stacioni i
energjisë tek Shtylla _____________________ Drejtimi përfshin terrenin kodrina dhe
habitatet bujqësore, dhe ajo kalon rrjedhat e shumta te ujit të.
Projekti përfshin ndërtimin për rreth një vit, duke përparuar nga jugu në veri. Këto
ndertime do të kene ruajtjen e mbeturinave, pasi puna e finalizohet në zonën akumulimit të
___________.
Forca e punës është parashikuar të arrijë kulmin në rreth 100 njerëz. Një përzierje standarde
e pajisjeve të ndërtimit dhe metodat qe do të përdoren, duke përfshirë një varietet të dheut
dhe duke i hapur pajisje të tilla si buldozerë, eskavator, dhe kamionë. Shuma e pajisjeve në
vend do të ndryshojnë ne perputhje me proceset e ndërtimit, dhe në përputhje me vendet e
punës. Puna do të jetë njekohesisht në vende të shumta në të njëjtën kohë dhe do të
përfshije forcat te drejtpërdrejta të punësuara.
Page 2
3 MATERIALET E RREZIKSHME DHE MBETURINAT
Materialet që potencialisht mund të përhapen në vendet e ndërtimit janë tipike të çdo
projekt ndërtimi të madh. Kjo kryesisht përfshin produktet e naftës të tilla si lëndë djegëse
të automjeteve, vaj motori, lubrifikant, dhe lëngjeve hidraulike. Bojra, sealant, antifriz,
tretës, dhe bateritë janë materiale të tjera të rrezikshme që do të ruhen dhe të përdoren.
Sasitë e materialeve të rrezikshme të depozituara në vend do të minimizohen dhe do të
vendosen në vende të caktuar (dhe të nënshkruar) per kontrollin dhe zonat e magazinimit të
përkohshëm. Në mënyrë të ngjashme, çdo mbeturina dhe mbeturinave të naftës rrezikshme
do të ruhen përkohësisht në një zonë të caktuar kontrolli dhe do te hidhen brenda 6 muajve.
Ky limit magazinimit minimizon të gjenerimit dhe magazinimit nevojat e përgjithshme.
Karburanti për pajisje të rënda të ndërtimit (p.sh., eskavator, buldozier) do të sillen në vend
me Bidona dhe do te përjashtohen autobotet. Karburantit për automjete të vogla do të
merren në stacionet lokale benzinë / naftë. Pajisjet e ndërtimit qe përmbajne lëndë djegëse
përfshi gjeneratorë, kompaktor, pompa dhe kompresorë etj. Nafta për këto pajisje do të
ruhen në depozita plastike ose bidona të vogjel sipas standarteve te mbajtjes se naftes në
zonat e magazinimit.
Çdo nënkontraktor do të jetë përgjegjës për menaxhimin e materialeve të rrezikshme dhe
përfshi identifikimin e duhur, trajtimin dhe kontrollin e çdo dhe të gjitha materialeve të
rrezikshme të përdorura dhe mbeturinave të rrezikshme të krijuara gjatë aktiviteteve të tyre
të ndërtimit. Çdo nënkontraktor duhet të sigurojë që të dorezoje tek Departamenti SSHM
tek kompania KOMPANIA, një listë e materialeve dhe mbetjeve të rrezikshme që
parashikojnë përdorimin ose gjeneruar në vendin e punës. Çdo nënkontraktor duhet të
rinovoje listën e tij fillestare kur materiale të reja të rrezikshme dhe mbetjet janë sjellë ose
gjeneruar në vend. Kjo listë duhet të sigurohet per Përfaqësuesin e (Sigurise Shendetit dhe
Mjedisit SSHM) të paktën nje here ne tre muaj.
Derdhjet e vogla (izoluar) dhe rrallë e produkteve të naftës janë tipike për këtë lloj
operacioni të ndërtimit, në vend se një derdhje të madhe. Kjo është për shkak se sasi të
mëdha të materialeve të rrezikshme të lëngshme (depozita të mëdha magazinimi) të mos
mbahen në vend, siç ndodh me një strukturë operacionale. Çdo derdhje do të zgjidhet duke
përdorur masa standarde parandalimi dhe kontrollin e derdhjes në industrinë e ndërtimit
dhe në përputhje me lejet dhe ligjet shqiptare.
Page 3
4 RREGULLAT DHE LEJET PERKATESE (LIGJET)
Ligjet që kanë të bëjnë me aspektet e derdhjes dhe parandalimin e ndotjes kontrollit, dhe
kundërmasat përfshijnë:
• Ligji Nr. 7501, data 19-06-1991 “Rruajtja e Mjedisit “.
• Ligji Nr. 8990, data 23-01-2003 “Vleresimi I Impakteve Mjedisore “.
• Ligji Nr. 8906, data 6-06-2003 “Zonat e Mbrojtura “.
• Ligji Nr 10431, data 9.6.2011 “Mbrojtja Mjedisore “(Ndryshuar).
• Ligji Nr.111, data 3.11.2012 “Meanxhimi Burimeve Ujore”.
• Ligji Nr.10440, data 7.7.2011 “Vleresimi I Impakteve Mjedisore “.
• Ligji Nr. 10463, “Për menaxhimin e integruar të mbetjeve të ngurta “.
• Ligji Nr. 8897, data 16.5.2002 “Për mbrojtjen e ajrit nga ndotja "(i
ndryshuar).
• Ligji Nr. 9010 data 13.2.2003 “Per administrimin Mjedisor te mBetjeve te
Ngurta’’
• Law No. 9115 data 24.7.2003 “Menanxhimi I Ujrave te Kontaminuara“.
• Law No.9108, data 17.7.2003 “Per Substancat dhe Lendet Kimike“.
• Law No. 9537, data 18.5.2006 “Per Menanxhimin e mbetjeve te rrezikshme“.
• Law No. 9774, data 12.7.2007 “Për vlerësimin dhe administrimin e
zhurmës në mjedis “.
Lejet që lidhen me derdhje dhe parandalimin dhe kontrollin e ndotjes përfshijnë:
• Ruajtjen e lëndëve djegëse, naftës dhe materialet që lidhen me përgatitjen e asfaltit
në vende të mbyllura dhe në platforma konkrete;
• Ruajtjen e materialeve të rrezikshme, në përputhje me ligjet dhe etiketimin e
produktit;
• Mbajtja e baterive (acid sulfurik) në mënyrë për të parandaluar zjarrin;
• Ruajtjen borjave dhe acideve në vende të largëta nga burime të zjarrit;
• Mbajtja e nje registry te posacem per materialet dhe lendet te cilat kane si rrezik
burimin e zjarrit ;
• Mirembajtja e vendeve te magazinimit te cilat mund te isnpektohen nga organet
perkatese ;
• Magazninimi I vajit te perdorur ne fuci ose bidona te standartizuar me normat
perkatese EN,ANSI ose ekuivalente.
5 PLANI AKSIONIT NE RAST RRJEDHJE (PANRD)
Derdhja,planifikimi i veprimit reagimit përshkruan hapat që duhet të ndërmerren në rast të
një incidenti që përfshin një derdhje të madhe apo të konsiderueshme të materialit gjatë
operacioneve të ndërtimit që përbën një kërcënim të menjëhershëm për shëndetin e njeriut
dhe / ose mjedisin. derdhjet e tilla të mëdha nuk mund të pastrohen në mënyrë të sigurtë pa
ndihmën e personelit te trajnuar dhe reagimit emergjent dhe / ose off-site pajisjeve
Page 4
përgjigje urgjente. Këto derdhjet janë ato që mund të ndikojë drejtpërdrejt zonat jashte
mbulimit (përfshirë ujërat sipërfaqësore, nëntokësore).
Përfaqësuesi i SSHM, në koordinim me Menaxherin e Projektit, do te axhornojne këtë plan
periodikisht sipas nevojës gjatë ndërtimit. Përfaqësuesi i SSHM do të sigurojë që ky plan
është shpërndarë në mënyrë efektive dhe se personeli i ndërtimit eshte I përgatitur për ta
zbatuar atë. Ky Plando të jetë në dispozicion në të gjitha zyrat në terren të projektit.
Ky Plan per Parandalimin e rrjedhjeve si dhe aksioni I ndermare perfshin personelin dhe
pankardat,sinjalizimet,:
Nje coordinator emergjent
Nje list me numrat e perkates se pergjegjesve perkates
Nje formalitet (skenar)te ekspozuar ne terren se si do te veprohet ne rast incidenti
Llojet e pajisjeve dhe vend magazinimi
Grupi pergjigjes emergjente
Harta e Evakuimit ne nje plan
Plani I Oblektit
Hapat nje per nje qe do te ndermeren
Dokumentacioni
5.1. Koordinatori I pergjgjes emergjente
Koordinatori I pergjigjes emergjente primar për këtë plan është;
Name: Arber Dogani
Title: Pergjegjes I Sigurise Shendetit
Dhe Mjedisit (SSHM)
Phone:+355689095227
Koordinatori I pergjgijes emergjente do të ketë trajnim dhe përvojë në lidhje me derdhjet
dhe kontrollin ,kundërmasat për operacionet e ndërtimit, si dhe përgjigje organizative dhe
shkathtësitë e menaxhimit dhe trajnimit. Ai do të jetë në dispozicion në vend, ose me
njoftim telefonik në qoftë nese ndodhet off-site, në çdo kohë gjatë gjithë kohëzgjatjes së
ndërtimit. Emri i tij dhe numrat e telefonit do të jetë postuar në të gjitha zyrat në terren të
projektit.
5.2. Lista telefonike e raportimeve
Koordinatori i pergjigjes Emergjente do të mbajnë me vete në çdo kohë listën e telefonit te
njoftimeve. Koordinatori I pergjigjes Emergjente ose mëkëmbësi i tij / saj do të fillojnë të
kontaktoje me individët dhe agjencitë e mëposhtme brenda 15 minutave të një ngjarje të
derdhjes që kërkon përgjigje emergjente. Koordinatori i Reagimit Emergjent do të zbatojë
dhe rend e procesit të njoftimit dhe veprimet korrigjuese të bazuar në llojin dhe madhësinë
e derdhjes dhe rrezik potencial për burimet dhe shëndetin. Incidenti dhe njoftimet do të
dokumentohet në formë të "incidentit dhe njoftimit"
Nr. Tittulli Organizativ Numer Kontakti
Page 5
1. Menanxheri Projektit
2. Zevendes Menanxheri Projektit
3. Lider I Sigurimit Teknik
4. Pergjegjes I Sigurimit Teknik
5. Menanxheri I Terrenit
5.3. Procesverbali Incidenti
Koordinatori i Aksionit Emergjent do të përdori këtë Formular njoftimi formë për të kapur
rrethanat te cilat nevojën për zbatimin e Planit të Veprimit dhe Reagimit per Derdhjet dhe
njoftimet e bëra. Kjo përfshin:
• Data, koha dhe lokacioni I incidentit;
• Pershkrimi Incidentit (tipi dhe lloji si dhe rethanat perkatese);
• Emrat e individeve te perfshire si dhe kontakten nese ka;
• Koha/Data e njoftimit
• Pershkrimi I cdo informimi I dhene nga personeli regulator;
• Pershkrimi I aksionit te ndermarre, planifikimi ose kompletimi;
5.4. Pajisjet, Makinerite dhe Magazinimi
Materialet për përgjigje do të ruhen në vende të shumta, në afërsi të vendeve të punës
aktive. Materialet Derdhja do të jetë e pranishëme në vendet aktive të punës, sidomos kur
Përfaqësuesi i SSHM ose mbikëqyresi Inxhinieri perfaqesues beson rrezikun e mundshëm
të një derdhje apo ndikim në një burim të caktuar (psh, ujore) ekziston. Lokacionet e
magazinimit mund të transferohen gjatë projektit të ndërtimit, si elemente të ndryshme nese
sheshit të ndërtimit janë përfunduar.
Magazinieri I caktuar nga Departamenti Mekanik do të jetë përgjegjës për inventarizimin
(tremujore) dhe trajnimin për të siguruar se materialet janë në dispozicion dhe ato të
personelit të ndërtimit di ku pajisjet reagimi dhe furnizime janë të vendosura.
Materialet e kontrollit te derdhjes do të veçohen (te shënuara) në vende të magazinimit, për
të dyja ujërat sipërfaqësore apo situatat me bazë në tokë.
Magazinimi I materialeve perfshin;
Fuci celiku ose plastike (200 litra), me kapak, për vendosjen e lendeve te derdhura
Plasmas per tu vendosur ne toke ne rast derdhe
Tallash Druri
Pompe thithese per parandalimin e rrjedhjeve derdhjeve te lendeve te rrezikshme ne situate
publike
Sfungjer plasmas per te thither lendet e rrezikshme nese ato jane derdhur ne lumenj gropa
uji etj
Dorashka gome per personelin
Page 6
Lopata
Eskavator emergjent si pjese e aksionit
5.5. Suporti Emergjent
Për situatat që kanë nevojë për mbështetje nga jashtë (zjarr, derdhjet e rëndësishme duke
paraqitur rreziqe për shëndetin, ujin, dhe burime të tjera), Koordinatori Emergjences
menjëherë do të njoftojë organizatat e mëposhtme dhe të heqë dorë per menaxhimin e
incidentit pas mbërritjes së tyre. Koordinatori Emergjences dhe Përfaqësuesi SSHM do të
vazhdojnë për të lehtësuar dhe koordinuar me këto organizata në lidhje me përdorimin e
burimeve në vend dhe kontrollin. Vendin numrat e urgjencës janë:
Departamenti Zjarrfikeses ne Shqiperi: Nr.Kontakti: 128
Departamenti Policise: Nr.Kontakti: 129
5.6. Plani Evakuimit
Nevoja për evakuim do t'i komunikohet projektit personelit nëpërmjet Inxhinierëve te
terrenit në telefon ose radio kontakt me Koordinatorin e Reagimit Emergjent dhe
Përfaqësuesit te SSH&M . Të gjithë të punësuarit e projektit do të fuqizohet për të lehtësuar
komunikimin në vend dhe të bashkë-punëtorëve, nëse një incident ndodh,duhet që te
garantohet evakuimi.
Evakuimi dhe pika mbledhjes do të zhvendoset si puna ndërtimore qe është e përparuar
përgjatë shtrirjes; kjo temë do të jetë pjesë e trajnimit fillestar të punonjësve të dhënë nga
SSH & M personelit dhe Inxhinierëve te Terrenit.Evakuimi dhe pikat e grumbullimit e
gjithashtu mund të zhvendosen në varësi të kushteve të erës (drejtimi i çdo ndotësve
ajrore). Pikat e evakuimit kryesore, nëse është e nevojshme, do të jetë në afërsi të aksesit të
punës ne terren, por në një anë në mënyrë që të mos bllokojnë pajisjet e emergjencës. pikat
e para-planifikuar te grumbullimit, rrugët e evakuimit, dhe rruga per spital do të jetë
postuar në zyrat e projektit.
5.7. Objektet e perkoheshme
Projekti do të ketë mirëmbajtjen rrethimeve te kantiereve. Lokacionet e zonave të
rrezikshme te mbeturinave (materialeve dhe mbetjeve) do te gjurmohen, inspektohen,
dokumentohen, dhe do miratohen paraprakisht nga Përfaqësuesi SSHM. Të gjitha
materialet dhe baterite e përfshira në këto fusha do të etiketohen dhe përmbajtja e tyre do te
identifikohet. Zonat e magazinimit do të jene te mbrojtura nga uji dhe stuhite. Vend
magazinimet do te kene sisteme te daljeve emergjente dhe sisteme te cilat ndajne naftën /
nga uji.
5.8. Hapat e veprimit
Derdhje madhore: Personeli i ndërtimit nese zbulon një derdhje të madhe do të njoftojë
mbikëqyresit ose inxhinierin e vendit dhe mund të marrë masa të menjëhershëm që mund të
Page 7
kryhen pa dëm për shëndetin dhe sigurinë e tyre (p.sh., stakim valvulash, përdorimin e
digave,mbrojtja e ujërave sipërfaqësore, luginat, zonat natyrore, dhe brigjet).
Inxhinieret e Terrenit menjëherë do të njoftojnë koordinatorin e Reagimit Emergjent dhe
Përfaqësuesin e SSH & M. Inxhinieri i vendit do të mbikëqyrë çdo veprime fillestare dhe
evakuimin derisa Koordinatori I Reagimit Emergjent te marre masat e duhura. Koordinatori
i Emergjences do të vlerësojë situatën, do zbatojë njoftimet, dhe masat e drejtpërdrejta të
kontrollit sipas nevojës.
Derdhje e vogël: Nese personeli i ndërtimit zbulon një derdhje të vogël (p.sh.,
automjeteve / pajisjeve rrjedhjen e naftës ose të lëngjeve hidraulike ne tokë apo konkrete)
do të njoftojë mbikëqyresit Inxhinieri i terrenit do te marrin masa për të ndaluar derdhjet /
rrjedhjet, dhe do të marrë masat për të vendosur materialet e parandalimit te
derdhjeve.Inxhinieri i terrenit do të njoftojë brenda 15 minutave SSH & M Përfaqësues i
cili do të përgjigjet dhe do të mobilizojë burimet e nevojshme nëse është e nevojshme.
Nga përkufizimi, derdhjet e vogla mund të përfshihen në mënyrë të sigurtë në afërsi të
derdhjes, nga personeli në vend, dh në dispozicion materialet përgjigje derdhjes (paketimi i
absorbuesve, lopata). Këto derdhje nuk kërcënojnë qe te shkaktojë një kërcënim të
menjëhershëm për shëndetin e njeriut / ose mjedisin.
5.9. Dokumentacioni
Major Spill: Kordinatori Planit te Emergjences si dhe perfaqesuesi I SSH&M(Sigurise
Shendetit&Mjedisit)do te perdorinper te dokumentuar rrjedhjet dhe masat e marra ose qe
do te merren ne formatin e incidenteve mjedisore sipas Planit te SSHM. Duke vepruar
kështu, ata do të mbledhin informacion nga personeli i projektit dhe agjencitë rregullatore
vendase.
Perfaqesuesit e SSHM do te arvikojne te gjtiha dokumentacionet te cilat do te kene si
burime informacioni te gjtha eventet dhe incidentet te shoqeruara me fotografi,deshmitar
okular fakte etj.
6 METODAT PER PARANDALIMIN E NDOTJES
6.1. Plani konstruksioneve dhe nenkontraktoret
Kërkesat rregullatore dhe praktikat më të mira të menaxhimit, do të përfshihen në
planifikimin e ndërtimit dhe ekzekutimin e punës.
Planifikuesit e ndërtimit do të jenë te nevojshem për të përfshirë parimet e Sigurise
Shendetit dhe Mjedisit SSH & M në planet e tyre të punës, perfaqesuesit e SSH&M do te
percaktojne dhe aprovojne te gjitha praktikat te cilat planfikuesit e projekteve do te
hartojne ne lidhje me parimet e SSH&M.
Per ë gjithë nënkontraktorët do të jetë e nevojshme të përfshijnë parandalimin derdhjes në
Planin e tyre te SSH & M, të paraqesin planin e tyre miratim nga kompania KOMPANIA
SHPK, dhe të ketë materiale të përshtatshme për parandalimin e derdhjes në vend që të
Page 8
përputhen me llojin dhe shtrirjen e punës së tyre.Mbikeqyresit perfaqesuesit e Sigurise
Mbrojtjes dhe Shendetit si dhe Inxhinierët e terrenit do të monitorojë pajtueshmërinë e tyre
per të gjitha zonat e magazinimit të përdorura nga nënkontraktorët.
6.2. Akumulimi dhe pikat e grumbullimit
Menaxheri i Projektit do të caktojë një person për të menaxhuar zonat e akumulimit të
mbeturinave dhe zonat e magazinimit te materialeve të rrezikshme. Ky person do të
sigurojë materialet e duhura për parandalimin e derdhjes të pranishme dhe do të inspektojë
periodikisht për të siguruar që zonat:
• Jane te organizuara ne menyre te sigurt;
• Jane te siguruara per shuarjen e zjarrit me Fikes portative;
• Qe sistemet e kanalizimeve dhe drenazhimeve jane ne gjendje te mire;
• Kane aksesin e duhur per inspektim;
Zonat akumulimit të mbeturinave do të kenë një sipërfaqe të papërshkueshme pa të çara.
Akumulimi dhe ruajtja e zonave do të kontrollohet zonat me qasje të kufizuar.
6.3. Koshat dhe kontinieret
Koshat dhe kontinieret te cilet do te permbajne mbeturina te rrezikshme do te jene:
• Ne gjendje te mire fizike (Pa carje, jo te degraduar);
• Te perdorshem me mbetje te cilat nuk demtojne permbajtjen e tyre;
• Te levizshem me mjetet dhe menyra te sigurta;
6.4. Perdorimi I pajisjeve dhe mirembajtja e tyre
Pajisje në vendet e punës mund të jenë një burim potencial i derdhjeve te vogla. Metodat e
parandalimit përfshihenë si në vijim:
• Pajisjet dhe mjetet do te mirembahen ne menyre periodike, so dhe do te inspektohen
per rrjedhje te mbetjeve te naftes vajit etj.
• Kontrollet e erozionit do të përdoret në faqet e perimetrit ne terren, duke ndihmuar për
të menaxhuar tokën dhe rrjedhjet e ujit stuhite dhe në këtë mënyrë lëvizjen e çdo
materiali te derdhur ose hedhur
Page 9
6.5. Ekzekutimi I punes
Menyra te ndryshme te cilat do te ndihmojne parandalimin e derdhjeve te lendeve te
ndryshme;
• Mbulimi dhe kullimi ne gropat e hapura pergjate punes dhe ne te cilat jane perfshire
material te rrezikshme;
• Materiale per te mbuluar rrjedhjet, derdhjet ne rast se ndodhin te tilla;
• Te korrdinohen punimet ne menyre te tille qe potenciali per infektimin e ujrave ne
zonat prane punimeve te zvogelohet;
• Te gjendet materiali dhe te jete prezent per kontaminimin e rrjedhjeve perpara
punimeve nese mendohet se do te kete rrjedhje ose derdhje te mbetjeve te rrezikshme;
• Te zvogelohen metodat e perdorimit te materialeve te rrezikshme duke planifikuar
punime me material sa me pak te rrezikshme;
• Te planifikohen vendet ne te cilat do te behet larja e mbetjeve te betonit si Batonieret
etj;
• Te mirembahet vendi I punes dhe te pastrohet periodikisht;
6.6 Transporti
Perpara transportimit ose marrjen e kontenierë, ato duhet të kontrollohen për të konfirmuar
integritetin strukturor për rrjedhje dhe derdhje të mundshme. Ato gjithashtu duhet të
etiketohen siç duhet dhe të jene te mbyllura, te përmbajnë material të përshtatshëm për
llojin e veçantë të tyre. Materiali i mbeturinave duhet të shfaqet si duhet, gjurmuar, dhe
hidhen në një vend te miratuar;
.
7 KONTROLLI DHE KUNDERMASAT
7.1. Rjedhjet e lendeve djegese
•
• Siguria mbi te gjitha. Per shmangjen e avujve duke qendruar kunder eres do te perdoren
pajisje per rezistence ndaj lendeve kimike si;(doreza, cizme, syze mbrojtese).
• Pergjate perdorimit te benzines duhet te shmangen bisedat telefonike me telefona
celular, ndezja e flakeve, perdorimi duhanit etj.
• Ne rast se derdhje te medha te lendeve djegese derdhen ne terren duhet te lajmerohen
perfaqesuesit e SSHM sigurise shendetit dhe mjedisit dhe ne vend do te ndalohet
qarkullimi duke e rrethuar me shirit sinjalizues.
7.3. Rrjedhjet Kimike acid, dylent etj)
• Siguria mbi te gjithe. Per shmangjen e avujve duke qendruar kunder eres do te perdoren
pajisje per rezistence ndaj lendeve kimike si;(doreza, cizme, syze mbrojtese).
Page 10
• Duhet te ndalohet burimi I rrjedhjes duke e izoluar ate sa me shpejt te jete e mundur me
praktika te sigurta. Te lajmerohet administrator mjedisor Brenda 15 minutave.
• Duke u referuar tek te dhenat e materialeve te cilat gjenden ne rregjistrat e magazinimit
ne ndermarjen Kompania, per cdo rrezik te specifikuar do te perdoren procedurat e
duhura per lendet kimike.
• Ato duhen te magazinohen ne kontinieret e duhur jo me shume se 180 dite kalendarike.
• If temporarily stored, place containers in the waste accumulation area for no more than
180 days.
• Per rrjedhje t emundeshme do te perdoret Raporti I rrjedhjeve si dhe raporti incidenteve
referuar Planit te SSHM Sigurise Shendetit dhe Mjedisit.
8 INSPEKTIMET DHE RREGISTRI I TYRE
8.1. Plani I shperndarjes
Një kopje e këtij plani do të shpërndahet për çdo inxhinier terreni dhe nënkontraktoreve te
ndërtimit që do te punojnë në vend. Një kopje do të jenë në dispozicion në çdo zyrë në
terren.
8.2. Monitorimi dhe Inspektimi
Përfaqësuesi i SSH & M do të inspektojë dhe të kryejnë monitorimin e sigurimit të cilësisë
të të gjitha zonave të punës dhe vendeve me karburant ose magazinimit të rrezikshm të
mbeturinave / materiale, në minimum, në baza javore dy dhe në përputhje me procedurat e
përshkruara në Planin e Ndërtimit Mjedisor të projektit të Kontrollit (PPKNM).Kushtet dhe
ndjekja mbahet në objektin e magazinimit dhe gjithashtu të përshkruara në raportin mujor
SSH & M. Çdo veprime korrigjuese që janë të nevojshme do të sillen në vëmendjen e
mbikëqyrës inxhinierit në të njëjtën ditë për zgjidhjen e shpejtë.
Përfaqësuesi i SSH & H do të raportojë te gjtiha tendencat e vërejtura dhe mësimet e
nxjerra në lidhje me potencialin për një ngjarje derdhje, ose kontrollin joadekuate, tek
Menaxheri i Projektit i cili do të japë drejtimin brenda forcës së punës ndërtimore për
veprimet korrigjuese dhe ndryshimet.
Çdo Përgjegjës I caktuar në një zonë të ndertimit, mirëmbajtjes, ose zonën e punës do të
jetë përgjegjës për inspektimin e përditshm për shenjat e derdhjet dhe siguruar që daljet
efektive për parandalimin dhe kontrollin e derdhjes. Cdo pergjegjes do të raportojnë çdo
veprime te nevojshme apo probleme të përsëritura tek mbikëqyrësi I inxhinierit te terrenit.
Në mënyrë të ngjashme, Inxhinierët e terrenit dhe nënkontraktorët gjithashtu do të jetë
përgjegjës për të vëzhguar dhe duke marrë parasysh të gjitha derdhjet në zonat e tyre të
punës, përshtatshmërinë e kufizimit dhe parandaluese masa, dhe duke marrë çdo veprim të
nevojshem.
8.4. Agjencitë rregullatore
Page 11
Përfaqësuesi i SSH & M do të shoqërojë çdo inspektorë nga agjencitë rregullatore. Kjo
mund të përfshijë Agjencinë për Mbrojtjen e Mjedisit apo zjarrfikësit. Një përfaqësues i
ekipit të menaxhimit të ndërtimit, të përcaktuar nga Menaxheri i Projektit, do të marrë pjesë
në çdo inspektime të tille rregullatore; në mënyrë që veprimet korrigjuese të zbatohen në
kohën e duhur siç përshkruhet nga personeli rregullator.
Menaxheri i Projektit do të transmetojë çdo dokumentacion të kërkuar nga personeli
rregullator. Lideri I SSH & M dhe përfaqësuesit do të mbajnë të dhënat, në dosje, të gjitha
inspektimet e rregullatoreve dhe korrespondencat.
8.5. Rregjistri
Siç përshkruhet në më sipër, Përfaqësuesi i SSH & M do të mbajë shënime, kopje të
ngjarjeve derdhjes, inspektimet e përputhshmërisë, deponimin e mbeturinave, dhe
korrespondencë rregullator për referencës dhe shqyrtim qëllime siç kërkohet.
9 TRAJNIMI
I gjithë personeli ndërtimit në vend të punës duhet të marrin pjesë në trajnimet formale te
Mjedisit, Sigurisë dhe Shëndetit (ES & H) në fillim të detyrës së tyre. Ky trajnim përfshin
parandalimin dhe kontrollin e derdhjes. Bisedimet ne terren do të përdoret në javë gjatë
periudhës së ndërtimit si pjese freskuese e trajnimit SSH & M ES & H. Lideri I Sigurise
Shendetiti dhe Mjedisit SSH & M i do të jetë përgjegjës për përgatitjen e materialeve te
trajnimit, mbajtjen e shënimeve të të gjithë pjestareve të trajnuar. Përfaqësuesi i SSH & M
do të jetë përgjegjës për zhvillimin e dokumenteve specifike të trajnimeve mjedisore dhe
materialeve, postimi i fletëve udhëzuese per vetëdijen, dhe postimi I listave e njoftimit në
vende të dukshme në zyrat në terren.
Punonjësit e kompanise, si pjesë e trajnimit te SSH & M, do të jepet drejtimi për të sjellë në
vëmendjen e mbikëqyrësit të tyre çdo kusht që ka potencial të jetë një rrezik mjedisor ose
rrezik për shëndetin dhe sigurinë ose rrezik - dhe për të marrë veprimet e nevojshme. Kjo
përfshin parandalimin dhe kontrollin e derdhjes. SSH & M do të jetë një pjesë e pandarë
dhe e pritshme e kulturës ne vendin e punës.
Të gjithe Inxhinierëte Terrenit do të jetë e nevojshme për të marrë pjesë në trajnime të
vazhdueshme dhe takimeve të rregullta të fokusuara në aspektet e hollësishme te SSH & M
per zbatimin e programit. Kjo përfshin parandalimin dhe kontrollin e derdhjes, dhe
menaxhimin e mbeturinave të rrezikshme. Trajnimi do paraqese fuqine punëtore në
ndryshim (personelin dhe numrin e personelit) dhe metodat e ndërtimit gjatë periudhës së
ndërtimit.
Korrdinatori I pergjigjes emergjente si dhe personeli I perfshire per parandalimin e
rrjedhjeve do te kene nje trajnim te avancuar specific per rrjedhjet dhe trajtimin e tyre,si
dhe menanxhimin e mbetjeve te rrezikshme.
_________________________________________________________________________
SHTOJCAT (Formularet):
Page 12
1. Formulari Incidenti dhe Lajmerimi
2. Formulari I raportimit te rrjedhjeve
3. Orientim per perdorimin e pajisjeve dhe materialeve kunder rrjedhjeve
4. Iventarizimi I mbeturinave te rrezikshme
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
5.
Formulari I inpektimeve mujore per magazinimin e mbeturinave te rrezikshme
10 GRUPI I PERGJIGJES EMERGJENTE (organigram)
Page 13
Emergency Response Organogram Team.
Foreman / Team
lead
HSE
Manager/Lead
Site Engineer
Ambulance-112
Police -129
Fireman -128
HOSPITAL
Deputy Manager
11. GRUPI I NDIHMES SE PARE
Perfaqesuesit e SSH & M do te jene te disponueshem per cdo keshillim dhe suport tek te gjithe pjestaret
pergjegjes per ndihmen e pare ne terren.
Përkufizimi i "ndihmës së parë", "një person i cili do të ketë nevojë për ndihmë nga një mjek apo infermier,
trajtim me qëllim të ruajtjes së jetës dhe të minimizuar pasojat e lëndimit dhe sëmundje deri në ndihmë të
tillë është marrë"
• Procedura do te mbuloje’’trajtimin e lendimeve te vogla te cilat perndryshe do te marrin trajtim
ose qe nuk kane nevoje per trajtim nga mjeket apo infermjeret’’
• Menaxhimi fillestar i ndonjë lëndimi apo sëmundje pësuar në punë të kryera, Ndihma e parë
duhet të bëhet shpejt dhe nga një person kompetent.
• Pajisjet e sinjalizuara me Kryqin E kuq do të jenë në vend për të lehtësuar shpejtë vëmendjen e
ndihmesit te pare dhe kujdes i cili nga ana e tij do të shpëtoje jetën dhe do të parandaloje
dëmtimet e lehta per duke u bërë demtime te medha.
• Ndihma e pare nuk do te perfshije ilace dhe medikamente te cilat nuk do te jene miratuar nga nje
mjek kompetent I cili me pare duhet te trajnoje personat e ndihmes se pare.
• Nje person kompetent dhe pergjegjes per dhenjen e ndihmes se pare duhet te plotesoje kushtet
ne vijim;
1) Kualifikimi per te qene nje person pergjegjes per ndihmen e pare duhet te kete kryer trajnimin nga
Kryqi iKuq 1 dite trajnim per cdo 3 vite.
11.1 INDENDIFIKIMI
• Identifikimi I personave qe japin ndihmen e pare ne terren do te behet behet duke u ngjitur nje
stiker nje shenje te kryqit te kuq ne helmeten ose jelekun e punonjesit. Keto sinjalistika do te
vihen ne dispozicion nga departamenti mekanik I kompanise.
• Kutite e ndihmes se pare duhet te jene Brenda standarteve te bashkimit europian.
Page 14
• Dhomat per dhenien e ndihmes se pare do te sinjalizohen tek porta ne hyrje me shenjen e kryqit
te kuq.
• Pikat emergjente do te indentifikohen ne nje plan evakuimi per cdo zyre ose kantier te kompanise.
• PROCEDURA TE PERGJITHSHME
• Punonjesit do te keshillohen per procedurat (perfshire dhe ndihmen e pare) pergjate instruktimit
periodic te tyre.
• Radio marresit do te perdoren si dhe telefonat cellular nese kontaktet e organizimit emergjent do
te afishohen ne terren.
• Personi per korrdinimin e situatave mjekesore do te kete si bashkepunim Policine dhe autoritet
emergjente, zjarrfikesit, ambulance etj.
• Perfaqesuesit e SSH & M do te keshillohen nga autoritet emergjente per cdo situate te
padeshiruar.
• Para fillimit të punës psh gjatë kartë induksioneve orientuese per projekte te ndryshme,
punonjësit duhet të këshillohen i cilet jane personat kompetent per ndihmen e pare si dhe ku do
te ndodhen/ kutite më te afërta te ndihmës së parë.) Inxhinieret e terrenit do te orientohen nga
departamenti Sigurise Shendetit & Mjedisit se ku do te kerkojne ndihme ne spitalet dhe pikat me
te aferta mjekesore per cdo situate te paparashikuar.
MBYLLJE
Programet e kompanise sone ne lidhje me Sigurine
Shendetin & Mjedisin jane hartuar ne menyre te tille qe te
parandalojne aksidentet.
Page 15
Bashkepunimi juaj I sinqerte eshte shume I rendesishem
per tu zbatuar 100% planet tona per SIGURINE.
Raportoni tek departamenti I Sigurise cdo sjellje te
rrezikshme te cilat mund te parandaloje aksidente qe do te
shpetonin JETE.
Kompania jone eshte shume krenare por do te vazhdje
punen per te zvogeluar sa me shume incidentet/aksidentet
te cilat kushtojne jete njerezish dhe shume per mjedisin.
Ndihma juaj do te ishte nje Bonus per te gjtihe ne.
Page 16

More Related Content

More from Arber Dogani

Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...Arber Dogani
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.doganiArber Dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...Arber Dogani
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statisticsArber Dogani
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber doganiArber Dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)Arber Dogani
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...Arber Dogani
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...Arber Dogani
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber doganiArber Dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesArber Dogani
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiArber Dogani
 
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018Arber Dogani
 
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimNew hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimArber Dogani
 
Basic harness awareness training albanian.
Basic harness awareness training albanian.Basic harness awareness training albanian.
Basic harness awareness training albanian.Arber Dogani
 
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Arber Dogani
 

More from Arber Dogani (15)

Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punes
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.dogani
 
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018Manuali i punes ndertimin e linjave dhe nst te tensionit te larte   shqip 2018
Manuali i punes ndertimin e linjave dhe nst te tensionit te larte shqip 2018
 
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertimNew hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
New hire orientation orientim per punonjesit e rinj linja transmetimi ndertim
 
Basic harness awareness training albanian.
Basic harness awareness training albanian.Basic harness awareness training albanian.
Basic harness awareness training albanian.
 
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
 

Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani

  • 1. PLANI EMERGJENCES | PLANI EMERGJENCES LINJA TRANSMETIMI Dokumenti I prezantuar eshte prone e Arber Qamil Dogani dhe eshte e ndaluar kopjimi I tij /ose imitimi me qellim kopjimin. 00 22/07/2015 Aprovim A.Dogani E.Berisha E. Barhani A. Kompania REV DATA LESHUAR PER Leshuar nga Kontrolluar nga QA/QC Menanxher Projekti Administrator
  • 2. KONTEKSTE 1. HYRJE 2. PERSHKRIMI I TERRENIT DHE PASQYRIMI I NDERTIMIT 3. MATERIALET E RREZIKSHME DHE MBETURINAT 4. REGULLAT DHE KERKESAT E LEJEVE PERKATESE 5. PLANI I AKSIONIT EMERGJENT 6. POLLUTION PREVENTION METHODS 7. KONTROLLI DHE MASAT E VENDOSURA 8. INSPEKTIME DHE REGJISTRIMI I TE DHENAVE 9. TRAJNIME 10. GRUPI GADISHMERISE EMRGJENTE 11. GRUPI I KRYQIT TE KUQ Page 1
  • 3. 1 HYRJE Ky Plan Emergjence eshte perpiluar per projektet e kompanive qe ndertojne linja transmetimi te TL. Ky Plan ka për qëllim të siguroje metodat dhe procedurat për mbrojtjen e mjedisit, shëndetit publik, si dhe për t'iu përgjigjur ndonjë incidenti të mundshëm, gjatë ndërtimit të projekteve. Ky plan përfshin njoftime të mundshme që mund të ndikojnë ujërat sipërfaqësore, nëntokësore te tokës dhe ajrit. Ky Plan gjithashtu përfshin metodat e kontrollit, masat e parandalimit të ndotjes, inspektime dhe mbajtje të regjistrimeve dhe kërkesat e trajnimit. Të gjithë menaxherët dhe personeli mbikëqyrës në terren duhet të jetë i ditur në lidhje me të gjitha aspektet e këtij plani. Ata duhet të sigurojnë zbatimin e tij, si dhe përputhshmërinë lidhur me të, nga i gjithë personeli ndërtimit dhe nënkontraktorët. Ky Plan do të përfshihen si dokument referimi në të gjitha kontratat me nenkontraktoret e lëshuara për projektet. I gjithë personeli i ndërtimit duhet të trajnohen për derdhje te mundeshme te lendeve te rrezikshme dhe parandalimin e ndotjes, kontrollin, dhe përgjigje. Ky plan thekson masat parandaluese, si dhe aftësinë e reagimit në rast te ngjarjeve të derdhjes ose të ndotjeve te ndryshme te mjedisit.Krijon shtigjet e komunikimit dhe ndërfaqe me agjencitë rregullatore, kështu që ka linja të qarta të përgjegjësisë dhe dokumentacionit efektiv. Edhe pse ky plan është paraqitur si një dokument më vete, ai në fakt është një element i një programi të përgjithshëm të pajtueshmërisë mjedisore zbatohet gjatë gjithë periudhës së ndërtimit. 2 PERSHKRIMI I TERRENIT DHE PASQYRIMI I NDERTIMIT Zona ndërtimi e planifikuar shtrihet ______________________________stacioni i energjisë tek Shtylla _____________________ Drejtimi përfshin terrenin kodrina dhe habitatet bujqësore, dhe ajo kalon rrjedhat e shumta te ujit të. Projekti përfshin ndërtimin për rreth një vit, duke përparuar nga jugu në veri. Këto ndertime do të kene ruajtjen e mbeturinave, pasi puna e finalizohet në zonën akumulimit të ___________. Forca e punës është parashikuar të arrijë kulmin në rreth 100 njerëz. Një përzierje standarde e pajisjeve të ndërtimit dhe metodat qe do të përdoren, duke përfshirë një varietet të dheut dhe duke i hapur pajisje të tilla si buldozerë, eskavator, dhe kamionë. Shuma e pajisjeve në vend do të ndryshojnë ne perputhje me proceset e ndërtimit, dhe në përputhje me vendet e punës. Puna do të jetë njekohesisht në vende të shumta në të njëjtën kohë dhe do të përfshije forcat te drejtpërdrejta të punësuara. Page 2
  • 4. 3 MATERIALET E RREZIKSHME DHE MBETURINAT Materialet që potencialisht mund të përhapen në vendet e ndërtimit janë tipike të çdo projekt ndërtimi të madh. Kjo kryesisht përfshin produktet e naftës të tilla si lëndë djegëse të automjeteve, vaj motori, lubrifikant, dhe lëngjeve hidraulike. Bojra, sealant, antifriz, tretës, dhe bateritë janë materiale të tjera të rrezikshme që do të ruhen dhe të përdoren. Sasitë e materialeve të rrezikshme të depozituara në vend do të minimizohen dhe do të vendosen në vende të caktuar (dhe të nënshkruar) per kontrollin dhe zonat e magazinimit të përkohshëm. Në mënyrë të ngjashme, çdo mbeturina dhe mbeturinave të naftës rrezikshme do të ruhen përkohësisht në një zonë të caktuar kontrolli dhe do te hidhen brenda 6 muajve. Ky limit magazinimit minimizon të gjenerimit dhe magazinimit nevojat e përgjithshme. Karburanti për pajisje të rënda të ndërtimit (p.sh., eskavator, buldozier) do të sillen në vend me Bidona dhe do te përjashtohen autobotet. Karburantit për automjete të vogla do të merren në stacionet lokale benzinë / naftë. Pajisjet e ndërtimit qe përmbajne lëndë djegëse përfshi gjeneratorë, kompaktor, pompa dhe kompresorë etj. Nafta për këto pajisje do të ruhen në depozita plastike ose bidona të vogjel sipas standarteve te mbajtjes se naftes në zonat e magazinimit. Çdo nënkontraktor do të jetë përgjegjës për menaxhimin e materialeve të rrezikshme dhe përfshi identifikimin e duhur, trajtimin dhe kontrollin e çdo dhe të gjitha materialeve të rrezikshme të përdorura dhe mbeturinave të rrezikshme të krijuara gjatë aktiviteteve të tyre të ndërtimit. Çdo nënkontraktor duhet të sigurojë që të dorezoje tek Departamenti SSHM tek kompania KOMPANIA, një listë e materialeve dhe mbetjeve të rrezikshme që parashikojnë përdorimin ose gjeneruar në vendin e punës. Çdo nënkontraktor duhet të rinovoje listën e tij fillestare kur materiale të reja të rrezikshme dhe mbetjet janë sjellë ose gjeneruar në vend. Kjo listë duhet të sigurohet per Përfaqësuesin e (Sigurise Shendetit dhe Mjedisit SSHM) të paktën nje here ne tre muaj. Derdhjet e vogla (izoluar) dhe rrallë e produkteve të naftës janë tipike për këtë lloj operacioni të ndërtimit, në vend se një derdhje të madhe. Kjo është për shkak se sasi të mëdha të materialeve të rrezikshme të lëngshme (depozita të mëdha magazinimi) të mos mbahen në vend, siç ndodh me një strukturë operacionale. Çdo derdhje do të zgjidhet duke përdorur masa standarde parandalimi dhe kontrollin e derdhjes në industrinë e ndërtimit dhe në përputhje me lejet dhe ligjet shqiptare. Page 3
  • 5. 4 RREGULLAT DHE LEJET PERKATESE (LIGJET) Ligjet që kanë të bëjnë me aspektet e derdhjes dhe parandalimin e ndotjes kontrollit, dhe kundërmasat përfshijnë: • Ligji Nr. 7501, data 19-06-1991 “Rruajtja e Mjedisit “. • Ligji Nr. 8990, data 23-01-2003 “Vleresimi I Impakteve Mjedisore “. • Ligji Nr. 8906, data 6-06-2003 “Zonat e Mbrojtura “. • Ligji Nr 10431, data 9.6.2011 “Mbrojtja Mjedisore “(Ndryshuar). • Ligji Nr.111, data 3.11.2012 “Meanxhimi Burimeve Ujore”. • Ligji Nr.10440, data 7.7.2011 “Vleresimi I Impakteve Mjedisore “. • Ligji Nr. 10463, “Për menaxhimin e integruar të mbetjeve të ngurta “. • Ligji Nr. 8897, data 16.5.2002 “Për mbrojtjen e ajrit nga ndotja "(i ndryshuar). • Ligji Nr. 9010 data 13.2.2003 “Per administrimin Mjedisor te mBetjeve te Ngurta’’ • Law No. 9115 data 24.7.2003 “Menanxhimi I Ujrave te Kontaminuara“. • Law No.9108, data 17.7.2003 “Per Substancat dhe Lendet Kimike“. • Law No. 9537, data 18.5.2006 “Per Menanxhimin e mbetjeve te rrezikshme“. • Law No. 9774, data 12.7.2007 “Për vlerësimin dhe administrimin e zhurmës në mjedis “. Lejet që lidhen me derdhje dhe parandalimin dhe kontrollin e ndotjes përfshijnë: • Ruajtjen e lëndëve djegëse, naftës dhe materialet që lidhen me përgatitjen e asfaltit në vende të mbyllura dhe në platforma konkrete; • Ruajtjen e materialeve të rrezikshme, në përputhje me ligjet dhe etiketimin e produktit; • Mbajtja e baterive (acid sulfurik) në mënyrë për të parandaluar zjarrin; • Ruajtjen borjave dhe acideve në vende të largëta nga burime të zjarrit; • Mbajtja e nje registry te posacem per materialet dhe lendet te cilat kane si rrezik burimin e zjarrit ; • Mirembajtja e vendeve te magazinimit te cilat mund te isnpektohen nga organet perkatese ; • Magazninimi I vajit te perdorur ne fuci ose bidona te standartizuar me normat perkatese EN,ANSI ose ekuivalente. 5 PLANI AKSIONIT NE RAST RRJEDHJE (PANRD) Derdhja,planifikimi i veprimit reagimit përshkruan hapat që duhet të ndërmerren në rast të një incidenti që përfshin një derdhje të madhe apo të konsiderueshme të materialit gjatë operacioneve të ndërtimit që përbën një kërcënim të menjëhershëm për shëndetin e njeriut dhe / ose mjedisin. derdhjet e tilla të mëdha nuk mund të pastrohen në mënyrë të sigurtë pa ndihmën e personelit te trajnuar dhe reagimit emergjent dhe / ose off-site pajisjeve Page 4
  • 6. përgjigje urgjente. Këto derdhjet janë ato që mund të ndikojë drejtpërdrejt zonat jashte mbulimit (përfshirë ujërat sipërfaqësore, nëntokësore). Përfaqësuesi i SSHM, në koordinim me Menaxherin e Projektit, do te axhornojne këtë plan periodikisht sipas nevojës gjatë ndërtimit. Përfaqësuesi i SSHM do të sigurojë që ky plan është shpërndarë në mënyrë efektive dhe se personeli i ndërtimit eshte I përgatitur për ta zbatuar atë. Ky Plando të jetë në dispozicion në të gjitha zyrat në terren të projektit. Ky Plan per Parandalimin e rrjedhjeve si dhe aksioni I ndermare perfshin personelin dhe pankardat,sinjalizimet,: Nje coordinator emergjent Nje list me numrat e perkates se pergjegjesve perkates Nje formalitet (skenar)te ekspozuar ne terren se si do te veprohet ne rast incidenti Llojet e pajisjeve dhe vend magazinimi Grupi pergjigjes emergjente Harta e Evakuimit ne nje plan Plani I Oblektit Hapat nje per nje qe do te ndermeren Dokumentacioni 5.1. Koordinatori I pergjgjes emergjente Koordinatori I pergjigjes emergjente primar për këtë plan është; Name: Arber Dogani Title: Pergjegjes I Sigurise Shendetit Dhe Mjedisit (SSHM) Phone:+355689095227 Koordinatori I pergjgijes emergjente do të ketë trajnim dhe përvojë në lidhje me derdhjet dhe kontrollin ,kundërmasat për operacionet e ndërtimit, si dhe përgjigje organizative dhe shkathtësitë e menaxhimit dhe trajnimit. Ai do të jetë në dispozicion në vend, ose me njoftim telefonik në qoftë nese ndodhet off-site, në çdo kohë gjatë gjithë kohëzgjatjes së ndërtimit. Emri i tij dhe numrat e telefonit do të jetë postuar në të gjitha zyrat në terren të projektit. 5.2. Lista telefonike e raportimeve Koordinatori i pergjigjes Emergjente do të mbajnë me vete në çdo kohë listën e telefonit te njoftimeve. Koordinatori I pergjigjes Emergjente ose mëkëmbësi i tij / saj do të fillojnë të kontaktoje me individët dhe agjencitë e mëposhtme brenda 15 minutave të një ngjarje të derdhjes që kërkon përgjigje emergjente. Koordinatori i Reagimit Emergjent do të zbatojë dhe rend e procesit të njoftimit dhe veprimet korrigjuese të bazuar në llojin dhe madhësinë e derdhjes dhe rrezik potencial për burimet dhe shëndetin. Incidenti dhe njoftimet do të dokumentohet në formë të "incidentit dhe njoftimit" Nr. Tittulli Organizativ Numer Kontakti Page 5
  • 7. 1. Menanxheri Projektit 2. Zevendes Menanxheri Projektit 3. Lider I Sigurimit Teknik 4. Pergjegjes I Sigurimit Teknik 5. Menanxheri I Terrenit 5.3. Procesverbali Incidenti Koordinatori i Aksionit Emergjent do të përdori këtë Formular njoftimi formë për të kapur rrethanat te cilat nevojën për zbatimin e Planit të Veprimit dhe Reagimit per Derdhjet dhe njoftimet e bëra. Kjo përfshin: • Data, koha dhe lokacioni I incidentit; • Pershkrimi Incidentit (tipi dhe lloji si dhe rethanat perkatese); • Emrat e individeve te perfshire si dhe kontakten nese ka; • Koha/Data e njoftimit • Pershkrimi I cdo informimi I dhene nga personeli regulator; • Pershkrimi I aksionit te ndermarre, planifikimi ose kompletimi; 5.4. Pajisjet, Makinerite dhe Magazinimi Materialet për përgjigje do të ruhen në vende të shumta, në afërsi të vendeve të punës aktive. Materialet Derdhja do të jetë e pranishëme në vendet aktive të punës, sidomos kur Përfaqësuesi i SSHM ose mbikëqyresi Inxhinieri perfaqesues beson rrezikun e mundshëm të një derdhje apo ndikim në një burim të caktuar (psh, ujore) ekziston. Lokacionet e magazinimit mund të transferohen gjatë projektit të ndërtimit, si elemente të ndryshme nese sheshit të ndërtimit janë përfunduar. Magazinieri I caktuar nga Departamenti Mekanik do të jetë përgjegjës për inventarizimin (tremujore) dhe trajnimin për të siguruar se materialet janë në dispozicion dhe ato të personelit të ndërtimit di ku pajisjet reagimi dhe furnizime janë të vendosura. Materialet e kontrollit te derdhjes do të veçohen (te shënuara) në vende të magazinimit, për të dyja ujërat sipërfaqësore apo situatat me bazë në tokë. Magazinimi I materialeve perfshin; Fuci celiku ose plastike (200 litra), me kapak, për vendosjen e lendeve te derdhura Plasmas per tu vendosur ne toke ne rast derdhe Tallash Druri Pompe thithese per parandalimin e rrjedhjeve derdhjeve te lendeve te rrezikshme ne situate publike Sfungjer plasmas per te thither lendet e rrezikshme nese ato jane derdhur ne lumenj gropa uji etj Dorashka gome per personelin Page 6
  • 8. Lopata Eskavator emergjent si pjese e aksionit 5.5. Suporti Emergjent Për situatat që kanë nevojë për mbështetje nga jashtë (zjarr, derdhjet e rëndësishme duke paraqitur rreziqe për shëndetin, ujin, dhe burime të tjera), Koordinatori Emergjences menjëherë do të njoftojë organizatat e mëposhtme dhe të heqë dorë per menaxhimin e incidentit pas mbërritjes së tyre. Koordinatori Emergjences dhe Përfaqësuesi SSHM do të vazhdojnë për të lehtësuar dhe koordinuar me këto organizata në lidhje me përdorimin e burimeve në vend dhe kontrollin. Vendin numrat e urgjencës janë: Departamenti Zjarrfikeses ne Shqiperi: Nr.Kontakti: 128 Departamenti Policise: Nr.Kontakti: 129 5.6. Plani Evakuimit Nevoja për evakuim do t'i komunikohet projektit personelit nëpërmjet Inxhinierëve te terrenit në telefon ose radio kontakt me Koordinatorin e Reagimit Emergjent dhe Përfaqësuesit te SSH&M . Të gjithë të punësuarit e projektit do të fuqizohet për të lehtësuar komunikimin në vend dhe të bashkë-punëtorëve, nëse një incident ndodh,duhet që te garantohet evakuimi. Evakuimi dhe pika mbledhjes do të zhvendoset si puna ndërtimore qe është e përparuar përgjatë shtrirjes; kjo temë do të jetë pjesë e trajnimit fillestar të punonjësve të dhënë nga SSH & M personelit dhe Inxhinierëve te Terrenit.Evakuimi dhe pikat e grumbullimit e gjithashtu mund të zhvendosen në varësi të kushteve të erës (drejtimi i çdo ndotësve ajrore). Pikat e evakuimit kryesore, nëse është e nevojshme, do të jetë në afërsi të aksesit të punës ne terren, por në një anë në mënyrë që të mos bllokojnë pajisjet e emergjencës. pikat e para-planifikuar te grumbullimit, rrugët e evakuimit, dhe rruga per spital do të jetë postuar në zyrat e projektit. 5.7. Objektet e perkoheshme Projekti do të ketë mirëmbajtjen rrethimeve te kantiereve. Lokacionet e zonave të rrezikshme te mbeturinave (materialeve dhe mbetjeve) do te gjurmohen, inspektohen, dokumentohen, dhe do miratohen paraprakisht nga Përfaqësuesi SSHM. Të gjitha materialet dhe baterite e përfshira në këto fusha do të etiketohen dhe përmbajtja e tyre do te identifikohet. Zonat e magazinimit do të jene te mbrojtura nga uji dhe stuhite. Vend magazinimet do te kene sisteme te daljeve emergjente dhe sisteme te cilat ndajne naftën / nga uji. 5.8. Hapat e veprimit Derdhje madhore: Personeli i ndërtimit nese zbulon një derdhje të madhe do të njoftojë mbikëqyresit ose inxhinierin e vendit dhe mund të marrë masa të menjëhershëm që mund të Page 7
  • 9. kryhen pa dëm për shëndetin dhe sigurinë e tyre (p.sh., stakim valvulash, përdorimin e digave,mbrojtja e ujërave sipërfaqësore, luginat, zonat natyrore, dhe brigjet). Inxhinieret e Terrenit menjëherë do të njoftojnë koordinatorin e Reagimit Emergjent dhe Përfaqësuesin e SSH & M. Inxhinieri i vendit do të mbikëqyrë çdo veprime fillestare dhe evakuimin derisa Koordinatori I Reagimit Emergjent te marre masat e duhura. Koordinatori i Emergjences do të vlerësojë situatën, do zbatojë njoftimet, dhe masat e drejtpërdrejta të kontrollit sipas nevojës. Derdhje e vogël: Nese personeli i ndërtimit zbulon një derdhje të vogël (p.sh., automjeteve / pajisjeve rrjedhjen e naftës ose të lëngjeve hidraulike ne tokë apo konkrete) do të njoftojë mbikëqyresit Inxhinieri i terrenit do te marrin masa për të ndaluar derdhjet / rrjedhjet, dhe do të marrë masat për të vendosur materialet e parandalimit te derdhjeve.Inxhinieri i terrenit do të njoftojë brenda 15 minutave SSH & M Përfaqësues i cili do të përgjigjet dhe do të mobilizojë burimet e nevojshme nëse është e nevojshme. Nga përkufizimi, derdhjet e vogla mund të përfshihen në mënyrë të sigurtë në afërsi të derdhjes, nga personeli në vend, dh në dispozicion materialet përgjigje derdhjes (paketimi i absorbuesve, lopata). Këto derdhje nuk kërcënojnë qe te shkaktojë një kërcënim të menjëhershëm për shëndetin e njeriut / ose mjedisin. 5.9. Dokumentacioni Major Spill: Kordinatori Planit te Emergjences si dhe perfaqesuesi I SSH&M(Sigurise Shendetit&Mjedisit)do te perdorinper te dokumentuar rrjedhjet dhe masat e marra ose qe do te merren ne formatin e incidenteve mjedisore sipas Planit te SSHM. Duke vepruar kështu, ata do të mbledhin informacion nga personeli i projektit dhe agjencitë rregullatore vendase. Perfaqesuesit e SSHM do te arvikojne te gjtiha dokumentacionet te cilat do te kene si burime informacioni te gjtha eventet dhe incidentet te shoqeruara me fotografi,deshmitar okular fakte etj. 6 METODAT PER PARANDALIMIN E NDOTJES 6.1. Plani konstruksioneve dhe nenkontraktoret Kërkesat rregullatore dhe praktikat më të mira të menaxhimit, do të përfshihen në planifikimin e ndërtimit dhe ekzekutimin e punës. Planifikuesit e ndërtimit do të jenë te nevojshem për të përfshirë parimet e Sigurise Shendetit dhe Mjedisit SSH & M në planet e tyre të punës, perfaqesuesit e SSH&M do te percaktojne dhe aprovojne te gjitha praktikat te cilat planfikuesit e projekteve do te hartojne ne lidhje me parimet e SSH&M. Per ë gjithë nënkontraktorët do të jetë e nevojshme të përfshijnë parandalimin derdhjes në Planin e tyre te SSH & M, të paraqesin planin e tyre miratim nga kompania KOMPANIA SHPK, dhe të ketë materiale të përshtatshme për parandalimin e derdhjes në vend që të Page 8
  • 10. përputhen me llojin dhe shtrirjen e punës së tyre.Mbikeqyresit perfaqesuesit e Sigurise Mbrojtjes dhe Shendetit si dhe Inxhinierët e terrenit do të monitorojë pajtueshmërinë e tyre per të gjitha zonat e magazinimit të përdorura nga nënkontraktorët. 6.2. Akumulimi dhe pikat e grumbullimit Menaxheri i Projektit do të caktojë një person për të menaxhuar zonat e akumulimit të mbeturinave dhe zonat e magazinimit te materialeve të rrezikshme. Ky person do të sigurojë materialet e duhura për parandalimin e derdhjes të pranishme dhe do të inspektojë periodikisht për të siguruar që zonat: • Jane te organizuara ne menyre te sigurt; • Jane te siguruara per shuarjen e zjarrit me Fikes portative; • Qe sistemet e kanalizimeve dhe drenazhimeve jane ne gjendje te mire; • Kane aksesin e duhur per inspektim; Zonat akumulimit të mbeturinave do të kenë një sipërfaqe të papërshkueshme pa të çara. Akumulimi dhe ruajtja e zonave do të kontrollohet zonat me qasje të kufizuar. 6.3. Koshat dhe kontinieret Koshat dhe kontinieret te cilet do te permbajne mbeturina te rrezikshme do te jene: • Ne gjendje te mire fizike (Pa carje, jo te degraduar); • Te perdorshem me mbetje te cilat nuk demtojne permbajtjen e tyre; • Te levizshem me mjetet dhe menyra te sigurta; 6.4. Perdorimi I pajisjeve dhe mirembajtja e tyre Pajisje në vendet e punës mund të jenë një burim potencial i derdhjeve te vogla. Metodat e parandalimit përfshihenë si në vijim: • Pajisjet dhe mjetet do te mirembahen ne menyre periodike, so dhe do te inspektohen per rrjedhje te mbetjeve te naftes vajit etj. • Kontrollet e erozionit do të përdoret në faqet e perimetrit ne terren, duke ndihmuar për të menaxhuar tokën dhe rrjedhjet e ujit stuhite dhe në këtë mënyrë lëvizjen e çdo materiali te derdhur ose hedhur Page 9
  • 11. 6.5. Ekzekutimi I punes Menyra te ndryshme te cilat do te ndihmojne parandalimin e derdhjeve te lendeve te ndryshme; • Mbulimi dhe kullimi ne gropat e hapura pergjate punes dhe ne te cilat jane perfshire material te rrezikshme; • Materiale per te mbuluar rrjedhjet, derdhjet ne rast se ndodhin te tilla; • Te korrdinohen punimet ne menyre te tille qe potenciali per infektimin e ujrave ne zonat prane punimeve te zvogelohet; • Te gjendet materiali dhe te jete prezent per kontaminimin e rrjedhjeve perpara punimeve nese mendohet se do te kete rrjedhje ose derdhje te mbetjeve te rrezikshme; • Te zvogelohen metodat e perdorimit te materialeve te rrezikshme duke planifikuar punime me material sa me pak te rrezikshme; • Te planifikohen vendet ne te cilat do te behet larja e mbetjeve te betonit si Batonieret etj; • Te mirembahet vendi I punes dhe te pastrohet periodikisht; 6.6 Transporti Perpara transportimit ose marrjen e kontenierë, ato duhet të kontrollohen për të konfirmuar integritetin strukturor për rrjedhje dhe derdhje të mundshme. Ato gjithashtu duhet të etiketohen siç duhet dhe të jene te mbyllura, te përmbajnë material të përshtatshëm për llojin e veçantë të tyre. Materiali i mbeturinave duhet të shfaqet si duhet, gjurmuar, dhe hidhen në një vend te miratuar; . 7 KONTROLLI DHE KUNDERMASAT 7.1. Rjedhjet e lendeve djegese • • Siguria mbi te gjitha. Per shmangjen e avujve duke qendruar kunder eres do te perdoren pajisje per rezistence ndaj lendeve kimike si;(doreza, cizme, syze mbrojtese). • Pergjate perdorimit te benzines duhet te shmangen bisedat telefonike me telefona celular, ndezja e flakeve, perdorimi duhanit etj. • Ne rast se derdhje te medha te lendeve djegese derdhen ne terren duhet te lajmerohen perfaqesuesit e SSHM sigurise shendetit dhe mjedisit dhe ne vend do te ndalohet qarkullimi duke e rrethuar me shirit sinjalizues. 7.3. Rrjedhjet Kimike acid, dylent etj) • Siguria mbi te gjithe. Per shmangjen e avujve duke qendruar kunder eres do te perdoren pajisje per rezistence ndaj lendeve kimike si;(doreza, cizme, syze mbrojtese). Page 10
  • 12. • Duhet te ndalohet burimi I rrjedhjes duke e izoluar ate sa me shpejt te jete e mundur me praktika te sigurta. Te lajmerohet administrator mjedisor Brenda 15 minutave. • Duke u referuar tek te dhenat e materialeve te cilat gjenden ne rregjistrat e magazinimit ne ndermarjen Kompania, per cdo rrezik te specifikuar do te perdoren procedurat e duhura per lendet kimike. • Ato duhen te magazinohen ne kontinieret e duhur jo me shume se 180 dite kalendarike. • If temporarily stored, place containers in the waste accumulation area for no more than 180 days. • Per rrjedhje t emundeshme do te perdoret Raporti I rrjedhjeve si dhe raporti incidenteve referuar Planit te SSHM Sigurise Shendetit dhe Mjedisit. 8 INSPEKTIMET DHE RREGISTRI I TYRE 8.1. Plani I shperndarjes Një kopje e këtij plani do të shpërndahet për çdo inxhinier terreni dhe nënkontraktoreve te ndërtimit që do te punojnë në vend. Një kopje do të jenë në dispozicion në çdo zyrë në terren. 8.2. Monitorimi dhe Inspektimi Përfaqësuesi i SSH & M do të inspektojë dhe të kryejnë monitorimin e sigurimit të cilësisë të të gjitha zonave të punës dhe vendeve me karburant ose magazinimit të rrezikshm të mbeturinave / materiale, në minimum, në baza javore dy dhe në përputhje me procedurat e përshkruara në Planin e Ndërtimit Mjedisor të projektit të Kontrollit (PPKNM).Kushtet dhe ndjekja mbahet në objektin e magazinimit dhe gjithashtu të përshkruara në raportin mujor SSH & M. Çdo veprime korrigjuese që janë të nevojshme do të sillen në vëmendjen e mbikëqyrës inxhinierit në të njëjtën ditë për zgjidhjen e shpejtë. Përfaqësuesi i SSH & H do të raportojë te gjtiha tendencat e vërejtura dhe mësimet e nxjerra në lidhje me potencialin për një ngjarje derdhje, ose kontrollin joadekuate, tek Menaxheri i Projektit i cili do të japë drejtimin brenda forcës së punës ndërtimore për veprimet korrigjuese dhe ndryshimet. Çdo Përgjegjës I caktuar në një zonë të ndertimit, mirëmbajtjes, ose zonën e punës do të jetë përgjegjës për inspektimin e përditshm për shenjat e derdhjet dhe siguruar që daljet efektive për parandalimin dhe kontrollin e derdhjes. Cdo pergjegjes do të raportojnë çdo veprime te nevojshme apo probleme të përsëritura tek mbikëqyrësi I inxhinierit te terrenit. Në mënyrë të ngjashme, Inxhinierët e terrenit dhe nënkontraktorët gjithashtu do të jetë përgjegjës për të vëzhguar dhe duke marrë parasysh të gjitha derdhjet në zonat e tyre të punës, përshtatshmërinë e kufizimit dhe parandaluese masa, dhe duke marrë çdo veprim të nevojshem. 8.4. Agjencitë rregullatore Page 11
  • 13. Përfaqësuesi i SSH & M do të shoqërojë çdo inspektorë nga agjencitë rregullatore. Kjo mund të përfshijë Agjencinë për Mbrojtjen e Mjedisit apo zjarrfikësit. Një përfaqësues i ekipit të menaxhimit të ndërtimit, të përcaktuar nga Menaxheri i Projektit, do të marrë pjesë në çdo inspektime të tille rregullatore; në mënyrë që veprimet korrigjuese të zbatohen në kohën e duhur siç përshkruhet nga personeli rregullator. Menaxheri i Projektit do të transmetojë çdo dokumentacion të kërkuar nga personeli rregullator. Lideri I SSH & M dhe përfaqësuesit do të mbajnë të dhënat, në dosje, të gjitha inspektimet e rregullatoreve dhe korrespondencat. 8.5. Rregjistri Siç përshkruhet në më sipër, Përfaqësuesi i SSH & M do të mbajë shënime, kopje të ngjarjeve derdhjes, inspektimet e përputhshmërisë, deponimin e mbeturinave, dhe korrespondencë rregullator për referencës dhe shqyrtim qëllime siç kërkohet. 9 TRAJNIMI I gjithë personeli ndërtimit në vend të punës duhet të marrin pjesë në trajnimet formale te Mjedisit, Sigurisë dhe Shëndetit (ES & H) në fillim të detyrës së tyre. Ky trajnim përfshin parandalimin dhe kontrollin e derdhjes. Bisedimet ne terren do të përdoret në javë gjatë periudhës së ndërtimit si pjese freskuese e trajnimit SSH & M ES & H. Lideri I Sigurise Shendetiti dhe Mjedisit SSH & M i do të jetë përgjegjës për përgatitjen e materialeve te trajnimit, mbajtjen e shënimeve të të gjithë pjestareve të trajnuar. Përfaqësuesi i SSH & M do të jetë përgjegjës për zhvillimin e dokumenteve specifike të trajnimeve mjedisore dhe materialeve, postimi i fletëve udhëzuese per vetëdijen, dhe postimi I listave e njoftimit në vende të dukshme në zyrat në terren. Punonjësit e kompanise, si pjesë e trajnimit te SSH & M, do të jepet drejtimi për të sjellë në vëmendjen e mbikëqyrësit të tyre çdo kusht që ka potencial të jetë një rrezik mjedisor ose rrezik për shëndetin dhe sigurinë ose rrezik - dhe për të marrë veprimet e nevojshme. Kjo përfshin parandalimin dhe kontrollin e derdhjes. SSH & M do të jetë një pjesë e pandarë dhe e pritshme e kulturës ne vendin e punës. Të gjithe Inxhinierëte Terrenit do të jetë e nevojshme për të marrë pjesë në trajnime të vazhdueshme dhe takimeve të rregullta të fokusuara në aspektet e hollësishme te SSH & M per zbatimin e programit. Kjo përfshin parandalimin dhe kontrollin e derdhjes, dhe menaxhimin e mbeturinave të rrezikshme. Trajnimi do paraqese fuqine punëtore në ndryshim (personelin dhe numrin e personelit) dhe metodat e ndërtimit gjatë periudhës së ndërtimit. Korrdinatori I pergjigjes emergjente si dhe personeli I perfshire per parandalimin e rrjedhjeve do te kene nje trajnim te avancuar specific per rrjedhjet dhe trajtimin e tyre,si dhe menanxhimin e mbetjeve te rrezikshme. _________________________________________________________________________ SHTOJCAT (Formularet): Page 12
  • 14. 1. Formulari Incidenti dhe Lajmerimi 2. Formulari I raportimit te rrjedhjeve 3. Orientim per perdorimin e pajisjeve dhe materialeve kunder rrjedhjeve 4. Iventarizimi I mbeturinave te rrezikshme 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. 5. Formulari I inpektimeve mujore per magazinimin e mbeturinave te rrezikshme 10 GRUPI I PERGJIGJES EMERGJENTE (organigram) Page 13 Emergency Response Organogram Team. Foreman / Team lead HSE Manager/Lead Site Engineer Ambulance-112 Police -129 Fireman -128 HOSPITAL Deputy Manager
  • 15. 11. GRUPI I NDIHMES SE PARE Perfaqesuesit e SSH & M do te jene te disponueshem per cdo keshillim dhe suport tek te gjithe pjestaret pergjegjes per ndihmen e pare ne terren. Përkufizimi i "ndihmës së parë", "një person i cili do të ketë nevojë për ndihmë nga një mjek apo infermier, trajtim me qëllim të ruajtjes së jetës dhe të minimizuar pasojat e lëndimit dhe sëmundje deri në ndihmë të tillë është marrë" • Procedura do te mbuloje’’trajtimin e lendimeve te vogla te cilat perndryshe do te marrin trajtim ose qe nuk kane nevoje per trajtim nga mjeket apo infermjeret’’ • Menaxhimi fillestar i ndonjë lëndimi apo sëmundje pësuar në punë të kryera, Ndihma e parë duhet të bëhet shpejt dhe nga një person kompetent. • Pajisjet e sinjalizuara me Kryqin E kuq do të jenë në vend për të lehtësuar shpejtë vëmendjen e ndihmesit te pare dhe kujdes i cili nga ana e tij do të shpëtoje jetën dhe do të parandaloje dëmtimet e lehta per duke u bërë demtime te medha. • Ndihma e pare nuk do te perfshije ilace dhe medikamente te cilat nuk do te jene miratuar nga nje mjek kompetent I cili me pare duhet te trajnoje personat e ndihmes se pare. • Nje person kompetent dhe pergjegjes per dhenjen e ndihmes se pare duhet te plotesoje kushtet ne vijim; 1) Kualifikimi per te qene nje person pergjegjes per ndihmen e pare duhet te kete kryer trajnimin nga Kryqi iKuq 1 dite trajnim per cdo 3 vite. 11.1 INDENDIFIKIMI • Identifikimi I personave qe japin ndihmen e pare ne terren do te behet behet duke u ngjitur nje stiker nje shenje te kryqit te kuq ne helmeten ose jelekun e punonjesit. Keto sinjalistika do te vihen ne dispozicion nga departamenti mekanik I kompanise. • Kutite e ndihmes se pare duhet te jene Brenda standarteve te bashkimit europian. Page 14
  • 16. • Dhomat per dhenien e ndihmes se pare do te sinjalizohen tek porta ne hyrje me shenjen e kryqit te kuq. • Pikat emergjente do te indentifikohen ne nje plan evakuimi per cdo zyre ose kantier te kompanise. • PROCEDURA TE PERGJITHSHME • Punonjesit do te keshillohen per procedurat (perfshire dhe ndihmen e pare) pergjate instruktimit periodic te tyre. • Radio marresit do te perdoren si dhe telefonat cellular nese kontaktet e organizimit emergjent do te afishohen ne terren. • Personi per korrdinimin e situatave mjekesore do te kete si bashkepunim Policine dhe autoritet emergjente, zjarrfikesit, ambulance etj. • Perfaqesuesit e SSH & M do te keshillohen nga autoritet emergjente per cdo situate te padeshiruar. • Para fillimit të punës psh gjatë kartë induksioneve orientuese per projekte te ndryshme, punonjësit duhet të këshillohen i cilet jane personat kompetent per ndihmen e pare si dhe ku do te ndodhen/ kutite më te afërta te ndihmës së parë.) Inxhinieret e terrenit do te orientohen nga departamenti Sigurise Shendetit & Mjedisit se ku do te kerkojne ndihme ne spitalet dhe pikat me te aferta mjekesore per cdo situate te paparashikuar. MBYLLJE Programet e kompanise sone ne lidhje me Sigurine Shendetin & Mjedisin jane hartuar ne menyre te tille qe te parandalojne aksidentet. Page 15
  • 17. Bashkepunimi juaj I sinqerte eshte shume I rendesishem per tu zbatuar 100% planet tona per SIGURINE. Raportoni tek departamenti I Sigurise cdo sjellje te rrezikshme te cilat mund te parandaloje aksidente qe do te shpetonin JETE. Kompania jone eshte shume krenare por do te vazhdje punen per te zvogeluar sa me shume incidentet/aksidentet te cilat kushtojne jete njerezish dhe shume per mjedisin. Ndihma juaj do te ishte nje Bonus per te gjtihe ne. Page 16