SlideShare a Scribd company logo
1 of 60
CABLE LAYOUT
CONTINUOUS BEAM
LOAD BALANCING METHOD
1/24/2014

1
Group 5B











Arafat Hossain
Sadik Hasan
Sadia Mahajabin
Raihan Mannan
Sadia Mannan
Tanvir Alam
Ikhtiar Khan
Ifat Hasan Shawon
Md. Asif Rahman
Sarani Reza

1/24/2014

10.01.03.096
10.01.03.097
10.01.03.098
10.01.03.101
10.01.03.102
10.01.03.104
10.01.03.106
10.01.03.107
10.01.03.108
10.01.03.110
2
1/24/2014

3
What is Cable Layout
 Cable : A strong thick rope, usually twisted hemp or wire

 Layout : The arrangement or plan of something

1/24/2014

4
Simple Beam Layout
 Simple Beam: a structural beam that rests on a support

at each end

 Simple Beam can be two types :

1. Pretensioned
2. Posttensioned

1/24/2014

5
 Pre-tensioning : When the steel is tensioned before concrete
placement, the process is called pre-tensioning.

 Post-tensioning : When the steel is tensioned after concrete
placement, the process is called post-tensioning.

1/24/2014

6
Layouts for pre-tensioned beam
1. Straight cables are preferred since they can be more
easily tensioned between two abutments.
2. Such a section can not often economically designed
because of conflicting requirements of the midspan and
end section.
3. At the maximum moment section generally occuring at
mid span, it is best to place the cable as near to the
bottom as possible.
4. Since there is no external moment at the end it is best to
arrange the tendons so that c.g.s will coincide with c.g.c

1/24/2014

7
Bent Soffit

Curved Soffit

1. For both layouts c.g.s at mid span can be depressed as low as desired.
2. The end can be kept near c.g.c

1/24/2014

8
Bent Extrados

Curved Extrados

1. When it is possible to vary the extrados of concrete it can be advantageously
used.
2. These will give a favorable height at mid span where it is most needed and yet
yield a concentric or nearly concentric prestress at end section.
3. (d) is simpler in formwork than (e).

1/24/2014

9
1. Most pretensionning plans in USA have buried anchores along the stressing
bed so that tendons for a pretensioned beam can be bent.
2. It may be economical to do so if the beam has to be of straight and uniform
section.

1/24/2014

10
Layouts For Post tensioned Beam

1. Most of the layouts for pre tensioned beams can be used for post
tensioned once as well.
2. For a beam of straight and uniform section the tendons are very often
curved.
3. Curving the tendons will permit favorable position of c.g.s to be
obtained at both the end and mid span sections and other points as
well.

1/24/2014

11
combination of curved tendons with curved
soffits

1. A combination of curved tendons with curved soffits is frequently used
when straight soffits are not required.
2. This will permit a smaller curvature in tendons thus reducing the friction.

1/24/2014

12
1. Curved or bent cables are also combine with beams of variable depth.

1. Combination of straight and curved tendons are sometimes found convenient.

1/24/2014

13
1. Some cables are bent upwards and anchored at the top flanges.

1. Some cables are stopped part way in the bottom flange.
2. This arrangements will save some steel but may not be justified unless
the saving is considerable as for very long span carrying heavy loads.

1/24/2014

14
Cantilever Beam
 A cantilever is a beam anchored at only one end. The beam carries the

load to the support where it is forced against by a moment and shear
stress.

 Two general layouts are possible for cantilevers :

1.Single Cantilevers
2. Double Cantilevers
1/24/2014

15
LAYOUTS FOR SINGLE CANTILEVER

1. For a short span with a short cantilever a straight and uniform section may be
the most economical.
2. It is only necessary to vary the c.g.s profile so that it will confirm with the
requirements of the moment diagrams.

1/24/2014

16
1. When the cantilever span become longer it is advisable to taper the beam.
2. If the anchore span is short compared to the cantilever it may be entirely
subjected to the negative moments and the c.g.s may have to be located
above the c.g.c

1/24/2014

17
1. For longer span it may be desirable to haunched them.
2. The c.g.s profile can be properly curved or may remain practically
straight.
1/24/2014

18
Layouts for double cantilever

1. For short double cantilevers a straight and uniform section can be adopted.

1. When the cantilevers are long they may be tapered.
1/24/2014

19
1. If the anchor span is long it may be haunched.

1. If the anchor span is short compared with the cantilevers the c.g.s
line may lie near the top of the beam.

1/24/2014

20
CONTINIOUS BEAM

1/24/2014

21
CONTINUOUS BEAM
A Continuous beam is one, which is
supported on more than two supports.
For usual loading on the beam

hogging ( -ve ) moments causing
convexity upwards at the supports
and sagging ( +ve ) moments causing
concavity upwards occur at mid span.
1/24/2014

22
ASSUMPTIONS OF CONTINUOUS
BEAM
1. The ecentricities of the

1/24/2014

prestressing cable are small
compared to length of the
members.
2. Frictional loss of prestress is
negligible.
3. The same tendons run through
the entire length of the member.

23
Advantages of Continuous Beam
Over Simply Supported Beam
 The maximum bending moment in case of

continuous beam is much less than in case of
simply supported beam of same span carrying same
loads.
 In case of continuous beam, the average bending
moment is lesser and hence lighter materials of
construction can be used to resist the bending
moment.
1/24/2014

24
COMPARING OF LOAD
CARRYING CAPACITY BETWEEN
SIMPLY SUPPORTED BEAM AND
CONTINIUOUS BEAM

1/24/2014

25
LOAD CARRYING CAPACITY OF
SIMPLE BEAM

1/24/2014

26
LOAD CARRYING CAPACITY OF
SIMPLE BEAM

1/24/2014

27
LOAD CARRYING CAPACITY OF
CONTINUOUS BEAM

1/24/2014

28
LOAD CARRYING CAPACITY OF
CONTINUOUS BEAM

1/24/2014

29
DISADVANTAGES OF CONTINUOUS BEAM

1. Frictional loss is significant
2. Shortening of long continuous
beam under prestress.
3. Concurrence of maximum moment
and shear over support.
4. Difficulties in achiving continuity
for precast elements.
1/24/2014

30
CABLE LAYOUT OF
CONTINUOUS BEAM

1/24/2014

31
Curbed Tendon In Straight Beam

•This lay out is often used for slabs or short span
beams
•The main objections here are the heavy frictional
loss
1/24/2014

32
Straight Tendon In Curbed
Beam

•Used for longer span and heavier loads.
•Often difficult to get the optimum eccentricities

along the beam if the tendons are to remain entirely
straight
1/24/2014

33
Curbed Tendon In Haunched Or
Curbed Beams

•This would permit optimum depth of beam as well as

ideal position of steel at all points,aboidin excessive
frictional loss.
1/24/2014

34
Overlapping Tendons

•Offer a possibility of varying prestressing force along

the beam

1/24/2014

35
Determination Of Resisting
Moment Of Continuous Beam
1. Plot the primary moment diagram for the entire

continuous beam as produced only by pre-stress
eccentricity. As if there were no support to the beam.
2. Plot shear diagram.
3. Plot loading diagram.
4. Plot moment diagram corresponding to loading diagram
considering all support.

1/24/2014

36
1/24/2014

37
1/24/2014

38
Load Balancing Method
 Load in the concrete is balanced by stressing the steel.

In the overall design of prestressed concrete
structure, the effect of prestressing is viewed as the
balancing of gravity load . This enables the
transformation of a flexural member into a member
under direct stress and thus greatly simplifies both the
design and analysis of structure.
 The application of this method requires taking the
concrete as a free body and replacing the tendons with
forces acting on the concrete along the span.

1/24/2014

39
Concept of Load Balancing Method
 There are three basic concepts in prestressed concrete

design
1. Stress concept : Treating prestressed concrete as an
elastic material
2. Strength concept: Considering prestressed concrete as
reinforced concrete dealing with ultimate strength.
3. Balanced load concept: Balancing a portion of the load
on the structure.
Load Balancing method follows the third one.
1/24/2014

40
Life History Of Prestressed
Member
 Analysing the life history of the prestressed member

under flexure leads to understanding the balanced load
concept relative to other two concept.
 So lets find out the load deflection relationship of a
member as a simple beam..

1/24/2014

41
 K1 = Factor of

safety applied to
working load to
obtain minimum
yield point.
 K2= Factor of

safety applied to
ultimate strength
design to obtain
minimum ultimate
load.
1/24/2014

42
 The load deflection relationship of the above figure

leads to several critical points. Such as..
 1. Point of no deflection which indicates rectangular
stress block.
 2. Point of no tension which indicates triangular stress

block with zero stress at the bottom fiber.


1/24/2014

43
3. Point of cracking which occurs when the extreme fiber
is stressed to the modulus of rupture.
4. Point of yielding at which steel is stressed beyond its
yield point so that complete recovery is not possible.
5. Point of ultimate load which represents the
maximum load carried by the member at failure.

1/24/2014

44
Mechanism & Explanation Of
Balanced load Concept
According to figure there are three stages of beam
Behavior :
Applied Loadings

Stages of beam behavior

 DL+k3LL

 No deflection

 DL+LL

 No tension

 K2(DL+LL)

 Ultimate

1/24/2014

45
 Where,
 DL+LL is the stress concept with some allowable

tension on beam or no tension.
 K2(DL+LL) is the strength concept consists with the
ultimate strength of the beam.
 DL+K3LL is the balanced load concept with the point
of no deflection where k3 is zero or some value much
less than one.

1/24/2014

46
 In balanced load concept design is done by point of no

deflection.
 So prestressing is done in such a way so that effective
prestress balances the sustained loading & beam
remain perfectly level without deflecting.

1/24/2014

47
ADVANTAGES OF LOAD BALANCING
METHOD
 1.simplest approach to prestressed design and
analysis for statically indeterminate structures.
 2.It has advantages both in calculating and in
visualizing.

 3.Convenience in the computation of deflections.

1/24/2014

48
SIMPLE & CANTILEVER BEAM
WITH LOAD BALANCING
METHOD

Figure illustrates how to balance a concentrated load
by sharply bending the c.g.s. at midspan , thus creating
an upward component
V=2Fsinθ

1/24/2014

49
 If V exactly balances a concentrated load P

Applied at midspan the beam is not subjected to any
transverse load.
The stresses in the beam at any section are simply given
by

Any loading addition to P will cause bending and
additional stresses computed by

1/24/2014

50
 Figure illustrates the balancing of a uniformly

distributed load by means of a parabolic cable
whose upward component is given by

1/24/2014

51
 If the externally applied load w is exactly balanced by

the component Wb there is no bending in the beam.
The beam is again under a uniform compression with
stress

External load produced moment M and corresponding
stresses

1/24/2014

52
 Figure represents a cantilever beam. Any vertical

component at the cantilever end C will upset the
balance, unless there is an externally applied load at
that tip.
1/24/2014

53
 To balance a uniform load w, the tangent to the c.g.s. at

C will have to be horizontal. Then the parabola for the
cantilever portion can best be located by computing

And the parabola for the anchor arm by

1/24/2014

54
EXAMPLE PROBLEM OF
CANTILEVER BEAM
 A double cantilever beam is to be designed so that its

prestress will exactly balance the total uniform load of 23.3
KN/m normally carried on the beam. Design the beam
using the least amount of prestress, assuming that the c.g.s
must have a concrete protection of at least 76.2mm. If a
concentrated load of 62KN is added at the mid span
compute the maximum top and bottom fiber stresses

1/24/2014

55
SOLUTION:
To use the least amount of prestress, the ecentricity over the
support should be a maximum that is , h=300mm or o.3m.
The prestress required is F = wL2 / 2h
=(23.3x62)/(2x0.300)=1395KN
The sag for the parabola must be h1
= w(L1)2/8F
=(23.3x14.82)/(8*1395)
=0.46m

1/24/2014

56
Uniform compressive stress
f= F/Ac = 1395/(2.28x105) = 6.12 Mpa
Moment M at the mid span due to P=62KN
M=PL/4=(62x14.8)/4=229KN-m
Extreme fiber stresses are
f=Mc/I=6M/bd2 = (6x229x106)/(300x7602)
= 7.93MPa
Stress at mid span are
ftop = -6.12-7.93=-14.05MPa compression
f bottom = -6.12+7.93 =+1.81 MPa tension
1/24/2014

57
EXAMPLE PROBLEM OF
CONTINUOUS BEAMS:
 For the symmetrical continuous beam prestressed
with
F= 1420KN along a parabolic cable as
shown, compute the extreme fiber stresses over the

center support DL+LL=23.0KN/m

1/24/2014

58
SOLUTION:
The upward transverse component of prestress is
Wb= 8Fh/L2 = (8x1420x0.3)/(15x15)=15.1KN/m
The beam is balanced under uniform stress
f= (1420x103)/(300x760)= -6.2MPa
For applied load w=23.0 KN/m, the unbalanced
downward load = (23.0-15.1) = 7.9 KN/m
This load produces a negative moment over the center
support, M= wl2/8 =(7.9x152)/8 = 222KN-m
And fiber stresses, f = Mc/I = (6x222x106)/(300x7602)
=
7.68 Mpa
ftop = -6.2+7.68=+1.48MPa tension
f bottom = -6.2-7.68 =+13.88 MPa compression
1/24/2014

59
1/24/2014

60

More Related Content

What's hot

Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
9833356555
 

What's hot (20)

Introduction to prestressed concrete structures
Introduction to prestressed concrete structuresIntroduction to prestressed concrete structures
Introduction to prestressed concrete structures
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Stiffness method of structural analysis
Stiffness method of structural analysisStiffness method of structural analysis
Stiffness method of structural analysis
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
 
4. Shallow Foundations
4. Shallow Foundations4. Shallow Foundations
4. Shallow Foundations
 
Design of Doubly Reinforced Beam
Design of Doubly Reinforced BeamDesign of Doubly Reinforced Beam
Design of Doubly Reinforced Beam
 
Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
design philosophy in structure design in civil engineering
design philosophy in structure design in civil engineeringdesign philosophy in structure design in civil engineering
design philosophy in structure design in civil engineering
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Structural analysis 2
Structural analysis   2Structural analysis   2
Structural analysis 2
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
 
Moment Distribution Method
Moment Distribution MethodMoment Distribution Method
Moment Distribution Method
 
Combined footings
Combined footingsCombined footings
Combined footings
 
Lecture 2 bearing capacity
Lecture 2 bearing capacityLecture 2 bearing capacity
Lecture 2 bearing capacity
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failures
 

Similar to Cable Layout, Continuous Beam & Load Balancing Method

Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
vijayvijay327286
 

Similar to Cable Layout, Continuous Beam & Load Balancing Method (20)

Design of Prestressed Concrete - <topic>
Design of Prestressed Concrete  - <topic>Design of Prestressed Concrete  - <topic>
Design of Prestressed Concrete - <topic>
 
Design and fabrication of pneumatic loaded simply supported beam apparatus
Design and fabrication of pneumatic loaded simply supported beam apparatusDesign and fabrication of pneumatic loaded simply supported beam apparatus
Design and fabrication of pneumatic loaded simply supported beam apparatus
 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
 
CE 72.52 - Lecture6 - Member Behavior
CE 72.52 - Lecture6 - Member BehaviorCE 72.52 - Lecture6 - Member Behavior
CE 72.52 - Lecture6 - Member Behavior
 
Prsesntation on Commercial building Project
Prsesntation on Commercial building ProjectPrsesntation on Commercial building Project
Prsesntation on Commercial building Project
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
 
RCD-Lecture 6-4.pdf
RCD-Lecture 6-4.pdfRCD-Lecture 6-4.pdf
RCD-Lecture 6-4.pdf
 
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
 
COMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdfCOMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdf
 
PSC Lecture PPT.pdf
PSC  Lecture PPT.pdfPSC  Lecture PPT.pdf
PSC Lecture PPT.pdf
 
RECTANGULAR BEAM BY W.S.D SINGLE & DOUBLE REINFORCED STRUCTURES
RECTANGULAR BEAM BY W.S.D SINGLE & DOUBLE REINFORCED STRUCTURESRECTANGULAR BEAM BY W.S.D SINGLE & DOUBLE REINFORCED STRUCTURES
RECTANGULAR BEAM BY W.S.D SINGLE & DOUBLE REINFORCED STRUCTURES
 
4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdf4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdf
 
Effect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionEffect of creep on composite steel concrete section
Effect of creep on composite steel concrete section
 
Deflection of Beams.pptx......pptx
Deflection of Beams.pptx......pptxDeflection of Beams.pptx......pptx
Deflection of Beams.pptx......pptx
 
Compression_members1.ppt
Compression_members1.pptCompression_members1.ppt
Compression_members1.ppt
 
Intze PPT
Intze PPTIntze PPT
Intze PPT
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
Presentation Slides
Presentation SlidesPresentation Slides
Presentation Slides
 

More from Md Tanvir Alam

Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
Gasification Performance Improvement of Treated SRF Residue by Using Minerals...Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
Md Tanvir Alam
 
A study on fixed bed gasification of treated solid refuse fuel residue
A study on fixed bed gasification of treated solid refuse fuel residueA study on fixed bed gasification of treated solid refuse fuel residue
A study on fixed bed gasification of treated solid refuse fuel residue
Md Tanvir Alam
 
Study on a fixed bed gasification of polyurethane SRF from electronic waste
Study on a fixed bed gasification of polyurethane SRF from electronic wasteStudy on a fixed bed gasification of polyurethane SRF from electronic waste
Study on a fixed bed gasification of polyurethane SRF from electronic waste
Md Tanvir Alam
 
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
Md Tanvir Alam
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
Md Tanvir Alam
 
Roadway Condition Survey
Roadway Condition SurveyRoadway Condition Survey
Roadway Condition Survey
Md Tanvir Alam
 
T-Beam Design by WSD Method
T-Beam Design by WSD MethodT-Beam Design by WSD Method
T-Beam Design by WSD Method
Md Tanvir Alam
 

More from Md Tanvir Alam (11)

Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
Gasification Performance Improvement of Treated SRF Residue by Using Minerals...Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
Gasification Performance Improvement of Treated SRF Residue by Using Minerals...
 
A study on fixed bed gasification of treated solid refuse fuel residue
A study on fixed bed gasification of treated solid refuse fuel residueA study on fixed bed gasification of treated solid refuse fuel residue
A study on fixed bed gasification of treated solid refuse fuel residue
 
Gasification of solid refuse fuel in a fixed bed reactor
Gasification of solid refuse fuel in a fixed bed reactorGasification of solid refuse fuel in a fixed bed reactor
Gasification of solid refuse fuel in a fixed bed reactor
 
Biomass gasification for hydrogen production
Biomass gasification for hydrogen productionBiomass gasification for hydrogen production
Biomass gasification for hydrogen production
 
Study on a fixed bed gasification of polyurethane SRF from electronic waste
Study on a fixed bed gasification of polyurethane SRF from electronic wasteStudy on a fixed bed gasification of polyurethane SRF from electronic waste
Study on a fixed bed gasification of polyurethane SRF from electronic waste
 
MSW to Energy Using Thermal Conversion Process
MSW to Energy Using Thermal Conversion ProcessMSW to Energy Using Thermal Conversion Process
MSW to Energy Using Thermal Conversion Process
 
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
Characteristics of Bottom Ash Produced from Fixed Bed and Bubbling Fluidized ...
 
Municipal Solid Waste (MSW) to Energy
Municipal Solid Waste (MSW) to EnergyMunicipal Solid Waste (MSW) to Energy
Municipal Solid Waste (MSW) to Energy
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
Roadway Condition Survey
Roadway Condition SurveyRoadway Condition Survey
Roadway Condition Survey
 
T-Beam Design by WSD Method
T-Beam Design by WSD MethodT-Beam Design by WSD Method
T-Beam Design by WSD Method
 

Recently uploaded

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 

Recently uploaded (20)

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 

Cable Layout, Continuous Beam & Load Balancing Method

  • 1. CABLE LAYOUT CONTINUOUS BEAM LOAD BALANCING METHOD 1/24/2014 1
  • 2. Group 5B           Arafat Hossain Sadik Hasan Sadia Mahajabin Raihan Mannan Sadia Mannan Tanvir Alam Ikhtiar Khan Ifat Hasan Shawon Md. Asif Rahman Sarani Reza 1/24/2014 10.01.03.096 10.01.03.097 10.01.03.098 10.01.03.101 10.01.03.102 10.01.03.104 10.01.03.106 10.01.03.107 10.01.03.108 10.01.03.110 2
  • 4. What is Cable Layout  Cable : A strong thick rope, usually twisted hemp or wire  Layout : The arrangement or plan of something 1/24/2014 4
  • 5. Simple Beam Layout  Simple Beam: a structural beam that rests on a support at each end  Simple Beam can be two types : 1. Pretensioned 2. Posttensioned 1/24/2014 5
  • 6.  Pre-tensioning : When the steel is tensioned before concrete placement, the process is called pre-tensioning.  Post-tensioning : When the steel is tensioned after concrete placement, the process is called post-tensioning. 1/24/2014 6
  • 7. Layouts for pre-tensioned beam 1. Straight cables are preferred since they can be more easily tensioned between two abutments. 2. Such a section can not often economically designed because of conflicting requirements of the midspan and end section. 3. At the maximum moment section generally occuring at mid span, it is best to place the cable as near to the bottom as possible. 4. Since there is no external moment at the end it is best to arrange the tendons so that c.g.s will coincide with c.g.c 1/24/2014 7
  • 8. Bent Soffit Curved Soffit 1. For both layouts c.g.s at mid span can be depressed as low as desired. 2. The end can be kept near c.g.c 1/24/2014 8
  • 9. Bent Extrados Curved Extrados 1. When it is possible to vary the extrados of concrete it can be advantageously used. 2. These will give a favorable height at mid span where it is most needed and yet yield a concentric or nearly concentric prestress at end section. 3. (d) is simpler in formwork than (e). 1/24/2014 9
  • 10. 1. Most pretensionning plans in USA have buried anchores along the stressing bed so that tendons for a pretensioned beam can be bent. 2. It may be economical to do so if the beam has to be of straight and uniform section. 1/24/2014 10
  • 11. Layouts For Post tensioned Beam 1. Most of the layouts for pre tensioned beams can be used for post tensioned once as well. 2. For a beam of straight and uniform section the tendons are very often curved. 3. Curving the tendons will permit favorable position of c.g.s to be obtained at both the end and mid span sections and other points as well. 1/24/2014 11
  • 12. combination of curved tendons with curved soffits 1. A combination of curved tendons with curved soffits is frequently used when straight soffits are not required. 2. This will permit a smaller curvature in tendons thus reducing the friction. 1/24/2014 12
  • 13. 1. Curved or bent cables are also combine with beams of variable depth. 1. Combination of straight and curved tendons are sometimes found convenient. 1/24/2014 13
  • 14. 1. Some cables are bent upwards and anchored at the top flanges. 1. Some cables are stopped part way in the bottom flange. 2. This arrangements will save some steel but may not be justified unless the saving is considerable as for very long span carrying heavy loads. 1/24/2014 14
  • 15. Cantilever Beam  A cantilever is a beam anchored at only one end. The beam carries the load to the support where it is forced against by a moment and shear stress.  Two general layouts are possible for cantilevers : 1.Single Cantilevers 2. Double Cantilevers 1/24/2014 15
  • 16. LAYOUTS FOR SINGLE CANTILEVER 1. For a short span with a short cantilever a straight and uniform section may be the most economical. 2. It is only necessary to vary the c.g.s profile so that it will confirm with the requirements of the moment diagrams. 1/24/2014 16
  • 17. 1. When the cantilever span become longer it is advisable to taper the beam. 2. If the anchore span is short compared to the cantilever it may be entirely subjected to the negative moments and the c.g.s may have to be located above the c.g.c 1/24/2014 17
  • 18. 1. For longer span it may be desirable to haunched them. 2. The c.g.s profile can be properly curved or may remain practically straight. 1/24/2014 18
  • 19. Layouts for double cantilever 1. For short double cantilevers a straight and uniform section can be adopted. 1. When the cantilevers are long they may be tapered. 1/24/2014 19
  • 20. 1. If the anchor span is long it may be haunched. 1. If the anchor span is short compared with the cantilevers the c.g.s line may lie near the top of the beam. 1/24/2014 20
  • 22. CONTINUOUS BEAM A Continuous beam is one, which is supported on more than two supports. For usual loading on the beam hogging ( -ve ) moments causing convexity upwards at the supports and sagging ( +ve ) moments causing concavity upwards occur at mid span. 1/24/2014 22
  • 23. ASSUMPTIONS OF CONTINUOUS BEAM 1. The ecentricities of the 1/24/2014 prestressing cable are small compared to length of the members. 2. Frictional loss of prestress is negligible. 3. The same tendons run through the entire length of the member. 23
  • 24. Advantages of Continuous Beam Over Simply Supported Beam  The maximum bending moment in case of continuous beam is much less than in case of simply supported beam of same span carrying same loads.  In case of continuous beam, the average bending moment is lesser and hence lighter materials of construction can be used to resist the bending moment. 1/24/2014 24
  • 25. COMPARING OF LOAD CARRYING CAPACITY BETWEEN SIMPLY SUPPORTED BEAM AND CONTINIUOUS BEAM 1/24/2014 25
  • 26. LOAD CARRYING CAPACITY OF SIMPLE BEAM 1/24/2014 26
  • 27. LOAD CARRYING CAPACITY OF SIMPLE BEAM 1/24/2014 27
  • 28. LOAD CARRYING CAPACITY OF CONTINUOUS BEAM 1/24/2014 28
  • 29. LOAD CARRYING CAPACITY OF CONTINUOUS BEAM 1/24/2014 29
  • 30. DISADVANTAGES OF CONTINUOUS BEAM 1. Frictional loss is significant 2. Shortening of long continuous beam under prestress. 3. Concurrence of maximum moment and shear over support. 4. Difficulties in achiving continuity for precast elements. 1/24/2014 30
  • 31. CABLE LAYOUT OF CONTINUOUS BEAM 1/24/2014 31
  • 32. Curbed Tendon In Straight Beam •This lay out is often used for slabs or short span beams •The main objections here are the heavy frictional loss 1/24/2014 32
  • 33. Straight Tendon In Curbed Beam •Used for longer span and heavier loads. •Often difficult to get the optimum eccentricities along the beam if the tendons are to remain entirely straight 1/24/2014 33
  • 34. Curbed Tendon In Haunched Or Curbed Beams •This would permit optimum depth of beam as well as ideal position of steel at all points,aboidin excessive frictional loss. 1/24/2014 34
  • 35. Overlapping Tendons •Offer a possibility of varying prestressing force along the beam 1/24/2014 35
  • 36. Determination Of Resisting Moment Of Continuous Beam 1. Plot the primary moment diagram for the entire continuous beam as produced only by pre-stress eccentricity. As if there were no support to the beam. 2. Plot shear diagram. 3. Plot loading diagram. 4. Plot moment diagram corresponding to loading diagram considering all support. 1/24/2014 36
  • 39. Load Balancing Method  Load in the concrete is balanced by stressing the steel. In the overall design of prestressed concrete structure, the effect of prestressing is viewed as the balancing of gravity load . This enables the transformation of a flexural member into a member under direct stress and thus greatly simplifies both the design and analysis of structure.  The application of this method requires taking the concrete as a free body and replacing the tendons with forces acting on the concrete along the span. 1/24/2014 39
  • 40. Concept of Load Balancing Method  There are three basic concepts in prestressed concrete design 1. Stress concept : Treating prestressed concrete as an elastic material 2. Strength concept: Considering prestressed concrete as reinforced concrete dealing with ultimate strength. 3. Balanced load concept: Balancing a portion of the load on the structure. Load Balancing method follows the third one. 1/24/2014 40
  • 41. Life History Of Prestressed Member  Analysing the life history of the prestressed member under flexure leads to understanding the balanced load concept relative to other two concept.  So lets find out the load deflection relationship of a member as a simple beam.. 1/24/2014 41
  • 42.  K1 = Factor of safety applied to working load to obtain minimum yield point.  K2= Factor of safety applied to ultimate strength design to obtain minimum ultimate load. 1/24/2014 42
  • 43.  The load deflection relationship of the above figure leads to several critical points. Such as..  1. Point of no deflection which indicates rectangular stress block.  2. Point of no tension which indicates triangular stress block with zero stress at the bottom fiber.  1/24/2014 43
  • 44. 3. Point of cracking which occurs when the extreme fiber is stressed to the modulus of rupture. 4. Point of yielding at which steel is stressed beyond its yield point so that complete recovery is not possible. 5. Point of ultimate load which represents the maximum load carried by the member at failure. 1/24/2014 44
  • 45. Mechanism & Explanation Of Balanced load Concept According to figure there are three stages of beam Behavior : Applied Loadings Stages of beam behavior  DL+k3LL  No deflection  DL+LL  No tension  K2(DL+LL)  Ultimate 1/24/2014 45
  • 46.  Where,  DL+LL is the stress concept with some allowable tension on beam or no tension.  K2(DL+LL) is the strength concept consists with the ultimate strength of the beam.  DL+K3LL is the balanced load concept with the point of no deflection where k3 is zero or some value much less than one. 1/24/2014 46
  • 47.  In balanced load concept design is done by point of no deflection.  So prestressing is done in such a way so that effective prestress balances the sustained loading & beam remain perfectly level without deflecting. 1/24/2014 47
  • 48. ADVANTAGES OF LOAD BALANCING METHOD  1.simplest approach to prestressed design and analysis for statically indeterminate structures.  2.It has advantages both in calculating and in visualizing.  3.Convenience in the computation of deflections. 1/24/2014 48
  • 49. SIMPLE & CANTILEVER BEAM WITH LOAD BALANCING METHOD Figure illustrates how to balance a concentrated load by sharply bending the c.g.s. at midspan , thus creating an upward component V=2Fsinθ 1/24/2014 49
  • 50.  If V exactly balances a concentrated load P Applied at midspan the beam is not subjected to any transverse load. The stresses in the beam at any section are simply given by Any loading addition to P will cause bending and additional stresses computed by 1/24/2014 50
  • 51.  Figure illustrates the balancing of a uniformly distributed load by means of a parabolic cable whose upward component is given by 1/24/2014 51
  • 52.  If the externally applied load w is exactly balanced by the component Wb there is no bending in the beam. The beam is again under a uniform compression with stress External load produced moment M and corresponding stresses 1/24/2014 52
  • 53.  Figure represents a cantilever beam. Any vertical component at the cantilever end C will upset the balance, unless there is an externally applied load at that tip. 1/24/2014 53
  • 54.  To balance a uniform load w, the tangent to the c.g.s. at C will have to be horizontal. Then the parabola for the cantilever portion can best be located by computing And the parabola for the anchor arm by 1/24/2014 54
  • 55. EXAMPLE PROBLEM OF CANTILEVER BEAM  A double cantilever beam is to be designed so that its prestress will exactly balance the total uniform load of 23.3 KN/m normally carried on the beam. Design the beam using the least amount of prestress, assuming that the c.g.s must have a concrete protection of at least 76.2mm. If a concentrated load of 62KN is added at the mid span compute the maximum top and bottom fiber stresses 1/24/2014 55
  • 56. SOLUTION: To use the least amount of prestress, the ecentricity over the support should be a maximum that is , h=300mm or o.3m. The prestress required is F = wL2 / 2h =(23.3x62)/(2x0.300)=1395KN The sag for the parabola must be h1 = w(L1)2/8F =(23.3x14.82)/(8*1395) =0.46m 1/24/2014 56
  • 57. Uniform compressive stress f= F/Ac = 1395/(2.28x105) = 6.12 Mpa Moment M at the mid span due to P=62KN M=PL/4=(62x14.8)/4=229KN-m Extreme fiber stresses are f=Mc/I=6M/bd2 = (6x229x106)/(300x7602) = 7.93MPa Stress at mid span are ftop = -6.12-7.93=-14.05MPa compression f bottom = -6.12+7.93 =+1.81 MPa tension 1/24/2014 57
  • 58. EXAMPLE PROBLEM OF CONTINUOUS BEAMS:  For the symmetrical continuous beam prestressed with F= 1420KN along a parabolic cable as shown, compute the extreme fiber stresses over the center support DL+LL=23.0KN/m 1/24/2014 58
  • 59. SOLUTION: The upward transverse component of prestress is Wb= 8Fh/L2 = (8x1420x0.3)/(15x15)=15.1KN/m The beam is balanced under uniform stress f= (1420x103)/(300x760)= -6.2MPa For applied load w=23.0 KN/m, the unbalanced downward load = (23.0-15.1) = 7.9 KN/m This load produces a negative moment over the center support, M= wl2/8 =(7.9x152)/8 = 222KN-m And fiber stresses, f = Mc/I = (6x222x106)/(300x7602) = 7.68 Mpa ftop = -6.2+7.68=+1.48MPa tension f bottom = -6.2-7.68 =+13.88 MPa compression 1/24/2014 59