•   Brief Profile of the company
•   Combined Cycle Power Plant
•   Working of Gas Power Plant
•   Heat Recovery Steam Generator (HRSG)
•   Plant Overview
•   Water Treatment Plant
•   Generator
•   Transformer
•   Switch Yard Description
•   Specifications
•   Merits & Demerits
•   Bibliography
Brief Profile of the company
• Under IPGCL i.e. Indraprastha Power Generation
  Company Limited,3 Power Stations are in
  operation.They are as follows :
  1)I.P STATION
  2)RAJGHAT POWER HOUSE
  3)GAS TURBINE POWER STATION (GTPS)

• Under PPCL i.e. Pragati Power Cooperation
  Limited, one Power Station is in operation and it is:
  PRAGATI POWER STATION
STATIONS      I.P STATION RAJGHAT            GTPS           PRAGATI
                          POWER                             POWER
                          STATION                           STATION
Station       247.5           135            282            330
Capacity
(MW)
Units         3*62.5 (GT) +   2*67.5 (GT)    6*30 (GT) + 2*104 (GT) +
              60 (ST)                        3*34 (WHRU) 1*122
                                                         (WHRU)
Year of      1967-71          1989-90        1986 & 1996    2002-2003
Commissionin
g
Coal          NCL,BINA        NCL,BINA       GAIL HBJ       GAIL HBJ
Field/Gas                                    Pipeline       Pipeline

Water         River Yamuna    River Yamuna   River Yamuna   Treated water from
                                                            Sen Nursing Home &
Sources                                                     Delhi Gate Sewage
                                                            Treatment Plants

Beneficiary   VIP-South &     Central &      NDMC-          NDMC,South
Areas         Central Delhi   North Delhi    VIP,DMRC       Delhi
MISSION OF THE COMPANY
• To make Delhi-Power Surplus
• To maximize generation from available capacity
• To plan and implement new generation capacity
  in Delhi
• To set ever so high standards of environment
  Protection
• To develop competent human resources for
  managing the company with good standards
Combined Cycle Power Plant
• Combined Cycle Power Plant (CCPP) or
  Combined Cycle Gas Turbine plant (CCGT)
• A gas turbine generator generates electricity and
  heat in the exhaust is used to make steam,
  which in turn drives a steam turbine to generate
  an additional electricity.
• In CCPP ,a successful common combination is
  the Brayton cycle (in the form of a turbine
  burning natural gas) and the Rankine cycle (in
  the form of a steam power plant)
• The gas turbine is comprised of three main
components: a compressor, combustor and a turbine.
• The air is, compressed in the compressor (adiabatic
compression-no heat gain or loss), then mixed with fuel
and burnt by combustor under constant pressure
conditions in the combustion chamber.
•The resulting hot gas expands through the turbine to
perform work (adiabatic expansion).
Working of Gas Power Plant
Heat Recovery Steam Generator
               (HRSG)
•   The Heat Recovery Steam Generator (HRSG) is a horizontal, natural
    circulation, single pressure, water tube type steam generator with a single
    drum.
•   It is unfired type and uses Gas turbine exhaust gases as heat source.
•   It has been designed to generate superheat steam at a pressure of 41.5 kg/
    cm2 and a temperature of 512 degree Celsius at a Main Stream Value
    (MSV).
•   It consists of following section :
    a) Superheater section
    b) Evaporator section
    c) Economizer section
    d) Condensate Pre heater (C.P.H) and components
    e) Steel chimney
Water Treatment Plant
        •The steam coming out of turbine is
        condensed and the condensate is
        feedback to the boiler as feed water. Some
        water may be lost due to blow-down,
        leakage etc and to make up these losses
        additional water called make up water, is
        required to be fed to the boiler.
        •The source of feed water contain
        impurities that could lead to scale
        formation.
        •The water is passed through alum-dosed
        clarifier which bonds impurities and thus
        removed.
        •Chlorine removes the algae and bacteria’s
        from the water. These processes takes
        place in clarifier from where water is sent
        to D.M Plant (De-mineralized plant).
ACTIVATED CARBON FILTER:
Water from the clarifier first comes in the ACF. It absorbs some of
the impurities.
STRONG ACID CATION:
It consists of resin named hydrocarbon. It removes the acidic
impurities. This is recharged by HCl acid.
DEGASIFIER:
Here the gases available in the water i.e. oxygen, carbon dioxide
is removed upto 5-6%.
STRONG BASE ANION:
It consists of resin, OH-.It removes the basic impurities. It is
recharged by NaOH. The pH is 8.5-9.5.
MIXED BED:
It consists of both resin, acid and basic. pH is maintained about
6.8-7.2.This is recharged by HCl & NaOH.
Generator
•Generator converts the mechanical
energy of turbine shaft into electrical
energy. Rotating field type generators are
employed which are ventilated by the fans
of rotor shaft or separately driven fans.
•At this power plant the requirements
of generator are:
POLES=2
FREQUENCY=50Hz
SPEED=120f/P=3000rpm

•The class of generator under consideration is steam turbine-
driven generators, commonly called turbo generators. Generally
they have the ratings up to 1900MW but here 3000rpm,50Hz
generators are used of capacities 122MW.
Transformer
                                •Transformer is a device that transforms
                                electrical energy form from one alternating
                                voltage to another alternating voltage
                                without change in frequency.
                                •IEEE defines transformer as a static
                                electrical device, involving no continuously
                                moving parts, used in electric power
                                system to transfer power between circuits
                                through the use of electromagnetic
                                induction.
•Types of transformer:
1) Power Transformer
2) Instrument Transformer
3) AutoTransformer
4) On the basis of working
1)   Power Transformer

2)   Instrument Transformer

3)   Auto Transformer




4)   On the basis of working
     4.1) Step down- converts H.V to L.V
     4.2) Step up- converts L.V to H.V
SWITCH YARD DESCRIPTION
• For any power station, switchyard is an important part which bridges
  the generating station and the distribution system i.e. via switchyard
  the generated electricity is fed to the sub-stations. It connects the
  GTPS to the northern grid.
• The switchyard of Gas Turbine Power Plant is of 66KV.
• The voltage generated is 11KV, which is then step up to 66KV by
  generator transformer. This 66KV is fed to the 66KV switchyard.
• The switchyard has the double bus bar system i.e. one is main bus
  and the other one is secondary bus.
• Some of the functions are:
 Change voltage from one level to another
 Switch transmission and distribution circuits into and out of the grid
  system.
 Measure electric power qualities flowing in the circuits.
 Eliminate lightning and other surges from the system.
•   ISOLATORS: They are designed to open a ckt under no load. Its main purpose is to
    isolate portion of the ckt from the other & is not intended to be opened while current
    is flowing in the line.




•   CIRCUIT BREAKERS: It is a piece of equipment which can break the circuit
    automatically under faulty conditions and make the circuit either manually or by
    remote control under faulty conditions. They can be classified as
iii. oil ckt breaker
iv. Gas(SF6) ckt breaker
v. Air-blast ckt breaker
vi. Vaccum ckt breaker
    The switch yard has gas (SF6) or Sulphur Hexa Fluoride ckt breaker.
3)INSULATORS: All the insulators are made of porcelain metal parts. They are free
   from radio interference. They support the conductors (bus bar) and confine the
   current to the conductors.




4)BUS COUPLERS: Breakers are used as
    a bus coupler. They provide coupling
   between the two bus bar of zones.




5)CURRENT TRANSFORMER: C.T is an instrument t/f used
   for protection & metering of high values of currents.
   C.T is used for reducing a.c from higher to lower value of
   measurement/protection/control.
6) POTENTIAL TRANSFORMER: They are used to increase
the range of voltmeters in electrical substations and
generating stations. They are also called voltage t/f.

7)LIGHTINING ARRESTORS: It is a protective
device used to protect the station, equipments
against atmospheric discharge.
8)EARTHING LINKS: Switchyard
Earthing is provided to protect
personally from shocks and
hazards from electrical
equipments.
9)MULSIFIER: They are used to protect the transformer against fire.
SPECIFICATIONS
•   Specifications of SF6 circuit breaker:
2)  Rated voltage             72.5kV
3)  Rated frequency           50Hz
4)  Rated current             2000A
5)  Impulse voltage (peak)    325kV
6)  Rated breaking capacity
    a) Symmetrical            25KA
    b) Asymmetrical           28KA
    c) Making (peak)          64KA
    d) Short time (for 1 sec) 2.5KA
11) Rated Pressure            5.5 bars
12) Total mass of ckt breaker 900kg
13) Total SF6 gas content     3.7kg
•     Specifications of 66KV Isolators and earthing switches:
2)    No. of Pole       03
3)    Installation      Outdoor
4)    Rated Voltage     72.5KV/66KV
5)    Rated Current     1250 Amp
6)    Rated Frequency 50 Hz


•     Specifications of 66KV Current Transformer:
8)    No. of Course             4
9)    Rated Voltage             72.5KV/66KV
10)   Rated Current             2000-1000
11)   Rated Frequency           50Hz
12)   Total Creep age distance 1700mm
13)   Short time Current Rating 25 KV for 1 sec
•   Specifications of Potential Transformer:
2) Type                   WH 72.5-17
3) Standard               IEC
4) Year of manufacturing 1986
5) Weight                 300kg
6) Minimum Temperature 10 degree Celsius
7) Maximum Temperature 50 degree Celsius
8) Frequency              50Hz
9) Voltage factor         1.5
10)Maximum Rating         1000-500 VA

•   Specifications of 66KV Lightning Arrestor:
12)Rated Voltage                  60KV
13)Power frequency Reseal Voltage 60KV
14)High Current Impulse           100 K Amps
15)Class of Arrestors             10 K Amps for heavy duty
16)Total creep age distance       1700mm
Merits & Demerits
•   Merits:
   Low operation and maintenance cost
   Less space is occupied
   Less gas storage
   Cheaper fuels like natural gas

• Demerits:
 Temp. of combustion chamber is too high, which results in
  shorter life time.
 Gas turbine has low thermal efficiency
 Has starting problem
 Efficient only in combined cycle
Bibliography
• Links referred :
  http://www.hrsgdesign.com/design0.htm
  http://ipgcl-ppcl.gov.in/
http://www.osha.gov/SLTC/etools/electric_po
wer/illustrated_glossary/substation.html#Equ
                   ipment
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation

More Related Content

What's hot

What's hot (20)

Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
kota super thermal power plant (kstps)
kota super thermal power plant (kstps)kota super thermal power plant (kstps)
kota super thermal power plant (kstps)
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
 
Thermal power station
Thermal power stationThermal power station
Thermal power station
 
KOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPTKOTA SUPER THERMAL POWER STATION PPT
KOTA SUPER THERMAL POWER STATION PPT
 
Regenerative feed water heating cycle
Regenerative feed water heating cycleRegenerative feed water heating cycle
Regenerative feed water heating cycle
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Industrial type gas turbine combustion chamber
Industrial type gas turbine combustion chamberIndustrial type gas turbine combustion chamber
Industrial type gas turbine combustion chamber
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Diesel Power Plant
Diesel Power PlantDiesel Power Plant
Diesel Power Plant
 
La mont boiler
La mont boilerLa mont boiler
La mont boiler
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
Coal Power Plant
Coal Power PlantCoal Power Plant
Coal Power Plant
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
ppt on kota super thermal power plant
ppt on kota super thermal power plantppt on kota super thermal power plant
ppt on kota super thermal power plant
 

Similar to IPGCL/PPCL Training presentation

Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
Ramendra Dhiman
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
Nipak Banerjee
 

Similar to IPGCL/PPCL Training presentation (20)

Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Avdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kotaAvdhehs kumar presention kstps kota
Avdhehs kumar presention kstps kota
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
 
tps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptxtps 180150109049 180150109078.pptx
tps 180150109049 180150109078.pptx
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
Htps
HtpsHtps
Htps
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
Lakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxLakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptx
 
Bangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants OverviewBangladesh Power Stations & Power Plants Overview
Bangladesh Power Stations & Power Plants Overview
 
kstps training report
kstps training reportkstps training report
kstps training report
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 

Recently uploaded

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 

Recently uploaded (20)

2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 

IPGCL/PPCL Training presentation

  • 1. Prepared by : Shubhra Dhyani Btech(EEE) III year 0919221054
  • 2. CONTENTS • Brief Profile of the company • Combined Cycle Power Plant • Working of Gas Power Plant • Heat Recovery Steam Generator (HRSG) • Plant Overview • Water Treatment Plant • Generator • Transformer • Switch Yard Description • Specifications • Merits & Demerits • Bibliography
  • 3. Brief Profile of the company • Under IPGCL i.e. Indraprastha Power Generation Company Limited,3 Power Stations are in operation.They are as follows : 1)I.P STATION 2)RAJGHAT POWER HOUSE 3)GAS TURBINE POWER STATION (GTPS) • Under PPCL i.e. Pragati Power Cooperation Limited, one Power Station is in operation and it is: PRAGATI POWER STATION
  • 4. STATIONS I.P STATION RAJGHAT GTPS PRAGATI POWER POWER STATION STATION Station 247.5 135 282 330 Capacity (MW) Units 3*62.5 (GT) + 2*67.5 (GT) 6*30 (GT) + 2*104 (GT) + 60 (ST) 3*34 (WHRU) 1*122 (WHRU) Year of 1967-71 1989-90 1986 & 1996 2002-2003 Commissionin g Coal NCL,BINA NCL,BINA GAIL HBJ GAIL HBJ Field/Gas Pipeline Pipeline Water River Yamuna River Yamuna River Yamuna Treated water from Sen Nursing Home & Sources Delhi Gate Sewage Treatment Plants Beneficiary VIP-South & Central & NDMC- NDMC,South Areas Central Delhi North Delhi VIP,DMRC Delhi
  • 5. MISSION OF THE COMPANY • To make Delhi-Power Surplus • To maximize generation from available capacity • To plan and implement new generation capacity in Delhi • To set ever so high standards of environment Protection • To develop competent human resources for managing the company with good standards
  • 6. Combined Cycle Power Plant • Combined Cycle Power Plant (CCPP) or Combined Cycle Gas Turbine plant (CCGT) • A gas turbine generator generates electricity and heat in the exhaust is used to make steam, which in turn drives a steam turbine to generate an additional electricity. • In CCPP ,a successful common combination is the Brayton cycle (in the form of a turbine burning natural gas) and the Rankine cycle (in the form of a steam power plant)
  • 7. • The gas turbine is comprised of three main components: a compressor, combustor and a turbine. • The air is, compressed in the compressor (adiabatic compression-no heat gain or loss), then mixed with fuel and burnt by combustor under constant pressure conditions in the combustion chamber. •The resulting hot gas expands through the turbine to perform work (adiabatic expansion).
  • 8. Working of Gas Power Plant
  • 9. Heat Recovery Steam Generator (HRSG) • The Heat Recovery Steam Generator (HRSG) is a horizontal, natural circulation, single pressure, water tube type steam generator with a single drum. • It is unfired type and uses Gas turbine exhaust gases as heat source. • It has been designed to generate superheat steam at a pressure of 41.5 kg/ cm2 and a temperature of 512 degree Celsius at a Main Stream Value (MSV). • It consists of following section : a) Superheater section b) Evaporator section c) Economizer section d) Condensate Pre heater (C.P.H) and components e) Steel chimney
  • 10.
  • 11.
  • 12. Water Treatment Plant •The steam coming out of turbine is condensed and the condensate is feedback to the boiler as feed water. Some water may be lost due to blow-down, leakage etc and to make up these losses additional water called make up water, is required to be fed to the boiler. •The source of feed water contain impurities that could lead to scale formation. •The water is passed through alum-dosed clarifier which bonds impurities and thus removed. •Chlorine removes the algae and bacteria’s from the water. These processes takes place in clarifier from where water is sent to D.M Plant (De-mineralized plant).
  • 13. ACTIVATED CARBON FILTER: Water from the clarifier first comes in the ACF. It absorbs some of the impurities. STRONG ACID CATION: It consists of resin named hydrocarbon. It removes the acidic impurities. This is recharged by HCl acid. DEGASIFIER: Here the gases available in the water i.e. oxygen, carbon dioxide is removed upto 5-6%. STRONG BASE ANION: It consists of resin, OH-.It removes the basic impurities. It is recharged by NaOH. The pH is 8.5-9.5. MIXED BED: It consists of both resin, acid and basic. pH is maintained about 6.8-7.2.This is recharged by HCl & NaOH.
  • 14. Generator •Generator converts the mechanical energy of turbine shaft into electrical energy. Rotating field type generators are employed which are ventilated by the fans of rotor shaft or separately driven fans. •At this power plant the requirements of generator are: POLES=2 FREQUENCY=50Hz SPEED=120f/P=3000rpm •The class of generator under consideration is steam turbine- driven generators, commonly called turbo generators. Generally they have the ratings up to 1900MW but here 3000rpm,50Hz generators are used of capacities 122MW.
  • 15. Transformer •Transformer is a device that transforms electrical energy form from one alternating voltage to another alternating voltage without change in frequency. •IEEE defines transformer as a static electrical device, involving no continuously moving parts, used in electric power system to transfer power between circuits through the use of electromagnetic induction. •Types of transformer: 1) Power Transformer 2) Instrument Transformer 3) AutoTransformer 4) On the basis of working
  • 16. 1) Power Transformer 2) Instrument Transformer 3) Auto Transformer 4) On the basis of working 4.1) Step down- converts H.V to L.V 4.2) Step up- converts L.V to H.V
  • 17. SWITCH YARD DESCRIPTION • For any power station, switchyard is an important part which bridges the generating station and the distribution system i.e. via switchyard the generated electricity is fed to the sub-stations. It connects the GTPS to the northern grid. • The switchyard of Gas Turbine Power Plant is of 66KV. • The voltage generated is 11KV, which is then step up to 66KV by generator transformer. This 66KV is fed to the 66KV switchyard. • The switchyard has the double bus bar system i.e. one is main bus and the other one is secondary bus. • Some of the functions are:  Change voltage from one level to another  Switch transmission and distribution circuits into and out of the grid system.  Measure electric power qualities flowing in the circuits.  Eliminate lightning and other surges from the system.
  • 18.
  • 19. ISOLATORS: They are designed to open a ckt under no load. Its main purpose is to isolate portion of the ckt from the other & is not intended to be opened while current is flowing in the line. • CIRCUIT BREAKERS: It is a piece of equipment which can break the circuit automatically under faulty conditions and make the circuit either manually or by remote control under faulty conditions. They can be classified as iii. oil ckt breaker iv. Gas(SF6) ckt breaker v. Air-blast ckt breaker vi. Vaccum ckt breaker The switch yard has gas (SF6) or Sulphur Hexa Fluoride ckt breaker.
  • 20. 3)INSULATORS: All the insulators are made of porcelain metal parts. They are free from radio interference. They support the conductors (bus bar) and confine the current to the conductors. 4)BUS COUPLERS: Breakers are used as a bus coupler. They provide coupling between the two bus bar of zones. 5)CURRENT TRANSFORMER: C.T is an instrument t/f used for protection & metering of high values of currents. C.T is used for reducing a.c from higher to lower value of measurement/protection/control.
  • 21. 6) POTENTIAL TRANSFORMER: They are used to increase the range of voltmeters in electrical substations and generating stations. They are also called voltage t/f. 7)LIGHTINING ARRESTORS: It is a protective device used to protect the station, equipments against atmospheric discharge. 8)EARTHING LINKS: Switchyard Earthing is provided to protect personally from shocks and hazards from electrical equipments. 9)MULSIFIER: They are used to protect the transformer against fire.
  • 22. SPECIFICATIONS • Specifications of SF6 circuit breaker: 2) Rated voltage 72.5kV 3) Rated frequency 50Hz 4) Rated current 2000A 5) Impulse voltage (peak) 325kV 6) Rated breaking capacity a) Symmetrical 25KA b) Asymmetrical 28KA c) Making (peak) 64KA d) Short time (for 1 sec) 2.5KA 11) Rated Pressure 5.5 bars 12) Total mass of ckt breaker 900kg 13) Total SF6 gas content 3.7kg
  • 23. Specifications of 66KV Isolators and earthing switches: 2) No. of Pole 03 3) Installation Outdoor 4) Rated Voltage 72.5KV/66KV 5) Rated Current 1250 Amp 6) Rated Frequency 50 Hz • Specifications of 66KV Current Transformer: 8) No. of Course 4 9) Rated Voltage 72.5KV/66KV 10) Rated Current 2000-1000 11) Rated Frequency 50Hz 12) Total Creep age distance 1700mm 13) Short time Current Rating 25 KV for 1 sec
  • 24. Specifications of Potential Transformer: 2) Type WH 72.5-17 3) Standard IEC 4) Year of manufacturing 1986 5) Weight 300kg 6) Minimum Temperature 10 degree Celsius 7) Maximum Temperature 50 degree Celsius 8) Frequency 50Hz 9) Voltage factor 1.5 10)Maximum Rating 1000-500 VA • Specifications of 66KV Lightning Arrestor: 12)Rated Voltage 60KV 13)Power frequency Reseal Voltage 60KV 14)High Current Impulse 100 K Amps 15)Class of Arrestors 10 K Amps for heavy duty 16)Total creep age distance 1700mm
  • 25. Merits & Demerits • Merits:  Low operation and maintenance cost  Less space is occupied  Less gas storage  Cheaper fuels like natural gas • Demerits:  Temp. of combustion chamber is too high, which results in shorter life time.  Gas turbine has low thermal efficiency  Has starting problem  Efficient only in combined cycle
  • 26. Bibliography • Links referred : http://www.hrsgdesign.com/design0.htm http://ipgcl-ppcl.gov.in/ http://www.osha.gov/SLTC/etools/electric_po wer/illustrated_glossary/substation.html#Equ ipment