SlideShare a Scribd company logo
1 of 29
KOTA SUPER THERMAL POWER STATION KOTA 
(RAJ.) 
SUBMITTED BY: 
Prakash Chandra Jarotia 
2011UEE!374
INTRODUCTION OF THE THERMAL POWER PLANT 
It was established in 1983. 
It is located at the left bank of the CHAMBAL River at the 
upstream of KOTA BAIRAJ. 
Favorable condition 
Abundant quantity of clean cooling water. 
Good transport facility 
Concentration of load in Kota region due to large number of 
industries.
INSTALLED CAPACITY 
Kota Thermal Power Station is Rajasthan's First major coal power station. Presently 
it is in operation with installed capacity of 1240MW.
DEFINITION OF THERMAL POWER STATION 
 A thermal power station is a power 
plant in which the prime mover is steam 
driven. Water is heated, turns into 
steam and spins a steam turbine which 
either drives an electrical generator . 
After it passes through the turbine, the 
steam is condensed in a condenser 
and recycled to where it was heated; 
this is known as a Rankine cycle . The 
greatest variation in the design of 
thermal power stations is due to the 
different fuel sources. Some prefer to 
use the term energy center because 
such facilities convert forms of heat 
energy into electrical energy.
OPERATIONS IN THERMAL POWER STATION 
Step wise operations in a 
thermal power plant are as 
follows:- 
 Coal is used as a fuel to boil 
the water. 
 Water is boiled to form 
pressurized steam. 
 Pressurized steam is the 
force that cause the turbine to 
rotate at a very high speed. 
 Low pressure steam after 
pushing through the turbine 
,it’s going into the condenser. 
 Condenser – the place where 
the steam is condensed back 
it it’s liquid form .Then the 
process is repeated
MAIN PARTS OF THERMAL POWER STATION 
1. Coal supply 
2. Coal pulverizer 
3. Boiler 
4. Precipitators 
and stack 
5. Turbine and 
generator 
6. Condensers 
and cooling 
water system 
7. Water 
purification 
8. Ash systems 
9. transformer 
and 
transmission 
lines
Coal Handling Plant 
Coal handling plant section 
• Wagon unloading system 
• Crushing system 
• Conveying system
WAGON UNLOADING SYSTEM 
 Unload the coal from wagon 
to hopper with the help of 
wagon Tripler. 
 Hopper allows to pass coal 
pieces ≤ 200mm 
 From hopper coal fall on 
vibrator which is supported 
by roller. 
 Rated Output : 71 KW. 
Rated 
 Voltage. : 415 V. 
Rated 
 Current. : 14.22 Amp. 
 Rated Speed. : 975rpm. 
 No. of phases. : 3 
 Frequency. : 50 HZ.
CRUSHING SYSTEM 
 CRUSHER HOUSE:- It 
consists of crushers which 
are used to crush the coal to 
20 mm size. 
 Two types 
 Primary crusher 
 Rail crusher 
 Rotary breaker 
 Secondary crusher 
 Capacity : 1350 TPH 
(Rates/ 1500 TPH Design.) 
 Feed material : Rom Coal. 
 Feed size : (-) 1200 mm 
(approx.) 
 End Product size : (-) 500 
mm Motor rating : 125 
KW,100 rpm 
 Crushers : 225.
CONVEYOR BELT 
Belt are used to convey coal 
from coal handling plant to 
furnace. 
Conveyor Belt Specification :- 
 Belt width : 1400 mm. 
 Speed : 2.2 m/second. 
 Schedule of motor : All 3-phas 
induction motor 
 Travel Motor : 7.5 KW. 
 Vibrating Feeder : 2x6 KW. 
 Total installed power. : 360 KW. 
 Capacity : 1) 1350 
tonne per hour 
 2) 750 
tonne per hour. 
 No. of conveyor : 38 
 Horizontal length : 28 meters
BOILER 
 It is a closed vessel in which water under pressure is 
converted into steam. 
 Hot water or steam used to transfer heat to a process. 
 A boiler is always designed to absorb maximum 
amount of heat released in process of combustion. 
 This is transferred to the boiler by all the three modes 
of heat transfer i.e. conduction. Convection and 
radiation. 
 Furnace:- It is primary part of boiler where the fuel is 
burnt to liberate the heat energy. 
Chemical 
Energy of 
fuel 
Thermal 
Energy by 
combustion
FIGURE BOILER
Boilers are classified as:- 
 Fire tube boiler:- In this type the products of 
combustion pass through the tubes which 
are surrounded by water. These are 
economical for low pressure only. 
Water tube boiler:- In this type of boiler 
water flows inside the tubes and hot gases 
flow outside the tubes. These tubes are 
interconnected to common water channels 
and to steam outlet.
SUPER HEATER :- Superheated steam is that steam, which contains 
more heat than the saturated steam at the same pressure i.e. it, has been 
heated above the temperature corresponding to its pressure. A 
superheater is a device which removes the last traces of moisture from the 
saturated steam leaving the boiler tubes and also increases its 
temperature above the saturation temperature. 
REHEATER :- Reheaters are provided to raise the temperature of the 
steam from which part of energy has already been extracted by HP turbine
PRECIPTATOR AND STACK :- 
 ELECTRO-STATIC PRECIPTATOR For general mankind, today 
an Eco friendly industry is must. As far as air pollution is 
concerned now a day various flue gases filter are there in service. 
The choice depends on the size of suspended particle matter. 
These filters are E.S.P. Fabric filter high efficiency cyclone 
separations and stalling room. Fop fly ash, where the particle size 
vary from 0.75 microns to 100 micron use gradually use E.S.P. to 
purify the flue gases due to its higher efficiency & low running 
cost etc. 
 In an ESP the dust lidder gas is passed through an intense 
electric field, which causes ionization of the gases& they changed 
into ion while travelling towards opposite charged electrode get 
deposited as particles and thus dust is electric deposited an 
electrode creating the field. It is continuous process. 
 The gas exiting the boiler is laden with fly ash.The fly ash is 
removed by electrostatic precipitators and passes through stack 
in environment.
STEAM TURBINE 
 It is a machine in which 
a shaft is rotated 
steadily by reaction of 
steam, air upon blades 
of a wheel. 
 When Steam is used 
then it is called steam 
turbine. 
 It works on Modified 
Rankine cycle. 
Heat of 
steam 
Mechanical 
Energy
THE MAIN TECHNICAL DATA OF 110 MW TURBINES IS 
GIVEN BELOW :- 
 Rated output : 110 MW. 
 Economic output : 95 MW. 
 Rated speed : 3000 rpm 
 Direction of rotation viewing from the front bearing 
pedestal : clock wise 
 Rated steam pressure before stop valve : 130 ata 
 Maximum steam pressure before stop valve : 146 ata 
 Rated temperature of steam before the stop valve. 
535°C Maximum temperature of steam before the 
stop valve. 545°C Rated pressure of steam 31.6 ata
•An electrical generator is a 
machine which converts 
mechanical energy into electrical 
energy through electro 
mechanical energy conversion . 
•The generator is driven by 
directly coupled steam turbine at 
a speed of 3000 r.p.m. 
Electrical 
Energy 
Mechanical 
Energy 
GENERATOR
CONDENSERS AND COOLING WATER SYSTEM 
 A condenser is a commonly used term 
for a water-cooled shell and tube heat 
exchanger installed on the exhaust 
steam from a steam turbine in thermal 
power stations. 
 These condensers are heat exchangers 
which convert steam from its gaseous to 
its liquid state at a pressure below 
atmospheric pressure 
 In thermal power plants, the primary 
purpose of a condenser is to condense 
the exhaust steam from a steam turbine 
to obtain maximum efficiency, and also 
to convert the turbine exhaust steam 
into pure water so that it may be reused 
in the steam generator or boiler as 
boiler feed water.
COOLING TOWERS 
o A condenser needs huge quantity of water to 
condense the steam . 
o Most plants use a closed cooling system where 
warm water coming from condenser is cooled 
and reused 
o Small plants use spray ponds and medium and 
large plants use cooling towers. 
o Cooling tower is a steel or concrete hyperbolic 
structure having a reservoir at the base for 
storage of cooled water 
o Diameter at the base is 150 m
WATER TREATTENT PLANT 
The principle problem in high pressure 
boiler is to control corrosion and steam 
quality. 
The impurities present in water are 
as follows:- 
1) Un-dissolved and suspended 
solid materials. 
2) Dissolved slats and minerals. 
3) Dissolved gases. 
4) Other minerals (oil, acid etc.). 
5). a) Turbidity & Sediment. 
b) Silica. 
c) Micro Biological. 
d) Sodium& Potassium Salt. 
e) Dissolved Sales Minerals. 
6). a) O2gas. b) CO2 gas.
 Pressure filter removes 
undisclosed impurities from 
raw water. 
 Carbon filter removes 
excess chlorine from 
clarified 
water. 
 D.M. plant removes 
dissolved impurities from 
clarified 
water. 
 Conductivity ,pH & silica 
content of this water must 
be 
checked time to time.
ASH HANDLING PLANT 
The percentage of ash in coal varies from 5% in good quality 
coal to about 40% in poor quality coal 
Power plants generally use poor quality of coal , thus amount 
of ash produced by it is pretty large. 
Electrostatic Precipitator is used in ash handling plant to 
remove fly ash 
The stations use some conveyor arrangement to carry ash to 
dump sites directly or for carrying and loading it to trucks and 
wagons which transport it to the site of disposal
UTILIZATION OF ASH 
1. Manufacturing of building materials. 
2. Making of concrete. 
3. Manufacturing of cement. 
4. Road construction etc.
SWITCHYARD 
 Two 220 KV bus bars have been 
provided in switch yard and are 
inter-connected through a bus 
coupler. 
 Each station transformer has two 
windings one secondary side and 
is rated for 50/25/25mva, 
270/7/7.2 kva four feeder take off 
from 220 switch yard two to 
SKATPURA GSS and other to 
HEERAPURA , Jaipur GSS. 
Each of four feeder are provided 
with bypass isolators which is 
connected across line breaker 
and breaker isolator
SALIENT FEATURE OF K.S.T.P.S. LOCATION 
LOCATION -:Sakatpura, Kota. 
CAPACITY-: 
A) 1st Stage-: 2x110 MW . 
B) 2nd Stage-: 2x210 MW. 
C) 3rd Stage-: 1x210 MW. 
D) 4th Stage-: 1x195 MW. 
E) 5th Stage-: 1x195 MW 
SOURCE OF WATER- : Chambal River. 
BOILER-: a) Types. Fire tube boiler and Water tube 
boiler. 
b) No. of units . 7 
c) Max. Efficiency. BHEL 87.6 % 
d) Capacity. 375 tonnes 1 Hr. 
e) Steam Pressure -:139 Kg./cm² 
f) Steam Temp. -:540
CONCLUSION 
 The first phase of practical training has proved to be quiet 
fruitful. It provided an opportunity for encounter with such 
huge machines like wagon tippler .110 MW, 210 MW & 195 
MW turbines and generators. 
 The architecture of the power plant the way various units 
are linked and the way working of whole plant is controlled 
make the student realize that engineering is not just learning 
the structured description and working of various machines, 
but the greater part is of planning proper management. 
 However training has proved to be quite fruitful. It has 
allowed an opportunity to get an exposure of the practical 
implementation to theoretical fundamentals.
Kota thermal power plant ppt

More Related Content

What's hot

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportDeepak Solanki
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCNITISHKHALKHO
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurAbhishek Mathur
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant vishal patel
 
ppt on kota super thermal power plant
ppt on kota super thermal power plantppt on kota super thermal power plant
ppt on kota super thermal power plantArpit Budania
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationLekhraJ Meena
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.pptAbhishek Awasthi
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanBHANUKISHAN1
 

What's hot (20)

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Kota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training reportKota Super Thermal Power Station Training report
Kota Super Thermal Power Station Training report
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVC
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
ppt on kota super thermal power plant
ppt on kota super thermal power plantppt on kota super thermal power plant
ppt on kota super thermal power plant
 
An Overview of Thermal Power Plant
An Overview of Thermal Power PlantAn Overview of Thermal Power Plant
An Overview of Thermal Power Plant
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
GSECL TPS SIKKA
GSECL TPS SIKKAGSECL TPS SIKKA
GSECL TPS SIKKA
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishan
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 

Similar to Kota thermal power plant ppt

Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingRadhe Shyam
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plantRama Charan
 
KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptxParulChandna6
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxssuser4c2635
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plantR G Sanjay Prakash
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminarCentury Rayon
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavmukesh yadav
 
MEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTMEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTAbhinaw Rai
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKRanjan Naik
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportLovesh Singla
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantHarshit Madaan
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
Sandeep verma ppt on kstps
Sandeep verma ppt on kstps   Sandeep verma ppt on kstps
Sandeep verma ppt on kstps sandeep244266
 

Similar to Kota thermal power plant ppt (20)

Ppt on btps bokaro industrial training
Ppt on btps bokaro industrial trainingPpt on btps bokaro industrial training
Ppt on btps bokaro industrial training
 
rajwest thermal power plant
rajwest thermal power plantrajwest thermal power plant
rajwest thermal power plant
 
KSTPS presentation.pptx
KSTPS presentation.pptxKSTPS presentation.pptx
KSTPS presentation.pptx
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptx
 
KTPS
KTPSKTPS
KTPS
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
MEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORTMEJIA THERMAL POWER STATION VT REPORT
MEJIA THERMAL POWER STATION VT REPORT
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
 
Ntpc dadri ppt
Ntpc dadri pptNtpc dadri ppt
Ntpc dadri ppt
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester report
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power Plant
 
kota super thermal poer plant
kota super thermal poer plantkota super thermal poer plant
kota super thermal poer plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
 
Sandeep verma ppt on kstps
Sandeep verma ppt on kstps   Sandeep verma ppt on kstps
Sandeep verma ppt on kstps
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 

Kota thermal power plant ppt

  • 1. KOTA SUPER THERMAL POWER STATION KOTA (RAJ.) SUBMITTED BY: Prakash Chandra Jarotia 2011UEE!374
  • 2. INTRODUCTION OF THE THERMAL POWER PLANT It was established in 1983. It is located at the left bank of the CHAMBAL River at the upstream of KOTA BAIRAJ. Favorable condition Abundant quantity of clean cooling water. Good transport facility Concentration of load in Kota region due to large number of industries.
  • 3. INSTALLED CAPACITY Kota Thermal Power Station is Rajasthan's First major coal power station. Presently it is in operation with installed capacity of 1240MW.
  • 4. DEFINITION OF THERMAL POWER STATION  A thermal power station is a power plant in which the prime mover is steam driven. Water is heated, turns into steam and spins a steam turbine which either drives an electrical generator . After it passes through the turbine, the steam is condensed in a condenser and recycled to where it was heated; this is known as a Rankine cycle . The greatest variation in the design of thermal power stations is due to the different fuel sources. Some prefer to use the term energy center because such facilities convert forms of heat energy into electrical energy.
  • 5. OPERATIONS IN THERMAL POWER STATION Step wise operations in a thermal power plant are as follows:-  Coal is used as a fuel to boil the water.  Water is boiled to form pressurized steam.  Pressurized steam is the force that cause the turbine to rotate at a very high speed.  Low pressure steam after pushing through the turbine ,it’s going into the condenser.  Condenser – the place where the steam is condensed back it it’s liquid form .Then the process is repeated
  • 6. MAIN PARTS OF THERMAL POWER STATION 1. Coal supply 2. Coal pulverizer 3. Boiler 4. Precipitators and stack 5. Turbine and generator 6. Condensers and cooling water system 7. Water purification 8. Ash systems 9. transformer and transmission lines
  • 7. Coal Handling Plant Coal handling plant section • Wagon unloading system • Crushing system • Conveying system
  • 8. WAGON UNLOADING SYSTEM  Unload the coal from wagon to hopper with the help of wagon Tripler.  Hopper allows to pass coal pieces ≤ 200mm  From hopper coal fall on vibrator which is supported by roller.  Rated Output : 71 KW. Rated  Voltage. : 415 V. Rated  Current. : 14.22 Amp.  Rated Speed. : 975rpm.  No. of phases. : 3  Frequency. : 50 HZ.
  • 9. CRUSHING SYSTEM  CRUSHER HOUSE:- It consists of crushers which are used to crush the coal to 20 mm size.  Two types  Primary crusher  Rail crusher  Rotary breaker  Secondary crusher  Capacity : 1350 TPH (Rates/ 1500 TPH Design.)  Feed material : Rom Coal.  Feed size : (-) 1200 mm (approx.)  End Product size : (-) 500 mm Motor rating : 125 KW,100 rpm  Crushers : 225.
  • 10. CONVEYOR BELT Belt are used to convey coal from coal handling plant to furnace. Conveyor Belt Specification :-  Belt width : 1400 mm.  Speed : 2.2 m/second.  Schedule of motor : All 3-phas induction motor  Travel Motor : 7.5 KW.  Vibrating Feeder : 2x6 KW.  Total installed power. : 360 KW.  Capacity : 1) 1350 tonne per hour  2) 750 tonne per hour.  No. of conveyor : 38  Horizontal length : 28 meters
  • 11. BOILER  It is a closed vessel in which water under pressure is converted into steam.  Hot water or steam used to transfer heat to a process.  A boiler is always designed to absorb maximum amount of heat released in process of combustion.  This is transferred to the boiler by all the three modes of heat transfer i.e. conduction. Convection and radiation.  Furnace:- It is primary part of boiler where the fuel is burnt to liberate the heat energy. Chemical Energy of fuel Thermal Energy by combustion
  • 13. Boilers are classified as:-  Fire tube boiler:- In this type the products of combustion pass through the tubes which are surrounded by water. These are economical for low pressure only. Water tube boiler:- In this type of boiler water flows inside the tubes and hot gases flow outside the tubes. These tubes are interconnected to common water channels and to steam outlet.
  • 14. SUPER HEATER :- Superheated steam is that steam, which contains more heat than the saturated steam at the same pressure i.e. it, has been heated above the temperature corresponding to its pressure. A superheater is a device which removes the last traces of moisture from the saturated steam leaving the boiler tubes and also increases its temperature above the saturation temperature. REHEATER :- Reheaters are provided to raise the temperature of the steam from which part of energy has already been extracted by HP turbine
  • 15. PRECIPTATOR AND STACK :-  ELECTRO-STATIC PRECIPTATOR For general mankind, today an Eco friendly industry is must. As far as air pollution is concerned now a day various flue gases filter are there in service. The choice depends on the size of suspended particle matter. These filters are E.S.P. Fabric filter high efficiency cyclone separations and stalling room. Fop fly ash, where the particle size vary from 0.75 microns to 100 micron use gradually use E.S.P. to purify the flue gases due to its higher efficiency & low running cost etc.  In an ESP the dust lidder gas is passed through an intense electric field, which causes ionization of the gases& they changed into ion while travelling towards opposite charged electrode get deposited as particles and thus dust is electric deposited an electrode creating the field. It is continuous process.  The gas exiting the boiler is laden with fly ash.The fly ash is removed by electrostatic precipitators and passes through stack in environment.
  • 16.
  • 17. STEAM TURBINE  It is a machine in which a shaft is rotated steadily by reaction of steam, air upon blades of a wheel.  When Steam is used then it is called steam turbine.  It works on Modified Rankine cycle. Heat of steam Mechanical Energy
  • 18. THE MAIN TECHNICAL DATA OF 110 MW TURBINES IS GIVEN BELOW :-  Rated output : 110 MW.  Economic output : 95 MW.  Rated speed : 3000 rpm  Direction of rotation viewing from the front bearing pedestal : clock wise  Rated steam pressure before stop valve : 130 ata  Maximum steam pressure before stop valve : 146 ata  Rated temperature of steam before the stop valve. 535°C Maximum temperature of steam before the stop valve. 545°C Rated pressure of steam 31.6 ata
  • 19. •An electrical generator is a machine which converts mechanical energy into electrical energy through electro mechanical energy conversion . •The generator is driven by directly coupled steam turbine at a speed of 3000 r.p.m. Electrical Energy Mechanical Energy GENERATOR
  • 20. CONDENSERS AND COOLING WATER SYSTEM  A condenser is a commonly used term for a water-cooled shell and tube heat exchanger installed on the exhaust steam from a steam turbine in thermal power stations.  These condensers are heat exchangers which convert steam from its gaseous to its liquid state at a pressure below atmospheric pressure  In thermal power plants, the primary purpose of a condenser is to condense the exhaust steam from a steam turbine to obtain maximum efficiency, and also to convert the turbine exhaust steam into pure water so that it may be reused in the steam generator or boiler as boiler feed water.
  • 21. COOLING TOWERS o A condenser needs huge quantity of water to condense the steam . o Most plants use a closed cooling system where warm water coming from condenser is cooled and reused o Small plants use spray ponds and medium and large plants use cooling towers. o Cooling tower is a steel or concrete hyperbolic structure having a reservoir at the base for storage of cooled water o Diameter at the base is 150 m
  • 22. WATER TREATTENT PLANT The principle problem in high pressure boiler is to control corrosion and steam quality. The impurities present in water are as follows:- 1) Un-dissolved and suspended solid materials. 2) Dissolved slats and minerals. 3) Dissolved gases. 4) Other minerals (oil, acid etc.). 5). a) Turbidity & Sediment. b) Silica. c) Micro Biological. d) Sodium& Potassium Salt. e) Dissolved Sales Minerals. 6). a) O2gas. b) CO2 gas.
  • 23.  Pressure filter removes undisclosed impurities from raw water.  Carbon filter removes excess chlorine from clarified water.  D.M. plant removes dissolved impurities from clarified water.  Conductivity ,pH & silica content of this water must be checked time to time.
  • 24. ASH HANDLING PLANT The percentage of ash in coal varies from 5% in good quality coal to about 40% in poor quality coal Power plants generally use poor quality of coal , thus amount of ash produced by it is pretty large. Electrostatic Precipitator is used in ash handling plant to remove fly ash The stations use some conveyor arrangement to carry ash to dump sites directly or for carrying and loading it to trucks and wagons which transport it to the site of disposal
  • 25. UTILIZATION OF ASH 1. Manufacturing of building materials. 2. Making of concrete. 3. Manufacturing of cement. 4. Road construction etc.
  • 26. SWITCHYARD  Two 220 KV bus bars have been provided in switch yard and are inter-connected through a bus coupler.  Each station transformer has two windings one secondary side and is rated for 50/25/25mva, 270/7/7.2 kva four feeder take off from 220 switch yard two to SKATPURA GSS and other to HEERAPURA , Jaipur GSS. Each of four feeder are provided with bypass isolators which is connected across line breaker and breaker isolator
  • 27. SALIENT FEATURE OF K.S.T.P.S. LOCATION LOCATION -:Sakatpura, Kota. CAPACITY-: A) 1st Stage-: 2x110 MW . B) 2nd Stage-: 2x210 MW. C) 3rd Stage-: 1x210 MW. D) 4th Stage-: 1x195 MW. E) 5th Stage-: 1x195 MW SOURCE OF WATER- : Chambal River. BOILER-: a) Types. Fire tube boiler and Water tube boiler. b) No. of units . 7 c) Max. Efficiency. BHEL 87.6 % d) Capacity. 375 tonnes 1 Hr. e) Steam Pressure -:139 Kg./cm² f) Steam Temp. -:540
  • 28. CONCLUSION  The first phase of practical training has proved to be quiet fruitful. It provided an opportunity for encounter with such huge machines like wagon tippler .110 MW, 210 MW & 195 MW turbines and generators.  The architecture of the power plant the way various units are linked and the way working of whole plant is controlled make the student realize that engineering is not just learning the structured description and working of various machines, but the greater part is of planning proper management.  However training has proved to be quite fruitful. It has allowed an opportunity to get an exposure of the practical implementation to theoretical fundamentals.