Cleaner Production Assessment Methodology
• How Cleaner Production can be implemented in industries
Cleaner Production (CP) is a practical program with an organized approach where a
structured step-by-step methodology is followed. CP programs can be implemented in large,
medium and small enterprises in the manufacturing or service sector. Before implementing
CP, the top management of the enterprise should be convinced about the need and advantages
of CP and acknowledge the existence of environmental pollution and resource wastage within
the organization. Without the management consent and commitment, a CP program would
not be successful or take off ground. However, CP is not a program that can be carried out by
a single person or with only the involvement of management. A CP program requires the
involvement of all employees and is driven by a team comprising a cross section of all
employee categories. An important feature of a CP program is the involvement of floor-level
employees such as operators without whom any decision arrived at the table would not get
implemented. Therefore before implementing a CP program, an adequate awareness should
be given to the employees and training provided to the CP team.
Achieving Cleaner Production or waste avoidance/minimization and resource efficiency
require any or all of the following:
1. Applying know how – improved processes, ways of achieving higher efficiencies,
use of new and better quality materials, material and energy recovery and recycling etc.
2. Improving technology – replace inefficient and outdated technology, use low fuel
consuming, low waste generating equipment, use correct capacity and VSD pumps etc.
3. Changing attitudes – “out of the box” thinking or doing things differently, being
flexible and amenable to other suggestions etc.
The CP methodology can be simply represented by three logical steps and they can be
followed when implementing CP in industries.
1. Source inventory - Where and how much of waste and emissions are generated in the
process? This would give an idea of current wasteful processes and practices with baseline
quantities of waste generated
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
2. Cause evaluation - Why are waste and emissions generated? There can be many reasons
such as broken equipment, bad practices, inefficient processes etc.
3. Option generation - How can these causes be eliminated? Replacement of technology, new
process, improved training etc.
Ten steps for introducing Cleaner Production program in an enterprise are as follows:
• Develop and implement a comprehensive corporate environmental policy that focuses on
prevention.
• Set corporate goals for the Cleaner Production program, with specific percentages and
timetables.
• Allocate responsibility, time and financial support for the entire Cleaner Production program
• Involve employees at all levels
• Develop waste reduction audit procedures within the company and use them on a regular
basis to identify, evaluate and eliminate waste at each stage in the production process.
• Obtain and use the best possible technical and other information, from both inside and outside
the company.
• Monitor and evaluate the progress of the Cleaner Production program.
• Regularly inform all employees on the Cleaner Production progress made during the last
month, six months, year and five years.
• Encourage and reward successful individual and group efforts to implement Cleaner
Production
• Remember that success in Cleaner Production is a journey, not a destination. Update the
waste minimization goals and timetables on a regular basis.
The detailed methodology described below, is an extension of these logical steps.
• Different methodologies applied in the past (UNEP/UNIDO/Indian)
There had been 5 major CP methodologies used during the last 2 decades. They were
UNEP Standard Methodologies
Dutch PRISMA Methodology (PRISMA)
Indian DESIRE Methodology
Van Berkel Methodology
UNEP/ UNIDO standard Methodology
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
Among them Dutch PRISMA Methodology, Indian Desire Methodology and UNEP/ UNIDO
standard Methodology are more popular and widely used.
The Dutch PRISMA Methodology has for main phases/ steps. They are
Step 1 – Planning & Organization
Step 2 – Assessment
Step 3 – Feasibility Analysis
Step 4 – Implementation
The 4 steps are future divided into 15 tasks.
The following pages will describe in details the Indian DESIRE Methodology and UNEP/
UNIDO standard methodology with their different phases.
The Indian approach consists of six Steps or stages comprising eighteen Tasks. The six steps
of a CP program can be listed as follows:
STEP 1: GETTING STARTED: PLANNING AND ORGANISATION
STEP 2: ANALYSING PROCESS STEPS
STPE 3: GENERATING CP OPPORTUNITIES
STEP 4: FEASIBILITY ANALYSIS
STEP 5: IMPLEMENTING AND MONITORING
STEP 6: SUSTAINING CP
Each step comprises of several tasks that require data collection and analysis. A brief
description of each task is provided below.
STEP 1: GETTING STARTED: PLANNING AND ORGANISATION
TASK 1: Establishing a Cleaner Production Team
For successful conduction of CP program, it is essential to designate a team, which will work
in close coordination and be responsible for carrying out the program. A cross-functional and
multi-hierarchical team is necessary for smooth coordination during the various stages of
assessment and implementation. The size and composition of team should be according to
the company's organizational structure. Depending on the progress and audit focus, there may
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
be the need, from time to time, to introduce additional members having specific expertise
including external experts.
Functions of a CP Team
• Collection and compilation of baseline information
• Synthesis and prioritization of baseline information
• To identify Cleaner Production opportunities
• Review existing processes for improvement
• To convert opportunities into feasible solution
• Prepare time schedule and detailed project report for implementation of CP solution
• To continue and sustain implemented CP solutions
 Communicate CP practices to all employees.
TASK 2: List Process Steps and Identify Waste Streams
A broad overview of the unit operation is necessary to give an idea about important process
steps, areas of materials and energy usage and sources of waste generation. The major
process steps followed shall be listed in the sequence in which they are carried out. This is
often done by collecting existing information and shop-floor walk through. Simultaneously
the team should identify the various inputs and output streams at each process step.
TASK 3: Select Audit Focus
A common mistake in companies implementing a CP program is to focus on too many
different areas simultaneously. Production processes are complex operations including
several process steps and it is impractical to cover the entire production process at a time. To
make the execution of CP program effective and simple, it is suggested to start with one
process step or one section of unit. The selection of audit focus depends on several factors
like consumption of input resources, potential of Cleaner Production, impact of process step
on entire process or intensity of waste generation.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
STEP 2: ANALYSING PROCESS STEPS
This step covers the detailed data collection and evaluation for the audit focus and therefore
requires the following tasks:
TASK 4: Prepare Process Flow Charts
Preparation of accurate and detailed process follow chart is a key step in CPA analysis and
form the basis for good understanding of current operations, material balances. Flow charts
are schematic representation of the production process in the order in which it is carried out.
It shall include to the extent possible all the inputs and output streams. Special care should be
taken with recycle stream. Free or cheap inputs such as air, water should be included as these
often end up being major cause of waste. Occasional used materials and/or which do not
appear in normal flow diagram should also be recorded. Therefore in developing a process
flow diagram normal, abnormal, accidental and maintenance operation should be considered.
TASK 5: Collect Baseline Data
Establishing the status quo is important to provide necessary baseline for changes and
improvement and to establish CP indicators/benchmark. During this phase, the information
available from existing and previous reports is suggested, to have idea about consumption
pattern and actual cost of production, productivity level and efficiency of production in terms
of product per raw material inputs.
Baseline information should be as far as possible representative of all operating conditions.
Due consideration should be given to seasonal variations and operational variations.
Therefore, it is recommended that data shall be collected for at least for last financial year
preferably with monthly break-up, one month in current year and one day at the kick-off CP
project. Formats for recording and documenting information should be decided commonly so
that information is understandable to all team members.
TASK 6: Material and Energy Balance
a) Initial Review
Initial review includes classification, synthesis and prioritization of the baseline information
collected in the previous task. The initial review should be anticipatory and shall be used to
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
establish as is situation in the company, compare the existing operating procedures with other
similar type of industries and check the deviation.
b) Component Balance
Information collected from records and reports is generally not sufficient and major gaps are
experienced for conducting CP assessment. It is important that information on core and non-
core activities is available and collected data is reliable and representative. Material balances
are needed to quantify the occurring losses also which cannot be obtained in previous task. It
is important to make component balance for important resources e.g. water, total solids, fibre
in Pulp and Paper industries or dyestuff in textile industry.
c) Loss Balance
Waste stream characterization is important to assess pollution load, specific waste generation
and also help in back calculating the "Loss Balance" if component balance is problematic.
For energy component or loss balance is more involved and it may be sufficient to review the
quantities of fuel and electrical energy used e.g. yearly consumption, monthly consumption,
daily consumption and specific consumption (such as KWhr/T of product).
TASK 7: Assigning Costs to Waste Stream
To assess the economic potential of waste stream, it is essential to assign costs to the waste.
Costing shall include cost of raw material and intermediate product lost with the waste stream
(like fibre loss in the paper mills), processing cost of lost material, cost of product in waste
(waste noodles), cost of treatment of waste and waste disposal and taxes, if any. In assigning
costs a selection of the basis is important. It may be the raw material and cost, step by step
value addition basis or final product cost basis. Each has its own merits and demerits.
TASK 8: Review of Process to Identify Waste/Excess Resource Consumption
Causes
Depending upon data availability and its accuracy, review of the process should identify the
possible cause and effect of deviations from norms and waste generation. Often, substantial
resources and time is required to locate the causes of a problem and normally fish bone or
Ishikawa diagram is used. A wide variety of possible causes are considered, according to CP
waste cause analysis.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
STEP 3: GENERATING CLEANER PRODUCTION OPPORTUNITIES
Causes identified in task 8 are used to identify opportunities to eliminate these causes.
Generating CP opportunities is crucial and requires the following tasks:
TASK 9: Identifying CP Opportunities
Equipped with detailed cause analysis, CP team shall start identifying various opportunities
to reduce the excessive consumption of input resources and/or reducing the waste generation.
Techniques such as brain-storming and group discussions should be used to determine a
range of options as broad as can be produced by the team’s knowledge and creativity. During
option generation, external help, personnel from similar mills, academic and sectoral research
institute, technology supplier and CP experts shall be solicited. At this stage all possible
opportunities should be listed and their influence on process or other waste stream shall be
recorded.
TASK 10: Preliminary Screening of CP Opportunities
At this stage, a preliminary screening of CP opportunities has to be done to select workable
CP options and weed out which are impractical. Weeding out task should be simple and
often qualitative based on CP team experience and it is done to reduce the efforts for detailed
feasibility analysis. For example, an option could be rejected by CP team due to following
reasons:
- Although technically suited but might be very expensive and unaffordable for the industry
- Implementation of the option is complicated and requires large resources like technical
manpower
- The option poses possible risk to the production and product quality
- The option is not yet proven
Under this task, options are classified into following four (4) categories:
(i) Rejected (R) - impractical at present
(ii) Directly Implementable (DI) - Simple and obvious
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
(iii) Require Future Analysis (RFA)
a) Require field trials to ensure no negative impact on quality
b) Requires detailed feasibility analysis.
STEP 4: FEASIBILITY ANALYSIS
For CP options listed in category (iv) above, detailed analysis has to be carried out in terms of
technical feasibility, economic feasibility and environmental assessment.
TASK 11: Assess Technical Feasibility
It is important to assess whether identified option is technically feasible or not considering
the following aspects.
• Process and Technology description
• Availability of required hardware
• Practicality of implementation and operation e.g. required space for new
equipments, technical capability to operate and maintain
• Quality - At least neutral (no negative effect on quality)
• Reliability - Risk in its effectiveness
• Safety - No additional safety hazard
During technical feasibility analysis assistance from manufacturer or provider of service,
consultants and experts shall be considered.
TASK 12: Assess Economic Viability
Economic viability often becomes the key parameter for the management acceptance or
rejection of proposed CP measure. In assessing economic viability, in addition to capital
costs, additional operating cost, maintenance cost, interest and depreciation of equipment and
machinery shall be included. For low cost CP option analysis, normally pay-back period
indicator is used whereas for high cost options, Internal Rate of Return (IRR) and Net Present
Value (NPV) can be used. Today business world considered any investment which has an
economic pay back less than 4 years as good.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
TASK 13: Environmental Assessment
CP option must be assessed in respect to their impact on environment as:
• Expected benefit from the option
• Nature of benefits
• Is the solution long term or short term?
Any option assessed to have negative impact on environment shall be dropped. In many
cases, it is not possible to quantify the impact, in such cases qualitative judgment on
reduction in pollution toxicity or the pollution load can be used.
TASK 14: Select Solutions for Implementation
An important activity in this task is to pay attention to the integrated evaluation of CP
options. Cause effect documented during evaluation are useful to understand the inter
relationship between options. Implementing one option might affect the need, or operations
of another option. To ensure effective CP implementation, it is necessary to look at the
options collectively so as to nullify any cumulative adverse effects or draw advantage from
their synergetic relationship.
STEP 5: IMPLMENTING CP SOLUTION AND MONITORING RESULTS
In any industry, major percentage of CP solutions is of low cost/no cost category and their
implementation start even during assessment phase as soon as they are identified. Cost
intensive solutions require a systematic plan of implementation.
TASK 15: Prepare Implementation Plan
Implementation plan is the document to be used for prioritizing implementing of Cleaner
Production solutions selected in previous task. For implementation of CP solution, it is
necessary to know the following: location of CP solution, category of CP solution, resources
necessary for implementation, professional & skills requirement, resources necessary for
implementation, down time required for implementation, responsibility matrix and task
allocation in teams, financial implication and their availability, target set for completion of
implementation etc.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
TASK 16: Implementing Cleaner Production Solutions
Similar to any other project for modification or expansion, CP solution involves planning,
scheduling, design, procurement, construction and commissioning. Depending upon
complexity of the project and availability of internal resources, there may be need to get
external assistance. Training of human resource is necessary to sustain the implementation.
TASK 17: Monitor and Evaluate Results
CP solutions after completion of implementation and commissioned, must be monitored and
evaluated. This task is important from the perspective of continual nature of CP process.
Once the solution has been implemented, it is necessary to compare the results achieved with
those estimated during feasibility analysis.
STEP 6: SUSTAINING CLEANER PRODUCTION PROGRAMME
Sustaining a CP program is a challenge. Efforts should be made to integrate CP with
company's routine planning process. Key to long term success is involvement of as many
employees as possible, training of staff and schemes of incentives and rewards for those who
specially perform well.
TASK 18: Identify another Audit Focus
Having audited and successfully implemented the 1st focus, CP team should go back to
TASK 3 to identify and select next important section or area as audit focus. This cycle
continues until all sections are completed and then come back to 1st audit focus to explore
more CP opportunities.
Cleaner Production philosophy must be developed within the company and integrated into its
activities. All successful Cleaner Production programs have been founded on this premise.
• Standard UNIDO, UNEP Cleaner Production methodology
The UNIDO/UNEP methodology is similar to the Indian NCPC methodology described
above with six stages and several tasks under each stage. The six stages and the sub tasks
under each such stage can be presented as below.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
Step 1: Getting started
1.1 Designate CP team
1.2 List process steps
1.3 Select assessment focus
Step 2: Analyzing process steps
2.1 Prepare flow chart
2.2 Make material & energy balances
2.3 Assign costs to waste streams
2.4 Review waste causes
Step 3: Generating CP opportunities
3.1 Develop CP opportunities
3.2 Select workable CP opportunities
Step 4: Selecting CP opportunities
4.1 Assess technical feasibility
4.2 Assess financial viability
4.3 Evaluate environmental aspects
4.4 Select solutions for
implementation
Step 5: Implementing CP solutions
5.1 Prepare implementation
5.2 Execute CP implementation
5.3 Monitor and evaluate results
Step 6: Sustaining CP solutions
6.1 Sustain CP solutions
6.2 Select wasteful process steps
A brief description of each stage, task and the outcome from each task is provided below.
STEP 1: GETTING STARTED - Sufficient interest and awareness is required prior to
initiating Step 1. Step 1 constitutes three specific tasks and on completion of the tasks, the CP
team is ready to move into step 2 with the selection of the audit focus.
Task 1.1: Designate CP Team
The designated CP team should be capable of identifying opportunities, developing solutions
and implementing them. The size and composition of the team depend on the structure of the
organization with the different functions/stakeholders being represented. CP team members
may include: Works/Production Manager; Maintenance Manager; Shop Floor Personnel:
Engineers, Supervisors, Workers; Finance/Purchase/Sales Representative; Quality Controller;
External Expert etc. Such a CP team will have authority, knowhow and capability to carryout
subsequent tasks.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
Task 1.2: List Process Steps
Specify all processes, including production, material handling, storage, utilities etc. Special
attention should be given to occasional processes such as cleaning. Identify most important
inputs and outputs to each process, including materials, energy, water, wastes and emissions.
At the end of this task, a complete qualitative account of all major processes and
material and energy flows (including wastes) is available to the CP team.
Task 1.3: Select Assessment Focus
Based on the available data from Task 1.2, the team should select one or few manageable CP
opportunities for further study. The selection could be based on either economic
considerations (e.g. monetary losses with waste streams/ high cost incurred) or environmental
considerations (e.g. volume and composition of waste streams) or technical considerations
(e.g. expected improvement potential). The outcome from this task is the availability of one
or few CP opportunities for further study.
STEP 2: ANALYZING PROCESS STEPS - This step consists of analysis. The qualitative
data obtained in Step 1 is mapped and converted to quantitative form by applying the laws of
conservation of mass and energy. Subsequently, these flows are expressed in economic terms
and cause evaluation is carried out for the material and energy losses.
Task 2.1: Prepare Flow Chart
Fig.1: Process block diagram for brown stock washing
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
A process block diagram should be drawn based on the arrangement of processes and
material and energy flows into and out of the processes in the organization. The process block
diagram is the pictorial representation of the data obtained in Task 1.2 (Process listing) with
linking of unit operations with material flows with matching of inputs and outputs. The flow
chart enables to quickly assign waste streams to unit operations and pinpoint operations in the
organization.
Task 2.2: Make Material and Energy Balances
Material and energy balances should be applied to each and every unit operation in the flow
chart to quantitatively express the flow streams into and out of the processes. The balance
principle based on law of conservation of mass could be simply expressed as:
Material in + material generated = material out + material consumed + material accumulated
The basis for analysis can be selected as appropriate as per time or per ton of production etc.
The most challenging aspect of conducting balances is obtaining accurate and appropriate
data. Where records are maintained and measuring devices are available, such data could be
made use of. In the absence of such data, the team is required to measure and monitor using
both direct and indirect methods for quantification. The data sources can be from on-site
measurements; purchase and sales records; production records etc. However, all data
obtained should be assessed for quality, reliability, accuracy and representativeness. All the
data should be converted to consistent units such as kg/day and kW etc. The more expensive
or toxic the materials are, the more precise the balance should be. Balances are more
meaningful if made for each constituent material. Simple cross checks can help reveal
inconsistencies.
On completion of this task, a complete quantitative picture of material and energy flows
within the organization is available to the team.
Task 2.3: Assign Costs to Waste Streams
Material and energy quantities are not understood by many non technical personnel and it is
convenient to express these in financial terms so that a common and easy to understand unit
is used and the magnitude of the losses can be easily comprehended by all. In converting
waste stream to costs, both internal and external cost components and cumulative costs due to
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
flow of material and energy through different operations should be taken into consideration.
The internal costs such as loss of raw materials and (intermediate) product; operation of
treatment facilities; waste collection and handling and external costs such as discharge fees;
levies, permit cost need to be apportioned for a realistic cost estimate.
Task 2.3 will enable the team to determine the waste streams with most economic loss.
Task 2.4: Review Waste Causes
Cause analysis is carried out prior to option generation to determine the causes for waste
streams. Factors such as product specifications, choice and quality of input materials,
technical factors (process/equipment design, equipment/piping layout, monitoring equipment
etc.), operating practices (production planning, operating procedures, maintenance schedules,
worker training) and waste handling procedures can be reasons for generation of waste.
This review would produce reason / reasons for waste generation which is required for the
subsequent option generation task.
At the end of Step 2, a listing of process waste sources and causes is available to the
team.
STEP 3: GENERATING CP OPPORTUNITIES – The third and the vital step involves
determining the ways and means by which the waste streams could be eliminated or reduced.
This step would provide the team with a listing of CP opportunities to avoid or minimize
waste.
Task 3.1: Develop CP Opportunities
Development of CP opportunities can be carried out in several ways. Brainstorming in project
team to find out ways of overcoming obstacles by pooling of thoughts from different
backgrounds of team members and by encouraging innovative thinking to solve the problem
at hand. The team can solicit ideas from outside the project team by inviting persons with
expertise and/or experience or encourage all players in enterprise to submit ideas by offering
a reward scheme. In cases where the problem at hand has been solved previously, such
information could be obtained through data bases, manuals, earlier CP reports etc.
Technology surveys and benchmarks may indicate opportunities and potential for
improvements by comparison.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
The following prevention practices can be explored in looking for CP opportunities: Product
modification, input material change, technology change, equipment modification, better
process control, good housekeeping, on site reuse or recovery, production of useful by
products.
At the end, the team will possess a list of CP opportunities for each waste stream considered.
Task 3.2: Select Workable CP Opportunities
Among the large number of CP opportunities generated above, selection of workable
opportunities is performed by initially screening the options into the following three
categories:
a) Implement obviously feasible options
b) Reject obviously non-feasible options
c) Remaining options - conduct feasibility analysis
Only opportunities in category c) need further analysis. These opportunities can be subjected
to a preliminary evaluation based on ease of implementation; expected technical feasibility;
expected economic feasibility; expected reduction of waste/emission. The team can involve
appropriate experts and technicians in the preliminary evaluation of opportunities.
At the completion of step 3 the industry will have a list of CP solutions.
STEP 4: SELECTING CP OPPORTUNITIES – This step is for performance improvement.
Through a very structured methodology, the opportunities in category c) above are further
evaluated based on technical feasibility, financial viability and environmental desirability. By
this step a list of CP solutions can be obtained after screening out the CP opportunities.
Task 4.1: Assess Technical Feasibility
If the CP opportunity is not technically feasible, there is no possibility of implementation.
Opportunities that fail this assessment are rejected. Technical feasibility can be assessed
based on availability and reliability of equipment, requirements for utilities, process
monitoring and control, space, maintenance requirements, required technical skills (operators,
technicians etc.) etc. On completion of Task 4.1, the CP opportunities can be narrowed down
to opportunities that have to be assessed against financial and environmental assessment.
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
Task 4.2: Assess Financial Viability
Table 1. Operational benefits for a technological change
This is a key task and criteria for many organizations in selecting CP solutions. Almost all CP
solutions will result in financial gain. Financial viability assessment requires data on
investments such as equipment, construction, training, start up etc., operational cost and
possible cost savings. A cost comparison is done between pre and post implementation
scenario. An example of operational benefits for replacement of pouches washer by double
screw press with 2-stage vacuum drum washer is shown in Table 1. Depending on the
organization’s accounting practices and financial policies, any of the economic instruments
such as simple pay back, dynamic pay back, Net Present Value (NPV), Internal Rate of
Return (IRR) can be employed to determine the financial viability of the CP opportunity.
Payback period = investment / net extra cash flow
This indicates how fast the investment is recovered and is a quick indicator of the risk of
investment. Payback period is appropriate for small investments / projects.
NPV = ∑
𝑁𝑒𝑡 𝑒𝑥𝑡𝑟𝑎 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤
(1+𝑖) 𝑗
𝑛
𝑗=1 − 𝐼,
where n = depreciation time (years)
i = annual interest rate (%)
I = total investment
IRR = ∑
𝑁𝑒𝑡 𝑒𝑥𝑡𝑟𝑎 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤
(1+𝑟) 𝑗
𝑛
𝑗=1 − 𝐼 = 0,
where r = internal rate of return
consumption rates unit price before after difference benefit
black pulp US$ 110/ton 480 ton/day 480 ton/day 0 ton/day US$ 0/day
labour US$ 5/hr 120 hr/day 96 hr/day -24 hr/day US$ 120/day
energy US$ 0.1/kWh 2,400 kWh/day 1,600 kWh/day -800 kWh/day US$ 80/day
water US$ 0.1/rn3
4,000 m3
/day 1,000 rn3
/day -3,000 rn3
/day US$ 30/day
washed pulp US$ 75/ton 780 ton/day 786 ton/day 6 ton/day US$ 450/day
conc. black liquor US$ 0.2/ton 0 ton/day 85 ton/day 85 ton/day US$ 17/day
wash water US$ 0.05 m3
3,550 m3
/day 615 m3
/day -2,935 m3
/day US$ 147/day
TOTAL US$ 844/day
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
The CP team should come to a consensus on a decision criterion prior to calculating the
return on investment. A typical decision criterion can be as below.
1. Payback time:
< 1-2 years (low-cost project)
< 3-4 years (medium cost project)
< 5 years (high cost project)
2. Net Present Value >> 0 (after depreciation time)
3. Internal Rate of Return >> bank interest rate
At the end of this task, the CP team can further screen out CP opportunities that do not come
within the organizations project financial criteria and subject the viable options to
environmental assessment.
Task 4.3: Evaluate Environmental Aspects
If the option does not have a positive environmental effect, such options are not CP options.
The options can be evaluated for environmental improvements such as reduction in quantity
of pollutants and waste generated; reduction of pollutant/waste toxicity; reduction in
materials consumption; reduction in use of non-renewable materials; reduction in energy
consumption; reduction in consumption of energy from non-renewable resources; reduction
of water consumption; reduction of “nuisance” noise, dust, smoke, smell, etc.
CP opportunities that have a positive environmental benefit are solutions that can be
implemented.
Task 4.4: Select Solutions for Implementation
There can be significant number of solutions after the above screening procedure that can be
implemented. The CP team can decide on an appropriate methodology such as weighted
average matrix method to prioritize the solutions giving suitable weightage to technical,
economic and environmental aspects of the CP solution. For example, an enterprise may give
higher priority to solutions with no cost/low cost or with higher return on investment.
Properly document expected results and benefits for each option to facilitate fund raising and
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
monitoring of implementation results. Task 4.4 will provide ranking of the solutions for
implementation.
On completion of step 4 the industry will have a prioritized list of CP solutions and an
implementation list.
STEP 5: IMPLEMENT CP SOLUTIONS – The vital practical step of implementation is
carried out under step 5. Preparation, execution and monitoring of the CP solutions are
covered here. The outcome at the end of this step is the successfully implemented CP
solutions.
Task 5.1: Prepare for Implementation
Prior to execution of the CP solution detailed preparations are required, especially for
technical and technological changes. In cases of technology changes detailed technical
equipment specifications need to be written for procurement; detailed construction plans
should be prepared for installation of equipment; comparative evaluation of equipment from
different suppliers and final selection should be made and planning to reduce installation
downtime need to be ensured. Adequate advanced preparation would reduce disruption to
production and ensure a smooth transition to the new conditions. At the end of this task, a
well planned program of action is in place for execution of the CP solution.
Task 5.2: Execute CP Implementation
Once procurement is completed, new constructions and installations can be supervised and
executed according to the plan. This period can also be utilized for preparation for start up by
purchasing start up chemicals, spare parts etc.; preparing preventive maintenance schedule
and training operators, supervisors and technicians. On completion of this task, the CP
solutions are implemented and are ready to monitor and evaluate results.
Task 5.3: Monitor and Evaluate Results
The implemented CP solutions need to be monitored to gather data for evaluation, of
achievements against estimation. Measurement and monitoring should be for change in waste
quantities; change in resource consumption or changes in profitability. These should be
monitored and recorded together with changes in total production output and changes in
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
products. Any negative changes should be reviewed immediately as it indicate s not
achieving desired results.
Once sufficient data is gathered over a period, progress can be evaluated by comparing
measured benefits with expected benefits; identifying ways to further improve the benefits of
the technical installations and verifying whether installation and operation are according to
specifications.
STEP 6: SUSTAIN CP SOLUTIONS – The final step is to sustain the CP activity in keeping
with continuous improvement and the PDCA cycle. The implemented CP solutions need to
be continued and new CP opportunities need to be implemented by following the same steps
as above. The outcome of this step is the continuation of CP activity.
Task 6.1: Sustain CP Solutions
In order to sustain CP activity, planning, changes to organizational structure, employee
involvement and technical development are required. Planning elements are setting up of
organizational structure for CP; involvement of employees through training and incentives;
adoption of long-term CP strategies and policies and integration of CP into technical
development. The changes to the organizational structure are assigning key responsibility to
implementing CP to the production departments; making managers and supervisors
accountable for waste generation and formalizing participation of technical and
environmental departments in further improvements.
In order to sustain CP culture the human resources need to be continuously educated and
motivated to change their attitudes. Further, CP benefits from good two-way internal
communication practices and these needs to be formerly established and fostered. To
motivate the staff and reward the champions of CP, an appropriate reward scheme can be
implemented. Technologically, scheduling of preventive maintenance, checking of
environmental performance of new equipment and integration of CP concepts in
technological research and development can help in sustaining CP in the enterprise.
Task 6.2: Select Wasteful Process Steps
The last task in CP methodology is selection of new set of wasteful processes. In selecting a
process, the seriousness of waste/emission generation; the internal and external
A product of National Cleaner Production Centre Sri Lanka may be used for training
programmes by others with acknowledgement.
environmental costs; the managerial level and the expected improvement potential is taken
into account. Based on the above, the most promising focuses are selected, for the next round
of CP.
• Detail description of different types of audits.
1. Walkthrough Assessments / Quick Scan Assessments
A Walk-through Audit (WA) also known as a quick scan audit is used in Cleaner Production
to carry out a rapid assessment of an industry or service organization. It is usually conducted
during a span of 2-3 hours to familiarize oneself with the processes and activities being
carried out. WA is an excellent way to carry out the initial environmental assessment of a
company as it will allow the CP consultant and team to get a broad level understanding of the
operations and possible environmental impacts of the relative sector. No measurements are
taken during a walk through assessment. Walkthrough assessments are usually carried out as
a precursor to a comprehensive / short audit.
2. Short Cleaner Production Assessments
This type of assessment is very similar to a comprehensive assessment though the detailing
can be less. Also the duration for the assessment will be shorter, usually involving only 5 – 7
man days. In a short CP audit sample material & energy be concerns our measurements are
done to a limited extent. The conclusions will be based on historically recorded data.
3. Comprehensive Assessments
A Comprehensive Cleaner Production Assessment is an in-depth assessment carried out at an
industry following the 6 Step, 18 Task methodology developed by UNEP and UNIDO. This
type of assessment usually takes more than 10 man days to complete and involves a
systematic study and analysis of the processes and activities taking place within the industry.
The focus of a comprehensive audit is the resource flow within the total process in order to
identify waste generation sources and causes. It also involves carrying out measurements in
order to develop an accurate understanding of what, where and how waste is being generated.
At the end of the assessment a detailed audit report is presented to the company listing out
options for waste avoidance / minimization.

More Related Content

What's hot

Efflunt treatment plant ppt
Efflunt treatment plant pptEfflunt treatment plant ppt
Efflunt treatment plant ppt
Rajat Thapliyal
 

What's hot (20)

Aeration method
Aeration methodAeration method
Aeration method
 
Treatment And Disposal Of Sludge
Treatment And Disposal Of SludgeTreatment And Disposal Of Sludge
Treatment And Disposal Of Sludge
 
Tertiary treatment
Tertiary treatmentTertiary treatment
Tertiary treatment
 
Properties of solid waste
Properties of solid wasteProperties of solid waste
Properties of solid waste
 
Cleaner production
Cleaner productionCleaner production
Cleaner production
 
L 2 effluent standards and stream standards
L 2 effluent standards and stream standardsL 2 effluent standards and stream standards
L 2 effluent standards and stream standards
 
Sludge handling and disposal
Sludge handling and disposalSludge handling and disposal
Sludge handling and disposal
 
Processing of Solid Waste
Processing of Solid Waste Processing of Solid Waste
Processing of Solid Waste
 
Sedimentation Tanks: Design and Working
Sedimentation Tanks: Design and WorkingSedimentation Tanks: Design and Working
Sedimentation Tanks: Design and Working
 
Cleaner production
Cleaner productionCleaner production
Cleaner production
 
Waste minimization - Municipal Solid Wastes
Waste minimization - Municipal Solid WastesWaste minimization - Municipal Solid Wastes
Waste minimization - Municipal Solid Wastes
 
Sludge management and Sludge digesters
Sludge management and Sludge digestersSludge management and Sludge digesters
Sludge management and Sludge digesters
 
Concept of cetp
Concept of cetpConcept of cetp
Concept of cetp
 
Sludge thickening and stabilization processes
Sludge thickening and stabilization processes  Sludge thickening and stabilization processes
Sludge thickening and stabilization processes
 
Aerobic Composting method
Aerobic Composting methodAerobic Composting method
Aerobic Composting method
 
Efflunt treatment plant ppt
Efflunt treatment plant pptEfflunt treatment plant ppt
Efflunt treatment plant ppt
 
Leachate Treatment
Leachate TreatmentLeachate Treatment
Leachate Treatment
 
tannery industry operation, process and treatment
 tannery industry operation, process and treatment tannery industry operation, process and treatment
tannery industry operation, process and treatment
 
Design for Environment
Design for EnvironmentDesign for Environment
Design for Environment
 
Environmental audit methodology
Environmental audit methodologyEnvironmental audit methodology
Environmental audit methodology
 

Viewers also liked

Organizacindelalumnado 131109043152-phpapp01
Organizacindelalumnado 131109043152-phpapp01Organizacindelalumnado 131109043152-phpapp01
Organizacindelalumnado 131109043152-phpapp01
Elena Bermúdez Redrajo
 
水硬度的測定
水硬度的測定水硬度的測定
水硬度的測定
5045033
 
1 cite space导出文献数据
1 cite space导出文献数据1 cite space导出文献数据
1 cite space导出文献数据
cueb
 
光磊設備&技術
光磊設備&技術光磊設備&技術
光磊設備&技術
5045033
 
Tft Lcd 模組構裝技術
Tft Lcd 模組構裝技術Tft Lcd 模組構裝技術
Tft Lcd 模組構裝技術
5045033
 
Irene Cabrera - Diccionario Bilingüe Chile.
Irene Cabrera - Diccionario Bilingüe Chile.Irene Cabrera - Diccionario Bilingüe Chile.
Irene Cabrera - Diccionario Bilingüe Chile.
ills
 

Viewers also liked (20)

Organizacindelalumnado 131109043152-phpapp01
Organizacindelalumnado 131109043152-phpapp01Organizacindelalumnado 131109043152-phpapp01
Organizacindelalumnado 131109043152-phpapp01
 
水硬度的測定
水硬度的測定水硬度的測定
水硬度的測定
 
Slide tpe barth_planificación 3_primer período_kindergarten
Slide tpe barth_planificación 3_primer período_kindergartenSlide tpe barth_planificación 3_primer período_kindergarten
Slide tpe barth_planificación 3_primer período_kindergarten
 
Modelos para el trabajo de puntillismo de 4º eso
Modelos para el trabajo de puntillismo de 4º esoModelos para el trabajo de puntillismo de 4º eso
Modelos para el trabajo de puntillismo de 4º eso
 
Tulum
TulumTulum
Tulum
 
PORTFOLIO
PORTFOLIOPORTFOLIO
PORTFOLIO
 
Resume
ResumeResume
Resume
 
A 6 Pack for Event Marketers: Lessons from the Craft Beer Industry
A 6 Pack for Event Marketers: Lessons from the Craft Beer IndustryA 6 Pack for Event Marketers: Lessons from the Craft Beer Industry
A 6 Pack for Event Marketers: Lessons from the Craft Beer Industry
 
1 cite space导出文献数据
1 cite space导出文献数据1 cite space导出文献数据
1 cite space导出文献数据
 
光磊設備&技術
光磊設備&技術光磊設備&技術
光磊設備&技術
 
Tft Lcd 模組構裝技術
Tft Lcd 模組構裝技術Tft Lcd 模組構裝技術
Tft Lcd 模組構裝技術
 
7.klass tarkus tuleb tasapisi grammatika_pidama-vormid ja tähendused
7.klass tarkus tuleb tasapisi grammatika_pidama-vormid ja tähendused7.klass tarkus tuleb tasapisi grammatika_pidama-vormid ja tähendused
7.klass tarkus tuleb tasapisi grammatika_pidama-vormid ja tähendused
 
õNnetus ei hüüa tulles nimetav kääne.nimisõna.omadussõna
õNnetus ei hüüa tulles nimetav kääne.nimisõna.omadussõnaõNnetus ei hüüa tulles nimetav kääne.nimisõna.omadussõna
õNnetus ei hüüa tulles nimetav kääne.nimisõna.omadussõna
 
Irene Cabrera - Diccionario Bilingüe Chile.
Irene Cabrera - Diccionario Bilingüe Chile.Irene Cabrera - Diccionario Bilingüe Chile.
Irene Cabrera - Diccionario Bilingüe Chile.
 
Ejercicios ap. reproductor.doc
Ejercicios ap. reproductor.docEjercicios ap. reproductor.doc
Ejercicios ap. reproductor.doc
 
Bloque 5: aprendizaje de la lengua de signos como sistema alternativo de comu...
Bloque 5: aprendizaje de la lengua de signos como sistema alternativo de comu...Bloque 5: aprendizaje de la lengua de signos como sistema alternativo de comu...
Bloque 5: aprendizaje de la lengua de signos como sistema alternativo de comu...
 
лікарські рослини 1 в
лікарські рослини  1 влікарські рослини  1 в
лікарські рослини 1 в
 
ми здорове покоління!!!
ми здорове покоління!!!ми здорове покоління!!!
ми здорове покоління!!!
 
Crescent Pure- Harvard business case study
Crescent Pure- Harvard business case study Crescent Pure- Harvard business case study
Crescent Pure- Harvard business case study
 
Tema 5 excretor
Tema 5 excretorTema 5 excretor
Tema 5 excretor
 

Similar to 20 hand out on cp assessment methodology -samantha

CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1
Sherrill Moore
 
Super User Certification Program - Logistics Final v1.1
Super User Certification Program - Logistics Final v1.1Super User Certification Program - Logistics Final v1.1
Super User Certification Program - Logistics Final v1.1
Calvin Yong
 

Similar to 20 hand out on cp assessment methodology -samantha (20)

Process Improvement Teams.pptx
Process Improvement Teams.pptxProcess Improvement Teams.pptx
Process Improvement Teams.pptx
 
Standard operating procedures
Standard operating proceduresStandard operating procedures
Standard operating procedures
 
Program planning
Program planningProgram planning
Program planning
 
Quality improvement paradigm (QIP)
Quality improvement paradigm (QIP)Quality improvement paradigm (QIP)
Quality improvement paradigm (QIP)
 
Business management 1 A
Business management 1 A Business management 1 A
Business management 1 A
 
Continuous Process Improvement.pptx
Continuous Process Improvement.pptxContinuous Process Improvement.pptx
Continuous Process Improvement.pptx
 
Total Productive Maintenance (Tpm) EVERTS 21Aug2018
Total Productive Maintenance (Tpm) EVERTS 21Aug2018Total Productive Maintenance (Tpm) EVERTS 21Aug2018
Total Productive Maintenance (Tpm) EVERTS 21Aug2018
 
CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1CV-SAM JAN 2016 - application 1
CV-SAM JAN 2016 - application 1
 
Lean Production POM.pptx
Lean Production POM.pptxLean Production POM.pptx
Lean Production POM.pptx
 
TPM Total Productive Maintenance for Quarry Plant(2)
TPM Total Productive Maintenance for Quarry Plant(2) TPM Total Productive Maintenance for Quarry Plant(2)
TPM Total Productive Maintenance for Quarry Plant(2)
 
Introduction to Productivity SA presentation with GAD
Introduction to Productivity SA presentation with GADIntroduction to Productivity SA presentation with GAD
Introduction to Productivity SA presentation with GAD
 
Set up and implementing an effective wmp
Set up and implementing an effective wmpSet up and implementing an effective wmp
Set up and implementing an effective wmp
 
PACMTN Portfolio1
PACMTN Portfolio1PACMTN Portfolio1
PACMTN Portfolio1
 
Module-7-Program-Monitoring-and-Evaluation.pptx
Module-7-Program-Monitoring-and-Evaluation.pptxModule-7-Program-Monitoring-and-Evaluation.pptx
Module-7-Program-Monitoring-and-Evaluation.pptx
 
Cleaner production
Cleaner productionCleaner production
Cleaner production
 
Continous process improvement
Continous process improvementContinous process improvement
Continous process improvement
 
Lean Innovation for Micro Enterprises Module 7 Lean Innovation Processes
Lean Innovation for Micro Enterprises Module 7  Lean Innovation ProcessesLean Innovation for Micro Enterprises Module 7  Lean Innovation Processes
Lean Innovation for Micro Enterprises Module 7 Lean Innovation Processes
 
Chapter 11_ The role of quality in performance management.pdf
Chapter 11_ The role of quality in performance management.pdfChapter 11_ The role of quality in performance management.pdf
Chapter 11_ The role of quality in performance management.pdf
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
Super User Certification Program - Logistics Final v1.1
Super User Certification Program - Logistics Final v1.1Super User Certification Program - Logistics Final v1.1
Super User Certification Program - Logistics Final v1.1
 

More from zubeditufail

More from zubeditufail (20)

International Environmental Impact Assessment - Atkins.pdf
International Environmental Impact Assessment - Atkins.pdfInternational Environmental Impact Assessment - Atkins.pdf
International Environmental Impact Assessment - Atkins.pdf
 
The Holy Quran with Easy Word Meaning
The Holy Quran with Easy Word MeaningThe Holy Quran with Easy Word Meaning
The Holy Quran with Easy Word Meaning
 
Use of fungus bricks in construction sector
Use of fungus bricks in construction sectorUse of fungus bricks in construction sector
Use of fungus bricks in construction sector
 
SPMC training iso 45001 awareness
SPMC training iso 45001 awarenessSPMC training iso 45001 awareness
SPMC training iso 45001 awareness
 
SPMC - Pakistan training iso 14001 EMS awareness
SPMC - Pakistan training iso 14001 EMS awarenessSPMC - Pakistan training iso 14001 EMS awareness
SPMC - Pakistan training iso 14001 EMS awareness
 
SPMC - Pakistan training iso 9001 QMS awareness
SPMC - Pakistan training iso 9001 QMS awarenessSPMC - Pakistan training iso 9001 QMS awareness
SPMC - Pakistan training iso 9001 QMS awareness
 
SPMC - Pakistan Training Calendar 2020
SPMC - Pakistan Training Calendar 2020SPMC - Pakistan Training Calendar 2020
SPMC - Pakistan Training Calendar 2020
 
ISO 9001:2015 Life Cycle
ISO 9001:2015 Life Cycle ISO 9001:2015 Life Cycle
ISO 9001:2015 Life Cycle
 
CODEX HACCP Short Introduction
CODEX HACCP Short Introduction CODEX HACCP Short Introduction
CODEX HACCP Short Introduction
 
Pakistan Income Tax Ordinance amendment 2016
Pakistan Income Tax Ordinance amendment 2016Pakistan Income Tax Ordinance amendment 2016
Pakistan Income Tax Ordinance amendment 2016
 
Heat stroke by SPMCpk.com
Heat stroke by SPMCpk.comHeat stroke by SPMCpk.com
Heat stroke by SPMCpk.com
 
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCEAPPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
APPLICATION IN FORM - I FOR PRIOR ENVIRONMENTAL CLEARANCE
 
Resettlement Policy Framework - Karachi Neighborhood Improvement Project (KNIP)
Resettlement Policy Framework - Karachi Neighborhood Improvement Project (KNIP)Resettlement Policy Framework - Karachi Neighborhood Improvement Project (KNIP)
Resettlement Policy Framework - Karachi Neighborhood Improvement Project (KNIP)
 
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...
Environmental and Social Management Framework (ESMF) - Karachi Neighborhood I...
 
Ohsas 18001 self assessment checklist
Ohsas 18001 self assessment checklistOhsas 18001 self assessment checklist
Ohsas 18001 self assessment checklist
 
Draft2 guiding principles_and_recommendations_for_businesses_in_and_around_kb...
Draft2 guiding principles_and_recommendations_for_businesses_in_and_around_kb...Draft2 guiding principles_and_recommendations_for_businesses_in_and_around_kb...
Draft2 guiding principles_and_recommendations_for_businesses_in_and_around_kb...
 
A global standard_for_the_identification_of_key_biodiversity_areas_final_web
A global standard_for_the_identification_of_key_biodiversity_areas_final_webA global standard_for_the_identification_of_key_biodiversity_areas_final_web
A global standard_for_the_identification_of_key_biodiversity_areas_final_web
 
The Daily Dawn newspaper - millineium development goals report - Pakistan
The Daily Dawn newspaper - millineium development goals report - PakistanThe Daily Dawn newspaper - millineium development goals report - Pakistan
The Daily Dawn newspaper - millineium development goals report - Pakistan
 
shehri Letter to sepa
shehri Letter to sepashehri Letter to sepa
shehri Letter to sepa
 
EIA of Engro Powergen Limited 450 MW RLNG CCPP at PQA, Karachi Sep 29, 2015 b...
EIA of Engro Powergen Limited 450 MW RLNG CCPP at PQA, Karachi Sep 29, 2015 b...EIA of Engro Powergen Limited 450 MW RLNG CCPP at PQA, Karachi Sep 29, 2015 b...
EIA of Engro Powergen Limited 450 MW RLNG CCPP at PQA, Karachi Sep 29, 2015 b...
 

Recently uploaded

一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
zubnm
 
Heat Index related presentation ppt in india
Heat Index related presentation ppt in indiaHeat Index related presentation ppt in india
Heat Index related presentation ppt in india
SriSravani2
 

Recently uploaded (20)

2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
 
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
 
Understanding Air Quality Monitoring A Comprehensive Guide.pdf
Understanding Air Quality Monitoring A Comprehensive Guide.pdfUnderstanding Air Quality Monitoring A Comprehensive Guide.pdf
Understanding Air Quality Monitoring A Comprehensive Guide.pdf
 
A Review on Integrated River Basin Management and Development Master Plan of ...
A Review on Integrated River Basin Management and Development Master Plan of ...A Review on Integrated River Basin Management and Development Master Plan of ...
A Review on Integrated River Basin Management and Development Master Plan of ...
 
Production, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollenProduction, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollen
 
My Museum presentation by Jamilyn Gonzalez
My Museum presentation by Jamilyn GonzalezMy Museum presentation by Jamilyn Gonzalez
My Museum presentation by Jamilyn Gonzalez
 
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
 
slidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reuseslidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reuse
 
A Complete Guide to Understanding Air Quality Monitoring.pptx
A Complete Guide to Understanding Air Quality Monitoring.pptxA Complete Guide to Understanding Air Quality Monitoring.pptx
A Complete Guide to Understanding Air Quality Monitoring.pptx
 
Smart Watering Solutions for Your Garden
Smart Watering Solutions for Your GardenSmart Watering Solutions for Your Garden
Smart Watering Solutions for Your Garden
 
ADBB 5cladba Precursor JWH018 +85244677121
ADBB 5cladba Precursor JWH018 +85244677121ADBB 5cladba Precursor JWH018 +85244677121
ADBB 5cladba Precursor JWH018 +85244677121
 
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
 
Book ℂall Girls Navi Mumbai Hire Me Neha 9910780858 Top Class ℂall Girl Servi...
Book ℂall Girls Navi Mumbai Hire Me Neha 9910780858 Top Class ℂall Girl Servi...Book ℂall Girls Navi Mumbai Hire Me Neha 9910780858 Top Class ℂall Girl Servi...
Book ℂall Girls Navi Mumbai Hire Me Neha 9910780858 Top Class ℂall Girl Servi...
 
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
 
Christmas Palm Trees in Florida The Ultimate Guide to Festive Landscaping wit...
Christmas Palm Trees in Florida The Ultimate Guide to Festive Landscaping wit...Christmas Palm Trees in Florida The Ultimate Guide to Festive Landscaping wit...
Christmas Palm Trees in Florida The Ultimate Guide to Festive Landscaping wit...
 
Heat Index related presentation ppt in india
Heat Index related presentation ppt in indiaHeat Index related presentation ppt in india
Heat Index related presentation ppt in india
 
Water Pollution
Water Pollution Water Pollution
Water Pollution
 
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
 
Yil Me Hu Spring 2024 - Nisqually Salmon Recovery Newsletter
Yil Me Hu Spring 2024 - Nisqually Salmon Recovery NewsletterYil Me Hu Spring 2024 - Nisqually Salmon Recovery Newsletter
Yil Me Hu Spring 2024 - Nisqually Salmon Recovery Newsletter
 
Introduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxIntroduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptx
 

20 hand out on cp assessment methodology -samantha

  • 1. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. Cleaner Production Assessment Methodology • How Cleaner Production can be implemented in industries Cleaner Production (CP) is a practical program with an organized approach where a structured step-by-step methodology is followed. CP programs can be implemented in large, medium and small enterprises in the manufacturing or service sector. Before implementing CP, the top management of the enterprise should be convinced about the need and advantages of CP and acknowledge the existence of environmental pollution and resource wastage within the organization. Without the management consent and commitment, a CP program would not be successful or take off ground. However, CP is not a program that can be carried out by a single person or with only the involvement of management. A CP program requires the involvement of all employees and is driven by a team comprising a cross section of all employee categories. An important feature of a CP program is the involvement of floor-level employees such as operators without whom any decision arrived at the table would not get implemented. Therefore before implementing a CP program, an adequate awareness should be given to the employees and training provided to the CP team. Achieving Cleaner Production or waste avoidance/minimization and resource efficiency require any or all of the following: 1. Applying know how – improved processes, ways of achieving higher efficiencies, use of new and better quality materials, material and energy recovery and recycling etc. 2. Improving technology – replace inefficient and outdated technology, use low fuel consuming, low waste generating equipment, use correct capacity and VSD pumps etc. 3. Changing attitudes – “out of the box” thinking or doing things differently, being flexible and amenable to other suggestions etc. The CP methodology can be simply represented by three logical steps and they can be followed when implementing CP in industries. 1. Source inventory - Where and how much of waste and emissions are generated in the process? This would give an idea of current wasteful processes and practices with baseline quantities of waste generated
  • 2. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. 2. Cause evaluation - Why are waste and emissions generated? There can be many reasons such as broken equipment, bad practices, inefficient processes etc. 3. Option generation - How can these causes be eliminated? Replacement of technology, new process, improved training etc. Ten steps for introducing Cleaner Production program in an enterprise are as follows: • Develop and implement a comprehensive corporate environmental policy that focuses on prevention. • Set corporate goals for the Cleaner Production program, with specific percentages and timetables. • Allocate responsibility, time and financial support for the entire Cleaner Production program • Involve employees at all levels • Develop waste reduction audit procedures within the company and use them on a regular basis to identify, evaluate and eliminate waste at each stage in the production process. • Obtain and use the best possible technical and other information, from both inside and outside the company. • Monitor and evaluate the progress of the Cleaner Production program. • Regularly inform all employees on the Cleaner Production progress made during the last month, six months, year and five years. • Encourage and reward successful individual and group efforts to implement Cleaner Production • Remember that success in Cleaner Production is a journey, not a destination. Update the waste minimization goals and timetables on a regular basis. The detailed methodology described below, is an extension of these logical steps. • Different methodologies applied in the past (UNEP/UNIDO/Indian) There had been 5 major CP methodologies used during the last 2 decades. They were UNEP Standard Methodologies Dutch PRISMA Methodology (PRISMA) Indian DESIRE Methodology Van Berkel Methodology UNEP/ UNIDO standard Methodology
  • 3. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. Among them Dutch PRISMA Methodology, Indian Desire Methodology and UNEP/ UNIDO standard Methodology are more popular and widely used. The Dutch PRISMA Methodology has for main phases/ steps. They are Step 1 – Planning & Organization Step 2 – Assessment Step 3 – Feasibility Analysis Step 4 – Implementation The 4 steps are future divided into 15 tasks. The following pages will describe in details the Indian DESIRE Methodology and UNEP/ UNIDO standard methodology with their different phases. The Indian approach consists of six Steps or stages comprising eighteen Tasks. The six steps of a CP program can be listed as follows: STEP 1: GETTING STARTED: PLANNING AND ORGANISATION STEP 2: ANALYSING PROCESS STEPS STPE 3: GENERATING CP OPPORTUNITIES STEP 4: FEASIBILITY ANALYSIS STEP 5: IMPLEMENTING AND MONITORING STEP 6: SUSTAINING CP Each step comprises of several tasks that require data collection and analysis. A brief description of each task is provided below. STEP 1: GETTING STARTED: PLANNING AND ORGANISATION TASK 1: Establishing a Cleaner Production Team For successful conduction of CP program, it is essential to designate a team, which will work in close coordination and be responsible for carrying out the program. A cross-functional and multi-hierarchical team is necessary for smooth coordination during the various stages of assessment and implementation. The size and composition of team should be according to the company's organizational structure. Depending on the progress and audit focus, there may
  • 4. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. be the need, from time to time, to introduce additional members having specific expertise including external experts. Functions of a CP Team • Collection and compilation of baseline information • Synthesis and prioritization of baseline information • To identify Cleaner Production opportunities • Review existing processes for improvement • To convert opportunities into feasible solution • Prepare time schedule and detailed project report for implementation of CP solution • To continue and sustain implemented CP solutions  Communicate CP practices to all employees. TASK 2: List Process Steps and Identify Waste Streams A broad overview of the unit operation is necessary to give an idea about important process steps, areas of materials and energy usage and sources of waste generation. The major process steps followed shall be listed in the sequence in which they are carried out. This is often done by collecting existing information and shop-floor walk through. Simultaneously the team should identify the various inputs and output streams at each process step. TASK 3: Select Audit Focus A common mistake in companies implementing a CP program is to focus on too many different areas simultaneously. Production processes are complex operations including several process steps and it is impractical to cover the entire production process at a time. To make the execution of CP program effective and simple, it is suggested to start with one process step or one section of unit. The selection of audit focus depends on several factors like consumption of input resources, potential of Cleaner Production, impact of process step on entire process or intensity of waste generation.
  • 5. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. STEP 2: ANALYSING PROCESS STEPS This step covers the detailed data collection and evaluation for the audit focus and therefore requires the following tasks: TASK 4: Prepare Process Flow Charts Preparation of accurate and detailed process follow chart is a key step in CPA analysis and form the basis for good understanding of current operations, material balances. Flow charts are schematic representation of the production process in the order in which it is carried out. It shall include to the extent possible all the inputs and output streams. Special care should be taken with recycle stream. Free or cheap inputs such as air, water should be included as these often end up being major cause of waste. Occasional used materials and/or which do not appear in normal flow diagram should also be recorded. Therefore in developing a process flow diagram normal, abnormal, accidental and maintenance operation should be considered. TASK 5: Collect Baseline Data Establishing the status quo is important to provide necessary baseline for changes and improvement and to establish CP indicators/benchmark. During this phase, the information available from existing and previous reports is suggested, to have idea about consumption pattern and actual cost of production, productivity level and efficiency of production in terms of product per raw material inputs. Baseline information should be as far as possible representative of all operating conditions. Due consideration should be given to seasonal variations and operational variations. Therefore, it is recommended that data shall be collected for at least for last financial year preferably with monthly break-up, one month in current year and one day at the kick-off CP project. Formats for recording and documenting information should be decided commonly so that information is understandable to all team members. TASK 6: Material and Energy Balance a) Initial Review Initial review includes classification, synthesis and prioritization of the baseline information collected in the previous task. The initial review should be anticipatory and shall be used to
  • 6. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. establish as is situation in the company, compare the existing operating procedures with other similar type of industries and check the deviation. b) Component Balance Information collected from records and reports is generally not sufficient and major gaps are experienced for conducting CP assessment. It is important that information on core and non- core activities is available and collected data is reliable and representative. Material balances are needed to quantify the occurring losses also which cannot be obtained in previous task. It is important to make component balance for important resources e.g. water, total solids, fibre in Pulp and Paper industries or dyestuff in textile industry. c) Loss Balance Waste stream characterization is important to assess pollution load, specific waste generation and also help in back calculating the "Loss Balance" if component balance is problematic. For energy component or loss balance is more involved and it may be sufficient to review the quantities of fuel and electrical energy used e.g. yearly consumption, monthly consumption, daily consumption and specific consumption (such as KWhr/T of product). TASK 7: Assigning Costs to Waste Stream To assess the economic potential of waste stream, it is essential to assign costs to the waste. Costing shall include cost of raw material and intermediate product lost with the waste stream (like fibre loss in the paper mills), processing cost of lost material, cost of product in waste (waste noodles), cost of treatment of waste and waste disposal and taxes, if any. In assigning costs a selection of the basis is important. It may be the raw material and cost, step by step value addition basis or final product cost basis. Each has its own merits and demerits. TASK 8: Review of Process to Identify Waste/Excess Resource Consumption Causes Depending upon data availability and its accuracy, review of the process should identify the possible cause and effect of deviations from norms and waste generation. Often, substantial resources and time is required to locate the causes of a problem and normally fish bone or Ishikawa diagram is used. A wide variety of possible causes are considered, according to CP waste cause analysis.
  • 7. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. STEP 3: GENERATING CLEANER PRODUCTION OPPORTUNITIES Causes identified in task 8 are used to identify opportunities to eliminate these causes. Generating CP opportunities is crucial and requires the following tasks: TASK 9: Identifying CP Opportunities Equipped with detailed cause analysis, CP team shall start identifying various opportunities to reduce the excessive consumption of input resources and/or reducing the waste generation. Techniques such as brain-storming and group discussions should be used to determine a range of options as broad as can be produced by the team’s knowledge and creativity. During option generation, external help, personnel from similar mills, academic and sectoral research institute, technology supplier and CP experts shall be solicited. At this stage all possible opportunities should be listed and their influence on process or other waste stream shall be recorded. TASK 10: Preliminary Screening of CP Opportunities At this stage, a preliminary screening of CP opportunities has to be done to select workable CP options and weed out which are impractical. Weeding out task should be simple and often qualitative based on CP team experience and it is done to reduce the efforts for detailed feasibility analysis. For example, an option could be rejected by CP team due to following reasons: - Although technically suited but might be very expensive and unaffordable for the industry - Implementation of the option is complicated and requires large resources like technical manpower - The option poses possible risk to the production and product quality - The option is not yet proven Under this task, options are classified into following four (4) categories: (i) Rejected (R) - impractical at present (ii) Directly Implementable (DI) - Simple and obvious
  • 8. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. (iii) Require Future Analysis (RFA) a) Require field trials to ensure no negative impact on quality b) Requires detailed feasibility analysis. STEP 4: FEASIBILITY ANALYSIS For CP options listed in category (iv) above, detailed analysis has to be carried out in terms of technical feasibility, economic feasibility and environmental assessment. TASK 11: Assess Technical Feasibility It is important to assess whether identified option is technically feasible or not considering the following aspects. • Process and Technology description • Availability of required hardware • Practicality of implementation and operation e.g. required space for new equipments, technical capability to operate and maintain • Quality - At least neutral (no negative effect on quality) • Reliability - Risk in its effectiveness • Safety - No additional safety hazard During technical feasibility analysis assistance from manufacturer or provider of service, consultants and experts shall be considered. TASK 12: Assess Economic Viability Economic viability often becomes the key parameter for the management acceptance or rejection of proposed CP measure. In assessing economic viability, in addition to capital costs, additional operating cost, maintenance cost, interest and depreciation of equipment and machinery shall be included. For low cost CP option analysis, normally pay-back period indicator is used whereas for high cost options, Internal Rate of Return (IRR) and Net Present Value (NPV) can be used. Today business world considered any investment which has an economic pay back less than 4 years as good.
  • 9. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. TASK 13: Environmental Assessment CP option must be assessed in respect to their impact on environment as: • Expected benefit from the option • Nature of benefits • Is the solution long term or short term? Any option assessed to have negative impact on environment shall be dropped. In many cases, it is not possible to quantify the impact, in such cases qualitative judgment on reduction in pollution toxicity or the pollution load can be used. TASK 14: Select Solutions for Implementation An important activity in this task is to pay attention to the integrated evaluation of CP options. Cause effect documented during evaluation are useful to understand the inter relationship between options. Implementing one option might affect the need, or operations of another option. To ensure effective CP implementation, it is necessary to look at the options collectively so as to nullify any cumulative adverse effects or draw advantage from their synergetic relationship. STEP 5: IMPLMENTING CP SOLUTION AND MONITORING RESULTS In any industry, major percentage of CP solutions is of low cost/no cost category and their implementation start even during assessment phase as soon as they are identified. Cost intensive solutions require a systematic plan of implementation. TASK 15: Prepare Implementation Plan Implementation plan is the document to be used for prioritizing implementing of Cleaner Production solutions selected in previous task. For implementation of CP solution, it is necessary to know the following: location of CP solution, category of CP solution, resources necessary for implementation, professional & skills requirement, resources necessary for implementation, down time required for implementation, responsibility matrix and task allocation in teams, financial implication and their availability, target set for completion of implementation etc.
  • 10. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. TASK 16: Implementing Cleaner Production Solutions Similar to any other project for modification or expansion, CP solution involves planning, scheduling, design, procurement, construction and commissioning. Depending upon complexity of the project and availability of internal resources, there may be need to get external assistance. Training of human resource is necessary to sustain the implementation. TASK 17: Monitor and Evaluate Results CP solutions after completion of implementation and commissioned, must be monitored and evaluated. This task is important from the perspective of continual nature of CP process. Once the solution has been implemented, it is necessary to compare the results achieved with those estimated during feasibility analysis. STEP 6: SUSTAINING CLEANER PRODUCTION PROGRAMME Sustaining a CP program is a challenge. Efforts should be made to integrate CP with company's routine planning process. Key to long term success is involvement of as many employees as possible, training of staff and schemes of incentives and rewards for those who specially perform well. TASK 18: Identify another Audit Focus Having audited and successfully implemented the 1st focus, CP team should go back to TASK 3 to identify and select next important section or area as audit focus. This cycle continues until all sections are completed and then come back to 1st audit focus to explore more CP opportunities. Cleaner Production philosophy must be developed within the company and integrated into its activities. All successful Cleaner Production programs have been founded on this premise. • Standard UNIDO, UNEP Cleaner Production methodology The UNIDO/UNEP methodology is similar to the Indian NCPC methodology described above with six stages and several tasks under each stage. The six stages and the sub tasks under each such stage can be presented as below.
  • 11. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. Step 1: Getting started 1.1 Designate CP team 1.2 List process steps 1.3 Select assessment focus Step 2: Analyzing process steps 2.1 Prepare flow chart 2.2 Make material & energy balances 2.3 Assign costs to waste streams 2.4 Review waste causes Step 3: Generating CP opportunities 3.1 Develop CP opportunities 3.2 Select workable CP opportunities Step 4: Selecting CP opportunities 4.1 Assess technical feasibility 4.2 Assess financial viability 4.3 Evaluate environmental aspects 4.4 Select solutions for implementation Step 5: Implementing CP solutions 5.1 Prepare implementation 5.2 Execute CP implementation 5.3 Monitor and evaluate results Step 6: Sustaining CP solutions 6.1 Sustain CP solutions 6.2 Select wasteful process steps A brief description of each stage, task and the outcome from each task is provided below. STEP 1: GETTING STARTED - Sufficient interest and awareness is required prior to initiating Step 1. Step 1 constitutes three specific tasks and on completion of the tasks, the CP team is ready to move into step 2 with the selection of the audit focus. Task 1.1: Designate CP Team The designated CP team should be capable of identifying opportunities, developing solutions and implementing them. The size and composition of the team depend on the structure of the organization with the different functions/stakeholders being represented. CP team members may include: Works/Production Manager; Maintenance Manager; Shop Floor Personnel: Engineers, Supervisors, Workers; Finance/Purchase/Sales Representative; Quality Controller; External Expert etc. Such a CP team will have authority, knowhow and capability to carryout subsequent tasks.
  • 12. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. Task 1.2: List Process Steps Specify all processes, including production, material handling, storage, utilities etc. Special attention should be given to occasional processes such as cleaning. Identify most important inputs and outputs to each process, including materials, energy, water, wastes and emissions. At the end of this task, a complete qualitative account of all major processes and material and energy flows (including wastes) is available to the CP team. Task 1.3: Select Assessment Focus Based on the available data from Task 1.2, the team should select one or few manageable CP opportunities for further study. The selection could be based on either economic considerations (e.g. monetary losses with waste streams/ high cost incurred) or environmental considerations (e.g. volume and composition of waste streams) or technical considerations (e.g. expected improvement potential). The outcome from this task is the availability of one or few CP opportunities for further study. STEP 2: ANALYZING PROCESS STEPS - This step consists of analysis. The qualitative data obtained in Step 1 is mapped and converted to quantitative form by applying the laws of conservation of mass and energy. Subsequently, these flows are expressed in economic terms and cause evaluation is carried out for the material and energy losses. Task 2.1: Prepare Flow Chart Fig.1: Process block diagram for brown stock washing
  • 13. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. A process block diagram should be drawn based on the arrangement of processes and material and energy flows into and out of the processes in the organization. The process block diagram is the pictorial representation of the data obtained in Task 1.2 (Process listing) with linking of unit operations with material flows with matching of inputs and outputs. The flow chart enables to quickly assign waste streams to unit operations and pinpoint operations in the organization. Task 2.2: Make Material and Energy Balances Material and energy balances should be applied to each and every unit operation in the flow chart to quantitatively express the flow streams into and out of the processes. The balance principle based on law of conservation of mass could be simply expressed as: Material in + material generated = material out + material consumed + material accumulated The basis for analysis can be selected as appropriate as per time or per ton of production etc. The most challenging aspect of conducting balances is obtaining accurate and appropriate data. Where records are maintained and measuring devices are available, such data could be made use of. In the absence of such data, the team is required to measure and monitor using both direct and indirect methods for quantification. The data sources can be from on-site measurements; purchase and sales records; production records etc. However, all data obtained should be assessed for quality, reliability, accuracy and representativeness. All the data should be converted to consistent units such as kg/day and kW etc. The more expensive or toxic the materials are, the more precise the balance should be. Balances are more meaningful if made for each constituent material. Simple cross checks can help reveal inconsistencies. On completion of this task, a complete quantitative picture of material and energy flows within the organization is available to the team. Task 2.3: Assign Costs to Waste Streams Material and energy quantities are not understood by many non technical personnel and it is convenient to express these in financial terms so that a common and easy to understand unit is used and the magnitude of the losses can be easily comprehended by all. In converting waste stream to costs, both internal and external cost components and cumulative costs due to
  • 14. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. flow of material and energy through different operations should be taken into consideration. The internal costs such as loss of raw materials and (intermediate) product; operation of treatment facilities; waste collection and handling and external costs such as discharge fees; levies, permit cost need to be apportioned for a realistic cost estimate. Task 2.3 will enable the team to determine the waste streams with most economic loss. Task 2.4: Review Waste Causes Cause analysis is carried out prior to option generation to determine the causes for waste streams. Factors such as product specifications, choice and quality of input materials, technical factors (process/equipment design, equipment/piping layout, monitoring equipment etc.), operating practices (production planning, operating procedures, maintenance schedules, worker training) and waste handling procedures can be reasons for generation of waste. This review would produce reason / reasons for waste generation which is required for the subsequent option generation task. At the end of Step 2, a listing of process waste sources and causes is available to the team. STEP 3: GENERATING CP OPPORTUNITIES – The third and the vital step involves determining the ways and means by which the waste streams could be eliminated or reduced. This step would provide the team with a listing of CP opportunities to avoid or minimize waste. Task 3.1: Develop CP Opportunities Development of CP opportunities can be carried out in several ways. Brainstorming in project team to find out ways of overcoming obstacles by pooling of thoughts from different backgrounds of team members and by encouraging innovative thinking to solve the problem at hand. The team can solicit ideas from outside the project team by inviting persons with expertise and/or experience or encourage all players in enterprise to submit ideas by offering a reward scheme. In cases where the problem at hand has been solved previously, such information could be obtained through data bases, manuals, earlier CP reports etc. Technology surveys and benchmarks may indicate opportunities and potential for improvements by comparison.
  • 15. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. The following prevention practices can be explored in looking for CP opportunities: Product modification, input material change, technology change, equipment modification, better process control, good housekeeping, on site reuse or recovery, production of useful by products. At the end, the team will possess a list of CP opportunities for each waste stream considered. Task 3.2: Select Workable CP Opportunities Among the large number of CP opportunities generated above, selection of workable opportunities is performed by initially screening the options into the following three categories: a) Implement obviously feasible options b) Reject obviously non-feasible options c) Remaining options - conduct feasibility analysis Only opportunities in category c) need further analysis. These opportunities can be subjected to a preliminary evaluation based on ease of implementation; expected technical feasibility; expected economic feasibility; expected reduction of waste/emission. The team can involve appropriate experts and technicians in the preliminary evaluation of opportunities. At the completion of step 3 the industry will have a list of CP solutions. STEP 4: SELECTING CP OPPORTUNITIES – This step is for performance improvement. Through a very structured methodology, the opportunities in category c) above are further evaluated based on technical feasibility, financial viability and environmental desirability. By this step a list of CP solutions can be obtained after screening out the CP opportunities. Task 4.1: Assess Technical Feasibility If the CP opportunity is not technically feasible, there is no possibility of implementation. Opportunities that fail this assessment are rejected. Technical feasibility can be assessed based on availability and reliability of equipment, requirements for utilities, process monitoring and control, space, maintenance requirements, required technical skills (operators, technicians etc.) etc. On completion of Task 4.1, the CP opportunities can be narrowed down to opportunities that have to be assessed against financial and environmental assessment.
  • 16. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. Task 4.2: Assess Financial Viability Table 1. Operational benefits for a technological change This is a key task and criteria for many organizations in selecting CP solutions. Almost all CP solutions will result in financial gain. Financial viability assessment requires data on investments such as equipment, construction, training, start up etc., operational cost and possible cost savings. A cost comparison is done between pre and post implementation scenario. An example of operational benefits for replacement of pouches washer by double screw press with 2-stage vacuum drum washer is shown in Table 1. Depending on the organization’s accounting practices and financial policies, any of the economic instruments such as simple pay back, dynamic pay back, Net Present Value (NPV), Internal Rate of Return (IRR) can be employed to determine the financial viability of the CP opportunity. Payback period = investment / net extra cash flow This indicates how fast the investment is recovered and is a quick indicator of the risk of investment. Payback period is appropriate for small investments / projects. NPV = ∑ 𝑁𝑒𝑡 𝑒𝑥𝑡𝑟𝑎 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 (1+𝑖) 𝑗 𝑛 𝑗=1 − 𝐼, where n = depreciation time (years) i = annual interest rate (%) I = total investment IRR = ∑ 𝑁𝑒𝑡 𝑒𝑥𝑡𝑟𝑎 𝑐𝑎𝑠ℎ 𝑓𝑙𝑜𝑤 (1+𝑟) 𝑗 𝑛 𝑗=1 − 𝐼 = 0, where r = internal rate of return consumption rates unit price before after difference benefit black pulp US$ 110/ton 480 ton/day 480 ton/day 0 ton/day US$ 0/day labour US$ 5/hr 120 hr/day 96 hr/day -24 hr/day US$ 120/day energy US$ 0.1/kWh 2,400 kWh/day 1,600 kWh/day -800 kWh/day US$ 80/day water US$ 0.1/rn3 4,000 m3 /day 1,000 rn3 /day -3,000 rn3 /day US$ 30/day washed pulp US$ 75/ton 780 ton/day 786 ton/day 6 ton/day US$ 450/day conc. black liquor US$ 0.2/ton 0 ton/day 85 ton/day 85 ton/day US$ 17/day wash water US$ 0.05 m3 3,550 m3 /day 615 m3 /day -2,935 m3 /day US$ 147/day TOTAL US$ 844/day
  • 17. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. The CP team should come to a consensus on a decision criterion prior to calculating the return on investment. A typical decision criterion can be as below. 1. Payback time: < 1-2 years (low-cost project) < 3-4 years (medium cost project) < 5 years (high cost project) 2. Net Present Value >> 0 (after depreciation time) 3. Internal Rate of Return >> bank interest rate At the end of this task, the CP team can further screen out CP opportunities that do not come within the organizations project financial criteria and subject the viable options to environmental assessment. Task 4.3: Evaluate Environmental Aspects If the option does not have a positive environmental effect, such options are not CP options. The options can be evaluated for environmental improvements such as reduction in quantity of pollutants and waste generated; reduction of pollutant/waste toxicity; reduction in materials consumption; reduction in use of non-renewable materials; reduction in energy consumption; reduction in consumption of energy from non-renewable resources; reduction of water consumption; reduction of “nuisance” noise, dust, smoke, smell, etc. CP opportunities that have a positive environmental benefit are solutions that can be implemented. Task 4.4: Select Solutions for Implementation There can be significant number of solutions after the above screening procedure that can be implemented. The CP team can decide on an appropriate methodology such as weighted average matrix method to prioritize the solutions giving suitable weightage to technical, economic and environmental aspects of the CP solution. For example, an enterprise may give higher priority to solutions with no cost/low cost or with higher return on investment. Properly document expected results and benefits for each option to facilitate fund raising and
  • 18. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. monitoring of implementation results. Task 4.4 will provide ranking of the solutions for implementation. On completion of step 4 the industry will have a prioritized list of CP solutions and an implementation list. STEP 5: IMPLEMENT CP SOLUTIONS – The vital practical step of implementation is carried out under step 5. Preparation, execution and monitoring of the CP solutions are covered here. The outcome at the end of this step is the successfully implemented CP solutions. Task 5.1: Prepare for Implementation Prior to execution of the CP solution detailed preparations are required, especially for technical and technological changes. In cases of technology changes detailed technical equipment specifications need to be written for procurement; detailed construction plans should be prepared for installation of equipment; comparative evaluation of equipment from different suppliers and final selection should be made and planning to reduce installation downtime need to be ensured. Adequate advanced preparation would reduce disruption to production and ensure a smooth transition to the new conditions. At the end of this task, a well planned program of action is in place for execution of the CP solution. Task 5.2: Execute CP Implementation Once procurement is completed, new constructions and installations can be supervised and executed according to the plan. This period can also be utilized for preparation for start up by purchasing start up chemicals, spare parts etc.; preparing preventive maintenance schedule and training operators, supervisors and technicians. On completion of this task, the CP solutions are implemented and are ready to monitor and evaluate results. Task 5.3: Monitor and Evaluate Results The implemented CP solutions need to be monitored to gather data for evaluation, of achievements against estimation. Measurement and monitoring should be for change in waste quantities; change in resource consumption or changes in profitability. These should be monitored and recorded together with changes in total production output and changes in
  • 19. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. products. Any negative changes should be reviewed immediately as it indicate s not achieving desired results. Once sufficient data is gathered over a period, progress can be evaluated by comparing measured benefits with expected benefits; identifying ways to further improve the benefits of the technical installations and verifying whether installation and operation are according to specifications. STEP 6: SUSTAIN CP SOLUTIONS – The final step is to sustain the CP activity in keeping with continuous improvement and the PDCA cycle. The implemented CP solutions need to be continued and new CP opportunities need to be implemented by following the same steps as above. The outcome of this step is the continuation of CP activity. Task 6.1: Sustain CP Solutions In order to sustain CP activity, planning, changes to organizational structure, employee involvement and technical development are required. Planning elements are setting up of organizational structure for CP; involvement of employees through training and incentives; adoption of long-term CP strategies and policies and integration of CP into technical development. The changes to the organizational structure are assigning key responsibility to implementing CP to the production departments; making managers and supervisors accountable for waste generation and formalizing participation of technical and environmental departments in further improvements. In order to sustain CP culture the human resources need to be continuously educated and motivated to change their attitudes. Further, CP benefits from good two-way internal communication practices and these needs to be formerly established and fostered. To motivate the staff and reward the champions of CP, an appropriate reward scheme can be implemented. Technologically, scheduling of preventive maintenance, checking of environmental performance of new equipment and integration of CP concepts in technological research and development can help in sustaining CP in the enterprise. Task 6.2: Select Wasteful Process Steps The last task in CP methodology is selection of new set of wasteful processes. In selecting a process, the seriousness of waste/emission generation; the internal and external
  • 20. A product of National Cleaner Production Centre Sri Lanka may be used for training programmes by others with acknowledgement. environmental costs; the managerial level and the expected improvement potential is taken into account. Based on the above, the most promising focuses are selected, for the next round of CP. • Detail description of different types of audits. 1. Walkthrough Assessments / Quick Scan Assessments A Walk-through Audit (WA) also known as a quick scan audit is used in Cleaner Production to carry out a rapid assessment of an industry or service organization. It is usually conducted during a span of 2-3 hours to familiarize oneself with the processes and activities being carried out. WA is an excellent way to carry out the initial environmental assessment of a company as it will allow the CP consultant and team to get a broad level understanding of the operations and possible environmental impacts of the relative sector. No measurements are taken during a walk through assessment. Walkthrough assessments are usually carried out as a precursor to a comprehensive / short audit. 2. Short Cleaner Production Assessments This type of assessment is very similar to a comprehensive assessment though the detailing can be less. Also the duration for the assessment will be shorter, usually involving only 5 – 7 man days. In a short CP audit sample material & energy be concerns our measurements are done to a limited extent. The conclusions will be based on historically recorded data. 3. Comprehensive Assessments A Comprehensive Cleaner Production Assessment is an in-depth assessment carried out at an industry following the 6 Step, 18 Task methodology developed by UNEP and UNIDO. This type of assessment usually takes more than 10 man days to complete and involves a systematic study and analysis of the processes and activities taking place within the industry. The focus of a comprehensive audit is the resource flow within the total process in order to identify waste generation sources and causes. It also involves carrying out measurements in order to develop an accurate understanding of what, where and how waste is being generated. At the end of the assessment a detailed audit report is presented to the company listing out options for waste avoidance / minimization.