SlideShare a Scribd company logo
1 of 19
Download to read offline
Technology
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Construction Technology III
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
POST-TENSIONING STRUCUTRAL ELEMENT
WHAT IS PRESTRESSED CONCRETE ?
The tendons are tensioned prior to
the concrete being cast.
A method in which compression
force is applied to the reinforced
concrete station.
POST-TENSIONING STRUCUTRAL ELEMENT
PRE-STRESSED = PRE-TENSIONED POST -TENSIONED
• Concrete is pre-stressed with
tendons before placing in
position.
• Preference : structural element is
small and easy to transport.
• Pre-stressing is done only after
the concrete attains sufficient
strength in other way after the
concrete has been casted.
• Preference: Structural element is
heavy.
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Primary function to place concrete
structure under compression in regions
where loads causes tensile stress.
Applies compressive stresses on the
material, balancing off tensile stress on
the concrete.
All construction joints and
crack control joints could
be eliminated because the
slab was poured
monolithically.
Provide sufficient pre-
compression on the slab.
Introduction + Function )
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Slabs on grade (office
buildings, multi-storey car
parks, warehouses etc.)
Floor slabs Bridge
Main beams
Cantilevered
Structures
Foundation Slabs
(rafts)
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Single Strand
Bonded Post-Tensioning
Unbonded Post- Tensioning
Single Strand
Multi Strand Flat Duct
Multi Strands Round Duct
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
End
Cap
Grout
Valve
Pocket
Former
Strands
Grout Pipe
Wedges
Strands
Anchor
Head
Bearing Plate
Duct
Flat Duct Round Duct
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Floor System Reinforced with
Grouted Post-Tensioning System
Flat Duct
Post- Tensioned Mat Foundation
using grouted Tendons
Flat Duct
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Anchorage Assembly
Details of unbonded
post - tensioning
Stressing Jack
Tendon Tail
(Additional length will be cut off)
Wedges
Stressing
Anchor
Split Pocket Former with
Intermediate Anchor
Pocket Former
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Example of a Floor System using the
Unbonded Post-tensioning System
Fortaleza, Brazil.
MAT FOUNDATION USING UNBONDED
TENDONS
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
BONDED POST-TENSIONING UNBONDED POST-TENSIONING
 Develops higher flexural strength. Provides greater available level arm
Does not depend on anchorage after
grouting.
Simplifies pre-fabrications of tendons
Localize the effects of damages. Grouting not required
Simple technique for demolishing or
providing future opening in slab.
Can be constructed faster
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
2. Casting of concrete
Pouring of concrete. The
concrete must achieve
proper strength before the
tendons are tensioned.
There is grout valve
for it to fill the ducts
are filled with grout.
Ducts not grouted and
tendon is held by the
end anchorages.
BONDED
UNBONDED
3. Tensioning of tendons
Tensioning of tendons is applied by
a jack. The tensioning of tendons
and pre-compression of concrete
occur simultaneously .
4.Seating of wedges
After tensioning is done, they
will put on the wedges to hold
the tendons whereby the extra
length of tendons.
5. Cutting of tendons
Tendon tails will be cut off using
either oxyacetylene touch ,
hydraulic shear, plasma cutter,
abrasive wheel.
1. Placing of ducts
The ducts for the
tendons are placed
along with the
reinforcement before
the casting of concrete. Placing
of
tendons
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Materials Savings
Increase in
Performance
Flexible in design
Quicker
Construction
Reduce lifetime
cost
Durable / Strong
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Accuracy
Poor workmanship
lead to accidents
Complexity of
work
Corrosion
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Honeycomb in
Concrete
Cracking WedgesSplicing of tendons
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
A glance of the project
Project Name: Morocco Mall
Project Value: US$253 million
Size: 165 000 𝑚2
Location: Casablanca, Africa
Timeline: Mid 2008 – October 2011
Large amounts of concrete were to
be used in the construction, which
would necessitate a large number
of expansion joints, and a large
numbers of precast slabs were to
be manufactured, at odds with the
tight construction timeless of
project.
CHALLENGE
SOLUTION
Replace the reinforced concrete
floor slabs and the precast panels
with post tensioned wall.
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Real Life Projects ( Oversea)
Process
1. Construction Site 2. Anchor Assembly 3. Stressing the strand 4. Grouting
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Real Life Projects (Local)
A glance at the project
Project Name: Klang Valley MRTV7
Project Value: RM800 million
Location: Kuala Lumpur, Malaysia
Developer: SPAD
 Comprise supply and installation of the external
post tension tendons to the erected segmental
boxed girders by using a 15.2 m multi-strand
system.
 HDPE smooth round ducts are used to house
tendons comprising of 19 strands each for piers
spanning from 30.00 to 39.50 Metres.
 Multi-strand tendons are then stressed with a
hydraulic jack that applies forces equivalent of
up to 400 tonnes.
The project comprises :
POST-TENSIONING STRUCUTRAL ELEMENT
TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
Thank You

More Related Content

What's hot

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMis_web
 
Construction of prestressed concrete structures
Construction of prestressed concrete structuresConstruction of prestressed concrete structures
Construction of prestressed concrete structuressanmilan
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioningCharlie Gupta
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slabArvind Vishwakarma
 
A report on "The open road-1951 Highway Construction"
A report on "The open road-1951 Highway Construction" A report on "The open road-1951 Highway Construction"
A report on "The open road-1951 Highway Construction" Debankur Baruah
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systemsHaripriya Kumar
 
post tension slabs in residential building
post tension slabs in residential buildingpost tension slabs in residential building
post tension slabs in residential buildinggovt.poly kalamassery
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteMAHFUZUR RAHMAN
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Rais Uddin
 
Introduction to Pre-stressed and Precast Concrete Technology
Introduction to Pre-stressed and Precast Concrete TechnologyIntroduction to Pre-stressed and Precast Concrete Technology
Introduction to Pre-stressed and Precast Concrete TechnologyEngr Shah Farooq
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12hlksd
 
Presentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinPresentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinRais Uddin
 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog bassamnakfour
 
Post tension Floor System
Post tension Floor SystemPost tension Floor System
Post tension Floor SystemAditya Shah
 

What's hot (19)

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
POST-TENSIONING SYSTEM
POST-TENSIONING SYSTEMPOST-TENSIONING SYSTEM
POST-TENSIONING SYSTEM
 
Construction of prestressed concrete structures
Construction of prestressed concrete structuresConstruction of prestressed concrete structures
Construction of prestressed concrete structures
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slab
 
A report on "The open road-1951 Highway Construction"
A report on "The open road-1951 Highway Construction" A report on "The open road-1951 Highway Construction"
A report on "The open road-1951 Highway Construction"
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systems
 
post tension slabs in residential building
post tension slabs in residential buildingpost tension slabs in residential building
post tension slabs in residential building
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
 
Introduction to Pre-stressed and Precast Concrete Technology
Introduction to Pre-stressed and Precast Concrete TechnologyIntroduction to Pre-stressed and Precast Concrete Technology
Introduction to Pre-stressed and Precast Concrete Technology
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12Prestressed concrete&metrorail 22-11-12
Prestressed concrete&metrorail 22-11-12
 
Presentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais UddinPresentation on prestressing prepared by Rais Uddin
Presentation on prestressing prepared by Rais Uddin
 
FORM WORK & SLIPFORM
FORM WORK & SLIPFORMFORM WORK & SLIPFORM
FORM WORK & SLIPFORM
 
Mega prefab post tension catalog
Mega prefab post tension catalog Mega prefab post tension catalog
Mega prefab post tension catalog
 
Special structure
Special structureSpecial structure
Special structure
 
Post tension Floor System
Post tension Floor SystemPost tension Floor System
Post tension Floor System
 

Similar to Final ct aa slides

Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete aishwaryasanap
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Wan Nee
 
Pre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyPre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyAnjith Augustine
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE524001
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete BridgeShubham Das
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Prasanth Dasu
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridgeBishnu prasad
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13Minhal Haider
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 

Similar to Final ct aa slides (20)

Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Pre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyPre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technology
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Stress ribbon-bridges
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Tony
TonyTony
Tony
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
 
prestress Register (1).pdf
prestress Register (1).pdfprestress Register (1).pdf
prestress Register (1).pdf
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 

More from Lam Yu

Group presentation compiled and updated 2
Group presentation compiled and updated 2Group presentation compiled and updated 2
Group presentation compiled and updated 2Lam Yu
 
Lamyu column 6 f (1)
Lamyu column 6 f (1)Lamyu column 6 f (1)
Lamyu column 6 f (1)Lam Yu
 
Lamyu column 1 e
Lamyu column 1 eLamyu column 1 e
Lamyu column 1 eLam Yu
 
Lamyu 4
Lamyu 4Lamyu 4
Lamyu 4Lam Yu
 
Lamyu 3
Lamyu 3Lamyu 3
Lamyu 3Lam Yu
 
Lamyu 2
Lamyu 2Lamyu 2
Lamyu 2Lam Yu
 
Lamyu 1
Lamyu 1Lamyu 1
Lamyu 1Lam Yu
 
Estimating final
Estimating  final Estimating  final
Estimating final Lam Yu
 
Estimating presentation (final)
Estimating presentation (final)Estimating presentation (final)
Estimating presentation (final)Lam Yu
 
Supply chain invidividual123123
Supply chain invidividual123123Supply chain invidividual123123
Supply chain invidividual123123Lam Yu
 
Supply chain invidividual
Supply chain invidividualSupply chain invidividual
Supply chain invidividualLam Yu
 
Ms (1)
Ms (1)Ms (1)
Ms (1)Lam Yu
 
Sc bim
Sc bimSc bim
Sc bimLam Yu
 
Bs1 (1)
Bs1 (1)Bs1 (1)
Bs1 (1)Lam Yu
 
Smart tunnel
Smart tunnelSmart tunnel
Smart tunnelLam Yu
 
Bs finallll (1)
Bs finallll (1)Bs finallll (1)
Bs finallll (1)Lam Yu
 
Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1Lam Yu
 
Site surveying-2-done-1
Site surveying-2-done-1Site surveying-2-done-1
Site surveying-2-done-1Lam Yu
 
Pile cap
Pile cap Pile cap
Pile cap Lam Yu
 
Introduction
IntroductionIntroduction
IntroductionLam Yu
 

More from Lam Yu (20)

Group presentation compiled and updated 2
Group presentation compiled and updated 2Group presentation compiled and updated 2
Group presentation compiled and updated 2
 
Lamyu column 6 f (1)
Lamyu column 6 f (1)Lamyu column 6 f (1)
Lamyu column 6 f (1)
 
Lamyu column 1 e
Lamyu column 1 eLamyu column 1 e
Lamyu column 1 e
 
Lamyu 4
Lamyu 4Lamyu 4
Lamyu 4
 
Lamyu 3
Lamyu 3Lamyu 3
Lamyu 3
 
Lamyu 2
Lamyu 2Lamyu 2
Lamyu 2
 
Lamyu 1
Lamyu 1Lamyu 1
Lamyu 1
 
Estimating final
Estimating  final Estimating  final
Estimating final
 
Estimating presentation (final)
Estimating presentation (final)Estimating presentation (final)
Estimating presentation (final)
 
Supply chain invidividual123123
Supply chain invidividual123123Supply chain invidividual123123
Supply chain invidividual123123
 
Supply chain invidividual
Supply chain invidividualSupply chain invidividual
Supply chain invidividual
 
Ms (1)
Ms (1)Ms (1)
Ms (1)
 
Sc bim
Sc bimSc bim
Sc bim
 
Bs1 (1)
Bs1 (1)Bs1 (1)
Bs1 (1)
 
Smart tunnel
Smart tunnelSmart tunnel
Smart tunnel
 
Bs finallll (1)
Bs finallll (1)Bs finallll (1)
Bs finallll (1)
 
Site surveying-almost-1
Site surveying-almost-1Site surveying-almost-1
Site surveying-almost-1
 
Site surveying-2-done-1
Site surveying-2-done-1Site surveying-2-done-1
Site surveying-2-done-1
 
Pile cap
Pile cap Pile cap
Pile cap
 
Introduction
IntroductionIntroduction
Introduction
 

Recently uploaded

Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 

Recently uploaded (20)

9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 

Final ct aa slides

  • 1. Technology TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Construction Technology III
  • 2. TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 POST-TENSIONING STRUCUTRAL ELEMENT WHAT IS PRESTRESSED CONCRETE ? The tendons are tensioned prior to the concrete being cast. A method in which compression force is applied to the reinforced concrete station.
  • 3. POST-TENSIONING STRUCUTRAL ELEMENT PRE-STRESSED = PRE-TENSIONED POST -TENSIONED • Concrete is pre-stressed with tendons before placing in position. • Preference : structural element is small and easy to transport. • Pre-stressing is done only after the concrete attains sufficient strength in other way after the concrete has been casted. • Preference: Structural element is heavy. TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161
  • 4. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Primary function to place concrete structure under compression in regions where loads causes tensile stress. Applies compressive stresses on the material, balancing off tensile stress on the concrete. All construction joints and crack control joints could be eliminated because the slab was poured monolithically. Provide sufficient pre- compression on the slab. Introduction + Function )
  • 5. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Slabs on grade (office buildings, multi-storey car parks, warehouses etc.) Floor slabs Bridge Main beams Cantilevered Structures Foundation Slabs (rafts)
  • 6. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Single Strand Bonded Post-Tensioning Unbonded Post- Tensioning Single Strand Multi Strand Flat Duct Multi Strands Round Duct
  • 7. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 End Cap Grout Valve Pocket Former Strands Grout Pipe Wedges Strands Anchor Head Bearing Plate Duct Flat Duct Round Duct
  • 8. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Floor System Reinforced with Grouted Post-Tensioning System Flat Duct Post- Tensioned Mat Foundation using grouted Tendons Flat Duct
  • 9. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Anchorage Assembly Details of unbonded post - tensioning Stressing Jack Tendon Tail (Additional length will be cut off) Wedges Stressing Anchor Split Pocket Former with Intermediate Anchor Pocket Former
  • 10. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Example of a Floor System using the Unbonded Post-tensioning System Fortaleza, Brazil. MAT FOUNDATION USING UNBONDED TENDONS
  • 11. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 BONDED POST-TENSIONING UNBONDED POST-TENSIONING  Develops higher flexural strength. Provides greater available level arm Does not depend on anchorage after grouting. Simplifies pre-fabrications of tendons Localize the effects of damages. Grouting not required Simple technique for demolishing or providing future opening in slab. Can be constructed faster
  • 12. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 2. Casting of concrete Pouring of concrete. The concrete must achieve proper strength before the tendons are tensioned. There is grout valve for it to fill the ducts are filled with grout. Ducts not grouted and tendon is held by the end anchorages. BONDED UNBONDED 3. Tensioning of tendons Tensioning of tendons is applied by a jack. The tensioning of tendons and pre-compression of concrete occur simultaneously . 4.Seating of wedges After tensioning is done, they will put on the wedges to hold the tendons whereby the extra length of tendons. 5. Cutting of tendons Tendon tails will be cut off using either oxyacetylene touch , hydraulic shear, plasma cutter, abrasive wheel. 1. Placing of ducts The ducts for the tendons are placed along with the reinforcement before the casting of concrete. Placing of tendons
  • 13. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Materials Savings Increase in Performance Flexible in design Quicker Construction Reduce lifetime cost Durable / Strong
  • 14. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Accuracy Poor workmanship lead to accidents Complexity of work Corrosion
  • 15. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Honeycomb in Concrete Cracking WedgesSplicing of tendons
  • 16. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 A glance of the project Project Name: Morocco Mall Project Value: US$253 million Size: 165 000 𝑚2 Location: Casablanca, Africa Timeline: Mid 2008 – October 2011 Large amounts of concrete were to be used in the construction, which would necessitate a large number of expansion joints, and a large numbers of precast slabs were to be manufactured, at odds with the tight construction timeless of project. CHALLENGE SOLUTION Replace the reinforced concrete floor slabs and the precast panels with post tensioned wall.
  • 17. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Real Life Projects ( Oversea) Process 1. Construction Site 2. Anchor Assembly 3. Stressing the strand 4. Grouting
  • 18. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Real Life Projects (Local) A glance at the project Project Name: Klang Valley MRTV7 Project Value: RM800 million Location: Kuala Lumpur, Malaysia Developer: SPAD  Comprise supply and installation of the external post tension tendons to the erected segmental boxed girders by using a 15.2 m multi-strand system.  HDPE smooth round ducts are used to house tendons comprising of 19 strands each for piers spanning from 30.00 to 39.50 Metres.  Multi-strand tendons are then stressed with a hydraulic jack that applies forces equivalent of up to 400 tonnes. The project comprises :
  • 19. POST-TENSIONING STRUCUTRAL ELEMENT TAN KAI XUAN 0325077 | TEE WAN NEE 0325074 | TANG LAM YU 0324966 | YAP CHOE HOONG 0323161 Thank You