SlideShare a Scribd company logo
1 of 26
SHIVANANDA ROY
M.TECH (STRUCTURAL ENGINEERING)
 A Stress Ribbon Bridge is a tension structure (similar in many ways
to a simple suspension bridge). The suspension cables are embedded in
the deck which follows a catenary arc between supports.
 Unlike the simple span, the ribbon is stressed in traction, which
adds to the stiffness of the structure. The supports in turn
support upward thrusting arcs that allow the grade to be
changed between spans.
 Typically made from concrete reinforced by steel tensioning
cables. Where such bridges carry vehicle traffic a certain degree
of stiffness is required to prevent excessive flexure of the
structure, obtained by stressing the concrete in compression.
 The stress ribbon design is rare. Few people including bridge
engineers are familiar with this form and fewer than 50 have
been built worldwide.
 Pedestrian Bridge
 Highly Stressed Freely Suspended Pre-Stressed Tendons
 Precast or Cast-in-situ deck Slab
 Characterized by successive and complementary smooth curves
 Catenary Shape or Funicular shape Stress Ribbon Bridge
 The suspension cables are embedded in the deck which follows a catenary
arc between the supports.
 As opposed to suspension bridges, where the cables carry the load, in
stress ribbon, by tensioning the cables and the deck between abutments,
the deck shares axial tension forces.
 Unlike the simple span the ribbon is stressed in compression, which adds to
the stiffness of the structure. A simple suspension span tends to sway and
bounce. The supports in turn support upward thrusting arcs that allow the
grade to be changed between spans, where multiple spans are used.
 Anchorage forces are unusually large since the structure is tightly
tensioned.
SUPERSTRUCTURE
 A typical stress ribbon bridge deck consists of precast concrete planks with
bearing tendons to support them during construction and separate
prestressing tendons which are tensioned to create the final designed
geometric form.
 The joints between the planks are most often sealed with in-situ concrete
before stressing the deck.
 The prestressing tendons transfer horizontal forces in to the abutments and
then to the ground most often using ground anchors. The tendons are
encased in ducts which are generally grouted after tensioning in order to lock
in the stress and protect them from corrosion.
SUBSTRUCTURE
 The abutments are designed to transfer the horizontal forces from the deck
cables into the ground via ground anchors.
 The ground anchors are normally tensioned in 2 stages, the first step is
tensioned before the deck is erected and the rest, after the deck is
complete.
 If stressed in one stage only, there will be a large out of balance force to be
resisted by the abutments in the temporary case. The soil pressure,
overturning and sliding has to be checked for construction as well as
permanent condition.
GROUND CONDITIONS
 The ideal ground condition for resisting large horizontal forces from the
ribbon is a rock base. This occurs rarely but suitable foundations can be
devised even if competent soils are only found at some depth below the
abutments.
 In some cases where soil conditions do not permit the use of anchors, piles
can also be used. Horizontal deformations can be significant and are
considered in the design. It is also possible to use a combination of anchors
and drilled shafts.
 The abutments and piers are built first. Then bearing cables were stretched from
abutment to abutment and draped over steel saddles that rested atop the piers.
 Once the bearing cables were tensioned to the specified design force,
precast panels were suspended via support rods located at the four corners
of each panel. At this point the bridge sagged into its catenary shape.
 The next step is to place post tensioning ducts in the bridge. The ducts is
placed directly above the bearing cables and support rods, which are all
located in two longitudinal troughs that run the length of the bridge.
 After the ducts were in place, the cast-in place concrete is placed in the
longitudinal troughs in small transverse closure joints. Concrete is poured
in the joints between the planks and allowed to harden before the final
tensioning is carried out.
 After allowing the cast in place concrete to cure and achieve its full strength,
the bridge was post tensioned. The post tensioning lifts each span, closes the
gap between the panels, puts the entire bridge in to compression and
transforms the bridge in to continuous ribbon of prestressed concrete.
 Cables are pre-tensioned by anchoring into support structure, hence this
region is highly stressed.
 Performance may be improved by construction of:
 Flexible saddle
 Parabolic haunch
 Intermediate arch support Stress Ribbon Bridge
Flexible saddle arrangement at supportSimple Support with Constant Section
Parabolic hunch arrangement at support Stress ribbon supported by arch
 Might be pre-fabricated or cast in-situ
 Stressed only by normal forces hence might be reduced by
waffles
 Integrated with end and intermediate supporting construction
so as to work as a composite structure. Stress Ribbon Bridge
Leviation Stage
1. Cables are hanged from supports
2. Pre cast segments are slided over the bearing tendons to desired position
3. Segments are jointed by cast in-situ composite slabs
Typical precast segment on
bearing cables
Shifting of precast segment on
bearing cables
BASIC STAGE
1. Static analysis is done at this stage.
2. After sufficient hardening of joints, post tensioning is done by pre-
stressing tendons.
3. Effect of dead load, creep, shrinkage, temperature and pre-stressing are
determined.
4. Shape at this stage determines the final sag in the bridge.
SERVICE/ULTIMATE STAGE
Analysis of structure for all service loads is done
Concrete or steel columns as
intermediate supports
Concrete arch as
intermediate supports
 Stress ribbon pedestrian bridges are very economical, aesthetical and almost
maintenance free structures.
 They require minimal quantity of materials.
 They are erected independently from existing terrain and therefore they have
a minimum impact upon the environment during construction.
 Minimal long-term maintenance is required.
 A stress ribbon bridge allows for long spans with a minimum number of
piers and the piers can be shorter than those required for cable stayed or
suspension bridges.
 They are quick and convenient to construct if given appropriate
conditions, without foam work.
 Large horizontal forces at the end and intermediate which determines
economy of bridge.
Remedy-
 Construction of flexible member close to supports
 Widening of deck at the ends
 Having an arch shaped intermediate support
 Danger of overturning and oscillations due to high span to width ratio.
Remedy-
 Increasing sag
 Proper dynamic analysis Stress Ribbon Bridge
Innovative design uses unidirectional solid
carbon fibre cables (TSC).
Unsupported spans were significantly
increased
Supporting structure was reduced
Installation time and cost were reduced by
over 80%
Stress Ribbon Bridge
Cuenca, ESP
 Stress ribbon bridges are a versatile
form of bridge, the adaptable form of
structure is applicable to a variety of
requirements.
 Post tensioned concrete minimizes
cracking and assures durability.
Bearings and expansion joints are
rarely required minimizing
maintenance and inspections.
 Using bearing tendons can eliminate
the need for site foam work and large
plant, contributing to fast
construction.
 The slender decks are visually pleasing
and have a visual impact on
surroundings giving a light aesthetic
impression.
 There is a wide range of different
topographies and soil conditions
found and a number of areas which
require aesthetic yet cost effective
pedestrian bridges to be built: Stress
ribbon bridges could provide elegant
solutions to these challenges.
Rio Colorado Bridge, CR
Rogue River Pedestrian
Bridge, USA
Glacis Bridge, GER
Kent Messenger Millennium
Bridge, UK
McLoughlin Boulevard
Pedestrian Bridge,USA
Shivananda Roy
LAKE HODGES BRIDGE
World’s longest stress ribbon bridge (990 ft)
San Diego, CA, USA

More Related Content

What's hot

PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concretefroskhan08
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge pptSAI KIRAN
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcreteDavinderpal Singh
 
stress ribbon bridge ppt
stress ribbon bridge pptstress ribbon bridge ppt
stress ribbon bridge pptvikash mishra
 
Precast structure
Precast structurePrecast structure
Precast structurepiyush9392
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 

What's hot (20)

PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
Tony
TonyTony
Tony
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed Concrete
 
Columns
ColumnsColumns
Columns
 
Rehabilitation of structure
Rehabilitation of structureRehabilitation of structure
Rehabilitation of structure
 
stress ribbon bridge ppt
stress ribbon bridge pptstress ribbon bridge ppt
stress ribbon bridge ppt
 
Precast structure
Precast structurePrecast structure
Precast structure
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 

Similar to Stress Ribbon Bridge Design and Construction

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
Chapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptChapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptHuzaifaZafar15
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
CTP.ppt
CTP.pptCTP.ppt
CTP.pptarun t
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdfRijuDasgupta
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete aishwaryasanap
 
STRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGESTRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGEFazalArif1
 

Similar to Stress Ribbon Bridge Design and Construction (20)

Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Chapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptChapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).ppt
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
CTP.ppt
CTP.pptCTP.ppt
CTP.ppt
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Ppt
PptPpt
Ppt
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
 
Pre-stressed concrete
Pre-stressed concrete Pre-stressed concrete
Pre-stressed concrete
 
STRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGESTRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGE
 

More from Shivananda Roy

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSShivananda Roy
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONShivananda Roy
 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESShivananda Roy
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & ExcavationShivananda Roy
 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction EquipmentsShivananda Roy
 

More from Shivananda Roy (6)

PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
 
UNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUESUNDERWATER CONCRETING TECHNIQUES
UNDERWATER CONCRETING TECHNIQUES
 
Trenching & Excavation
Trenching & ExcavationTrenching & Excavation
Trenching & Excavation
 
Construction Equipments
Construction EquipmentsConstruction Equipments
Construction Equipments
 
Green concrete
Green concreteGreen concrete
Green concrete
 

Recently uploaded

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Stress Ribbon Bridge Design and Construction

  • 2.
  • 3.  A Stress Ribbon Bridge is a tension structure (similar in many ways to a simple suspension bridge). The suspension cables are embedded in the deck which follows a catenary arc between supports.  Unlike the simple span, the ribbon is stressed in traction, which adds to the stiffness of the structure. The supports in turn support upward thrusting arcs that allow the grade to be changed between spans.
  • 4.  Typically made from concrete reinforced by steel tensioning cables. Where such bridges carry vehicle traffic a certain degree of stiffness is required to prevent excessive flexure of the structure, obtained by stressing the concrete in compression.  The stress ribbon design is rare. Few people including bridge engineers are familiar with this form and fewer than 50 have been built worldwide.
  • 5.  Pedestrian Bridge  Highly Stressed Freely Suspended Pre-Stressed Tendons  Precast or Cast-in-situ deck Slab  Characterized by successive and complementary smooth curves  Catenary Shape or Funicular shape Stress Ribbon Bridge
  • 6.  The suspension cables are embedded in the deck which follows a catenary arc between the supports.  As opposed to suspension bridges, where the cables carry the load, in stress ribbon, by tensioning the cables and the deck between abutments, the deck shares axial tension forces.  Unlike the simple span the ribbon is stressed in compression, which adds to the stiffness of the structure. A simple suspension span tends to sway and bounce. The supports in turn support upward thrusting arcs that allow the grade to be changed between spans, where multiple spans are used.  Anchorage forces are unusually large since the structure is tightly tensioned.
  • 7.
  • 8. SUPERSTRUCTURE  A typical stress ribbon bridge deck consists of precast concrete planks with bearing tendons to support them during construction and separate prestressing tendons which are tensioned to create the final designed geometric form.  The joints between the planks are most often sealed with in-situ concrete before stressing the deck.  The prestressing tendons transfer horizontal forces in to the abutments and then to the ground most often using ground anchors. The tendons are encased in ducts which are generally grouted after tensioning in order to lock in the stress and protect them from corrosion.
  • 9. SUBSTRUCTURE  The abutments are designed to transfer the horizontal forces from the deck cables into the ground via ground anchors.  The ground anchors are normally tensioned in 2 stages, the first step is tensioned before the deck is erected and the rest, after the deck is complete.  If stressed in one stage only, there will be a large out of balance force to be resisted by the abutments in the temporary case. The soil pressure, overturning and sliding has to be checked for construction as well as permanent condition.
  • 10. GROUND CONDITIONS  The ideal ground condition for resisting large horizontal forces from the ribbon is a rock base. This occurs rarely but suitable foundations can be devised even if competent soils are only found at some depth below the abutments.  In some cases where soil conditions do not permit the use of anchors, piles can also be used. Horizontal deformations can be significant and are considered in the design. It is also possible to use a combination of anchors and drilled shafts.
  • 11.  The abutments and piers are built first. Then bearing cables were stretched from abutment to abutment and draped over steel saddles that rested atop the piers.  Once the bearing cables were tensioned to the specified design force, precast panels were suspended via support rods located at the four corners of each panel. At this point the bridge sagged into its catenary shape.  The next step is to place post tensioning ducts in the bridge. The ducts is placed directly above the bearing cables and support rods, which are all located in two longitudinal troughs that run the length of the bridge.  After the ducts were in place, the cast-in place concrete is placed in the longitudinal troughs in small transverse closure joints. Concrete is poured in the joints between the planks and allowed to harden before the final tensioning is carried out.
  • 12.  After allowing the cast in place concrete to cure and achieve its full strength, the bridge was post tensioned. The post tensioning lifts each span, closes the gap between the panels, puts the entire bridge in to compression and transforms the bridge in to continuous ribbon of prestressed concrete.
  • 13.  Cables are pre-tensioned by anchoring into support structure, hence this region is highly stressed.  Performance may be improved by construction of:  Flexible saddle  Parabolic haunch  Intermediate arch support Stress Ribbon Bridge
  • 14. Flexible saddle arrangement at supportSimple Support with Constant Section Parabolic hunch arrangement at support Stress ribbon supported by arch
  • 15.  Might be pre-fabricated or cast in-situ  Stressed only by normal forces hence might be reduced by waffles  Integrated with end and intermediate supporting construction so as to work as a composite structure. Stress Ribbon Bridge
  • 16. Leviation Stage 1. Cables are hanged from supports 2. Pre cast segments are slided over the bearing tendons to desired position 3. Segments are jointed by cast in-situ composite slabs
  • 17. Typical precast segment on bearing cables Shifting of precast segment on bearing cables
  • 18. BASIC STAGE 1. Static analysis is done at this stage. 2. After sufficient hardening of joints, post tensioning is done by pre- stressing tendons. 3. Effect of dead load, creep, shrinkage, temperature and pre-stressing are determined. 4. Shape at this stage determines the final sag in the bridge.
  • 19. SERVICE/ULTIMATE STAGE Analysis of structure for all service loads is done
  • 20. Concrete or steel columns as intermediate supports Concrete arch as intermediate supports
  • 21.  Stress ribbon pedestrian bridges are very economical, aesthetical and almost maintenance free structures.  They require minimal quantity of materials.  They are erected independently from existing terrain and therefore they have a minimum impact upon the environment during construction.  Minimal long-term maintenance is required.  A stress ribbon bridge allows for long spans with a minimum number of piers and the piers can be shorter than those required for cable stayed or suspension bridges.  They are quick and convenient to construct if given appropriate conditions, without foam work.
  • 22.  Large horizontal forces at the end and intermediate which determines economy of bridge. Remedy-  Construction of flexible member close to supports  Widening of deck at the ends  Having an arch shaped intermediate support  Danger of overturning and oscillations due to high span to width ratio. Remedy-  Increasing sag  Proper dynamic analysis Stress Ribbon Bridge
  • 23. Innovative design uses unidirectional solid carbon fibre cables (TSC). Unsupported spans were significantly increased Supporting structure was reduced Installation time and cost were reduced by over 80% Stress Ribbon Bridge Cuenca, ESP
  • 24.  Stress ribbon bridges are a versatile form of bridge, the adaptable form of structure is applicable to a variety of requirements.  Post tensioned concrete minimizes cracking and assures durability. Bearings and expansion joints are rarely required minimizing maintenance and inspections.  Using bearing tendons can eliminate the need for site foam work and large plant, contributing to fast construction.  The slender decks are visually pleasing and have a visual impact on surroundings giving a light aesthetic impression.  There is a wide range of different topographies and soil conditions found and a number of areas which require aesthetic yet cost effective pedestrian bridges to be built: Stress ribbon bridges could provide elegant solutions to these challenges.
  • 25. Rio Colorado Bridge, CR Rogue River Pedestrian Bridge, USA Glacis Bridge, GER Kent Messenger Millennium Bridge, UK McLoughlin Boulevard Pedestrian Bridge,USA
  • 26. Shivananda Roy LAKE HODGES BRIDGE World’s longest stress ribbon bridge (990 ft) San Diego, CA, USA