SlideShare a Scribd company logo
1 of 14
STRESS RIBBON BRIDGE
INTRODUCTION
 A stress ribbon bridge is a tension structure (similar in
many ways to a simple suspension bridge).
 Stress Ribbon Bridge uses the theory of a catenary
transmitting loads via tension in the deck to abutments
which are anchored to the ground.
 Unlike the simple span the ribbon is stressed in
compression, which adds to the stiffness of the structure.
 Stress ribbon bridges are very economical, aesthetic and
almost maintenance free structure. They require minimal
quantity of materials.
HISTORY
 The first stress ribbon bridge was constructed in Switzerland in the 1960s.
This concept was first introduced by a German engineer Ulrich
Finsterwalder.
FORM OF A STRESS RIBBON BRIDGE
Superstructure:-
 A typical stress ribbon bridge deck consists of precast concrete planks with
bearing tendons to support them during construction and separate pre stressing
tendons which are tensioned to create the final designed geometric form.
 The pre stressing tendons transfer horizontal forces in to the abutments and
then to the ground most often using ground anchors.
 The tendons are encased in ducts which are generally grouted after tensioning in
order to lock in the stress and protect them from corrosion. Since the bending in
the deck is low, the depth can be minimized and results in reduction in dead
load and horizontal forces in abutments.
 The abutments are designed to transfer the horizontal forces from
the deck cables into the ground via ground anchors. Pedestrians,
wind and temperature loads can cause large changes in the bending
moments in the deck close to the abutments and accordingly crack
widths and fatigue in reinforcement must be considered.
 The ground anchors are normally tensioned in 2 stages, the first
step is tensioned before the deck is erected and the rest, after the
deck is complete. If stressed in one stage only, there will be a large
out of balance force to be resisted by the abutments in the
temporary case.
 The soil pressure, overturning and sliding has to be checked for
construction as well as permanent condition.
 Substructure:-
Ground Conditions:-
 The ideal ground condition for resisting large horizontal forces from the ribbon
is a rock base. This occurs rarely but suitable foundations can be devised even
if competent soils are only found at some depth below the abutments.
 In some cases where soil conditions do not permit the use of anchors, piles
can also be used. Horizontal deformations can be significant and are
considered in the design.
 It is also possible to use a combination of anchors and drilled shafts. Battered
micropilling is another alternative which can resist the load from the ribbon
because of its compression and tension capacity.
CONSTRUCTION TECHNIQUE
 The abutments and piers are built first. Next the bearing cables were stretched from
abutment to abutment and draped over steel saddles that rested atop the piers.
 The bearing tendons generally support the structure during construction, and only rarely
is additional false work used. Once the bearing cables were tensioned to the specified
design force, precast panels were suspended via support rods located at the four corners
of each panel. At this point the bridge sagged into its catenary shape.
 The next step was to place post tensioning ducts in the bridge. The ducts were placed
directly above the bearing cables and support rods, which are all located in two
longitudinal troughs that run the length of the bridge. After the ducts were in place, the
cast-in place concrete was placed in the longitudinal troughs in small transverse closure
joints.
STRUCTURAL SYSTEM
 The development of the self-anchored stress-ribbon structure supported by an arch.
 It is clear that the intermediate support of a multi-span stress-ribbon can also have the
shape of an arch.
 The arch serves as a saddle from which the stress-ribbon spans can rise during post-
tensioning and during temperature drop, and where the center "band" can rest during a
temperature rise.
 In the initial stage, the stress-ribbon behaves as a two-span cable supported by the
saddle that is fixed to the end abutments.
COMPARISION WITH SIMPLE SUSPENSION
BRIDGE
 A stress ribbon bridge is a tension
structure similar in many ways to a
simple suspension bridge. The
suspension cables are embedded in
the deck which follows a catenary
arc between the supports.
 Unlike the simple span the ribbon
is stressed in compression, which
adds to the stiffness of the
structure.
 As opposed to suspension bridges,
where the cables carry the load, in
stress ribbon, by tensioning the
cables and the deck between
abutments, the deck shares axial
tension forces.
 A simple suspension span tends to
sway and bounce. The supports in
turn support upward thrusting arcs
that allow the grade to be changed
between spans, where multiple
spans are used.
ADVANTAGES
 Stress ribbon pedestrian bridges are very economical, aesthetical and almost
maintenance free structures.
 They require minimal quantity of materials.
 They are erected independently from existing terrain and therefore they have
a minimum impact upon the environment during construction.
 They are quick and convenient to construct if given appropriate conditions,
without false work.
 A stress ribbon bridge allows for long spans with a minimum number of
piers and the piers can be shorter than those required for cable stayed or
suspension bridges.
APPLICATION & INSTANCE
 Eco duct:
 A tunnel which was built as part of a large network of motorways outside Brno.
The theory is the same as a self-anchored arch but the geometry is much more
complex. It is 50m wide and spans 70m a finite element program was used in
its design.
 Stuttgart trade fair hall roof: The suspended asymmetric roof comprises a
regular repetition of stressed trusses with individual I-beam ribbons of steel
between them. The trusses function as strut and tie A-frames based on
concrete strip foundations and are tied back to the ground with anchors. The
stresses in the ribbons and weight of its ‘green roof’ were used to resist wind
uplift.
CONCLUSION
 Stress ribbon bridges are a versatile form of bridge, the adaptable form of
structure is applicable to a variety of requirements.
 The slender decks are visually pleasing and have a visual impact on
surroundings giving a light aesthetic impression.
 Post tensioned concrete minimizes cracking and assures durability. Bearings
and expansion joints are rarely required minimizing maintenance and
inspections.
 Since erection using pre-cast segments does not depend on particular site
condition and permits labour saving erection and a short time to delivery.
Using bearing tendons can eliminate the need for site form work and large
plant, contributing to fast construction programmes and preservation of the
environments.
 Stressed ribbon bridge is a solution to the areas which require aesthetic yet
cost effective pedestrian bridges to be built .
THANK YOU

More Related Content

What's hot

Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acpJigar Shah
 
Immersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaImmersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaAbhay Ocean India ltd.
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls Manvinder Kingra
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridgesMadujith Sagara
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structuresMuhammad Qasim Jameel
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridgemantukr4ever
 
Analysis of Prestressed Concrete Girder for Bridges
Analysis of Prestressed Concrete Girder for BridgesAnalysis of Prestressed Concrete Girder for Bridges
Analysis of Prestressed Concrete Girder for Bridgesijtsrd
 
Submerged Floating Tunnel
Submerged Floating TunnelSubmerged Floating Tunnel
Submerged Floating TunnelIntikhab Alam
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdfGaurav Rawat
 

What's hot (20)

Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acp
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
Immersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaImmersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, India
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Susppension bridges
Susppension bridges Susppension bridges
Susppension bridges
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridges
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Grouting
Grouting Grouting
Grouting
 
Skew slab bridge
Skew slab bridgeSkew slab bridge
Skew slab bridge
 
Basic components and parts of bridge structures
Basic components and parts of bridge structuresBasic components and parts of bridge structures
Basic components and parts of bridge structures
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridge
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
 
Analysis of Prestressed Concrete Girder for Bridges
Analysis of Prestressed Concrete Girder for BridgesAnalysis of Prestressed Concrete Girder for Bridges
Analysis of Prestressed Concrete Girder for Bridges
 
Submerged Floating Tunnel
Submerged Floating TunnelSubmerged Floating Tunnel
Submerged Floating Tunnel
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 

Similar to Stress Ribbon Bridge: An Economical and Aesthetic Structure

PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
Chapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptChapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptHuzaifaZafar15
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malikjunaid bashir
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
STRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGESTRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGEFazalArif1
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
 
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptxSuspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptxsamratr1103
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Prasanth Dasu
 
CTP.ppt
CTP.pptCTP.ppt
CTP.pptarun t
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdfRijuDasgupta
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
Explain any tube system and structural configuration of a building having tha...
Explain any tube system and structural configuration of a building having tha...Explain any tube system and structural configuration of a building having tha...
Explain any tube system and structural configuration of a building having tha...World Of Engineers Consultant.
 

Similar to Stress Ribbon Bridge: An Economical and Aesthetic Structure (20)

STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Chapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).pptChapter 1 Basic Concepts (PART I) (1).ppt
Chapter 1 Basic Concepts (PART I) (1).ppt
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malik
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
STRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGESTRESS_RIBBON_BRIDGE
STRESS_RIBBON_BRIDGE
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
 
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptxSuspension-Bridge-dfsdfsfdsfsdppt sos.pptx
Suspension-Bridge-dfsdfsfdsfsdppt sos.pptx
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
CTP.ppt
CTP.pptCTP.ppt
CTP.ppt
 
Presentation1
Presentation1Presentation1
Presentation1
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
Explain any tube system and structural configuration of a building having tha...
Explain any tube system and structural configuration of a building having tha...Explain any tube system and structural configuration of a building having tha...
Explain any tube system and structural configuration of a building having tha...
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

Stress Ribbon Bridge: An Economical and Aesthetic Structure

  • 1.
  • 3. INTRODUCTION  A stress ribbon bridge is a tension structure (similar in many ways to a simple suspension bridge).  Stress Ribbon Bridge uses the theory of a catenary transmitting loads via tension in the deck to abutments which are anchored to the ground.  Unlike the simple span the ribbon is stressed in compression, which adds to the stiffness of the structure.  Stress ribbon bridges are very economical, aesthetic and almost maintenance free structure. They require minimal quantity of materials.
  • 4. HISTORY  The first stress ribbon bridge was constructed in Switzerland in the 1960s. This concept was first introduced by a German engineer Ulrich Finsterwalder.
  • 5. FORM OF A STRESS RIBBON BRIDGE Superstructure:-  A typical stress ribbon bridge deck consists of precast concrete planks with bearing tendons to support them during construction and separate pre stressing tendons which are tensioned to create the final designed geometric form.  The pre stressing tendons transfer horizontal forces in to the abutments and then to the ground most often using ground anchors.  The tendons are encased in ducts which are generally grouted after tensioning in order to lock in the stress and protect them from corrosion. Since the bending in the deck is low, the depth can be minimized and results in reduction in dead load and horizontal forces in abutments.
  • 6.  The abutments are designed to transfer the horizontal forces from the deck cables into the ground via ground anchors. Pedestrians, wind and temperature loads can cause large changes in the bending moments in the deck close to the abutments and accordingly crack widths and fatigue in reinforcement must be considered.  The ground anchors are normally tensioned in 2 stages, the first step is tensioned before the deck is erected and the rest, after the deck is complete. If stressed in one stage only, there will be a large out of balance force to be resisted by the abutments in the temporary case.  The soil pressure, overturning and sliding has to be checked for construction as well as permanent condition.  Substructure:-
  • 7. Ground Conditions:-  The ideal ground condition for resisting large horizontal forces from the ribbon is a rock base. This occurs rarely but suitable foundations can be devised even if competent soils are only found at some depth below the abutments.  In some cases where soil conditions do not permit the use of anchors, piles can also be used. Horizontal deformations can be significant and are considered in the design.  It is also possible to use a combination of anchors and drilled shafts. Battered micropilling is another alternative which can resist the load from the ribbon because of its compression and tension capacity.
  • 8. CONSTRUCTION TECHNIQUE  The abutments and piers are built first. Next the bearing cables were stretched from abutment to abutment and draped over steel saddles that rested atop the piers.  The bearing tendons generally support the structure during construction, and only rarely is additional false work used. Once the bearing cables were tensioned to the specified design force, precast panels were suspended via support rods located at the four corners of each panel. At this point the bridge sagged into its catenary shape.  The next step was to place post tensioning ducts in the bridge. The ducts were placed directly above the bearing cables and support rods, which are all located in two longitudinal troughs that run the length of the bridge. After the ducts were in place, the cast-in place concrete was placed in the longitudinal troughs in small transverse closure joints.
  • 9. STRUCTURAL SYSTEM  The development of the self-anchored stress-ribbon structure supported by an arch.  It is clear that the intermediate support of a multi-span stress-ribbon can also have the shape of an arch.  The arch serves as a saddle from which the stress-ribbon spans can rise during post- tensioning and during temperature drop, and where the center "band" can rest during a temperature rise.  In the initial stage, the stress-ribbon behaves as a two-span cable supported by the saddle that is fixed to the end abutments.
  • 10. COMPARISION WITH SIMPLE SUSPENSION BRIDGE  A stress ribbon bridge is a tension structure similar in many ways to a simple suspension bridge. The suspension cables are embedded in the deck which follows a catenary arc between the supports.  Unlike the simple span the ribbon is stressed in compression, which adds to the stiffness of the structure.  As opposed to suspension bridges, where the cables carry the load, in stress ribbon, by tensioning the cables and the deck between abutments, the deck shares axial tension forces.  A simple suspension span tends to sway and bounce. The supports in turn support upward thrusting arcs that allow the grade to be changed between spans, where multiple spans are used.
  • 11. ADVANTAGES  Stress ribbon pedestrian bridges are very economical, aesthetical and almost maintenance free structures.  They require minimal quantity of materials.  They are erected independently from existing terrain and therefore they have a minimum impact upon the environment during construction.  They are quick and convenient to construct if given appropriate conditions, without false work.  A stress ribbon bridge allows for long spans with a minimum number of piers and the piers can be shorter than those required for cable stayed or suspension bridges.
  • 12. APPLICATION & INSTANCE  Eco duct:  A tunnel which was built as part of a large network of motorways outside Brno. The theory is the same as a self-anchored arch but the geometry is much more complex. It is 50m wide and spans 70m a finite element program was used in its design.  Stuttgart trade fair hall roof: The suspended asymmetric roof comprises a regular repetition of stressed trusses with individual I-beam ribbons of steel between them. The trusses function as strut and tie A-frames based on concrete strip foundations and are tied back to the ground with anchors. The stresses in the ribbons and weight of its ‘green roof’ were used to resist wind uplift.
  • 13. CONCLUSION  Stress ribbon bridges are a versatile form of bridge, the adaptable form of structure is applicable to a variety of requirements.  The slender decks are visually pleasing and have a visual impact on surroundings giving a light aesthetic impression.  Post tensioned concrete minimizes cracking and assures durability. Bearings and expansion joints are rarely required minimizing maintenance and inspections.  Since erection using pre-cast segments does not depend on particular site condition and permits labour saving erection and a short time to delivery. Using bearing tendons can eliminate the need for site form work and large plant, contributing to fast construction programmes and preservation of the environments.  Stressed ribbon bridge is a solution to the areas which require aesthetic yet cost effective pedestrian bridges to be built .