SlideShare a Scribd company logo
1 of 54
Download to read offline
WELCOME
CONSTRUCTION SUPERVISION CONSULTANT, PMBP
BANGLADESH ARMY
PRESTRESSING OF
BRIDGE GIRDER
INTRODUCTION
ADVANTAGE OF PRESTRESSING
The prestressing of concrete has several advantages as compared to traditional
reinforced concrete (RC) without prestressing. A fully prestressed concrete member is
usually subjected to compression during service life. The advantages of prestress
concrete are as follows:
 Section remains uncracked under service loads.
 Reduction of steel corrosion and thereby increase in durability.
 Full section is utilised.
● Higher moment of inertia.
● Less deformations (improved serviceability).
 Increase in shear, bending and torsional capacities.
ADVANTAGE OF PRESTRESSING
 Improved performance (resilience) under dynamic and fatigue loading.
 Sections can behave elastically.
 Larger spans possible with prestressing (bridges, buildings).
 For the same span, less depth compared to RC member.
● Reduction in self weight.
● More aesthetic appeal due to slender sections.
● More economical sections.
ADVANTAGE OF PRESTRESSING
 Suitabality for precast construction
● Rapid construction
● Better quality control
● Reduced maintenance
● Suitable for repetitive construction
● Multiple use of formwork
● Availability of standard shapes
LIMITATIONS OF PRESTRESSING
● Prestressing needs skilled manpower
● The use of high strength materials is costly
● There is additional cost in auxiliary equipments
● There is need for quality control and inspection
TERMINOLOGY
Post-Tensioning
The application of a compressive force to the concrete by stressing tendons or bars
after the concrete has been cast and cured. The force in the stressed tendons or
bars in transferred to the concrete by means of anchorages.
Wires
Prestressing wire is a single unit made of steel.
Strands
An assembly of several high strength steel wires wound together. Stands usually
have six outer wires helically wound around a single straight wire of a similar
diameter.
Tendon
A group of strands or wires are wound to form a prestressing tendon.
TERMINOLOGY
Anchorage
An assembly of various hardware components which secure a tendon at its ends
after it has been stressed and imparts the tendon force into the concrete.
Anchor Plate (Tube Unit)
The part of the anchorage which bears directly on the concrete and through which
the tendon force is transmitted.
Wedges
A small conically shaped steel component placed around a strand to grip and
secure it by wedge action in a tapered hole through a wedge plate.
Wedge Plate
A circular steel component of the anchorage containing a number of tapered holes
through which the strands pass and are secured by conical wedges.
GIRDER SECTION INCLUDING
REBAR PLACEMENT
Reinforcement placing (Side view) Reinforcement placing (Top view)
GIRDER SECTION INCLUDING
REBAR PLACEMENT
End Section Mid Section
SHEATHING DUCT
Raw Material for Sheathing Duct
SHEATHING DUCT
Preparation of Sheathing Duct
SHEATHING DUCT
Prepared Sheathing Duct
PRESTRESSING STRAND
Coil Strand (7 wire)Wire
STRESSING CABLE & THEIR PLACEMENT
WITHIN RABAR
Cable Profile checking of cable ductCable within the rebar inside
sheating duct
ANCHORAGE MATERIALS
Tube Unit (Anchor Plate) Wedge Plate Wedges
CONCRETE MIX DESIGN
Concrete class : C50
28 days cube strength : 50 mpa
Materials
Cement : Bashundhara (Ordinary Portland Cement) OPC
Fine Aggregate : Sylhet Sand, Bangladesh
Coarse Aggregate : Meghaloy, India
Admixture : Master Polyheed 8632
Water Cement Ratio : 0.3
Slump : 150mm ~ 200mm
CONCRETE MIX DESIGN
Batch Weight per cum of Concrete on SSD Condition
Cement : 470 kg
Water : 141 kg
Fine Aggregate : 658.6 kg
Coarse Aggregate : 1152 kg
Admixture : 5.9 kg
Mix Proportion : Cement : Sand : Stone
1 : 1.40 : 2.45
CONCRETING WORK OF PC GIRDER
Girder ready for concreting Concrete Transit Mixer Car Slump Test
CONCRETING WORK OF PC GIRDER
Concreting is going on Form Vibrator
CURING
PRESTRESSING JACK & ITS FUNCTION
Jack (Front Side) Jack (Back Side)
PRESTRESSING JACK & ITS FUNCTION
Jack Setting Prestressing Pump Machine
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Tube Unit Wedge Plate
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Collar Setting Safety Protection
GIRDER END ARRANGEMENT
FOR PRESTRESSING
Master Grip
Inserting
Master Grip
Inserting
Master Grip
Jack
Setting
PRESTRESSING PULL (ELONGATION)
FROM BOTH END
1st Reading : 62 mm Final Reading : 163 mm Reading after lock off : 153 mm
Slip : 163-153= 10 mm
PRESTRESSING PULL (ELONGATION)
FROM BOTH END
Work supervised by CSC Engr. Reading just after stressing : 200 mm Reading after 24 hours : 200 mm
After 24 hours slip: 200-200=0
STRUCTURE LOAD ON EACH GIRDER AND HOW IT IS
MAINTAINED BY PRESTRESSING
Total load (LL+DL) on each 30m girder = 1643.19 kN
Jacking force on each cable = 2475 kN (As per Contract Drawings)
Jacking force on each girder (3 no cable) = 2475 x 3 = 7425 kN
Hence 7425 kN>1643 kN
Factor of Safety, FS = 7425÷1643 = 4.5 [Minimum FS is required 1.5]
So Girder is safe.
PRESTRESSING PULL IS CONVERTED INTO STRESS
Jacking force, F = 2475 kN [As per Contract Drawings]
= 2475÷0.96 [Jack efficiency 96%]
= 2578.125 kN
= 2578.125 x 1000 N [1 kN = 1000 N]
= 2578.125 x 1000÷9.81 kg [1 Kg = 9.81 N]
= 262805.81 kg
Jacking Ram Area, A = 563.72 cm2
Stress = Force/Area = F/A = 262805.81/563.72 kg/cm2
= 466.19 kg/cm2
HOGGING & IT’S MEASUREMENT
After Stressing Hogging at centre : 33 mm Measurement taking by level machine
BUCKLING & IT’S MEASUREMENT
After Stressing Reading at end section : 100 mm Reading at max buckling point
90 mm
GROUT MIX DESIGN
Water cement ratio : 0.45
Mix proportion : Water : Cement : Admixture (Cebex-100)
22.5 Kg : 50 Kg : 1 Pkt
GROUTING PROCESS
Setting Grout Inlet Pipe Washing Duct Pipe by Air
Compressor
Washing Duct Pipe by Air
Compressor
GROUTING PROCESS
Pouring Water in Agitator Pouring Cement in Agitator Mixing Grout Materials in Agitator
GROUTING PROCESS
Grouting Pump Machine Grout Come out from Agitator Grouting in Progress
GROUTING PROCESS
Grout Come out from Outlet Pipe Lock off Outlet Pipe Provide Pressure 5.25 Kg/cm2
WEIGHT OF 30M GIRDER
CRANE CAPACITY
PIER CAP SEAT ARRANGEMENT
BEARING PAD (ELASTOMERIC PAD)
Size of Bearing Pad : 500 x 250 x 60mmPlan of Bearing and Pedestal
BEARING PAD (ELASTOMERIC PAD)
BEARING PAD (ELASTOMERIC PAD)
PLACING OF RUBBER BEARING PAD
(ELASTOMERIC PAD)
Bearing Pedestal Placing Bearing Pad on Pedestal
PLACING OF GIRDER ON BEARING PAD
TIEING WITH CRANE AT GIRDER END
GIRDER LIFTING AND PLACING
GIRDER LIFTING AND PLACING
LEAVE THE GIRDER AFTER PLACING
ON PIER CAP
Cross Girder Rebar is
welded for Tieing Girders
GAP BETWEEN FLANGE TO
FLANGE OF GIRDER
Design Gap : 40mm Maximum Gap (Actual) : 85mm
GAP BETWEEN FLANGE TO
FLANGE OF GIRDER
Design Gap : 40mm Minimum Gap (Actual) : 12mm
GAP BETWEEN TWO GIRDER
Design Gap : 100mm Gap (Actual) : 115mm
CONCLUSION

More Related Content

What's hot

Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of BridgesAIT Solutions
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel StructureGaurang Kakadiya
 
ductile detailing of seismic design
ductile detailing of seismic design ductile detailing of seismic design
ductile detailing of seismic design Rahul Kumar Raj
 
Presentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinPresentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinRais Uddin
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresanand bhatnagar
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000VVIETCIVIL
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slabArvind Vishwakarma
 
OVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptOVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptSaritaJoshi5
 
Slabs -Design steps
Slabs -Design steps Slabs -Design steps
Slabs -Design steps rohinibjn
 
Module4 plastic theory- rajesh sir
Module4 plastic theory- rajesh sirModule4 plastic theory- rajesh sir
Module4 plastic theory- rajesh sirSHAMJITH KM
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxmrujjavalsinghvarana
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteMAHFUZUR RAHMAN
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaMukesh Singh Ghuraiya
 
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 SoftwareANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 SoftwareAbhinav Verma
 

What's hot (20)

Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of Bridges
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
ductile detailing of seismic design
ductile detailing of seismic design ductile detailing of seismic design
ductile detailing of seismic design
 
Presentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais UddinPresentation on Prestressing prepared by Rais Uddin
Presentation on Prestressing prepared by Rais Uddin
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slab
 
IS 800 2007
IS 800 2007IS 800 2007
IS 800 2007
 
Is 1893-part2-2014
Is 1893-part2-2014Is 1893-part2-2014
Is 1893-part2-2014
 
OVM250 Stay Cable System.ppt
OVM250 Stay Cable System.pptOVM250 Stay Cable System.ppt
OVM250 Stay Cable System.ppt
 
Structures and Materials- Section 2 Tension
Structures and Materials- Section 2 TensionStructures and Materials- Section 2 Tension
Structures and Materials- Section 2 Tension
 
Slabs -Design steps
Slabs -Design steps Slabs -Design steps
Slabs -Design steps
 
Module4 plastic theory- rajesh sir
Module4 plastic theory- rajesh sirModule4 plastic theory- rajesh sir
Module4 plastic theory- rajesh sir
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 SoftwareANALYSIS AND DESIGN OF G+3 STOREY BUILDINGUSING STAAD PRO vi8 Software
ANALYSIS AND DESIGN OF G+3 STOREY BUILDING USING STAAD PRO vi8 Software
 

Viewers also liked

CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concreteParag Pal
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concretefroskhan08
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1সাফকাত অরিন
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 

Viewers also liked (8)

CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 
Pre stressed concrete
Pre stressed concretePre stressed concrete
Pre stressed concrete
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1Prestressing Concept, Materials and Prestressing System - Section B, Group 1
Prestressing Concept, Materials and Prestressing System - Section B, Group 1
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 

Similar to Prestressing bridge girders

Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemLatif Hyder Wadho
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyoverPeer Mohideen
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
continuity of pre-cast concrete girders
 continuity of pre-cast concrete girders continuity of pre-cast concrete girders
continuity of pre-cast concrete girdersKamel Farid
 
Composite construction and cambering
Composite construction and camberingComposite construction and cambering
Composite construction and camberingguruvignesh N
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxstilliegeorgiana
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridgeDivya Vishnoi
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfad_gordon
 
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessDesign and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessNitesh Sharma
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs632k18BilalAhmad
 
FYP Presentation group 1.pptx
FYP Presentation group 1.pptxFYP Presentation group 1.pptx
FYP Presentation group 1.pptxlongwalls4
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing DesignJames Craig
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion JointRais Uddin
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptxmayur280524
 

Similar to Prestressing bridge girders (20)

Prestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing SystemPrestressing Concept, Materilas and Prestressing System
Prestressing Concept, Materilas and Prestressing System
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
continuity of pre-cast concrete girders
 continuity of pre-cast concrete girders continuity of pre-cast concrete girders
continuity of pre-cast concrete girders
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Pipe bending machine
Pipe bending machinePipe bending machine
Pipe bending machine
 
Composite construction and cambering
Composite construction and camberingComposite construction and cambering
Composite construction and cambering
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
FL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdfFL AWWA Steel Pipelines_0.pdf
FL AWWA Steel Pipelines_0.pdf
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning ProcessDesign and Preparation of Aluminium Nozzle Using Metal Spinning Process
Design and Preparation of Aluminium Nozzle Using Metal Spinning Process
 
Shear lug verification example
Shear lug verification exampleShear lug verification example
Shear lug verification example
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs1-Basics of Prestressed Concrete.pdforgs
1-Basics of Prestressed Concrete.pdforgs
 
FYP Presentation group 1.pptx
FYP Presentation group 1.pptxFYP Presentation group 1.pptx
FYP Presentation group 1.pptx
 
Drilling Engineering - Casing Design
Drilling Engineering - Casing DesignDrilling Engineering - Casing Design
Drilling Engineering - Casing Design
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Design of tension member.pptx
Design of tension member.pptxDesign of tension member.pptx
Design of tension member.pptx
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 

Prestressing bridge girders

  • 4. ADVANTAGE OF PRESTRESSING The prestressing of concrete has several advantages as compared to traditional reinforced concrete (RC) without prestressing. A fully prestressed concrete member is usually subjected to compression during service life. The advantages of prestress concrete are as follows:  Section remains uncracked under service loads.  Reduction of steel corrosion and thereby increase in durability.  Full section is utilised. ● Higher moment of inertia. ● Less deformations (improved serviceability).  Increase in shear, bending and torsional capacities.
  • 5. ADVANTAGE OF PRESTRESSING  Improved performance (resilience) under dynamic and fatigue loading.  Sections can behave elastically.  Larger spans possible with prestressing (bridges, buildings).  For the same span, less depth compared to RC member. ● Reduction in self weight. ● More aesthetic appeal due to slender sections. ● More economical sections.
  • 6. ADVANTAGE OF PRESTRESSING  Suitabality for precast construction ● Rapid construction ● Better quality control ● Reduced maintenance ● Suitable for repetitive construction ● Multiple use of formwork ● Availability of standard shapes
  • 7. LIMITATIONS OF PRESTRESSING ● Prestressing needs skilled manpower ● The use of high strength materials is costly ● There is additional cost in auxiliary equipments ● There is need for quality control and inspection
  • 8. TERMINOLOGY Post-Tensioning The application of a compressive force to the concrete by stressing tendons or bars after the concrete has been cast and cured. The force in the stressed tendons or bars in transferred to the concrete by means of anchorages. Wires Prestressing wire is a single unit made of steel. Strands An assembly of several high strength steel wires wound together. Stands usually have six outer wires helically wound around a single straight wire of a similar diameter. Tendon A group of strands or wires are wound to form a prestressing tendon.
  • 9. TERMINOLOGY Anchorage An assembly of various hardware components which secure a tendon at its ends after it has been stressed and imparts the tendon force into the concrete. Anchor Plate (Tube Unit) The part of the anchorage which bears directly on the concrete and through which the tendon force is transmitted. Wedges A small conically shaped steel component placed around a strand to grip and secure it by wedge action in a tapered hole through a wedge plate. Wedge Plate A circular steel component of the anchorage containing a number of tapered holes through which the strands pass and are secured by conical wedges.
  • 10. GIRDER SECTION INCLUDING REBAR PLACEMENT Reinforcement placing (Side view) Reinforcement placing (Top view)
  • 11. GIRDER SECTION INCLUDING REBAR PLACEMENT End Section Mid Section
  • 12. SHEATHING DUCT Raw Material for Sheathing Duct
  • 16. STRESSING CABLE & THEIR PLACEMENT WITHIN RABAR Cable Profile checking of cable ductCable within the rebar inside sheating duct
  • 17. ANCHORAGE MATERIALS Tube Unit (Anchor Plate) Wedge Plate Wedges
  • 18. CONCRETE MIX DESIGN Concrete class : C50 28 days cube strength : 50 mpa Materials Cement : Bashundhara (Ordinary Portland Cement) OPC Fine Aggregate : Sylhet Sand, Bangladesh Coarse Aggregate : Meghaloy, India Admixture : Master Polyheed 8632 Water Cement Ratio : 0.3 Slump : 150mm ~ 200mm
  • 19. CONCRETE MIX DESIGN Batch Weight per cum of Concrete on SSD Condition Cement : 470 kg Water : 141 kg Fine Aggregate : 658.6 kg Coarse Aggregate : 1152 kg Admixture : 5.9 kg Mix Proportion : Cement : Sand : Stone 1 : 1.40 : 2.45
  • 20. CONCRETING WORK OF PC GIRDER Girder ready for concreting Concrete Transit Mixer Car Slump Test
  • 21. CONCRETING WORK OF PC GIRDER Concreting is going on Form Vibrator
  • 23. PRESTRESSING JACK & ITS FUNCTION Jack (Front Side) Jack (Back Side)
  • 24. PRESTRESSING JACK & ITS FUNCTION Jack Setting Prestressing Pump Machine
  • 25. GIRDER END ARRANGEMENT FOR PRESTRESSING Tube Unit Wedge Plate
  • 26. GIRDER END ARRANGEMENT FOR PRESTRESSING Collar Setting Safety Protection
  • 27. GIRDER END ARRANGEMENT FOR PRESTRESSING Master Grip Inserting Master Grip Inserting Master Grip Jack Setting
  • 28. PRESTRESSING PULL (ELONGATION) FROM BOTH END 1st Reading : 62 mm Final Reading : 163 mm Reading after lock off : 153 mm Slip : 163-153= 10 mm
  • 29. PRESTRESSING PULL (ELONGATION) FROM BOTH END Work supervised by CSC Engr. Reading just after stressing : 200 mm Reading after 24 hours : 200 mm After 24 hours slip: 200-200=0
  • 30. STRUCTURE LOAD ON EACH GIRDER AND HOW IT IS MAINTAINED BY PRESTRESSING Total load (LL+DL) on each 30m girder = 1643.19 kN Jacking force on each cable = 2475 kN (As per Contract Drawings) Jacking force on each girder (3 no cable) = 2475 x 3 = 7425 kN Hence 7425 kN>1643 kN Factor of Safety, FS = 7425÷1643 = 4.5 [Minimum FS is required 1.5] So Girder is safe.
  • 31. PRESTRESSING PULL IS CONVERTED INTO STRESS Jacking force, F = 2475 kN [As per Contract Drawings] = 2475÷0.96 [Jack efficiency 96%] = 2578.125 kN = 2578.125 x 1000 N [1 kN = 1000 N] = 2578.125 x 1000÷9.81 kg [1 Kg = 9.81 N] = 262805.81 kg Jacking Ram Area, A = 563.72 cm2 Stress = Force/Area = F/A = 262805.81/563.72 kg/cm2 = 466.19 kg/cm2
  • 32. HOGGING & IT’S MEASUREMENT After Stressing Hogging at centre : 33 mm Measurement taking by level machine
  • 33. BUCKLING & IT’S MEASUREMENT After Stressing Reading at end section : 100 mm Reading at max buckling point 90 mm
  • 34. GROUT MIX DESIGN Water cement ratio : 0.45 Mix proportion : Water : Cement : Admixture (Cebex-100) 22.5 Kg : 50 Kg : 1 Pkt
  • 35. GROUTING PROCESS Setting Grout Inlet Pipe Washing Duct Pipe by Air Compressor Washing Duct Pipe by Air Compressor
  • 36. GROUTING PROCESS Pouring Water in Agitator Pouring Cement in Agitator Mixing Grout Materials in Agitator
  • 37. GROUTING PROCESS Grouting Pump Machine Grout Come out from Agitator Grouting in Progress
  • 38. GROUTING PROCESS Grout Come out from Outlet Pipe Lock off Outlet Pipe Provide Pressure 5.25 Kg/cm2
  • 39. WEIGHT OF 30M GIRDER
  • 41. PIER CAP SEAT ARRANGEMENT
  • 42. BEARING PAD (ELASTOMERIC PAD) Size of Bearing Pad : 500 x 250 x 60mmPlan of Bearing and Pedestal
  • 45. PLACING OF RUBBER BEARING PAD (ELASTOMERIC PAD) Bearing Pedestal Placing Bearing Pad on Pedestal
  • 46. PLACING OF GIRDER ON BEARING PAD
  • 47. TIEING WITH CRANE AT GIRDER END
  • 50. LEAVE THE GIRDER AFTER PLACING ON PIER CAP Cross Girder Rebar is welded for Tieing Girders
  • 51. GAP BETWEEN FLANGE TO FLANGE OF GIRDER Design Gap : 40mm Maximum Gap (Actual) : 85mm
  • 52. GAP BETWEEN FLANGE TO FLANGE OF GIRDER Design Gap : 40mm Minimum Gap (Actual) : 12mm
  • 53. GAP BETWEEN TWO GIRDER Design Gap : 100mm Gap (Actual) : 115mm