CONTENT
 Introduction to rock bolting
Rock Bolts, Rock Anchors
 Tension bolt
 mechanical bolt
 friction bolt
 grouted bolt or cable
 Shear bolt (dowel action)
 Long or relatively short?
Benefits of a Bolt
Tensile force in bolt produces greater normal force &
hence joint friction and anti-sliding force, Ta
TYPES 0F ROCKBOLTS
A. Mechanically Anchored
 Cone forced into expanding shell @ base by
screwing nut to shank
 Voids subsequently grouted
 Moderately hard to hard rocks
 slipping likely in VERY hard rock
 Blast vibration may loosen anchor
 Digunakan untuk lubang bukaan pada
batuan terkekarkan
 Daerah yang berpotensi terjadinya
runtuhan baji atau blok
 Mudah dan cepat dalam
pemasangannya
 Dapat ditarik untuk memberi efek
kuncian pada potensial baji yang
tidak stabil
Terbagi menjadi ( berdasarkan
pengaplikasiaannya):
 Ungrouted mechanicals anchored bolt
• pada daerah non korosi
• Untuk penggunaan jangka pendek
dan menengah
 Grouted mechanicals anchored bolt
• Terdapat resiko korosi
• Penggunaan jangka panjang
• Grouted dilakukan setelah periode
tarikan
Reference: Hoek, E., Ch 14 of
Practical Rock Engineering, 2007
http://www.rocscience.com/hoek/pdf/14_Rockbolts_and_cables.pdf
TYPES 0F ROCKBOLTS
B. Friction Anchored Rock Bolts (heavily jointed
rock) perlu wire mesh/shotcrete
Split-set & Swellex
1. Swellex - collapsed tube, expanded in drillhole
with water pressure
 Pull-out resistance dependent on applied water
pressure
 Expensive and temporary
http://www.swellex.com/
TYPES 0F ROCKBOLTS
B. Friction Anchored Rock Bolts
2. Split-set - collapsed tube, expanded in drillhole
with water pressure
 borehole diameter crucial: must be slightly smaller than
split-set
 no tension
 bolt lengths < 3 m
www.splitset.com/rock-bolts.html
TYPES 0F ROCKBOLTS
C. Grouted Rock Bolts
 Cement or resin cartridge placed in drillhole
 Reobar ‘drilled’ through cartridges
 Top of the bolt not bonded to the grout (wrapped
in PVC tape)
 Nut tensioned against anchored end
 Versatile, high corrosion resistance
http://www.rocscience.com/hoek/pdf/14_Rockbolts_and_cables.pdf
Reference: Hoek, E., Ch 14 of
Practical Rock Engineering, 2007
TYPES 0F ROCKBOLTS
D. Grouted Cable Bolts
 Temporary support systems
 Untensioned fully grouted cables (used in the
mining industry)
 act as passive reinforcement
 the rock mass must be in a state of compression
during installation
 dilation upon shearing tensions the anchor
Passive reinforcement
- non-tensioned
Tensile force develops as slide initiates:
dilational joint only (rough, undulating)
Example of use of Cable Bolts
Windy Point Great Ocean Road
 instability of 200,000 tons of rock
 Sandstones, interbedded mudstones, 27° dip seaward
 Problems during installation; slide moving @ 2 cm per
day
 Slide stopped after first 7 anchors installed
 45 x 170 ton anchors, 18 to 43m long
 Estimated F of S = 1.07
Summary: Rock bolts
Rock bolts and cables can incorporate;
• mechanical anchorage
• grout
Rock bolts and cables may be post-
tensioned (active) or rely on the rock
mass to do the work (passive)

More Related Content

What's hot

Rock bolts simon madiro
Rock bolts   simon madiroRock bolts   simon madiro
Rock bolts simon madiroSimon Madiro
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation openingJyoti Khatiwada
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in miningRishabh Ranjan
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKAKeith Kong
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drillpavan kumar
 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic AnalysisKrishnagnr
 
Response Spectrum
Response SpectrumResponse Spectrum
Response SpectrumTeja Ande
 
Down the hole drilling
Down the hole drillingDown the hole drilling
Down the hole drillingAnil Kilania
 
Engineering rock mechanics volume1
Engineering rock mechanics volume1Engineering rock mechanics volume1
Engineering rock mechanics volume1batbold113o
 
Dynamic Analysis of Machine Foundation
Dynamic Analysis of Machine FoundationDynamic Analysis of Machine Foundation
Dynamic Analysis of Machine FoundationIRJET Journal
 
Techniques for measuring insitu stresses
Techniques for measuring insitu stressesTechniques for measuring insitu stresses
Techniques for measuring insitu stressesZeeshan Afzal
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound minesUlimella Siva Sankar
 
Slope monitoring & instrumentation
Slope monitoring & instrumentationSlope monitoring & instrumentation
Slope monitoring & instrumentationRathin Biswas
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal minesSunil Varma
 

What's hot (20)

Rock bolts simon madiro
Rock bolts   simon madiroRock bolts   simon madiro
Rock bolts simon madiro
 
Rock testing
Rock testingRock testing
Rock testing
 
Stress types around excavation opening
Stress types around excavation openingStress types around excavation opening
Stress types around excavation opening
 
SLOPE STABILITY AND FAILURE
SLOPE STABILITY AND FAILURESLOPE STABILITY AND FAILURE
SLOPE STABILITY AND FAILURE
 
Behaviour Pattern of Slopes Tunnels in Discontinous Rock Media
Behaviour Pattern of Slopes Tunnels in Discontinous Rock MediaBehaviour Pattern of Slopes Tunnels in Discontinous Rock Media
Behaviour Pattern of Slopes Tunnels in Discontinous Rock Media
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in mining
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKA
 
Design of openings
Design of openingsDesign of openings
Design of openings
 
Blast hole drill
Blast hole drillBlast hole drill
Blast hole drill
 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic Analysis
 
Response Spectrum
Response SpectrumResponse Spectrum
Response Spectrum
 
Down the hole drilling
Down the hole drillingDown the hole drilling
Down the hole drilling
 
Engineering rock mechanics volume1
Engineering rock mechanics volume1Engineering rock mechanics volume1
Engineering rock mechanics volume1
 
Dynamic Analysis of Machine Foundation
Dynamic Analysis of Machine FoundationDynamic Analysis of Machine Foundation
Dynamic Analysis of Machine Foundation
 
Ductile detailing ppt
Ductile detailing pptDuctile detailing ppt
Ductile detailing ppt
 
Techniques for measuring insitu stresses
Techniques for measuring insitu stressesTechniques for measuring insitu stresses
Techniques for measuring insitu stresses
 
Ground control in undergound mines
Ground control in undergound minesGround control in undergound mines
Ground control in undergound mines
 
Slope monitoring & instrumentation
Slope monitoring & instrumentationSlope monitoring & instrumentation
Slope monitoring & instrumentation
 
Subsidence control in coal mines
Subsidence control in coal minesSubsidence control in coal mines
Subsidence control in coal mines
 

Similar to pdfslide.net_rock-bolts-2009ppt.ppt

PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE524001
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridgeDivya Vishnoi
 
Geology Presentation
Geology PresentationGeology Presentation
Geology Presentationguest1a8d587
 
Chapter 5 rock_slope_stabilization
Chapter 5 rock_slope_stabilizationChapter 5 rock_slope_stabilization
Chapter 5 rock_slope_stabilizationSunil Nepal
 
slides construction engineering 2024.pptx
slides construction engineering 2024.pptxslides construction engineering 2024.pptx
slides construction engineering 2024.pptxnishalini16
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1DYPCET
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingHamed Zarei
 
Pre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyPre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyAnjith Augustine
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdfRijuDasgupta
 
Post tensioning شد لاحق - مسبق الاجهاد
Post tensioning   شد لاحق - مسبق الاجهادPost tensioning   شد لاحق - مسبق الاجهاد
Post tensioning شد لاحق - مسبق الاجهادDr.Youssef Hammida
 
Transmission tower
Transmission towerTransmission tower
Transmission towerKiran Hadiya
 

Similar to pdfslide.net_rock-bolts-2009ppt.ppt (20)

PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
PHC-Pile-Brochure.pdf
PHC-Pile-Brochure.pdfPHC-Pile-Brochure.pdf
PHC-Pile-Brochure.pdf
 
Expansion joints in bridge
Expansion joints in bridgeExpansion joints in bridge
Expansion joints in bridge
 
Geology Presentation
Geology PresentationGeology Presentation
Geology Presentation
 
Chapter 5 rock_slope_stabilization
Chapter 5 rock_slope_stabilizationChapter 5 rock_slope_stabilization
Chapter 5 rock_slope_stabilization
 
slides construction engineering 2024.pptx
slides construction engineering 2024.pptxslides construction engineering 2024.pptx
slides construction engineering 2024.pptx
 
Prestressed
PrestressedPrestressed
Prestressed
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Geosynthetics in Civil Engineering
Geosynthetics in Civil Engineering Geosynthetics in Civil Engineering
Geosynthetics in Civil Engineering
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
Pre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technologyPre stressed concrete- modular construction technology
Pre stressed concrete- modular construction technology
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
Post tensioning شد لاحق - مسبق الاجهاد
Post tensioning   شد لاحق - مسبق الاجهادPost tensioning   شد لاحق - مسبق الاجهاد
Post tensioning شد لاحق - مسبق الاجهاد
 
Transmission tower
Transmission towerTransmission tower
Transmission tower
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 

Recently uploaded

TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxJisc
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsNbelano25
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsSandeep D Chaudhary
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptxJoelynRubio1
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfPondicherry University
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfDr Vijay Vishwakarma
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
What is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptxWhat is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptxCeline George
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonhttgc7rh9c
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfKartik Tiwari
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfNirmal Dwivedi
 

Recently uploaded (20)

TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
VAMOS CUIDAR DO NOSSO PLANETA! .
VAMOS CUIDAR DO NOSSO PLANETA!                    .VAMOS CUIDAR DO NOSSO PLANETA!                    .
VAMOS CUIDAR DO NOSSO PLANETA! .
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
OSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & SystemsOSCM Unit 2_Operations Processes & Systems
OSCM Unit 2_Operations Processes & Systems
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
What is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptxWhat is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptx
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdfDiuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
Diuretic, Hypoglycemic and Limit test of Heavy metals and Arsenic.-1.pdf
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
 

pdfslide.net_rock-bolts-2009ppt.ppt

  • 1. ROCK BOLTING Rock and Soils 2009 Don Cameron
  • 3. Rock Bolts, Rock Anchors  Tension bolt  mechanical bolt  friction bolt  grouted bolt or cable  Shear bolt (dowel action)  Long or relatively short?
  • 4. Benefits of a Bolt Tensile force in bolt produces greater normal force & hence joint friction and anti-sliding force, Ta
  • 5. TYPES 0F ROCKBOLTS A. Mechanically Anchored  Cone forced into expanding shell @ base by screwing nut to shank  Voids subsequently grouted  Moderately hard to hard rocks  slipping likely in VERY hard rock  Blast vibration may loosen anchor
  • 6.  Digunakan untuk lubang bukaan pada batuan terkekarkan  Daerah yang berpotensi terjadinya runtuhan baji atau blok  Mudah dan cepat dalam pemasangannya  Dapat ditarik untuk memberi efek kuncian pada potensial baji yang tidak stabil
  • 7. Terbagi menjadi ( berdasarkan pengaplikasiaannya):  Ungrouted mechanicals anchored bolt • pada daerah non korosi • Untuk penggunaan jangka pendek dan menengah  Grouted mechanicals anchored bolt • Terdapat resiko korosi • Penggunaan jangka panjang • Grouted dilakukan setelah periode tarikan
  • 8. Reference: Hoek, E., Ch 14 of Practical Rock Engineering, 2007 http://www.rocscience.com/hoek/pdf/14_Rockbolts_and_cables.pdf
  • 9. TYPES 0F ROCKBOLTS B. Friction Anchored Rock Bolts (heavily jointed rock) perlu wire mesh/shotcrete Split-set & Swellex 1. Swellex - collapsed tube, expanded in drillhole with water pressure  Pull-out resistance dependent on applied water pressure  Expensive and temporary http://www.swellex.com/
  • 10. TYPES 0F ROCKBOLTS B. Friction Anchored Rock Bolts 2. Split-set - collapsed tube, expanded in drillhole with water pressure  borehole diameter crucial: must be slightly smaller than split-set  no tension  bolt lengths < 3 m www.splitset.com/rock-bolts.html
  • 11. TYPES 0F ROCKBOLTS C. Grouted Rock Bolts  Cement or resin cartridge placed in drillhole  Reobar ‘drilled’ through cartridges  Top of the bolt not bonded to the grout (wrapped in PVC tape)  Nut tensioned against anchored end  Versatile, high corrosion resistance
  • 13. TYPES 0F ROCKBOLTS D. Grouted Cable Bolts  Temporary support systems  Untensioned fully grouted cables (used in the mining industry)  act as passive reinforcement  the rock mass must be in a state of compression during installation  dilation upon shearing tensions the anchor
  • 14. Passive reinforcement - non-tensioned Tensile force develops as slide initiates: dilational joint only (rough, undulating)
  • 15. Example of use of Cable Bolts Windy Point Great Ocean Road  instability of 200,000 tons of rock  Sandstones, interbedded mudstones, 27° dip seaward  Problems during installation; slide moving @ 2 cm per day  Slide stopped after first 7 anchors installed  45 x 170 ton anchors, 18 to 43m long  Estimated F of S = 1.07
  • 16.
  • 17. Summary: Rock bolts Rock bolts and cables can incorporate; • mechanical anchorage • grout Rock bolts and cables may be post- tensioned (active) or rely on the rock mass to do the work (passive)