SlideShare a Scribd company logo
1 of 68
Download to read offline
NAME: SAPTADEEP
DASGUPTA
SUB:PRESTRESSED
CONCRETE TOPIC:P LINE
&C LINE METHOD
SUBJECT
CODE:CE(PE)702A
DEPT.:CE
YEAR: 4ND
SEM: 7TH
ROLL NO.: 26901321007
MODERN
INSTITUTE OF
ENGINEERING &
TECHNOLOGY
{DEDICATED TO EXCELLENCE}
METHODS OF PRESTRESSING
IN CONCRETE
PRESTENSIONING & POST- TENSIONING
INDEX
🞇 INTRODUCTION
🞇 PRESTRESSED
CONCRETE
🞇 METHODS & BENIFIT
🞇 PROPERTIES
🞇 CONCLUSION
🞇 REFERENCE
🞇 ACKNOWLEDGEMENT
PRESTRESSED CONCRETE
●
●
PRINCIPLE – Using high tensile strength
steel alloys producing permanent pre-
compression in areas subjected to Tension.
A portion of tensile stress is counteracted
thereby reducing the cross-sectional area of
the steel reinforcement .
● METHODS :- a) Pretensioning
b)Post-tensioning
●
●
PRETENSIONING :- Placing of concrete
around reinforcing tendons that have been
stressed to the desired degree.
POST-TENSIONING :- Reinforcing tendons
are stretched by jacks whilst keeping them in
serted in voids left pre-hand during curing of
●
concrete.
These spaces are then pumped full of grout to
bond steel tightly to the concrete.
STEEL BARS BEING
STRETCHED BY JACKS
POST - TENSIONING
● WHAT IS POST-TENSIONING?
● Post-tensioning- is a method of reinforcing
(strengthening) concrete or other materials with high-
strength steel strands called tendons.
● Post-tensioning allows construction
otherwise be impossible due to
that would
either site
●
constraints or architectural requirements.
Requires specialized knowledge and expertise to
fabricate, assemble and install.
● After adequate curing of concrete, reinforcing
tendons (placed in side the voids of the structure)
are tensioned/stretched by jacks on the sides &
grouts filled with appropriate mix.
● Applications – a) Structural members beams,
bridge-deck panels, Roof –Slabs, Concrete Silos
Etc.
POST –TENSIONING METHOD
B E N E F I T S
●
●
●
●
●
●
● Concrete is very strong in compression but
weak in tension,
This deflection will cause the bottom of the beam
to elongate slightly & cause cracking.
Steel reinforcing bars (“rebar”) are typically
embedded in the concrete as tensile
reinforcement to limit the crack widths.
Rebar is what is called “passive” reinforcement
however; it does not carry any force until the
concrete has already deflected enough to crack.
Post-tensioning tendons, on the other hand, are
considered “active” reinforcing.
Because it is prestressed, the steel is effective
as reinforcement even though the concrete may
not be cracked .
Post-tensioned structures can be designed to
have minimal deflection and cracking, even
under full load.
Post –Tensioned Structure
ADVANTAGES/APPLICATIONS
●
●
●
●
●
Post-tensioning allows longer clear spans, thinner
slabs, fewer beams and more slender, dramatic
elements.
Thinner slabs mean less concrete is required. It
means a lower overall building height for the same
floor-to-floor height.
Post-tensioning can thus allow a significant
reduction in building weight versus a conventional
concrete building with the same number of floors
reducing the foundation load and can be a major
advantage in seismic areas.
A lower building height can also translate to
considerable savings in mechanical systems and
façade costs.
Another advantage of post-tensioning is that beams
and slabs can be continuous, i.e. a single beam can
building to
run continuously from one end of the
the other.
Reduces occurrence of cracks .
●
● Freezing & thawing durability is higher than non
prestressed concrete.
This innovative form is result of
post tensioning.
Bridge decks
●Post-tensioning is the system of choice for parking structures
since it allows a high degree of flexibility in the column layout,
span lengths and ramp configurations.
● In areas where there are expansive clays or soils with low
bearing capacity, post-tensioned slabs-on-ground and mat
foundations reduce problems with cracking and differential
●
settlement.
Post-tensioning allows bridges to be built to very
demanding geometry requirements, including complex
curves, and significant grade changes.
●
●
●
●
●
Post-tensioning also allows extremely long span bridges to be
constructed without the use of temporary intermediate
supports. This minimizes the impact on the environment
and avoids disruption to water or road traffic below.
In stadiums, post-tensioning allows long clear spans and very
creative architecture. 
Post-tensioning can also be used to produce virtually crack-free
concrete for water-tanks.
The high tensile strength & precision of placement gives
maximum efficiency in size & weight of structural members.
Applications of various prestressed techniques enable quick
assembly of standard units such as bridge members,building
frames, bridge decks providing cost-time savings.
CONSTRUCTION
●
●
●
●
●
●
●
● In slab-on-ground construction, unbonded tendons
are typically prefabricated at a plant and delivered to
the construction site, ready to install.
The tendons are laid out in the forms in accordance
with installation drawings that .
After the concrete is placed and has reached its
required
strength, usually between 3000 and 3500 psi
(“pounds per
square inch”), the tendons are stressed and
anchored.
The tendons, like rubber bands, want to return to
their original length but are prevented from doing so
by the anchorages.
The fact the tendons are kept in a permanently
stressed
(elongated) state causes a compressive force to act
on the
concrete.
The compression that results from the post-tensioning
counteracts the tensile forces created by subsequent
applied loading (cars, people, the weight of the
beam itself when the shoring is removed).
This significantly increases the load-carrying capacity
of the concrete.
Since post-tensioned concrete is cast in place at the
job site, there is almost no limit to the shapes that can
be formed.
Limitations of Prestressing
The limitations of prestressed concrete are few and really
depend only upon the imagination of the designer and the
terms of his brief. The only real limitation where
prestressing is a possible solution may be the cost of
providing moulds for runs of limited quantity of small
numbers of non-standard units.
Method of post-tensioning
TENDONS
Wedges tensioned by
jacks
Tendons
PRESTRESSED CONCRETE
●
●
●
●
●
●
●
● Prestressed concrete, invented by Eugene
Frevssinet in 1928 is a method for overcoming
concrete’’s natural weakness in tension . It can
be used to produce beams , floors or bridges
with a longer span than is practical with
ordinary reinforced concrete.
It can be accomplished in three ways: pre-
tensioned concrete, and bonded or unbonded.
Pre-tensioned concrete
Pre-tensioned concrete is cast around already tensioned
tendons.
This method produces a good bond between the tendon
and concrete, which both protects the tendon from
corrosion and allows for direct transfer of tension.
The cured concrete adheres and bonds to the bars and
when the tension is released it is transferred to the
concrete as compression by static friction.
However, it requires stout anchoring points between
which the tendon is to be stretched and the tendons are
usually in a straight line.
Thus, most pretensioned concrete elements are
prefabricated in a factory and must be transported to the
construction site, which limits their size.
Pre-tensioned elements may be balcony elements, lintels
, floor slabs, beams or foundation piles.
Bonded post-tensioned concrete
●
●
●
●
●
●
● Bonded post-tensioned concrete is the descriptive term for a
method of applying compression after pouring concrete and
the curing process (in situ).
The concrete is cast around a plastic, steel or aluminium
curved duct, to follow the area where otherwise tension would
occur in the concrete element.
A set of tendons are fished through the duct and the concrete
is poured. Once the concrete has hardened, the tendons are
tensioned by hydraulic jacks.
When the tendons have stretched sufficiently, according to the
design specifications they are wedged in position and maintain
tension after the jacks are removed, transferring pressure to
the concrete.
The duct is then grouted to protect the tendons from corrosion.
This method is commonly used to create monolithic slabs for
house construction in locations where expansive soils create
problems for the typical perimeter foundation.
All stresses from seasonal expansion and contraction of the
underlying soil are taken into the entire tensioned slab, which
supports the building without significant flexure. Post-stressing
is also used in the construction of various bridges.
The advantages of this system over unbonded post-tensioning
are:
DECKSTEELLA
YING
● Large reduction in traditional reinforcement
requirements as tendons cannot destress in
accidents.
● Tendons can be easily 'weaved' allowing a
more efficient design approach.
● Higher ultimate strength due to bond
generated between the strand and concrete.
● No long term issues with maintaining the
integrity of the anchor/dead end.
Unbonded post-tensioned
concrete
● Unbonded post-tensioned concrete differs
from bonded post-tensioning by providing
each individual cable permanent freedom of
movement relative to the concrete.
●
● To achieve this, each individual tendon is
coated with a grease (generally lithium
based) and covered by a plastic sheathing
formed in an extrusion process.
The transfer of tension to the concrete is
achieved by the steel cable acting against
steel anchors in the perimeter of the slab.
● The main disadvantage over bonded post-
tensioning is the fact that a cable can
destress itself and burst out of the slab if
damaged (such as during repair on the slab).
The advantages of this system over bonded
post-tensioning are:
External Prestressing
●
●
This refers to the case where prestressing tendons are
placed outside the concrete section and the
prestressing force is transferred to a structural member
through end anchorages or deviators. Advantages of
external prestressing include the possibility of
monitoring and replacing tendons, ease in concreting
and hence better concrete quality and the use of
narrower webs. External prestressing is being
increasingly used in the construction of new bridges
and is a primary method for the strengthening and
rehabilitation of existing structures.
At NUS, a three-year project on the application of
external prestressing in structural strengthening has
been completed, and this has resulted in design charts
being developed for such applications. Works were
also carried out on the use of fibre-reinforced polymer
(FRP) reinforcement as external tendons in both
simply supported and continuous beams.
•Fallingwater is comprised of a series of concrete cantilever
“trays” 30-ft. above a waterfall. Previous efforts failed to
permanently address excessive deflections of the cantilever
and repair the cracks. After a thorough design review, the
owner and engineer selected an external post-tensioning
solution for its durability, aesthetics and structural
unobtrusiveness.
•Construction plans called for strengthening of three support
girders spanning in the north-south direction with multistrand
post-tensioning tendons consisting of multiple 0.5” diameter
strands.
•Thirteen strand tendons were placed on each side of two
girders. One 10-strand tendon was placed on the western side
of the third girder (access on the eastern side of this girder
was not available). Eight monostrand tendons, 0.6” diameter,
were slated for the east-west direction.
•The monostrand tendons were stressed in the east-west
direction and then the multistrand tendons were stressed in
the north-south direction and grouted with a high quality, low-
bleed cementitious grout mixture.
•VSL’s scope of work also included welding steel cover plates,
attaching structural steel channels, injecting epoxy grout,
doweling reinforced cast in place concrete blocks and the
installation of near surface mounted carbon fiber rods.
Challenged with maintaining Fallingwater’s original setting,
furnishings and artwork, the project was successfully
completed in six months.
The lower and upper terraces cantilever
over the stream below. The temporary
structural steel shoring was placed beneath
the main level terrace.
Frank Lloyd Wright's Fallingwater
Mill Run, Pennsylvania
APPLICATIONS
●
●
●
●
●
●
Cline Avenue Bridge
Gary, Indiana
The Cline Avenue Bridge (SR 912) is a predominately cast-in-place post-tensioned
structure located in Gary, Indiana. The bridge mainline is over 6,000 LF, has two
adjacent segments nearly 35 feet wide each, and contains four connecting ramps.
An inspection and analysis team was assembled to perform a thorough investigation
of the bridge. The team concentrated on the existing post-tensioning system and
interior and exterior concrete cracks. The engineer retained VSL to assist with the
inspection of the tendons.
VSL approached the Cline Avenue project with a guideline that outlines a statistically
sound method of sampling the tendons. A statistical sample pool (which consisted of
the mainline structure and the ramps) was defined by referencing the American
National Standard Institute’s (ANSI) guideline “Sampling Procedures and Tables for
Inspection by Attributes as published by the American Society for Quality Control
(1993).”
The probable void locations throughout the structure’s mainline segments and ramps
were initially identified by VSL to appropriately distribute the sampling population.
Such areas consisted of high points, areas approaching and leaving the high points,
and couplers.
Using non-destructive Ground Penetrating Radar (GPR) and field layout drawings,
VSL located existing post-tensioning tendons. Once the layout was performed,
specific tendons throughout the bridge and ramp structures were sampled by drilling
into the duct and exposing the tendon for visual inspection. The use of a borescope
allowed for detailed visual inspection of the tendon and also captured video footage
to share with the owner and the engineer. After review of each inspection, VSL
placed epoxy in the borescope hole to protect the tendons from air and moisture
intrusion. When voids were encountered, the project team observed and
documented the condition of the strand based on the PCI Journal guideline,
“Evaluation of Degree of Rusting on Prestressed Concrete Strand.” VSL used
vacuum grouting technology to fill the void, thereby protecting the previously
exposed strand.
The tendon inspection data was analyzed with other findings (such as crack survey
findings) to determine what type of rehabilitation was required. VSL’s goal to
establish a statistically sound sample of physically inspected tendons that proGvrio
du
etdi
ngof void using VSL’s specialized vacuum grouting equipment
valid data as to the current state of the existing PT system was accomplished
●
●
●
●
85th Street Bridge
Valley Center, Kansas
The 85th Street North Bridge is a seven span post-tensioned
haunched slab bridge with a typical span of 26 meters for the
middle five spans, and 20 meters at the ends. This 170 meter
long bridge accommodates two lanes of traffic reaching over
the Wichita Valley Center Floodway. VSL post-tensioning
systems utilized for this project include 5-19 longitudinal
tendons as well as 6-4 transverse tendons.
Post-tensioned haunched slab bridges are noted for ease of
construction. Once the geometry of the bridge falsework has
been obtained, prefabricated spacer frames are set into
place. The spacer frames serve as templates for profiling the
longitudinal post-tensioning tendons and aid in the placement
of the remaining conventional reinforcement. Transverse
tendons maintain mid-depth placement along the geometry
of the haunched slab and provide the minimum pre-
compression over the length of the structure.
The finished product has several advantages over
conventionally reinforced concrete. Dead loads are balanced
by the use of longitudinal post-tensioning reducing the
sustained loading and associated creep. Corrosion
resistance is increased due to the encapsulation of the post-
tensioning reinforcement. Through the use of transverse
post-tensioning, added compression improves the longevity
of the structure by adding resistance to de-icing methods
such as salt and magnesium chloride. Post-tensioned
haunched slab bridges allow for a larger span to depth ratio
than that of conventionally reinforced haunched slab bridges.
The labor and material savings on mild reinforcement is
another clear advantage to using post-tensioning for this
application.
Overlooking the 85th Street Bridge prior to concrete placement
Colorado Convention Center
Expansion
Denver, Colorado
●
●
●
● The Colorado Convention Center Expansion
project is a 1.4 million square foot expansion of
the existing facility. This was a multi-level
project, which included a 1,000-car attached
parking garage.
The garage above the street was constructed
using precast tees and columns with a cast-in-
place topping slab. In order to maintain regular
spacing for the columns in the precast section
of the garage and still maintain an
unobstructed path for the road and light rail,
large post-tensioned transfer girders were
required to support several of the columns
above. The transfer girders allowed for the
placement of columns required for the precast
design despite the restricted column locations
at the street level.
Post-tensioning the transfer girders resulted in
smaller dimensions than a conventional
reinforced concrete design, an important factor
given the girders are over 7 feet high and up to
7 feet wide and a larger section would not fit
within the space constraints of the building.
The girders could not be stressed until after the
precast garage was fully erected and the
topping slab poured on the truck dock.
Temporary columns were placed under the
girders to support the load until stressing.
The effective post-tensioning force required for
the beams ranged from 2176 to 5457 kips. A
multistrand bonded system was installed
●
●
●
●
The Seward Silo project involved the post-tensioning of three
interconnected ash silos that are part of the Seward Re-Powering
Project in Seward, Pennsylvania. The overall project involved the
construction of a new, state-of-the-art 208 MW power plant designed to
burn low-grade coal that can not be burned in ordinary coal plants. This
is a design-build project with Drake-Fluor Daniel as the
owner/construction manager until the completed plant is turned over to
Reliant Energy, the ultimate owner.
T.E. Ibberson Company was contracted to build three 187’-6” tall,
interconnected, in-line silos; two 82’-4” diameter fly ash silos and one
64’-8” diameter bed ash silo. The silos were built using the slip-form
method of construction and are believed to be the first interconnected
silos in the world built using post-tensioning as the primary
circumferential reinforcement.
VSL’s work was performed from November 2003 through February
2004, during the second coldest winter on record locally. Significant
snowfall and subzero temperatures made progress challenging, yet with
a strong focus on safety, both cold-related and otherwise, the job was
completed with no incidents. The job required close coordination
between the various trades working in close proximity and constant
communication between parties working above and below VSL’s work
locations to phase the work to avoid having personnel under an active
work zone.
The strand installation, stressing and grouting operations were
completed successfully, with cold-weather grouting made possible
through a variety of heating methods.
Seward Silo
THE BICYCLE WHEEL
●
●
●
● Bicycle wheel as we know it today - each is
associated with an application of prestressing to
a structural system.
The first and most obvious is the tensioned
spokes - the rider's weight is carried from the
forks to the ground not by hanging off the top
spokes, but by reducing the pretension in the
lower spokes - only a couple of spokes are
carrying the load at any one time.
The second is the pneumatic tyre, where the
compressive load is carried to the ground by
reducing the tension in the sidewall. The air
pressure in the tyre does not change when the
load is applied.
The final prestressing system is the tyre cord,
which is shorter than the perimeter of the rim.
The cord is thus in tension, holding the tyre on
the rim, which enables the pretension in the
sidewalls to be reacted
EQUIPMENTS :-
●
●
T6Z-08 Air Powered Grout Pump
Pumps cement grout only, no sand. 32 Gallon Mixing
Tank. Mixes up to 2 sacks of material at once and allows
for grout to be pumped during mixing or mixed without
pumping.
Approxim
atesize 50
" long
30
.5" high
52" wide
Weight 560 lbs.
ProductionRate 8 gallonsper minute
at 150 psi
●
●
Colloidal Grout Plant
The heavy duty, high volume Colloidal Grout Plant is favored for precision
post-tension grouting. The unit features a high speed shear mixer that
thoroughly wets each particle and discharges the mixed material into a 13
cubic foot capacity agitating holding tank. A direct coupled progressing
cavity pump delivers slurries at a rate of up to 20 gpm and pressures of up
to 261 psi. The unit easily mixes and pumps slurries of Portland cement,
fly ash, bentonite, and lime flour. All controls are conveniently located on
the operator platform for easy one-man control.
Pump
Pump Type
31.6 progressing
cavity
Output/Pressure
variable up to 20
gpm, 261 psi
Colloidal Mixer
Mix Tank
13.0 CF with
bottom clean out
Mixing Pump
2 x 3 x 6 diffuser-
type centrifugal
Holding Tank
13.0 paddle
agitating
Drive Power Air 300 CFM, 100 psi
Physical
Specifications
Dimensions
96" L x 60" W x 63"
H
Weight 1800-2800 lbs.
●
●
●
T7Z Hydraulic Jacks
Used for testing and pre-stressing anchor bolts. Available
with up to 5-1/8" center hole. Unit comes with ram, pump,
gauge, hoses, jack stand, high strength coupling, high
strength test rod, plate, hex nut and knocker wrench.
Calibrations are available upon request.
Note: Jack pull rods should have a higher capacity than the
anchor rod.
●
●
T80 Post-Tensioning Jacks
With the T80 series the enclosed bearing
housing contains a geared socket drive to
tighten the bolt hex nut during tensioning.
Test jack housing will accommodate up to a
9” deep pocket.
T8
0Post-Tensioning Jacks
● T8Z-18 Hydraulic Torque Wrench
● The hydraulic torque wrench is used for tensioning
anchors in tight fitting locations where it would be difficult
to use an hydraulic jack. The wrench is also
recommended for use when setting the large diameter
Spin-Lock anchors. The torque wrenches are light weight
and can achieve a maximum of 8,000 ft-lbs. Torque
Tensioning charts Williams products can be found here.
Maximum
Torque
5,590
ft./lbs.
(773 kg/M)
8,000 ft.lbs.
(1,006
kg/M)
Length Height Weight
11.11" 4.49" 16.75 lbs.
(279 mm) (114 kg) (7.6 kg)
12.57" 5.09" 24.95 lbs.
(319 kg) (129 kg) (11.3 kg)
●
●
T8Z Torque Wrench
For applying torque to the anchor bolt
when setting the anchor. Torque
Tensioning charts Williams products can
be found here.
Bolt
Diameter
*1/2"-1"
1/2"-1"
*1-1/8"-2"
Square
Drive Size
3/4"
3/4"
1"
Capacity
(ft. lbs.)
0-500
0-600
0-1,000
T8Z-04 Torque Multiplier (4:1)
For use with T8Z Torque Wrench. Other sizes
available
Size Drive
Input
Square Square
Drive
Output
Maxim
um
Torque
GA 186 1" 1-1/2"
4,000
(ft. lbs.)
●
●
T1Z & T2Z Long Fitting Tool Adapters
For driving hex nuts and setting tools,
typically with our Spin-Lock anchor
systems. Works with torque wrench or
impact gun.
Available with 1" or 1-1/2" square drive.
Please specify square drive for
compatability with your equipment.
2Z RegularSocket T1ZDeepSocket
K3F-26 Long Fitting Wrench Adapter
For applying torque to recessed anchor nuts that are under tension
when using hydraulic jacks. Available in all anchor sizes.
Corrosion Protection
Corrosion
Protection
Type
Abrasion
Resistance
(4=best)
Typical
Thickness
Relative
Cost
(4=highest)
Lead Time
Can be
applied to
accessories
?
Hot Dip
Galvanizing
4 3-4 mils 2 2-4 weeks yes
Epoxy
Coating
1 7-12 mils 1 2-3 weeks yes
Pre-Grouted
Bars
3
2", 3" or 4"
tubing
3 2 weeks no
Extruded
Polyethylene 2 23-25 mils 1 2-4 weeks no
Coating
Corrosion
Inhibiting 2 N.A. 2 2-4 weeks yes
Compound
Methodsof CorrosionProtection
Methods of Corrosion Protection
● Epoxy Coating
Fusion bonded epoxy coating of steel bars to help prevent
corrosion has been successfully employed in many applications
because of the chemical stability of epoxy resins. Epoxy coated
bars and fasteners should be done in accordance with ASTM A-
775 or ASTM 934. Coating thickness is generally specified
between 7 to 12 mils. Epoxy coated bars and components are
subject to damage if dragged on the ground or mishandled.
Heavy plates and nuts are often galvanized even though the bar
may be epoxy coated since they are difficult to protect against
abrasion in the field. Epoxy coating patch kits are often used in
the field for repairing nicked or scratched epoxy surfaces.
Cement Grout filled corrugated polyethylene tubing is often used to
provide an additional barrier against corrosion attack in highly
aggressive soils. These anchors are often referred to as MCP or
Multiple Corrosion Protection anchors. The steel bars are wrapped
with an internal centralizer then placed inside of the polyethylene tube
where they are then factory pre-grouted. When specifying couplings
with MCP ground anchors, verify coupling locations with a Williams
representative.
Pre-GroutedBars
●
●
Williams strand tendons contain an extruded high density
polyethylene sheathing around each individual strand in the
free-stressing portion of the anchorage. The sheathing is
minimum 60 mils thick and applied once the 7-wire strand
has been coated with a corrosion inhibiting compound.
Extruded polyethylene sheathing provides a moisture tight
barrier for corrosion protection and allows the strand to
elongate freely throughout the free-stressing length during
the prestressing operation
Hot Dip Galvanizing
Zinc serves as a sacrificial metal corroding preferentially
to the steel. Galvanized bars have excellent bond
characteristics to grout or concrete and do not require as
much care in handling as epoxy coated bars. However,
galvanization of anchor rods is more expensive than
epoxy coating and often has greater lead time. Hot dip
galvanizing bars and fasteners should be done in
accordance with ASTM A-153. Typical galvanized
coating thickness for steel bars and components is
between 3 and 4 mils. 150 KSI high strength steel bars
should always be mechanically cleaned (never acid
washed) to avoid problems associated with hydrogen
embrittlement.
Extruded Polyethylene
CorrosionInhibitingWaxorGreasewithSheath
Williams corrosion inhibiting compounds can be placed in the
free stressing sleeves, in the end caps, or in the trumpet
areas. Often bars are greased/waxed and PVC is slipped
over the greased/waxed bar prior to shipping. Each are
of an organic compound with either a grease or wax
base. They provide the appropriate polar moisture
displacement and have corrosion inhibiting additives with
self-healing properties. They can be pumped or applied
manually. Corrosion inhibiting compounds stay
permanently viscous, chemically stable and non-reactive
with the prestressing steel, duct materials or grout. Both
compounds meet PTI standards for Corrosion Inhibiting
Coating.
Coal Tar Epoxy
Coal tar epoxy has shown to be abrasion resistant,
economical and durable. This product when specified
should meet or exceed the requirements of (a) Corp of
Engineers C-200, C200a and (b) AWWA C-210-92 for
exterior. Typically the thickness is between 8 and 24
mils. Make sure that the surfaces of the bar are clean
and dry before coating.
●
●
Heat Shrink Tubing
Heat Shrink Tubing provides a corrosion
protected seal when connecting smooth or
corrugated segments.
E
poxy CoatingPatchKits
Epoxy Coating Patch Kits are available uponrequest.
Anchor Head Protection
The most important section of a ground anchor that needs adequate
corrosion protection is the portion of the anchor exposed to air/oxygen.
This is typically defined as the "anchor head", which generally consists of a
steel bearing plate, a hex nut and washer for a bar system, or a wedge
plate and wedges for a strand system. For permanent ground anchors it is
best to galvanize the hex nut and plates even if the bar is epoxy coated.
Galvanized components, if scratched during shipping, are less likely to
provide corrosion protection at otherwise exposed anchor ends.
FiberReinforced
cause corrosion concerns than scratched epoxy coated components. TheNylonCap
end of the steel bar protruding out from the hex nut is often protected by
the use of a plastic or steel end cap packed with grease or cement grout.
Williams offers several different types of PVC and metal end caps to
Strand
E
ndCap
Screw-On
PVCCap
SteelTubeW
eldedonFlangewith
ThreadedScrewConnections
●
●
Field Splice for Bars
Continuous corrosion protection can even be
accomplished for the MCP Pregrouted anchors
manufactured from Williams Form Engineering. To
achieve the equivalent levels of corrosion protection
the coupled sections of bar anchors can be wrapped
in a grease impregnated tape that is further protected
with heat shrink sleeving. This scheme is acceptable
by most governing agencies and is specified in the
PTI Recommendations for Prestresed Rock and Soil
Anchors.
PRESTRESSED CONCRETE
●
●
PRINCIPLE – Using high tensile strength
steel alloys producing permanent pre-
compression in areas subjected to Tension.
A portion of tensile stress is counteracted
thereby reducing the cross-sectional area of
the steel reinforcement .
● METHODS :- a) Pretensioning
b)Post-tensioning
●
●
PRETENSIONING :- Placing of concrete
around reinforcing tendons that have been
stressed to the desired degree.
POST-TENSIONING :- Reinforcing tendons
are stretched by jacks whilst keeping them in
serted in voids left pre-hand during curing of
●
concrete.
These spaces are then pumped full of grout to
bond steel tightly to the concrete.
STEEL BARS BEING
STRETCHED BY JACKS
POST - TENSIONING
● WHAT IS POST-TENSIONING?
● Post-tensioning- is a method of reinforcing
(strengthening) concrete or other materials with high-
strength steel strands called tendons.
● Post-tensioning allows construction
otherwise be impossible due to
that would
either site
●
constraints or architectural requirements.
Requires specialized knowledge and expertise to
fabricate, assemble and install.
● After adequate curing of concrete, reinforcing
tendons (placed in side the voids of the structure)
are tensioned/stretched by jacks on the sides &
grouts filled with appropriate mix.
● Applications – a) Structural members beams,
bridge-deck panels, Roof –Slabs, Concrete Silos
Etc.
POST –TENSIONING METHOD
B E N E F I T S
●
●
●
●
●
●
● Concrete is very strong in compression but
weak in tension,
This deflection will cause the bottom of the beam
to elongate slightly & cause cracking.
Steel reinforcing bars (“rebar”) are typically
embedded in the concrete as tensile
reinforcement to limit the crack widths.
Rebar is what is called “passive” reinforcement
however; it does not carry any force until the
concrete has already deflected enough to crack.
Post-tensioning tendons, on the other hand, are
considered “active” reinforcing.
Because it is prestressed, the steel is effective
as reinforcement even though the concrete may
not be cracked .
Post-tensioned structures can be designed to
have minimal deflection and cracking, even
under full load.
Post –Tensioned Structure
ADVANTAGES/APPLICATIONS
●
●
●
●
●
Post-tensioning allows longer clear spans, thinner
slabs, fewer beams and more slender, dramatic
elements.
Thinner slabs mean less concrete is required. It
means a lower overall building height for the same
floor-to-floor height.
Post-tensioning can thus allow a significant
reduction in building weight versus a conventional
concrete building with the same number of floors
reducing the foundation load and can be a major
advantage in seismic areas.
A lower building height can also translate to
considerable savings in mechanical systems and
façade costs.
Another advantage of post-tensioning is that beams
and slabs can be continuous, i.e. a single beam can
building to
run continuously from one end of the
the other.
Reduces occurrence of cracks .
●
● Freezing & thawing durability is higher than non
prestressed concrete.
This innovative form is result of
post tensioning.
Bridge decks
●Post-tensioning is the system of choice for parking structures
since it allows a high degree of flexibility in the column layout,
span lengths and ramp configurations.
● In areas where there are expansive clays or soils with low
bearing capacity, post-tensioned slabs-on-ground and mat
foundations reduce problems with cracking and differential
●
settlement.
Post-tensioning allows bridges to be built to very
demanding geometry requirements, including complex
curves, and significant grade changes.
●
●
●
●
●
Post-tensioning also allows extremely long span bridges to be
constructed without the use of temporary intermediate
supports. This minimizes the impact on the environment
and avoids disruption to water or road traffic below.
In stadiums, post-tensioning allows long clear spans and very
creative architecture. 
Post-tensioning can also be used to produce virtually crack-free
concrete for water-tanks.
The high tensile strength & precision of placement gives
maximum efficiency in size & weight of structural members.
Applications of various prestressed techniques enable quick
assembly of standard units such as bridge members,building
frames, bridge decks providing cost-time savings.
CONSTRUCTION
●
●
●
●
●
●
●
● In slab-on-ground construction, unbonded tendons
are typically prefabricated at a plant and delivered to
the construction site, ready to install.
The tendons are laid out in the forms in accordance
with installation drawings that .
After the concrete is placed and has reached its
required
strength, usually between 3000 and 3500 psi
(“pounds per
square inch”), the tendons are stressed and
anchored.
The tendons, like rubber bands, want to return to
their original length but are prevented from doing so
by the anchorages.
The fact the tendons are kept in a permanently
stressed
(elongated) state causes a compressive force to act
on the
concrete.
The compression that results from the post-tensioning
counteracts the tensile forces created by subsequent
applied loading (cars, people, the weight of the
beam itself when the shoring is removed).
This significantly increases the load-carrying capacity
of the concrete.
Since post-tensioned concrete is cast in place at the
job site, there is almost no limit to the shapes that can
be formed.
Limitations of Prestressing
The limitations of prestressed concrete are few and really
depend only upon the imagination of the designer and the
terms of his brief. The only real limitation where
prestressing is a possible solution may be the cost of
providing moulds for runs of limited quantity of small
numbers of non-standard units.
Method of post-tensioning
TENDONS
Wedges tensioned by
jacks
Tendons
PRESTRESSED CONCRETE
●
●
●
●
●
●
●
● Prestressed concrete, invented by Eugene
Frevssinet in 1928 is a method for overcoming
concrete’’s natural weakness in tension . It can
be used to produce beams , floors or bridges
with a longer span than is practical with
ordinary reinforced concrete.
It can be accomplished in three ways: pre-
tensioned concrete, and bonded or unbonded.
Pre-tensioned concrete
Pre-tensioned concrete is cast around already tensioned
tendons.
This method produces a good bond between the tendon
and concrete, which both protects the tendon from
corrosion and allows for direct transfer of tension.
The cured concrete adheres and bonds to the bars and
when the tension is released it is transferred to the
concrete as compression by static friction.
However, it requires stout anchoring points between
which the tendon is to be stretched and the tendons are
usually in a straight line.
Thus, most pretensioned concrete elements are
prefabricated in a factory and must be transported to the
construction site, which limits their size.
Pre-tensioned elements may be balcony elements, lintels
, floor slabs, beams or foundation piles.
Bonded post-tensioned concrete
●
●
●
●
●
●
● Bonded post-tensioned concrete is the descriptive term for a
method of applying compression after pouring concrete and
the curing process (in situ).
The concrete is cast around a plastic, steel or aluminium
curved duct, to follow the area where otherwise tension would
occur in the concrete element.
A set of tendons are fished through the duct and the concrete
is poured. Once the concrete has hardened, the tendons are
tensioned by hydraulic jacks.
When the tendons have stretched sufficiently, according to the
design specifications they are wedged in position and maintain
tension after the jacks are removed, transferring pressure to
the concrete.
The duct is then grouted to protect the tendons from corrosion.
This method is commonly used to create monolithic slabs for
house construction in locations where expansive soils create
problems for the typical perimeter foundation.
All stresses from seasonal expansion and contraction of the
underlying soil are taken into the entire tensioned slab, which
supports the building without significant flexure. Post-stressing
is also used in the construction of various bridges.
The advantages of this system over unbonded post-tensioning
are:
DECKSTEELLA
YING
● Large reduction in traditional reinforcement
requirements as tendons cannot destress in
accidents.
● Tendons can be easily 'weaved' allowing a
more efficient design approach.
● Higher ultimate strength due to bond
generated between the strand and concrete.
● No long term issues with maintaining the
integrity of the anchor/dead end.
Unbonded post-tensioned
concrete
● Unbonded post-tensioned concrete differs
from bonded post-tensioning by providing
each individual cable permanent freedom of
movement relative to the concrete.
●
● To achieve this, each individual tendon is
coated with a grease (generally lithium
based) and covered by a plastic sheathing
formed in an extrusion process.
The transfer of tension to the concrete is
achieved by the steel cable acting against
steel anchors in the perimeter of the slab.
● The main disadvantage over bonded post-
tensioning is the fact that a cable can
destress itself and burst out of the slab if
damaged (such as during repair on the slab).
The advantages of this system over bonded
post-tensioning are:
External Prestressing
●
●
This refers to the case where prestressing tendons are
placed outside the concrete section and the
prestressing force is transferred to a structural member
through end anchorages or deviators. Advantages of
external prestressing include the possibility of
monitoring and replacing tendons, ease in concreting
and hence better concrete quality and the use of
narrower webs. External prestressing is being
increasingly used in the construction of new bridges
and is a primary method for the strengthening and
rehabilitation of existing structures.
At NUS, a three-year project on the application of
external prestressing in structural strengthening has
been completed, and this has resulted in design charts
being developed for such applications. Works were
also carried out on the use of fibre-reinforced polymer
(FRP) reinforcement as external tendons in both
simply supported and continuous beams.
•Fallingwater is comprised of a series of concrete cantilever
“trays” 30-ft. above a waterfall. Previous efforts failed to
permanently address excessive deflections of the cantilever
and repair the cracks. After a thorough design review, the
owner and engineer selected an external post-tensioning
solution for its durability, aesthetics and structural
unobtrusiveness.
•Construction plans called for strengthening of three support
girders spanning in the north-south direction with multistrand
post-tensioning tendons consisting of multiple 0.5” diameter
strands.
•Thirteen strand tendons were placed on each side of two
girders. One 10-strand tendon was placed on the western side
of the third girder (access on the eastern side of this girder
was not available). Eight monostrand tendons, 0.6” diameter,
were slated for the east-west direction.
•The monostrand tendons were stressed in the east-west
direction and then the multistrand tendons were stressed in
the north-south direction and grouted with a high quality, low-
bleed cementitious grout mixture.
•VSL’s scope of work also included welding steel cover plates,
attaching structural steel channels, injecting epoxy grout,
doweling reinforced cast in place concrete blocks and the
installation of near surface mounted carbon fiber rods.
Challenged with maintaining Fallingwater’s original setting,
furnishings and artwork, the project was successfully
completed in six months.
The lower and upper terraces cantilever
over the stream below. The temporary
structural steel shoring was placed beneath
the main level terrace.
Frank Lloyd Wright's Fallingwater
Mill Run, Pennsylvania
APPLICATIONS
●
●
●
●
●
●
Cline Avenue Bridge
Gary, Indiana
The Cline Avenue Bridge (SR 912) is a predominately cast-in-place post-tensioned
structure located in Gary, Indiana. The bridge mainline is over 6,000 LF, has two
adjacent segments nearly 35 feet wide each, and contains four connecting ramps.
An inspection and analysis team was assembled to perform a thorough investigation
of the bridge. The team concentrated on the existing post-tensioning system and
interior and exterior concrete cracks. The engineer retained VSL to assist with the
inspection of the tendons.
VSL approached the Cline Avenue project with a guideline that outlines a statistically
sound method of sampling the tendons. A statistical sample pool (which consisted of
the mainline structure and the ramps) was defined by referencing the American
National Standard Institute’s (ANSI) guideline “Sampling Procedures and Tables for
Inspection by Attributes as published by the American Society for Quality Control
(1993).”
The probable void locations throughout the structure’s mainline segments and ramps
were initially identified by VSL to appropriately distribute the sampling population.
Such areas consisted of high points, areas approaching and leaving the high points,
and couplers.
Using non-destructive Ground Penetrating Radar (GPR) and field layout drawings,
VSL located existing post-tensioning tendons. Once the layout was performed,
specific tendons throughout the bridge and ramp structures were sampled by drilling
into the duct and exposing the tendon for visual inspection. The use of a borescope
allowed for detailed visual inspection of the tendon and also captured video footage
to share with the owner and the engineer. After review of each inspection, VSL
placed epoxy in the borescope hole to protect the tendons from air and moisture
intrusion. When voids were encountered, the project team observed and
documented the condition of the strand based on the PCI Journal guideline,
“Evaluation of Degree of Rusting on Prestressed Concrete Strand.” VSL used
vacuum grouting technology to fill the void, thereby protecting the previously
exposed strand.
The tendon inspection data was analyzed with other findings (such as crack survey
findings) to determine what type of rehabilitation was required. VSL’s goal to
establish a statistically sound sample of physically inspected tendons that proGvrio
du
etdi
ngof void using VSL’s specialized vacuum grouting equipment
valid data as to the current state of the existing PT system was accomplished
●
●
●
●
85th Street Bridge
Valley Center, Kansas
The 85th Street North Bridge is a seven span post-tensioned
haunched slab bridge with a typical span of 26 meters for the
middle five spans, and 20 meters at the ends. This 170 meter
long bridge accommodates two lanes of traffic reaching over
the Wichita Valley Center Floodway. VSL post-tensioning
systems utilized for this project include 5-19 longitudinal
tendons as well as 6-4 transverse tendons.
Post-tensioned haunched slab bridges are noted for ease of
construction. Once the geometry of the bridge falsework has
been obtained, prefabricated spacer frames are set into
place. The spacer frames serve as templates for profiling the
longitudinal post-tensioning tendons and aid in the placement
of the remaining conventional reinforcement. Transverse
tendons maintain mid-depth placement along the geometry
of the haunched slab and provide the minimum pre-
compression over the length of the structure.
The finished product has several advantages over
conventionally reinforced concrete. Dead loads are balanced
by the use of longitudinal post-tensioning reducing the
sustained loading and associated creep. Corrosion
resistance is increased due to the encapsulation of the post-
tensioning reinforcement. Through the use of transverse
post-tensioning, added compression improves the longevity
of the structure by adding resistance to de-icing methods
such as salt and magnesium chloride. Post-tensioned
haunched slab bridges allow for a larger span to depth ratio
than that of conventionally reinforced haunched slab bridges.
The labor and material savings on mild reinforcement is
another clear advantage to using post-tensioning for this
application.
Overlooking the 85th Street Bridge prior to concrete placement
Colorado Convention Center
Expansion
Denver, Colorado
●
●
●
● The Colorado Convention Center Expansion
project is a 1.4 million square foot expansion of
the existing facility. This was a multi-level
project, which included a 1,000-car attached
parking garage.
The garage above the street was constructed
using precast tees and columns with a cast-in-
place topping slab. In order to maintain regular
spacing for the columns in the precast section
of the garage and still maintain an
unobstructed path for the road and light rail,
large post-tensioned transfer girders were
required to support several of the columns
above. The transfer girders allowed for the
placement of columns required for the precast
design despite the restricted column locations
at the street level.
Post-tensioning the transfer girders resulted in
smaller dimensions than a conventional
reinforced concrete design, an important factor
given the girders are over 7 feet high and up to
7 feet wide and a larger section would not fit
within the space constraints of the building.
The girders could not be stressed until after the
precast garage was fully erected and the
topping slab poured on the truck dock.
Temporary columns were placed under the
girders to support the load until stressing.
The effective post-tensioning force required for
the beams ranged from 2176 to 5457 kips. A
multistrand bonded system was installed
●
●
●
●
The Seward Silo project involved the post-tensioning of three
interconnected ash silos that are part of the Seward Re-Powering
Project in Seward, Pennsylvania. The overall project involved the
construction of a new, state-of-the-art 208 MW power plant designed to
burn low-grade coal that can not be burned in ordinary coal plants. This
is a design-build project with Drake-Fluor Daniel as the
owner/construction manager until the completed plant is turned over to
Reliant Energy, the ultimate owner.
T.E. Ibberson Company was contracted to build three 187’-6” tall,
interconnected, in-line silos; two 82’-4” diameter fly ash silos and one
64’-8” diameter bed ash silo. The silos were built using the slip-form
method of construction and are believed to be the first interconnected
silos in the world built using post-tensioning as the primary
circumferential reinforcement.
VSL’s work was performed from November 2003 through February
2004, during the second coldest winter on record locally. Significant
snowfall and subzero temperatures made progress challenging, yet with
a strong focus on safety, both cold-related and otherwise, the job was
completed with no incidents. The job required close coordination
between the various trades working in close proximity and constant
communication between parties working above and below VSL’s work
locations to phase the work to avoid having personnel under an active
work zone.
The strand installation, stressing and grouting operations were
completed successfully, with cold-weather grouting made possible
through a variety of heating methods.
Seward Silo
THE BICYCLE WHEEL
●
●
●
● Bicycle wheel as we know it today - each is
associated with an application of prestressing to
a structural system.
The first and most obvious is the tensioned
spokes - the rider's weight is carried from the
forks to the ground not by hanging off the top
spokes, but by reducing the pretension in the
lower spokes - only a couple of spokes are
carrying the load at any one time.
The second is the pneumatic tyre, where the
compressive load is carried to the ground by
reducing the tension in the sidewall. The air
pressure in the tyre does not change when the
load is applied.
The final prestressing system is the tyre cord,
which is shorter than the perimeter of the rim.
The cord is thus in tension, holding the tyre on
the rim, which enables the pretension in the
sidewalls to be reacted
EQUIPMENTS :-
●
●
T6Z-08 Air Powered Grout Pump
Pumps cement grout only, no sand. 32 Gallon Mixing
Tank. Mixes up to 2 sacks of material at once and allows
for grout to be pumped during mixing or mixed without
pumping.
Approxim
atesize 50
" long
30
.5" high
52" wide
Weight 560 lbs.
ProductionRate 8 gallonsper minute
at 150 psi
●
●
Colloidal Grout Plant
The heavy duty, high volume Colloidal Grout Plant is favored for precision
post-tension grouting. The unit features a high speed shear mixer that
thoroughly wets each particle and discharges the mixed material into a 13
cubic foot capacity agitating holding tank. A direct coupled progressing
cavity pump delivers slurries at a rate of up to 20 gpm and pressures of up
to 261 psi. The unit easily mixes and pumps slurries of Portland cement,
fly ash, bentonite, and lime flour. All controls are conveniently located on
the operator platform for easy one-man control.
Pump
Pump Type
31.6 progressing
cavity
Output/Pressure
variable up to 20
gpm, 261 psi
Colloidal Mixer
Mix Tank
13.0 CF with
bottom clean out
Mixing Pump
2 x 3 x 6 diffuser-
type centrifugal
Holding Tank
13.0 paddle
agitating
Drive Power Air 300 CFM, 100 psi
Physical
Specifications
Dimensions
96" L x 60" W x 63"
H
Weight 1800-2800 lbs.
●
●
●
T7Z Hydraulic Jacks
Used for testing and pre-stressing anchor bolts. Available
with up to 5-1/8" center hole. Unit comes with ram, pump,
gauge, hoses, jack stand, high strength coupling, high
strength test rod, plate, hex nut and knocker wrench.
Calibrations are available upon request.
Note: Jack pull rods should have a higher capacity than the
anchor rod.
●
●
T80 Post-Tensioning Jacks
With the T80 series the enclosed bearing
housing contains a geared socket drive to
tighten the bolt hex nut during tensioning.
Test jack housing will accommodate up to a
9” deep pocket.
T8
0Post-Tensioning Jacks
● T8Z-18 Hydraulic Torque Wrench
● The hydraulic torque wrench is used for tensioning
anchors in tight fitting locations where it would be difficult
to use an hydraulic jack. The wrench is also
recommended for use when setting the large diameter
Spin-Lock anchors. The torque wrenches are light weight
and can achieve a maximum of 8,000 ft-lbs. Torque
Tensioning charts Williams products can be found here.
Maximum
Torque
5,590
ft./lbs.
(773 kg/M)
8,000 ft.lbs.
(1,006
kg/M)
Length Height Weight
11.11" 4.49" 16.75 lbs.
(279 mm) (114 kg) (7.6 kg)
12.57" 5.09" 24.95 lbs.
(319 kg) (129 kg) (11.3 kg)
●
●
T8Z Torque Wrench
For applying torque to the anchor bolt
when setting the anchor. Torque
Tensioning charts Williams products can
be found here.
Bolt
Diameter
*1/2"-1"
1/2"-1"
*1-1/8"-2"
Square
Drive Size
3/4"
3/4"
1"
Capacity
(ft. lbs.)
0-500
0-600
0-1,000
T8Z-04 Torque Multiplier (4:1)
For use with T8Z Torque Wrench. Other sizes
available
Size Drive
Input
Square Square
Drive
Output
Maxim
um
Torque
GA 186 1" 1-1/2"
4,000
(ft. lbs.)
●
●
T1Z & T2Z Long Fitting Tool Adapters
For driving hex nuts and setting tools,
typically with our Spin-Lock anchor
systems. Works with torque wrench or
impact gun.
Available with 1" or 1-1/2" square drive.
Please specify square drive for
compatability with your equipment.
2Z RegularSocket T1ZDeepSocket
K3F-26 Long Fitting Wrench Adapter
For applying torque to recessed anchor nuts that are under tension
when using hydraulic jacks. Available in all anchor sizes.
Corrosion Protection
Corrosion
Protection
Type
Abrasion
Resistance
(4=best)
Typical
Thickness
Relative
Cost
(4=highest)
Lead Time
Can be
applied to
accessories
?
Hot Dip
Galvanizing
4 3-4 mils 2 2-4 weeks yes
Epoxy
Coating
1 7-12 mils 1 2-3 weeks yes
Pre-Grouted
Bars
3
2", 3" or 4"
tubing
3 2 weeks no
Extruded
Polyethylene 2 23-25 mils 1 2-4 weeks no
Coating
Corrosion
Inhibiting 2 N.A. 2 2-4 weeks yes
Compound
Methodsof CorrosionProtection
Methods of Corrosion Protection
● Epoxy Coating
Fusion bonded epoxy coating of steel bars to help prevent
corrosion has been successfully employed in many applications
because of the chemical stability of epoxy resins. Epoxy coated
bars and fasteners should be done in accordance with ASTM A-
775 or ASTM 934. Coating thickness is generally specified
between 7 to 12 mils. Epoxy coated bars and components are
subject to damage if dragged on the ground or mishandled.
Heavy plates and nuts are often galvanized even though the bar
may be epoxy coated since they are difficult to protect against
abrasion in the field. Epoxy coating patch kits are often used in
the field for repairing nicked or scratched epoxy surfaces.
Cement Grout filled corrugated polyethylene tubing is often used to
provide an additional barrier against corrosion attack in highly
aggressive soils. These anchors are often referred to as MCP or
Multiple Corrosion Protection anchors. The steel bars are wrapped
with an internal centralizer then placed inside of the polyethylene tube
where they are then factory pre-grouted. When specifying couplings
with MCP ground anchors, verify coupling locations with a Williams
representative.
Pre-GroutedBars
●
●
Williams strand tendons contain an extruded high density
polyethylene sheathing around each individual strand in the
free-stressing portion of the anchorage. The sheathing is
minimum 60 mils thick and applied once the 7-wire strand
has been coated with a corrosion inhibiting compound.
Extruded polyethylene sheathing provides a moisture tight
barrier for corrosion protection and allows the strand to
elongate freely throughout the free-stressing length during
the prestressing operation
Hot Dip Galvanizing
Zinc serves as a sacrificial metal corroding preferentially
to the steel. Galvanized bars have excellent bond
characteristics to grout or concrete and do not require as
much care in handling as epoxy coated bars. However,
galvanization of anchor rods is more expensive than
epoxy coating and often has greater lead time. Hot dip
galvanizing bars and fasteners should be done in
accordance with ASTM A-153. Typical galvanized
coating thickness for steel bars and components is
between 3 and 4 mils. 150 KSI high strength steel bars
should always be mechanically cleaned (never acid
washed) to avoid problems associated with hydrogen
embrittlement.
Extruded Polyethylene
CorrosionInhibitingWaxorGreasewithSheath
Williams corrosion inhibiting compounds can be placed in the
free stressing sleeves, in the end caps, or in the trumpet
areas. Often bars are greased/waxed and PVC is slipped
over the greased/waxed bar prior to shipping. Each are
of an organic compound with either a grease or wax
base. They provide the appropriate polar moisture
displacement and have corrosion inhibiting additives with
self-healing properties. They can be pumped or applied
manually. Corrosion inhibiting compounds stay
permanently viscous, chemically stable and non-reactive
with the prestressing steel, duct materials or grout. Both
compounds meet PTI standards for Corrosion Inhibiting
Coating.
Coal Tar Epoxy
Coal tar epoxy has shown to be abrasion resistant,
economical and durable. This product when specified
should meet or exceed the requirements of (a) Corp of
Engineers C-200, C200a and (b) AWWA C-210-92 for
exterior. Typically the thickness is between 8 and 24
mils. Make sure that the surfaces of the bar are clean
and dry before coating.
●
●
Heat Shrink Tubing
Heat Shrink Tubing provides a corrosion
protected seal when connecting smooth or
corrugated segments.
E
poxy CoatingPatchKits
Epoxy Coating Patch Kits are available uponrequest.
Anchor Head Protection
The most important section of a ground anchor that needs adequate
corrosion protection is the portion of the anchor exposed to air/oxygen.
This is typically defined as the "anchor head", which generally consists of a
steel bearing plate, a hex nut and washer for a bar system, or a wedge
plate and wedges for a strand system. For permanent ground anchors it is
best to galvanize the hex nut and plates even if the bar is epoxy coated.
Galvanized components, if scratched during shipping, are less likely to
provide corrosion protection at otherwise exposed anchor ends.
FiberReinforced
cause corrosion concerns than scratched epoxy coated components. TheNylonCap
end of the steel bar protruding out from the hex nut is often protected by
the use of a plastic or steel end cap packed with grease or cement grout.
Williams offers several different types of PVC and metal end caps to
Strand
E
ndCap
Screw-On
PVCCap
SteelTubeW
eldedonFlangewith
ThreadedScrewConnections
●
●
Field Splice for Bars
Continuous corrosion protection can even be
accomplished for the MCP Pregrouted anchors
manufactured from Williams Form Engineering. To
achieve the equivalent levels of corrosion protection
the coupled sections of bar anchors can be wrapped
in a grease impregnated tape that is further protected
with heat shrink sleeving. This scheme is acceptable
by most governing agencies and is specified in the
PTI Recommendations for Prestresed Rock and Soil
Anchors.
CONCLUSION
🞇 FRO M THE WHO LE DISCUSSIO N WE CAN CONCLUDE P LINE & AND C
LINE METHOD IS VERY ESSENTIAL FOR HIGHLY LOADED STRUCTURES
ACKNOWLEDGEMENT
🞇 Iwould like to express my special thanks of
gratitude to my teacher SAPTADEEP
DASGUPTAwho gave a golden opportunity
to do this wonder full PPT on the topic
“ P LINE AND C LINE METHODS” which
also helped me to gather more knowledge
on it.
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf

More Related Content

Similar to 26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf

Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE524001
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment ReportWan Nee
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints Hanzlahakhlaq
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteUdisha15
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingAnchitSharma17
 

Similar to 26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf (20)

Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
PRE STRESSED CONCRETE
PRE STRESSED CONCRETEPRE STRESSED CONCRETE
PRE STRESSED CONCRETE
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
A Post Tension Primer
A Post Tension PrimerA Post Tension Primer
A Post Tension Primer
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment Report
 
Long Span Structures
Long Span StructuresLong Span Structures
Long Span Structures
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Difogfufl l
Difogfufl lDifogfufl l
Difogfufl l
 
Post Tensioning
Post TensioningPost Tensioning
Post Tensioning
 
prestress Register (1).pdf
prestress Register (1).pdfprestress Register (1).pdf
prestress Register (1).pdf
 
Pre fabricatted and pre engineered building
Pre fabricatted and pre engineered buildingPre fabricatted and pre engineered building
Pre fabricatted and pre engineered building
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 

More from RijuDasgupta

26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf
26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf
26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdfRijuDasgupta
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdfRijuDasgupta
 
swpiracyslideshare-180302131348.pdf
swpiracyslideshare-180302131348.pdfswpiracyslideshare-180302131348.pdf
swpiracyslideshare-180302131348.pdfRijuDasgupta
 
L16_17_Shell structures.pdf
L16_17_Shell structures.pdfL16_17_Shell structures.pdf
L16_17_Shell structures.pdfRijuDasgupta
 
5-180501044424.pdf
5-180501044424.pdf5-180501044424.pdf
5-180501044424.pdfRijuDasgupta
 
6_2022_11_09!10_18_35_PM.ppt
6_2022_11_09!10_18_35_PM.ppt6_2022_11_09!10_18_35_PM.ppt
6_2022_11_09!10_18_35_PM.pptRijuDasgupta
 
rivetedjoints-130404054301-phpapp02 (1).pdf
rivetedjoints-130404054301-phpapp02 (1).pdfrivetedjoints-130404054301-phpapp02 (1).pdf
rivetedjoints-130404054301-phpapp02 (1).pdfRijuDasgupta
 
Compression_members1.ppt
Compression_members1.pptCompression_members1.ppt
Compression_members1.pptRijuDasgupta
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptRijuDasgupta
 
2415536_Unit-ISIGHTDISTNCE.pptx
2415536_Unit-ISIGHTDISTNCE.pptx2415536_Unit-ISIGHTDISTNCE.pptx
2415536_Unit-ISIGHTDISTNCE.pptxRijuDasgupta
 
presentation47-190318045824 (1).pdf
presentation47-190318045824 (1).pdfpresentation47-190318045824 (1).pdf
presentation47-190318045824 (1).pdfRijuDasgupta
 
presentation_propertiesofcement_1513407631_244125.pptx
presentation_propertiesofcement_1513407631_244125.pptxpresentation_propertiesofcement_1513407631_244125.pptx
presentation_propertiesofcement_1513407631_244125.pptxRijuDasgupta
 
populationforecasting-200810153117 (1).pdf
populationforecasting-200810153117 (1).pdfpopulationforecasting-200810153117 (1).pdf
populationforecasting-200810153117 (1).pdfRijuDasgupta
 
AGGREGATES_AND_OTHERS.pptx
AGGREGATES_AND_OTHERS.pptxAGGREGATES_AND_OTHERS.pptx
AGGREGATES_AND_OTHERS.pptxRijuDasgupta
 

More from RijuDasgupta (16)

26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf
26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf
26901321007_SAPTADEEP DASGUPTA_CIVIL ENGINEERING (2).pdf
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
 
swpiracyslideshare-180302131348.pdf
swpiracyslideshare-180302131348.pdfswpiracyslideshare-180302131348.pdf
swpiracyslideshare-180302131348.pdf
 
L16_17_Shell structures.pdf
L16_17_Shell structures.pdfL16_17_Shell structures.pdf
L16_17_Shell structures.pdf
 
5-180501044424.pdf
5-180501044424.pdf5-180501044424.pdf
5-180501044424.pdf
 
6_2022_11_09!10_18_35_PM.ppt
6_2022_11_09!10_18_35_PM.ppt6_2022_11_09!10_18_35_PM.ppt
6_2022_11_09!10_18_35_PM.ppt
 
rivetedjoints-130404054301-phpapp02 (1).pdf
rivetedjoints-130404054301-phpapp02 (1).pdfrivetedjoints-130404054301-phpapp02 (1).pdf
rivetedjoints-130404054301-phpapp02 (1).pdf
 
Compression_members1.ppt
Compression_members1.pptCompression_members1.ppt
Compression_members1.ppt
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.ppt
 
beamanalysis.ppt
beamanalysis.pptbeamanalysis.ppt
beamanalysis.ppt
 
2415536_Unit-ISIGHTDISTNCE.pptx
2415536_Unit-ISIGHTDISTNCE.pptx2415536_Unit-ISIGHTDISTNCE.pptx
2415536_Unit-ISIGHTDISTNCE.pptx
 
forecast.ppt
forecast.pptforecast.ppt
forecast.ppt
 
presentation47-190318045824 (1).pdf
presentation47-190318045824 (1).pdfpresentation47-190318045824 (1).pdf
presentation47-190318045824 (1).pdf
 
presentation_propertiesofcement_1513407631_244125.pptx
presentation_propertiesofcement_1513407631_244125.pptxpresentation_propertiesofcement_1513407631_244125.pptx
presentation_propertiesofcement_1513407631_244125.pptx
 
populationforecasting-200810153117 (1).pdf
populationforecasting-200810153117 (1).pdfpopulationforecasting-200810153117 (1).pdf
populationforecasting-200810153117 (1).pdf
 
AGGREGATES_AND_OTHERS.pptx
AGGREGATES_AND_OTHERS.pptxAGGREGATES_AND_OTHERS.pptx
AGGREGATES_AND_OTHERS.pptx
 

Recently uploaded

Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 

26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf

  • 1. NAME: SAPTADEEP DASGUPTA SUB:PRESTRESSED CONCRETE TOPIC:P LINE &C LINE METHOD SUBJECT CODE:CE(PE)702A DEPT.:CE YEAR: 4ND SEM: 7TH ROLL NO.: 26901321007 MODERN INSTITUTE OF ENGINEERING & TECHNOLOGY {DEDICATED TO EXCELLENCE}
  • 2. METHODS OF PRESTRESSING IN CONCRETE PRESTENSIONING & POST- TENSIONING
  • 3. INDEX 🞇 INTRODUCTION 🞇 PRESTRESSED CONCRETE 🞇 METHODS & BENIFIT 🞇 PROPERTIES 🞇 CONCLUSION 🞇 REFERENCE 🞇 ACKNOWLEDGEMENT
  • 4. PRESTRESSED CONCRETE ● ● PRINCIPLE – Using high tensile strength steel alloys producing permanent pre- compression in areas subjected to Tension. A portion of tensile stress is counteracted thereby reducing the cross-sectional area of the steel reinforcement . ● METHODS :- a) Pretensioning b)Post-tensioning ● ● PRETENSIONING :- Placing of concrete around reinforcing tendons that have been stressed to the desired degree. POST-TENSIONING :- Reinforcing tendons are stretched by jacks whilst keeping them in serted in voids left pre-hand during curing of ● concrete. These spaces are then pumped full of grout to bond steel tightly to the concrete. STEEL BARS BEING STRETCHED BY JACKS
  • 5. POST - TENSIONING ● WHAT IS POST-TENSIONING? ● Post-tensioning- is a method of reinforcing (strengthening) concrete or other materials with high- strength steel strands called tendons. ● Post-tensioning allows construction otherwise be impossible due to that would either site ● constraints or architectural requirements. Requires specialized knowledge and expertise to fabricate, assemble and install. ● After adequate curing of concrete, reinforcing tendons (placed in side the voids of the structure) are tensioned/stretched by jacks on the sides & grouts filled with appropriate mix. ● Applications – a) Structural members beams, bridge-deck panels, Roof –Slabs, Concrete Silos Etc.
  • 7. B E N E F I T S ● ● ● ● ● ● ● Concrete is very strong in compression but weak in tension, This deflection will cause the bottom of the beam to elongate slightly & cause cracking. Steel reinforcing bars (“rebar”) are typically embedded in the concrete as tensile reinforcement to limit the crack widths. Rebar is what is called “passive” reinforcement however; it does not carry any force until the concrete has already deflected enough to crack. Post-tensioning tendons, on the other hand, are considered “active” reinforcing. Because it is prestressed, the steel is effective as reinforcement even though the concrete may not be cracked . Post-tensioned structures can be designed to have minimal deflection and cracking, even under full load. Post –Tensioned Structure
  • 8. ADVANTAGES/APPLICATIONS ● ● ● ● ● Post-tensioning allows longer clear spans, thinner slabs, fewer beams and more slender, dramatic elements. Thinner slabs mean less concrete is required. It means a lower overall building height for the same floor-to-floor height. Post-tensioning can thus allow a significant reduction in building weight versus a conventional concrete building with the same number of floors reducing the foundation load and can be a major advantage in seismic areas. A lower building height can also translate to considerable savings in mechanical systems and façade costs. Another advantage of post-tensioning is that beams and slabs can be continuous, i.e. a single beam can building to run continuously from one end of the the other. Reduces occurrence of cracks . ● ● Freezing & thawing durability is higher than non prestressed concrete. This innovative form is result of post tensioning. Bridge decks
  • 9. ●Post-tensioning is the system of choice for parking structures since it allows a high degree of flexibility in the column layout, span lengths and ramp configurations. ● In areas where there are expansive clays or soils with low bearing capacity, post-tensioned slabs-on-ground and mat foundations reduce problems with cracking and differential ● settlement. Post-tensioning allows bridges to be built to very demanding geometry requirements, including complex curves, and significant grade changes. ● ● ● ● ● Post-tensioning also allows extremely long span bridges to be constructed without the use of temporary intermediate supports. This minimizes the impact on the environment and avoids disruption to water or road traffic below. In stadiums, post-tensioning allows long clear spans and very creative architecture. Post-tensioning can also be used to produce virtually crack-free concrete for water-tanks. The high tensile strength & precision of placement gives maximum efficiency in size & weight of structural members. Applications of various prestressed techniques enable quick assembly of standard units such as bridge members,building frames, bridge decks providing cost-time savings.
  • 10. CONSTRUCTION ● ● ● ● ● ● ● ● In slab-on-ground construction, unbonded tendons are typically prefabricated at a plant and delivered to the construction site, ready to install. The tendons are laid out in the forms in accordance with installation drawings that . After the concrete is placed and has reached its required strength, usually between 3000 and 3500 psi (“pounds per square inch”), the tendons are stressed and anchored. The tendons, like rubber bands, want to return to their original length but are prevented from doing so by the anchorages. The fact the tendons are kept in a permanently stressed (elongated) state causes a compressive force to act on the concrete. The compression that results from the post-tensioning counteracts the tensile forces created by subsequent applied loading (cars, people, the weight of the beam itself when the shoring is removed). This significantly increases the load-carrying capacity of the concrete. Since post-tensioned concrete is cast in place at the job site, there is almost no limit to the shapes that can be formed. Limitations of Prestressing The limitations of prestressed concrete are few and really depend only upon the imagination of the designer and the terms of his brief. The only real limitation where prestressing is a possible solution may be the cost of providing moulds for runs of limited quantity of small numbers of non-standard units.
  • 11. Method of post-tensioning TENDONS Wedges tensioned by jacks Tendons
  • 12. PRESTRESSED CONCRETE ● ● ● ● ● ● ● ● Prestressed concrete, invented by Eugene Frevssinet in 1928 is a method for overcoming concrete’’s natural weakness in tension . It can be used to produce beams , floors or bridges with a longer span than is practical with ordinary reinforced concrete. It can be accomplished in three ways: pre- tensioned concrete, and bonded or unbonded. Pre-tensioned concrete Pre-tensioned concrete is cast around already tensioned tendons. This method produces a good bond between the tendon and concrete, which both protects the tendon from corrosion and allows for direct transfer of tension. The cured concrete adheres and bonds to the bars and when the tension is released it is transferred to the concrete as compression by static friction. However, it requires stout anchoring points between which the tendon is to be stretched and the tendons are usually in a straight line. Thus, most pretensioned concrete elements are prefabricated in a factory and must be transported to the construction site, which limits their size. Pre-tensioned elements may be balcony elements, lintels , floor slabs, beams or foundation piles.
  • 13. Bonded post-tensioned concrete ● ● ● ● ● ● ● Bonded post-tensioned concrete is the descriptive term for a method of applying compression after pouring concrete and the curing process (in situ). The concrete is cast around a plastic, steel or aluminium curved duct, to follow the area where otherwise tension would occur in the concrete element. A set of tendons are fished through the duct and the concrete is poured. Once the concrete has hardened, the tendons are tensioned by hydraulic jacks. When the tendons have stretched sufficiently, according to the design specifications they are wedged in position and maintain tension after the jacks are removed, transferring pressure to the concrete. The duct is then grouted to protect the tendons from corrosion. This method is commonly used to create monolithic slabs for house construction in locations where expansive soils create problems for the typical perimeter foundation. All stresses from seasonal expansion and contraction of the underlying soil are taken into the entire tensioned slab, which supports the building without significant flexure. Post-stressing is also used in the construction of various bridges. The advantages of this system over unbonded post-tensioning are: DECKSTEELLA YING
  • 14. ● Large reduction in traditional reinforcement requirements as tendons cannot destress in accidents. ● Tendons can be easily 'weaved' allowing a more efficient design approach. ● Higher ultimate strength due to bond generated between the strand and concrete. ● No long term issues with maintaining the integrity of the anchor/dead end. Unbonded post-tensioned concrete ● Unbonded post-tensioned concrete differs from bonded post-tensioning by providing each individual cable permanent freedom of movement relative to the concrete. ● ● To achieve this, each individual tendon is coated with a grease (generally lithium based) and covered by a plastic sheathing formed in an extrusion process. The transfer of tension to the concrete is achieved by the steel cable acting against steel anchors in the perimeter of the slab. ● The main disadvantage over bonded post- tensioning is the fact that a cable can destress itself and burst out of the slab if damaged (such as during repair on the slab). The advantages of this system over bonded post-tensioning are:
  • 15. External Prestressing ● ● This refers to the case where prestressing tendons are placed outside the concrete section and the prestressing force is transferred to a structural member through end anchorages or deviators. Advantages of external prestressing include the possibility of monitoring and replacing tendons, ease in concreting and hence better concrete quality and the use of narrower webs. External prestressing is being increasingly used in the construction of new bridges and is a primary method for the strengthening and rehabilitation of existing structures. At NUS, a three-year project on the application of external prestressing in structural strengthening has been completed, and this has resulted in design charts being developed for such applications. Works were also carried out on the use of fibre-reinforced polymer (FRP) reinforcement as external tendons in both simply supported and continuous beams.
  • 16. •Fallingwater is comprised of a series of concrete cantilever “trays” 30-ft. above a waterfall. Previous efforts failed to permanently address excessive deflections of the cantilever and repair the cracks. After a thorough design review, the owner and engineer selected an external post-tensioning solution for its durability, aesthetics and structural unobtrusiveness. •Construction plans called for strengthening of three support girders spanning in the north-south direction with multistrand post-tensioning tendons consisting of multiple 0.5” diameter strands. •Thirteen strand tendons were placed on each side of two girders. One 10-strand tendon was placed on the western side of the third girder (access on the eastern side of this girder was not available). Eight monostrand tendons, 0.6” diameter, were slated for the east-west direction. •The monostrand tendons were stressed in the east-west direction and then the multistrand tendons were stressed in the north-south direction and grouted with a high quality, low- bleed cementitious grout mixture. •VSL’s scope of work also included welding steel cover plates, attaching structural steel channels, injecting epoxy grout, doweling reinforced cast in place concrete blocks and the installation of near surface mounted carbon fiber rods. Challenged with maintaining Fallingwater’s original setting, furnishings and artwork, the project was successfully completed in six months. The lower and upper terraces cantilever over the stream below. The temporary structural steel shoring was placed beneath the main level terrace. Frank Lloyd Wright's Fallingwater Mill Run, Pennsylvania APPLICATIONS
  • 17. ● ● ● ● ● ● Cline Avenue Bridge Gary, Indiana The Cline Avenue Bridge (SR 912) is a predominately cast-in-place post-tensioned structure located in Gary, Indiana. The bridge mainline is over 6,000 LF, has two adjacent segments nearly 35 feet wide each, and contains four connecting ramps. An inspection and analysis team was assembled to perform a thorough investigation of the bridge. The team concentrated on the existing post-tensioning system and interior and exterior concrete cracks. The engineer retained VSL to assist with the inspection of the tendons. VSL approached the Cline Avenue project with a guideline that outlines a statistically sound method of sampling the tendons. A statistical sample pool (which consisted of the mainline structure and the ramps) was defined by referencing the American National Standard Institute’s (ANSI) guideline “Sampling Procedures and Tables for Inspection by Attributes as published by the American Society for Quality Control (1993).” The probable void locations throughout the structure’s mainline segments and ramps were initially identified by VSL to appropriately distribute the sampling population. Such areas consisted of high points, areas approaching and leaving the high points, and couplers. Using non-destructive Ground Penetrating Radar (GPR) and field layout drawings, VSL located existing post-tensioning tendons. Once the layout was performed, specific tendons throughout the bridge and ramp structures were sampled by drilling into the duct and exposing the tendon for visual inspection. The use of a borescope allowed for detailed visual inspection of the tendon and also captured video footage to share with the owner and the engineer. After review of each inspection, VSL placed epoxy in the borescope hole to protect the tendons from air and moisture intrusion. When voids were encountered, the project team observed and documented the condition of the strand based on the PCI Journal guideline, “Evaluation of Degree of Rusting on Prestressed Concrete Strand.” VSL used vacuum grouting technology to fill the void, thereby protecting the previously exposed strand. The tendon inspection data was analyzed with other findings (such as crack survey findings) to determine what type of rehabilitation was required. VSL’s goal to establish a statistically sound sample of physically inspected tendons that proGvrio du etdi ngof void using VSL’s specialized vacuum grouting equipment valid data as to the current state of the existing PT system was accomplished
  • 18. ● ● ● ● 85th Street Bridge Valley Center, Kansas The 85th Street North Bridge is a seven span post-tensioned haunched slab bridge with a typical span of 26 meters for the middle five spans, and 20 meters at the ends. This 170 meter long bridge accommodates two lanes of traffic reaching over the Wichita Valley Center Floodway. VSL post-tensioning systems utilized for this project include 5-19 longitudinal tendons as well as 6-4 transverse tendons. Post-tensioned haunched slab bridges are noted for ease of construction. Once the geometry of the bridge falsework has been obtained, prefabricated spacer frames are set into place. The spacer frames serve as templates for profiling the longitudinal post-tensioning tendons and aid in the placement of the remaining conventional reinforcement. Transverse tendons maintain mid-depth placement along the geometry of the haunched slab and provide the minimum pre- compression over the length of the structure. The finished product has several advantages over conventionally reinforced concrete. Dead loads are balanced by the use of longitudinal post-tensioning reducing the sustained loading and associated creep. Corrosion resistance is increased due to the encapsulation of the post- tensioning reinforcement. Through the use of transverse post-tensioning, added compression improves the longevity of the structure by adding resistance to de-icing methods such as salt and magnesium chloride. Post-tensioned haunched slab bridges allow for a larger span to depth ratio than that of conventionally reinforced haunched slab bridges. The labor and material savings on mild reinforcement is another clear advantage to using post-tensioning for this application. Overlooking the 85th Street Bridge prior to concrete placement
  • 19. Colorado Convention Center Expansion Denver, Colorado ● ● ● ● The Colorado Convention Center Expansion project is a 1.4 million square foot expansion of the existing facility. This was a multi-level project, which included a 1,000-car attached parking garage. The garage above the street was constructed using precast tees and columns with a cast-in- place topping slab. In order to maintain regular spacing for the columns in the precast section of the garage and still maintain an unobstructed path for the road and light rail, large post-tensioned transfer girders were required to support several of the columns above. The transfer girders allowed for the placement of columns required for the precast design despite the restricted column locations at the street level. Post-tensioning the transfer girders resulted in smaller dimensions than a conventional reinforced concrete design, an important factor given the girders are over 7 feet high and up to 7 feet wide and a larger section would not fit within the space constraints of the building. The girders could not be stressed until after the precast garage was fully erected and the topping slab poured on the truck dock. Temporary columns were placed under the girders to support the load until stressing. The effective post-tensioning force required for the beams ranged from 2176 to 5457 kips. A multistrand bonded system was installed
  • 20. ● ● ● ● The Seward Silo project involved the post-tensioning of three interconnected ash silos that are part of the Seward Re-Powering Project in Seward, Pennsylvania. The overall project involved the construction of a new, state-of-the-art 208 MW power plant designed to burn low-grade coal that can not be burned in ordinary coal plants. This is a design-build project with Drake-Fluor Daniel as the owner/construction manager until the completed plant is turned over to Reliant Energy, the ultimate owner. T.E. Ibberson Company was contracted to build three 187’-6” tall, interconnected, in-line silos; two 82’-4” diameter fly ash silos and one 64’-8” diameter bed ash silo. The silos were built using the slip-form method of construction and are believed to be the first interconnected silos in the world built using post-tensioning as the primary circumferential reinforcement. VSL’s work was performed from November 2003 through February 2004, during the second coldest winter on record locally. Significant snowfall and subzero temperatures made progress challenging, yet with a strong focus on safety, both cold-related and otherwise, the job was completed with no incidents. The job required close coordination between the various trades working in close proximity and constant communication between parties working above and below VSL’s work locations to phase the work to avoid having personnel under an active work zone. The strand installation, stressing and grouting operations were completed successfully, with cold-weather grouting made possible through a variety of heating methods. Seward Silo
  • 21. THE BICYCLE WHEEL ● ● ● ● Bicycle wheel as we know it today - each is associated with an application of prestressing to a structural system. The first and most obvious is the tensioned spokes - the rider's weight is carried from the forks to the ground not by hanging off the top spokes, but by reducing the pretension in the lower spokes - only a couple of spokes are carrying the load at any one time. The second is the pneumatic tyre, where the compressive load is carried to the ground by reducing the tension in the sidewall. The air pressure in the tyre does not change when the load is applied. The final prestressing system is the tyre cord, which is shorter than the perimeter of the rim. The cord is thus in tension, holding the tyre on the rim, which enables the pretension in the sidewalls to be reacted
  • 22. EQUIPMENTS :- ● ● T6Z-08 Air Powered Grout Pump Pumps cement grout only, no sand. 32 Gallon Mixing Tank. Mixes up to 2 sacks of material at once and allows for grout to be pumped during mixing or mixed without pumping. Approxim atesize 50 " long 30 .5" high 52" wide Weight 560 lbs. ProductionRate 8 gallonsper minute at 150 psi
  • 23. ● ● Colloidal Grout Plant The heavy duty, high volume Colloidal Grout Plant is favored for precision post-tension grouting. The unit features a high speed shear mixer that thoroughly wets each particle and discharges the mixed material into a 13 cubic foot capacity agitating holding tank. A direct coupled progressing cavity pump delivers slurries at a rate of up to 20 gpm and pressures of up to 261 psi. The unit easily mixes and pumps slurries of Portland cement, fly ash, bentonite, and lime flour. All controls are conveniently located on the operator platform for easy one-man control. Pump Pump Type 31.6 progressing cavity Output/Pressure variable up to 20 gpm, 261 psi Colloidal Mixer Mix Tank 13.0 CF with bottom clean out Mixing Pump 2 x 3 x 6 diffuser- type centrifugal Holding Tank 13.0 paddle agitating Drive Power Air 300 CFM, 100 psi Physical Specifications Dimensions 96" L x 60" W x 63" H Weight 1800-2800 lbs.
  • 24. ● ● ● T7Z Hydraulic Jacks Used for testing and pre-stressing anchor bolts. Available with up to 5-1/8" center hole. Unit comes with ram, pump, gauge, hoses, jack stand, high strength coupling, high strength test rod, plate, hex nut and knocker wrench. Calibrations are available upon request. Note: Jack pull rods should have a higher capacity than the anchor rod.
  • 25. ● ● T80 Post-Tensioning Jacks With the T80 series the enclosed bearing housing contains a geared socket drive to tighten the bolt hex nut during tensioning. Test jack housing will accommodate up to a 9” deep pocket. T8 0Post-Tensioning Jacks
  • 26. ● T8Z-18 Hydraulic Torque Wrench ● The hydraulic torque wrench is used for tensioning anchors in tight fitting locations where it would be difficult to use an hydraulic jack. The wrench is also recommended for use when setting the large diameter Spin-Lock anchors. The torque wrenches are light weight and can achieve a maximum of 8,000 ft-lbs. Torque Tensioning charts Williams products can be found here. Maximum Torque 5,590 ft./lbs. (773 kg/M) 8,000 ft.lbs. (1,006 kg/M) Length Height Weight 11.11" 4.49" 16.75 lbs. (279 mm) (114 kg) (7.6 kg) 12.57" 5.09" 24.95 lbs. (319 kg) (129 kg) (11.3 kg)
  • 27. ● ● T8Z Torque Wrench For applying torque to the anchor bolt when setting the anchor. Torque Tensioning charts Williams products can be found here. Bolt Diameter *1/2"-1" 1/2"-1" *1-1/8"-2" Square Drive Size 3/4" 3/4" 1" Capacity (ft. lbs.) 0-500 0-600 0-1,000 T8Z-04 Torque Multiplier (4:1) For use with T8Z Torque Wrench. Other sizes available Size Drive Input Square Square Drive Output Maxim um Torque GA 186 1" 1-1/2" 4,000 (ft. lbs.)
  • 28. ● ● T1Z & T2Z Long Fitting Tool Adapters For driving hex nuts and setting tools, typically with our Spin-Lock anchor systems. Works with torque wrench or impact gun. Available with 1" or 1-1/2" square drive. Please specify square drive for compatability with your equipment. 2Z RegularSocket T1ZDeepSocket K3F-26 Long Fitting Wrench Adapter For applying torque to recessed anchor nuts that are under tension when using hydraulic jacks. Available in all anchor sizes.
  • 29. Corrosion Protection Corrosion Protection Type Abrasion Resistance (4=best) Typical Thickness Relative Cost (4=highest) Lead Time Can be applied to accessories ? Hot Dip Galvanizing 4 3-4 mils 2 2-4 weeks yes Epoxy Coating 1 7-12 mils 1 2-3 weeks yes Pre-Grouted Bars 3 2", 3" or 4" tubing 3 2 weeks no Extruded Polyethylene 2 23-25 mils 1 2-4 weeks no Coating Corrosion Inhibiting 2 N.A. 2 2-4 weeks yes Compound Methodsof CorrosionProtection
  • 30. Methods of Corrosion Protection ● Epoxy Coating Fusion bonded epoxy coating of steel bars to help prevent corrosion has been successfully employed in many applications because of the chemical stability of epoxy resins. Epoxy coated bars and fasteners should be done in accordance with ASTM A- 775 or ASTM 934. Coating thickness is generally specified between 7 to 12 mils. Epoxy coated bars and components are subject to damage if dragged on the ground or mishandled. Heavy plates and nuts are often galvanized even though the bar may be epoxy coated since they are difficult to protect against abrasion in the field. Epoxy coating patch kits are often used in the field for repairing nicked or scratched epoxy surfaces. Cement Grout filled corrugated polyethylene tubing is often used to provide an additional barrier against corrosion attack in highly aggressive soils. These anchors are often referred to as MCP or Multiple Corrosion Protection anchors. The steel bars are wrapped with an internal centralizer then placed inside of the polyethylene tube where they are then factory pre-grouted. When specifying couplings with MCP ground anchors, verify coupling locations with a Williams representative. Pre-GroutedBars
  • 31. ● ● Williams strand tendons contain an extruded high density polyethylene sheathing around each individual strand in the free-stressing portion of the anchorage. The sheathing is minimum 60 mils thick and applied once the 7-wire strand has been coated with a corrosion inhibiting compound. Extruded polyethylene sheathing provides a moisture tight barrier for corrosion protection and allows the strand to elongate freely throughout the free-stressing length during the prestressing operation Hot Dip Galvanizing Zinc serves as a sacrificial metal corroding preferentially to the steel. Galvanized bars have excellent bond characteristics to grout or concrete and do not require as much care in handling as epoxy coated bars. However, galvanization of anchor rods is more expensive than epoxy coating and often has greater lead time. Hot dip galvanizing bars and fasteners should be done in accordance with ASTM A-153. Typical galvanized coating thickness for steel bars and components is between 3 and 4 mils. 150 KSI high strength steel bars should always be mechanically cleaned (never acid washed) to avoid problems associated with hydrogen embrittlement. Extruded Polyethylene
  • 32. CorrosionInhibitingWaxorGreasewithSheath Williams corrosion inhibiting compounds can be placed in the free stressing sleeves, in the end caps, or in the trumpet areas. Often bars are greased/waxed and PVC is slipped over the greased/waxed bar prior to shipping. Each are of an organic compound with either a grease or wax base. They provide the appropriate polar moisture displacement and have corrosion inhibiting additives with self-healing properties. They can be pumped or applied manually. Corrosion inhibiting compounds stay permanently viscous, chemically stable and non-reactive with the prestressing steel, duct materials or grout. Both compounds meet PTI standards for Corrosion Inhibiting Coating. Coal Tar Epoxy Coal tar epoxy has shown to be abrasion resistant, economical and durable. This product when specified should meet or exceed the requirements of (a) Corp of Engineers C-200, C200a and (b) AWWA C-210-92 for exterior. Typically the thickness is between 8 and 24 mils. Make sure that the surfaces of the bar are clean and dry before coating.
  • 33. ● ● Heat Shrink Tubing Heat Shrink Tubing provides a corrosion protected seal when connecting smooth or corrugated segments. E poxy CoatingPatchKits Epoxy Coating Patch Kits are available uponrequest. Anchor Head Protection The most important section of a ground anchor that needs adequate corrosion protection is the portion of the anchor exposed to air/oxygen. This is typically defined as the "anchor head", which generally consists of a steel bearing plate, a hex nut and washer for a bar system, or a wedge plate and wedges for a strand system. For permanent ground anchors it is best to galvanize the hex nut and plates even if the bar is epoxy coated. Galvanized components, if scratched during shipping, are less likely to provide corrosion protection at otherwise exposed anchor ends. FiberReinforced cause corrosion concerns than scratched epoxy coated components. TheNylonCap end of the steel bar protruding out from the hex nut is often protected by the use of a plastic or steel end cap packed with grease or cement grout. Williams offers several different types of PVC and metal end caps to Strand E ndCap Screw-On PVCCap SteelTubeW eldedonFlangewith ThreadedScrewConnections
  • 34. ● ● Field Splice for Bars Continuous corrosion protection can even be accomplished for the MCP Pregrouted anchors manufactured from Williams Form Engineering. To achieve the equivalent levels of corrosion protection the coupled sections of bar anchors can be wrapped in a grease impregnated tape that is further protected with heat shrink sleeving. This scheme is acceptable by most governing agencies and is specified in the PTI Recommendations for Prestresed Rock and Soil Anchors.
  • 35. PRESTRESSED CONCRETE ● ● PRINCIPLE – Using high tensile strength steel alloys producing permanent pre- compression in areas subjected to Tension. A portion of tensile stress is counteracted thereby reducing the cross-sectional area of the steel reinforcement . ● METHODS :- a) Pretensioning b)Post-tensioning ● ● PRETENSIONING :- Placing of concrete around reinforcing tendons that have been stressed to the desired degree. POST-TENSIONING :- Reinforcing tendons are stretched by jacks whilst keeping them in serted in voids left pre-hand during curing of ● concrete. These spaces are then pumped full of grout to bond steel tightly to the concrete. STEEL BARS BEING STRETCHED BY JACKS
  • 36. POST - TENSIONING ● WHAT IS POST-TENSIONING? ● Post-tensioning- is a method of reinforcing (strengthening) concrete or other materials with high- strength steel strands called tendons. ● Post-tensioning allows construction otherwise be impossible due to that would either site ● constraints or architectural requirements. Requires specialized knowledge and expertise to fabricate, assemble and install. ● After adequate curing of concrete, reinforcing tendons (placed in side the voids of the structure) are tensioned/stretched by jacks on the sides & grouts filled with appropriate mix. ● Applications – a) Structural members beams, bridge-deck panels, Roof –Slabs, Concrete Silos Etc.
  • 38. B E N E F I T S ● ● ● ● ● ● ● Concrete is very strong in compression but weak in tension, This deflection will cause the bottom of the beam to elongate slightly & cause cracking. Steel reinforcing bars (“rebar”) are typically embedded in the concrete as tensile reinforcement to limit the crack widths. Rebar is what is called “passive” reinforcement however; it does not carry any force until the concrete has already deflected enough to crack. Post-tensioning tendons, on the other hand, are considered “active” reinforcing. Because it is prestressed, the steel is effective as reinforcement even though the concrete may not be cracked . Post-tensioned structures can be designed to have minimal deflection and cracking, even under full load. Post –Tensioned Structure
  • 39. ADVANTAGES/APPLICATIONS ● ● ● ● ● Post-tensioning allows longer clear spans, thinner slabs, fewer beams and more slender, dramatic elements. Thinner slabs mean less concrete is required. It means a lower overall building height for the same floor-to-floor height. Post-tensioning can thus allow a significant reduction in building weight versus a conventional concrete building with the same number of floors reducing the foundation load and can be a major advantage in seismic areas. A lower building height can also translate to considerable savings in mechanical systems and façade costs. Another advantage of post-tensioning is that beams and slabs can be continuous, i.e. a single beam can building to run continuously from one end of the the other. Reduces occurrence of cracks . ● ● Freezing & thawing durability is higher than non prestressed concrete. This innovative form is result of post tensioning. Bridge decks
  • 40. ●Post-tensioning is the system of choice for parking structures since it allows a high degree of flexibility in the column layout, span lengths and ramp configurations. ● In areas where there are expansive clays or soils with low bearing capacity, post-tensioned slabs-on-ground and mat foundations reduce problems with cracking and differential ● settlement. Post-tensioning allows bridges to be built to very demanding geometry requirements, including complex curves, and significant grade changes. ● ● ● ● ● Post-tensioning also allows extremely long span bridges to be constructed without the use of temporary intermediate supports. This minimizes the impact on the environment and avoids disruption to water or road traffic below. In stadiums, post-tensioning allows long clear spans and very creative architecture. Post-tensioning can also be used to produce virtually crack-free concrete for water-tanks. The high tensile strength & precision of placement gives maximum efficiency in size & weight of structural members. Applications of various prestressed techniques enable quick assembly of standard units such as bridge members,building frames, bridge decks providing cost-time savings.
  • 41. CONSTRUCTION ● ● ● ● ● ● ● ● In slab-on-ground construction, unbonded tendons are typically prefabricated at a plant and delivered to the construction site, ready to install. The tendons are laid out in the forms in accordance with installation drawings that . After the concrete is placed and has reached its required strength, usually between 3000 and 3500 psi (“pounds per square inch”), the tendons are stressed and anchored. The tendons, like rubber bands, want to return to their original length but are prevented from doing so by the anchorages. The fact the tendons are kept in a permanently stressed (elongated) state causes a compressive force to act on the concrete. The compression that results from the post-tensioning counteracts the tensile forces created by subsequent applied loading (cars, people, the weight of the beam itself when the shoring is removed). This significantly increases the load-carrying capacity of the concrete. Since post-tensioned concrete is cast in place at the job site, there is almost no limit to the shapes that can be formed. Limitations of Prestressing The limitations of prestressed concrete are few and really depend only upon the imagination of the designer and the terms of his brief. The only real limitation where prestressing is a possible solution may be the cost of providing moulds for runs of limited quantity of small numbers of non-standard units.
  • 42. Method of post-tensioning TENDONS Wedges tensioned by jacks Tendons
  • 43. PRESTRESSED CONCRETE ● ● ● ● ● ● ● ● Prestressed concrete, invented by Eugene Frevssinet in 1928 is a method for overcoming concrete’’s natural weakness in tension . It can be used to produce beams , floors or bridges with a longer span than is practical with ordinary reinforced concrete. It can be accomplished in three ways: pre- tensioned concrete, and bonded or unbonded. Pre-tensioned concrete Pre-tensioned concrete is cast around already tensioned tendons. This method produces a good bond between the tendon and concrete, which both protects the tendon from corrosion and allows for direct transfer of tension. The cured concrete adheres and bonds to the bars and when the tension is released it is transferred to the concrete as compression by static friction. However, it requires stout anchoring points between which the tendon is to be stretched and the tendons are usually in a straight line. Thus, most pretensioned concrete elements are prefabricated in a factory and must be transported to the construction site, which limits their size. Pre-tensioned elements may be balcony elements, lintels , floor slabs, beams or foundation piles.
  • 44. Bonded post-tensioned concrete ● ● ● ● ● ● ● Bonded post-tensioned concrete is the descriptive term for a method of applying compression after pouring concrete and the curing process (in situ). The concrete is cast around a plastic, steel or aluminium curved duct, to follow the area where otherwise tension would occur in the concrete element. A set of tendons are fished through the duct and the concrete is poured. Once the concrete has hardened, the tendons are tensioned by hydraulic jacks. When the tendons have stretched sufficiently, according to the design specifications they are wedged in position and maintain tension after the jacks are removed, transferring pressure to the concrete. The duct is then grouted to protect the tendons from corrosion. This method is commonly used to create monolithic slabs for house construction in locations where expansive soils create problems for the typical perimeter foundation. All stresses from seasonal expansion and contraction of the underlying soil are taken into the entire tensioned slab, which supports the building without significant flexure. Post-stressing is also used in the construction of various bridges. The advantages of this system over unbonded post-tensioning are: DECKSTEELLA YING
  • 45. ● Large reduction in traditional reinforcement requirements as tendons cannot destress in accidents. ● Tendons can be easily 'weaved' allowing a more efficient design approach. ● Higher ultimate strength due to bond generated between the strand and concrete. ● No long term issues with maintaining the integrity of the anchor/dead end. Unbonded post-tensioned concrete ● Unbonded post-tensioned concrete differs from bonded post-tensioning by providing each individual cable permanent freedom of movement relative to the concrete. ● ● To achieve this, each individual tendon is coated with a grease (generally lithium based) and covered by a plastic sheathing formed in an extrusion process. The transfer of tension to the concrete is achieved by the steel cable acting against steel anchors in the perimeter of the slab. ● The main disadvantage over bonded post- tensioning is the fact that a cable can destress itself and burst out of the slab if damaged (such as during repair on the slab). The advantages of this system over bonded post-tensioning are:
  • 46. External Prestressing ● ● This refers to the case where prestressing tendons are placed outside the concrete section and the prestressing force is transferred to a structural member through end anchorages or deviators. Advantages of external prestressing include the possibility of monitoring and replacing tendons, ease in concreting and hence better concrete quality and the use of narrower webs. External prestressing is being increasingly used in the construction of new bridges and is a primary method for the strengthening and rehabilitation of existing structures. At NUS, a three-year project on the application of external prestressing in structural strengthening has been completed, and this has resulted in design charts being developed for such applications. Works were also carried out on the use of fibre-reinforced polymer (FRP) reinforcement as external tendons in both simply supported and continuous beams.
  • 47. •Fallingwater is comprised of a series of concrete cantilever “trays” 30-ft. above a waterfall. Previous efforts failed to permanently address excessive deflections of the cantilever and repair the cracks. After a thorough design review, the owner and engineer selected an external post-tensioning solution for its durability, aesthetics and structural unobtrusiveness. •Construction plans called for strengthening of three support girders spanning in the north-south direction with multistrand post-tensioning tendons consisting of multiple 0.5” diameter strands. •Thirteen strand tendons were placed on each side of two girders. One 10-strand tendon was placed on the western side of the third girder (access on the eastern side of this girder was not available). Eight monostrand tendons, 0.6” diameter, were slated for the east-west direction. •The monostrand tendons were stressed in the east-west direction and then the multistrand tendons were stressed in the north-south direction and grouted with a high quality, low- bleed cementitious grout mixture. •VSL’s scope of work also included welding steel cover plates, attaching structural steel channels, injecting epoxy grout, doweling reinforced cast in place concrete blocks and the installation of near surface mounted carbon fiber rods. Challenged with maintaining Fallingwater’s original setting, furnishings and artwork, the project was successfully completed in six months. The lower and upper terraces cantilever over the stream below. The temporary structural steel shoring was placed beneath the main level terrace. Frank Lloyd Wright's Fallingwater Mill Run, Pennsylvania APPLICATIONS
  • 48. ● ● ● ● ● ● Cline Avenue Bridge Gary, Indiana The Cline Avenue Bridge (SR 912) is a predominately cast-in-place post-tensioned structure located in Gary, Indiana. The bridge mainline is over 6,000 LF, has two adjacent segments nearly 35 feet wide each, and contains four connecting ramps. An inspection and analysis team was assembled to perform a thorough investigation of the bridge. The team concentrated on the existing post-tensioning system and interior and exterior concrete cracks. The engineer retained VSL to assist with the inspection of the tendons. VSL approached the Cline Avenue project with a guideline that outlines a statistically sound method of sampling the tendons. A statistical sample pool (which consisted of the mainline structure and the ramps) was defined by referencing the American National Standard Institute’s (ANSI) guideline “Sampling Procedures and Tables for Inspection by Attributes as published by the American Society for Quality Control (1993).” The probable void locations throughout the structure’s mainline segments and ramps were initially identified by VSL to appropriately distribute the sampling population. Such areas consisted of high points, areas approaching and leaving the high points, and couplers. Using non-destructive Ground Penetrating Radar (GPR) and field layout drawings, VSL located existing post-tensioning tendons. Once the layout was performed, specific tendons throughout the bridge and ramp structures were sampled by drilling into the duct and exposing the tendon for visual inspection. The use of a borescope allowed for detailed visual inspection of the tendon and also captured video footage to share with the owner and the engineer. After review of each inspection, VSL placed epoxy in the borescope hole to protect the tendons from air and moisture intrusion. When voids were encountered, the project team observed and documented the condition of the strand based on the PCI Journal guideline, “Evaluation of Degree of Rusting on Prestressed Concrete Strand.” VSL used vacuum grouting technology to fill the void, thereby protecting the previously exposed strand. The tendon inspection data was analyzed with other findings (such as crack survey findings) to determine what type of rehabilitation was required. VSL’s goal to establish a statistically sound sample of physically inspected tendons that proGvrio du etdi ngof void using VSL’s specialized vacuum grouting equipment valid data as to the current state of the existing PT system was accomplished
  • 49. ● ● ● ● 85th Street Bridge Valley Center, Kansas The 85th Street North Bridge is a seven span post-tensioned haunched slab bridge with a typical span of 26 meters for the middle five spans, and 20 meters at the ends. This 170 meter long bridge accommodates two lanes of traffic reaching over the Wichita Valley Center Floodway. VSL post-tensioning systems utilized for this project include 5-19 longitudinal tendons as well as 6-4 transverse tendons. Post-tensioned haunched slab bridges are noted for ease of construction. Once the geometry of the bridge falsework has been obtained, prefabricated spacer frames are set into place. The spacer frames serve as templates for profiling the longitudinal post-tensioning tendons and aid in the placement of the remaining conventional reinforcement. Transverse tendons maintain mid-depth placement along the geometry of the haunched slab and provide the minimum pre- compression over the length of the structure. The finished product has several advantages over conventionally reinforced concrete. Dead loads are balanced by the use of longitudinal post-tensioning reducing the sustained loading and associated creep. Corrosion resistance is increased due to the encapsulation of the post- tensioning reinforcement. Through the use of transverse post-tensioning, added compression improves the longevity of the structure by adding resistance to de-icing methods such as salt and magnesium chloride. Post-tensioned haunched slab bridges allow for a larger span to depth ratio than that of conventionally reinforced haunched slab bridges. The labor and material savings on mild reinforcement is another clear advantage to using post-tensioning for this application. Overlooking the 85th Street Bridge prior to concrete placement
  • 50. Colorado Convention Center Expansion Denver, Colorado ● ● ● ● The Colorado Convention Center Expansion project is a 1.4 million square foot expansion of the existing facility. This was a multi-level project, which included a 1,000-car attached parking garage. The garage above the street was constructed using precast tees and columns with a cast-in- place topping slab. In order to maintain regular spacing for the columns in the precast section of the garage and still maintain an unobstructed path for the road and light rail, large post-tensioned transfer girders were required to support several of the columns above. The transfer girders allowed for the placement of columns required for the precast design despite the restricted column locations at the street level. Post-tensioning the transfer girders resulted in smaller dimensions than a conventional reinforced concrete design, an important factor given the girders are over 7 feet high and up to 7 feet wide and a larger section would not fit within the space constraints of the building. The girders could not be stressed until after the precast garage was fully erected and the topping slab poured on the truck dock. Temporary columns were placed under the girders to support the load until stressing. The effective post-tensioning force required for the beams ranged from 2176 to 5457 kips. A multistrand bonded system was installed
  • 51. ● ● ● ● The Seward Silo project involved the post-tensioning of three interconnected ash silos that are part of the Seward Re-Powering Project in Seward, Pennsylvania. The overall project involved the construction of a new, state-of-the-art 208 MW power plant designed to burn low-grade coal that can not be burned in ordinary coal plants. This is a design-build project with Drake-Fluor Daniel as the owner/construction manager until the completed plant is turned over to Reliant Energy, the ultimate owner. T.E. Ibberson Company was contracted to build three 187’-6” tall, interconnected, in-line silos; two 82’-4” diameter fly ash silos and one 64’-8” diameter bed ash silo. The silos were built using the slip-form method of construction and are believed to be the first interconnected silos in the world built using post-tensioning as the primary circumferential reinforcement. VSL’s work was performed from November 2003 through February 2004, during the second coldest winter on record locally. Significant snowfall and subzero temperatures made progress challenging, yet with a strong focus on safety, both cold-related and otherwise, the job was completed with no incidents. The job required close coordination between the various trades working in close proximity and constant communication between parties working above and below VSL’s work locations to phase the work to avoid having personnel under an active work zone. The strand installation, stressing and grouting operations were completed successfully, with cold-weather grouting made possible through a variety of heating methods. Seward Silo
  • 52. THE BICYCLE WHEEL ● ● ● ● Bicycle wheel as we know it today - each is associated with an application of prestressing to a structural system. The first and most obvious is the tensioned spokes - the rider's weight is carried from the forks to the ground not by hanging off the top spokes, but by reducing the pretension in the lower spokes - only a couple of spokes are carrying the load at any one time. The second is the pneumatic tyre, where the compressive load is carried to the ground by reducing the tension in the sidewall. The air pressure in the tyre does not change when the load is applied. The final prestressing system is the tyre cord, which is shorter than the perimeter of the rim. The cord is thus in tension, holding the tyre on the rim, which enables the pretension in the sidewalls to be reacted
  • 53. EQUIPMENTS :- ● ● T6Z-08 Air Powered Grout Pump Pumps cement grout only, no sand. 32 Gallon Mixing Tank. Mixes up to 2 sacks of material at once and allows for grout to be pumped during mixing or mixed without pumping. Approxim atesize 50 " long 30 .5" high 52" wide Weight 560 lbs. ProductionRate 8 gallonsper minute at 150 psi
  • 54. ● ● Colloidal Grout Plant The heavy duty, high volume Colloidal Grout Plant is favored for precision post-tension grouting. The unit features a high speed shear mixer that thoroughly wets each particle and discharges the mixed material into a 13 cubic foot capacity agitating holding tank. A direct coupled progressing cavity pump delivers slurries at a rate of up to 20 gpm and pressures of up to 261 psi. The unit easily mixes and pumps slurries of Portland cement, fly ash, bentonite, and lime flour. All controls are conveniently located on the operator platform for easy one-man control. Pump Pump Type 31.6 progressing cavity Output/Pressure variable up to 20 gpm, 261 psi Colloidal Mixer Mix Tank 13.0 CF with bottom clean out Mixing Pump 2 x 3 x 6 diffuser- type centrifugal Holding Tank 13.0 paddle agitating Drive Power Air 300 CFM, 100 psi Physical Specifications Dimensions 96" L x 60" W x 63" H Weight 1800-2800 lbs.
  • 55. ● ● ● T7Z Hydraulic Jacks Used for testing and pre-stressing anchor bolts. Available with up to 5-1/8" center hole. Unit comes with ram, pump, gauge, hoses, jack stand, high strength coupling, high strength test rod, plate, hex nut and knocker wrench. Calibrations are available upon request. Note: Jack pull rods should have a higher capacity than the anchor rod.
  • 56. ● ● T80 Post-Tensioning Jacks With the T80 series the enclosed bearing housing contains a geared socket drive to tighten the bolt hex nut during tensioning. Test jack housing will accommodate up to a 9” deep pocket. T8 0Post-Tensioning Jacks
  • 57. ● T8Z-18 Hydraulic Torque Wrench ● The hydraulic torque wrench is used for tensioning anchors in tight fitting locations where it would be difficult to use an hydraulic jack. The wrench is also recommended for use when setting the large diameter Spin-Lock anchors. The torque wrenches are light weight and can achieve a maximum of 8,000 ft-lbs. Torque Tensioning charts Williams products can be found here. Maximum Torque 5,590 ft./lbs. (773 kg/M) 8,000 ft.lbs. (1,006 kg/M) Length Height Weight 11.11" 4.49" 16.75 lbs. (279 mm) (114 kg) (7.6 kg) 12.57" 5.09" 24.95 lbs. (319 kg) (129 kg) (11.3 kg)
  • 58. ● ● T8Z Torque Wrench For applying torque to the anchor bolt when setting the anchor. Torque Tensioning charts Williams products can be found here. Bolt Diameter *1/2"-1" 1/2"-1" *1-1/8"-2" Square Drive Size 3/4" 3/4" 1" Capacity (ft. lbs.) 0-500 0-600 0-1,000 T8Z-04 Torque Multiplier (4:1) For use with T8Z Torque Wrench. Other sizes available Size Drive Input Square Square Drive Output Maxim um Torque GA 186 1" 1-1/2" 4,000 (ft. lbs.)
  • 59. ● ● T1Z & T2Z Long Fitting Tool Adapters For driving hex nuts and setting tools, typically with our Spin-Lock anchor systems. Works with torque wrench or impact gun. Available with 1" or 1-1/2" square drive. Please specify square drive for compatability with your equipment. 2Z RegularSocket T1ZDeepSocket K3F-26 Long Fitting Wrench Adapter For applying torque to recessed anchor nuts that are under tension when using hydraulic jacks. Available in all anchor sizes.
  • 60. Corrosion Protection Corrosion Protection Type Abrasion Resistance (4=best) Typical Thickness Relative Cost (4=highest) Lead Time Can be applied to accessories ? Hot Dip Galvanizing 4 3-4 mils 2 2-4 weeks yes Epoxy Coating 1 7-12 mils 1 2-3 weeks yes Pre-Grouted Bars 3 2", 3" or 4" tubing 3 2 weeks no Extruded Polyethylene 2 23-25 mils 1 2-4 weeks no Coating Corrosion Inhibiting 2 N.A. 2 2-4 weeks yes Compound Methodsof CorrosionProtection
  • 61. Methods of Corrosion Protection ● Epoxy Coating Fusion bonded epoxy coating of steel bars to help prevent corrosion has been successfully employed in many applications because of the chemical stability of epoxy resins. Epoxy coated bars and fasteners should be done in accordance with ASTM A- 775 or ASTM 934. Coating thickness is generally specified between 7 to 12 mils. Epoxy coated bars and components are subject to damage if dragged on the ground or mishandled. Heavy plates and nuts are often galvanized even though the bar may be epoxy coated since they are difficult to protect against abrasion in the field. Epoxy coating patch kits are often used in the field for repairing nicked or scratched epoxy surfaces. Cement Grout filled corrugated polyethylene tubing is often used to provide an additional barrier against corrosion attack in highly aggressive soils. These anchors are often referred to as MCP or Multiple Corrosion Protection anchors. The steel bars are wrapped with an internal centralizer then placed inside of the polyethylene tube where they are then factory pre-grouted. When specifying couplings with MCP ground anchors, verify coupling locations with a Williams representative. Pre-GroutedBars
  • 62. ● ● Williams strand tendons contain an extruded high density polyethylene sheathing around each individual strand in the free-stressing portion of the anchorage. The sheathing is minimum 60 mils thick and applied once the 7-wire strand has been coated with a corrosion inhibiting compound. Extruded polyethylene sheathing provides a moisture tight barrier for corrosion protection and allows the strand to elongate freely throughout the free-stressing length during the prestressing operation Hot Dip Galvanizing Zinc serves as a sacrificial metal corroding preferentially to the steel. Galvanized bars have excellent bond characteristics to grout or concrete and do not require as much care in handling as epoxy coated bars. However, galvanization of anchor rods is more expensive than epoxy coating and often has greater lead time. Hot dip galvanizing bars and fasteners should be done in accordance with ASTM A-153. Typical galvanized coating thickness for steel bars and components is between 3 and 4 mils. 150 KSI high strength steel bars should always be mechanically cleaned (never acid washed) to avoid problems associated with hydrogen embrittlement. Extruded Polyethylene
  • 63. CorrosionInhibitingWaxorGreasewithSheath Williams corrosion inhibiting compounds can be placed in the free stressing sleeves, in the end caps, or in the trumpet areas. Often bars are greased/waxed and PVC is slipped over the greased/waxed bar prior to shipping. Each are of an organic compound with either a grease or wax base. They provide the appropriate polar moisture displacement and have corrosion inhibiting additives with self-healing properties. They can be pumped or applied manually. Corrosion inhibiting compounds stay permanently viscous, chemically stable and non-reactive with the prestressing steel, duct materials or grout. Both compounds meet PTI standards for Corrosion Inhibiting Coating. Coal Tar Epoxy Coal tar epoxy has shown to be abrasion resistant, economical and durable. This product when specified should meet or exceed the requirements of (a) Corp of Engineers C-200, C200a and (b) AWWA C-210-92 for exterior. Typically the thickness is between 8 and 24 mils. Make sure that the surfaces of the bar are clean and dry before coating.
  • 64. ● ● Heat Shrink Tubing Heat Shrink Tubing provides a corrosion protected seal when connecting smooth or corrugated segments. E poxy CoatingPatchKits Epoxy Coating Patch Kits are available uponrequest. Anchor Head Protection The most important section of a ground anchor that needs adequate corrosion protection is the portion of the anchor exposed to air/oxygen. This is typically defined as the "anchor head", which generally consists of a steel bearing plate, a hex nut and washer for a bar system, or a wedge plate and wedges for a strand system. For permanent ground anchors it is best to galvanize the hex nut and plates even if the bar is epoxy coated. Galvanized components, if scratched during shipping, are less likely to provide corrosion protection at otherwise exposed anchor ends. FiberReinforced cause corrosion concerns than scratched epoxy coated components. TheNylonCap end of the steel bar protruding out from the hex nut is often protected by the use of a plastic or steel end cap packed with grease or cement grout. Williams offers several different types of PVC and metal end caps to Strand E ndCap Screw-On PVCCap SteelTubeW eldedonFlangewith ThreadedScrewConnections
  • 65. ● ● Field Splice for Bars Continuous corrosion protection can even be accomplished for the MCP Pregrouted anchors manufactured from Williams Form Engineering. To achieve the equivalent levels of corrosion protection the coupled sections of bar anchors can be wrapped in a grease impregnated tape that is further protected with heat shrink sleeving. This scheme is acceptable by most governing agencies and is specified in the PTI Recommendations for Prestresed Rock and Soil Anchors.
  • 66. CONCLUSION 🞇 FRO M THE WHO LE DISCUSSIO N WE CAN CONCLUDE P LINE & AND C LINE METHOD IS VERY ESSENTIAL FOR HIGHLY LOADED STRUCTURES
  • 67. ACKNOWLEDGEMENT 🞇 Iwould like to express my special thanks of gratitude to my teacher SAPTADEEP DASGUPTAwho gave a golden opportunity to do this wonder full PPT on the topic “ P LINE AND C LINE METHODS” which also helped me to gather more knowledge on it.