CONTENTS:-
*Introduction to NTPC
*Working process of NTPC
*Cooling Towers
*CW Pumps
*Compressors
*Boiler
*Turbine
*Generator
*Types of Fan used
*Coal Handling Plant(CHP)
*Fly Ash Brick
About NTPC Ltd.
 Vindhyachal Thermal Power Station is located in
Singrauli district of Indian state of Madhya Pradesh.
One of NTPC's coal-based power stations, it is India's
largest powerhouse with an installed capacity of
4760 MW. Coal is obtained from Nigahi mines for the
power plant, and the water source gets the discharge
canal of Singrauli Super Thermal Power Station.
Vindhyachal STPP was built as a pit head coal-based
super thermal power plant for capacity of 3260 MW
(6X210 MW + 2x500 MW + 2x500 MW) for which the
land was acquired during the stage-I of the project. .
The work of Phase I, II and III is going on in six units
of 210 MW (Stage-1), two units of 500 MW (stage2)
and two units of 500 MW (Stage 3).
Cooling tower:-
*The cooling tower is used to cool the steam and convert it to the
water for reuse because the steam which is released after the L.p.
turbine can not be used again before cooling it as the property of water
of steam changes due to extreme heating.
*Remove heat from the water discharged from the condenser so that the
water can be discharged to the river or re circulated and re used .
CW Pumps -
*CW pumps are used to circulate cooling water or circulating water
through the condenser tubes.
*Inside the condenser the phase conversion of saturated steam takes
place.
*During this phase conversion lot of latent heat is released which is
absorbed by the cooling water supplied by CW pumps.
* After absorbing the heat ,cooling water is passed through the natural
draft cooling tower. There it releases heat naturally.
* After that cooling water is again used in the cycle by CW pumps.
Compressors-
Screw type compressor-
It contains basically two rotating screws in opposite direction to each other.
And while Rotating, it sucks air into the chamber and due to rotation of both
screws in opposite direction , sucked air gets compressed and sends it to the
outlet for the further use.
Main parts used-
Rotors/Rollers
Compressor cylinder
Air filter
Oil filter
Bearings
Suction valve
Discharge valve
Motor
Storage tank
Separator
Boiler:-
It is a large tube like structure of different metal alloy.
A boiler is a closed vessel in which water is converted into steam by
utilizing the heat of coal combustion .
Steam boilers are broadly classified into two types:
a) water tube boilers b) fire tube boilers
NTPC mainly uses the water tube boilers .
In water tube boilers water flows through tubes and the hot gases for
the combustion flows over the tubes .
Turbine:-
* A turbine is rotary mechanical device that extarcts energy from fluid
flow and converts it into usefull work.
* It consists one moving part called a rotor assembly .
* Steam turbines are used for the generation of electricity in thermal
power plants.
* In thermal power plants turbine is sub devided into three parts:
High presuure turbine
Indicated pressure turbine
Low pressure turbine
Turbine:-
Generator:-
An electric generator is a device that converts mechanical energy
to electrical energy.
it is based upon the principle of electromagnetic induction
Generator provides nearly all of the power for electric power grids.
Types of fan used:-
There are mainly three types of fan used :-
Primary Fan:-
These types of fan are used to lift pulverised coal from mill to furnace of boiler.
Primary fans carries cold and hot air both for preventing formation of lumps so it
can not cause choke of pipes carrying pulverised coal.
Cold air insures that the coal is nt burnt in carrying process.
Forced draught fan (F.D. fan):-
It provides air to coal in the furnace for proper burning of under sufficient
quantity of air.
The air supplied is also called as secondary air.
The quantity of secondary air is decided by amount of co
and co2 In the flue gases.
The F.D. fan also carry both cold and hot air.
Induced draught fan (I.D. fan):-
I.d. fan is used to transport the flue gases to the chimney.
The aim of I.d. fan is to maintain the pressure inside the
furnace so that fuel burnt constantly and efficiently.
Coal handling plant:-
First of all the coal from coal mines is loaded in trains and transported to
the plant and dumped in an area from where it is it is used for various
operation.
Now the coal from stackyard area is transported to the crusher house with
the help of conveyer belt for crushing into smaller pieces for proper burning
and full utilization of energy which is obtained by burning of coal.
After crushing of coal, it is transported to the mill and crushed into powdered
form in it to feed the fuel to the furnace for continuous burning.
About 70 metric tons of coal comes per day from coal mines to NTPC plant.
Pulverizing plant
• In modern thermal power plant , coal is pulverised i.e.
ground to dust like size and carried to the furnace in a
stream of hot air.
• Pulverizing is done in pulverizing mill.
• Pulverizing mill is further classified in three types:
Contact mill
Ball mill
Impact mill
Ash Handling plant
• The percentage of ash in coal varies from 5% in good
quality coal to about 40% in poor quality coal.
• Power plants generally of coal, thus amount of ash
produced by it pretty large .
• A modern 2000MW plant produces about 5000 tons of
ash daily.
FLY ASH BRICK:-
Fly ash bricks are the building unit of construction work made from ash,
sand cement and water.
•These are light in weight .
•These are cheap and easy to construct.
•These have good strength than clay brick.
•Ash released due to burning of coal is utilised which is also helpful from
environment point of view.
Composition of fly ash brick:-
Ash – 57%
Sand – 34%
Ordinary portland Cement -9%
Conclusion:-
1)The training experience at n.t.p.c is good.
2)I have learned a lot of things of construction which help
me in future.
3) In this 30 days i came in contact with experienced
person who helps me lot to achieve my goals and provide
proper guidance to me.
4)The staff was very polite and helpful.
Vivek ntpc final report

More Related Content

What's hot

Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parul
Swapnil Sharma
 
Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikas
Vikas Gupta
 

What's hot (20)

Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
 
SUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPTSUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPT
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parul
 
Unit i ppe
Unit   i ppeUnit   i ppe
Unit i ppe
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
Power plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikasPower plant ppt on kalisindh by vikas
Power plant ppt on kalisindh by vikas
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
 
Seminar on Cyclone engine ppt
Seminar on Cyclone engine ppt Seminar on Cyclone engine ppt
Seminar on Cyclone engine ppt
 
Gas Turbine Power Plant
Gas Turbine Power PlantGas Turbine Power Plant
Gas Turbine Power Plant
 
Basics of Gas Turbine Power Plant
Basics of Gas Turbine Power PlantBasics of Gas Turbine Power Plant
Basics of Gas Turbine Power Plant
 
report on VTPS
report on VTPSreport on VTPS
report on VTPS
 
Gas turbine Power-plant, NTPC Anta, Rajasthan
Gas turbine Power-plant, NTPC Anta, RajasthanGas turbine Power-plant, NTPC Anta, Rajasthan
Gas turbine Power-plant, NTPC Anta, Rajasthan
 
Steam powerplant by polayya chintada
Steam powerplant by polayya chintadaSteam powerplant by polayya chintada
Steam powerplant by polayya chintada
 
Gas Turbine Theory - Principle of Operation and Construction
Gas Turbine Theory  - Principle of Operation and ConstructionGas Turbine Theory  - Principle of Operation and Construction
Gas Turbine Theory - Principle of Operation and Construction
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
 
. Gas turbine presentation
. Gas turbine presentation. Gas turbine presentation
. Gas turbine presentation
 
Gas ykj
Gas ykjGas ykj
Gas ykj
 
Ntpc ppt complete
Ntpc ppt completeNtpc ppt complete
Ntpc ppt complete
 
Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 

Similar to Vivek ntpc final report

thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPC
richa khatri
 

Similar to Vivek ntpc final report (20)

NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
vocational training at DVC andal
 vocational training at DVC andal vocational training at DVC andal
vocational training at DVC andal
 
Emam training
Emam training Emam training
Emam training
 
ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan  ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan
 
Industrial Traning at SSTPS ppt
Industrial Traning at SSTPS pptIndustrial Traning at SSTPS ppt
Industrial Traning at SSTPS ppt
 
Industrial Training at Suratgarh Super Thermal Power Plant ppt
Industrial Training at Suratgarh Super Thermal Power Plant pptIndustrial Training at Suratgarh Super Thermal Power Plant ppt
Industrial Training at Suratgarh Super Thermal Power Plant ppt
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
 
Ppt aman
Ppt amanPpt aman
Ppt aman
 
Thermal Power Plant.pptx
Thermal Power Plant.pptxThermal Power Plant.pptx
Thermal Power Plant.pptx
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
National thermal power corporation
National thermal power corporationNational thermal power corporation
National thermal power corporation
 
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPC
 
Richappt
RichapptRichappt
Richappt
 

Recently uploaded

Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
AbrahamGadissa
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 

Recently uploaded (20)

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 

Vivek ntpc final report

  • 1. VOCATIONAL TRAINING AT (NATIONAL THERMAL POWER CORPORATION) Prepared by- Vivek Singh 11702662 Programe-B.Tech.(Mech. Hons.)
  • 2. CONTENTS:- *Introduction to NTPC *Working process of NTPC *Cooling Towers *CW Pumps *Compressors *Boiler *Turbine *Generator *Types of Fan used *Coal Handling Plant(CHP) *Fly Ash Brick
  • 3. About NTPC Ltd.  Vindhyachal Thermal Power Station is located in Singrauli district of Indian state of Madhya Pradesh. One of NTPC's coal-based power stations, it is India's largest powerhouse with an installed capacity of 4760 MW. Coal is obtained from Nigahi mines for the power plant, and the water source gets the discharge canal of Singrauli Super Thermal Power Station. Vindhyachal STPP was built as a pit head coal-based super thermal power plant for capacity of 3260 MW (6X210 MW + 2x500 MW + 2x500 MW) for which the land was acquired during the stage-I of the project. . The work of Phase I, II and III is going on in six units of 210 MW (Stage-1), two units of 500 MW (stage2) and two units of 500 MW (Stage 3).
  • 4.
  • 5.
  • 6. Cooling tower:- *The cooling tower is used to cool the steam and convert it to the water for reuse because the steam which is released after the L.p. turbine can not be used again before cooling it as the property of water of steam changes due to extreme heating. *Remove heat from the water discharged from the condenser so that the water can be discharged to the river or re circulated and re used .
  • 7. CW Pumps - *CW pumps are used to circulate cooling water or circulating water through the condenser tubes. *Inside the condenser the phase conversion of saturated steam takes place. *During this phase conversion lot of latent heat is released which is absorbed by the cooling water supplied by CW pumps. * After absorbing the heat ,cooling water is passed through the natural draft cooling tower. There it releases heat naturally. * After that cooling water is again used in the cycle by CW pumps.
  • 8. Compressors- Screw type compressor- It contains basically two rotating screws in opposite direction to each other. And while Rotating, it sucks air into the chamber and due to rotation of both screws in opposite direction , sucked air gets compressed and sends it to the outlet for the further use. Main parts used- Rotors/Rollers Compressor cylinder Air filter Oil filter Bearings Suction valve Discharge valve Motor Storage tank Separator
  • 9. Boiler:- It is a large tube like structure of different metal alloy. A boiler is a closed vessel in which water is converted into steam by utilizing the heat of coal combustion . Steam boilers are broadly classified into two types: a) water tube boilers b) fire tube boilers NTPC mainly uses the water tube boilers . In water tube boilers water flows through tubes and the hot gases for the combustion flows over the tubes .
  • 10. Turbine:- * A turbine is rotary mechanical device that extarcts energy from fluid flow and converts it into usefull work. * It consists one moving part called a rotor assembly . * Steam turbines are used for the generation of electricity in thermal power plants. * In thermal power plants turbine is sub devided into three parts: High presuure turbine Indicated pressure turbine Low pressure turbine
  • 12. Generator:- An electric generator is a device that converts mechanical energy to electrical energy. it is based upon the principle of electromagnetic induction Generator provides nearly all of the power for electric power grids.
  • 13.
  • 14. Types of fan used:- There are mainly three types of fan used :- Primary Fan:- These types of fan are used to lift pulverised coal from mill to furnace of boiler. Primary fans carries cold and hot air both for preventing formation of lumps so it can not cause choke of pipes carrying pulverised coal. Cold air insures that the coal is nt burnt in carrying process. Forced draught fan (F.D. fan):- It provides air to coal in the furnace for proper burning of under sufficient quantity of air. The air supplied is also called as secondary air.
  • 15. The quantity of secondary air is decided by amount of co and co2 In the flue gases. The F.D. fan also carry both cold and hot air. Induced draught fan (I.D. fan):- I.d. fan is used to transport the flue gases to the chimney. The aim of I.d. fan is to maintain the pressure inside the furnace so that fuel burnt constantly and efficiently.
  • 16. Coal handling plant:- First of all the coal from coal mines is loaded in trains and transported to the plant and dumped in an area from where it is it is used for various operation. Now the coal from stackyard area is transported to the crusher house with the help of conveyer belt for crushing into smaller pieces for proper burning and full utilization of energy which is obtained by burning of coal. After crushing of coal, it is transported to the mill and crushed into powdered form in it to feed the fuel to the furnace for continuous burning. About 70 metric tons of coal comes per day from coal mines to NTPC plant.
  • 17.
  • 18. Pulverizing plant • In modern thermal power plant , coal is pulverised i.e. ground to dust like size and carried to the furnace in a stream of hot air. • Pulverizing is done in pulverizing mill. • Pulverizing mill is further classified in three types: Contact mill Ball mill Impact mill
  • 19. Ash Handling plant • The percentage of ash in coal varies from 5% in good quality coal to about 40% in poor quality coal. • Power plants generally of coal, thus amount of ash produced by it pretty large . • A modern 2000MW plant produces about 5000 tons of ash daily.
  • 20. FLY ASH BRICK:- Fly ash bricks are the building unit of construction work made from ash, sand cement and water. •These are light in weight . •These are cheap and easy to construct. •These have good strength than clay brick. •Ash released due to burning of coal is utilised which is also helpful from environment point of view. Composition of fly ash brick:- Ash – 57% Sand – 34% Ordinary portland Cement -9%
  • 21.
  • 22. Conclusion:- 1)The training experience at n.t.p.c is good. 2)I have learned a lot of things of construction which help me in future. 3) In this 30 days i came in contact with experienced person who helps me lot to achieve my goals and provide proper guidance to me. 4)The staff was very polite and helpful.