This report analyzes and optimizes the manufacturing system of a client that produces screw pump rotors. Key points:
1) The factory currently has 3 CNC workstations and produces rotors in batch production. Cycle times were recorded to calculate production rates.
2) The optimum number of workstations was calculated to be 2.97, matching the current 3 workstations. Motion studies were conducted to reduce repositioning times.
3) Implementation of layout changes reduced average cycle times, increasing production rates. Machine clustering allowed one worker to manage multiple machines.
4) Cost analyses showed the optimized system with clustering lowered production costs per unit compared to the present situation. Further automation of material handling was recommended