SlideShare a Scribd company logo
URBAN TRACK
Final Conference
Alternative to Floating Track Slab
High Attenuation Sleeper
Presented by Ian Robertson, ALSTOM
24 June 2010, Prague
Final Conference – 24 June 2010 2
Contents
Specific objectives of study
Chosen concept
Detailed design and laboratory test
Site test (ongoing)
Conclusions
Final Conference – 24 June 2010 3
Specific objectives of study
 Develop slab track with following technical characteristics
 metro environment (18t axle load, 100 kph)
 equivalent vibration performance to Floating Slab Track
 ability to meet all railway constraints
 Safety (derailment) including track level evacuation
 Comfort
 maintenance
 Construction method
 for standard equipment and methods
 production rate as conventional track slab
 Lower costs compared to AFST
 For capital portion (design+procure+build)
 For maintenance portion
Final Conference – 24 June 2010 4
Chosen concept
Review of existing systems worldwide
Previous generation bi-block sleepers for CTRL
 Relatively low weight
 Tie bar overstressed with very soft pads
 Track gauge variations with very soft pads
Chosen concept = mono-block resilient sleeper
High attenuation due to
 High sleeper mass (350 – 400 kg)
 Very soft resilient inserts (8KN/mm/fastener)
Adapted to tracklaying gantries
Maintenance friendly
Final Conference – 24 June 2010 5
Detailed design and laboratory test
HAS mono-bloc sleeper concept
Rigid boot
Concrete
sleeperFastening
system
according
to
customer
choice
sealing
Holes for
conductor
rail
support
Final Conference – 24 June 2010 6
Detailed design and laboratory test
Comparison of Different Antivibratile System
-60
-50
-40
-30
-20
-10
0
10
20 1
1,6
2,5
4
6,3
10
16
25
40
63
100
158
251
Frequency (Hz)
InsertionGain(dB)
Insertion Gain SFS 312 (dB)
Insertion Gain DFC Pandrol (dB)
Insertion Gain CTRL 2(dB)
Insertion Gain FST (Taipei) (dB)
Insertion Gain EGG_2(dB)
Insertion gain target
Final Conference – 24 June 2010 7
Detailed design and laboratory test
DESIGN FULLY COMPLIANT WITH MOST RAIL FASTENERS
Typical tunnel layout
Final Conference – 24 June 2010 8
Detailed design and laboratory test
Based on OBLEX project 20 cm gain
Dia.5.8 Dia. 5.6
Typical case of impact on tunnel diameter
Final Conference – 24 June 2010 9
Detailed design and laboratory test
Time
Load 2 Hz
5 Hz
Fmax
.Fmax
Actual load diagram with sine shape
Optimum load diagram with triangle shape simulating wheel passage
Simplified load diagram used during fatigue test to simulate bogie passage
ACHIEVED 4,5 MILLIONS LOAD CYCLE WITH SUCCESS
HAS mono-bloc sleeper dynamic testing regime
Final Conference – 24 June 2010 10
Detailed design and laboratory test
Mechanical test carried out
 Fatigue test with inclined loads according to the
following phases :
 1M Cycles @ low frequency (3 Hz) applied load between 10kN et
75kN, centred, inclined at 38°
 0.5MCycles @ moderate frequency (5 Hz) applied load between
30/40kN et 75kN centred , inclined at 38°
 2M Cycles @ low frequency (3 Hz) applied load between 10kN et
75kN, inclined at 10° and 38°
 1 M Cycles @ moderate frequency (5 Hz) applied load between
30/40kN et 75kN, inclined at 10° and 38°
NO PAD WEARING & NO VERTICAL STIFFNESS LOSS AFTER 4.5M
CYCLES
(EN13230: 2M CYCLES)
Final Conference – 24 June 2010 11
Detailed design and laboratory test
EXCITATIO
N
MONOBLOC
SLEEPER
RAIL
RIGID
HULL
RAIL
PRELOAD
CONCRETE
BASE
SENSOR
S
Testing arrangements
Acoustic test
mechanical test
Final Conference – 24 June 2010 12
Detailed design and laboratory test
0
2
4
6
8
10
12
MN/m
0 32 40 50 64
kN
Stifffness vs static load at 8Hz
K (MN/m)
Dynamic test results
Final Conference – 24 June 2010 13
Site test (ongoing)
Several possibilities reviewed notably
 SINGAPORE Circle Line
 CEF test site (Valenciennes)
CEF chosen
 Easier logistics
 To respect URBAN TRACK timing
Construction just completed June 11
Vibration tests scheduled July
Introduction
Final Conference – 24 June 2010 14
Site test - Situation
Test section
• 190m radius
• 160mm cant
Situation within CEF site
Actual track to replace
• ballasted track
• fishplated U50 rail
• good ground conditions
EV2 above 80 MPA
Final Conference – 24 June 2010 15
Site test
 50m of High Attenuation Track
 2 x 6.5m of transition slab with ballasted track
 Sleeper spacing 700mm
 Welded rail on high attenuation zone
 Fishplated joints allowing movement at each end of test
General Layout
Final Conference – 24 June 2010 16
Site test
Typical section
Final Conference – 24 June 2010 17
Site test
Detailed design concept
230
230
80
2583
80200
Reinforced U-shaped foundation
Track « slab » concrete
 unreinforced
 With frequent joints to avoid shrinkage cracking
Final Conference – 24 June 2010 18
Site test
After HAS vibration testing
 Axle load = 25 tonnes
 Total load = 280MGT
 HAS resilient inserts to replace by stiffer inserts
(30MN/M)
Structural design based on Eurocode 2
 Load Model 71
 Crack 0.2mm
Detailed design assumptions
Final Conference – 24 June 2010 19
Site test
 Neighbouring (existing) ballast track
 Total dynamic stiffness around 80kN/mm per fastener
 High Attenuation Sleeper Track
 Under sleeper pad = 1,5*8 kN/mm
 Total stiffness = 11kN/mm per fastener
 Transition zone
 Target total stiffness = 46kN/mm
 Under sleeper pad = 70 to 80 kN/mm per fastener
 Total stiffness = 47 to 52 kN/mm per fastener
0.70.6 0.7
HAS
Track
Ballast
track
Transition zone
7
0.7
Transition slab design
Final Conference – 24 June 2010 20
Site test
Construction after concreting of foundation
Final Conference – 24 June 2010 21
Site test
Construction before track slab concreting
Final Conference – 24 June 2010 22
Site test
In July testing of following zones
 HAS track
 Transition track
Static measurements
 Soil impedance
 Unloaded and loaded track impedance
 Determination of in situ HAS track characteristics
 Rail surface quality
Testing
Final Conference – 24 June 2010 23
Site test
Dynamic measurements (6 pass-bys)
 train induced vibration levels
 on track slab concrete
 outside U shaped foundation
 rail and sleeper deflection of both rails
 rail and sleeper lateral displacements
Testing
Final Conference – 24 June 2010 24
Site test
Strain measurements
 Captors on rail foot
 5 sleeper spacing per measurement site
Testing
Final Conference – 24 June 2010 25
Site test
Vibration simulation
 HAS track parameters measured
 PACT reference track parameters
 Measured roughness
 Rolling Stock data
 Insertion gain calculation in 1/3rd octave bands
Testing
Final Conference – 24 June 2010 26
Conclusions
 High performance alternative to floating track slab
 Ideal for underground metro applications
 Could absorb railway loads applied to sensitive bridges
 In high speed tunnel application
 Theoretically compared to “S3” high speed –4dB (halved the vibration level)
 Limiting operational criteria (mixed operations, speed, twist…) to determine
 Costing being completed but ballpark figures are
 Compared to typical metro floating track slab
 Design, procure and build cost HAS gives 10% saving
 Maintenance costs for HAS are much lower
 Potential to reduce tunnelling costs
 Further information
 final report will be ready after completion of CEF tests in August 2010
 See URBAN TRACK website http://www.urbantrack.eu/
 RGCF no 191 February 2010
 Railway Engineering 2009
High Attenuation Sleeper

More Related Content

What's hot

Presentation_CH 450_2015
Presentation_CH 450_2015Presentation_CH 450_2015
Presentation_CH 450_2015
Brian Johnson
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
Sravan Muguda
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
coderweb
 

What's hot (20)

11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
 
Material Handling Corrugated Sidewall Conveyor Belt with Cleat - Monster Belting
Material Handling Corrugated Sidewall Conveyor Belt with Cleat - Monster BeltingMaterial Handling Corrugated Sidewall Conveyor Belt with Cleat - Monster Belting
Material Handling Corrugated Sidewall Conveyor Belt with Cleat - Monster Belting
 
Lec 8 pile load test
Lec 8 pile load testLec 8 pile load test
Lec 8 pile load test
 
GDP_Poster_Adrian_Azorin
GDP_Poster_Adrian_AzorinGDP_Poster_Adrian_Azorin
GDP_Poster_Adrian_Azorin
 
Presentation_CH 450_2015
Presentation_CH 450_2015Presentation_CH 450_2015
Presentation_CH 450_2015
 
Track Performance
Track PerformanceTrack Performance
Track Performance
 
Proof loading of existing bridges
Proof loading of existing bridges Proof loading of existing bridges
Proof loading of existing bridges
 
Evolution of Freight Stock in Indian Railways
Evolution of Freight Stock in Indian RailwaysEvolution of Freight Stock in Indian Railways
Evolution of Freight Stock in Indian Railways
 
Dynamic pile testing
Dynamic pile testingDynamic pile testing
Dynamic pile testing
 
Pile load test
Pile load testPile load test
Pile load test
 
Improved formulation for compressive fatigue strength of concrete
Improved formulation for compressive fatigue strength of concreteImproved formulation for compressive fatigue strength of concrete
Improved formulation for compressive fatigue strength of concrete
 
Conveyors by om
Conveyors by omConveyors by om
Conveyors by om
 
Telescopic crane
Telescopic crane Telescopic crane
Telescopic crane
 
Proof loading of existing reinforced concrete bridges in The Netherlands
Proof loading of existing reinforced concrete bridges in The NetherlandsProof loading of existing reinforced concrete bridges in The Netherlands
Proof loading of existing reinforced concrete bridges in The Netherlands
 
Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)Pavement Design (Transportation Engineering)
Pavement Design (Transportation Engineering)
 
Shear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt BridgeShear and moment capacity of the Ruytenschildt Bridge
Shear and moment capacity of the Ruytenschildt Bridge
 
Beam experiments to investigate loading protocol and stop criteria for load t...
Beam experiments to investigate loading protocol and stop criteria for load t...Beam experiments to investigate loading protocol and stop criteria for load t...
Beam experiments to investigate loading protocol and stop criteria for load t...
 
Design of material handling system belt conveyor system for crushed coal for ...
Design of material handling system belt conveyor system for crushed coal for ...Design of material handling system belt conveyor system for crushed coal for ...
Design of material handling system belt conveyor system for crushed coal for ...
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
Dragline
DraglineDragline
Dragline
 

Similar to Urban track singapore

Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Eva Lantsoght
 
BTS 2016 - Composite SCL - Jiang Su_rev0.6
BTS 2016 - Composite SCL - Jiang Su_rev0.6BTS 2016 - Composite SCL - Jiang Su_rev0.6
BTS 2016 - Composite SCL - Jiang Su_rev0.6
Jiang Su
 
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
SandipPaul46
 
Epoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and smaEpoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and sma
jbors
 
Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...
l’Institut français des sciences et technologies des transports, de l’aménagement et des réseaux
 

Similar to Urban track singapore (20)

Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
Effective Width in Shear of Reinforced Concrete Solid Slab Bridges under Whee...
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
BTS 2016 - Composite SCL - Jiang Su_rev0.6
BTS 2016 - Composite SCL - Jiang Su_rev0.6BTS 2016 - Composite SCL - Jiang Su_rev0.6
BTS 2016 - Composite SCL - Jiang Su_rev0.6
 
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
KHRI- Webinar( 23-05-2020)-Analysis of Pile Foundations under Earthquake Case...
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
 
Epoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and smaEpoxy asphalt vs gussasphalt and sma
Epoxy asphalt vs gussasphalt and sma
 
MobileMT airborne surveys
MobileMT airborne surveysMobileMT airborne surveys
MobileMT airborne surveys
 
Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...Full scale test on prefabricated slabs for electrical supply by induction of ...
Full scale test on prefabricated slabs for electrical supply by induction of ...
 
4 Barrier Design 2008
4   Barrier Design 20084   Barrier Design 2008
4 Barrier Design 2008
 
cfst columns
cfst columnscfst columns
cfst columns
 
FULLTEXT01(5).pdf
FULLTEXT01(5).pdfFULLTEXT01(5).pdf
FULLTEXT01(5).pdf
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
 
Applications of Vane Shear Test in Geotechnical soil investigations
Applications of Vane Shear Test in Geotechnical soil investigationsApplications of Vane Shear Test in Geotechnical soil investigations
Applications of Vane Shear Test in Geotechnical soil investigations
 
Modeling of symmetrically and asymmetrically loaded reinforced concrete slabs
Modeling of symmetrically and asymmetrically loaded reinforced concrete slabsModeling of symmetrically and asymmetrically loaded reinforced concrete slabs
Modeling of symmetrically and asymmetrically loaded reinforced concrete slabs
 
Presentation CIE619
Presentation CIE619 Presentation CIE619
Presentation CIE619
 
Gunther koller
Gunther kollerGunther koller
Gunther koller
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
 
Smart materials in smart structural system
Smart materials in smart structural systemSmart materials in smart structural system
Smart materials in smart structural system
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 

Recently uploaded

Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 

Urban track singapore

  • 1. URBAN TRACK Final Conference Alternative to Floating Track Slab High Attenuation Sleeper Presented by Ian Robertson, ALSTOM 24 June 2010, Prague
  • 2. Final Conference – 24 June 2010 2 Contents Specific objectives of study Chosen concept Detailed design and laboratory test Site test (ongoing) Conclusions
  • 3. Final Conference – 24 June 2010 3 Specific objectives of study  Develop slab track with following technical characteristics  metro environment (18t axle load, 100 kph)  equivalent vibration performance to Floating Slab Track  ability to meet all railway constraints  Safety (derailment) including track level evacuation  Comfort  maintenance  Construction method  for standard equipment and methods  production rate as conventional track slab  Lower costs compared to AFST  For capital portion (design+procure+build)  For maintenance portion
  • 4. Final Conference – 24 June 2010 4 Chosen concept Review of existing systems worldwide Previous generation bi-block sleepers for CTRL  Relatively low weight  Tie bar overstressed with very soft pads  Track gauge variations with very soft pads Chosen concept = mono-block resilient sleeper High attenuation due to  High sleeper mass (350 – 400 kg)  Very soft resilient inserts (8KN/mm/fastener) Adapted to tracklaying gantries Maintenance friendly
  • 5. Final Conference – 24 June 2010 5 Detailed design and laboratory test HAS mono-bloc sleeper concept Rigid boot Concrete sleeperFastening system according to customer choice sealing Holes for conductor rail support
  • 6. Final Conference – 24 June 2010 6 Detailed design and laboratory test Comparison of Different Antivibratile System -60 -50 -40 -30 -20 -10 0 10 20 1 1,6 2,5 4 6,3 10 16 25 40 63 100 158 251 Frequency (Hz) InsertionGain(dB) Insertion Gain SFS 312 (dB) Insertion Gain DFC Pandrol (dB) Insertion Gain CTRL 2(dB) Insertion Gain FST (Taipei) (dB) Insertion Gain EGG_2(dB) Insertion gain target
  • 7. Final Conference – 24 June 2010 7 Detailed design and laboratory test DESIGN FULLY COMPLIANT WITH MOST RAIL FASTENERS Typical tunnel layout
  • 8. Final Conference – 24 June 2010 8 Detailed design and laboratory test Based on OBLEX project 20 cm gain Dia.5.8 Dia. 5.6 Typical case of impact on tunnel diameter
  • 9. Final Conference – 24 June 2010 9 Detailed design and laboratory test Time Load 2 Hz 5 Hz Fmax .Fmax Actual load diagram with sine shape Optimum load diagram with triangle shape simulating wheel passage Simplified load diagram used during fatigue test to simulate bogie passage ACHIEVED 4,5 MILLIONS LOAD CYCLE WITH SUCCESS HAS mono-bloc sleeper dynamic testing regime
  • 10. Final Conference – 24 June 2010 10 Detailed design and laboratory test Mechanical test carried out  Fatigue test with inclined loads according to the following phases :  1M Cycles @ low frequency (3 Hz) applied load between 10kN et 75kN, centred, inclined at 38°  0.5MCycles @ moderate frequency (5 Hz) applied load between 30/40kN et 75kN centred , inclined at 38°  2M Cycles @ low frequency (3 Hz) applied load between 10kN et 75kN, inclined at 10° and 38°  1 M Cycles @ moderate frequency (5 Hz) applied load between 30/40kN et 75kN, inclined at 10° and 38° NO PAD WEARING & NO VERTICAL STIFFNESS LOSS AFTER 4.5M CYCLES (EN13230: 2M CYCLES)
  • 11. Final Conference – 24 June 2010 11 Detailed design and laboratory test EXCITATIO N MONOBLOC SLEEPER RAIL RIGID HULL RAIL PRELOAD CONCRETE BASE SENSOR S Testing arrangements Acoustic test mechanical test
  • 12. Final Conference – 24 June 2010 12 Detailed design and laboratory test 0 2 4 6 8 10 12 MN/m 0 32 40 50 64 kN Stifffness vs static load at 8Hz K (MN/m) Dynamic test results
  • 13. Final Conference – 24 June 2010 13 Site test (ongoing) Several possibilities reviewed notably  SINGAPORE Circle Line  CEF test site (Valenciennes) CEF chosen  Easier logistics  To respect URBAN TRACK timing Construction just completed June 11 Vibration tests scheduled July Introduction
  • 14. Final Conference – 24 June 2010 14 Site test - Situation Test section • 190m radius • 160mm cant Situation within CEF site Actual track to replace • ballasted track • fishplated U50 rail • good ground conditions EV2 above 80 MPA
  • 15. Final Conference – 24 June 2010 15 Site test  50m of High Attenuation Track  2 x 6.5m of transition slab with ballasted track  Sleeper spacing 700mm  Welded rail on high attenuation zone  Fishplated joints allowing movement at each end of test General Layout
  • 16. Final Conference – 24 June 2010 16 Site test Typical section
  • 17. Final Conference – 24 June 2010 17 Site test Detailed design concept 230 230 80 2583 80200 Reinforced U-shaped foundation Track « slab » concrete  unreinforced  With frequent joints to avoid shrinkage cracking
  • 18. Final Conference – 24 June 2010 18 Site test After HAS vibration testing  Axle load = 25 tonnes  Total load = 280MGT  HAS resilient inserts to replace by stiffer inserts (30MN/M) Structural design based on Eurocode 2  Load Model 71  Crack 0.2mm Detailed design assumptions
  • 19. Final Conference – 24 June 2010 19 Site test  Neighbouring (existing) ballast track  Total dynamic stiffness around 80kN/mm per fastener  High Attenuation Sleeper Track  Under sleeper pad = 1,5*8 kN/mm  Total stiffness = 11kN/mm per fastener  Transition zone  Target total stiffness = 46kN/mm  Under sleeper pad = 70 to 80 kN/mm per fastener  Total stiffness = 47 to 52 kN/mm per fastener 0.70.6 0.7 HAS Track Ballast track Transition zone 7 0.7 Transition slab design
  • 20. Final Conference – 24 June 2010 20 Site test Construction after concreting of foundation
  • 21. Final Conference – 24 June 2010 21 Site test Construction before track slab concreting
  • 22. Final Conference – 24 June 2010 22 Site test In July testing of following zones  HAS track  Transition track Static measurements  Soil impedance  Unloaded and loaded track impedance  Determination of in situ HAS track characteristics  Rail surface quality Testing
  • 23. Final Conference – 24 June 2010 23 Site test Dynamic measurements (6 pass-bys)  train induced vibration levels  on track slab concrete  outside U shaped foundation  rail and sleeper deflection of both rails  rail and sleeper lateral displacements Testing
  • 24. Final Conference – 24 June 2010 24 Site test Strain measurements  Captors on rail foot  5 sleeper spacing per measurement site Testing
  • 25. Final Conference – 24 June 2010 25 Site test Vibration simulation  HAS track parameters measured  PACT reference track parameters  Measured roughness  Rolling Stock data  Insertion gain calculation in 1/3rd octave bands Testing
  • 26. Final Conference – 24 June 2010 26 Conclusions  High performance alternative to floating track slab  Ideal for underground metro applications  Could absorb railway loads applied to sensitive bridges  In high speed tunnel application  Theoretically compared to “S3” high speed –4dB (halved the vibration level)  Limiting operational criteria (mixed operations, speed, twist…) to determine  Costing being completed but ballpark figures are  Compared to typical metro floating track slab  Design, procure and build cost HAS gives 10% saving  Maintenance costs for HAS are much lower  Potential to reduce tunnelling costs  Further information  final report will be ready after completion of CEF tests in August 2010  See URBAN TRACK website http://www.urbantrack.eu/  RGCF no 191 February 2010  Railway Engineering 2009 High Attenuation Sleeper