SlideShare a Scribd company logo
1 of 62
PARTICIPANTS
INDEX
1.1 SUB-STATION
1.2 SWITCHYARD
1.3 TYPES OF SWITCHYARDS
1.3a SINGLE BUS BUS
1.3b Double bus bus
1.3c One and Half Breaker Switchyard
1.3d EHT Switchyard using GIS Switchgear
3.10 LIST OF MAJOR EQUIPMENT IN SUB-STATION/ SWITCHYARD/
SUBSTATION
3.11 SAFETY
3.12 I.E. RULES RELATED TO SAFETY AND MINIMUM CLEARANCES
TO BE KNOWN BEFORE ENTERING A SWITCHYARD
.
3.12 a)FOR LOW(230V TO 630V) & MEDIUM Voltage (630V TO
11000V)
Phase to Earth…5.8 MTR. Mnm.Clearance
Phase to Phase….. Mtr. Mnm. Clearances
3.12 b) FOR HIGH Voltage(11kV TO 66kV) AND EXTRA HIGH
VOLTAGE (66KV TO 400KV/750KV ONWARDS…IN
INDIA
Phase to Earth= 6.1 Mtr. Mnm
Phase to Phase….. Mtr. Mnm. Clearance
3.13) WORK PERMIT FOR ATTENDING SWITCHYARD/
SUB- STATION.
3.2) MAINTENANCE OF EQUIPMENT
3.2a) ROUTINE MAINTENANCE
3.2b) PREVENTIVE MAINTENANCE
3.2c) BREAKDOWN MAINTENANCE
4.1 MANUFACTURERS’ OWN AMC
4.2 LIST OF MANUFACTURER / VENDORS OF EHT
EQUIPMENT APPLYING ANNUAL MAINTENANCE
SCHEME
4.2a) M/S SIEMENS INDIA LIMITED.
4.2b) M/S ABB
4.2c) M/S ALSTHOM
5.0 HT & EHT TRANSMISSION LINES FEEDING
SWITCHYARDS & SUB-STATION
6.0 DIFERENT TYPES ( A,B,C,D &SPECIALTYPE) OF
TOWERS FOR TRANSMISSION LINES.
DESCRIPTION
OF
INDEX
1.1 SUB-STATION
A HT & EHT Sub-station is a switchyard with
One or more Transformers for distribution of
Electrical power, at reduced voltages,
suitable to the network.
1.2 SWITCHYARD
A Switchyard is a Nodal place where HT and
EHT POWER is brought IN and DISTRIBUTED
OUT, through different Overhead Lines and UG
Cables. A switchyard does not have any
Transformer
1.3 TYPES OF SWITCHYARDS
1.3a) SINGLE BUS
Advantages of single bus system.
1) Its Very SIMPLE IN DESIGN
2) Very COST EFFECTIVE
3) Very CONVENIENT TO OPERATE
Disadvantages of single bus system
One major difficulty of these type of arrangement is that, MAINTENANACE OF
EQUIPMENT OF Any bay, CANNOT BE POSSIBLE WITHOUT INTERRUPTING THE
FEEDER, or transformer connected to that bay.
Single Bus System with Bus Sectionalizer
Advantages with bus sectionalizer
If any of the sources is out of system, still all loads can be fed by
switching on the sectional circuit breaker or bus coupler breaker.
If one section of the bus bar system is under maintenance, part
load of the substation can be fed by energizing the other section
of bus bar.
Disadvantages of single bus system with bus sectionalizer
As in the case of single bus system, maintenance of equipment
of any bay cannot be possible without interrupting the feeder or
transformer connected to that bay.
The use of isolator for bus sectionalizing does not fulfill the
purpose. The isolators have to be operated ‘off circuit’ and which
is not possible without total interruption of bus – bar. So
investment for bus-coupler breaker is required.
1.3b) DOUBLE BUS BUS
In double bus bar system two identical bus bars are used in such
a way that any outgoing or incoming feeder can be taken from
any of the bus.
Actually every feeder is connected to both of the buses in
parallel through individual isolator as shown in the figure.
By closing any of the isolators one can put the feeder to
associated bus. Both of the buses are energized and total
feeders are divided into two groups, one group is fed from
one bus and other from other bus. But any feeder at any
time can be transferred from one bus to other. There is one
bus coupler breaker which should be kept close during bus
transfer operation. For transfer operation, one should first
close the bus coupler circuit breaker then close the isolator
associated with the bus to where the feeder would be
transferred and then open the isolator associated with the
bus from where feeder is transferred. Lastly after this
transfer operation he or she should open the bus coupler
breaker.
Advantages of Double Bus System
Double Bus Bar Arrangement increases the
flexibility of system.
Disadvantages of Double Bus System
The arrangement does not permit breaker
maintenance with out interruption.
Double Breaker Bus System
In double breaker bus bar system two identical bus bars are
used in such a way that any outgoing or incoming feeder can be
taken from any of the bus similar to double bus bar system.
Only difference is that here every feeder is connected to both
of the buses in parallel through individual breaker instead only
isolator as shown in the figure. By closing any of the breakers
and its associated isolators, one can put the feeder to
respective bus. Both of the buses are energized and total
feeders are divided into two groups, one group is fed from one
bus and other from other bus similar to previous case. But any
feeder at any time can be transferred from one bus to other.
There is no need of bus coupler as because the operation is
done by breakers instead of isolator. For transfer operation, one
should first close the isolators and then the breaker associated
with the bus to where the feeder would be transferred and
then he or she opens the breaker and then isolators associated
with the bus from where feeder is transferred.
1.3c) ONE AND HALF BREAKER SWITCHYARD
One and a half Breaker Bus System
This is an improvement on the double breaker scheme to effect saving
in the number of circuit breakers. For every two circuits only one spare
breaker is provided. The protection is however complicated since it
must associate the central breaker with the feeder whose own breaker
is taken out for maintenance. For the reasons given under double
breaker scheme and because of the prohibitory costs of equipment
even this scheme is not much popular. As shown in the figure that it is
a simple design, two feeders are fed from two different buses through
their associated breakers and these two feeders are coupled by a third
breaker which is called tie breaker. Normally all the three breakers are
closed and power is fed to both the circuits from two buses which are
operated in parallel. The tie breaker acts as coupler for the two feeder
circuits.
During failure of any feeder breaker, the power is fed through the
breaker of the second feeder and tie breaker, therefore each feeder
breaker has to be rated to feed both the feeders, coupled by tie
breaker.
Advantages of One and a half Breaker Bus System
During any fault on any one of the buses, that faulty bus will be cleared
instantly without interrupting any feeders in the system since all feeders will
continue to feed from other healthy bus.
Disadvantages of One and a half Breaker Bus System
This scheme is much expensive due to investment for third breaker.
1.3d) EHT SWITCHYARD USING GIS SWITCHGEAR A GIS(Gas
Insulated Sub-station/Switchyard) is normally used where
there is paucity of space and specially located in the heart of
largely populated cities with concentrated load centers.
Since the interconnections in-between CBs, Isolators, CTs,
CVTs., etc., are closely knit in a GIS, due to increased pressure
of INERT GAS(SF6) inside, there is a great reduction of power
layout space. This criterion is utilized advantageously, while
Designing the power layout, involving GIS.
2.0 TROUBLE SHOOTING IN SWITCHYARD &
SUB-STATION EQUIPMENT.
 THE TERM “TROUBLE SHOOTING” mainly
attributes to NON-CLOSURE OF “CLOSING
COIL” OR “ TRIPPING COIL” OF ALL CIRCUIT
BREAKERS OR/AND ALL REMOTE OPERATING
ISOLATORS THEREFORE, TROUBLE SHOOTING
MAINLY CONCERNS.
 THE D.C. CONTROL SYSTEM (THE SOURCE OF
AUXILIARY POWER), FOR AIR BLAST TYPE, SF6 TYPE
AND VACCUM CIRCUIT BREAKERS.
 THE INTER CONNECTIVITY OF THE PARTICULAR CIRCUIT
INCLUDING THE VARIOUS INTERLOCKING LIMIT
SWITCHES AND RELAY CONTACTS.
 IN THE AIR BLAST TYPE, THE PNEUMATIC SYSTEM
INCLUDING THE COPPER TUBING AND ITS END
TERMINATIONS.
 CHECK FOR SYMULTANEOUS OPEN & CLOSE OF SLOW
OPEN & CLOSE OF MAIN CONTACTS, OF CIRCUIT
BREAKERS AND ISOLATORS.
3.0 OPERATION & MAINTENANCE OF
SWITCHYARD
EHT Switchyard /Substation being in the
PRIMARY NETWORK of power distribution, it is
the most vital nodal point in the NETWORK.
RELIABILITY of POWER DISTRIBUTION, greatly
depends on these NODES.
It is therefore, very important to check and
enhance the longevity and quality of each item,
comprising these Nodes (SWITCHYARD).
3.1 LIST OF MAJOR EQUIPMENT IN
SWITCHYARD/ SUBSTATION
1. TRANSFORMERS
a) DRY TYPE (CAST RESIN TYPE)
b) OIL FILLED TYPE
2. CIRCUIT BREAKERS
a) AIR BLAST TYPE ( 33KV, 132KV, 220KV)
b) SF6 TYPE (220KV, 400KV )
c) VACCUM TYPE (220KV, 400KV)
3. POWER ISOLATERS
a) HORIZONTAL DOUBLE BREAK ISOLATORS (33KV,132KV)
b) HORIZONTAL CENTRE BREAK ISOLATORS (220KV, 400KV)
c) VERTICAL PANTOGRAPH ISOLATORS (220KV, 400KV)
4. EARTHING SWITCHES
a) REMOTE POWER OPERATED (220KV, 400KV)
b) LOCAL MANNUAL OPERATED(UPTO 33KV)
5. GALVANISED STEEL LATICE STRUCTURES FOR
BEAMS & COLUMNS
6. STEEL PIPES FOR EQUIPMENT SUPPORT
7. ALL ALUMINIUM CLAMPS & CONNECTORS
8. ALL ALUMINIUM BUS BUS TUBES FOR MAIN BUS
9. SECONDARY EMERGENCY SOURCE FOR PROVIDING.
POWER TO THE CONTROLLING SYSTEM (BATTERY,
BATTERY CHARGER, DC BOARD)
10. HORIZONTAL ISOLATORS WITH DOUBLE BREAK
(33KV)
11. VERTICAL ISOLATORS WITH DOUBLE BREAK TYPE
(33KV)
12. HORIZONTAL CENTRAL BREAK ISOLATORS
(220KV & 400KV)
13. (220KV/400KV) VERTICAL BREAK PAN TO GRAPH
ISOLATORS
14. SF6 SINGLE BREAK CIRCUIT BREAKERS
(132KV,220KV)
15. SF6 DOUBLE BREAK CIRCUIT BREAKERS(400KV)
16. VACCUUM SINGLE BREAK CIRCUIT BREAKE
(132KV,220KV)
17. VACUUM D0UBLE BREAK CIRCUIT BREAKER
(400KV)
18. EARTHING SWITCHES FOR 400KV HVDC
SWITCHYARDS.
19. BUS POST INSULATORS
20. MULTICORE CTs, CVTs
21. WAVE TRAPS FOR COMMUNICATION & LINE
PROTECTION
22. SWITCHYARD MAIN EARTHING
23. SWITCHYARD AUXILIARY EARTHING FOR MAIN
EQPMNT.
24. SWITCHYARD LIGHTING TOWERS/MASTS
25. LIGHTENING PROTECTION SCHEMES OF
SWITCHYARD
26. 2 No’s of 30 KVA UPS BACK TO BACK, With
minimum 20 minutes battery Back-up. The
Emergency Back-up should be essentially connected
to at least 25% of the Lighting System of the
CONTROL ROOM, Video Conference Room, Main
and Half Landing of Stair cases, Walking corridor,
Toilets, Flashing Exit Lights, etc.
3.11 SAFETY
MAINTAIN SAFETY OF PERSONNEL AND EQUIPMENTAT
ANY COST SAFETY RULES SHOULD BE FOLLOWED
RELIGIOUSLYAND SEQUENTIALLY TO AVOID ACCIDENT/
ELECTROCUTION.
3.12 I.E. RULES RELATED TO SAFETY AND MINIMUM
CLEARANCES TO BE KNOWN BEFORE ENTERING A
SWITCHYARD.
a) FOR LOW(230V TO 630V) & MEDIUM Voltage
(630V TO 11000V)
Phase to Earth…5.8 MTR. Mnm.Clearance
Phase to Phase….. Mtr. Mnm. Clearance
B) FOR HIGH Voltage AND EXTRA HIGH VOLTAGE
Phase to Earth= 6.1 Mtr.Mnm.Clearance
Phase to Phase….. Mtr. Mnm. Clearance
3.13) WORK PERMIT FOR ATTENDING SWITCHYARD/
SUB- STATION.
ISSUE of WORK PERMIT / RETURN of WORK-PERMIT.
This is a very IMPORTANT DOCUMENT and the person who
issues / accepts it, should be a RESPONSIBLE Person, not less
than the rank of a SUPERINTENDENT ENGINEER from
OPERATION & MAINTENANCE GROUP.
1) SWITCH OFF the Concerned feeders.
2) ISOLATE the Feeders.
3) Remove and keep the Controlling Fuses in safe
custody.
4) Inspect all the accessible BUS SHUTTERS TO BE
CLOSED and PADLOCKED.
5) ISSUE the WORK PERMIT, BY NAME OF THE PERSON
WHO TAKES IT, mentioning all these important
activities.
6) Apply local EARTHING BY SHORTING EARTHING ALL
THE PHASES. After COMPLETION of all work, the safety
devices and all shortings and EARTHINGS ARE
REMOVED AND THE WORK PERMIT is returned. Again
as a precautionary method, the same person who took
the WORK PERMIT, SHOULD RETURN IT’.
3.2) MAINTENANCE OF EQUIPMENT
3.2a) ROUTINE MAINTENANCE
3.2b) PREVENTIVE MAINTENANCE
3.2c) BREAKDOWN MAINTENANCE
4.0 ANNUAL MAINTENANCE CONTRACT
Any Switchyard being upstream in the loadflow diagram,
anything and everything in a switchyard, is very critical. An
outage due to malfunctioning of any item, is disastrous.
Like all other equipment, a procedural Format is followed
by the manufacturers, to generate a list of various parts of
all the Equipment, erected in a Switchyard.
These parts and their sub-parts are codifiedand identified
individually and madecompatible to SAP.
An inventory of all these items aremeticulously maintained,
so that in the event of an outage, downtime shall be
minimum.
4.1 MANUFACTURERS’ OWN AMC
4.2 LIST OF MANUFACTURER / VENDORS OF EHT
EQUIPMENT APPLYING ANNUAL MAINTENANCE
SCHEME
4.2a) M/S SIEMENS INDIA LIMITED
4.2b) M/S ABB
4.2c) M/S ALSTHOM
5.0 DIFERENT TYPES ( A,B,C,D & SPECIAL TYPE)
OF TOWERS FOR TRANSMISSION LINES.
In order to build up a Transmission Line, keeping within
the allocated power corridor, various types of TOWERS
are used. These are :-
a) (TYPE) Tangent Tower..( max deviation from TOWER
Centre Line being 0to5 Degrees)
b) (TYPE)…Angular Tower…(max Deviation 5 to15
degrees).
c) (TYPE)…Angular Tower…(15 to 30 degrees).
d) (TYPE)…Angular Tower…( 30 to 60 degrees)
SPECIAL TYPES OF TOWERS.. (60 to 90 degrees).
TERMINATION OF OVERHEAD EHT
TRANSMISSION LINES ON TO THE
SWITCHYARD GANTRIES
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
EPC OF EHT OVERHEAD TRANSMISSION LINES
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
6.0 BASIC STEPS TAKEN FOR ENGINEERING,
PROCUREMENT & CONSTRUCTION OF EHT
TRANSMISSION LINES
6.1 ROUTE SURVEYING
(WALK THROUGH SURVEY)
As the name suggests, the WALK THROUGH SURVEY, is a
very informative survey and determines the nature of the
PROJECT, as per points appended :
1. The existing contours above Finished Ground Level
and within the pre-defined route, as per the
GOVERNMENT NOTIFICATION put –up in the local
GAZETTE, are carefully noted, studied and finally
fixed, keeping in mind TOWER SPOTTING
LOCATIONS & THE MINIMUM GROUND
CLEARANCES THAT SHALL BE REQUIRED, as per I.E.
Rules.
2. Any existing water-fronts which are to be
encountered
3. Any SHORING required for the Tower foot near
water-fronts.
4. Any BENCHING required while crossing, hills.
6.2 TOWER SPOTTING (MAINTAINING
MINIMUM CLEARANCES).
As per the span available on both sides, of any Tower,
the particular SPOT of the next Towers are fixed,
keeping in mind if any SHORING / BENCHING is
required or not.
6.3 ALLOCATING TYPE OF TOWER TO BE USED,
MAINTAIN SAG, TENSION & MINIMUM
CLEARANCES AS PER I.E. RULES & ACTS.
Once the TOWER SPOTS are fixed, the Type of Tower
(A,B,C,D,Special) ,required for the situation is finally
frozen.
6.4 ESTABLISHING R.O.W. FOR POWER
CORRIDOR AS PER STATUTARY RULES.
6.5 LAND AQUISITIONING & PAYING
COMPENSATION AS PER RULES.
6.6 ERECTION, TESTING &COMMISSIONING
OF EHT OVERHEAD TRANSMISSION LINES.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Switchyard and Substation Operation, Maintenance, and Safety Guide

More Related Content

What's hot

High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...Ali Sepehri
 
NGR & Zig-Zag Transformer.pptx
NGR & Zig-Zag Transformer.pptxNGR & Zig-Zag Transformer.pptx
NGR & Zig-Zag Transformer.pptxMUHAMMAD TAHIR
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Switchgears and protection devices
Switchgears and protection devicesSwitchgears and protection devices
Switchgears and protection devicesManojkarader
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work pptDemsew Mitiku
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Sourabh sharma
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREPremanandDesai
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training pptsitesh95074
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationankesh kumar
 

What's hot (20)

High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
 
NGR & Zig-Zag Transformer.pptx
NGR & Zig-Zag Transformer.pptxNGR & Zig-Zag Transformer.pptx
NGR & Zig-Zag Transformer.pptx
 
Dog Conductor
Dog ConductorDog Conductor
Dog Conductor
 
Basics of busbar protection
Basics of busbar protectionBasics of busbar protection
Basics of busbar protection
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Electric substation
Electric substation Electric substation
Electric substation
 
Switchgears and protection devices
Switchgears and protection devicesSwitchgears and protection devices
Switchgears and protection devices
 
33kv substation
33kv substation33kv substation
33kv substation
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training ppt
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 

Similar to Switchyard and Substation Operation, Maintenance, and Safety Guide

Template ppt power engg.
Template ppt power engg.Template ppt power engg.
Template ppt power engg.sharukhkhan786
 
Substation Layouts - electrical power system that transforms voltage levels, ...
Substation Layouts - electrical power system that transforms voltage levels, ...Substation Layouts - electrical power system that transforms voltage levels, ...
Substation Layouts - electrical power system that transforms voltage levels, ...ssuser9e9be71
 
LEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemLEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemMuhammadAliImran11
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Mohit Kothari
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Mohit Kothari
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Mohit Kothari
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its typesJay Ranvir
 
power grid design
power grid designpower grid design
power grid designsusanta das
 
Modern substation design 2
Modern substation design 2Modern substation design 2
Modern substation design 2rajesh18001 R
 
Modern substation design
Modern substation designModern substation design
Modern substation designrajesh18001 R
 
A report on 220 kv gss mansarovar, jaipur by ravindra kumar goma
A report on 220 kv gss mansarovar, jaipur by ravindra kumar gomaA report on 220 kv gss mansarovar, jaipur by ravindra kumar goma
A report on 220 kv gss mansarovar, jaipur by ravindra kumar gomaravindragoma
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptxRahaf Waheep
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgearAdnan Sayed
 
TDU Unit 03 Distribution Systems
TDU Unit  03 Distribution SystemsTDU Unit  03 Distribution Systems
TDU Unit 03 Distribution SystemsPremanandDesai
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training reportMuntazir Mehdi
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training reportGyanendra Prakash
 

Similar to Switchyard and Substation Operation, Maintenance, and Safety Guide (20)

Template ppt power engg.
Template ppt power engg.Template ppt power engg.
Template ppt power engg.
 
Single breaker
Single breakerSingle breaker
Single breaker
 
Substation Layouts - electrical power system that transforms voltage levels, ...
Substation Layouts - electrical power system that transforms voltage levels, ...Substation Layouts - electrical power system that transforms voltage levels, ...
Substation Layouts - electrical power system that transforms voltage levels, ...
 
Substation
SubstationSubstation
Substation
 
0000.000
0000.0000000.000
0000.000
 
LEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution systemLEC #01 INTRODUCTION to power distribution system
LEC #01 INTRODUCTION to power distribution system
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
 
power grid design
power grid designpower grid design
power grid design
 
Modern substation design 2
Modern substation design 2Modern substation design 2
Modern substation design 2
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
A report on 220 kv gss mansarovar, jaipur by ravindra kumar goma
A report on 220 kv gss mansarovar, jaipur by ravindra kumar gomaA report on 220 kv gss mansarovar, jaipur by ravindra kumar goma
A report on 220 kv gss mansarovar, jaipur by ravindra kumar goma
 
Busbar protection LEC 2.pptx
Busbar protection LEC 2.pptxBusbar protection LEC 2.pptx
Busbar protection LEC 2.pptx
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
TDU Unit 03 Distribution Systems
TDU Unit  03 Distribution SystemsTDU Unit  03 Distribution Systems
TDU Unit 03 Distribution Systems
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 

More from Marcep Inc.

Troubleshooting of Distillation
Troubleshooting of DistillationTroubleshooting of Distillation
Troubleshooting of DistillationMarcep Inc.
 
Regulatory requirements and expectations from us, europe, and other regulator...
Regulatory requirements and expectations from us, europe, and other regulator...Regulatory requirements and expectations from us, europe, and other regulator...
Regulatory requirements and expectations from us, europe, and other regulator...Marcep Inc.
 
Commissioning, Shutdowns and turnarounds
Commissioning, Shutdowns and turnaroundsCommissioning, Shutdowns and turnarounds
Commissioning, Shutdowns and turnaroundsMarcep Inc.
 
Impact of changing technology on strategic procurement
Impact of changing technology on strategic procurementImpact of changing technology on strategic procurement
Impact of changing technology on strategic procurementMarcep Inc.
 
Troubleshooting chemical plants training - Techniques to Identify and Correct...
Troubleshooting chemical plants training - Techniques to Identify and Correct...Troubleshooting chemical plants training - Techniques to Identify and Correct...
Troubleshooting chemical plants training - Techniques to Identify and Correct...Marcep Inc.
 
Smart instrumentation for process plants training
Smart instrumentation for process plants trainingSmart instrumentation for process plants training
Smart instrumentation for process plants trainingMarcep Inc.
 
Asset corrosion management cui - masterclass 2018
Asset corrosion management   cui - masterclass 2018Asset corrosion management   cui - masterclass 2018
Asset corrosion management cui - masterclass 2018Marcep Inc.
 
electrical engineering, electrical fire, and safety, electrical safety audits...
electrical engineering, electrical fire, and safety, electrical safety audits...electrical engineering, electrical fire, and safety, electrical safety audits...
electrical engineering, electrical fire, and safety, electrical safety audits...Marcep Inc.
 
Electrical Fixtures Electrical Fittings
Electrical Fixtures Electrical Fittings Electrical Fixtures Electrical Fittings
Electrical Fixtures Electrical Fittings Marcep Inc.
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Marcep Inc.
 
Compressor Master Class
Compressor Master ClassCompressor Master Class
Compressor Master ClassMarcep Inc.
 
Advance electrical and installation safety 2017
Advance electrical and installation safety 2017Advance electrical and installation safety 2017
Advance electrical and installation safety 2017Marcep Inc.
 
Pharmaceutical qualification and validations training
Pharmaceutical qualification and validations trainingPharmaceutical qualification and validations training
Pharmaceutical qualification and validations trainingMarcep Inc.
 
Damage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsDamage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsMarcep Inc.
 
Data integrity issues in pharma industry in India
Data integrity issues in pharma industry in IndiaData integrity issues in pharma industry in India
Data integrity issues in pharma industry in IndiaMarcep Inc.
 
Achieving excellence in pharma manufacturing plants
Achieving excellence in pharma manufacturing plantsAchieving excellence in pharma manufacturing plants
Achieving excellence in pharma manufacturing plantsMarcep Inc.
 
Advance maintenance & corrosion engineering
Advance maintenance & corrosion engineeringAdvance maintenance & corrosion engineering
Advance maintenance & corrosion engineeringMarcep Inc.
 
Clean coal technology for power plants
Clean coal technology for power plantsClean coal technology for power plants
Clean coal technology for power plantsMarcep Inc.
 
Maintenance contracting & outsourcing
Maintenance contracting & outsourcingMaintenance contracting & outsourcing
Maintenance contracting & outsourcingMarcep Inc.
 

More from Marcep Inc. (20)

Troubleshooting of Distillation
Troubleshooting of DistillationTroubleshooting of Distillation
Troubleshooting of Distillation
 
Regulatory requirements and expectations from us, europe, and other regulator...
Regulatory requirements and expectations from us, europe, and other regulator...Regulatory requirements and expectations from us, europe, and other regulator...
Regulatory requirements and expectations from us, europe, and other regulator...
 
Commissioning, Shutdowns and turnarounds
Commissioning, Shutdowns and turnaroundsCommissioning, Shutdowns and turnarounds
Commissioning, Shutdowns and turnarounds
 
Impact of changing technology on strategic procurement
Impact of changing technology on strategic procurementImpact of changing technology on strategic procurement
Impact of changing technology on strategic procurement
 
Troubleshooting chemical plants training - Techniques to Identify and Correct...
Troubleshooting chemical plants training - Techniques to Identify and Correct...Troubleshooting chemical plants training - Techniques to Identify and Correct...
Troubleshooting chemical plants training - Techniques to Identify and Correct...
 
Smart instrumentation for process plants training
Smart instrumentation for process plants trainingSmart instrumentation for process plants training
Smart instrumentation for process plants training
 
Asset corrosion management cui - masterclass 2018
Asset corrosion management   cui - masterclass 2018Asset corrosion management   cui - masterclass 2018
Asset corrosion management cui - masterclass 2018
 
electrical engineering, electrical fire, and safety, electrical safety audits...
electrical engineering, electrical fire, and safety, electrical safety audits...electrical engineering, electrical fire, and safety, electrical safety audits...
electrical engineering, electrical fire, and safety, electrical safety audits...
 
Electrical Fixtures Electrical Fittings
Electrical Fixtures Electrical Fittings Electrical Fixtures Electrical Fittings
Electrical Fixtures Electrical Fittings
 
Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design Electrical Plan Electrical System Electrical Design
Electrical Plan Electrical System Electrical Design
 
Compressor Master Class
Compressor Master ClassCompressor Master Class
Compressor Master Class
 
Advance electrical and installation safety 2017
Advance electrical and installation safety 2017Advance electrical and installation safety 2017
Advance electrical and installation safety 2017
 
Pharmaceutical qualification and validations training
Pharmaceutical qualification and validations trainingPharmaceutical qualification and validations training
Pharmaceutical qualification and validations training
 
Damage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipmentsDamage mechanism affecting fixed equipments
Damage mechanism affecting fixed equipments
 
Data integrity issues in pharma industry in India
Data integrity issues in pharma industry in IndiaData integrity issues in pharma industry in India
Data integrity issues in pharma industry in India
 
Achieving excellence in pharma manufacturing plants
Achieving excellence in pharma manufacturing plantsAchieving excellence in pharma manufacturing plants
Achieving excellence in pharma manufacturing plants
 
Advance maintenance & corrosion engineering
Advance maintenance & corrosion engineeringAdvance maintenance & corrosion engineering
Advance maintenance & corrosion engineering
 
Clean coal technology for power plants
Clean coal technology for power plantsClean coal technology for power plants
Clean coal technology for power plants
 
Maintenance contracting & outsourcing
Maintenance contracting & outsourcingMaintenance contracting & outsourcing
Maintenance contracting & outsourcing
 
Water Chemistry
Water ChemistryWater Chemistry
Water Chemistry
 

Recently uploaded

VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

Switchyard and Substation Operation, Maintenance, and Safety Guide

  • 1.
  • 3. 1.1 SUB-STATION 1.2 SWITCHYARD 1.3 TYPES OF SWITCHYARDS 1.3a SINGLE BUS BUS 1.3b Double bus bus 1.3c One and Half Breaker Switchyard 1.3d EHT Switchyard using GIS Switchgear
  • 4.
  • 5. 3.10 LIST OF MAJOR EQUIPMENT IN SUB-STATION/ SWITCHYARD/ SUBSTATION 3.11 SAFETY 3.12 I.E. RULES RELATED TO SAFETY AND MINIMUM CLEARANCES TO BE KNOWN BEFORE ENTERING A SWITCHYARD . 3.12 a)FOR LOW(230V TO 630V) & MEDIUM Voltage (630V TO 11000V) Phase to Earth…5.8 MTR. Mnm.Clearance Phase to Phase….. Mtr. Mnm. Clearances
  • 6. 3.12 b) FOR HIGH Voltage(11kV TO 66kV) AND EXTRA HIGH VOLTAGE (66KV TO 400KV/750KV ONWARDS…IN INDIA Phase to Earth= 6.1 Mtr. Mnm Phase to Phase….. Mtr. Mnm. Clearance 3.13) WORK PERMIT FOR ATTENDING SWITCHYARD/ SUB- STATION. 3.2) MAINTENANCE OF EQUIPMENT 3.2a) ROUTINE MAINTENANCE 3.2b) PREVENTIVE MAINTENANCE 3.2c) BREAKDOWN MAINTENANCE
  • 7. 4.1 MANUFACTURERS’ OWN AMC 4.2 LIST OF MANUFACTURER / VENDORS OF EHT EQUIPMENT APPLYING ANNUAL MAINTENANCE SCHEME 4.2a) M/S SIEMENS INDIA LIMITED. 4.2b) M/S ABB 4.2c) M/S ALSTHOM
  • 8. 5.0 HT & EHT TRANSMISSION LINES FEEDING SWITCHYARDS & SUB-STATION 6.0 DIFERENT TYPES ( A,B,C,D &SPECIALTYPE) OF TOWERS FOR TRANSMISSION LINES.
  • 10.
  • 11. 1.1 SUB-STATION A HT & EHT Sub-station is a switchyard with One or more Transformers for distribution of Electrical power, at reduced voltages, suitable to the network.
  • 12. 1.2 SWITCHYARD A Switchyard is a Nodal place where HT and EHT POWER is brought IN and DISTRIBUTED OUT, through different Overhead Lines and UG Cables. A switchyard does not have any Transformer
  • 13. 1.3 TYPES OF SWITCHYARDS
  • 14. 1.3a) SINGLE BUS Advantages of single bus system. 1) Its Very SIMPLE IN DESIGN 2) Very COST EFFECTIVE 3) Very CONVENIENT TO OPERATE Disadvantages of single bus system One major difficulty of these type of arrangement is that, MAINTENANACE OF EQUIPMENT OF Any bay, CANNOT BE POSSIBLE WITHOUT INTERRUPTING THE FEEDER, or transformer connected to that bay.
  • 15. Single Bus System with Bus Sectionalizer Advantages with bus sectionalizer If any of the sources is out of system, still all loads can be fed by switching on the sectional circuit breaker or bus coupler breaker. If one section of the bus bar system is under maintenance, part load of the substation can be fed by energizing the other section of bus bar.
  • 16. Disadvantages of single bus system with bus sectionalizer As in the case of single bus system, maintenance of equipment of any bay cannot be possible without interrupting the feeder or transformer connected to that bay. The use of isolator for bus sectionalizing does not fulfill the purpose. The isolators have to be operated ‘off circuit’ and which is not possible without total interruption of bus – bar. So investment for bus-coupler breaker is required.
  • 18. In double bus bar system two identical bus bars are used in such a way that any outgoing or incoming feeder can be taken from any of the bus. Actually every feeder is connected to both of the buses in parallel through individual isolator as shown in the figure.
  • 19. By closing any of the isolators one can put the feeder to associated bus. Both of the buses are energized and total feeders are divided into two groups, one group is fed from one bus and other from other bus. But any feeder at any time can be transferred from one bus to other. There is one bus coupler breaker which should be kept close during bus transfer operation. For transfer operation, one should first close the bus coupler circuit breaker then close the isolator associated with the bus to where the feeder would be transferred and then open the isolator associated with the bus from where feeder is transferred. Lastly after this transfer operation he or she should open the bus coupler breaker.
  • 20. Advantages of Double Bus System Double Bus Bar Arrangement increases the flexibility of system. Disadvantages of Double Bus System The arrangement does not permit breaker maintenance with out interruption.
  • 22. In double breaker bus bar system two identical bus bars are used in such a way that any outgoing or incoming feeder can be taken from any of the bus similar to double bus bar system. Only difference is that here every feeder is connected to both of the buses in parallel through individual breaker instead only isolator as shown in the figure. By closing any of the breakers and its associated isolators, one can put the feeder to respective bus. Both of the buses are energized and total feeders are divided into two groups, one group is fed from one bus and other from other bus similar to previous case. But any feeder at any time can be transferred from one bus to other. There is no need of bus coupler as because the operation is done by breakers instead of isolator. For transfer operation, one should first close the isolators and then the breaker associated with the bus to where the feeder would be transferred and then he or she opens the breaker and then isolators associated with the bus from where feeder is transferred.
  • 23. 1.3c) ONE AND HALF BREAKER SWITCHYARD
  • 24. One and a half Breaker Bus System This is an improvement on the double breaker scheme to effect saving in the number of circuit breakers. For every two circuits only one spare breaker is provided. The protection is however complicated since it must associate the central breaker with the feeder whose own breaker is taken out for maintenance. For the reasons given under double breaker scheme and because of the prohibitory costs of equipment even this scheme is not much popular. As shown in the figure that it is a simple design, two feeders are fed from two different buses through their associated breakers and these two feeders are coupled by a third breaker which is called tie breaker. Normally all the three breakers are closed and power is fed to both the circuits from two buses which are operated in parallel. The tie breaker acts as coupler for the two feeder circuits. During failure of any feeder breaker, the power is fed through the breaker of the second feeder and tie breaker, therefore each feeder breaker has to be rated to feed both the feeders, coupled by tie breaker.
  • 25. Advantages of One and a half Breaker Bus System During any fault on any one of the buses, that faulty bus will be cleared instantly without interrupting any feeders in the system since all feeders will continue to feed from other healthy bus. Disadvantages of One and a half Breaker Bus System This scheme is much expensive due to investment for third breaker.
  • 26. 1.3d) EHT SWITCHYARD USING GIS SWITCHGEAR A GIS(Gas Insulated Sub-station/Switchyard) is normally used where there is paucity of space and specially located in the heart of largely populated cities with concentrated load centers. Since the interconnections in-between CBs, Isolators, CTs, CVTs., etc., are closely knit in a GIS, due to increased pressure of INERT GAS(SF6) inside, there is a great reduction of power layout space. This criterion is utilized advantageously, while Designing the power layout, involving GIS.
  • 27. 2.0 TROUBLE SHOOTING IN SWITCHYARD & SUB-STATION EQUIPMENT.
  • 28.  THE TERM “TROUBLE SHOOTING” mainly attributes to NON-CLOSURE OF “CLOSING COIL” OR “ TRIPPING COIL” OF ALL CIRCUIT BREAKERS OR/AND ALL REMOTE OPERATING ISOLATORS THEREFORE, TROUBLE SHOOTING MAINLY CONCERNS.  THE D.C. CONTROL SYSTEM (THE SOURCE OF AUXILIARY POWER), FOR AIR BLAST TYPE, SF6 TYPE AND VACCUM CIRCUIT BREAKERS.
  • 29.  THE INTER CONNECTIVITY OF THE PARTICULAR CIRCUIT INCLUDING THE VARIOUS INTERLOCKING LIMIT SWITCHES AND RELAY CONTACTS.  IN THE AIR BLAST TYPE, THE PNEUMATIC SYSTEM INCLUDING THE COPPER TUBING AND ITS END TERMINATIONS.  CHECK FOR SYMULTANEOUS OPEN & CLOSE OF SLOW OPEN & CLOSE OF MAIN CONTACTS, OF CIRCUIT BREAKERS AND ISOLATORS.
  • 30. 3.0 OPERATION & MAINTENANCE OF SWITCHYARD
  • 31. EHT Switchyard /Substation being in the PRIMARY NETWORK of power distribution, it is the most vital nodal point in the NETWORK. RELIABILITY of POWER DISTRIBUTION, greatly depends on these NODES. It is therefore, very important to check and enhance the longevity and quality of each item, comprising these Nodes (SWITCHYARD).
  • 32. 3.1 LIST OF MAJOR EQUIPMENT IN SWITCHYARD/ SUBSTATION
  • 33. 1. TRANSFORMERS a) DRY TYPE (CAST RESIN TYPE) b) OIL FILLED TYPE 2. CIRCUIT BREAKERS a) AIR BLAST TYPE ( 33KV, 132KV, 220KV) b) SF6 TYPE (220KV, 400KV ) c) VACCUM TYPE (220KV, 400KV) 3. POWER ISOLATERS a) HORIZONTAL DOUBLE BREAK ISOLATORS (33KV,132KV) b) HORIZONTAL CENTRE BREAK ISOLATORS (220KV, 400KV) c) VERTICAL PANTOGRAPH ISOLATORS (220KV, 400KV)
  • 34. 4. EARTHING SWITCHES a) REMOTE POWER OPERATED (220KV, 400KV) b) LOCAL MANNUAL OPERATED(UPTO 33KV) 5. GALVANISED STEEL LATICE STRUCTURES FOR BEAMS & COLUMNS 6. STEEL PIPES FOR EQUIPMENT SUPPORT 7. ALL ALUMINIUM CLAMPS & CONNECTORS 8. ALL ALUMINIUM BUS BUS TUBES FOR MAIN BUS
  • 35. 9. SECONDARY EMERGENCY SOURCE FOR PROVIDING. POWER TO THE CONTROLLING SYSTEM (BATTERY, BATTERY CHARGER, DC BOARD) 10. HORIZONTAL ISOLATORS WITH DOUBLE BREAK (33KV) 11. VERTICAL ISOLATORS WITH DOUBLE BREAK TYPE (33KV) 12. HORIZONTAL CENTRAL BREAK ISOLATORS (220KV & 400KV)
  • 36. 13. (220KV/400KV) VERTICAL BREAK PAN TO GRAPH ISOLATORS 14. SF6 SINGLE BREAK CIRCUIT BREAKERS (132KV,220KV) 15. SF6 DOUBLE BREAK CIRCUIT BREAKERS(400KV) 16. VACCUUM SINGLE BREAK CIRCUIT BREAKE (132KV,220KV)
  • 37. 17. VACUUM D0UBLE BREAK CIRCUIT BREAKER (400KV) 18. EARTHING SWITCHES FOR 400KV HVDC SWITCHYARDS. 19. BUS POST INSULATORS 20. MULTICORE CTs, CVTs 21. WAVE TRAPS FOR COMMUNICATION & LINE PROTECTION
  • 38. 22. SWITCHYARD MAIN EARTHING 23. SWITCHYARD AUXILIARY EARTHING FOR MAIN EQPMNT. 24. SWITCHYARD LIGHTING TOWERS/MASTS 25. LIGHTENING PROTECTION SCHEMES OF SWITCHYARD
  • 39. 26. 2 No’s of 30 KVA UPS BACK TO BACK, With minimum 20 minutes battery Back-up. The Emergency Back-up should be essentially connected to at least 25% of the Lighting System of the CONTROL ROOM, Video Conference Room, Main and Half Landing of Stair cases, Walking corridor, Toilets, Flashing Exit Lights, etc.
  • 40. 3.11 SAFETY MAINTAIN SAFETY OF PERSONNEL AND EQUIPMENTAT ANY COST SAFETY RULES SHOULD BE FOLLOWED RELIGIOUSLYAND SEQUENTIALLY TO AVOID ACCIDENT/ ELECTROCUTION.
  • 41. 3.12 I.E. RULES RELATED TO SAFETY AND MINIMUM CLEARANCES TO BE KNOWN BEFORE ENTERING A SWITCHYARD. a) FOR LOW(230V TO 630V) & MEDIUM Voltage (630V TO 11000V) Phase to Earth…5.8 MTR. Mnm.Clearance Phase to Phase….. Mtr. Mnm. Clearance B) FOR HIGH Voltage AND EXTRA HIGH VOLTAGE Phase to Earth= 6.1 Mtr.Mnm.Clearance Phase to Phase….. Mtr. Mnm. Clearance
  • 42. 3.13) WORK PERMIT FOR ATTENDING SWITCHYARD/ SUB- STATION. ISSUE of WORK PERMIT / RETURN of WORK-PERMIT. This is a very IMPORTANT DOCUMENT and the person who issues / accepts it, should be a RESPONSIBLE Person, not less than the rank of a SUPERINTENDENT ENGINEER from OPERATION & MAINTENANCE GROUP.
  • 43.
  • 44. 1) SWITCH OFF the Concerned feeders. 2) ISOLATE the Feeders. 3) Remove and keep the Controlling Fuses in safe custody. 4) Inspect all the accessible BUS SHUTTERS TO BE CLOSED and PADLOCKED. 5) ISSUE the WORK PERMIT, BY NAME OF THE PERSON WHO TAKES IT, mentioning all these important activities.
  • 45. 6) Apply local EARTHING BY SHORTING EARTHING ALL THE PHASES. After COMPLETION of all work, the safety devices and all shortings and EARTHINGS ARE REMOVED AND THE WORK PERMIT is returned. Again as a precautionary method, the same person who took the WORK PERMIT, SHOULD RETURN IT’.
  • 46. 3.2) MAINTENANCE OF EQUIPMENT 3.2a) ROUTINE MAINTENANCE 3.2b) PREVENTIVE MAINTENANCE 3.2c) BREAKDOWN MAINTENANCE
  • 47. 4.0 ANNUAL MAINTENANCE CONTRACT Any Switchyard being upstream in the loadflow diagram, anything and everything in a switchyard, is very critical. An outage due to malfunctioning of any item, is disastrous. Like all other equipment, a procedural Format is followed by the manufacturers, to generate a list of various parts of all the Equipment, erected in a Switchyard. These parts and their sub-parts are codifiedand identified individually and madecompatible to SAP. An inventory of all these items aremeticulously maintained, so that in the event of an outage, downtime shall be minimum.
  • 48. 4.1 MANUFACTURERS’ OWN AMC 4.2 LIST OF MANUFACTURER / VENDORS OF EHT EQUIPMENT APPLYING ANNUAL MAINTENANCE SCHEME 4.2a) M/S SIEMENS INDIA LIMITED 4.2b) M/S ABB 4.2c) M/S ALSTHOM
  • 49. 5.0 DIFERENT TYPES ( A,B,C,D & SPECIAL TYPE) OF TOWERS FOR TRANSMISSION LINES.
  • 50. In order to build up a Transmission Line, keeping within the allocated power corridor, various types of TOWERS are used. These are :- a) (TYPE) Tangent Tower..( max deviation from TOWER Centre Line being 0to5 Degrees) b) (TYPE)…Angular Tower…(max Deviation 5 to15 degrees). c) (TYPE)…Angular Tower…(15 to 30 degrees). d) (TYPE)…Angular Tower…( 30 to 60 degrees)
  • 51. SPECIAL TYPES OF TOWERS.. (60 to 90 degrees). TERMINATION OF OVERHEAD EHT TRANSMISSION LINES ON TO THE SWITCHYARD GANTRIES XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
  • 52. XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX EPC OF EHT OVERHEAD TRANSMISSION LINES XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
  • 53. 6.0 BASIC STEPS TAKEN FOR ENGINEERING, PROCUREMENT & CONSTRUCTION OF EHT TRANSMISSION LINES
  • 54. 6.1 ROUTE SURVEYING (WALK THROUGH SURVEY) As the name suggests, the WALK THROUGH SURVEY, is a very informative survey and determines the nature of the PROJECT, as per points appended :
  • 55. 1. The existing contours above Finished Ground Level and within the pre-defined route, as per the GOVERNMENT NOTIFICATION put –up in the local GAZETTE, are carefully noted, studied and finally fixed, keeping in mind TOWER SPOTTING LOCATIONS & THE MINIMUM GROUND CLEARANCES THAT SHALL BE REQUIRED, as per I.E. Rules. 2. Any existing water-fronts which are to be encountered
  • 56. 3. Any SHORING required for the Tower foot near water-fronts. 4. Any BENCHING required while crossing, hills.
  • 57. 6.2 TOWER SPOTTING (MAINTAINING MINIMUM CLEARANCES). As per the span available on both sides, of any Tower, the particular SPOT of the next Towers are fixed, keeping in mind if any SHORING / BENCHING is required or not.
  • 58. 6.3 ALLOCATING TYPE OF TOWER TO BE USED, MAINTAIN SAG, TENSION & MINIMUM CLEARANCES AS PER I.E. RULES & ACTS. Once the TOWER SPOTS are fixed, the Type of Tower (A,B,C,D,Special) ,required for the situation is finally frozen.
  • 59. 6.4 ESTABLISHING R.O.W. FOR POWER CORRIDOR AS PER STATUTARY RULES.
  • 60. 6.5 LAND AQUISITIONING & PAYING COMPENSATION AS PER RULES.
  • 61. 6.6 ERECTION, TESTING &COMMISSIONING OF EHT OVERHEAD TRANSMISSION LINES. XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX